You are on page 1of 69

PROJECT: Infrastructure buildings of the residential complex (phase 2) of ITCC complex - RIYADH REVISED BOQ FOR PARKING CLUSTERS

(CL03) ITEM Soil investigation The contractor shall implemented of exploratory drilling and mechanical test in all types of soil with on site testing and the issuance of the final report which contain the test results and recommendations of the foundation work. 01 Research and treatment for cavities Implementation through a perforating exploratory(cavity probing) In all types of rock to determined the horizontal and vertical elongation of cavities, the contractor will be responsible for treatment all cavities By injection and treatment for all cavities and voids of rock with all necessary work accordance with the technical specifications and instructions of the Supervising engineer SITE DEVELOPMENT The bidder is advised to visit the site before quoting the rates in order to get himself familiarized with the present site conditions Site clearance and demolitions 02 Demolish and clear away existing structures, pavings, electrical lighting, pavements or upstands, cut and plug or reroute existing service lines or utilities inside property line, clear site of rubbish or any impediments, loose top soil and as deemed necessary, for the total site cluster number 2 (CL02) area, approximately (23360m2), pension agency as shown on drawing CL02- XC-01 Item Note DESCRIPTION QTY UNIT RATE AMOUNT SR

M3

To Collection

SR

Project No. J10-13300 ZUHAIR FAYEZ PARTNERSHIP

1 / 69 REVISED PAGE

Date: MAY 2012

PROJECT: Infrastructure buildings of the residential complex (phase 2) of ITCC complex - RIYADH REVISED BOQ FOR PARKING CLUSTERS (CL03) ITEM SITE GRADING Bulk excavate over site on unclassified ground including all hard and rock layers to reduced levels generally in cutting profiles the work shall include clear away to approved disposals. All additional excavation required for temporary works and spaces, shoring, dewatering, removal of surplus excavated materials, support, temporary spoil heaps and general compaction EXCAVATION AND EARTHWORK Necessary moving or transportation about the site excavation material including handling to temporary stockpile or ultimate disposal off site is to be included in the unit rate of excavation SITE PREPARATION AND GRADING 01 Excavation oversite on unclassified ground including all hard and rock layers (if any) to reduced levels generally in cutting profiles and forming depressions, falls and the like and clear away to approved disposal tip. Fill oversite with approved imported fill material according to site soil report recommendation including compaction in making up levels to required formations, embankments, contouring and the like as per drawings and spec. Note DESCRIPTION QTY UNIT RATE AMOUNT SR

Note

825

M3

02

20

M3

Note
Work on proposed structural built-up areas from part of the Work pertaining to respective building or structure as measured elsewhere.

To Collection

SR

Project No. J10-13300 ZUHAIR FAYEZ PARTNERSHIP

2 / 69 REVISED PAGE

Date: MAY 2012

PROJECT: Infrastructure buildings of the residential complex (phase 2) of ITCC complex - RIYADH REVISED BOQ FOR PARKING CLUSTERS (CL03) ITEM DESCRIPTION PAVING AND SURFACING 01 Supply and install precast concrete shotblasted pavers (beige color) size 400x400x60mm thk. W./photocatalytic titanmium dioxide coating including 100mm thick cast-in-place concrete slab with A193-WWF mesh reinforcement, 20mm thick cement mortar setting bed, moisture barrier on compacted subgrade, 3mm water proofing membrane on R.C. slab as per detail no A1 on drawing CL03-XL301 to suit required locations as shown on drawing CL03-XL101 Supply and install precast concrete shotblasted pavers (grey & light grey color) size 400x400x60mm thk w./ photocatalytic titanium dioxide coating including 100mm thick cast-in-place concrete slab with A193-WWF mesh reinforcement, 20mm thick cement mortar setting bed, polyethylene moisture barrier, compacted subgrade, 3mm water proofing membrane on R.C. slab as per detail no. A6 on drawing CL03-XL301 to suit required locations as shown on drawing CL03-XL101 Supply and install precast concrete shotblasted pavers (dark & light color) size 400x400x30mm w./ dark colorgranite band size 200x200x30mm thk including 100mm thick cast-in-place concrete slab with A193-WWF mesh reinforcement, 20mm thick cement mortar setting bed, polyethylene moisture barrier, compacted subgrade, 3mm water proofing membrane on R.C. slab as per detail no. A2 on drawing CL03-XL301 to suit required locations as shown on drawing CL03-XL101 Supply and install precast concrete shotblasted pavers (beige & light beige color) size 400x400x60mm thk w./grey color granite band size 200x200x30mm thk. and photocatalytic titanium dioxide coating including 100mm thick cast-in-place concrete slab with A193-WWF mesh reinforcement, 20mm thick cement mortar setting bed, polyethylene moisture barrier, compacted subgrade, 3mm water proofing membrane on R.C. slab as per detail no. B3 on drawing CL03-XL301 to suit required locations as shown on drawing CL03-XL101 Supply and install polished granite paving dark &light colors,size 400x400x30mm thk w.\ granite band dark color, size 200x200x30mm including 100mm thick cast-in-place concrete slab with A193-WWF mesh reinforcement, 20mm thick cement mortar setting bed, polyethylene moisture barrier, compacted subgrade, 3mm water proofing membrane on R.C. slab as per detail no. C2 on drawing CL03-XL301 to suit required locations as shown on drawing CL03-XL101 To Collection QTY UNIT RATE AMOUNT SR

640

M2

02

1235

M2

03

182

M2

04

961

M2

05

392

M2

SR

Project No. J10-13300 ZUHAIR FAYEZ PARTNERSHIP

3 / 69 REVISED PAGE

Date: MAY 2012

PROJECT: Infrastructure buildings of the residential complex (phase 2) of ITCC complex - RIYADH REVISED BOQ FOR PARKING CLUSTERS (CL03) ITEM DESCRIPTION PAVING AND SURFACING 01 Supply and install concrete screed with epoxy coat finish including 100mm/50mm thick cast-in-place concrete slab with A193-WWF reinforcement mesh, polyethylene moisture barrier, compacted sub grade, 3mm water proofing membrane on R.C. slab as per detail no. D on drawing CL03-XL301 to suit required locations as shown on drawing CL03-XL101 Supply and install 50mm thk rubber pavement green, blue , brown & red color including adhesive mixture,100mm thick cast-in-place concrete slab with A193-WWF mesh reinforcement smooth finish, polyethylene moisture barrier, compacted subgrade, 3mm water proofing membrane on R.C. slab as per detail no. E7 on drawing CL03-XL301 to suit required locations as shown on drawing CL03-XL101 Supply and install asphalt paving comprising 80mm bituminous wearing course, bituminous prime coat, including granular base course, 3mm water proofing membrane on R.C. slab as per detail no. F on drawing CL03-XL301 to suit required locations as shown on drawing CL03-XL101 Supply and install precast concrete shotblasted pavers (beige & brown color) size 400x400x60mm thk w./photocatalytic titanium dioxide coating including 100mm thick cast-in-place and w./ grey precast band w./ photocatalytic titanium dioxide coating size 200x200x60mm thk. concrete slab with A193-WWF mesh reinforcement, 20mm thick cement mortar setting bed, polyethylene moisture barrier, compacted subgrade, 3mm water proofing membrane on R.C. slab as per detail no. A4 on drawing CL03-XL301 to suit required locations as shown on drawing CL03-XL101 Supply and install precast concrete shotblasted pavers (beige & brown color) size 400x400x60mm thk w./photocatalytic titanium dioxide coating including 100mm thick cast-in-place concrete slab with A193-WWF mesh reinforcement, 20mm thick cement mortar setting bed, polyethylene moisture barrier, compacted subgrade, 3mm water proofing membrane on R.C. slab as per detail no. A5 on drawing CL03-XL301 to suit required locations as shown on drawing CL03-XL101 QTY UNIT RATE AMOUNT SR

1166

M2

02

140

M2

03

281

M2

04

385

M2

05

168

M2

To Collection

SR

Project No. J10-13300 ZUHAIR FAYEZ PARTNERSHIP

4 / 69 REVISED PAGE

Date: MAY 2012

PROJECT: Infrastructure buildings of the residential complex (phase 2) of ITCC complex - RIYADH REVISED BOQ FOR PARKING CLUSTERS (CL03) ITEM DESCRIPTION PAVING AND SURFACING EARTH MOUNT 01 Supply and formation of 500-1500 mm height earth mount including compacted sub base layer, 100 mmm thick layer of sand, 100 mm thk. Layer of planting soilmix and gravel mix, and all required to complete and finish te work as shown on drawing CL03- XL101, and as per detail no. 4 on drawing CL03- XL302 and sections details on drawing CL03- XL303 (Softscape and planting soil mix are measured elsewhere)(area measured on plan) CURBS AND EDGING 02 Supply and install precast concrete road curb, size 300X500X150 mm with exposed aggregate finish including bedding, haunching, 100 mm thk. cast in place concrete base and concrete grout behind curb, 20mm thick cement mortar setting bed, on R.C. slab as per detail no.1 on drawing CL03-XL302 to suit required locations as shown on drawing CL03-XL101 Supply and install precast concrete mowing edge, size 200X100X65 mm including concrete base, 20mm thick cement mortar setting bed, cast in place concrete base on R.C. slab, as per detail no. 2 on drawing CL03-XL302 to suit required locations as shown on drawing CL03-XL101 SUNDRIES TENSILE STRUCTURE 04 Supply and install tensile staructure comprising columns, tent fabric, foundation, earthwork, and all required to compleet and fix the work as shown on drawing CL03- XL101 and as per detail no. 6 on drawing CL03- XL302, and sections details on drawing CL03XL303 and as per manufacturer's recommendations and subject to engineer's approoval to cover an area of 64 m2 . Contractor shall submitt shop drawings for approval before supply QTY UNIT RATE AMOUNT SR

429

M2

484

03

38

No.

To Collection

SR

Project No. J10-13300 ZUHAIR FAYEZ PARTNERSHIP

5 / 69 REVISED PAGE

Date: MAY 2012

PROJECT: Infrastructure buildings of the residential complex (phase 2) of ITCC complex - RIYADH REVISED BOQ FOR PARKING CLUSTERS (CL03) ITEM DESCRIPTION PAVING AND SURFACING TREE-PALM CAST IRON PIT Supply and install 1600x1600mm tree-palm cast iron pit with cast iron grate, brick edge, 200x100x60mm thk. Concrete pavers including soil mix, gravel mulch, and all required to complete and finish the work as per detail 7 on drawing CL03-XL302 01 Tree-palm cast iron pit to suit required locations as shown on drawing CL03-XL101 WOODEN SHADE STRUCTURE Supply and install wooden shade structure comprising 50x100mm artificial wooden louvers every 150mm o.c.(typ.) with 60 angle on horizontal beam, 100x200 mm artificial wooden beam(typ.) fixed w/ steel bolts, 200x200mm artificial wooden post including concrete footings, earthworks, insulation, finishing, fixing, and all required to complete the work as per detail 5 on drawing CL03-XL302 02 Wooden shade structure, approximate area 150 m2 on plan to suit required locations as shown on drawing CL03-XL101 RAISED CONC. PLANTER & WOODEN BENCH Supply and install raised concrete planter with 50x75mm interior wood rails (wooden bench) including soil mix, drainage layer, filter , membrane, sealant and all required to complete and finish the work as per detail 3 on drawing CL03-XL302 03 Raised planter, approximate area 490 m2 on plan t to suit required locations as shown on drawing CL03-XL101 QTY UNIT RATE AMOUNT SR

11

No.

No.

16

No.

To Collection

SR

Project No. J10-13300 ZUHAIR FAYEZ PARTNERSHIP

6 / 69 REVISED PAGE

Date: MAY 2012

PROJECT: Infrastructure buildings of the residential complex (phase 2) of ITCC complex - RIYADH REVISED BOQ FOR PARKING CLUSTERS (CL03) ITEM SITE SIGNAGE Manufacturer's standard outdoor sings, letters and plaques including fixings, finishes, accessories complete as per details on drawing CL03-XC-04, CL03-XC-05 and as per specifications REGULATORY SIGNS 01 02 Ref. type R2-1 ( GIVE WAY, ) Ref. type R5-1 ( ENTRY PROHIBTED ) INFORMATIVE SIGNS 03 04 05 Ref. type I-1 (PARKING) Ref. type I-2 (ENTRY ) Ref. type I-3 (EXIT ) Warning signs 06 Ref. type W11-1 (PEDESTRIAN CROSSING, ) Manufacturer's standard outdoor sings, letters and plaques including fixings, finishes, accessories complete as per details on drawing CL03-XL602, and as per specifications 07 08 09 10 11 12 RESIDENTIAL SIGN, as per detail (1) DIRECTIONAL SIGN, as per detail (2) SMALL MOSQUE SIGN, as per detail (3) SMALL MOSQUE PARKING SIGN, as per detail (4) KINDERGARDEN BUILDING SIGN, as per detail (5) GATE SIGN, as per detail (6) DESCRIPTION QTY UNIT RATE AMOUNT SR

1 7

No. No.

3 5 3

No. No. No.

No.

4 3 1 1 2 1

No. No. No. No. No. No.

To Collection

SR

Project No. J10-13300 ZUHAIR FAYEZ PARTNERSHIP

7 / 69 REVISED PAGE

Date: MAY 2012

PROJECT: Infrastructure buildings of the residential complex (phase 2) of ITCC complex - RIYADH REVISED BOQ FOR PARKING CLUSTERS (CL03) ITEM DESCRIPTION ROAD SIGNAGE & PAVEMENTMARKING Thermoplastic paint for traffic marking on drive way at basement/ground floor and ramps floor as per Manufacturer's standard as shown on details on drawing CL03-XC-05, to suit required locations as shown on drawing CL03-XC-04, as per specification and as per engineer's instructions Pavement marking 01 02 03 04 05 06 07 08 White edge line, ref. detail (2) Lane marking, as per detail (3) Direction separation lines, ref. detail (5) White stop line, ref. detail (6) Dotted line marking (give way line), ref. detail (7) Pedestrian crossing, ref. detail (8) Through traffic arrow, ref. detail (9-1) Left turn arrow, ref. detail (9-3) QTY UNIT RATE AMOUNT SR

616 185 27 4 495 82 21 2

M M M M M M No. No.

To Collection

SR

Project No. J10-13300 ZUHAIR FAYEZ PARTNERSHIP

8 / 69 REVISED PAGE

Date: MAY 2012

PROJECT: Infrastructure buildings of the residential complex (phase 2) of ITCC complex - RIYADH REVISED BOQ FOR PARKING CLUSTERS (CL03) ITEM LANDSCAPING Palms including pit excavation, stakes and ties, soil planting mix, mulching, filter membrane and drainage layer all as details and planting schedule as per detail P1, on drawing CL03-XL-401 01 P/Wf Trees including pit excavation, stakes and ties, soil planting mix, mulching, filter membrane and drainage layer all as details and planting schedule as per detail P2 on drawing CL03-XL-401 02 03 04 T/Af T/Bv T/Fm Shrubs including planting, site excavation as required, soil planting mix, mulching, filter membrane, screed sloped to drain and drainage layer all as per details and planting schedule as per detail P3 on drawing CL03-XL-401 05 06 07 08 09 S/Hs S/To S/Ld S/Pav S/Mc DESCRIPTION QTY UNIT RATE AMOUNT SR

No.

3 6 11

No. No. No.

196 3 3 39 98

No. No. No. No. No.

To Collection

SR

Project No. J10-13300 ZUHAIR FAYEZ PARTNERSHIP

9 / 69 REVISED PAGE

Date: MAY 2012

PROJECT: Infrastructure buildings of the residential complex (phase 2) of ITCC complex - RIYADH REVISED BOQ FOR PARKING CLUSTERS (CL03) ITEM LANDSCAPING Ground cover including planting, site excavation as required, soil planting mix, mulching, filter membrane, screed sloped to drain and drainage layer all as per details and planting schedule as per detail P3, P5, on drawing CL03-XL-401 01 02 03 04 G/As G/Lm G/Cgp G/Gr (Y) Lawn planting, including soil planting mix, filter membrane and drainage layer, screed sloped to drain all as per details and planting schedule as per detail P4 on drawing CL03-XL-401 05 L/Cd DESCRIPTION QTY UNIT RATE AMOUNT SR

764 653 746 763

No. No. No. No.

704

M2

To Collection

SR

Project No. J10-13300 ZUHAIR FAYEZ PARTNERSHIP

10 / 69 REVISED PAGE

Date: MAY 2012

PROJECT: Infrastructure buildings of the residential complex (phase 2) of ITCC complex - RIYADH REVISED BOQ FOR PARKING CLUSTERS (CL03) ITEM DESCRIPTION PLUMBING INSTALLATION WASTE AND DRAINAGE INSTALLATION Supply, install and testing pipework, UPVC schedule 40, the work shall include but not limited to fittings, supports, cast iron pipes on roof for vent with caps, installation, all associate works and all materials and equipments required to complete and finish the work according to drawings, specification and code of practices 01 02 03 75 mm dia. 100 mm dia. 150 mm dia. Accesssories 04 Ground cleanout 100 mm dia, ref. GCO Construction work for briks inspection chamber, the work shall include bit not limited to earth work, plain concrete for foundation BED, concrete channel at chamber DED with standard cast iron manhole frame and double cover and all materials and equipments required to complete and finish the work according to specifications, drawings and code of practice 05 06 Inspection chamber, ref. (IC) 600x600mm Inspection chamber, ref. (STIC) 600x600mm WASTE AND DRAINAGE INSTALLATION Supply, installation and test drainage pipe work UPVC schedule 80 the work shall include but not limited to fittings, supports hangers, excavation, backfilling, cast iron pipes on roof for vent with caps and all materials and equipment required to complete and finish the work according to specifiactions, drawings and code of practice 07 08 75 mm dia 100 mm dia 18 20 M M 5 5 No No 4 No 48 215 65 M M M QTY UNIT RATE AMOUNT SR

To Collection

SR

Project No. J10-13300 ZUHAIR FAYEZ PARTNERSHIP

11 / 69 REVISED PAGE

Date: MAY 2012

PROJECT: Infrastructure buildings of the residential complex (phase 2) of ITCC complex - RIYADH REVISED BOQ FOR PARKING CLUSTERS (CL03) ITEM DESCRIPTION Drainage installation to the external drainage network Construction work for briks inspection chamber, the work shall include bit not limited to earth work, plain concrete for foundation BED, concrete channel at chamber DED with standard cast iron manhole frame and double cover, UPVC pipework schedule 40 to nearest main sewer manhole and all materials and equipments required to complete and finish the work according to specifications, drawings and code of practice 01 02 Inspection chamber, ref. (IC) 600x600mm Slow down chamber 3 4 No No QTY UNIT RATE AMOUNT SR

To Collection

SR

Project No. J10-13300 ZUHAIR FAYEZ PARTNERSHIP

12 / 69 REVISED PAGE

Date: MAY 2012

PROJECT: Infrastructure buildings of the residential complex (phase 2) of ITCC complex - RIYADH REVISED BOQ FOR PARKING CLUSTERS (CL03) ITEM DESCRIPTION POTABLE WATER INSTALLATION Supply, install and testing pipework, UPVC Schedule 80 for potable water the work shall include but not limited to fittings, supports, all associate works and all materials and equipments required to complete and finish the work according to drawings, specification and code of practices 01 02 03 04 05 20 mm dia. 25 mm dia. 32 mm dia. 40 mm dia. 100 mm dia. Reinforced concrete under ground water tank and pump room with proprietary cast iron manhole covers and frames the work shall include but not limited to earthworks, concrete works, sump pit, and submersible pump internal lining and water proofing, access ladders, pipework and valving, test main fold vent pipes, truck fill pipework with back flow preventer, ventilating fan and duct work within tank and pump room structure, and UPVC schedule 80 drainge pipe from submersible pump to the nearest sewer manhole and all materials and equipments required to complete and finish the work according to drawings, specification and code of practices 06 07 Potable water tank CAP 378 M3 Fire water tank 1 1 No. No. 40 7 30 40 78 M M M M M QTY UNIT RATE AMOUNT SR

To Collection

SR

Project No. J10-13300 ZUHAIR FAYEZ PARTNERSHIP

13 / 69 REVISED PAGE

Date: MAY 2012

PROJECT: Infrastructure buildings of the residential complex (phase 2) of ITCC complex - RIYADH REVISED BOQ FOR PARKING CLUSTERS (CL03) ITEM DESCRIPTION POTABLE WATER SUPPLY SYSTEM Supply, installation and test Packaged type constant pressure booster potable water pumps, set of one duty and one stand by pump, including piping and valving network within pump chamber, complete with all controllers, accessories for automatic operateion and all associate works as per code standard and as described on drawings and specification 01 02 Ref. PWP CAP 7.17 KW Ref. CP CAP 0.5 HP Accessories 03 03 04 05 Water meter assembly 50 mm dia., ref. WMA Isolating & check valve assembly 63 mm dia., Isolating & check valve assembly 100 mm dia., Back flow preventer assembly, 100mm dia., ref. BFPA FIRE WATER UTILITIES Supply, installation and test Pipework, UPVC class 5 including fittings, trenching, back fill supports system and all associate works as per code standard 06 63 mm dia. Supply, installation and test Electrically driven horizontal split case centrifugal fire pump, including piping network and valving within pump chamber,complete with all controllers, accessories for automatic operateion and all associate workks as per code standard and as scheduled on drawings and specification 07 08 Ref. FP1 CAP 75 KW electrically driven Ref. FP2 CAP 75 KW fuel diesel driven 1 1 No No 130 M 2 1 1 2 No No No No 1 1 Set Set QTY UNIT RATE AMOUNT SR

To Collection

SR

Project No. J10-13300 ZUHAIR FAYEZ PARTNERSHIP

14 / 69 REVISED PAGE

Date: MAY 2012

PROJECT: Infrastructure buildings of the residential complex (phase 2) of ITCC complex - RIYADH REVISED BOQ FOR PARKING CLUSTERS (CL03) ITEM DESCRIPTION FIRE WATER UTILITIES Supply, installation and test Electrically driven peripheral turbine Jockey pump, including piping network and valving within pump chamber, complete with all controllers, accessories for automatic operateion and all associate workks as per code standard and as scheduled on drawings and specification 01 Ref. JP CAP 5 KW IRRIGATION WATER INSTALLATION Supply, install and testing pipework, UPVC Schedule 80 for Irrigataion water the work shall include but not limited to fittings, supports, all associate works and all materials and equipments required to complete and finish the work according to drawings, specification and code of practices 02 03 04 05 25 mm dia. 32 mm dia. 40 mm dia. 50 mm dia. Accessories 06 Supply and installation irrigation controller as detailed on drwings and as per specifications Supply and installation bubbler for trees Supply and installation spray lawn sprinkler Gate valve W/valve box 25 mm dia., Gate valve W/valve box 40 mm dia., Gate valve W/valve box 50 mm dia., 1 No. 105 16 168 160 M M M M 1 No QTY UNIT RATE AMOUNT SR

07 08 09 10 11

10 21 1 2 5

No. No. No. No. No.

To Collection

SR

Project No. J10-13300 ZUHAIR FAYEZ PARTNERSHIP

15 / 69 REVISED PAGE

Date: MAY 2012

PROJECT: Infrastructure buildings of the residential complex (phase 2) of ITCC complex - RIYADH REVISED BOQ FOR PARKING CLUSTERS (CL03) ITEM DESCRIPTION DIVISION 15 - MECHANICAL IRRIGATION WATER INSTALLATION Supply and installation remote control valve assembly including piping complete with valve box, Y-strainer, accessories and all associated works as detail on drawing and as per specifications section 02810 01 02 03 Ref. RCV 25mm dia. Ref. RCV 40mm dia. Ref. RCV 50mm dia. 2 3 5 No. No. No. QTY UNIT RATE AMOUNT SR

To Collection

SR

Project No. J10-13300 ZUHAIR FAYEZ PARTNERSHIP

16 / 69 REVISED PAGE

Date: MAY 2012

PROJECT: Infrastructure buildings of the residential complex (phase 2) of ITCC complex - RIYADH REVISED BOQ FOR PARKING CLUSTERS (CL03) ITEM DESCRIPTION SITE DEVELOPMENT Collection Sheet -1 Sheet -2 Sheet -3 Sheet -4 Sheet -5 Sheet -6 Sheet -7 Sheet -8 Sheet -9 Sheet -10 Sheet -11 Sheet -12 Sheet -13 Sheet -14 Sheet -15 Sheet -16 QTY UNIT RATE AMOUNT SR

To Bill Summary

SR

Project No. J10-13300 ZUHAIR FAYEZ PARTNERSHIP

17 / 69 REVISED PAGE

Date: MAY 2012

PROJECT: Infrastructure buildings of the residential complex (phase 2) of ITCC complex - RIYADH REVISED BOQ FOR PARKING CLUSTERS (CL03) ITEM DESCRIPTION DIVISION 2 - SITE WORK SITE GRADING All additional excavation required for temporary works and spaces, shoring, dewatering, removal of surplus excavated materials, support, temporary spoil heaps and general compaction EXCAVATION AND EARTHWORK Necessary moving or transportation about the site excavation material including handling to temporary stockpile or ultimate disposal off site is to be included in the unit rate of excavation Excavation in natural land consisting of solid rock formation, cracked rocks, bolders and natural contoured soil, temporary earthwork supports, dewatering ( if any ) as per specifications sections 02200 01 Excavation for foundations commencing from existing grade level Backfilling 02 Approved selected imported fill material including compaction in making up levels around and over foundations, beds and the like as per spec. sections 02200 Approved fill material selected from excavated material including compaction as per specification section 02200 Soil treatment application for termite control 05 To subgrades of slabs and along periphery of building The work shall include all materials and equipments required to complete and finish the work according to specifications and code of practice Note QTY UNIT RATE AMOUNT SR

Note

53400

1450

03

price only

9865

To Collection

SR

Project No. J10-13300 ZUHAIR FAYEZ PARTNERSHIP

18 / 69 REVISED PAGE

Date: MAY 2012

PROJECT: Infrastructure buildings of the residential complex (phase 2) of ITCC complex - RIYADH REVISED BOQ FOR PARKING CLUSTERS (CL03) ITEM DESCRIPTION DIVISION 2 - SITE WORK TRAFFIC MARKING DIMENSION Thermoplastic paint for traffic marking on parking pavement as detail 11 shown on drawing CL-GA-901 and specification 01 02 03 04 05 06 07 08 09 Straight arrows Straight & curved arrows Turning arrows Parking lane marking Handicapped marking on floor ENTRY (text) NO ENTRY (text) EXIT (text) Lane numbers QTY UNIT RATE AMOUNT SR

36 2 5 2021 14 1 2 1 239

No. No. No. M No. No. No. No. No

To Collection Collection Sheet - 18 Sheet - 19

SR

To Bill Summary

SR

Project No. J10-13300 ZUHAIR FAYEZ PARTNERSHIP

19 / 69 REVISED PAGE

Date: MAY 2012

PROJECT: Infrastructure buildings of the residential complex (phase 2) of ITCC complex - RIYADH REVISED BOQ FOR PARKING CLUSTERS (CL03) ITEM DESCRIPTION DIVISION 3 - CONCRETE CONCRETE WORK CONCRETE TYPES Include in Unit Rates for concrete of the following types and locations: 20 Mpa a) Blinding concrete b) Catch basins and side walks 40 Mpa a) Footings b) Columns and R.C. walls c) Floor and roof slabs, beams, girders, stairs d) Concrete topping or structural screed e) Slab on grade f) water tanks Water stops including junction accessories are not measured separately The cost of water stop items are to be included in the unit rates of the related concrete items QTY UNIT RATE AMOUNT SR

Note

To Collection

SR

Project No. J10-13300 ZUHAIR FAYEZ PARTNERSHIP

20 / 69 REVISED PAGE

Date: MAY 2012

PROJECT: Infrastructure buildings of the residential complex (phase 2) of ITCC complex - RIYADH REVISED BOQ FOR PARKING CLUSTERS (CL03) ITEM DESCRIPTION DIVISION 3 - CONCRETE Plain insitu concrete, 20 Mpa, cement type V as per drawings and specifications section 03300 01 02 03 Blinding beds, 100 mm thick 50mm thck. screed Blinding beds, 100 mm thick (to suit tanks) Insitu reinforced concrete, 40 Mpa, type V cement including but not limited to formwork, steel reinforcement conforming to ASTM A615 according to specifications, drawings, and code of practice in: 04 Raft foundation various thickening including depression areas, sump pits and elevators pits and electrical cables trench Retaining walls Shear wall Reinforced concrete to suit foundation gray water tank Reinforced concrete to suit walls gray water tank Reinforced concrete to suit slab gray water tank QTY UNIT RATE AMOUNT SR

1100 550 45

M M M

7150

05 06 07 08 09

630 282 37 60 17

M M3 M
3

M3 M3

To Collection

SR

Project No. J10-13300 ZUHAIR FAYEZ PARTNERSHIP

21 / 69 REVISED PAGE

Date: MAY 2012

PROJECT: Infrastructure buildings of the residential complex (phase 2) of ITCC complex - RIYADH REVISED BOQ FOR PARKING CLUSTERS (CL03) ITEM DESCRIPTION DIVISION 3 - CONCRETE CONCRETE WORK Supply and placing of Insitu reinforced concrete, 40 Mpa type I cement including formwork and steel reinforcements conforming to ASTM A615 and A185 and all requirements to finish the work according to the drawings,as per specifications sections 03100, 03200 & 03300,and code of practice 01 02 03 04 05 06 07 08 09 10 11 Columns Shear wall 300mm suspended flat slab 380mm suspended flat slab 450mm suspended flat slab 500mm suspended flat slab 600mm suspended flat slab Beams Reinforced concrete for Ramps Stairs including landings Precast concrete wheel stopper including dowels, grouting and accessories for complete installation as per detail 21 on drawing CL-GA-901 and specification 88 282 1820 540 362 110 35 22 100 53 235 M M M M M M M M M M No. QTY UNIT RATE AMOUNT SR

To Collection

SR

Project No. J10-13300 ZUHAIR FAYEZ PARTNERSHIP

22 / 69 REVISED PAGE

Date: MAY 2012

PROJECT: Infrastructure buildings of the residential complex (phase 2) of ITCC complex - RIYADH REVISED BOQ FOR PARKING CLUSTERS (CL03) ITEM DESCRIPTION DIVISION 3 - CONCRETE CONCRETE WORK Sundries 01 Allow for reinforced concrete equipment pads including upstand surrounds and anti-vibration accessories as required Allow for expansion joint, fillers, back rods and sealants at expansion joints of concrete as required. Per number, corner and column guard detail 18 on drawing CL-GA-901 150mm thick raised slabs, Handicapped`s ramps and curbs to suit required areas as per detail 10,14, 20 on drawing CL-GA-901 5 M QTY UNIT RATE AMOUNT SR

02

205

03

210

No.

04

To Collection Collection Sheet - 20 Sheet - 21 Sheet - 22 Sheet - 23

SR

To Bill Summary

SR

Project No. J10-13300 ZUHAIR FAYEZ PARTNERSHIP

23 / 69 REVISED PAGE

Date: MAY 2012

PROJECT: Infrastructure buildings of the residential complex (phase 2) of ITCC complex - RIYADH REVISED BOQ FOR PARKING CLUSTERS (CL03) ITEM DESCRIPTION DIVISION 4 - MASONRY UNIT MASONRY Supply and fix concrete masonry blocks in courses with cement lime mortar including concrete lintels over openings , horizontal and vertical reinforcement, fixings, fillers, sealants and grout to complete the work according to specifications and drawings 01 02 200 mm thick wall, one hour fire rated Ditto, but two hour fire rated QTY UNIT RATE AMOUNT SR

740 550

M M

To Bill Summary

SR

Project No. J10-13300 ZUHAIR FAYEZ PARTNERSHIP

24 / 69 REVISED PAGE

Date: MAY 2012

PROJECT: Infrastructure buildings of the residential complex (phase 2) of ITCC complex - RIYADH REVISED BOQ FOR PARKING CLUSTERS (CL03) ITEM DESCRIPTION DIVISION 5 - METALS Expansion joint Supply and install expansion joint cover including extruded aluminum assembles, fillets, accessories, fixing and sealants as per drawing CL-GA-902 and according to specifications 01 02 03 04 05 06 Floor to floor cover as per detail no. 1a Wall to wall cover as per detail no. 1b Wall to wall cover as per detail no. 1e Floor to wall cover as per detail no. 1d Ceiling to ceiling cover as per detail no. 1j Wall to ceiling cover as per detail no. 1h QTY UNIT RATE AMOUNT SR

1707 957 1083 504 1707 504

M M M M M M

Steel cover as per details on drawings 07 08 09 To suit electrical cable trench To suit PG. trench at basement`s ramps To suit sump pits at basement

60 15 12

M2 M No

To Bill Summary

SR

Project No. J10-13300 ZUHAIR FAYEZ PARTNERSHIP

25 / 69 REVISED PAGE

Date: MAY 2012

PROJECT: Infrastructure buildings of the residential complex (phase 2) of ITCC complex - RIYADH REVISED BOQ FOR PARKING CLUSTERS (CL03) ITEM DESCRIPTION DIVISION 7 - THERMAL AND MOISTURE PROTECTION QTY UNIT RATE AMOUNT SR

Water proofing and moisture protection as per specification section 07100 01 02 03 04 Membrane waterproofing to suit concrete wall and foundation Protection board to suit concrete walls Membrane waterproofing to suit gray water tank Protection board to suit gray water tank 11835 2600 320 155 M2 M2 M
2

M2

To Bill Summary

SR

Project No. J10-13300 ZUHAIR FAYEZ PARTNERSHIP

26 / 69 REVISED PAGE

Date: MAY 2012

PROJECT: Infrastructure buildings of the residential complex (phase 2) of ITCC complex - RIYADH REVISED BOQ FOR PARKING CLUSTERS (CL03) ITEM DESCRIPTION DIVISION 8 - DOORS AND WINDOWS DOOR SETS Supply and install all doors to suit masonry openings and approved samples including fixings, decorations, frames, architrave, hardwares and saddles and all required materials and equipments to complete and finish the work as detailed on drawing CL-GA-801 and according to specifications and code of practice 44mm thick painted hollow metal insulated door including frames and decortion as per drawings and specification 01 02 Type B1, double leavs door, size 900x2150mm, 45 min. fire rated Type B6, double leavs door, size 950x2150mm, 45 min. fire rated 44mm thick fully louvered painted hollow metal door motorized adjutable louvers panel working upon, signal from fire alarm system for generator including frames, finishes as shown on drawing and specification 03 04 Type C1, double leavs door, size 950x2400mm, 45 min. fire rated Type C2, double leavs door, size 1050x2400mm, 45 min. fire rated QTY UNIT RATE AMOUNT SR

Note

3 5

No. No.

4 1

No. No.

To Collection

SR

Project No. J10-13300 ZUHAIR FAYEZ PARTNERSHIP

27 / 69 REVISED PAGE

Date: MAY 2012

PROJECT: Infrastructure buildings of the residential complex (phase 2) of ITCC complex - RIYADH REVISED BOQ FOR PARKING CLUSTERS (CL03) ITEM DESCRIPTION DIVISION 8 - DOORS AND WINDOWS Aluminum panels Supply and install 8mm thick single tempered clear fixed glazing all on powder coated aluminum frame as described on drawing CL-GA-802 and according to specifications section 08920 01 Ref. P17, overall size 3200 x 2950mm (glazed door measured elsewhere) Ref. P22, overall size 3200 x 7900mm (glazed door measured elsewhere) Ref. P11, overall size 2900 x 4800 mm (glazed door measured elsewhere) Supply and install 8mm thick single tempered clear fixed glazing all on powder coated aluminum frame. Double glass will be use 24 mm thk. On building entrance, as described on drawing CL-GA-802 and according to specifications section 08920 04 Ref. P16, overall size 3200 x 6000 mm (glazed door measured elsewhere) QTY UNIT RATE AMOUNT SR

No

02

No

03

No

10

No

To Collection

SR

Collection Sheet - 27 Sheet - 28

To Bill Summary

SR

Project No. J10-13300 ZUHAIR FAYEZ PARTNERSHIP

28 / 69 REVISED PAGE

Date: MAY 2012

PROJECT: Infrastructure buildings of the residential complex (phase 2) of ITCC complex - RIYADH REVISED BOQ FOR PARKING CLUSTERS (CL03) ITEM DESCRIPTION DIVISION 9 - FINISHES INTERNAL FINISHES Flooring including respective types of bounding materials, concrete screed sub-floor of required thickness, (if any) accessories for complete installations as per ID drawing and specification 01 02 03 Epoxy paint on cement screed , ref. EC Anti carbonation protection epoxy coating for pavement , ref. AEC Multi component epoxy coating on concrete screed for drive way & turns , ref. MEC 8mm thk. Heavy duty multi component apoxy screed with polyurethane base on concrete screed to suit car ramps, supported with linear mrtal strips for non sliding, ref. HES Finishings : walls including metal angle beads and lathing at junctions of differing backgrounds 05 06 Cement plaster to suit walls Paint on cement plaster ,ref. W01 Finishings : ceilings 07 08 Cement plaster to suit ceiling Paint on cement plaster, ref. CO1 QTY UNIT RATE AMOUNT SR

357 1000 6200

M M M

04

320

7229 7229

M M

330 330

M M

To Collection

SR

Project No. J10-13300 ZUHAIR FAYEZ PARTNERSHIP

29 / 69 REVISED PAGE

Date: MAY 2012

PROJECT: Infrastructure buildings of the residential complex (phase 2) of ITCC complex - RIYADH REVISED BOQ FOR PARKING CLUSTERS (CL03) ITEM DESCRIPTION DIVISION 9 - FINISHES EXTERNAL FINISHES Stone cladding mechanical fixation including fixings , finishings and all associated work as per detail on drawings and specification 01 300x600mm Natural stone cladding, riyadh stone QTY UNIT RATE AMOUNT SR

835

M2

To Collection Collection Sheet - 29 Sheet - 30

SR

To Bill Summary

SR

Project No. J10-13300 ZUHAIR FAYEZ PARTNERSHIP

30 / 69 REVISED PAGE

Date: MAY 2012

PROJECT: Infrastructure buildings of the residential complex (phase 2) of ITCC complex - RIYADH REVISED BOQ FOR PARKING CLUSTERS (CL03) ITEM DESCRIPTION DIVISION 10 -SPECIALTIES TOILET AND BATH ACCESSORIES Supply and installation of fixed anodized aluminum sand trap louvers panels on anodized aluminum frame as described on drawing CL - GA - 802 and specification to suit locations as required Aluminum louvers 01 Ref. L06, overall size 2500 x 2300mm (glazed door measured elsewhere) Ref. L07, overall size 450 x 700mm (glazed door measured elsewhere) Ref. L08, overall size 400 x 700mm (glazed door measured elsewhere) QTY UNIT RATE AMOUNT SR

No

02

No

03

No

To Collection

SR

Project No. J10-13300 ZUHAIR FAYEZ PARTNERSHIP

31 / 69 REVISED PAGE

Date: MAY 2012

PROJECT: Infrastructure buildings of the residential complex (phase 2) of ITCC complex - RIYADH REVISED BOQ FOR PARKING CLUSTERS (CL03) ITEM DESCRIPTION DIVISION 10 -SPECIALTIES SIGNAGE Manufacturer's standard indoor signs, letters and plaques including fixings, finishes, accessories complete as per interior design drawings CL02-i901 to CL02-i916 and all required materials and equipments to complete and finish the works according to specifications, drawings and code of practice 01 02 03 04 05 06 07 Ref. type S01 Ref. type S02 Ref. type S07 Ref. type S10 Ref. type S11 Ref. type S12 Ref. type S13 65 40 7 53 16 15 2 No No No No No No No QTY UNIT RATE AMOUNT SR

To Collection Collection Sheet - 31 Sheet - 32

SR

To Bill Summary

SR

Project No. J10-13300 ZUHAIR FAYEZ PARTNERSHIP

32 / 69 REVISED PAGE

Date: MAY 2012

PROJECT: Infrastructure buildings of the residential complex (phase 2) of ITCC complex - RIYADH REVISED BOQ FOR PARKING CLUSTERS (CL03) ITEM DESCRIPTION DIVISION 14 - CONVEYING SYSTEMS AUTOMATED WASTE COLLECTION SYSTEM Supply and provide all required to construct, test and operate automated waste collection system, consisting of the following items:01 Discharge valve room with basement floor including all required works as detailed on drawing no. STM - ITCCP2 - TD - 008. Contractor shall perform all required coordination with other trade to ensure proper installation and operation of the complete system to transport waste from tower chute to pipe networks as shown on drawings STM - ITCCP2 - TD - 001 to 007 and 015, 016 and according to manufacturer's standards and specifications PIPE WORK Supply and installation of Automated waste collection system piping. Item shall include the earth works, insulation, ,concentric reducer, puddle flanges ,inspection covers and all required materials and equipments to complete the transport pipe line from DV rooms , outdoor load stations and full vacuum load stations to waste plant 02 508mm under/above ground transport pipe RC MANHOLE Supply and install cast insitu or precast reinforced concrete manhole ,the item shall include excavation, backfill insulation ,inspection cover steel rungs and all required to complete the work. 03 RC manhole to suit required location in sitesas shown on drawings STM - ITCCP2 - TD 001 to 016 545 M 7 No. QTY UNIT RATE AMOUNT SR

18

No.

To Bill Summary

SR

Project No. J10-13300 ZUHAIR FAYEZ PARTNERSHIP

33 / 69 REVISED PAGE

Date: MAY 2012

PROJECT: Infrastructure buildings of the residential complex (phase 2) of ITCC complex - RIYADH REVISED BOQ FOR PARKING CLUSTERS (CL03) ITEM DESCRIPTION DIVISION 15 - MECHANICAL PLUMBING INSTALLATIONS WASTE AND DRAINAGE INSTALLATION Supply, installation and test drainage pipe work UPVC schedule 40 the work shall include but not limited to fittings, supports hangers, excavation, backfilling, cast iron pipes on roof for vent with caps and all materials and equipment required to complete and finish the work according to specifiactions, drawings and code of practice 01 02 03 04 32 mm dia 50 mm dia 100 mm dia 150 mm dia Supply, installation and test drainage pipe work UPVC schedule 80 the work shall include but not limited to fittings, supports hangers, excavation, backfilling, cast iron pipes on roof for vent with caps and all materials and equipment required to complete and finish the work according to specifiactions, drawings and code of practice 05 100 mm dia Accessories 06 07 08 09 10 11 Floor drain, 50 mm dia., ref. (FD) Parking drain, 150mm dia., ref. PD Cleanout, 75 mm dia., ref. (CO) Cleanout, 100 mm dia., ref. (CO) Cleanout, 150 mm dia., ref. (CO) Running trap 32mm dia., 18 25 32 92 25 7 No. No. No. No. No. No. 205 M 240 165 1060 660 M M M M QTY UNIT RATE AMOUNT SR

To Collection

SR

Project No. J10-13300 ZUHAIR FAYEZ PARTNERSHIP

34 / 69 REVISED PAGE

Date: MAY 2012

PROJECT: Infrastructure buildings of the residential complex (phase 2) of ITCC complex - RIYADH REVISED BOQ FOR PARKING CLUSTERS (CL03) ITEM DESCRIPTION DIVISION 15 - MECHANICAL PLUMBING INSTALLATIONS WASTE AND DRAINAGE INSTALLATION Accessories 01 02 03 04 Floor cleanout 50mm dia., ref. (FCO) Floor cleanout 100mm dia., ref. (FCO) Floor cleanout 150mm dia., ref. (FCO) Trench drain outlet, 100mm dia., ref. TDO Reinforced concrete gray water tank with required capacity and proprietary medium duty cast iron manhole cover and frame, including sump pit, submersible pumps, internal lining, access ladder vent pipework within tank as detailed on drawing (Concrete work, earthwork & water proofing measured elsewhere) 05 06 07 Gray water tank CAP. 51 m3 Gray water tank CAP. 39 m3 Gray water tank CAP. 32 m3 Packaged type variable speed discharge pressure system Gray water lift pumps, including piping and valves network within pump chamber, complete with all controllers, accessories for automatic operation as scheduled on drawing as per spec. section 15453 08 Gray water lift pumps CAP. 5 KW Reinforced concrete sump pit including internal lining, proprietary galvanized steel manhole cover and frame, guide bar, lifting chain and all associated works, valves pipework within sump pit chamber as detailed on drawings (concrete work & earthwork, waterproofing measured elsewhere) 09 Sump pit 6 No. 3 Set 1 1 1 No No No 10 3 9 4 No. No. No. No. QTY UNIT RATE AMOUNT SR

To Collection

SR

Project No. J10-13300 ZUHAIR FAYEZ PARTNERSHIP

35 / 69 REVISED PAGE

Date: MAY 2012

PROJECT: Infrastructure buildings of the residential complex (phase 2) of ITCC complex - RIYADH REVISED BOQ FOR PARKING CLUSTERS (CL03) ITEM DESCRIPTION DIVISION 15 - MECHANICAL PLUMBING INSTALLATIONS WASTE AND DRAINAGE INSTALLATION Submersible pumps (one duty and one stand-by) including associated valves, pipework, valves controllers and accessories within sump pit chamber as described on drawings (sump pit measured separately) 01 Ref. SP1 capacity 1.5 HP Allow for the design, supply and installation of packaged type waste water treatment plant complete including filter, chemical feeders, air blowers controls, wirings, piping and all as associated works as per specifications section 02736 and scheduled on drawing 02 03 04 Packaged water treatment unit. Cap. 51 m3/day Packaged water treatment unit. Cap. 39 m3/day Packaged water treatment unit. Cap. 32 m3/day POTABLE WATER INSTALLATION Supply, installation and test pipework, plypropylene for potable water the work shall include but not limited to installation, fittings, insulation for hot pipework, valves, supports and all materials and equipment required to complete and finish the work according to specifications, drawings and code of practice 05 06 07 08 09 10 20 mm dia. 25 mm dia. 50 mm dia. 63 mm dia. 75 mm dia. 100 mm dia. 445 70 370 120 95 60 M M M M M M 1 1 1 No. No. No. 6 Set QTY UNIT RATE AMOUNT SR

To Collection

SR

Project No. J10-13300 ZUHAIR FAYEZ PARTNERSHIP

36 / 69 REVISED PAGE

Date: MAY 2012

PROJECT: Infrastructure buildings of the residential complex (phase 2) of ITCC complex - RIYADH REVISED BOQ FOR PARKING CLUSTERS (CL03) ITEM DESCRIPTION DIVISION 15 - MECHANICAL PLUMBING INSTALLATIONS NON-POTABLE WATER INSTALLATION Supply, installation and test pipework, plypropylene for non-potable water the work shall include but not limited to installation, fittings, insulation for hot pipework, valves, supports and all materials and equipment required to complete and finish the work according to specifications, drawings and code of practice 01 02 03 50 mm dia. 75 mm dia. 100 mm dia. Accessories 04 05 06 07 08 09 10 Water meter assembly 63mm dia., Isolating valve, 25 mm dia, ref. (IV) Isolating valve, 50 mm dia, ref. (IV) Isolating valve, 75 mm dia, ref. (IV) IV & CV assembly 50 mm dia., IV & CV assembly 100 mm dia., Hose bib 20mm dia., ref. (HB) 7 7 14 14 3 3 34 No. No. No. No. No. No. No. 1035 430 120 M M M QTY UNIT RATE AMOUNT SR

To Collection

SR

Project No. J10-13300 ZUHAIR FAYEZ PARTNERSHIP

37 / 69 REVISED PAGE

Date: MAY 2012

PROJECT: Infrastructure buildings of the residential complex (phase 2) of ITCC complex - RIYADH REVISED BOQ FOR PARKING CLUSTERS (CL03) ITEM DESCRIPTION DIVISION 15 - MECHANICAL FIRE WATER UTILITIES Supply, installation and test Pipework, UPVC class 5 including fittings, trenching, back fill supports system and all associate works as per code standard 01 02 03 04 05 06 25 mm dia. 32 mm dia. 40 mm dia. 50 mm dia. 100 mm dia. 150 mm dia. Accessories 07 08 09 10 11 12 Pendent sprinkler head Upright sprinkler head Side wall sprinkler head 100mm Fire departement valve , ref. FDV Floor control valve assembly 150mm dia., ref. FCVA Fire department connection, 2 way fire department inlet connection type with gate and check valve 100mm dia. 98 669 13 21 3 No No No No No 1570 340 415 175 1085 160 M M M M M M QTY UNIT RATE AMOUNT SR

No

To Collection

SR

Project No. J10-13300 ZUHAIR FAYEZ PARTNERSHIP

38 / 69 REVISED PAGE

Date: MAY 2012

PROJECT: Infrastructure buildings of the residential complex (phase 2) of ITCC complex - RIYADH REVISED BOQ FOR PARKING CLUSTERS (CL03) ITEM DESCRIPTION DIVISION 15 - MECHANICAL FIRE WATER UTILITIES Supply, install, testing and commissioning proprietary integrated fire hose reel and fire extinguisher cabinet the work shall include but not limited to fire extinguisher, hose reel nozzle, fixings, isolating valve 40 mm dia., trims and all associate works and all materials and equipments required to complete and finish the work according to drawings, specification and code of practices 01 Ref. FHC Supply, install, testing and commissioning portable multipurpose fire extinguisher the work shall include but not limited to fixing to wall, all associate works and all materials and equipments required to complete and finish the work according to drawings, specification and code of practices 02 Ref. CO2 CO2 system Supply, install and test CO2 cylinders including pipe work, black steel seamless for CO2 fittings, supports valves, regulators, sleeves, as shown on drawings and as per specification 03 04 05 06 07 08 09 CO2 cylinders CAP 45 KG Control panel Remote manual release Abort switch Alarm bell 4-port nozzle Ioization detector 32 14 14 14 14 14 14 7 No 10 No QTY UNIT RATE AMOUNT SR

No. No. No. No. No. No. No.

To Collection

SR

Project No. J10-13300 ZUHAIR FAYEZ PARTNERSHIP

39 / 69 REVISED PAGE

Date: MAY 2012

PROJECT: Infrastructure buildings of the residential complex (phase 2) of ITCC complex - RIYADH REVISED BOQ FOR PARKING CLUSTERS (CL03) ITEM DESCRIPTION DIVISION 15 - MECHANICAL PLUMBING INSTALLATION DIESEL FUEL STORAGE TANK INSTALLATION Allow for underground fiberglass diesel fuel storage tank with required capacity including concrete anti-flotation pad, heavy duty traffic type manhole ring and cover, pipework, valves duplex diesel fuel transfer pumps, steel ladder, pea gravel bed, earthworks, fixings and accessories all as detailed on drawings 01 Proprietary tank units CAP. 1890 Lit. 2 No. QTY UNIT RATE AMOUNT SR

To Collection

SR

Collection Sheet -34 Sheet -35 Sheet -36 Sheet -37 Sheet -38 Sheet -39 Sheet -40

To Bill Summary

SR

Project No. J10-13300 ZUHAIR FAYEZ PARTNERSHIP

40 / 69 REVISED PAGE

Date: MAY 2012

PROJECT: Infrastructure buildings of the residential complex (phase 2) of ITCC complex - RIYADH REVISED BOQ FOR PARKING CLUSTERS (CL03) ITEM DESCRIPTION DIVISION 15B - MECHANICAL HVAC INSTALLATIONS CHILLED WATER SYSTEM Supply, install and test black steel pipework including fittings thermal insulation, flexible connections and accessories as per required drawings and spec. sections15050 to 15140 ,15510 01 02 03 04 05 06 07 08 09 10 15 mm dia. 20 mm dia. 25 mm dia. 32 mm dia. 50 mm dia. 80 mm dia. 100 mm dia. 150 mm dia. 200 mm dia. 250 mm dia. Supply and install valve / BTU meter Butterfly valve 11 Ref. MBFV 250 mm dia., QTY UNIT RATE AMOUNT SR

100 25 10 60 120 5 195 400 190 95

M M M M M M M M M M

No.

To Collection

SR

Project No. J10-13300 ZUHAIR FAYEZ PARTNERSHIP

41 / 69 REVISED PAGE

Date: MAY 2012

PROJECT: Infrastructure buildings of the residential complex (phase 2) of ITCC complex - RIYADH REVISED BOQ FOR PARKING CLUSTERS (CL03) ITEM DESCRIPTION DIVISION 15B - MECHANICAL HVAC INSTALLATIONS CHILLED WATER SYSTEM Isolating valve 01 32mm dia., Check valve 02 32mm dia., BTU meter 03 32mm dia., Supply and install heat exchanger including valves and short length piping as detailed on drawings and as per specifications 04 Ref. HEX-01 to 05, 1850 KW capacity Supply, install, test and commission, variable speed chilled water centrifugal inline pumps unit including valves, flexible connections, Y-striners, mounting and fixing to pads (measured separately) as detailed on drawing and specifications 05 Ref. SCWP-01 to 03, 49 L/S capacity 40 m TDH Supply, install and commission, expansion tank as detailed on drawings and specifications 06 Ref. ET, 600 liter capacity QTY UNIT RATE AMOUNT SR

14

No.

No.

No.

No.

No.

No.

To Collection

SR

Project No. J10-13300 ZUHAIR FAYEZ PARTNERSHIP

42 / 69 REVISED PAGE

Date: MAY 2012

PROJECT: Infrastructure buildings of the residential complex (phase 2) of ITCC complex - RIYADH REVISED BOQ FOR PARKING CLUSTERS (CL03) ITEM DESCRIPTION DIVISION 15B - MECHANICAL HVAC INSTALLATIONS CHILLED WATER SYSTEM Supply, install and commission, air separator tank as detailed on drawings and specifications 01 Ref. AS Supply, install, test and commission, Fan coil units ducted type including control valves, pressure & temperature, gauge, Y-strainer mounting and fixing as per drawings and specifications section 15781 02 03 04 Ref. FCU-01, 12.2 KW cooling capacity Ref. FCU-03, 4.0 KW cooling capacity Ref. FCU-04, 5.1 KW cooling capacity Supply, install, test and commission DX-ducted split unit including control, pipes and fixing as per drawing and specifications 05 Ref. RAC-01, 3.51 KW nominal coollling capacity Supply, install, test and commission, DX-ducted split unit including control, pipes and fixing as per drawings and specifications section 15781 06 Ref. FCU-02/ACCU-02 , 4.0 KW capacity Supply, install, test and commission automatic chemical dosing unit as detailed on drawings and specifications 07 Ref. ACDU QTY UNIT RATE AMOUNT SR

No.

1 7 7

No. No. No.

15

No.

No.

No.

To Collection

SR

Project No. J10-13300 ZUHAIR FAYEZ PARTNERSHIP

43 / 69 REVISED PAGE

Date: MAY 2012

PROJECT: Infrastructure buildings of the residential complex (phase 2) of ITCC complex - RIYADH REVISED BOQ FOR PARKING CLUSTERS (CL03) ITEM DESCRIPTION DIVISION 15B - MECHANICAL HVAC INSTALLATIONS Supply, install, test and commission, Ventilating fans as details on drawings and specifications, section 15860 01 Ref. PEF- 01, 13500/22500 LPS capacity with exh. Duct and CAP. Ref. EF- 01, 60 LPS capacity Ref. EF- 02, 50 LPS capacity Ref. EF- 03, 1335 LPS capacity Ref. EF- 04, 150 LPS capacity Ref. EF- 05, 1335 LPS capacity Ref. EF- 06, 105 LPS capacity Ref. EF- 07, 90 LPS capacity Ref. EF- 08, 30 LPS capacity Ref. BIF-01, 3340 LPS capacity Supply, install, test and commission, Supply air round ceiling diffusers with opposed blade volume damper including frame trims & insulated plenum box as detailed on drawing and specification, section 15860 11 12 Ref. SD1 Ref. SD2 Supply, install, test and commission, supply air register as detailed on drawings and specification 13 Ref. SR 1 / RR1 QTY UNIT RATE AMOUNT SR

No.

02 03 04 05 06 07 08 09 10

14 2 1 2 1 2 2 7 12

No. No. No. No. No. No. No. No. No.

14 14

No. No.

No.

To Collection

SR

Project No. J10-13300 ZUHAIR FAYEZ PARTNERSHIP

44 / 69 REVISED PAGE

Date: MAY 2012

PROJECT: Infrastructure buildings of the residential complex (phase 2) of ITCC complex - RIYADH REVISED BOQ FOR PARKING CLUSTERS (CL03) ITEM DESCRIPTION DIVISION 15B - MECHANICAL HVAC INSTALLATIONS Supply, install, test and commission, Return round louver face ceiling diffusers as detailed on drawing and specification 01 02 Ref. RD1 Ref. RD2 Supply, install, test and commission, door grill as detalied and specificaitons 03 04 05 Ref. DG1 Ref. DG2 Ref. DG3 Supply, install, test and commission, motorized damber door louver as detailed on drawing and specification 06 Size 950 x 2200 mm Supply and install exhaust air register as detailed on drawing and specification, section 15891 07 Ref. ER1 Supply and install Galvanized steel sheet rectangular ductwork, including supports and volume damper , and bill mouth opening as per drawings and specification 08 Various gauges Supply and install Duct insulation 09 Thermal semi-rigid insulation to rectangular ductwork Supply, install and test generator exhaust ductwork with canvass connection To suit generator room To Collection QTY UNIT RATE AMOUNT SR

14 14

No. No.

9 14 1

No. No. No.

No.

No.

700

Kg

170

10

No.
SR

Project No. J10-13300 ZUHAIR FAYEZ PARTNERSHIP

45 / 69 REVISED PAGE

Date: MAY 2012

PROJECT: Infrastructure buildings of the residential complex (phase 2) of ITCC complex - RIYADH REVISED BOQ FOR PARKING CLUSTERS (CL03) ITEM DESCRIPTION DIVISION 15B - MECHANICAL HVAC INSTALLATIONS Supply, install, test and commission, of electric works and motor control centers MCC C/W weather proof, magnetic starters, cabinets including power cables, wiring and conduits and cable trays from the MCC to HVAC equipment, interlocks, earthing ...etc, all materials and equipments required to complete and finish the work according to drawings, specifications and code of practices 01 Ref. MCC- CWP QTY UNIT RATE AMOUNT SR

No.

To Collection Collection Sheet - 41 Sheet - 42 Sheet - 43 Sheet - 44 Sheet - 45 Sheet - 46

SR

To Bill Summary

SR

Project No. J10-13300 ZUHAIR FAYEZ PARTNERSHIP

46 / 69 REVISED PAGE

Date: MAY 2012

PROJECT: Infrastructure buildings of the residential complex (phase 2) of ITCC complex - RIYADH REVISED BOQ FOR PARKING CLUSTERS (CL03) ITEM DESCRIPTION DIVISION 16 - ELECTRICAL MEDIUM VOLTAGE INSTALLATION MVSWGR (medium voltage switchgear) Supply , install , testing and commissioning 13.8 KV, 3 phase, 60 Hz,SF6 MVSWGR with 3 cells (1 inputs + 2 outputs) including all associated works to complete installation as per drawings and specifications. The contractor shall prepare sketches and details for approval from SEC and shall make arrangement and required coordination with supervising engineer to complete the work 01 M.V Switchgear unit ref (MVSWGR/CL-3) 1 No QTY UNIT RATE AMOUNT SR

RING MAIN UNIT Only installation, testing and commissioning for 13.8 KV, 3 phase, 60 Hz SF6 ring main unit including all associated works for complete installation as per drawings and specifications and required coordination (supply will be by client) 02 Ring main units RMU1-2 MEDIUM AND LOW VOLTAGE DISTRIBUTION Supply installation, testing and commissioning of the following equipment including all accessories and necessary works required for installation as shown on the drawings E-701,E201 and as described in specifications section 16461,16124and and by making arrangiement with supervising engineer to achieve the work to the best possible and specifications 03 Dry type transformers , 1600 KVA, 13.8 KV ,400/230V , 3PH, 60HZ, ref (TR1,2-CL3) ,

No

No.

To Collection

SR

Project No. J10-13300 ZUHAIR FAYEZ PARTNERSHIP

47 / 69 REVISED PAGE

Date: MAY 2012

PROJECT: Infrastructure buildings of the residential complex (phase 2) of ITCC complex - RIYADH REVISED BOQ FOR PARKING CLUSTERS (CL03) ITEM DESCRIPTION DIVISION 16 - ELECTRICAL MEDIUM VOLTAGE INSTALLATION Supply , install and test medium voltage copper Cables 15KV/ XLPE/STA/PVC, between medium voltage equipments as shown on drawings and coordination with other disciplines shall be conducted during work execution as per technical specifications, drawings and by making arrangement with supervising engineer to achieve the work to the best possible and specifications 01 Medium voltage cable comprising 3 core 70 mm CU / XLPE /STA/ PVC, cables route from RMU up to transformers Medium voltage cable comprising 3 core 300 mm CU / XLPE /STA/ PVC, cables 10 M QTY UNIT RATE AMOUNT SR

02

165

Smart Metering System Supply, installation , testing and commissioning of Smart Metering System comprising of M-bus master controller complete with soft ware and bus IP router, including digital electrical KWH meters, 1 pair twisted cable # 22 AWG type to TCP/IP net work and all associated works required as shown on drawing E-501--E520 and as described in specifications section 16211 To suit Building Smart Metering System with multi -electronic meter (MEM) and main bus and IP router as required to form a complete and fully operative system to link all project buildings with the existing data center at phase 1 03 04 05 Electronic KWH meters M-bus master controller complete with software M-bus IP router 7 7 7

Note

No No No

To Collection

SR

Project No. J10-13300 ZUHAIR FAYEZ PARTNERSHIP

48 / 69 REVISED PAGE

Date: MAY 2012

PROJECT: Infrastructure buildings of the residential complex (phase 2) of ITCC complex - RIYADH REVISED BOQ FOR PARKING CLUSTERS (CL03) ITEM DESCRIPTION DIVISION 16 - ELECTRICAL MAIN AND SUB-MAIN POWER Supply and install an Emergency Power Generating Sets including Generator Control Panel (GCP). In addition to circuit breakers, pads, supports, controls and daily diesel fuel storage tank, including all necessary equipment, accessories and associated works, as shown on drawings E-701,E201 as described in specifications section 16231, and by making arrangiement with supervising engineer to achieve the work to the best possible and specifications 01 02 Generator, 400 KVA, 3 phase 4 wire ,400/230V , 60 Hz. Generator , 450 KVA, 3 phase 4 wire ,400/230V , 60 Hz. MAIN AND SUB-MAIN POWER supply , install, testing and commissioning multicore copper cable ( XLPE/PVC -1000/600V) in cable tray or cable trench (measured elsewhere) including junction boxes, connection for feeders and various power loads as shown on drawings E-701 and as per specification section 16126 and by making arrangement with supervising engineer to achieve the work to the best possible specifications 01 02 03 04 05 06 07 08 09 (4 C-10 mm ) + 10 mm G/cable trench (4 C-10 mm ) + 10 mm G/ 150mmd UPVCconduits (4 C-10 mm ) + 10 mm G/cable tray 4 C-50 mm + 25mm G/ cable trench 4 C-50 mm + 25mm G/ cable tray 4 C-70 mm + 35mm G/ cable trench 4 C-70 mm + 35mm G/ 1110mmd UPVCconduits 4 C-70 mm + 35mm G/ cable tray 4 C-95 mm + 50mm G/ cable trench QTY UNIT RATE AMOUNT SR

1 1

No. No.

25 138 70 5 533 15 90 35 15

M M M M M M M M M

To Collection

SR

Project No. J10-13300 ZUHAIR FAYEZ PARTNERSHIP

49 / 69 REVISED PAGE

Date: MAY 2012

PROJECT: Infrastructure buildings of the residential complex (phase 2) of ITCC complex - RIYADH REVISED BOQ FOR PARKING CLUSTERS (CL03) ITEM DESCRIPTION DIVISION 16 - ELECTRICAL MAIN AND SUB-MAIN POWER supply , install, testing and commissioning multicore copper cable ( XLPE/PVC -1000/600V) in cable tray or cable trench (measured elsewhere) including junction boxes, connection for feeders and various power loads as shown on drawings E-701 and as per specification section 16126 and by making arrangement with supervising engineer to achieve the work to the best possible specifications 01 02 03 04 05 06 07 08 09 10 4 C-95 mm + 50mm G/ 1110mmd UPVCconduits 4 C-120 mm + 70 mm G/ cable tray 4 C-150 mm + 95 mm G/ cable trench 4 C-150 mm + 95 mm G/ 1110mmd UPVCconduits 4 C-300 mm + 150 mm G/ cable tray 2(4X1C-150mm2)/ cable trench 2(4X1C-150mm2)+ 150 mm G/ cable tray 2(4X1C-185mm2) G/cable trench 2(4X1C-630mm2) G/ cable trench 3(4X1C-630mm2) G/ cable trench The length of cables including the cluster-3 cables and cables in the first floor for AP05 according to No's for each AP in site QTY UNIT RATE AMOUNT SR

168 90 5 65 453 70 498 60 10 10

M M M M M M M M M M Note

To Collection

SR

Project No. J10-13300 ZUHAIR FAYEZ PARTNERSHIP

50 / 69 REVISED PAGE

Date: MAY 2012

PROJECT: Infrastructure buildings of the residential complex (phase 2) of ITCC complex - RIYADH REVISED BOQ FOR PARKING CLUSTERS (CL03) ITEM DESCRIPTION DIVISION 16 - ELECTRICAL MAIN AND SUB-MAIN POWER Supply , install , power distribution heavy duty galvanized steel cable trays with cover including fixings, supports and all accessories as shown on drawingsE201--E220 and coordination & integration with other systems shall be conducted during work execution as per technical specifications section 16050 and by making arrangement with supervising engineer to achieve the work to the best possible specifications 01 02 03 04 05 06 07 08 09 Cable tray 200 mm width Cable tray 200 mm width for emergency cables Cable tray 300 mm width Cable tray 400 mm width for emergency cables Cable tray 400mm width, two layers, Cable tray 600 mm width Cable tray 1000 mm width Covered cable tray 300 mm width for optical fiber cables and Cable tray 400mm width, two layers for communication QTY UNIT RATE AMOUNT SR

95 185 265 108 87 55 18 350 15

M M M M M M M M M

To Collection

SR

Project No. J10-13300 ZUHAIR FAYEZ PARTNERSHIP

51 / 69 REVISED PAGE

Date: MAY 2012

PROJECT: Infrastructure buildings of the residential complex (phase 2) of ITCC complex - RIYADH REVISED BOQ FOR PARKING CLUSTERS (CL03) ITEM DESCRIPTION DIVISION 16 - ELECTRICAL MAIN AND SUB-MAIN POWER supply and install reinforced concrete Man / Holes connected via duct banks, complete with man / hand hole bolted type metal cover, drain pipe outlet, including trenching and backfilling for duct banks, conduits for M.V cables in duct banks, tapes, all as required to suit locations as shown on drawings drawings E201--E220and as all accessories and coordination & integration with other systems shall be conducted during work execution as per technical specificationssection 16180 and by making arrangement with supervising engineer to achieve the work to the best possible specifications 01 Power Man Holes (180018001800) Ref. MH including UPVC conduit Power Hand Holes (900900900) Ref. HH including UPVC conduit Site work 03 Power Man Hole (180018001800) Ref. MH including UPVC conduit Power Hand Holes (900900900) Ref. HH including UPVC conduit supply and install Electrical concrete ATTIC including trenching and backfilling for duct banks, conduits for M.V cables in duct banks, tapes, all as required to suit locations as shown on drawings E205--E208and as per specifications section 16180 and by making arrangement with supervising engineer to achieve the work to the best possible specifications 05 Concrete ATTIC for M.V works QTY UNIT RATE AMOUNT SR

No

02

No

No

04

12

No

18

To Collection

SR

Project No. J10-13300 ZUHAIR FAYEZ PARTNERSHIP

52 / 69 REVISED PAGE

Date: MAY 2012

PROJECT: Infrastructure buildings of the residential complex (phase 2) of ITCC complex - RIYADH REVISED BOQ FOR PARKING CLUSTERS (CL03) ITEM DESCRIPTION DIVISION 16 - ELECTRICAL MAIN AND SUB-MAIN POWER Supply , install , testing and commissioning of panel boards including grounding, circuit breakers, grounding, fixings, markers and , other functional units and all associated works as required and shown on drawings E 701,E704 , E201--E220 and coordination & integration with other systems shall be conducted during work execution as per technical specificationssection 16442,16410,16415 and by making arrangement with supervising engineer to achieve the work to the best possible specifications 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 17 Ref. MDP-P1 Ref. MDP-P2 Ref. Ref. EMDP-P1 EMDP-P2 QTY UNIT RATE AMOUNT SR

1 1 1 1 7 7 7 1 1 7 1 1 1 1 1 1 7
To Collection

No. No. No. No. No. No. No. No. No. No. No. No. No. No. No. No. No.
SR

Ref. DP51 Ref. DP52 Ref. DPS5 Ref. DPSB1 Ref. DPSB2 Ref. EDPS5 Ref. EDPSB1 with ATS built in and interlock Ref. EDPSB2 with ATS built in and interlock Ref. EPMSB1 Ref. EPMSB2 Ref. Ref. Ref. EPSB1 EPSB2 EPSD

Project No. J10-13300 ZUHAIR FAYEZ PARTNERSHIP

53 / 69 REVISED PAGE

Date: MAY 2012

PROJECT: Infrastructure buildings of the residential complex (phase 2) of ITCC complex - RIYADH REVISED BOQ FOR PARKING CLUSTERS (CL03) ITEM DESCRIPTION DIVISION 16 - ELECTRICAL MAIN AND SUB-MAIN POWER Supply , install , testing and commissioning of panel boards including grounding, circuit breakers, grounding, fixings, markers and , other functional units and all associated works as required and shown on drawings E 701,E704 , E201--E220 and coordination & integration with other systems shall be conducted during work execution as per technical specificationssection 16442,16410,16415 and by making arrangement with supervising engineer to achieve the work to the best possible specifications 01 02 03 Ref. Ref. Ref. PPSB1 PPSB2 PPSD QTY UNIT RATE AMOUNT SR

1 1 7

No. No. No.

Pump rooms 04 05 Ref. Ref. EPP (IP 54 ) EPPA (IP 54 )

1 1

No. No.

To Collection

SR

Project No. J10-13300 ZUHAIR FAYEZ PARTNERSHIP

54 / 69 REVISED PAGE

Date: MAY 2012

PROJECT: Infrastructure buildings of the residential complex (phase 2) of ITCC complex - RIYADH REVISED BOQ FOR PARKING CLUSTERS (CL03) ITEM DESCRIPTION DIVISION 16 - ELECTRICAL POWER INSTALLATION The contractor is to insure that all power outlets mounted in wet areas and all service outlets for kitchens, bathrooms, laundry and water heaters are to be protected by central ground fault circuit interrupter (GFCI) Supply , install, testing and commissioning of power and sockets accessories including all necessary boxes, faces(according to the engineer approvement ) comprising cables, conduits, fittings, connections, from the outlets to Panelboards feeder associated works as required to suit the locations shown on drawings E201--E220 Coordination with other disciplines shall be conducted during work execution as per technical specifications, section 16050and by making arrangiement with supervising engineer to achieve the work to the best possible specifications 01 02 03 Junction box ,wall mounted Junction box ceiling mounted Disconnect switch, non-fusedand with pilot light 16A, 1P, 230V ,weatherproof for waste collection pumps Disconnect switch, non-fusedand with pilot light 20A, 1P, 230V ,weatherproof for s. pumps Disconnect switch, fused and with pilot light 20A, 1P, 230V for RAC-01 Above false ceiling disconnect 20A, 1P, 230V for FCU-02,05 Above false ceiling disconnect 20A, 3P, 400V for BIF-01 Disconnect switch, non-fused and with pilot light 20A, 1P, 230V forFACP,BD5,FDG5,FDB1,2,SP,A,P,switcher Disconnect switch non-fused, and with pilot light 20A, 3P, 400V ,weatherproof for G. pump Note QTY UNIT RATE AMOUNT SR

13 21 7 7 18 15 12 23

No. No. No. No. No. No. No. No.

04

05

06 07 08

09

No.

To Collection

SR

Project No. J10-13300 ZUHAIR FAYEZ PARTNERSHIP

55 / 69 REVISED PAGE

Date: MAY 2012

PROJECT: Infrastructure buildings of the residential complex (phase 2) of ITCC complex - RIYADH REVISED BOQ FOR PARKING CLUSTERS (CL03) ITEM DESCRIPTION DIVISION 16 - ELECTRICAL Supply , install, testing and commissioning of power and sockets accessories including all necessary boxes, faces(according to the engineer approvement ) comprising cables, conduits, fittings, connections, from the outlets to Panelboards feeder associated works as required to suit the locations shown on drawings E201--E220 Coordination with other disciplines shall be conducted during work execution as per technical specifications, section 16050and by making arrangiement with supervising engineer to achieve the work to the best possible specifications 01 Disconnect switch,fused and with pilot light ,32A, 1P, 230V FCU-02 Disconnect switch, non-fused and with pilot light 50A, 3P,400V weatherproof for PEF-01 Disconnect switch, non-fused ,200A, 3P,400V weatherproof for SCWP For exhust fan outlet Motor switch with built-in over load protection,(tumbler switch) Single socket outlet, 13A, 230V, grounding type, Single socket outlet, 13A, 230V, grounding type, weatherproof Single socket outlet, 13A, 230V, grounding type, EF Duplex socket outlet, 16A, 230V, grounding type Circuit breaker 200A for fire alarm panel (magnetic trip only) Single pole one-way ,one gang switch (13A) Single pole one-way ,two gang switch (13A Push button switch QTY UNIT RATE AMOUNT SR

No.

02

No.

03

No.

04 05 06 07 08 09 10 11 12 13

29 24 91 94 30 8 1 55 6 21

No No No No No No No. No. No. No.

To Collection

SR

Project No. J10-13300 ZUHAIR FAYEZ PARTNERSHIP

56 / 69 REVISED PAGE

Date: MAY 2012

PROJECT: Infrastructure buildings of the residential complex (phase 2) of ITCC complex - RIYADH REVISED BOQ FOR PARKING CLUSTERS (CL03) ITEM DESCRIPTION DIVISION 16 - ELECTRICAL POWER INSTALLATION Supply , install, testing and commissioning of power and sockets accessories including all necessary boxes, faces(according to the engineer approvement ) comprising cables, conduits, fittings, connections, from the outlets to Panelboards feeder associated works as required to suit the locations shown on drawings E201--E220 Coordination with other disciplines shall be conducted during work execution as per technical specifications, section 16050and by making arrangiement with supervising engineer to achieve the work to the best possible specifications 01 02 Junction box ,floor mounted for site Disconnect switch, non-fused and with pilot light16A, 1P, 230V ,weatherproof forcollection pumps QTY UNIT RATE AMOUNT SR

1 4

No. No.

Pump rooms 03 04 Junction box ceiling mounted Disconnect switch, non-fused and with pilot light 20A, 3P,400V weatherproof for P.W. pump Disconnect switch, non-fused ,200A, 3P,400V weatherproof for fire& jockey pump, Motor switch with built-in over load protection (tumbler switch), weatherproof Single socket outlet, 13A, 230V, grounding type, weatherproof Single pole one-way ,one gang switch (13A), weatherproof Circuit breaker 500A for fire alarm panel

2 1

No. No.

05

No.

06

No

07 08 09

2 2

No No. No.

To Collection

SR

Project No. J10-13300 ZUHAIR FAYEZ PARTNERSHIP

57 / 69 REVISED PAGE

Date: MAY 2012

PROJECT: Infrastructure buildings of the residential complex (phase 2) of ITCC complex - RIYADH REVISED BOQ FOR PARKING CLUSTERS (CL03) ITEM DESCRIPTION DIVISION 16 - ELECTRICAL LIGHTING INSTALLATION Supply, install , testing and commissioning of lighting fixture outlets and including conduits, wires and all boxes belong to Lighting Panelboards and associated works as required to suit the locations shown on drawings E101--E120 .Coordination with other disciplines shall be conducted during work execution as per technical specifications, section 16050 and by making arrangiement with supervising engineer to achieve the work to the best possible specifications 01 Lighting fixer outlet Pump rooms 02 Lighting fixer outlet QTY UNIT RATE AMOUNT SR

785

No.

No.

To Collection

SR

Project No. J10-13300 ZUHAIR FAYEZ PARTNERSHIP

58 / 69 REVISED PAGE

Date: MAY 2012

PROJECT: Infrastructure buildings of the residential complex (phase 2) of ITCC complex - RIYADH REVISED BOQ FOR PARKING CLUSTERS (CL03) ITEM DESCRIPTION DIVISION 16 - ELECTRICAL LIGHTING INSTALLATION Supply ,install, testing and commissioning of lighting fixture (furnishe with lamp and electronic blast, accessories and internal wires) mounting accessories.(according to the engineer approval ) associated works as required to suit the locations shown on drawings E101--E120 ,GE-E01,GE-E01 and Coordination with other disciplines shall be conducted during work execution as per technical specifications, section 16500 and by making arrangiement with supervising engineer to achieve the work to the best possible specifications 01 02 03 04 05 06 07 08 09 10 11 12 Type EX ( wall mounted, single sided) Type EX ( ceiling mounted, single sided) Type F1 Type F1E Type F2 Type F2E Type F7E Type NE Type WL3 Type WL3E Type WL4E Type FT1 flixible tube LED cove light Pump rooms 13 Type F1E QTY UNIT RATE AMOUNT SR

14 42 295 87 140 63 35 25 14 14 36 485

No. No. No. No. No. No. No. No. No. No. No. M.

No.

To Collection

SR

Project No. J10-13300 ZUHAIR FAYEZ PARTNERSHIP

59 / 69 REVISED PAGE

Date: MAY 2012

PROJECT: Infrastructure buildings of the residential complex (phase 2) of ITCC complex - RIYADH REVISED BOQ FOR PARKING CLUSTERS (CL03) ITEM DESCRIPTION DIVISION 16 - ELECTRICAL GROUNDING SYSTEM Supply, installation , test and commissioning of a grounding system comprising bare copper conductor to bond the building's distribution boards and HVAC equipments to the main ear thing grid of the building. Including necessary earthwork, buried galvanized steel foundations strips surrounding the building phosphor bronze test joints & triangular counter poise and all associated works to suit grounding resistivity required as shown on drawings E301--E310 and as described in specifications16452,16453 by making arrangiement with supervising engineer to achieve the work to the best possible specifications 01 Complete building grounding system network to suit ground resistivity as shown on drawings and specification To suit grounding system for low current system equipment as shown on drawings and specification 03 To suit grounding system for Pump rooms as shown on drawings and specification QTY UNIT RATE AMOUNT SR

Item

02

Item

Item

To Collection

SR

Project No. J10-13300 ZUHAIR FAYEZ PARTNERSHIP

60 / 69 REVISED PAGE

Date: MAY 2012

PROJECT: Infrastructure buildings of the residential complex (phase 2) of ITCC complex - RIYADH REVISED BOQ FOR PARKING CLUSTERS (CL03) ITEM DESCRIPTION DIVISION 16 - ELECTRICAL TELECOMMUNICATION SYSTEM Supply, installation, testing and commissioning of telecommunication system commporising of server, Building distributor with core switch,floor distribution, data/telephone outlets including cable / wires and conduits as shown on drawings E- 501--E520 ,E801and as described in specification section 16715,16720 and by making arrangiement with supervising engineer to achieve the work to the best possible specifications To suit system network equipped with: 01 Building distributor ,ref ( BD5) contains main optical data patch panel (F.O.P.P) Floor distribution includes( fiber optical patch panel F.O.P.P , data switch CAT6 a 1 24 RJ 45 ports and UTP P.P CAT6 a 1 24 ports and blank ),ref FD5G with and connected with power supply Wall mounted telecommunication outlet 1 port (1data ) , ref. (T0) Ceiling mounted telecommunication outlet 1 port (1data ) , ref. (T0) Wall mounted telecommunication outlet 1 port forintercome system Wall mounted telecommunication outlet 1 port (1 Tel ) at 1500 mm A.F.F.L , ref. (T01) Wall mounted telecommunication outlet3 port ( 2data , 1Tel.) , ref. (T04) Primary and secondary activ switch ( NIC) QTY UNIT RATE AMOUNT SR

No

02

.No

03 04 05 06

12 41

.No .No
No.

7
33

.No

07

No.

08 09

No.
Item

1 Telecommunication system network including conduits, wiring, pull boxes, connections, and all required accessories to form a complete and fully operative system Pump rooms

10

Wall mounted telecommunication outlet 1 port (1 Tel ) at 1500 mm A.F.F.L , ref. (T01) To Collection

No.
SR

Project No. J10-13300 ZUHAIR FAYEZ PARTNERSHIP

61 / 69 REVISED PAGE

Date: MAY 2012

PROJECT: Infrastructure buildings of the residential complex (phase 2) of ITCC complex - RIYADH REVISED BOQ FOR PARKING CLUSTERS (CL03) ITEM DESCRIPTION DIVISION 16 - ELECTRICAL VOICE EVACUATION SYSTEM
Supply, install , testing and commissioning of voice evacuation system comprising of voice evacuation speakers including associated cable wires, earthing for equipment and conducting, interfacing with other systems as shown on drawings E401--E408,E-801and .Coordination, integration with other disciplines shall be conducted during work execution as per technical section 16721 and drawings and by making arrangiement with supervising engineer to achieve the work to the best possible and specifications

QTY

UNIT

RATE

AMOUNT SR

To suit system network equipped with: 01 Master control panel for voice evacuation system with master mic control ,96 switch control .integrated fire phone conneted with power supply with battary back up ( 3 hours continual operation) Distribution panel for voice evacuation system with ( 3 amplifier 100 watt) and conneted with emergency power supplyof (CL-03) Distribution panel for voice evacuation system with ( `2 amplifier 100 watt) and conneted with emergency power supply of (AP-05) 2 watt, voice evacuation speakers, wall mounted 2 watt, voice evacuation speakers, ceiling mounted Voice evacuation systemnetwork including conduits, wiring, pull boxes, connections, and all required accessories to form a complete and fully operative system

No.

02

No.

03

No.

04 05 06

29 21
1

No. No.
Item

To Collection

SR

Project No. J10-13300 ZUHAIR FAYEZ PARTNERSHIP

62 / 69 REVISED PAGE

Date: MAY 2012

PROJECT: Infrastructure buildings of the residential complex (phase 2) of ITCC complex - RIYADH REVISED BOQ FOR PARKING CLUSTERS (CL03) ITEM DESCRIPTION DIVISION 16 - ELECTRICAL FIRE ALARM SYSTEM Supply, installation, testing and commissioning of fire detection/alarm system comprising of Modular analogue addressable fire alarm system with back up battary, sounders detectors, control, alarm bell, pull stations, modules including associated cable wires and conduiting, interfacing as shown on drawings E-401--E420,E801and as described in specifications 16721 and by making arrangiement with supervising engineer to achieve the work to the best possible specifications To suit system network equipped with: 01 Master analouge musicable fire alarm control panel , ref.FACP with TCP-IP interface and power supply unit and auto dialer connected to civil defense authority located for(CL03) Master analouge addressable fire alarm control panel , ref.FACP 3 loops ) with TCP-IP interface, power supply unit and auto dialer connected to civil defense authority at ground floor of (AP-05) Optical smoke detector Ceiling mounted Ceiling mounted multi sensor (CO, heat, smoke) Fire alarm manual call station Fire alarm bill Fire alarm interface unit Fire man s telephone jack Fire fighting telephone panel( FFT) Pull boxes for fire alarm system QTY UNIT RATE AMOUNT SR

No.

02

No.

03 04 05 06 07 08 09 10

63 105 42 25 25 21 7
14

No. No. No. No. No. No. No. No.

To Collection

SR

Project No. J10-13300 ZUHAIR FAYEZ PARTNERSHIP

63 / 69 REVISED PAGE

Date: MAY 2012

PROJECT: Infrastructure buildings of the residential complex (phase 2) of ITCC complex - RIYADH REVISED BOQ FOR PARKING CLUSTERS (CL03) ITEM DESCRIPTION DIVISION 16 - ELECTRICAL FIRE ALARM SYSTEM Supply, installation, testing and commissioning of fire detection/alarm system comprising of Modular analogue addressable fire alarm system with back up battary, sounders detectors, control, alarm bell, pull stations, modules including associated cable wires and conduiting, interfacing as shown on drawings E-401--E420,E801and as described in specifications 16721 and by making arrangiement with supervising engineer to achieve the work to the best possible specifications 01 Fire alarm system network including conduits, wiringes, connections, and all required accessories to form a complete and fully operative system Pump rooms 02 Optical smoke detector Ceiling mounted 1 Item QTY UNIT RATE AMOUNT SR

No.

To Collection

SR

Project No. J10-13300 ZUHAIR FAYEZ PARTNERSHIP

64 / 69 REVISED PAGE

Date: MAY 2012

PROJECT: Infrastructure buildings of the residential complex (phase 2) of ITCC complex - RIYADH REVISED BOQ FOR PARKING CLUSTERS (CL03) ITEM DESCRIPTION DIVISION 16 - ELECTRICAL AUDIO VIDIO INTERCOM SYSTEM
Supply, install , testing and commissioning of voice evacuation system comprising of voice evacuation speakers including associated cable wires, earthing for equipment and conducting, interfacing with other systems as shown on drawings E401--E404,E-801and .Coordination, integration with other disciplines shall be conducted during work execution as per technical section 16721 and drawings and by making arrangiement with supervising engineer to achieve the work to the best possible and specifications

QTY

UNIT

RATE

AMOUNT SR

To suit audio video intercom system network equipped with: 01 02 03 04 05 Outdoor Intercom station with camera( 48 lines ) for AP-05 type Electrical door loock power supply unit Network controller Audio video intercom system network including conduits, wiring, pull boxes, connections, and all required accessories to form a complete and fully operative system

7 7 7 1
1

No. No. No. No.


Item

To Collection

SR

Project No. J10-13300 ZUHAIR FAYEZ PARTNERSHIP

65 / 69 REVISED PAGE

Date: MAY 2012

PROJECT: Infrastructure buildings of the residential complex (phase 2) of ITCC complex - RIYADH REVISED BOQ FOR PARKING CLUSTERS (CL03) ITEM DESCRIPTION DIVISION 16 - ELECTRICAL Supply , installation testing and commisioning of audio video intercom system comprising of outdoor Intercom station with camera , electrical door lock , power supply , cables and conduits and associated works as required to suit the locations shown on drawingsE-601--E620 and coordination & integration & communication kit with other systems shall be conducted during work execution as per technical specifications section 16760 and by making arrangement with supervising engineer to achieve the work to the best possible and specifications 01 02 03 04 05 06 07 08 09 10 11 12 13 Intelligent security controler ( ISC) Reader interface module ,ref (RIM) with power supply Double reader interface module ,ref (DRIM) with power supply Access control push button ,ref (PB) Access control card reader,ref (CR) magnetic door contact Electromagnetic lock for one side door Electromagnetic lock for double side door Outdoor ,wall mounted IP CCD DAY / night camera Ceiling mounted Indoor IP CCD DAY / night camera Ceiling mounted Indoor IP fixed dome camera Outdoor motion sensor with time delay security system network including conduits, wiring, pull boxes, connections, and all required accessories to form a complete and fully operative system QTY UNIT RATE AMOUNT SR

7 14 31 48 76 56 38 8 14 7 23 28
1

No. No. No. No. No. No. No. No. No. No. No. No.
Item

To Collection

SR

Project No. J10-13300 ZUHAIR FAYEZ PARTNERSHIP

66 / 69 REVISED PAGE

Date: MAY 2012

PROJECT: Infrastructure buildings of the residential complex (phase 2) of ITCC complex - RIYADH REVISED BOQ FOR PARKING CLUSTERS (CL03) ITEM DESCRIPTION DIVISION 16 - ELECTRICAL BUILDING MANAGEMENT SYSTEM (BMS) Supply, install, testing, commissioning and integrating the building / cluster BMS system or sub system items (equipment controllers, routers, cables inside the building between system items, conduits, boxes, fiber optic cables,..etc) with phase 1 main BMS system (located in the data center)via LAN network as shown on the building drawings, indicated in plumbing, HVAC and electrical input/ output schedules (all BMS schedules) and as described in the specifications, consisting of but not limited to: 01 To suit building BMS system network and the system should be applicable to linked with existing operating system in phase one after getting approval from service and operation team in phase one to complete the work to the best possible 1 Item QTY UNIT RATE AMOUNT SR

To Collection

SR

Project No. J10-13300 ZUHAIR FAYEZ PARTNERSHIP

67 / 69 REVISED PAGE

Date: MAY 2012

PROJECT: Infrastructure buildings of the residential complex (phase 2) of ITCC complex - RIYADH REVISED BOQ FOR PARKING CLUSTERS (CL03) ITEM DESCRIPTION DIVISION 16 - ELECTRICAL Collection:Sheet - 47 Sheet - 48 Sheet - 49 Sheet - 50 Sheet - 51 Sheet - 52 Sheet - 53 Sheet - 54 Sheet - 55 Sheet - 56 Sheet - 57 Sheet - 58 Sheet - 59 Sheet - 60 Sheet - 61 Sheet - 62 Sheet - 63 Sheet - 64 Sheet - 65 Sheet - 66 Sheet - 67 QTY UNIT RATE AMOUNT SR

To Bill Summary

SR

Project No. J10-13300 ZUHAIR FAYEZ PARTNERSHIP

68 / 69 REVISED PAGE

Date: MAY 2012

PROJECT: Infrastructure buildings of the residential complex (phase 2) of ITCC complex - RIYADH REVISED BOQ FOR PARKING CLUSTERS (CL03) ITEM DESCRIPTION AMOUNT S.R.

BILL SUMMARY Sheet - 17 Sheet - 19 Sheet - 23 Sheet - 24 Sheet - 25 Sheet - 26 Sheet - 28 Sheet - 30 Sheet - 32 Sheet - 33 Sheet - 40 Sheet - 46 Sheet - 68 SITE DEVELOPMENT SITEWORK CONCRETE MASONRY METALS THERMAL AND MOISTURE PROTECTION DOORS AND WINDOWS FINISHES SPECIALTIES CONVEYING SYSTEMS PLUMBING HVAC ELECTRICAL 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0

To Tender Summary

SR

0.0

Project No. J10-13300 ZUHAIR FAYEZ PARTNERSHIP

69 / 69 REVISED PAGE

Date: MAY 2012

You might also like