REVISED PARAMETERS FOR ONLINE PROCESSING OF AICTE SCHEMES FROM FINANCIAL YEAR 2012-13

1 Schemes RPS Research Promotion Scheme National Project

2 NCP Coordinated

3 NAFETIC

4 MODROBS

5 EDC Entrepreneurship Development Cell

Parameters

National Facilities in Modernization and Engineering & Technology with Removal of Obsolescence Industrial Collaboration

Eligibility of Institute

AICTE approved Institutes or AICTE approved University Departments with relevant PG Programs

IISc., IITs, IIMs, NITs, AICTE approved Institutes & AICTE approved University Departments with relevant PG Programs with Accreditation from NBA.

AICTE approved Institutes or AICTE approved Institutes AICTE approved Institutes AICTE approved University or AICTE approved or AICTE approved Departments with relevant PG University Departments. University Departments. Programs with Accreditation from NBA.

Requirements

Method of Assessment

Duration of Project

Full time regular i. Coordinator must be full i. Coordinator must be full faculty with research time regular faculty of time regular faculty of the experience and the Institute. institute. publications; ii. Multi-institutional ii. AICTE approved institutes ii. Research facilities projects. and University Departments available in the iii. Association between running PG programmes. Institute; reputed institutes like IIT, iii. Having accreditation of the iii. Not more than one NIT, IIM, IISc., & AICTE UG/PG programme under proposal from one PI approved Institutes and respective department from at any given time. University Departments NBA. iv. Accreditation from NBA. iv. Matching grant from the Industry. 3 members Expert 3 members Expert 3 members Expert Committee; Committee; out of which 2 Committee; out of which 2 out of which 2 members from members from the members from the the concerned stream not below concerned stream not concerned stream not the rank of Associate Professor. below the rank of Associate below the rank of Associate Professor. Professor. 3 years 3 years 3 years

i.

i. Institute must be 10 years or more old. ii. For self-financing Institutes not more than 3 proposals per institutes per year can be submitted. iii. For Govt./Govt.-aided Institute not more than 10 proposals per Institute per year can be submitted. 3 members Expert Committee; out of which 2 members from the concerned stream not below the rank of Associate Professor. 1 year

I. II. III.

Full time regular faculty as Coordinator One proposal per institute. Existing AICTE sponsored EDC Institutes not eligible to apply again.

3 members Expert Committee; out of which 2 members from the concerned stream not below the rank of Associate Professor. 2 years

Limit of Funding

25 Lakhs

50 Lakhs

50 Lakhs from AICTE & 50 Lakhs from the Industry.

20 Lakhs

10 Lakhs Rs. 4 laks NR Rs. 3 laks R Year 1 Rs. 3 laks R Year 2


and 100% of Non-Recurring Recurring of year 1 Recurring of Year 2 and

Disbursement of funds#

On sanction of proposal Year 2 Year 3


#

100% of Non-Recurring Recurring of year 1

and

100% of Non-Recurring Recurring of year 1

and

100% of Non-Recurring and Recurring of year 1 Recurring of Year 2 Recurring of Year 3

100% of Non-Recurring Recurring of year 1

Recurring of Year 2 Recurring of Year 3

Recurring of Year 2 Recurring of Year 3

---

--

i. Annual Submission of i. Project Completion i. Annual Submission of Progress Report. Report. Progress Report. ii. Project Completion Report. ii. Payment & Receipt A/c. ii. Project Completion iii. Payment & Receipt A/c. iii. Duly audited UC. Report. iv. Duly audited UC. iii. Payment & Receipt A/c. iv. Duly audited UC. Expected outcome To provide state of arts, R&D Modernization of existing In stimulating and achieving facilities, sophisticated testing Lab. excellence in technical and design centre and also education & should be self provide necessary facilities. sustainable after 2 years of establishment. Deliverables i. At least one PhD thesis i. At least one PhD thesis i. At least one PhD thesis Minimum 3 Conferences submitted at the end of submitted at the end of submitted at the end of 3 /Seminars / Workshop / 3 Years. 3 Years. Years. Training Programs ii. Minimum 5 papers ii. Minimum 5 papers ii. Minimum 5 papers organized / annum published out of which published out of which published out of which one one at least in National at least one in National at least in National /International Journal. /International Journal. /International Journal. iii. Minimum 3 Conferences iii. Minimum 3 Conferences iii. Minimum 3 Conferences / / Seminars / Workshop / / Seminars / Workshop / Seminars/Workshop/ Training Programs Training Programs Training Programs organized. organized. organized. iv. Minimum 3 Consultancy iv. Minimum 3 Consultancy iv. Minimum 3 Consultancy projects executed projects executed projects executed # Disbursement of funds for year 2 and 3 shall be based on submission of progress reports to the satisfaction of authority.

Terms and Conditions (Documents to be submitted)

i. Annual Submission of Progress Report. ii. Project Completion Report. iii. Payment & Receipt A/c. iv. Duly audited UC. To create & update general research capabilities.

i. Annual Submission of Progress Report. ii. Project Completion Report. iii. Payment & Receipt A/c. iv. Duly audited UC. The research which contribute directly to the society at large.