COST PLANNING

Presented by: Joe Martin, BCIS Executive Director Date: 19 May 2009

RIBA London CPD, 19-May-09

What is it going to cost?


Early cost advice Order of cost estimate Setting a budget

Developing a cost plan


From elementals to design elements From elements to trades

Life Cycle Cost Planning

RIBA London CPD, 19-May-09

RIBA/BCIS Building Cost Calculator BCIS Online BCIS Building Running Costs Online

RIBA London CPD, 19-May-09

What is it going to cost?

RIBA London CPD, 19-May-09

What cost do we mean?

Capital Cost Best Value Life Cycle Cost Most Economically Advantageous Tender Whole Life Cost Whole Life Value

RIBA London CPD, 19-May-09

What are we going to cost

Schedule of functional requirements Schedule of accommodation Sketch design Outline design

RIBA London CPD, 19-May-09

What are we going to cost?

Schedule of accommodation Offices Shops Catering Theatre Archive 5000m2 1000m2 1000m2 500m2 2000m2

RIBA London CPD, 19-May-09

What are we going to cost?

RIBA London CPD, 19-May-09

What are we going to cost?

Bunker solution (QS design?)

Everything else needs to represent added value to the client


RIBA London CPD, 19-May-09

Developing a cost plan

RIBA London CPD, 19-May-09

Developing the cost plan

Costing at Appraisal, Design Brief


Benchmark estimates Costing the functional requirements Sets the budget

Costing at concept design


Part functional Part costing a design

Costing as design develops


Costing a design solution

RIBA London CPD, 19-May-09

Developing the cost plan

Costing at Appraisal, Design Brief


Cost per m2 building Cost per m2 elements

Costing at concept design


Cost per element unit quantities Cost of designed elements, composite

Costing as design develops


Costing a design solution

RIBA London CPD, 19-May-09

Elements and designed elements

Element Frame

Designed element Steel Frame Weight (tonnes)

Designed element Concrete Length (m)

Designed element Timber Area (m2)

RIBA London CPD, 19-May-09

Design elements and trades

Element External walls

Designed element Profiled sheet cladding

Designed element Brick/block

Designed element curtain walling

'Trade' Brickwork

'Trade' Blockwork

'Trade' Insulation

'Trade' Etc

RIBA London CPD, 19-May-09

Developing the cost plan

NRM New Rules of Measurement Order of cost estimating and elemental cost planning
Provides a structured basis for measuring building work and presenting a consistent approach for dealing with other key cost components associated with a building project. The rules represent essential good practice

RIBA London CPD, 19-May-09

Life cycle cost plan

RIBA London CPD, 19-May-09

COST PLANNING

Presented by: Joe Martin, BCIS Executive Director Date: 19 May 2009

RIBA London CPD, 19-May-09