Professional Documents
Culture Documents
Ritika Sinha(Presenter) Molly Dogra Power Systems Group (N.Nair@auckland.ac.nz) Electrical & Computer Engineering Department University of Auckland 5 October 2011
Presentation Overview
Objective Introduction Protection schemes Implementation Test bench setup Analysis Matrix Conclusions
8/03/2012
To compare bus protection schemes for a 11 kV busbar in Powercos substation Schemes to be compared:
Zone interlocking bus protection scheme Arc flash protection scheme IEC 61850 based GOOSE messaging
INTRODUCTION
Powerco: New Zealands 2nd largest gas and electricity distribution company Busbar: portion of a switchyard or switchgear that electrically interconnects a number of circuit breakers and switches
Copper Busbar
8/03/2012
BUSBAR FAULTS
Causes:
Insulation failure Arcing and Insulation flashover Incorrect handling of switching equipment
Leads to short circuiting of one or more phases Busbar faults can cause:
Damage to the neighboring equipments Damage to the generating units
Outgoing Feeder
8/03/2012
Incoming feeder
8/03/2012
An arc flash occurs due the rapid release of energy due to an arcing fault occurring Arc-flash protection system consists of a network of light sensors placed all throughout the electrical network
Network
IEC61850 GOOSE
8/03/2012
Computer
8/03/2012
PSS SINCAL
PSCAD
Used to simulate the busbar network Stored the fault current waveforms as playback file
8/03/2012
Computer
Playbacks the fault current waveforms Generated waveforms are amplified using power amplifiers
8/03/2012
RELAYS
3 Phase currents were injected in the relay Monitors and picks up the overcurrent signal Issues commands and trips the circuit breaker according to the logic
8/03/2012
ANALYSIS FACTORS
The performance of a Bus protection scheme is judged based on the following criteria: Selectivity Security Speed Cost Complexity
SELECTIVITY
Selectivity of a protection scheme is measured by how accurately it activates the protection of a zone in which the fault has occurred Zone-interlocked schemes achieve selectivity by logic Bus protection systems generally require high levels of selectivity
10
8/03/2012
SECURITY
Security of a bus protection scheme is measured by how well the tripping of the bus in the event of an external fault is prevented Arc Flash Protection Scheme: High inherent security Zone-interlocked Protection: High inherent security
COST
Necessary to obtain the best protection for the minimum cost Arc Flash Protection scheme: additional cost of monitor and sensors Zone- interlocked scheme with GOOSE messaging cheaper than scheme without GOOSE messaging
11
8/03/2012
COMPLEXITY
The most significant aspects impacting scheme complexity are the number of active devices and connecting wires. Zone interlocked GOOSE messaging is least complex in comparison to arc flash protection and zone interlocked scheme without GOOSE messaging
SPEED
Arc Flash protection activated within 10ms Zone-interlocked scheme with and without GOOSE is activated within minimum 45ms
12
8/03/2012
RESULTS
Bus Protection Schemes Comparison
Zone Interlocked Bus Protection Arc Flash Protection Zone Interlocked Bus Protection with IEC 61850 GOOSE messaging High Moderate High Low Low
CONCLUSIONS
Reviewed the existing bus protection schemes Explored IEC 61850 enabled bus protection scheme Tested the schemes using UoA Lab Facilities Formulated a Comparison matrix for assessing the options
13
8/03/2012
Future Work
IEC61850 based GOOSE implementation between relay from different manufacturers Detailed cost analysis for implementing each scheme based on the size and current configuration of substation
Acknowledgements
14
8/03/2012
Ritika Sinha(Presenter) Molly Dogra Power Systems Group (N.Nair@auckland.ac.nz) Electrical & Computer Engineering Department University of Auckland 5 October 2011
15