M/s.

K J S CEMENT LIMITED, MAIHAR


6000 TPD GREENFIELD CEMENT PLANT
Date: 30.08.12

SITE STATUS REPORT ON

SEWAGE TREATMENT PLANT


As per site observation on date 30th August-2012 and the points raised by M/s. AASTHA during their visit on 7th July-2012; following points are noticed---1. Platform for Screen Chamber and Oil & Grease Trap : As per drawing, M/s. AASTHA doesnt have given any clear detail regarding the Platform i.e. Finish Level of Platform & Type of Platform ( RCC or Structural) M/s. KJS Site In-charge also not cleared about the same, weather it is RCC work or structural. 2. Cut Out of Screen Chamber : As per M/s. PETRON, the detailed drawing issued them late on 04.04.12, and now there are---- No provision of supply of electrical power to run the cutting machine, The Screen Chamber is now full of water that needed to be removed first. 3. Inlet Pipe to Screen Chamber is small & needed to change : There is no clear detail in the drawing about the size of Inlet Pipe, and M/s. PETRON has provided 150NB pipe that is now needed to replace.

..Trusst Engineers

4. Brick Work for Sludge Drying Bed : Brick Work is not scope of M/s. PETRON, At present the work is completed by M/s. KJS.

5. Completion of Panel Room : The frame work (RCC activities only) already completed by M/s. PETRON, and balance activities are not in M/s. PETRONs scope i.e. brick work & carpentry activities. Present status towards the completion of Panel Room Plastering Work for Brick Wall in progress by KJS labour, Preparation for Flooring work in progress, and There is no work for fixing Window and Doors. 6. Cut Out of Wall between O & G Trap and Equalization Tank is not Ok. The cut out is not done due to late receipt of drawing and the wall is casted already without providing any cut out. M/s. PETRON is ready to make cut out as per the need but presently --- No power supply at the spot to run cutting machine, The tanks are full of water that should be removed first. 7. Hand Rail work for all Tanks and Staircases : The work is not scope of M/s. PETRON

8. Sludge Recirculation Line : The work is not scope of M/s. PETRON The work need to be finalized.

~2~

9. Completion of Hydro-Testing of all Tanks before back filling : Hydro testing work already completed by M/s. PETRON, Back filling work is not M/s. PETRONs scope; about 75% backing work to Tanks done by M/s. KJS. Balance back filling & compaction is urgent in order to give front to M/s. PETRON to work with upcoming small footings. 10. Back filling & Plinth Protection of Tanks are not completed : Back filling work is not scope of M/s. PETRON, Plinth Protection can only be done after compacted back filling work. 11. Foundation / Platform for all Pumps, Air Blowers and Filter : Foundation work for these items can only be carried out after compacted back filling to the desired areas. 12. Return Effluent drain not completed : This is not scope of M/s. PETRON

Submitted By TRUSST ENGINEERS

~3~