You are on page 1of 131

Consultancy Services for Third Party Quality Audit

in Joint Venture with

MONTHLY REPORT
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

CONTENTS

1.0 2.0 3.0 4.0

Project Background Major Activities and Review Meetings of the Month Out Line Tasks to be carried out Activities of Third Party Quality Audit Consultant

2 3 3 5

Page 1 of 130

MONTHLY REPORT
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

1. Project Background

Andhra Pradesh (AP) state has one of the longest coastal belts in India. Out of 67,362 Km of road network in the state, the nine coastal districts cover 26,000 km of road length. Every year during the period of April-May and September-December, cyclonic situations set in to the Bay of Bengal. With the recent changes in climatic conditions, the catastrophic events are increasing resulting in very devastating cyclones like Laila, Jal etc where the loss is enormous. In the 97 years ranging from 1892 to 1989, there were as many as 67 cyclones within the State. It is essential to provide safe residential accommodation to the vulnerable population during any eventuality or disaster due to natural calamities such as cyclones and associated tidal waves and storm surges. The project is formulated based on experiences of Government of Andhra Pradesh in mitigating such disasters during the past and also keeping in view the existing facilities available in the project area in Andhra Pradesh. The Government of India has applied for a credit of US$ 255 Million equivalent from the International Development Association (IDA) toward the cost of National Cyclone Risk Mitigation Project (NCRMP), and it intends to apply the proceeds to payments for goods, works, related services and consulting services under this Project. National Cyclone Risk Mitigation Project (NCRMP) Project Implementation Unit (PIU), Andhra Pradesh, headquartered at Hyderabad has invited the consultants to submit proposals for providing the consultancy services for Third Party Quality Audit for 9 coastal districts namely Srikakulam, Vijayanagaram, Visakhapatnam, East Godavari, West Godavari, Krishna, Guntur, Prakasam and Nellore. The project Construction of Multipurpose Cyclone Shelters, Roads to Cyclone Shelters, Roads to habitations, Roads & Bridges and Saline Embankments under NCRMP is funded by International Development Association and received through Government of India. This consultancy is envisaged to audit the quality of works being implemented by various line departments working under PIU. To provide Consulting Services of Third Party Quality Auditor for Construction of Multipurpose Cyclone Shelters, Roads to Cyclone Shelters, Roads to habitations, and Roads and Bridges under NCRMP in 9 coastal districts The Commissioner for Disaster Management & Project Director, Project Implementation Unit (PIU) NCRMP has selected Egis International in JV with Egis India Consulting Engineers (I) Pvt. Ltd. On 15th April13, the Contract for Consultancy Service was signed between The Commissioner for Disaster Management & Project Director, Project Implementation Unit (PIU) NCRMP and the Egis International in JV with Egis India Consulting Engineers (I) Pvt. Ltd.

Page 2 of 130

MONTHLY REPORT
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

2. Major Activities and Review Meetings of the Month S.No 1 2 Place Prakasam Hyderabad Date 18.07.2013 29.07.2013 Activity Conducted workshop for Engineers and Contractors on Quality Assurance on NCRMP works at Chief Planning office, Ongole Attended NCRMP Review meeting at 'H' Block, AP Secretariat, Hyderabad

3. Outline of tasks to be carried out The scopes of services for the Third Party Quality Audit (TPQA) assignment are A. The consultant will prepare an inception report within 30 days from signing of the contract that details the method agreed during negotiations to be employed in performing the services. B. Assist SPIU in resolving issues related to Non compliances. C. The field testing being conducted by the implementation staff will be observed and when doubts arise in such observations another sample will be taken and will be tested independently to verify whether it is as per the standards or not. D. The consultant will review civil work components of the cyclone shelters and related roads & bridges of these buildings and compliances and non-compliances will be reported regularly to PIU and line department. E. Consultants will visit the sites for each stage of work and audit F. The consultant will visit the construction sites randomly without prior information to the implementing agency, along with the regular site visits. The consultant will be submitting weekly reports before the 3rd day of the following week. Monthly reports, quarterly reports, annual reports will be submitted as per the scheduled time plan. In case of noncompliance the consultant will be reporting the same to the concerned SPIU representative along with photo documentation and will be suggesting the corrective measures. Regular feedback will be given with regards to compliance of suggested corrective measures. Wherever compliances are not happening, a report should be submitted to the SPIU and line departments and if necessary Stop Work notices will be issued through the Engineer in-charge. G. The consultant will be presenting the quarterly review status which will be giving clear idea of the quality and quantum of work in progress. It gives a clear idea of the compliances and non-

Page 3 of 130

MONTHLY REPORT
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

compliances of the works, the remedial measured suggested & taken up for non-compliances and the modifications needed in the work plan basing on the experiences in the lapsed quarter. H. The consultant will assist SPIU in ensuring the works, by way of reporting, are carried out as per specifications, quality & quantity and towards achieving the desired results. Any defective work noticed by the consultant shall be reported immediately and suggest corrective measures to the field engineers, for immediate rectification and give feedback to SPIU with regards to compliance of suggested corrective measures. Wherever compliances are not happening, a report will be submitted to the SPIU& line department. I. The consultant will participate in the workshops / trainings administrated by the PIUs / line departments, quarterly and also as and when called for to give their inputs and also to act as resource persons as and when needed. J. The competency of the implementation staff will be verified and reported to SPIU and suitable suggestions will be made. K. The work plans of the implementation agency will be observed and suitable modifications will be suggested basing on the past experiences in the sites. L. The consultant will prescribe suitable formats for progress reporting and the same formats will be used to report regularly. M. The consultant will advise on the required site audit procedures for individual duties and responsibilities, including detailed inspection schedules and check lists. N. The Third Party Quality Audit will carry out additional tests, where a prime facie doubt arises related to quality of works and / or compliance of standards using mobile laboratory available with the consultant or nearby approved laboratories. The consultant shall advise few more labs for testing suitably, which after the approval of the SPIU / line departments, can be used for testing. O. Review the workers safety standards being followed in the construction site to avoid any type of losses / damages, as far as possible. P. The tests shall include all common tests as specified in Terms of Reference (ToR). Consultant will take the samples and get it tested in accredited/approved laboratories which will be first inspected and recommended for accrediting by Consultant under the project by SPIU. The identification and certification of the testing agency will be specific to the tests that can be carried out in a particular laboratory. Q. The Consultant will establish a mobile laboratory exclusively for Embankments. R. Surprise field visits will be carried out without advance information to the Line departments and Contractors.

Page 4 of 130

MONTHLY REPORT
Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

S. At the end of every week the Consultant will submit a report containing the details of field visits undertaken during the week indicating the date of visit. In addition to the site level reports and weekly report, consolidated reports would be submitted every month and quarter, compiling the findings in the site reports, summary audit opinion, corrective actions, progress of works and issues etc. The Consultant will also make presentations on audit findings at the designated forums as and when required by the client. 4. Activities of Third Party Quality Audit Consultant. All the activities of TPQA consultant, such as status of TPQA visits, Quality Audit reports, NCR status reports, status of Quality Control tests and other reports are summarized in the tables and furnished in this Monthly Progress Report as detailed below. Status of NCRMP Year-1 works are given in Table-1 Final QCRs to be submitted for the Year-1 works statement is given in Table-2 Spillover works statement for the Year-1 works are given in Table-3 Details of Spillover works for the year-1 works are given in Table-4 Agreements communicated for NCRMP Year-2 works statement given in Table-5 Overall statement of Agreements communicated Year-2 works + Spillover Year-1 works statement is given in Table-6 Status of works communicated agreements and spill over works abstract is given in Table-7 Work wise status for all 9 districts are enclosed as Annexure-A District wise NCR submitted are enclosed as Annexure-B District wise QC tests conducted are enclosed as Annexure-C District wise Civil Engineers, Environmental and Social staff and Electrical engineers site visits abstract and details of visits are enclosed as Annexure-D District wise Surpise site visits abstract enclosed as Annexure-E Statement of Quality Control Audit reports submitted by TPQA Consultant in the month of June-2013 is enclosed as Annexure-F. Photographs of TPQA visits are enclosed as Annexure-G.

Page 5 of 130

Status of NCRMP Year-1 works up to 14.04.2013


No. of works Completed Roads (R&B) No. of Final Reports Submitted No. of works(Under Concluded Agreements) Roads (R&B) S.no Bridges District RHB RCS

TABLE - 1
No. of works not started No. of works under Progress Roads (R&B)

Bridges

Bridges

MPCS

MPCS

MPCS

Total

Total

1 Srikakulam 2 Vizianagaram 3 Visakhapatnam 4 East Godavari 5 West Godavari 6 Krishna 7 Guntur 8 Prakasham 9 Nellore
Total

6 8 2 10 5 3 14 16 64

8 6 8 3 12 7 10 54

2 7 3 2 14

4 2 2 1 9

1 1 2

21 3 21 13 10 8 17 24 26 143

3 0 8 2 10 5 3 14 16 61

8 0 6 7 0 3 11 7 8 50

0 0 5 2 0 0 0 2 0 9

3 2 0 0 0 0 1 1 0 7

1 1 0 0 0 0 0 0 0 2

15 3 19 11 10 8 15 24 24 129

12 3 14 8 10 8 9 24 24 112

3 0 0 0 0 0 0 0 0 3

0 0 0 0 0 0 1 0 2 3

2 0 1 1 0 0 0 0 0 4

1 0 0 0 0 0 1 0 0 2

0 0 0 0 0 0 0 0 0 0

Total

RHB

RHB

RCS

RCS

6 0 1 1 0 0 2 0 2 12

0 0 1 1 0 0 0 0 0 2

Total No. of works entrusted in Year-1 = 143 nos No. of works completed by 14.04.2013 = 129 nos No. of works for which Final QCRs submitted = 112 nos

No. of works deleted = 2 nos Spillover works in to Year 2 = 143 2 129 = 12 nos No. of works for which Final QCRs to be submitted = 17 nos

Page 6 of 130

List of Works which are completed and final QCRs to be submitted by TPQA (awaiting approval of W.E/R.E)
Sl. Dist Categ No rict ory Srikakulam 1 2 3 4 Visakhapatnam 5 6 7 8 East Godavari 9 10 11 12 13 Guntur 14 15 16 17 RCS NCRMP/B-W/AP/RCS/PRED/ 04/Uppalaguptam/003 NCRMP/B-W/AP/MPCS/PRED/ 04/Thondangi/001 NCRMP/B-W/AP/MPCS/PRED/ 04/Thondangi/001 NCRMP/B-W/AP/RCS/PRED/ 07/PV Palem/001 Packages allotted under Phase - 1 s.no Names of works under each package 1 RHB NCRMP/B-W/AP/RHB/PRED/ 01/Santhabommali/003 2 3 NCRMP/B-W/AP/MPCS/PRED /03/Payakaraopeta/003 MPCS NCRMP/B-W/AP/MPCS/PRED /03/Nakkapalli/002 1 2 3 4 5 1 2 3 1 2 3 RCS NCRMP/B-W/AP/RCS/PRED/ 07/Karlapalem/002 4 5 6 Road from DPN R&B road to Uddandapalem Road from K. Umilada Junction to Koduru (Link Road) Road from Borubhadra, Malagam to Kollipadu via Seepuram, Gantapeta Construction of CS at Gajapathinagaram Construction of CS at Ratnayampeta Construction of CS at Patimeeda Construction of CS at Mullaparra Construction of CS at Bangarampeta Road from R&B Road to Chinaraghavulapeta CS Construction of CS at Lakshmanudipeta in Thondangi Construction of CS at Avulamanda Road from R&B road to Mandevaripalem Road from Ganapavaram R&B Road to Pedamarpuvaripalem Road from R&B Road to Chinapuluguvaripalem From R&B road to Yaramvaripalem Road from R&B Road to Pedagollapalem CS Pedagollapalem PR road to Bonthagoralapalem Work Status Work completed Work completed Work completed Work completed Work completed Work completed Work completed Work completed Work completed Work completed Work completed Work completed Work completed Work completed Work completed Work completed Work completed

TABLE - 2

Remarks EOAT and Approval of working estimate awaited EOAT and Approval of working estimate awaited EOAT and Approval of working estimate awaited Approval of working estimate awaited Approval of working estimate awaited working estimate approval not received working estimate approval not received working estimate approval not received Approval of working estimate awaited & ATRs not received working estimate approval not received working estimate approval not received Approval of working estimate awaited Approval of working estimate ATR not received Approval of working estimate ATR not received Approval of working estimate ATR not received Approval of working estimate ATR not received Approval of working estimate ATR not received awaited & awaited & awaited & awaited & awaited &

MPCS

Page 7 of 130

Details of Spill over (NCRMP Year-1) works which are not completed by 14.04.2013
PR Sl. No. District MPCS RCS RHB TOTAL R&B Bridges I & CAD Saline Embankment Works

TABLE - 3
TOTAL Packages Works

Packages Works Packages Works Packages Works Packages Works Packages Works Packages

1 Srikakulam 2 Vizianagaram 3 Visakhapatnam 4 East Godavari 5 West Godavari 6 Krishna 7 Guntur 8 Prakasam 9 Nellore Total

1 0 1 1 0 0 0 0 0 3

2 0 1 1 0 0 0 0 0 4

0 0 0 0 0 0 1 0 1 2

0 0 0 0 0 0 1 0 2 3

2 0 0 0 0 0 0 0 0 2

3 0 0 0 0 0 0 0 0 3

3 0 1 1 0 0 1 0 1 7

5 0 1 1 0 0 1 0 2 10

1 0 0 0 0 0 1 0 0 2

1 0 0 0 0 0 1 0 0 2

0 0 0 0 0 0 0 0 0 0

0 0 0 0 0 0 0 0 0 0

4 0 1 1 0 0 2 0 1 9

6 0 1 1 0 0 2 0 2 12

Page 8 of 130

SPILL OVER (NCRMP YEAR-1) WORKS STATUS


Sl. No 1 2 3 Srikaulam 4 R&B bridge RHB District Categ ory Packages allotted under Phase - 1 NCRMP/B-W/AP/RHB/PRED/ 01/Polaki/006 NCRMP/B-W/AP/RHB/PRED/ 01/Polaki/005 NCRMP/B-W/AP/Br/R&B/ 01/Uppugedda/002 s.no Names of works under each package 1 2 3 Road from R&B road Mobagam to Duubakavanipeta via Gajapathinagaram Road from Talasamudram to Dola Regulator Road from R&B road Edulavalasa - Killam to Jonnam via Talasamudram Construction of High level bridge across Uppugedda at KM 7/6 of Srikakulam muncipal limits to Pukkalapeta via Killipalem in Srikakulam Dt, A.P. Construction of CS at Kollipadu Construction of CS at Runku Agreement No. / Date /2010-11, Dt. 30.04.2011 /2010-11, Dt. 30.04.2011 /2011-12, Dt. 30.04.2011 47/2010-2011, Dt17.12.2010 G.o rt No 451 dt 06.04.2010 G.o rt No 451 dt 06.04.2010 /2011-12, Dt. 03.10.2011 78/2011-12 Dt:17.10.2011 78/2010-11 1.12.2010 2011-2012 1.11.2011 14.09.2012 14.09.2012 Work Status Completed Completed Completed Work in Progress Work in Progress Work in Progress work in progress Completed work in progress Completed work in progress Work completed
WBM Gr-II progress

TABLE - 4
Remarks

Bridge hand rails and finishing work is in progress, Approach road earth work completed Finishings is in progress, & compound wall work is in progress Finishings is in progress, & Sump, Septic tank anfd compound wall execavation is in progress.

5 MPCS 6

NCRMP/B_W/AP/MPCS/PRED/ 01/Santhabommalli/005

5 6

Visakhapa 7 MPCS tnam


8 9

NCRMP/B-W/AP/MPCS/PRED /03/Rambilli/004 NCRMP/B-W/AP/MPCS/PRED/ 04/ Uppalaguptam/002 NCRMP/B-W/AP/Br/R&B/ 07/Bapatla/011 NCRMP/B-W/AP/RCS/PRED/ 07/PV Palem/001 NCRMP/B-W/AP/RCS/PRED/ 09/TADA/009

Construction of CS at Venkayyapalem Construction of CS at Pedaraghavulapeta of Uppalaguptam Mandal Reconstruction of HLB @Km2/4 of Bapatla Pandurangapuram Road across perali drain Road from R&B Road Alluru to Yadavapalem Road from @ 56/8 to C.K road to Periyavettu kuppam CS Providing BT road to Pedapannamgadu in Tada Mandal

All slabs, brick work, plastering, wood joinery, flooring, plumbing, painting completed. One side compound wall is to be construct.

East Godavari Guntur

MPCS Bridges RCS

1 4 6 3 2

Bridge completed Approaches Pending due to LA problem

10 11 12

SPSR Nellore

RCS

Road furniture is balance

Page 9 of 130

Details of Agreements Communicated by SPIU to TPQA Consultant during Quarter 1 ending with June 2013
PR Sl. No. District MPCS RCS RHB TOTAL R&B Bridges I & CAD Saline Embankment Works

TABLE - 5
TOTAL Packages Works

Packages Works Packages Works Packages Works Packages Works Packages Works Packages

1 Srikakulam 2 Vizianagaram 3 Visakhapatnam 4 East Godavari 5 West Godavari 6 Krishna 7 Guntur 8 Prakasam 9 Nellore Total

11 1 1 3 0 0 2 0 0 18

22 1 1 5 0 0 2 0 0 31

4 1 3 6 4 8 2 3 10 41

11 5 4 9 9 26 3 11 18 96

4 0 3 5 8 8 1 8 9 46

10 0 5 8 24 23 1 23 19 113

19 2 7 14 12 16 5 11 19 105

43 6 10 22 33 49 6 34 37 240

0 0 0 2 0 0 1 1 0 4

0 0 0 2 0 0 1 1 0 4

0 0 0 0 0 0 0 0 0 0

0 0 0 0 0 0 0 0 0 0

19 2 7 16 12 16 6 12 19 109

43 6 10 24 33 49 7 35 37 244

Page 10 of 130

TABLE - 6 Details of Agreements Communicated by SPIU to TPQA Consultant during Quarter 1 ending with June 2013 + Spill over works of Year-1
PR Sl. No. District MPCS Packages Works RCS Packages Works RHB Packages Works TOTAL Packages Works R&B Bridges Packages Works I & CAD Saline Embankment Packages Works TOTAL Packages Works

1 Srikakulam 2 Vizianagaram 3 Visakhapatnam 4 East Godavari 5 West Godavari 6 Krishna 7 Guntur 8 Prakasam 9 Nellore Total

12 1 2 4 0 0 2 0 0 21

24 1 2 6 0 0 2 0 0 35

4 1 3 6 4 8 3 3 11 43

11 5 4 9 9 26 4 11 20 99

6 0 3 5 8 8 1 8 9 48

13 0 5 8 24 23 1 23 19 116

22 2 8 15 12 16 6 11 20 112

48 6 11 23 33 49 7 34 39 250

1 0 0 2 0 0 2 1 0 6

1 0 0 2 0 0 2 1 0 6

0 0 0 0 0 0 0 0 0 0

0 0 0 0 0 0 0 0 0 0

23 2 8 17 12 16 8 12 20 118

49 6 11 25 33 49 9 35 39 256

Page 11 of 130

ABSTRACT OF NCRMP WORKS PROGRESS STATUS UP TO JULY 2013


Review of Contract Document Work Entrusted Sl. No. Status of Works Cummulative Visits of TPQA Electrical Engg visits Civil Engineers visits Total No. of QC tests conducted NCRs By TPQA

TABLE - 7
Cummulative Audit Reports submitted by TPQA Electrical Audit reports Social & Env Audit reports Civil Audit Reports

Env & Social visits

Not started

Total Visits

Completed

Stopped / Deleted

I & CADD

Progress

1 Srikakulam 2 Vizianagaram 3 Visakhapatnam 4 East Godavari 5 West Godavari 6 Krishna 7 Guntur 8 Prakasam 9 Nellore Total

48 6 11 23 33 49 7 34 39 250

1 0 0 2 0 0 2 1 0 6

0 0 0 0 0 0 0 0 0 0

49 6 11 25 33 45 9 35 39 252

40 6 11 17 31 38 6 35 39 223

5 0 0 8 2 11 3 0 0 29

40 6 11 17 31 38 5 35 39 222

0 0 0 1 0 0 1 0 0 2

4 0 0 0 0 0 0 0 0 4

192 28 122 114 164 59 70 187 150 1086

32 5 18 1 1 11 2 36 46 152

2 0 13 5 0 0 0 0 0 20

226 33 153 120 165 70 72 223 196

168 48 528 135 229 57 26 654 1030

15 0 10 1 16 5 0 19 15 81

1 0 1 1 16 2 0 10 9 40

Pending

Started

District PR

R&B - Bridges

Issued

Closed

14 0 9 0 0 3 0 9 6 41

17 5 20 4 8 4 1 29 27 115

23 0 9 0 0 8 0 18 24 82

2 17 3 22

1258 2875

Page 12 of 130

Annexure - A

Status of Works

Page 13 of 130

Consolidated Abstract Status of NCRMP Works to the end of July 2013

RATE OF PROGRESS OF WORKS

No of works

up to 10% 11 to 40% 41 to 70% 71 to 100% Works Not Started Deleted


Total No of Works

92 78 19 34 29 4
256

100 90 80 70 60 50 40 30 20 10 0

92 78

34 19

29

4 up to 10% 11 to 40% 41 to 70% 71 to 100% Works Not Started Deleted

Page 14 of 130

Abstract Status of NCRMP Works in Srikakulam District to the end of July 2013

RATE OF PROGRESS OF WORKS

No of works

up to 10% 11 to 40% 41 to 70% 71 to 100% works Deleted Works Not Started Completed
Total No of works

20 13 0 7 4 5 3
49

25 20 15 10 5 0 up to 10% 11 to 40% 0 41 to 70% 71 to 100% works Deleted Works Not Started 20

13

7 4 5

Page 15 of 130

Status of NCRMP works in Srikakulam District to the end of July 2013


Sl. No . Package Nos. Catag S.n Projec ory o t code Work Name Length (Mts) Estimate Value (Rs.lakhs)
110.00

DHS

Date of commencem ent of work


19.10.2011

DFC

Stage of work

% of work done

Reasons for non-started works

Remarks

MPCS NCRMP/BW/AP/MPCS/PRED /01/Santhabommali/00 5

Y2-001

Construction of CS in Kollipadu

7.10.2011

5.07.13

Finishings is in progress, & compound wall work is in progress Finishings is in progress, & Sump, Septic tank anfd compound wall execavation is in progress.

95%

Sand Material is not available for 6 months.

MPCS

Construction of CS in Y2-002 Runku Construction of CS in Amalpadu

109.42

Decebmer 2012

Dec-12

5.07.13

90%

Site handed over to contractor in december 2012, Sand not available for 6 Months.

MPCS

Y2-005

Deleted PR engineers took position of the requuired land in Gramkantam.The villagers wanted to cinstruct the cyclone shelter at Amalapadu. PR officers informed that it will be resolved after elections. Deleted Deleted PR engineers took position of the requuired land in Gramkantam.The villagers wanted to cinstruct the cyclone shelter at Amalapadu. PR officers informed that it will be resolved after elections. 15% 15% 10% Deleted 74.20 20.3.13 _ 14.03.14 Not started Contractor has informed that the work will be started before 1508-2013 Contractor has informed that the work will be started before 1508-2013 _ _ _

MPCS

Y2-006

Construction of CS in Angavanipeta

82.50

18.04.14

Not started

NCRMP/BW/AP/MPCS/PRED/ 01/V.Kotturu/003

MPCS MPCS

5 6

Construction of CS in Ch.Batsalavanipeta Construction of CS in Y2-008 Chintavanipeta Y2-007

MPCS

Y2-009

Construction of CS in U.Narasingupalli

85.00

18.09.14

Not started

MPCS 3 NCRMP/BW/AP/MPCS/PRED/ 01/V.Kotturu/004 MPCS MPCS MPCS 4 NCRMP/BW/AP/MPCS/PRED/ 01/Ranasthalam/008 MPCS

8 9 10 11 12

Construction of CS in Bypalli Construction of CS in Y2-011 Chinavanka Construction of CS in Y2-012 Chinnakothuru Construction of CS in Y2-013 Chinnajittuvani palam Y2-010 Construction of A type Y2-018 CS in Kommaravanipeta, Ranasthalam mandal Construction of MPCS in Y2-023 Ch. Karrivanipalem (Type B), Kaviti mandal

85.00 85.00 74.20

25.03.2013 25.03.2013 25.03.2013

18.04.13 20.04.13 20.05.13

18.09.14 18.09.14 18.09.14

Reinforcement for footings is in progress PCC completed Earth work completed

NCRMP/B-W/AP/MPCS/ MPCS PRED/ 01/Kaviti/011

13

85.00

23.05.2013

19.03.14

Not started

Page 16 of 130

Status of NCRMP works in Srikakulam District to the end of July 2013


Sl. No .
6

Package Nos.

Catag S.n Projec ory o t code

Work Name

Length (Mts)

Estimate Value (Rs.lakhs)


85.00 82.50 82.50

DHS

Date of commencem ent of work


19.06.13 4.05.13 _

DFC

Stage of work

% of work done
5% 10%

Reasons for non-started works


_ _ Contractor has informed that the work will be started before 1508-2013

Remarks

NCRMP/B-W/AP/MPCS/ MPCS PRED/ 01/Sompeta/012 NCRMP/BW/AP/MPCS/PRED/ 01/V.Kothuru/013 MPCS MPCS

14 15 16

Construction of MPCS in Y2-024 Ramayyapatnam (Type B) Y2-025 Y2-026 Construction of MPCS in Metturu (Type D) Construction of MPCS in Nuvvalarevu (Type D)

23.05.2013 20.03.13 20.03.13

14.03.14 Earth work is in progress 14.06.14 14.06.14 Foundation concrete is in progress Not started

With in the mile stone

NCRMP/BW/AP/MPCS/PRED/ MPCS 01/Santhabommali/014 MPCS MPCS MPCS

17

Construction of MPCS in Y2-027 Reddica Sunnapalli (Type C) Y2-028 Construction of MPCS in Calingapatnam (Type D)

74.20

03.04.13

28.06.13

02.04.14 Earth work is in progress

5%

NCRMP/BW/AP/MPCS/PRED/ 01/Gara/015 NCRMP/BW/AP/MPCS/PRED/ 01/Polaki/018

18 19 20

110.00 110.00 85.00

20.03.13 20.3.13 15.03.13

15.04.13 05.05.13 10.04.13

14.06.14 14.06.14 14.03.14

Foundation completed, Back filling is in progress Foundation concrete is in progress PCC work is in progress

20% 15% 10%

With in the mile stone With in the mile stone within milestones Progress slow. Some problem in availability of materials. Site is located in interior area. Progress slow. Some problem in availabilit of materials. Site is located in interior area. Progress slow. Some problem in availability of materials. Site is located in interior area. Progress slow. Some problem in availability of materials. Site is located in interior area. With in the mile stones With in the mile stones With in the mile stones With in the mile stones

Construction of MPCS in Y2-029 Bandravanipeta (Type D) Y2-030 Construction of MPCS in Akkuvaram (Type B)

10

11

NCRMP/BW/AP/MPCS/PRED/ 01/Ranasthalam/016

MPCS

21

Construction of MPCS in Y2-031 Jaganadhapuram (Type B) Y2-032 Construction of MPCS in Kothamukkam (Type A)

82.50

20.03.13

28.06.13

14.06.13

PCC completed

10%

MPCS

22

82.50

20.03.13

30.07.13

14.06.13 Earth work is in progress

5%

12

NCRMP/BW/AP/MPCS/PRED/ 01/Etcherla/017A

MPCS

23

Construction of MPCS in Y2-036 Bonthalakoduru (Type B) Construction of MPCS in Y2-037 Pathadibbalapalem (Type A) Y2-145 Road from Chinnavanka to Gopaladavooru 3675 500 265 785

82.50

15.04.13

10.07.13

2.07.14

Earth work is in progress

5%

MPCS

24

82.50

15.04.13

26.06.13

2.07.14

Earth work completed Road widening is in progress Road widening is in progress GSB layer completed Road widening is in progress

5%

RCS NCRMP/BW/AP/RCS/PRED/ 01/V.Kottoru/001 RCS RCS RCS

25 26 27 28

62.00 23.00 18.00 27.00

25.03.13 25.03.13 25.03.13 25.03.13

18.04.13 18.04.13 18.04.13 18.04.13

14.03.14 14.03.14 14.03.14 14.03.14

10% 10% 20% 10%

13

Road from MN peta Y2-146 Road to Kondavooru and to CS Road from R&B Road to Y2-147 S.J. Puram Y2-148 Road from Kothapeta Road to Sainooru CS

Page 17 of 130

Status of NCRMP works in Srikakulam District to the end of July 2013


Sl. No .
14

Package Nos.
NCRMP/B-W/AP /RCS/PRED/01/ Santhabommali/008

Catag S.n Projec ory o t code


RCS 29

Work Name

Length (Mts)
2000

Estimate Value (Rs.lakhs)


82.00

DHS

Date of commencem ent of work


20.05.13

DFC

Stage of work
Road widening work is in progress and culverts completed. Road widening is in progress Road widening is in progress Road widening is in progress CC road completed, Shoulders work is in progress. Road widening is in progress and culverts completed. Road widening is in progress Completed

% of work done
20%

Reasons for non-started works

Remarks

Borubhadra Y2-150 Meghavaram Road to M. Maruvada Road from Yeeramukkam Rati Y2-154 R&B road to Dunnavooru Road from Y2-155 Yeeramukkam Rati R&B road Geddavooru Road from R&B road Y2-156 Ganguwada to road to Sigalaputtuga Y2-157 Road from R&B road to Akkuvaram Road from R&B road to Pathadibbalapalem Road from R & B road to Pothayyapeta CS Road from R&B road Edulavalasa - Killam to Jonnam via Talasamudram Road from R&B road Mobagam to Duubakavanipeta via Gajapathinagaram

03.04.13

14.01.14

With in mile stones

RCS

30

350

15.75

18.03.13

29.04.13

14.03.14

10%

With in mile stones

15

NCRMP/BW/AP/RCS/PRED/ 01/Mandasa/010

RCS

31

600

27.75

18.03.13

29.04.13

14.03.14

10%

With in mile stones

RCS

32

875

31.43

18.03.13

29.04.13

14.03.14

10%

With in mile stones

RCS NCRMP/BW/AP/RCS/PRED/ 01/Etcherla & Ranasathalam/012

33

585

25.76

18.03.13

17.04.13

14.03.14

90%

With in mile stones

RCS RCS

34 35

Y2-158 Y2-159

3500 1300

100.00 54.00

20.03.13 20.03.13

5.04.13 15.04.13

14.03.14 14.03.14

10% 5%

With in mile stones With in mile stones

16

NCRMP/B-W/AP/RHB/ 17 PRED/01/Polaki/005

RHB

36

Y1-096

2700

76.10

30.04.2011

11.10.2011

31.05.13

100%

RHB 18 NCRMP/B-W/AP/RHB/ PRED/01/Polaki/006 RHB

37

Y1-097

2750

100.40

30.04.2011

11.10.2011

31.05.13

Completed

100%

38

Road from Y1-098 Talasamudram to Dola Regulator Y2-265 Y2-266 Y2-267 Y2-268 Road from B.M (R&B) Road to Simmayyapeta Road from R&B road to Marripadu Road from R&B Road to Kakarapalli Road from R&B road to Marripadu

1600

43.00

30.04.2011

11.10.2011

31.05.13

Completed

100%

RHB RHB NCRMP/B-W/AP /RHB/PRED/01/ Santhabommali/001A RHB RHB

39 40 41 42

1350 400 1200 107.50 700

30.03.13 30.03.13 30.03.13 30.03.13

10.05.13 7.05.13 1.05.13 7.05.13

24.06.14

Road widening is in progress

10%

With in mile stones

24.06.14 GSB laying is in progress 24.06.14 Road widening is in progress

20% 10% 20%

With in mile stones With in mile stones With in mile stones

19

24.06.14 GSB laying is in progress

Page 18 of 130

Status of NCRMP works in Srikakulam District to the end of July 2013


NCRMP/B-W/AP Sl. Catag S.n Projec 19 /RHB/PRED/01/ No Package Nos. ory o t code Santhabommali/001A .

Work Name

Length (Mts)

Estimate 107.50 Value (Rs.lakhs)

DHS

Date of commencem ent of work

DFC

Stage of work

% of work done

Reasons for non-started works


Adjoining land oweners(Paddy fields) are objecting to earthwork widening, Department officers are trying to reslove the issue.

Remarks

RHB

43

Y2-269

Road from R&B road to Pathalingudu

500

24.06.14

Jungle clearence is in progress

20

NCRMP/BW/AP/RHB/PRED/ 01/Santhabommali/001 B

RHB

44

Y2-270

Road from DPN road to Gangaram Village via Palatalagam, Srikrishnapuram

3700

204.00

03.04.13

5.04.13

22.09.14

Sub grade layer completed from km 0/000 to Km 3/200, Bridge earth work completed. Road widening and culverts work completed, WBM gr-II collection is in progress WBM GR-II laying is in progress Road widening and culverts work completed. Road widening and culverts work completed. Bridge hand rails and finishing work is in progress, Approach road earth work completed

25%

Bridge designs are under revision due to short fall in number of spans

21

NCRMP/BW/AP/RHB/PRED/ 01/Polaki/007

RHB

45

DPN road to D.L.Puram jn. via Koduru, Y2-273 Magathapadu, Guppidipeta Y2-274 Guppidipeta road to Chinnakoviripeta

2350

100.00

25.03.13

18.04.2013

19.03.14

30%

With in mile stones

RHB

46

1340

54.00

25.03.13

18.04.2013

19.03.14

30%

With in mile stones

22

NCRMP/B-W/AP/RHB/ PRED/ 01/Polaki/008

RHB

47

K.C. Road to Y2-275 Rajarampuram via Ampalem Revuamplam Y2-276 KC road to Amplam (via) Urjam, Nandigam

900

44.00

29.03.13

18.04.13

24.03.14

20%

With in mile stones

RHB

48

1.6

54.00

29.03.13

18.04.13

24.03.14

20%

With in mile stones

NCRMP/B23 W/AP/Br/R&B/ 01/Uppugedda/002

R&BBr

49

Construction of High level bridge across Uppugedda at KM 7/6 of Y2-438 Srikakulam muncipal limits to Pukkalapeta via Killipalem

128.00

17.12.2010

25.08.12

31.07.13

90%

Delayed due to revision of Drawings. EOAT shall be obtained

Page 19 of 130

Abstract Status of NCRMP Works in Vizianagaram District to the end of July 2013

RATE OF PROGRESS OF WORKS

No of works

up to 10% 11 to 40% 41 to 70% 71 to 100% Works Not Started


Total No of works

6 0 0 0 0
6

35 7 30 6 25 5 20 4 15 3 10 2 5 1 0

31 6

11 6 0 up to 10% 11 to 40% 1 0 41 to 70% 0 71 to 100% 0 Works Not Started

Page 20 of 130

Status of NCRMP works in Vizianagaram District to the end of July 2013


Sl. No. Package Nos. catag S. Project ory no code
Work Name Length (Mts) Estimate Value in (Rs.Lakh s) DHS Date of commence ment of work DFC Stage of work % of work done Reasons for nonstarted works Remarks

NCRMP/BW/AP/MPCS/ PRED/ MPCS 02/Pusapatir ega/003 RCS RCS RCS RCS RCS

Y2-041

Construction of MPCS in Boddugurayyapeta (Type A)

80

14.03.2013

12.06.2013

Earthwork Excavation, PCC for footings, RCC footings, pedestals and columns upto 13.03.2014 bottom of plinth beam work completed. Back filling in foundation completed. 13.03.2014 13.03.2014 13.03.2014 13.03.2014 13.03.2014 Earth work for widening is in progress. Earth work for widening is in progress. Earth work for widning, GSB work completed. Earth work for widning, GSB work completed. Earth work for widning, GSB work completed.

20%

2 3 4 5 6

Y2-160 Y2-161 Y2-162 Y2-163 Y2-164

Road from R & B Road to Gudepuvalasa CS Road from R&B road to Kavulawada CS Road from R & B Road to Roluchappidi CS Road from R&B road to Chinapathiwada CS Road from R&B road to BV peta

440 150 550 60 770

14 16 18.5 4.5 28

14.03.2013 14.03.2013 14.03.2013 14.03.2013 14.03.2013

14.03.2013 14.03.2013 14.03.2013 14.03.2013 14.03.2013

2% 2% 12% 7% 7%

Progress of work is slow Progress of work is slow

NCRMP/BW/AP/RCS/P RED/ 02/Bhogapur am/001

Progress of work is slow progress of work is slow

Page 21 of 130

Abstract Status of NCRMP Works in Visakhapatnam District to the end of July 2013

RATE OF PROGRESS OF WORKS

No of works

up to 10% 11 to 40% 41 to 70% 71 to 100% Works Not Started


Total No of works

1 1 2 7 0
11

8 35 7 30 6 25 5 4 20 3 15 2 10 1 5 0 0

7 31

2 1 1 6 1 41 to 70% 41 to 70%

11

0 0 71 to 100% 71 to 100% Works Not Started Works Not Started

up to 10% up to 10%

11 to 40% 11 to 40%

Page 22 of 130

Status of NCRMP works in Visakhapatnam District to the end of July 2013


Sl. catago Project Package Nos. S.no No. ry code Work name Length (Mts) Estimate Value in Lakhs (Rs.lakhs) DHS Date of commence ment of work DFC Stage of work % of work done Reasons for nonstarted works

Remarks

NCRMP/B-W/ AP/MPCS/ PRED/03/ Rambillii/004

MPCS

Construction of Y2-048 cyclone shelter at Venkayyapalem

70

Re start All slabs, brick work, 02.07.2012 after getting plastering, wood joinery, EOAT approval of flooring,plumbing, painting 03.10.11 approved foundation completed. One side up to re design on compound wall is to be 17.06.2013 29.06.2012 construct.

97%

EOAT shall be obtained from competent authority


Initially Contractor started earthwork on a site handed over to him. The site belongs to forest department. Revenue officials promised to hand over a revenue site adjacent to the forest site. The site is likely to be handed over after elections.

NCRMP/B-W/ AP/MPCS/ PRED/03/ S. Rayavaram/ 009

MPCS

Construction of CS at Bangarampalem I Y2-057 & II H/o Vakadu. (Type D)

110

20.04.13

20.04.2013

19.04.13

Earthwork excavation started and stop due to site dispute. Alternate site is identified and approval is pending.

RCS NCRMP/B-W/ AP/RCS/PRED/ 03/Bheemili/00 5

Road from R & B road to Y2-165 Chinanagamayyapal em CS

1525 Meters

73

11.03.13

11.03.2013

10.12.13

WBM Gr-II From KM 0.000 to Km 0.800 completed. Three nos. CD works completed. WBM Gr-III From KM 0.000 to Km 0.800 spreading completed, compaction work is in progress. WBM Gr-II ( From km0.00 to 1.057 ) and CC Road work ( From km 1.057 to KM 1.107 ) completed . WBM Gr-III From KM 0.000 to Km 0.800 spreading completed, compaction work is in progress.

35%

From KM 0.800 to KM 1.525 is not started. (This stretch falls under forest land.). PIU pursuing the mater with forest department.

RCS

Road from R & B Y2-166 road to Annavaram CS

1100 Meters

73

11.03.13

11.03.2013

10.12.13

51%

Page 23 of 130

Status of NCRMP works in Visakhapatnam District to the end of July 2013


Sl. catago Project Package Nos. S.no No. ry code Work name Length (Mts) Estimate Value in Lakhs (Rs.lakhs) DHS Date of commence ment of work DFC Stage of work % of work done Reasons for nonstarted works

Remarks

NCRMP/B-W/ AP/RCS/PRED/ 03/S.Rayavara am/006 NCRMP/B-W/ AP/RCS/PRED/ 03/Rambilli/00 7

RCS

Road from R & B Y2-167 road to Revupolavaram CS

1065 Meters

56.46

07.03.13

07.03.2013

06.12.13

Earth work for widening, CC Road work completed from KM 0.000 to KM 0.8538 and from KM 0.8845 KM 1.072 Earth work, sub grade,GSB and CC Road work completed from KM 0.000 to KM 0.610 One pipe culvert, WBM GrII, Gr-III and OGPC seal coat Work is completed From KM 0.0 to KM 0.425
Sub grade with selected earth(Gravel): From km 0.640 to 0.750, from KM 1.190 to Km 1.764 completed. Earth work and WBM Gr-II completed From KM 0.000 to KM 0.012, from KM 0.030 to KM 1.764. GSB : 1488 Meters From KM 0.030 to KM 0.094, from KM 0.340 to KM 1.764 completed.

98%

RCS

Road from R & B Y2-168 road to Kothapatnam CS

650 Meters

37

11.03.13

11.03.2013

10.09.13

98%

RHB

Road from R & B Y2-280 road to Rajavaram

425 Meters

168

07.03.13

07.03.2013

06.06.14

95%

RHB NCRMP/B-W/ AP/RHB/PRED/ 03/Payakaraop eta/005

Road from Rajala R Y2-281 & B Road to Rajaraidupalem

1764 Meters

168

07.03.13

07.03.2013

06.06.14

45%

RHB

Road from R & B road to Y2-282 Gajareddipalem via Venkaypalem

2614 Meters

168

07.03.13

07.03.2013

06.06.14

4 Nos pipe culverts completed. From Km 0/106 to Km 1/600 and from km 2/0 to km 2/620 GSB,WBM Gr-II,Grade-III and OGPC + Seal coat completed. From KM 1.600 to Km 2.0 and From KM 2.620 to KM 2.720 GSB work completed.

85%

From KM 1.600 to Km 2.000 and in KM 2.620 to KM 2.720, The local people stopped the work by demanding shifting of electrical poles.

Page 24 of 130

Status of NCRMP works in Visakhapatnam District to the end of July 2013


Sl. catago Project Package Nos. S.no No. ry code Work name Length (Mts) Estimate Value in Lakhs (Rs.lakhs) DHS Date of commence ment of work DFC Stage of work
One single row and one two row pipe culvert works completed. Retaining wall work completed for 62.55 Meters ( 62.55m in km 0/600 ). Earth work, GSB and CC pavement From Km 0/0323 to Km 0/4021, from Km 0/689 to 0/9294 and Cross Road from Km 0/328 to 0/498 Completed

% of work done

Reasons for nonstarted works

Remarks

NCRMP/B-W/ AP/RHB/PRED/ 03/Payakaraop eta/008

RHB

10

Road from Z.P Road Y2-283 Palmanpeta to Korlayyapeta

1110 Meters

58

07.03.13

07.03.2013

06.12.13

93%

NCRMP/B-W/ AP/RHB/PRED/ 03/Atchuta puram/009

RHB

11

Y2-284

Road from R & B Road to Vadapalem

450 Meters

23

07.03.13

07.03.2013

06.09.13

CC Road completed from KM 0.000 to KM 0.4244

95%

Page 25 of 130

Abstract Status of NCRMP Works in East Godavari District to the end of July 2013

RATE OF PROGRESS OF WORKS

No of works

up to 10% 11 to 40% 41 to 70% 71 to 100% Works Not Started


Total No of works

12 3 1 1 8
25

14 12 10 8 6 4 2 0 up to 10% 11 to 40% 41 to 70% 71 to 100% Works Not Started 3 1 1 8 12

Page 26 of 130

Status of NCRMP works in East Godavari District to the end of July 2013
Sl. Package Nos. No. NCRMP/BW/AP/MPCS/PRED/ 04/ Uppalaguptam/002 categor S.no y Project code Work Name Length (Mts) Estimate Value (Rs.lakhs) DHS Date of commencem ent of work DFC Stage of work % of work done Reasons for non-started works Remarks

MPCS

Y2-062

Construction of Cyclone Shelter at Pedaraghavulapeta of Uppalaguptam Mandal

105.65

17.10.11

24.02.12

16.07.13

Completed

100%

NCRMP/BW/AP/MPCS/PRED/ 04/Sakhinetipally/01 0

MPCS

Y2-074

Construction of CS at Kesavadasupalem (Type D)

120

23.04.13

22.07.14

Nil

Nil

site handed over on 2906-2013. Contractor is making arrangements to commence the work _

MPCS

Y2-075

Construction of CS at Pallipalem (Type D) Construction of CS at Padamatapalem (Type D)

120

23.04.13

12.07.2013

22.07.14

Gravel collected for Cattle Ramp Footings and Columns completed ( F1, F4,CF2, CF1, F3, SF2, CF3, SF1 )up to Plinth beam.

0.1

MPCS NCRMP/BW/AP/MPCS/PRED/ 04/Malikipuram/011 MPCS

Y2-076

106.94

22.04.13

21.06.13

21.07.14

5%

Y2-077

Construction of CS at Kesanapalli (Type D)

106.94

22.04.13

No

21.07.14

Nil

Nil

NCRMP/BW/AP/MPCS/PRED/ 04/Mamidikuduru/01 2 NCRMP/BW/AP/RCS/PRED/ 04/U. Kothapalli/002 NCRMP/BW/AP/RCS/PRED/ 04/Malikipuram/009

MPCS

Y2-078

Construction of CS at Karavaka (Type B)

94

22.04.13

No

21.04.14

Nil

Nil

Villge people abjected on the location and Contractor has Not yet started. Departmental officers wanted to resole the issue after elections.

RCS RCS RCS RCS RCS RCS

7 8 9 10 11 12

Y2-169 Y2-170 Y2-171 Y2-172 Y2-173 Y2-174

Road from R&B road to Samanthkurru Pallepalem CS Approach Road from R & B Road to Turupupalem CS Road from R & B Road to Kesanapalli (New) CS Road from R & B Road to Padamatipalem CS Road from R & B Road to Katrenipadu Lanka CS Road from R & B road to Kesavadasupalem (New) CS Road from R&B road to Karavaka CS

120 100 100 1880 640 430

9 7.5 7 70.5 20.5 29.5

26.03.13 04.04.13 04.04.13 04.04.13 29.04.13 29.04.13

06.07.13 No No 14.06.13 08.06.13 16.07.13

25.12.13 03.03.14 03.03.14 03.03.14 30.10.13 30.10.13

Carting Earth Completed. Nil Nil Widening with Earth work Completed. OGPC + Seal coat completed from Km. 0.000 to Km 0.500. Widening and Carting Earth work Completed. 2no. Pipe Culvert Completed

12% Nil Nil 5% 55% 5%

_ Contractor has Not not yet started Contractor has Not not yet started Not started Not started

NCRMP/BW/AP/RCS/PRED/ 04/Razole & Sakhinetipalli/010 NCRMP/BW/AP/RCS/PRED/ 04/Mamidikuduru/01 3

RCS

13

Y2-175

800

33

08.03.13

18.06.13

07.09.13

3%

Page 27 of 130

Status of NCRMP works in East Godavari District to the end of July 2013
Sl. Package Nos. No. NCRMP/BW/AP/RCS/PRED/ 04/Katrenikona/015 categor S.no y Project code Work Name Length (Mts) Estimate Value (Rs.lakhs) DHS Date of commencem ent of work DFC Stage of work % of work done Reasons for non-started works Remarks

RCS

14

Y2-176

CC Road from main proposed road to Neellarevu II CS in Neellarevu Road from R&B road to Samanthakurru CS Road from R&B road to Korukondavari Group Road from R&B road to Gondi Kodapa BT road from Komaragiripatnam to Kadadari and to CS Road from R&B road Samanthakurru to Chakkavaripeta Rameswaram Road from Guthena deevi to Gogullanka Road from R&B road to Ramalayampeta Pallamkurru (v) Road from N. Kothapalli to G.Pora in Katrenikone (v) Road from R&B road to Aravapalem Construction of Bridge at Km 43/10 of Vakalapudi - Edatam road across Pampa Yeru in EG District. Construction of Bridge at Km 43/6 of Vakalapudi - Edatam road across Pampa Yeru in EG District.

540

29

08.03.13

06.07.13

07.02.14

Widening and Carting Earth work Completed. Retaining wall Completed. Widening and Carting Earth work Completed. Widening and Carting Earth work Completed. Widening and Carting Earth work Completed. Widening work Completed. Nil Nil

5%

NCRMP/B10 W/AP/RCS/PRED/ 04/Allavaram/016 NCRMP/BW/AP/RHB/PRED/ 11 04/Sakhinetipalli/00 8

RCS RHB RHB RHB RHB RHB RHB

15 16 17 18 19 20 21

Y2-177 Y2-289 Y2-290 Y2-293 Y2-294 Y2-295 Y2-296

380 1000 830 3500 880 1920 1350

41 44.5 49.5 93 55 105 105

29.04.13 30.03.13 30.03.13 30.03.13 30.03.13 27.04.13 27.04.13

02.06.13 06.06.13 12.06.13 09.07.13 14.07.13 No No

30.10.13 29.02.14 29.02.14 29.03.14 29.03.14 26.04.14 26.04.14

11% 6% 7% 6% 7% _ _ Contractor has Not not yet started Contractor has Not not yet started Contractor has Not not yet started Not started Not started

NCRMP/B12 W/AP/RHB/PRED/ 04/Allavaram/012

NCRMP/B13 W/AP/RHB/PRED/ 04/Katrenikona/014 NCRMP/B14 W/AP/RHB/PRED/ 04/Katrenikona/016 NCRMP/B15 W/AP/RHB/PRED/ 04/Razole/020 NCRMP/BW/AP/Br/R&B/ 16 04/Pampa Yeru1/015 NCRMP/BW/AP/Br/R&B/ 17 04/Pampa Yeru2/016

RHB

22

Y2-297

3500

157

30.03.13

No

29.03.14

Nil WBM Grade III Spreding completed for 200m. Pier 1,2,3 and 4 Wells concrete and shinking in progress. Pier 2 cutting Edge and Kerb completed and Pier 2 cutting Edge and Kerb Reinforcement is in Progress.

Not started

RHB

23

Y2-298

740

13

25.03.13

04.07.13

24.09.13

7%

Bridge

24

Y2-444

8374

505

26.03.13

13.04.13

25.09.14

18%

Bridge

25

Y2-445

5054

355

25.03.13

20.05.13

24.09.14

8%

Page 28 of 130

Abstract Status of NCRMP Works in West Godavari District to the end of July 2013

RATE OF PROGRESS OF WORKS

No of works

up to 10% 11 to 40% 41 to 70% 71 to 100% Works Not Started


Total No of works

7 21 2 1 2
33

25 21 20 15 10 5 0 up to 10% 11 to 40% 41 to 70% 71 to 100% Works Not Started

7 2 2

Page 29 of 130

Status of NCRMP works in West Godavari District to the end of July 2013
Sl. No. Package Nos. catago S. Project ry no code Work Name Estimate Length Value Rs. in (Mts) Rs.lakhs DHS Date of commenceme nt of work DFC Stage of work % of work done Reasons for nonstarted works Remarks

NCRMP/BW/AP/RCS/PRED/ 05/Achanta/002 NCRMP/BW/AP/RCS/PRED/ 05/Bhimavaram/004

RCS

Y2-178

Road from R&B road to Ayodya lanka Marrimula CS. (CC Road)

2500

136.00

30.03.2013

05.04.2013

29.03.2014

Sub grade completed. Sub grade, GSB completed. Sub grade, GSB, CD Works completed. Sub grade, GSB, CD Works completed. Sub grade,GSB completed. CD works is in Progress. Scarifying is in progress. Sub grade completed.

6.00

RCS RCS

2 3 4 5 6 7 8 9

Construction of approach road to Y2-181 CS in Losari of Bhimavaram Mandal. Y2-182 Y2-183 Y2-184 Road from R&B road to Kothakayalathippa CS Road from Narsapur Perupalem R&B road to Mandavarithota

100 1200 1500 850 880 1300 1200 750

7.00 51.70 59.35

08.03.2014

16.05.2013 02.04.2013 02.04.2013

07.09.2013

14.00 27.00 33.70 13.35 10.09 5.23 10.16 10.45

NCRMP/BW/AP/RCS/PRED/ 05/Mogaltur/005

RCS RCS RCS RCS

Road from Mollaparru R & B road to Mollaparru Patha Colony Road from K.P Palem (N) Y2-185 Panchayat office to Metturevu Palli palem Y2-186 R&B road to Chinamynavanilanka Y2-187 PR road to Ramanujapuram Y2-188 Road from P.R road to Prakasapuram K.G. R&B Road to Mamidipudi of Kalawapudi. Khalipatnam R&B Road to Khalipatnam ferry

20.03.2013 58.80 36.15 58.70 61.30 30.00 02.04.2013 02.04.2013 02.07.2013 21.03.2013 02.07.2013 02.07.2013

29.06.14

NCRMP/BW/AP/RCS/PRED/ 05/Narsapur/006

RCS RCS

20.03.2014

Sub grade completed. Sub grade completed.

NCRMP/BW/AP/RHB/PRED/ 05/Kalla/004 NCRMP/BW/AP/RHB/PRED/ 05/Mogaltur/006

RHB

10

Y2-299

2080

91.00

08.03.2013

15.04.2013

07.12.2013

GSB Material collection.

5.09

RHB

11

Y2-302

1800

77.00

21.03.2013

12.04.2013

20.12.2013

Scarifying completed. Earth Work is in Progress. Sub grade,GSB completed. CD works is in Progress. Sub grade,GSB completed. CD works is in Progress. Sub grade & CD Works is in Progress. Sub grade 950 m Completed.

6.54

RHB

12

NCRMP/BW/AP/RHB/PRED/ 05/Mogaltur/008

RHB

13

RHB RHB

14 15

Road from Narsapur Perupalem Y2-306 R&B Road to Melamvaripalem Perupalem (S) Road from Perupalem Mollaparru Y2-307 R&B road via Sattinenivarimeraka to K.D. Pallavapalem Road from Perupalem Y2-308 Dibbalapallipalem R&B road to Mellapallavapalem Road from Perupalem beach R&B Y2-309 Road to Challavarimeraka via Mucherlavarimeraka

800

41.00

15.04.2013

30.41

730

34.20 06.03.2013

15.04.2013 05.06.2014 15.04.2013 15.04.2013

22.45

1860 1760

77.25 76.55

6.06 4.14

Page 30 of 130

Status of NCRMP works in West Godavari District to the end of July 2013
Sl. No. Package Nos. catago S. Project ry no code Work Name Estimate Length Value Rs. in (Mts) Rs.lakhs 1600 62.25 DHS Date of commenceme nt of work 15.04.2013 DFC Stage of work % of work done 19.00 Reasons for nonstarted works Remarks

RHB NCRMP/BW/AP/RHB/PRED/ 05/Mogaltur/009

16

Y2-310

Road from Perupalem R&B road to Dindla

Sub grade completed. CD works is in Progress. 17.06.2014 Sub grade, GSB 1.000 KM completed. CD works is in Progress. Sub grade completed. CD works is in Progress. Sub grade & CD works completed. 13.06.2014 Sub grade completed.. Sub grade & CD works completed.

RHB

17

Road from Narsapur Perupalem Y2-311 R&B road to Nellipallipalem via Ambedkar colony Harijanapeta Y2-312 Y2-313 Road from Perupalem R&B Road to Kouruvaripalem Road from SP R&B road to Pasaladeevi

4600

175.35

18.03.2013 15.04.2013

19.36

RHB RHB 9 NCRMP/BW/AP/RHB/PRED/ 05/Narsapur/010 RHB RHB

18 19 20 21

1800 2650 800 3750

82.15 140.00 34.53 149.47

15.04.2013 20.03.2013 14.03.2013 20.03.2013 20.03.2013

10.32 26.51 12.63 22.53 Villagers are objected. Now the problem is resolved. Work will commence shortly Some villagers went to court not to proceed with work.

Y2-314 LT R&B road to Modi Y2-315 SP R&B road to Gannabathulavari palem of Chamakuripalem

RHB

22

Road from R&B road to SC Colony Y2-316 of Pedalanka

750

47.60

Not Started

0.00

RHB NCRMP/BW/AP/RHB/PRED/ 05/Narsapur/012

23

Y2-317

R&B road to Rajeev Nagar of Darbharevu SP R&B road to Pedathota of Turputallu

1600

76.20

Not Started Sub grade, GSB, WMM, CD Works completed. Shoulders Work is in progress. Scarifying completed. Earth Work & Sub grade work is in Progress. Sub grade, GSB, WMM, CD Works completed. Shoulders Work is in progress. Sub grade & GSB completed. Sub grade completed. 24.03.2014 Sub grade, GSB, CD Works completed. GSB Material collection.

0.00

10

RHB

24

Y2-318

250

18.10

27.03.2013

01.04.2013

26.06.2014

52.92

RHB

25

Y2-319 R&B road to Peta of Turputallu

920

45.70

01.04.2013

12.14

RHB

26

R&B road to Pedathota of Y2-320 Turputallu Y2-321 R&B road to Guttulavarimeraka Y2-322 Road from R & B Road to Pulaparthivaripalem

380

19.40

01.04.2013

54.28

RHB NCRMP/BW/AP/RHB/PRED/ 05/Narsapur/013 RHB RHB RHB

27 28 29 30

970 2000 630 190

40.80 85.65 25.03.2013 39.50 14.05

01.04.2013 01.04.2013 01.04.2013 01.04.2013

14.00 20.12 22.07 5.16

11

Y2-323 R&B road to Pedaedigapalem Y2-324 R&B road to Evanivarimeraka

Page 31 of 130

Status of NCRMP works in West Godavari District to the end of July 2013
Sl. No. Package Nos. catago S. Project ry no code Work Name Estimate Length Value Rs. in (Mts) Rs.lakhs 300 17.00 DHS Date of commenceme nt of work 22.03.2013 DFC Stage of work % of work done 20.00 Reasons for nonstarted works Remarks

RHB

31

Road from PR Road to Y2-325 Prakashpuram SC colony of Vemuladeevi (E) Road from PR road to Vemuladeevi Y2-326 (E) colony (Via) Ralla cheruvu of Vemuladeevi (E) Road from PR road to Y2-327 Addalavarimeraka of Vemuladeevi (E)

Sub grade Completed. Scarifying, WMM & SDBC, Shoulders Completed From Km 0.00 to km 2.484. Subgrade, GSB Form Km 2.484 to 3.025 KM Completed. Sub grade Completed.

12

NCRMP/BW/AP/RHB/PRED/ 05/Narsapur/014

RHB

32

3025

102.00

08.03.2013 22.03.2013

07.03.2014

82.00

RHB

33

1400

56.00

22.03.2013

20.09

Page 32 of 130

Abstract Status of NCRMP Works in Krishna District to the end of July 2013

RATE OF PROGRESS OF WORKS

No of works

up to 10% 11 to 40% 41 to 70% 71 to 100% Works Not Started


Total No of works

31 6 1 0 11
49

35 30 25 20 15 10 5 0

31

11 6 1 up to 10% 11 to 40% 41 to 70% 0 71 to 100% Works Not Started

Page 33 of 130

Status of NCRMP works in Krishna District to the end of July 2013


Sl. No. Package Nos. catago Project S.no ry code Work Name Estimate Length Value of Road (Rs.Lakh (Mts) s) 690 500 290 390 1950 510 43.25 31.08 16.16 21.39 95.16 30.15 DHS Date of commence ment of work 28.05.13 22.07.13 22.07.13 28.05.13 20.07.13 04.06.13 DFC Stage of work % of work done 40 9 3 40 20 4.8 Reasons for non-started works Remarks

RCS NCRMP/BW/AP/RCS/P RED/ 06/koduru/00 1 RCS RCS RCS RCS NCRMP/BW/AP/RCS/P RED/ 06/koduru/00 2 RCS

1 2 3 4 5 6

Y2-189 Y2-190

Road from R&B road to CS @ Ullipalem

21.03.13 21.03.13 21.03.13 21.03.13 21.03.13 21.03.13

Road from R & B Road to CS at Jaruguvanipalem Road from R&B road to CS @ Y2-191 Utagundam Y2-192 Y2-193 Y2-194 Road from R&B road to CS @ Ramakrishna puram Road from R&B road to CS @ Chintakolla Road from R&B road to CS @ Padalavaripalem Road from R&B road to CS @ Mandapakala

CD work, GSB 20.06.14 completed. WMM is in progress 20.06.14 sub grade is in progress Earth work and 20.06.14 scrarifying completed 20.06.14 GSB completed,wmm is in progess

20.06.14 GSB work in progress Earth work completed 20.06.14 and material collected for CD works Widening completed 20.06.14 GSB collection is in progress. 20.03.14 20.03.14 24.06.14 24.06.14 24.06.14 19.06.14 19.06.14 19.06.14 19.06.14 Jungle clearance, earth work completed jungle clearance, earth work in progress Jungle clearance is in progress Jungle clearance ,Scarifying earth work excavation is in progress Jungle clearance is in progress Jungle clearance ,Scarifying earth work excavation is in progress Material collected for CD works RCC slab compled, earth work excavation complted Jungle clearance work is in progress

RCS

Y2-195

590

34.55

21.03.13

04.06.13

5.3

NCRMP/BW/AP/RCS/P RED/ 06/Nagayala nka/003 NCRMP/BW/AP/RCS/P RED/ 06/Nagayala nka/004

RCS RCS RCS RCS RCS RCS

8 9 10 11 12 13 14 15 16

Road from R&B road to Y2-196 Ramakrishna puram R & B Road via Pathaupakali Y2-197 Y2-198 Y2-199 Y2-200 Y2-201 Y2-202 Y2-203 Y2-204 R & B Road to CS at Kothaupakali Road from Uppu Canal drain to CS at Nali Road from Nali R & B Road to Barrankula CS From R&B road to Bhavadevarapalli Road from R&B road to CS at Pedapalem Road from Gullalamoda R&B road to Etimoga Road from R&B to CS at China Etimoga Road from R & B Road to CS at China Kammavaripalem

3300 510 630 2430 230 570 183 210 300

179.04 32.26 33.90 99.78 29.85 37.23 19.65 33.79 26.51

21.03.13 21.03.13 25.03.13 25.03.13 25.03.13 20.03.13 20.03.13 20.03.13 20.03.13

29.07.13 29.07.13 29.07.13 29.07.13 29.07.13 29.07.13 27.07.13 25.05.13 27.07.13

1 1 1 3 1 3.5 1 2 1

NCRMP/BW/AP/RCS/P RED/ 06/Nagayala nka/005

RCS RCS RCS

Page 34 of 130

Status of NCRMP works in Krishna District to the end of July 2013


Sl. No. Package Nos. catago Project S.no ry code Work Name Estimate Length Value of Road (Rs.Lakh (Mts) s) DHS Date of commence ment of work DFC Stage of work % of work done Reasons for non-started works Remarks

RCS

17

Road from China Zinkapalem Y2-205 to Gollamanda via Peda Zinkapalem

2030

103.90

22.03.13

21.06.14 Work not started

RCS NCRMP/BW/AP/RCS/P RED/ 06/Nagayala nka/006

18

Y2-206

Road from R&B road to CS at Gollamanda

900

47.92

22.03.13

21.06.14 Work not started

RCS

19

Y2-207

Road from ZP Road to CS at Natchugunta

300

17.31

22.03.13

21.06.14 Work not started

RCS

20

Y2-208

Road from Krishna River to Elichetladibba CS

720

58.85

22.03.13

21.06.14 Work not started

Materials are to transported across salt creek using punts. Due to the problem of approach roads during rainy season, the works can be taken up after the rainy season only. Prior to the onset of monsoon some work should have been done. Contractor has now informed that the works would be completed before agreement time.

NCRMP/BW/AP/RCS/P RED/ 06/Machilipat nam/008

RCS

21

Road from Kammavanicheruvu R&B road Y2-211 to Venkata durgambapuram in Machilipatnam Mandal Y2-212 Road from R&B Road Pedayadara to Harijanawada Road from R&B Road Karagraharam to Pallipalem

4100

203.77

22.03.13

13.04.13

Earth work started and 21.04.14 GSB material collection in progress 21.04.14 Material collected for CD works

19.5

RCS

22

1100

66.33

22.03.13

02.07.13

Contractor is making arrangements to commence the work. He has informed the works would be completed well before agreement time.

RCS NCRMP/BW/AP/RCS/P RED/ 06/Machilipat nam/010

23

Y2-215

630

41.49

04.06.13

01.09.14 Work not started

RCS

24

RCS RCS

25 26

Road from R&B Road Y2-216 Kammavaricheruvu to KPT palem Road from R&B Road Y2-217 Kammavaricheruvu to Malakayalanka Road from R&B Road Y2-218 Pallithumalapalem to Nelithippa

820

62.74

04.06.13

01.09.14 Work not started

450 245

32.50 17.48

04.06.13 04.06.13

01.09.14 Work not started 01.09.14 Work not started

Page 35 of 130

Status of NCRMP works in Krishna District to the end of July 2013


Sl. No. Package Nos. NCRMP/BW/AP/RHB/ PRED/ 06/Koduru/0 04 NCRMP/BW/AP/RHB/P RED/ 06/Koduru/0 catago Project S.no ry code Work Name Estimate Length Value of Road (Rs.Lakh (Mts) s) DHS Date of commence ment of work DFC Stage of work % of work done Reasons for non-started works Remarks

RHB

27

Y2-328

Road from R&B Road to Narsimhapuram

3550

155.10

22.03.13

19.04.13

21.03.14

CD work& GSB, WMM completed. Material collected for CD works Jungle clearance work is in progress

58.06

10

RHB RHB RHB

28 29 30 31 32 33

Road from R&B Road to Krishnapuram Road from R&B road to Y2-330 Pedagudumotu Road from R&B Road to Parra Y2-335 chivara Y2-329 Y2-336 Y2-337 Y2-338 Road from R&B road to Pedagowdapalem Road from R & B Road to Mulapalem Road from Ganapeswaram R&B Road to Pullaiahgaridibba

2530 1850 800 810 660 1810

118.60 87.40 51.58 54.90 36.05 132.16

22.03.13 22.03.13 25.03.13 25.03.13 25.03.13 25.03.13

25.07.13 17.05.13 17.07.13 17.07.13 17.07.13 17.07.13

21.03.14

1 2 1 2 1 4

21.03.14 CD work is in progress. 24.06.14

11

NCRMP/BW/AP/RHB/P RED/ 06/Nagayala nka/008

RHB RHB RHB

jungle clearance 24.06.14 completed & road widening is in progress 24.06.14 Jungle clearance work is in progress

jungle clearance 24.06.14 completed & road widening is in progress Jungle clearance work is in progress

RHB

34

Road from R & B Road to Y2-343 Indiramma Tank in Gullalamoda

1600

114.24

22.03.13

29.07.13

21.06.14

0.1 Contractor has received mobilization advance on 19.07.13. Contractor has informed that he was making arrangements commence other items of work and complete these works well before agreement time.

12

NCRMP/BW/AP/RHB/P RED/ 06/Nagayala nka/010

RHB

35

Y2-344

Construction of road from ST colony to Uppu drain in Dindi.

1260

104.43

22.03.13

29.07.13

21.06.14

Jungle clearance work is in progress

0.1 Just startrd

RHB

36

Y2-345

Road from Z.P.road to Sorlagondi

1380

110.23

22.03.13

29.07.13

21.06.14

Jungle clearance work is in progress

0.1

RHB

37

Road from R & B road to Y2-346 MPUP School in Sangameswaram

610

44.21

22.03.13

29.07.13

21.06.14

Jungle clearance work is in progress

0.1

Page 36 of 130

Status of NCRMP works in Krishna District to the end of July 2013


Sl. No. Package Nos. catago Project S.no ry code Work Name Estimate Length Value of Road (Rs.Lakh (Mts) s) 1320 72.94 DHS Date of commence ment of work 20.05.13 DFC Stage of work % of work done Reasons for non-started works Remarks

RHB NCRMP/BW/AP/RHB/P RED/ 06/Kruthiven nu/011

38

Road from Matlam Z.P road to Y2-347 Govindarajuladibba in Kruthivennu mandal Road from R&B road to Y2-348 Amudalapalli (Pennamdibba) in Kruthivennu mandal Road from Seethannapalli Y2-349 R&B Road to Gollagudem in Kruthivennu mandal Road from R&B Road to Y2-350 Bolugondi in Kruthivennu mandal Road from R&B Road to Y2-351 Ramapuram

14.03.13

jungle clearance 13.02.14 completed & road widening is in progress CD works completed 13.02.14 &.road widening is in progress CD works completed 13.02.14 &.road widening is in progress CD works completed 13.02.14 &.road widening is in progress

10

13

RHB

39

2000

118.63

14.03.13

01.04.13

11

RHB RHB

40 41

720 1200

51.83 77.44

14.03.13 14.03.13

01.04.13 01.04.13

9 12

Contractor is making arrangements to commence the work. He has informed the works would be completed well before agreement time. Contractor making arrangements to commence the work

14

NCRMP/BW/AP/RHB/P RED/ 06/Kruthiven nu/013

RHB

42

1370

96.05

18.03.13

17.06.14 Work not started

RHB

43

Y2-352

Road from Chinapandraka R&B Road to Uppuluru

3920

271.11

18.03.13

17.06.14 Work not started

15

NCRMP/BW/AP/RHB/P RED/ 06/Kruthiven nu/014

RHB

44

Y2-353 Road from B.L road to Matlam

1950

152.00

26.03.13

17.06.13

25.06.14

Gravel collection is in progress for Sub Base

RHB

45

Y2-354

Road from Interu R&B road to Parvathipuram Road from Gokavaram R & B road to Vodarevupalem Road from Gokavaram R & B road to Baduguvaripalem Road from R&B Road Thallapalem to Rayapalli Road from Manginapudi R & B Road to Pathareddypalem

3054

309.90

26.03.13

25.06.14 Work not started Jungle clearance 16.04.14 completed & road widening is in progress Jungle clearance 16.04.14 completed & road widening is in progress Jungle clearance 16.04.14 completed & road widening is in progress Jungle clearance 16.04.14 completed & road widening is in progress

RHB NCRMP/BW/AP/RHB/P RED/ 06/Machilipat nam/020

46

Y2-366

1060

50.90

18.03.13

25.07.13

RHB

47

Y2-367

470

35.07

18.03.13

25.07.13

16

RHB

48

Y2-368

470

29.49

18.03.13

25.07.13

RHB

49

Y2-369

515

39.55

18.03.13

25.07.13

Page 37 of 130

Abstract Status of NCRMP Works in Guntur District to the end of July 2013

RATE OF PROGRESS OF WORKS

No of works

up to 10% 11 to 40% 41 to 70% 71 to 100% Works Not Started


Total No of works

3 1 0 2 3
9

3.5 3 2.5 2 1.5 1 0.5 0 up to 10% 11 to 40% 0 41 to 70% 71 to 100% Works Not Started 1 2 3 3

Page 38 of 130

Status of NCRMP works in Guntur District to the end of July 2013


Sl. No. Package Nos. NCRMP/B-W/ AP/MPCS/ PRED/07/ Nizampatham/00 3 NCRMP/BW/AP/MPCS/PRE D/ 07/Repalle/005 NCRMP/BW/AP/RCS/PRED / 07/Nizampatnam /005 NCRMP/BW/AP/RCS/PRED / 07/PV Palem/001 catagor y S.no Project code Work Name Length (Mts) Estimate Value (Rs.lakhs) DHS Date of commence ment of work DFC Stage of work % of work done Reasons for nonstarted works Contractor sick. Deprtment issued notice. Praposed to start the work in August. Contractor sick. Department issued notice. Proposed start the work in August Remarks

MPCS

Y2-097

Construction of CS in Sanjeevanagar of Kothapalem (Type B)

35x40

85

22.3.2013

21.3.2014

Work not Started

0%

MPCS

Y2-101

Construction of CS in Lankavanidibba (Type D)

35x40

110

22.3.2013

21.3.2014

Work not Started

0%

RCS

Road from R&B Y2-225 Koosureiyuvaripalem Road to Marakavaripalem

1050

54

21.3.2013

3.6.2013

20.12.2013

GSB is in progress

15%

RCS

Y2-219

Road from R&B Road Alluru to Yadavapalem

1033

51

1.11.2011

15.5.2012

30.4.2013

Work completed

100% -

NCRMP/BW/AP/RCS/PRED / 07/Bapatla/006

RCS

Road from Adavipallipalem R& B Y2-226 road to New Tsunami colony (via) Krupanagar Colony, Adavi Village

751

52

1.4.2013

20.12.2013

Work not Started

0%

Contractor has informed that the work would be started before 1508-2013 -

RCS NCRMP/B-W /AP/RHB/ PRED/07/ Nagaram/007 NCRMP/B-W /AP/Br/ R&B/07/ Bapatla/011 NCRMP/B-W/ AP/Br/R&B/07/ Peddapalli/022

Y2-227

Road from R & B road to Pattapupalem Road from R&B road to Gattuvaripalem

750

46

1.4.2013

18.6.2013

31.3.2014

Earth work is in progress

5%

RHB

Y2-379

2175

124

21.3.2013

3.6.2013

20.3.2014

Earth work is in progress

10%

Bridge

Reconstruction of HLB @Km2/4 of Y2-450 Bapatla-Pandurangapuram Road across perali drain Reconstruction of bridge across Peddapalli drain at km 14/6 of Y2-453 Chandole bridge to Nizampatnam road

355

370

1.12.2010

7.7.2011

31.8.2012

Bridge completed Approaches Pending due to LA problem

90% 5% -

Bridge

193

145

12.3.2012

9.5.2013

11.3.2014

Earth work is in progress

Page 39 of 130

Abstract Status of NCRMP Works in Prakasam District to the end of July 2013

RATE OF PROGRESS OF WORKS

No of works

up to 10% 11 to 40% 41 to 70% 71 to 100% Works Not Started


Total No of works

9 13 4 9 0
35

14 12 10 8 6 4 2 0 up to 10% 9

13

0 11 to 40% 41 to 70% 71 to 100% Works Not Started

Page 40 of 130

Status of NCRMP works in Prakasam District to the end of July 2013


Sl. No. Package Nos. catago Project S.no ry code RCS 1 Y2-228 Work Name Length (Mts) 870 Estimate Value in Lakhs 49 DHS Date of commenc ement of work DFC Stage of work % of work done 10% Reasons for non-started works

Remarks

RCS NCRMP/BW/AP/RCS/PRED/ 08/Chinaganjam & Chirala/006

RCS

RCS RCS

4 5

Road from R&B road to Motupalli CS Road from Km1/2+186 of Chinaganjam Railway gateY2-229 Bapaianagar ZP Road to Ramachandranagar H/o Kothapalem Road from Motupalli R&B Road to Nirikshanagiri (via) Y2-230 Rudramambapuram CS in Motupalli G.P. Road from R&B road to Y2-231 Mattigunta CS Y2-232 Vedullapalli Vodarevu R&B road to CS at Vijayalakshmipuram

25.03.2013 15.05.2013 25.05.2014 Eatrh work in progress

836

39.1

25.03.2013 15.05.2013 25.05.2014 Eatrh work in progress

10%

2276

88.4

25.03.2013 15.05.2013 25.05.2014 GSB in progress

15%

363 482

12.47 19

25.03.2013 15.05.2013 25.05.2014 Eatrh work in progress 25.03.2013 15.05.2013 25.05.2014 Eatrh work in progress 1) GSB Work completed. 2) C.C Work progress. 14.03.2013 02.04.2013 14.05.2014 3) WBM Grade-II, Spreading in progress. 14.03.2013 02.04.2013 14.05.2014 GSB work in progress. 14.03.2013 02.04.2013 14.05.2014 GSB work in progress. 14.03.2013 02.04.2013 14.05.2014 GSB work in progress. 1)GSB & C.C Work completed 2) Shoulders to be done.

10% 10%

RCS NCRMP/B-W/AP /RCS/PRED/08/ S.Konda & Tangutur/010

Road from Pakala PR Road to Y2-233 Chellammagaripattapupalem CS Road from Pakala PR road to Y2-234 Potthaiahgaripalem CS, Kranthinagar Revu. Road from Woollapalem R&B Y2-235 road to Devalampallipalem CS Y2-236 Road from Tangutur to Ananthavaram Road from Z.P. road to Srirampattapupalem

1200

55

30%

RCS RCS RCS

7 8 9

2150 1200 640

102 47 42

20% 20% 20%

RCS 3 NCRMP/B-W/AP /RCS/PRED/08/ Ulavapadu/009

10

Y2-238

2040

108

11.03.2013 15.03.2013 10.03.2014

95%

RCS

11

Y2-239

Road from ZP road to Pallipalem of Chakicharala

800

47.79

GSB Completed, CC Completed CD Completed & WBM Gr-II Completed. 11.03.2013 15.03.2013 10.03.2014 WBM Gr-III Completed, OGPC + SC Completed, CD Works Completed Shoulders in Progress.

98%

Page 41 of 130

Abstract Status of NCRMP Works in SPSR Nellore District to the end of July 2013

RATE OF PROGRESS OF WORKS

No of works

up to 10% 11 to 40% 41 to 70% 71 to 100% Works Not Started


Total No of works

3 20 9 7 0
39

25 20 15 10 5 0 up to 10% 11 to 40% 41 to 70% 71 to 100% 9 7 3 0 Works Not Started 20

Page 42 of 130

Status of NCRMP works in SPSR Nellore District to the end of July 2013
Sl. Package Nos. No. Catagor y S.no Project code Work Name Road from @ 56/8 to C.K road to Periyavettu kuppam cyclone shelter Providing BT road to Pedapannamgadu in Tada Mandal Approach road to Labbipalem Road from R & B road to Pathakadapalem Road from Ramudupalem on R&B road to Pallipalem Road from Korutur to Pattapupalem Road from 230/6 Km of M.C Raod to Pedapattapupalem Road from R&B road to Utukuru Pallipalem Road Ponnapudi R&B Road to Ramachendrapuram. Ponnapudi R&B road to Busagadipalem Road from Ponnapudi R&B Road to Lakshimipuram Road from R&B Road to Ramalingapuram Road from R&B Road Lingavaram to Narravaripalem Road from R&B road (via) Narravaripalrm to Srinivasa Satram Length Mts Estimate Value in lakhs 85 DHS Date of commence ment of work 15.09.2012 DFC Stage of work % of work done 55% Reasons for nonstarted works NIL Remarks

RCS 1 NCRMP/B-W/AP/RCS/PRED/ 09/TADA/009 RCS NCRMP/B-W/AP/RCS/ PRED/09/Alluru/012 NCRMP/B-W/AP/RCS/ PRED/09/Bogole/013

Y2-240

2000

14.09.2012

13.09.2013

WBM Gr-II progress

Y2-241

1015

37.5

14.09.2012

15.09.2012

13.09.2013 BT completed CC pavement is progress Earth work is progress GSB is progress CD works complete Gsb progress, GSB completed.

90%

NIL

2 3

RCS RCS RCS

3 4 5

Y2-242 Y2-243 Y2-244

420 1400 3600

21.97 52.37 203

` 20.03.13 20.03.13

1.05.2013 1.05.2013 10.04.2013

17.09.13 19.09.13 19.06.14

85% 20% 50%

NIL NIL NIL

NCRMP/B-W/AP/RCS/PRED/ 09/I. Pet/018

RCS

Y2-245

2250

148

20.03.13

1.06.2013

19.06.14

34%

NIL

NCRMP/B-W/AP/RCS/PRED/ 09/Kavali/020

RCS

Y2-246

6200

197.92

28.02.13

1.03.2013

27.02.14

41%

NIL

RCS

Y2-247

3800

138

20.03.13

1.04.13

19.06.14

GSB is progress

24%

NIL

RCS 6 NCRMP/B-W/AP/RCS/PRED/ 09/Vidavaluru/ 021 RCS RCS RCS NCRMP/B-W/AP/RCS/PRED/ 09/Chillakur/ 014 NCRMP/B-W/AP/RCS/PRED/ 09/Chillakur/015

9 10 11 12

Y2-248 Y2-249 Y2-250 Y2-251

2000 1900 1000 1700

114 92 51.5 75.5

20.03.13 20.03.13 20.03.13 20.03.13

1.04.13 1.04.13 12.04.2013 12.04.2013

19.06.14 19.06.14 19.06.14 19.06.14

GSB completed GSB progress sub grade completed. CC road in progress Eath work in progress GSB progress

40% 25% 20% 20%

NIL NIL NIL NIL

RCS

13

Y2-252

6808

338.86

21.03.13 21.03.13

22.03.2013

20.03.14

25%

NIL

RCS

14

Y2-253

2260

100.72

1.04.2013

20.03.14

GSB is completed.

30%

NIL

Page 43 of 130

Status of NCRMP works in SPSR Nellore District to the end of July 2013
Sl. Package Nos. No. NCRMP/B-W/AP/RCS/PRED/ 09/Kota/016 Catagor y S.no Project code Work Name Road from R&B Road to Doruvukatta road (via) Allmpadu, Deyyaladibba Road from Kotha Kudur Katepalli road to Patha Pattapupalem Road from C.S. Puram to Edurupalem Road from Mahlakshmi puram to Sagara Sangamam (via) Muthyalathopu Pattapupalem Road from R&B road Nelaturu to Ananthavaram CS Road from @ Km 65/4 of CK Road to Tada Kuppam CS Road from R.I Road to C.R. Palem (via) Sambhunipalem Salt Road from Iskapalli to Salt fields at Kotha Kurrupattapupalem Road from R&B road to Zuvvagu Lakshmipuram Road from R&B Road to Zuvvagu Road from Annagaripalem R&B road to Pedanattu Pattapupalem Road from Pedapattapupalem to Nandempuram Length Mts Estimate Value in lakhs 181.32 DHS Date of commence ment of work 21.03.13 DFC Stage of work % of work done 90% Reasons for nonstarted works NIL Remarks

RCS

15

Y2-254

4320

20.03.13

19.03.14

BT completed

RCS

16

Y2-255

600

35

15.03.13

1.07.2013

14.06.14

Eath work in progress GSB progress

10%

NIL

RCS 10 NCRMP/B-W/AP/RCS/PRED/ 09/T.P.Gudur& Muthukur/019

17

Y2-256

2200

96

15.03.13

1.05.2013

14.06.14

25%

NIL

RCS

18

Y2-257

2600

81

15.03.13

1.05.2013

14.06.14

B.T.completed

90%

NIL

RCS

19

Y2-258

100

11

15.03.13

1.07.2013

14.06.14

Eath work in progress Gsb completed,WMM is progress Vented road dam is progress Gsb completed,WMM progress GSB progress Gsb completed,WMM progress Eath work in progress Gsb completed,WMM progress

5%

NIL

11

NCRMP/B-W/AP/RCS/PRED/ 09/Tada/024 NCRMP/B-W/AP/RHB/PRED/ 09/Allur/018

RCS

20

Y2-259

1900

83.63

22.03.13

23.03.2013

21.03.14

54%

NIL

12

RHB

21

Y2-419

4000

110.01

18.03.13

1.06.2013

17.03.14

10%

NIL

RHB NCRMP/B-W/AP/RHB/PRED/ 09/Allur/019

22

Y2-420

3000

131

18.03.13

19.03.2013

17.03.14

55%

NIL

13

RHB

23

Y2-421

1800

81

18.03.13

19.03.2013

17.03.14

12%

NIL

RHB

24

Y2-422

2100

28

18.03.13

19.03.2013

17.03.14

58%

NIL

14

NCRMP/B-W/AP/RHB/PRED/ 09/Kavali/024

RHB

25

Y2-423

2100

71

04.03.13

1.06.2013

03.03.14

23%

NIL

RHB

26

Y2-424

2800

94

04.03.13

4.3.2013

03.03.14

40.00%

NIL

Page 44 of 130

Status of NCRMP works in SPSR Nellore District to the end of July 2013
Sl. Package Nos. No. Catagor y S.no Project code Work Name Length Mts Estimate Value in lakhs 133.5 54.5 49 64 DHS Date of commence ment of work 21.3.2013 21.3.2013 21.3.2013 21.3.2013 DFC Stage of work % of work done 25% 45% 25% 20% Reasons for nonstarted works NIL NIL NIL NIL Remarks

RHB 15 NCRMP/B-W/AP/RHB/PRED/ 09/Vidavaluru/025 RHB RHB RHB

27 28 29 30

Y2-425 Y2-426 Y2-427 Y2-428

Ponnapudi-Utukur road to Pattapupalem Road from R&B road to Venkatareddypalem Ponnapudi R&B road to Anjanayapuram Ponnapudi Utukur road to Srigowripuram Road from Ponnapudi Utukur R&B road To Kothuru Road from Ponnapudi Utukur R&B road to Prasanthi giri colony Ponnapudi R & B road to Venkatanarayanapuram Road from Ponnapudi R & B road to Ponnapudi Road from Mypadu R&B Road to Kollimittapalem Road from Nellore Mypadu R&B Road to West Pattapupalem Road from Thirumalammapalem R&B Road to Gajulapalli Koneru Road from R&B road Kothapatnam to Yamadinnepalem (via) Srinivasasatram Road from at km 22/5 of Yamadinne palem road to Gunnampadia

2800 1100 950 1100

20.03.13 20.03.13 20.03.13 20.03.13

19.03.14 19.03.14 19.03.14 19.06.14

Eath work in progress Eath work in progress sub grade is in progress sub grade is in progress GSB Completed. Gsb completed,WMM in progress GSB Completed,WMM in progress CC pavement completd GSB completed,WMM is in progress GSB is in progress

RHB NCRMP/B-W/AP/RHB/PRED/ 09/Vidavaluru/026

31

Y2-429

800

59

20.03.13

21.3.2013

19.06.14

25%

NIL

16

RHB

32

Y2-430

1200

64.5

20.03.13

21.3.2013

19.06.14

45%

NIL

RHB

33

Y2-431

1200

64.5

20.03.13

21.3.2013

19.06.14

40%

NIL

RHB RHB 17 NCRMP/B-W/AP/RHB/PRED/ 09/I.Peta/027

34 35

Y2-432 Y2-433

500 2350

35 123.5

20.03.13 20.03.13

21.3.2013 21.03.2013

19.06.14 19.03.14

90% 45%

NIL NIL

RHB

36

Y2-434

900

56.5

20.03.13

20.06.2013

19.03.14

20%

NIL

18

NCRMP/B-W/AP/RHB/PRED/ 09/V.Chalam/021

RHB

37

Y2-435

2400

95.88

08.02.13

9.2.2013

07.11.13

BT completed

90%

NIL

19

NCRMP/B-W/AP/RHB/PRED/ 09/Kota/022

RHB

38

Y2-436

6100

267.31

19.03.13

20.03.2013

18.06.14

GSB completed

25%

NIL

20

NCRMP/B-W/AP/RHB/PRED/ 09/Kota/023

RHB

39

Y2-437

1320

71.78

08.02.13

9.2.2013

07.11.13

BT completed

90%

NIL

Page 45 of 130

Annexure - B

NCR Status of Works

Page 46 of 130

SRIKAKULAM DISTRICT
Sl. No. 1 Package No. NCRMP/B-W/AP/RCS/PRED/ 01/Polaki/006. catag Project ory code RCS Y1-098 Work name Road from Talasamudram to Dola regulator Construction of Cyclone shelter at Calingapatnam Construction of Cyclone shelter at bandaruvanipeta Road from R&B road tyo SJ puram Construction of Cyclone shelter at Metturu Construction of Cyclone shelter at Bypalli Construction of Cyclone shelter at Chinavanka Construction of Cyclone shelter at ChinaKotturu Road from DPN road to gangaram village via Srikrishnapuram, palatalagam Construction of Cyclone shelter at Akkuvaram Date of Issued NCR No.

NCR STATUS AS ON 31.07.2013


Observations aggrement Time completed on 31.05.13, Work continued without sanctioned EOAT, WBM Gr-III layer laid without any intimation ot TPQA Cyclone shelter site located in village limits, Insistsed to provide strong barrication. Cyclone shelter site located in village limits, Insistsed to provide strong barrication. At Some locations, in shoulder portion electrical poles are observed, insist to shift the electrical poles Cyclone shelter site located in School premisis , Insistsed to provide strong barrication. Cyclone shelter site located in School premisis , Insistsed to provide strong barrication. Cyclone shelter site located in School premisis , Insistsed to provide strong barrication. Cyclone shelter site located in School premisis , Insistsed to provide strong barrication. Remedial meassures Present status of NCR

08.06.13

57

NCR-57 Issued and the contractor/Line Department is requested to take suitable remedial action . NCR-1 Issued and the contractor/Line Department is requested to take suitable remedial action . NCR-2 Issued and the contractor/Line Department is requested to take suitable remedial action . NCR-3 Issued and the contractor/Line Department is requested to take suitable remedial action . NCR-4 Issued and the contractor/Line Department is requested to take suitable remedial action . NCR-5 Issued and the contractor/Line Department is requested to take suitable remedial action . NCR-6Issued and the contractor/Line Department is requested to take suitable remedial action . NCR-7Issued and the contractor/Line Department is requested to take suitable remedial action .

Pending

NCRMP/B-W/AP/MPCS/PRED/ MPCS 01/Gara/015. NCRMP/B-W/AP/MPCS/PRED/ MPCS 01/Gara/015. NCRMP/B-W/AP/RCS/PRED/ 01/V.Kotturu/001. RCS

Y2-028

15.06.13

Pending

Y2-029

15.06.13

Pending

Y2-147

17.06.13

Pending

NCRMP/B-W/AP/MPCS/PRED/ MPCS 01/V.kotturu/013. NCRMP/B-W/AP/MPCS/PRED/ MPCS 01/V.kotturu/004. NCRMP/B-W/AP/MPCS/PRED/ MPCS 01/V.kotturu/004. NCRMP/B-W/AP/MPCS/PRED/ MPCS 01/V.kotturu/004. NCRMP/B-W/AP/RHB/PRED/ 01/Santhabommali/001B.

Y2-25

17.06.13

Pending

Y2-010

17.06.13

Pending

Y2-011

17.06.13

Pending

Y2-012

17.06.13

Pending

RHB

Y2-270

17.06.13

bridge portion execavated and barrication not NCR-8Issued and the contractor/Line Department is requested to take suitable provided, Insisted to Provide strong barrication. remedial action . Cyclone shelter site located in School premisis Department is requested to take suitable , Insistsed to provide strong barrication.

Pending

10

NCRMP/B-W/AP/MPCS/PRED/ MPCS 01/Polaki/018.

NCR-9Issued and the contractor/Line remedial action .

Y2-030

17.06.13

Pending

11

NCRMP/B-W/AP/RHB/PRED/ 01/Polaki/007.

RHB

Y2-274

Road from Guppidipeta to Chinnakovvaripeta

29.06.13

10

the GSB layer thickness verified at Km 0/045,0/360,0/600 and observed thickness are 90mm, 95mm, and 92mm respectively instead of 100 mm as specified drawing. Insisted to rectify the same. Prior permission was not taken to Water using for road curing purpose

NCR-10Issued and the contractor/Line Department is requested to take suitable remedial action . NCR no-11 Issued to the contractor/Line department is requested to take suitable remedial action.

NCR-10 closed

12

NCRMP/B-W/AP/RCS/PRED/ 01/Mandasa/010.

RCS

Y2-157

Road from R&B road to Akkuvaram

6.7.13

11

Pending

Page 47 of 130

SRIKAKULAM DISTRICT
Sl. No. 13 Package No. NCRMP/B-W/AP/RCS/PRED/ 01/V.Kotturu/001. catag Project ory code RCS Work name Road from Kotharoad to Sainoore Date of Issued NCR No.

NCR STATUS AS ON 31.07.2013


Observations At some locations, Raingullies are observed, insists to rectify the same. Remedial meassures Present status of NCR

Y2-148

6.7.13

12

NCR no-12 Issued to the contractor/Line department is requested to take suitable remedial action.

Pending

14

NCRMP/B-W/AP/MPCS/PRED/ MPCS 01/Gara/015.

Y2-028

Construction of Cyclone shelter at Calingapatnam

8.7.13

13

NCR no-13 Issued to the contractor/Line Saftey equipment was not provided to concrete workers,insists to provide the safety department is requested to take suitable euipment to workers. remedial action. NCR no-14 Issued to the contractor/Line Saftey equipment was not provided to concrete workers,insists to provide the safety department is requested to take suitable euipment to workers. remedial action.

Pending

15

NCRMP/B-W/AP/MPCS/PRED/ MPCS 01/Santhabommali/005.

Y2-001

Construction of Cyclone shelter at Kollipadu

8.7.13

14

Pending

Page 48 of 130

VIZIANAGARAM DISTRICT
Sl. No. Package No. catago Project ry code Work name Date of Issued NCR No.

NCR STATUS AS ON 31.07.2013


Observations Remedial meassures Present status of NCR

Page 49 of 130

VISAKHAPATNAM DISTRICT
Sl. No. 1 Package No. NCRMP/B-W/AP/RCS/PRED/ 03/Bheemili/005 catago Project ry code RCS Work name Date of Issued NCR No. 1

NCR STATUS AS ON 31.07.2013


Observations WBM Gr-III sample collected and condut the sive analysis test .The test results are IS sieve 45mm size at percentage of 96.13 as agaist of 60% to 90%. The mateial is under size in IS sieve 45mm size. Right side compound wall is in obstruction Km2/652 to 2/658 approximaty 1mt.leftside formers place is there.no contractor and line department are tackling the land acqusition issue at Km1/6 to Km1/9 (at stretch 400mts) shoulders not widths At some locations in shoulder portion Electrical Poles prevents formation/ Compaction of Shoulders.Insisteed to shift the Electrical Poles. Remedial meassures NCR-1 Issued to take suitable remedial action before proceding with further work. The rejected material to be removed from the site and replaced with suitable material NCR-2 Issued to take suitable remedial action before proceding with further work. Present status of NCR NCR pending

Y2-165 Road from R&B road to 20.05.2013 Chinanagamayyapalem cyclone shelter

NCRMP/B-W/AP/RHB/PRED/ 03/Payakaraopeta/005

RHB

Y2-282 Road from R&B road to Gajareddypalem

25.05.13

NCR pending

NCRMP/B-W/AP/RHB/PRED/ 03/Payakaraopeta/005

RHB

Y2-280 Road from R&B Road to Rajavaram

12.06.13

NCRMP/B-W/AP/RHB/PRED/ 03/Payakaraopeta/008

RHB

Y2-283 Road from ZP Road Palmanpeta to Korlayyapeta

12.06.13

At some locations in shoulder portion Electrical Poles prevents formation/ Compaction of Shoulders.Insisteed to shift the Electrical Poles.

NCRMP/B-W/AP/RCS/PRED/ 03/S.Rsyavaram/006

RCS

Y2-167 Road from R&B Road to Revu polavaram cyclone sheler

12.06.13

At some locations in shoulder portion Electrical Poles prevents formation/ Compaction of Shoulders.Insisteed to shift the Electrical Poles.

NCRMP/B-W/AP/RCS/PRED/ 03/Rambilli/007

RCS

Y2-168 Road from R&B Road to Kothapatnam cyclone shelter

12.06.13

At some locations in shoulder portion Electrical Poles prevents formation/ Compaction of Shoulders.Insisteed to shift the Electrical Poles.

NCRMP/B-W/AP/RCS/PRED/ 03/Bheemili/005

RCS

Y2-165 Road from R&B road to Chinanagamayyapalem cyclone shelter

12.06.13

At some locations in shoulder portion Electrical Poles prevents formation/ Compaction of Shoulders.Insisteed to shift the Electrical Poles.

NCR-3 Issued to take suitable remedial action before proceding with further work. The field officer are informed that they collected the demand note from AP Transco and sent from approval NCR-4 Issued to take suitable remedial action before proceding with further work. The field officer are informed that they collected the demand note from AP Transco and sent from approval. NCR-5 Issued to take suitable remedial action before proceding with further work. The field officer are informed that they collected the demand note from AP Transco and sent from approval. NCR-6 Issued to take suitable remedial action before proceding with further work. The field officer are informed that they collected the demand note from AP Transco and sent from approval. NCR-7Issued to take suitable remedial action before proceding with further work. The field officer are informed that they collected the demand note from AP Transco and sent from approval.

NCR pending

NCR pending

NCR pending

NCR pending

NCR pending

Page 50 of 130

VISAKHAPATNAM DISTRICT
Sl. No. 8 Package No. NCRMP/B-W/AP/RCS/PRED/ 03/Bheemili/005 catago Project ry code RCS Work name Date of Issued 12.06.13 NCR No. 8

NCR STATUS AS ON 31.07.2013


Observations Remedial meassures Present status of NCR NCR pending

Y2-166 Road from R&B Road to Annavaram cyclone shelter

NCRMP/B-W/AP/RHB/PRED/ 03/Atchuthapuram/009

RHB

Y2-284 Road from R&B Road to Vadapalem

12.06.13

At some locations in shoulder portion Electrical NCR-8 Issued to take suitable remedial action Poles prevents formation/ Compaction of before proceding with further work. The field Shoulders.Insisteed to shift the Electrical Poles. officer are informed that they collected the demand note from AP Transco and sent from approval. At some locations in shoulder portion Electrical NCR-9 Issued to take suitable remedial action Poles prevents formation/ Compaction of before proceding with further work. The field Shoulders.Insisteed to shift the Electrical Poles. officer are informed that they collected the demand note from AP Transco and sent from approval.

NCR pending

Page 51 of 130

EAST GODAVARI DISTRICT


Sl. No. Package No. catago Project ry code Work name Date of Issued NCR No.

NCR STATUS AS ON 31.07.2013


Observations Remedial meassures Present status of NCR

Page 52 of 130

WEST GODAVARI DISTRICT


Sl. No. 1 Package No. NCRMP/BW/AP/RCS/PRED/ 05/Bhimavaram/004 NCRMP/BW/AP/RCS/PRED/ 05/Mogaltur/005 NCRMP/BW/AP/RCS/PRED/ 05/Mogaltur/005 catago Project ry code RCS Work name Date of Issued 06.07.2013 NCR No. 9

NCR STATUS AS ON 31.07.2013


Observations Thickness of G.S.S is found to be 80mm to 85mm as against the thickness of 100mm in the strech from KM 0/000 to 0/1 00 KM,is shall be rectified immediately Field density tests were conducted at two locations on GSB layer. The observed relatve compaction values are 97.62% and 98.26% as against the specified min 100%. Re compaction is to be done. Field density tests were conducted at two locations on GSB layer. The observed relatve compaction values are 98.26% and 99.58% as against the specified min 100%. Re compaction is to be done. Field density tests were conducted at two locations on GSB layer. The observed relatve compaction values are 96.98% and 99.06% as against the specified min 100%. Re compaction is to be done. Deep rain gullyes are formed in shoulder position at on canal side at several places from Km 0/000 to 0/621 Km. They shall be rectified immediately. Deep rain gullyes are formed in shoulder position at on canal side at several places from Km 0/000 to 0/140 Km. They shall be rectified immediately. Remedial meassures NCR-9 Issued and the contractor/Line Department is requested to take suitable remedial action before proceeding with further work. NCR-10 Issued and the contractor/Line Department is requested to take suitable remedial action before proceeding with further work. NCR-11 Issued and the contractor/Line Department is requested to take suitable remedial action before proceeding with further work. NCR-12 Issued and the contractor/Line Department is requested to take suitable remedial action before proceeding with further work. NCR-13 Issued and the contractor/Line Department is requested to take suitable remedial action before proceeding with further work. NCR-14 Issued and the contractor/Line Department is requested to take suitable remedial action before proceeding with further work. Present status of NCR Closed

Construction of approach Y2-181 road to CS in Losari of Bhimavaram Mandal Road from R&B Road to Y2-182 Kothakayalathippa CS in Mogaltur Mandal Road from Narsapur Perupalem R&B Road to Y2-183 Mandavarithota CS in Mogaltur Mandal Road from Mollaparru R&B Y2-184 Road to Mollaparru Patha Colony in Mogaltur Mandal Road from Narsapur Perupalem R&B Road to Y2-306 Melamvaripalem Perupalem (S) in Mogaltur Mandal Road from R&B Road to Y2-310 Dindla in Mogaltur Mandal

RCS

23.07.2013

10

Closed

RCS

23.7.2013

11

Closed

NCRMP/BW/AP/RCS/PRED/ 05/Mogaltur/005

RCS

23.7.2013

12

Closed

NCRMP/BW/AP/RHB/PRED/ 05/Mogaltur/008 NCRMP/BW/AP/RHB/PRED/ 05/Mogaltur/009 NCRMP/BW/AP/RHB/PRED / 05/Narsapur/012

RHB

23.7.2013

13

Closed

RHB

23.7.2013

14

Closed

RHB

Y2-318

R&B road to Pedathota of Turputallu

27.07.2013

15

NCRMP/BW/AP/RCS/PRED / 05/Bhimavaram/004

RCS

Construction of approach Y2-181 road to CS in Losari of Bhimavaram Mandal.

27.07.2013

16

Field density tests were conducted at two locations on WMM layer. The observed relative Compaction values are 98.31% & 97.57% as against the Specified min 100%, Re Compaction is to be done. Field density tests were conducted at two locations on WMM layer. The observed relative Compaction values are 95.74% & 96.49% as against the Specified min 100%, Re Compaction is to be done.

NCR-15 Issued and the contractor/Line Department is requested to take suitable remedial action before proceeding with further work. NCR-16 Issued and the contractor/Line Department is requested to take suitable remedial action before proceeding with further work.

Closed

Closed

Page 53 of 130

KRISHNA DISTRICT
Sl. No. 1 Package No. catago Project ry code RCS Work name Date of Issued 12.06.13 NCR No. 3

NCR STATUS AS ON 31.07.2013


Observations Electrical poles and Service wire is inconvinent for laying of road. So please take necessary action and For GSB and Carting earth work Test reports are not submitted. Electrical pole @ 375 is in the shoulder portion. So please take necessary action for further work, Electrical pole 12 No's are existing in the shoulder portion. Remedial meassures NCR-3 Issued and the contractor/Line Department is requested to take suitable remedial action before proceeding with further work. NCR-4 issued please shift the electrical pole as soon as possible for further work. NCR-5 issued please shift the electrical pole as soon as possible for furthur work. Present status of NCR

NCRMP/B-W/AP/RCS/PRED/ 06/Machilipatnam/008 NCRMP/B-W/AP/RCS/PRED/ 06/koduru/001 NCRMP/B-W/AP/RHB/ PRED/06/Koduru/004

Road from kammavanicheruvu R&B road Y2-211 to Venkata durgambapuram in Bandar Mandal Y2-189 Y2-328 Road from R&B road to Cyclone Shelter @ Ullipalem Road from R&B Road to Narsimhapuram

Pending

2 3

RCS RHB

26.06.13 26.06.13

4 5

Pending Pending

Page 54 of 130

GUNTUR DISTRICT
Sl. No. Package No. catago Project ry code Work name Date of Issued NCR No.

NCR STATUS AS ON 31.07.2013


Observations Remedial meassures Present status of NCR

Page 55 of 130

PRAKASAM DISTRICT
Sl. No. 1 Package No. NCRMP/B-W/AP/RHB/PRED/ 08/Kothapatnam/019 catago Project ry code RHB Work name Date of Issued 05.06.2013 NCR No.

NCR STATUS AS ON 31.07.2013


Observations Contraction Joints are not Provided as per MORD CLAUSE 1501.8.3 From km 2/500 to km 2/700, WBM grade-II Material is collected at site. Sieve analysis tests are conducted on Random samples.The gradation of the material collected is not satisfying the grading requirements given in MORD TABLE 400.8 Remedial meassures NCR-5 Issued and the contractor/Line Department is requested to take suitable remedial action before proceeding with further work. NCR-10 Issued and the contractor/Line Department is requested to take suitable remedial action before proceeding with further work. Present status of NCR

Road from KEM R&B Road to Y2-410 Pinnivaripalem

Pending

NCRMP/B-W/AP/RHB/PRED/ 08/Chinaganjam/012

RHB

Road from Chinaganjam Y2-388 Railway Gate to Bapaiah Nagar

17.06.2013

10

closed

NCRMP/B-W/AP/RHB/PRED/ 08/Ulavapadu/016 NCRMP/B-W/AP/RCS/PRED/ 08/Ulavapadu/009

RHB

Y2-414

Road from M.C road to West S.T Colony of Veerepalli Road from Pallepalem of Chakicherla

25.06.2013

11

RCS

Y2-239

25.06.2013

12

NCRMP/B-W/AP/RCS/PRED/ 08/S Konda & Tangutur/010

RCS

Road from Pakala PR Road to Y2-233 Chellammagaripattapupalem in 5.07.2013 Singarayakonda Mandal Salt Road from Madnur ZP Y2-400 Road to Bapuji Yanadi Colony 24.07.2013 in Kothapatnam Mandal Y2-401 Salt Road from Madnur ZP Road to Namburi Yanadi Colony in Kothapatnam Mandal Salt Road from Madnur ZP Road to Thotagunta Yanadi Colony in Kothapatnam Mandal 24.07.2014

13

NCRMP/B-W/AP/RHB/PRED/ 08/Kothapatnam/020 NCRMP/B-W/AP/RHB/PRED/ 08/Kothapatnam/020 NCRMP/B-W/AP/RHB/PRED/ 08/Kothapatnam/020 NCRMP/B-W/AP/RHB/PRED/ 08/Kothapatnam/020

RHB

14

RHB

15

RHB

Y2-402

24.07.2014

16

RHB

Salt Road from Madnur ZP Y2-398 Road to Pedapattapupalem in 24.07.2015 Kothapatnam Mandal Y2-399 Salt Road from Madnur ZP Road to 24.07.2016 Swarnandhrapattapupalem in Kothapatnam Mandal

17

NCRMP/B-W/AP/RHB/PRED/ 10 08/Kothapatnam/020

RHB

18

NCRMP/B-W/AP/RHB/PRED/ 11 08/Chinnaganjam/012

RHB

Salt Road from Chinnaganjam Rly gate to Bapuji Yanadi Y2-388 26.07.2013 Colony in Chinnaganjam Mandal

19

NCR-11 Issued and the contractor/Line 11 Culverts are going on ,No safety measures Department is requested to take suitable are taken. remedial action before proceeding with further work. NCR-12 Issued and the contractor/Line A Carved stone of a temple is in obstruction Department is requested to take suitable in carriage way at chainage 0/675 km , remedial action before proceeding with Protection is not provided. further work. From Km 0/400 to Km 0/550 WBM Grade-II NCR-13 Issued and the contractor/Line material is collected at site, sieve analysis tests are conducted on random samples, the Department is requested to take suitable remedial action before proceeding with gradation of the material collected is not satisfying the gradation requirements given in further work. MORD table 400.8 NCR-14 Issued and the contractor/Line Contraction Joints are not Provided as per Department is requested to take suitable MORD CLAUSE 1501.8.3 remedial action before proceeding with further work. NCR-15 Issued and the contractor/Line Contraction Joints are not Provided as per Department is requested to take suitable MORD CLAUSE 1501.8.3 remedial action before proceeding with further work. NCR-16 Issued and the contractor/Line Contraction Joints are not Provided as per Department is requested to take suitable MORD CLAUSE 1501.8.3 remedial action before proceeding with further work. NCR-17 Issued and the contractor/Line Contraction Joints are not Provided as per Department is requested to take suitable MORD CLAUSE 1501.8.3 remedial action before proceeding with further work. NCR-18 Issued and the contractor/Line Contraction Joints are not Provided as per Department is requested to take suitable MORD CLAUSE 1501.8.3 remedial action before proceeding with further work. From Km 3.750 to Km 3.850 WBM Grade-II material is collected at site. Sieve analysis NCR-19 Issued and the contractor/Line tests are conducted on random samples. The Department is requested to take suitable gradation of the materials collected is not remedial action before proceeding with satisfying the gradation requirements given in further work. MORD table 400.8

closed

Pending

Pending

Pending

Pending

Pending

Pending

Pending

Pending

Page 56 of 130

SPSR NELLORE DISTRICT


Sl. No. 1 Package No. NCRMP/B-W/AP/RCS/ PRED/09/KAVALI/020 catago Project ry code RCS Work name Date of Issued 07.06.2013 NCR No. 6

NCR STATUS AS ON 31.07.2013


Observations Remedial meassures Present status of NCR

Road from 230/6Km of M.C Y2-426 Road to Pedapattapupalem of Kavali Mandal Salt road from Iskapalli to Salt fields at Kotha Y2-420 Kurrupattapupalem of Allur madal

NCR-6Issued and the contractor/Line Contractor fails to provide personal protective Department is requested to take suitable eqipement to the Workers remedial action before proceeding with further work. The site condition worse. Contractor fails to provide personal protective eqipement and temperory shelters to the workers. Workers do not have shelter to eat. From km1/8 to km2/0, the camber of WMM is not as specified. It requires immediate rectification. It shall be scarified and re-paved to the required uniform profile. TPQA engineers shall be informed after the rectification for verification. From km 1/8 to km 2/2 no.of electric poles are to be shifted 11 no of Electric poles.4. Action shall be taken to shift water pipe lines, two water sumps and a pressure release valve in the carriageway From km 1/8 to km 2/2. NCR-8 Issued and the contractor/Line Department is requested to take suitable remedial action before proceeding with further work. NCR-9 issued and the contractor/Line Department is requested to take suitable remedial action before proceeding with further work.

NCR PENDING

NCRMP/B-W/AP/RHB/PRED/ 09/Allur/019

RHB

07.06.2013

NCR PENDING

NCRMP/B-W/AP/RHB/PRED/ 09/Kavali/024

RHB

Road from Pedapattapupalem Y2-424 07.06.2013 to Nandempuram

NCR PENDING

NCRMP/B-W/AP/RCS/ PRED/ 09/T.P.Gudur & Muthukur/019

RCS

Road from C.S Puram to Y2-256 Edurupalem

13.06.2013

12

NCR-12 Issued and the contractor/Line Department is requested to take suitable remedial action before proceeding with further work.

NCR PENDING

NCRMP/B-W/AP/RCS/ PRED/ 09/T.P.Gudur & Muthukur/019 NCRMP/B-W/AP/RCS/ PRED/09/Alluru/012

RCS

Road from C.S Puram to Y2-256 Edurupalem

3.07.2013

14

NCR-14 Issued and the contractor/Line WMM material is not satisfying the gradation Department is requested to take suitable requirement as per MORD with Table-412.12. remedial action before proceeding with paver or grader is not avaluble at site. further work. NCR-15 Issued and the contractor/Line Contraction joints are not provided until Department is requested to take suitable now,it shell be provided immediately as per remedial action before proceeding with MORD Clause1501.8.3 further work.

NCR PENDING

RCS

Approach road to Labbipalem Y2-242 in nellore dt

25.07.2013

15

NCR PENDING

Page 57 of 130

Annexure - C
QC Tests conducted by TPQA

Page 58 of 130

Srikakulam District
Sl. Layer/Component of Road No QC tests done to the end of Last Month Total Passed Failed

Summary of QC Tests up to July-2013


QC tests done during this Month Total Passed Failed Cumulative no. of tests Total Passed Failed Remarks

1 2 3 4 5

Embankment Shoulders Granular Sub Base Base Course (WBM) TACK COAT/ SDBC/ OGPC

0 0 12 0 0

0 0 12 0 0

0 0 0 0 0

5 0 0 12 0

0 0 0 12 0

0 0 0 0 0

5 0 12 12 0

0 0 12 12 0

0 0 0 0 0

Tests on Materials (CD Works) 6 7 8 9 Sand Coarse Agreegate Cement Steel 24 20 2 6 8 32 1 0 105 24 20 2 6 8 32 1 0 105 0 0 0 0 0 0 0 0 0 11 10 0 0 6 23 1 0 68 10 9 0 0 6 20 1 0 58 1 1 0 0 0 3 0 0 5 35 30 2 6 14 55 2 0 173 34 29 2 6 14 52 2 0 163 1 1 0 0 0 3 0 0 5 -

10 CC cubes - sets 11 Slump test 12 Water test 13 core cutting test Total

Page 59 of 130

Vizianagaram District
Sl. Layer/Component of Road No QC tests done to the end of Last Month Total Passed Failed

Summary of QC Tests up to July-2013


QC tests done during this Month Total Passed Failed Cumulative no. of tests Total Passed Failed Remarks

1 2 3 4 5

Embankment Soil /Shoulders/SGD Granular Sub Base Base Course (WMM) SDBC

0 0 0 0 0

0 0 0 0 0

0 0 0 0 0

0 0 12 0 0

0 0 12 0 0

0 0 0 0 0

0 0 12 0 0

0 0 12 0 0

0 0 0 0 0

Tests on Materials (CD Works) 6 7 8 9 Sand Coarse Agreegate Cement Steel & Water 4 8 1 0 2 1 12 0 28 4 8 1 0 2 0 12 0 27 0 0 0 0 0 1 0 0 1 2 2 0 0 0 4 0 0 20 2 1 0 0 0 4 0 0 19 0 1 0 0 0 0 0 0 1 6 10 1 0 2 5 12 0 48 6 9 1 0 2 4 12 0 46 0 1 0 0 0 1 0 0 2

10 pH Values 11 CC cubes 12 Workability 13 core cutting test Total

Page 60 of 130

Visakhapatnam District
Sl. No QC tests done to the end of Last Month Total Passed Failed

Summary of QC Tests up to July-2013


QC tests done during this Month Total Passed Failed Cumulative no. of tests Remarks Total Passed Failed

Layer/Component of Road

1 2 3 4 5

Embankment Soil - set Granular Sub Base/ Shoulders Base Course (WBM) OGPC

0 4 24 79 14

0 4 24 78 13

0 0 0 1 1

0 1 8 19 0

0 1 8 19 0

0 0 0 0 0

0 5 32 98 14

0 5 32 97 13

0 0 0 1 1

Tests on Materials (CD Works) 6 7 8 9 Sand Coarse Agreegate Cement Steel & Water 56 66 9 0 24 57 151 7 8 499 56 66 9 0 24 57 151 7 8 497 0 0 0 0 0 0 0 0 0 2 0 0 0 0 0 6 0 0 0 34 0 0 0 0 0 6 0 0 0 34 0 0 0 0 0 0 0 0 0 0 56 66 9 0 24 63 151 7 8 533 56 66 9 0 24 63 151 7 8 531 0 0 0 0 0 0 0 0 0 2 -

10 pH Value 11 CC cubes 12 Workability 13 Bricks 14 Rebound Hammer Total

Page 61 of 130

East Godavari District


Sl. Layer/Component of Road No QC tests done to the end of Last Month Total Passed Failed

Summary of QC Tests up to July-2013


QC tests done during this Month Total Passed Failed Cumulative no. of tests Remarks Total Passed Failed

1 Embankment 2 Soil 3 Granular Sub Base/ Shoulders 4 Base Course (WBM) 5 OGPC Tests on Materials (CD Works) 1 Sand 2 Coarse Agreegate 3 Cement 4 Steel & Water 5 pH Value 6 CC cubes 7 Workability 8 Bricks 9 Rebound Hammer Tests on Materials (MPCS) 1 Sand 2 Coarse Agreegate 3 Cement 4 Steel & Water 5 pH Value 6 CC cubes 7 Workability 8 Bricks 9 Rebound Hammer 10 SBC

0 0 0 9 10 0 0 4 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

0 0 0 9 10 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

0 0 0 0 0 2 5 1 0 1 1 6 0 0 2 5 1 0 2 2 12 0 0 1

0 0 0 0 0 2 5 1 0 1 1 6 0 0 2 5 1 0 2 2 12 0 0 1

0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

0 0 0 9 10 2 5 5 0 1 1 6 0 0 2 5 1 0 2 2 12 0 0 1

0 0 0 9 10 2 5 1 0 1 1 6 0 0 2 5 1 0 2 2 12 0 0 1

0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

Page 62 of 130

East Godavari District


Sl. Layer/Component of Road No QC tests done to the end of Last Month Total Passed Failed

Summary of QC Tests up to July-2013


QC tests done during this Month Total Passed Failed Cumulative no. of tests Remarks Total Passed Failed

Tests on Materials (R&B Bridges) 1 Sand 2 Coarse Agreegate 3 Cement 4 Steel & Water 5 pH Value 6 CC cubes 7 Workability 8 Bricks 9 Rebound Hammer 10 SBC Total

2 6 1 0 1 2 18 0 0 1 56

2 6 1 0 1 2 18 0 0 1 52

0 0 0 0 0 0 0 0 0 0 0

4 11 2 0 3 3 12 0 0 0 79

4 11 2 0 3 3 12 0 0 0 79

0 0 0 0 0 0 0 0 0 0 0

6 17 3 0 4 5 30 0 0 1 135

6 17 3 0 4 5 30 0 0 1 131

0 0 0 0 0 0 0 0 0 0 0

Page 63 of 130

West Godavari District


Sl. Layer/Component of No Road QC tests done to the end of Last Month Total Passed Failed

Summary of QC Tests up to July-2013


QC tests done during this Month Total Passed Failed Cumulative no. of tests Remarks Total Passed Failed

1 2 3 4 5 6

Embankment Shoulders Sub Grade Granular Sub Base Base Course (WMM) SDBC

0 0 59 20 12 6

0 0 59 20 12 6

0 0 0 0 0 0

0 0 9 47 9 0

0 0 9 39 7 0

0 0 0 8 2 0

0 0 68 67 21 6

0 0 68 59 19 6

0 0 0 8 2 0

Tests on Materials (CD Works) 7 8 9 Sand Coarse Aggregate Cement 13 13 3 0 12 26 164 13 13 3 0 12 26 164 0 0 0 0 0 0 0 0 0 0 0 0 0 65 0 0 0 0 0 0 55 0 0 0 0 0 0 10 13 13 3 0 12 26 229 13 13 3 0 12 26 219 0 0 0 0 0 0 10 -

10 Steel 11 CC cubes 12 Slump test Total

Page 64 of 130

Krishna District
Sl. Layer/Component of Road No 1 2 3 3 4 5 6 7 8 9 10 11 12 13 14 Embankment Shoulders Sub grade Granular Sub Base Base Course (WMM) SDBC Sand Coarse Aggregate Cement Steel CC cubes CC Cores Slump test Field density by core cutter method Field density test by sand replacement method Total

Summary of QC Tests up to July-2013


QC tests done to the end of Last QC tests done during this Month Month Total Passed Failed Total Passed Failed Cumulative no. of tests Remarks Total Passed Failed

0 0 0 7 4 0 8 14 0 0 0 0 0 0 0
33

0 0 0 6 4 0 8 13 0 0 0 0 0 0 0
31

0 0 0 1 0 0 0 1 0 0 0 0 0 0 0
2

0 0 0 2 2 0 2 6 0 0 1 0 2 0 0
15

0 0 0 2 2 0 2 6 0 0 1 0 2 0 0
15

0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
0

0 0 0 9 6 0 10 20 0 0 1 0 2 0 9
57

0 0 0 8 6 0 10 19 0 0 1 0 2 0 9
55

0 0 0 1 0 0 0 1 0 0 0 0 0 0 0
2

Tests on Materials (CD Works)

Page 65 of 130

Guntur District
Sl. No Layer/Component of Road

Summary of QC Tests up to July-2013


QC tests done to the end of Last QC tests done during this Month Month Total Passed Failed Total Passed Failed Cumulative no. of tests Remarks Total Passed Failed

1 2 3

Embankment Sub Grade Granual Sub Base Gradation Relative Compaction (FDD)

0 0 1 0 0 0 0 0 0 0 0 0 0 0 0 0

0 0 1 0 0 0 0 0 0 0 0 0 0 0 0 0

0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

0 0 1 0 0 0 0 0 0 0 0 0 0 0 0 0

0 0 1 0 0 0 0 0 0 0 0 0 0 0 0 0

0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

WBM Grade-II Gradation Volumetric Analysis Aggregate Impact Value Water Absorption Screenings

WBM Grade-III Gradation Volumetric Analysis Aggregate Impact Value Water Absorption Screenings

6 7

Prime Coat Rate of spread of Binder Tack Coat Rate of spread of Binder

Page 66 of 130

Guntur District
Sl. No Layer/Component of Road

Summary of QC Tests up to July-2013


QC tests done to the end of Last QC tests done during this Month Month Total Passed Failed Total Passed Failed Cumulative no. of tests Remarks Total Passed Failed

OGPC Grading of 13.2mm & 11.2mm chips Temperature % of BT Content 0 0 0 0 0 0 0 1 1 1 0 1 1 2 1 0 0 0 0 0 0 0 0 0 1 1 1 0 1 1 2 1 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 1 1 1 2 1 2 6 3 0 0 17 0 0 0 0 0 0 0 1 1 1 2 1 2 6 3 0 0 17 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 2 2 2 2 2 3 8 4 0 0 26 0 0 0 0 0 0 0 2 2 2 2 2 3 8 4 0 0 26 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 -

Seal Coat Temperature % of BT Content

10 OGPC + SC Bitumen Extraction Test 11 Shoulder Sand Replacement (FDD) 12 Concrete Cement Combined Gradation FA-Silt Content CA-Gradation CA-AIV CA-Water Absorption Water pH Test Slump Concrete Cubes Concrete Core Rebound Hammer Total

Page 67 of 130

Prakasam District
Sl. Layer/Component of Road No QC tests done to the end of Last Month Total Passed Failed

Summary of QC Tests up to July-2013


QC tests done during this Month Total Passed Failed Cumulative no. of tests Total Passed Failed Remarks

1 2 3

Embankment Sub Grade Granual Sub Base Gradation Relative Compaction(FDD)

0 0 55 37 20 6 6 10 20 10 2 2 4 8 6 6

0 0 54 37 20 6 6 10 20 9 2 2 4 8 6 6

0 0 1

0 0 18 13

0 0 18 13 15 5 5 6 18 9 3 3 6 12 0 0

0 0 0 0 2 0 0 0 0 0 0 0 0 0 0 0

0 0 73 50 37 11 11 16 38 19 5 5 10 20 6 6

0 0 72 50 35 11 11 16 38 18 5 5 10 20 6 6

0 0 1 0 2 0 0 0 0 1 0 0 0 0 0 0

WBM Grade-II Gradation Volumetric Analysis Aggregate Impact Value Water Absorption Screenings 0 0 0 0 0 1 0 0 0 0 0 0 17 5 5 6 18 9 3 3 6 12 0 0

WBM Grade-III Gradation Volumetric Analysis Aggregate Impact Value Water Absorption Screenings

6 7

Prime Coat Rate of spread of Binder Tack Coat Rate of spread of Binder

Page 68 of 130

Prakasam District
Sl. Layer/Component of Road No QC tests done to the end of Last Month Total Passed Failed

Summary of QC Tests up to July-2013


QC tests done during this Month Total Passed Failed Cumulative no. of tests Total Passed Failed Remarks

OGPC Grading of 13.2mm & 11.2mm chips Temperature % of BT Content 12 6 6 6 6 12 0 11 29 21 21 10 11 30 42 44 0 0 459 12 6 6 6 6 12 0 11 29 21 21 10 11 30 42 44 0 0 457 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 2 0 0 0 0 0 3 3 5 8 9 1 5 5 6 11 10 0 14 195 0 0 0 0 0 3 3 5 8 9 1 5 5 6 11 10 0 14 193 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 2 12 6 6 6 6 15 3 16 37 30 22 15 16 36 53 54 0 14 654 12 6 6 6 6 15 3 16 37 30 22 15 16 36 53 54 0 14 650 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 4 -

Seal Coat Temperature % of BT Content

10 OGPC + SC Bitumen Extraction Test 11 Shoulder Sand Replacement (FDD) 12 Concrete Cement Combined Gradation FA-Silt Content CA-Gradation CA-AIV CA-Water Absorption Water pH Test Slump Concrete Cubes Concrete Core Rebound Hammer Total

Page 69 of 130

SPSR Nellore District


Sl. Layer/Component of No Road QC tests done to the end of Last Month Total Passed Failed

Summary of QC Tests up to July-2013


QC tests done during this Month Total Passed Failed Cumulative no. of tests Remarks Total Passed Failed

1 2 3 4 5

Embankment Sub Grade Granual Sub Base WMM MSS

96 93 203 69 45

96 93 202 69 45

0 0 1 0 0

0 4 19 33 0

0 4 19 33 0

0 0 0 0 0

96 97 222 102 45

96 97 222 102 45

0 0 1 0 0

Tests on Materials 6 7 8 9 Sand Coarse Agreegate Cement Steel 77 44 57 0 133 4 110 24 Total 955 79 42 57 0 133 4 110 24 954 2 2 0 0 0 0 0 0 5 4 1 3 0 6 0 4 1 75 4 1 3 0 6 0 4 1 75 0 0 0 0 0 0 0 0 0 81 45 60 0 139 4 114 25 1030 81 45 60 0 139 4 114 25 1030 2 2 0 0 0 0 0 0 5 -

10 CC cubes 11 Cores 12 Slump 13 Water ph

Page 70 of 130

Annexure - D Visits by TPQA Consultants

Page 71 of 130

NCRMP WORKS - ABSTRACT OF TPQA (CIVIL ENGG) INSPECTION STATUS UP TO JUNE-2013 PR


MPCS Cummulative During this Month Up to last month Sl. No. District Works RCS Cummulative During this Month Up to last month RHB Cummulative During this Month Up to last month R&B BRIDGES Cummulative During this Month Up to last month I & CADD Total Visits SALINE EMBANKMENTS Cummulative During this Month Up to last month

Works

Works

Works

Works

1 Srikakulam 2 Vizianagaram 3 Visakhapatnam 4 East Godavari 5 West Godavari 6 Krishna 7 Guntur 8 Prakasam 9 Nellore Total

24 1 8 6 0 0 2 0 0 41

71 7 33 7 0 0 12 2 0 132

33 3 0 7 0 0 0 0 0 43

104 10 33 14 0 0 12 2 0 175

11 5 4 9 9 22 4 11 20 95

32 12 40 13 25 15 15 27 59 238

8 6 5 3 16 30 7 8 30 113

44 18 45 16 41 45 22 35 89 355

13 0 5 8 24 23 1 23 19 116

27 0 38 12 105 13 8 86 69 358

10 0 6 2 16 29 6 55 64 188

35 0 44 14 121 42 14 141 133 544

1 0 0 2 0 0 2 1 0 6

8 0 0 10 0 0 22 4 0 44

3 0 0 8 0 0 7 7 0 25

11 0 0 18 0 0 29 11 0 69

0 0 0 0 0 0 0 0 0 0

0 0 0 0 0 0 0 0 0 0

0 0 0 0 0 0 0 0 0 0

0 0 0 0 0 0 0 0 0 0

194 28 122 62 162 87 77 189 222 1143

Page 72 of 130

TPQA (CIVIL ENGG) SITE INSPECTIONS DURING THE MONTH OF JULY-2013 Name of the District: SRIKAKULAM
Sl. Project catago No Code ry 1 2 3 6 7 9 11 12 13 14 15 18 19 Y2-270 Y2-266 Y2-268 Y2-273 Y2-274 Y2-002 Y2-001 MPCS MPCS Name of work visited Construction of Cyclone shelter at Runku in Santhabommali Mandal. Construction of Cyclone shelter at Kollipadu in Santhabommali Mandal. Construction of HLB across uppugedda at Km 7/6 of Srikakulam municipal limits to Pukkalapeta Road from R&B road to S.J.puram Road from Kothapeta Road to Sainooru CS Road from R&B road to pathadibbapalem Road from R&B road to Akkuvaram Road from Borubadra, Meghavaram road to M.Maruvada Road from DPN road to gangaram village Via Palatalagam, Srikrishnapuram Road from DPN R&B road to Marripadu Road from DPN R&B road to Marripadu Adl DPN road to DL purtam jn via Koduru, magathapadu, Guppidipeta Guppidipeta road to Chinnakoviripeta Work stage Finishings is in progress, & Sump, Septic tank and compound wall execavation completed Finishings is in progress, & Sump, Septic tank and compound wall execavation is in progress. Wearing coat completed and Hand rails work is in progress, Approach road earth work Completed GSb layer completed Road widening is in progress Culverts completed, Road widening is in progress CC road completed, Shoulders work is in progress Culverts completed and road widening is in progress Sub grade layer completed, and bridge earth work is in progress. GSB laying is in progress GSB laying is in progress Culverts completed and WBM GR-II collection is in proress. WBM GR-II laying is in progress Date of visit 19.07.13 19.07.13 4.7.13 10.7.13 27.7.13 6.7.13 6.7.13 1.7.13 20.7.13 1.7.13 5.7.13 19.7.13 15.7.13 9.7.13 19.7.13 26.7.13 19.7.13 19.7.13 22.07.13 26.7.13 1.7.13 6.7.13 22.7.13 3.7.13 8.7.13 19.7.13 24.7.13 27.7.13 8.7.13 24.7.13 27.7.13 2.7.13 6.7.13 12.7.13 18.7.13 19.7.13 22.7.13 2.7.13 6.7.13 12.7.13 19.7.13 6.7.13 12.07.13 19.7.13 6.7.13 8.7.13 17.7.13 20.7.13 26.7.13 8.7.13 8.7.13 8.7.13 8.7.13 31.7.13 Total visits 1 1 3 1 1 2 3 1 3 1 1 2 3

Y2-438 R&B Br Y2-147 Y2-148 Y2-158 Y2-157 RCS RCS RCS RCS RCS RHB RHB RHB RHB RHB

20

Y2-028

MPCS Construction of cyclone shelter at Calingapatnam

Foundation completed, Back filling is in progress

21

Y2-029

MPCS Construction of Cyclone shelter at Bandaruvanipeta

Foundation concrete work is in progress

23

Y2-025

MPCS Construction of Cyclone shelter at Metturu

Foundation concrete work is in progress

24

Y2-010

MPCS Construction of Cyclone shelter at Bypalli

Reinforcement of Foundation is in progress

25 26 27

Y2-011 Y2-012 Y2-031

MPCS Construction of Cyclone shelter at Chinavanka MPCS Construction of Cyclone shelter at Chinakotturu MPCS Construction of Cyclone shelter at Jaganadhapuram

Pcc completed Earth work completed Pcc completed

3 1 4

28 29 30 31

Y2-032 Y2-018 Y2-036 Y2-037

MPCS Construction of Cyclone shelter at Kottamukkam MPCS Construction of Cyclone shelter at Komaravanipeta MPCS Construction of Cyclone shelter at Bonthalakoduru MPCS Construction of Cyclone shelter at patadibbalapalem

Earth work is in progress jungle clearence is in progress jungle clearence is in progress Earth work completed

1 1 1 2

Page 73 of 130

TPQA (CIVIL ENGG) SITE INSPECTIONS DURING THE MONTH OF JULY-2013 Name of the District: VIZIANAGARAM
Sl. Project catago No Code ry 1 2 3 Y2-162 Y2-163 Y2-164 RCS RCS RCS Name of work visited Road from R&B Road to Roluchappidi cyclone shelter Road from R&B road to Chinapathiwada Cyclone shelter. Road from R&B road to B.V.Peta cyclone shelter Work stage Date of visit 02.07.13 10.07.13 02.07.13 10.07.13 02.07.13 10.07.13 Total visits

Earth work for widning, GSB work completed. Earth work for widning, GSB work completed. Earth work for widning, GSB work completed.

2 2 2

Y2-041

MPCS

Construction of cyclone shelter at Buddugurayyapeta

Earthwork Excavation, PCC for footings, RCC footings, pedestals and columns upto bottom of plinth beam work completed. Back filling in foundation completed.

02.07.13 10.07.13 31.07.13

Page 74 of 130

TPQA (CIVIL ENGG) SITE INSPECTIONS DURING THE MONTH OF JULY-2013 Name of the District: VISAKHAPATNAM
Sl. Project catago No Code ry 1 Y2-165 RCS Name of work visited Road from R&B road to Chinanagamayyapalem cyclone shelter Road from R&B road to Annavaram cyclone shelter Road from R&B road to Kothapatnam Road from Rajala R&B road to Rajarayyudupalem Work stage WBM Gr-II From KM 0.000 to Km 0.800 completed. 3 nos. CD works completed. WBM Gr-III From KM 0.000 to Km 0.800 spreading completed, compaction work is in progress. WBM Gr-II ( From km0.00 to 1.057 ) and CC Road work ( From km 1.057 to KM 1.107 ) completed . WBM Gr-III From KM 0.000 to Km 0.800 spreading completed, compaction work is in progress. Earth work, sub grade,GSB and CC Road work completed from KM 0.000 to KM 0.610 Sub grade with selected earth(Gravel): From km 0.640 to 0.750, from KM 1.190 to Km 1.764 completed. Earth work and WBM Gr-II completed From KM 0.000 to KM 0.012, from KM 0.030 to KM 1.764. GSB : 1488 Meters From KM 0.030 to KM 0.094, from KM 0.340 to KM 1.764 completed. One single row and one two row pipe culvert works completed. Retaining wall work completed for 62.55 Meters ( 62.55m in km 0/600 ). Earth work, GSB and CC pavement From Km 0/0323 to Km 0/4021, from Km 0/689 to 0/9294 and Cross Road from Km 0/328 to 0/498 Completed Date of visit 02.07.13 10.07.13 02.07.13 10.07.13 04.07.13 01.07.13 04.07.13 08.07.13 17.07.13 Total visits 2

Y2-166

RCS

Y2-168

RCS

Y2-281

RHB

Y2-283

RHB

Road from ZP Road Palamanpeta to Korlayyapeta.

17.07.13 24.07.13

Page 75 of 130

TPQA (CIVIL ENGG) SITE INSPECTIONS DURING THE MONTH OF JULY-2013 Name of the District: EAST GODAVARI
Sl. Project catago No Code ry 1 2 3 4 5 6 7 8 9 Y2-060 Y2-061 Y2-062 Y2-076 Y2-075 Y2-289 Y2-290 Y2-173 Y2-174 MPCS MPCS MPCS MPCS MPCS RHB RHB RCS RCS Name of work visited Cyclone Shelter at Avulamanda and of Thondangi Mandal , E.G.Dt. Cyclone Shelter at Lakshmanudipeta of Thondangi Mandal, E.G.Dt. Cyclone Shelter at Pedaraghavulapeta of Uppalaguptam Mandal, E.G.Dt. Construction of Cyclone Shelter at Padamatipalem ( Type - D) Consruction of Cyclone Shelter at Pallipalem ( Type - D) Road from R&B Road to Korukondavari Group Road from R&B Road to Gondi Kodapa Road from R&B road to Katrenipadu Lanka Cyclone Shelter Road from R&B road to Kesavadasupalem (New) Cyclone Shelter Construction of Bridge at Km.43/10 of VakalapudiEdatam road across Pampa Yeru in EG DT. Work stage Completed Completed Completed Date of visit 05.07.2013 05.07.2013 04.07.2013 Total visits 1 1 1 3 1 1 1 2 1

02.07.2013, RCC Raft and Columns work is in progress 18.07.2013, 27.07.2013 Gravel Stacks is in progress for Cattle ramp 27.07.2013 GSB is in Progress GSB is in Progress OGPC + Seal Coat Completed From Km. 0.000 to Km 0.500 Carting Earth Work is in Progress. Pier 1, 2, 3 and 4 Cutting Edge work is in progress 02.07.2013 02.07.2013 02.07.2013, 27.07.2013 27.07.2013

10

Y2-444

Bridge

11

Y2-445

Bridge

Construction of Bridge at Km.43/6of Vakalapudi- Edatam road across Pampayeru in EG DT.

11.07.2013, 13.07.2013, 19.07.2013, 25.07.2013 11.07.2013, Pier 2 Well Concrete and Shinking work is 13.07.2013, in progress 19.07.2013, 25.07.2013

20

Page 76 of 130

TPQA (CIVIL ENGG) SITE INSPECTIONS DURING THE MONTH OF JULY-2013 Name of the District: WEST GODAVARI
Sl. Project catago No Code ry 2 3 4 5 7 8 9 Y2-181 Y2-182 Y2-183 Y2-184 Y2-186 Y2-187 Y2-188 RCS RCS RCS RCS RCS RCS RCS Name of work visited Work stage Date of visit 06.07.2013, 10.07.2013, 26.07.2013, 31.07.2013 23.07.2013, 29.07.2013 23.07.2013, 29.07.2013 23.07.2013, 29.07.2013 02.07.2013, 09.07.2013 02.07.2013, 09.07.2013 02.07.2013, 09.07.2013 Total visits

Construction of approach road to CS in Losari of Bhimavaram Mandal. Road from R&B road to Kothakayalathippa CS Road from Narsapur Perupalem R&B road to Mandavarithota Road from Mollaparru R & B road to Mollaparru Patha Colony R&B road to Chinamynavanilanka PR road to Ramanujapuram Road from P.R road to Prakasapuram Road from Narsapur Perupalem R&B Road to Melamvaripalem Perupalem (S) Road from Perupalem Mollaparru R&B road via Sattinenivarimeraka to K.D. Pallavapalem

GSB completed. GSB, CD Works completed. Sub grade, GSB, CD Works completed. Sub grade,GSB completed. CD works is in Progress. Sub grade completed. Sub grade completed. Sub grade completed. Sub grade,GSB completed. CD works is in Progress. Sub grade,GSB completed. CD works is in Progress.

4 2 2 2 2 2 2

12 13

Y2-306 Y2-307

RHB RHB

05.07.2013, 23.07.2013, 29.07.2013 04.07.2013, 23.07.2013 03.072013, 29.07.2013

3 2

16

Y2-310

RHB

Road from Perupalem R&B road to Dindla

Sub grade completed. CD works is 23.07.2013, in Progress. Sub grade, GSB 1.000 KM completed. CD works is in Progress. Sub grade, GSB, WMM, CD Works completed. Shoulders Work is in progress. Sub grade, GSB, WMM, CD Works completed. Shoulders Work is in progress. Sub grade & GSB completed.

17

Y2-311

RHB

Road from Narsapur Perupalem R&B road to Nellipallipalem via Ambedkar colony Harijanapeta SP R&B road to Pedathota of Turputallu

09.07.2013

24

Y2-318

RHB RHB RHB

09.07.2013 09.07.2013, 27.07.2013, 31.07.2013 08.07.2013, 27.07.2013,

26 28

Y2-320 Y2-322

R&B road to Pedathota of Turputallu Road from R & B Road to Pulaparthivaripalem

3 2

32

Y2-326

RHB

Road from PR road to Vemuladeevi (E) colony (Via) Ralla cheruvu of Vemuladeevi (E)

Scarifying, WMM & SDBC, Shoulders Completed From Km 0.00 to km 2.484. Subgrade, GSB 27.07.2013 From Km 2.484 to 3.025 KM Completed.

Page 77 of 130

TPQA (CIVIL ENGG) SITE INSPECTIONS DURING THE MONTH OF JULY-2013 Name of the District: KRISHNA
Sl. No 1 Project catagory Code Y2-189 RCS Name of work visited Work stage Date of visit 06.07.13 24.07.13 22.07.13 31.07.13 22.07.13 27.07.13 20.07.13 31.07.13 09.07.13 27.07.13 31.07.13 29.07.13 31.07.13 29.07.13 31.07.13 29.07.13 31.07.13 22.07.13 29.07.13 31.07.13 29.07.13 29.07.13 27.07.13 22.07.13 27.07.13 27.07.13 06.07.13 24.07.13 02.07.13 24.07.13 06.07.13 24.07.13 31.07.13 25.07.13 31.07.13 27.07.13 17.07.13 27.07.13 31.07.13 17.07.13 27.07.13 31.07.13 Total visits 2

Road from R&B road to Cyclone Shelter @ Ullipalem

WMM 1st layer completed.

2 3 4 5 6 7 8 9 10

Y2-190 Y2-191 Y2-192 Y2-193 Y2-194 Y2-195 Y2-196 Y2-197 Y2-198

RCS RCS RCS RCS RCS RCS RCS RCS RCS

Road from R & B Road to CS at Jaruguvanipalem Road from R&B road to Cyclone Shelter @ Utagundam Road from R&B road to Cyclone Shelter @ Ramakrisna puram Road from R&B road to Cyclone shelter @ Chintakolla Road from R&B road to Cyclone Shelter @ Padalavaripalem Road from R&B road to Cyclone Shelter @ Mandapakala

Earth work is in progress earth work and scrarifying completed GSB completed,wmm is in progess GSB work in progress Earth work completed and material collected for CD works GSB & WMM collection in progress

2 1 1 2 2 1 2 2 2

Road from R&B road to Ramakrishnapuram R & B Road Scarifying work completed, GSB work via Pathaupakali is in progress R & B Road to Cyclone Shelter at Kothaupakali Material collected for CD works

Road from Uppu Canal drain to Cyclone shelter at Nali jungle clearance is in progress Road from Nali R & B Road to Barrankula Cyclone shelter Road from R&B road to Bhavadevarapalli Road from R&B road to cyclone shelter at Pedapalem Road from Gullalamoda R&B road to Etimoga Road from R&B to cyclone shelter at China Etimoga Road from R & B Road to Cyclone Shelter at China Kammavaripalem Road from kammavanicheruvu R&B road to Venkata durgambapuram in Bandar Mandal Road from R&B Road Pedayadara to Harijanawada Scarifying work completed from KM 0/0 to 2/0, Road formation with carting earth completed from KM 0/0 to 2/0. jungle clearance is in progress

11 12 13 14 15 16 21 22

Y2-199 Y2-200 Y2-201 Y2-202 Y2-203 Y2-204 Y2-211 Y2-212

RCS RCS RCS RCS RCS RCS RCS RCS

3 1 1 1 2 1 2 2

jungle clearance is in progress ,Scarifying is in progress Material collected for CD works


RCC slab in KM 0/0 is completed, Road formation with carting earth completed

jungle clearance work is in progress


GSB completed,WMM 1 st layer completed Material collected for CD works, Road formation with carting earth completed 600mm dia pipe culvert in Km0/8,1/10and 2/4 are completed, 450mm dia pipe culvert in KM2/4 is completed, GSB (HBG)layer completed ,WMM completed. GSB work is in progress from 0/00 to 0/660, Slab culvert is in progress in KM 2/4 CD works (900mm dia pipe culverts in KM 0/4 is completed, 600mm dia pipe culverts in KM 0/6,0/8,1/2,1/4 and 1/6 is completed. jungle clearance work is in progress jungle clearance work is in progress

27

Y2-328

RHB

Road from R&B Road to Narsimhapuram

28

Y2-329

RHB

Road from R&B Road to Krishnapuram

29

Y2-330

RHB

Road from R&B road to Pedagudumotu

30 31

Y2-335 Y2-336

RHB RHB

Road from R&B Road to Parra chivara Road from R&B road to Pedagowdapalem

3 3

Page 78 of 130

Name of the District: KRISHNA


Sl. No 32 33 34 35 36 37 41 44 46 47 48 49 Project catagory Code Y2-337 Y2-338 Y2-343 Y2-344 Y2-345 Y2-346 Y2-350 Y2-353 Y2-366 Y2-367 Y2-368 Y2-369 RHB RHB RHB RHB RHB RHB RHB RHB RHB RHB RHB RHB Name of work visited Road from R & B Road to Mulapalem Village Road from Ganapeswaram R&B Road to Pullaiahgaridibba Road from R & B Road to Indiramma Tank Construction of road from ST colony to Uppu drain in Dindi. Road from Z.P.road to Sorlagondi Road from R & B road to MPUP School Sangameswaram Road from R&B Road to Boligondi 'Road from B.L road to Matlam Road from Gokavaram R & B road to Vodarevupalem Work stage jungle clearance work is in progress Earth work completed from KM 0/0 to KM 1/140. jungle clearance work is in progress jungle clearance work is in progress jungle clearance work is in progress jungle clearance work is in progress CD works completed &.road widening is in progress Sub grade work is in progress Date of visit 17.07.13 31.07.13 17.07.13 22.07.13 31.07.13 29.07.13 29.07.13 29.07.13 31.07.13 29.07.13 31.07.13 26.07.13 20.07.13 25.07.13 25.07.13 25.07.13 25.07.13 Total visits 2 3 1 1 2 2 1 1 1 1 1 1

jungle clearance completed & road widening is in progress Road from Gokavaram R & B road to Badugovanipalem jungle clearance completed & road widening is in progress
Road from R&B Road Thallapalem to Rayapalli Road from Manganepudi R & B Road to Pathareddypalem

jungle clearance completed & road widening is in progress jungle clearance completed & road widening is in progress

Page 79 of 130

TPQA (CIVIL ENGG) SITE INSPECTIONS DURING THE MONTH OF JULY-2013 Name of the District: GUNTUR
Sl. Project catago No Code ry 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 Y2-453 BRIDGE Y2-225 Y2-227 Y2-379 Y2-379 RCS RCS RHB RHB Name of work visited Construction of HLB across Pedapalli No-2 Drain @km 14/6 of Chandolu bridge to Nizampatnam road Road from R&B Krosurivariplam road to Markavaripalem Road from R & B road to Pattapupalem Road from R&B road to Gattuvaripalem Road from R&B road to Gattuvaripalem Work stage Earth work is in progress GSB in progress Earth work is in progress
Earth work is in progress Earth work is in progress

Date of visit 02.07.13 02.07.13 02.07.13 02.07.13 05.07.13 06.07.13 06.07.13 08.07.13 08.07.13 08.07.13 20.07.13 20.07.13 22.07.13 22.07.13 26.07.13 26.07.13 29.07.13 29.07.13 29.07.13 29.07.13

Total visits 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1

Construction of HLB across Pedapalli No-2 Drain @km Y2-453 BRIDGE 14/6 of Chandolu bridge to Nizampatnam road Y2-225 Y2-225 Y2-379 RCS RCS RHB Road from R&B Krosurivariplam road to Markavaripalem Road from R&B Krosurivariplam road to Markavaripalem Road from R&B road to Gattuvaripalem

Earth work is in progress GSB in progress GSB in progress


Earth work is in progress

Construction of HLB across Pedapalli No-2 Drain @km 14/6 of Chandolu bridge to Nizampatnam road Construction of HLB across Pedapalli No-2 Drain @km Y2-453 BRIDGE 14/6 of Chandolu bridge to Nizampatnam road Y2-453 BRIDGE Y2-225 Y2-379 RCS RHB Road from R&B Krosurivariplam road to Markavaripalem Road from R&B road to Gattuvaripalem Construction of HLB across Pedapalli No-2 Drain @km Y2-453 BRIDGE 14/6 of Chandolu bridge to Nizampatnam road Y2-379 RHB Road from R&B road to Gattuvaripalem Construction of HLB across Pedapalli No-2 Drain @km Y2-453 BRIDGE 14/6 of Chandolu bridge to Nizampatnam road Y2-379 RHB Road from R&B road to Gattuvaripalem Construction of HLB across Pedapalli No-2 Drain @km Y2-453 BRIDGE 14/6 of Chandolu bridge to Nizampatnam road Y2-225 Y2-227 RCS RCS Road from R&B Krosurivariplam road to Markavaripalem Road from R & B road to Pattapupalem

Earth work is in progress Earth work is in progress GSB in progress


Earth work is in progress

Earth work is in progress


Earth work is in progress

Earth work is in progress


Earth work is in progress

Earth work is in progress GSB in progress Earth work is in progress

Page 80 of 130

TPTPQA (CIVIL ENGG) SITE INSPECTIONS DURING THE MONTH OF JULY-2013 Name of the District: PRAKASAM
Sl. No Project catago Code ry Name of work visited Work stage GSB Completed, WBM Gr-II Completed, CC Completed, WBM Grade-III completed. OGPC +SC Layer to be done. GSB Completed, WBM Grade-II Completed, WBM Grade-III Progress . Date of visit 02.07.2013 04.07.2013 13.07.2013 30.07.2013 02.07.2013 15.07.2013 17.07.2013 02.07.2013 04.07.2013 13.07.2013 02.07.2013 04.07.2013 13.07.2013 05.07.2013 05.07.2013 18.07.2013 25.07.2013 05.07.2013 05.07.2013 02.07.2013 15.07.2013 17.07.2013 02.07.2013 15.07.2013 24.07.2013 02.07.2013 15.07.2013 24.07.2013 02.07.2013 24.07.2013 02.07.2013 15.07.2013 24.07.2013 02.07.2013 24.07.2013 06.07.2013 17.07.2013 26.07.2013 06.07.2013 17.07.2013 26.07.2013 06.07.2013 17.07.2013 26.07.2013 29.07.2013 05.07.2013 13.07.2013 18.07.2013 05.07.2013 18.07.2013 01.07.2013 17.07.2013 20.07.2013 01.07.2013 17.07.2013 20.07.2013 01.07.2013 17.07.2013 20.07.2013 06.07.2013 26.07.2013 26.07.2013 26.07.2013 02.07.2013 04.07.2013 13.07.2013 15.07.2013 17.07.2013 24.07.2013 30.07.2013 Total visits

Y2-410

RHB

KEM R&B road to Pinnivaripalem

2 3 4 5

Y2-409 Y2-413 Y2-411 Y2-403

RHB RHB RHB RHB

KEM R&B road to Vajjireddypalem KEM R&B road to Chenchupapayapalem

3 3 3 1

Y2-414

RHB

7 8 9 10 11 12 13 14 15 16

Y2-239 Y2-238 Y2-397 Y2-399 Y2-398 Y2-401 Y2-402 Y2-400 Y2-229 Y2-389

RCS RCS RHB RHB RHB RHB RHB RHB RCS RHB

GSB Completed, WBM Gr-II Completed, CC Completed, WBM Grade-III completed. OGPC +SC Layer to be done. GSB Completed, WBM Gr-II Completed, CC Salt road Madnur ZP road to Chinnapattupalem Completed, WBM Grade-III completed. OGPC +SC Layer to be done. Road from Tangutur to Tallapalem (via) velagapudi Retaining Wall 145m Completed. Earth work (km 4/5 to 7/465) widening Completed & GSB Completed 1) Earth work widening completed 2) 13 no's Culverts completed Road from M.C Road to West S.T Colony of Verepalli 3) Retaining wall completed 4) GSB Completed , WBM Grade-II Progress 5) Side drains work completed. Road form Z.P Road to pallepalem of Chakicherla Eatrh work in progress 1)GSB & C.C Work completed Road from Z.P Road to Sriramapattapupalem 2) Shoulders to be done. KEM R&B road to Chinnapattupalem Salt road from Madnur Z.P road to Swarnandhrapattapupalem Salt road from Madnur Z.P road to Peddapattupalem Salt road from Madnur Z.P road to Namburi yanadi colony Salt road from Madnur Z.P road to Thotagunta yanadi colony Salt road from Madnur Z.P road to Bapuji yanadi colony Road from Chinaganjam Railway station to Bapaiah nagar Road from R&B Road to Kothapalem GSB Completed, WBM Grade-II Completed, WBM Grade-III Progress & C.C Completed. GSB Completed, CC completed, WBM Grade-II completed & WBM Grade-III Progress. GSB Completed, CC completed, WBM Grade-II completed & WBM Grade-III Progress. GSB Completed & WBM Grade-II completed, C.C Completed & WBM Grade-III Progress. GSB Completed, C.C Work completed , WBM Grade-II Completed. GSB Completed, CC completed & Shoulders to be done. Eatrh work in progress GSB Completed, C.C Work completed , WBM Grade-II Completed. GSB Completed, CC Work in progress

1 1 3 3 3 2 3 2 3 3

17

Y2-387

RHB

Road from R&B Road to Pulavaripalem

18 19 20 21 22 23 24 25 26

Y2-404 Y2-233 Y2-405 Y2-406 Y2-407 Y2-230 Y2-390 Y2-391 Y2-392

RHB RCS RHB RHB RHB RCS RHB RHB RHB

Road from Tangutur-Ravivaripalem road @1/2 km to Earthwork Widening in Progress , Sub grade Pasukuduru (Quary waste ) completed. Road from Pakala PR Road to Chellammagaripattapupalem CS Road from Kanuparthy to Kukkalavaripalem Road from Kanuparthy to Yanadi Sangam Road from Kanuparthy to MS Pattapupalem Road from Motupalli R&B Road to Nirikshanagiri (via) Rudramambapuram CS in Motupalli G.P. Road from Motupalli R & B Road to Krishna Nagar Road from R & B Road to Yanadi Sangam Road from Jeedichetlapalem R&B road to Kunkuduchetlapalem 1) GSB Work completed. 2) C.C Work progress. 3) WBM Grade-II, Spreading in progress. Earthwork widening completed Earthwork widening completed Earthwork widening completed GSB in progress GSB in progress Eatrh work in progress Eatrh work in progress

3 2 3 3 3 1 1 1 1

27

Y2-455 BRIDGE

Reconstruction of high level bridge at km 11/10 of ongole kothapatnam road in prakasam district

Well curb work is in progress.

Page 81 of 130

TPQA (CIVIL ENGG) SITE INSPECTIONS DURING THE MONTH OF JULY-2013 Name of the District: SPSR NELLORE
Sl. No 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 Project catag Code ory Y2-436 Y2-254 Y2-252 Y2-436 Y2-254 Y2-252 Y2-254 Y2-433 Y2-420 Y2-422 Y2-256 Y2-254 Y2-433 Y2-420 Y2-422 Y2-256 Y2-257 Y2-257 Y2-426 Y2-432 Y2-248 Name of work visited Work stage Date of visit 02.07.2013 02.07.2013 02.07.2013 02.07.2013 02.07.2013 02.07.2013 03.07.2013 03.07.2013 03.07.2013 03.07.2013 03.07.2013 03.07.2013 03.07.2013 03.07.2013 03.07.2013 03.07.2013 04.07.2013 04.07.2013 10.07.2013 10.07.2013 10.07.2013 Total visits 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1

Road from R&B road Kothapatnam to RHB Yamadinnepalem (via) Srinivasasatram in Nellore District Road from R&B Road to Doruvukatta road (via) RCS Allmpadu, Deyyaladibba in Nellore District Road from R&B Road Lingavaram to RCS Narravaripalemin Nellore District Road from R&B road Kothapatnam to RHB Yamadinnepalem (via) Srinivasasatram in Nellore District Road from R&B Road to Doruvukatta road (via) RCS Allmpadu, Deyyaladibba in Nellore District Road from R&B Road Lingavaram to RCS Narravaripalemin Nellore District RCS RHB RHB RHB RCS RCS RHB RHB RHB RCS Road from R&B Road to Doruvukatta road (via) Allmpadu, Deyyaladibba in Nellore District.

GSB completed BT completed GSB progress GSB completed BT completed GSB progress BT completed

Road from Mypadu R&B Road to Kollimittapalem GSB completed,WMM is in in Nellore District. progress Salt Road from Iskapalli to Salt fields at Kotha Kurrupattapupalem in Nellore District. Road from R&B Road to Zuvvagu in Nellore District. GSB completed,WMM progress GSB completed,WMM progress

Road from C.S. Puram to Edurupalem in Nellore GSB progress District. Road from R&B Road to Doruvukatta road (via) Allmpadu, Deyyaladibba in Nellore District. BT completed

Road from Mypadu R&B Road to Kollimittapalem GSB completed,WMM is in in Nellore District. progress Salt Road from Iskapalli to Salt fields at Kotha Kurrupattapupalem in Nellore District. Road from R&B Road to Zuvvagu in Nellore District. GSB completed,WMM progress GSB completed,WMM progress

Road from C.S. Puram to Edurupalem in Nellore GSB progress District. Road from Mahlakshmi puram to Sagara RCS Sangamam (via) Muthyalathopu Pattapupalem B.T.completed in Nellore Road fromDistrict Mahlakshmi puram to Sagara RCS Sangamam (via) Muthyalathopu Pattapupalem B.T.completed RHB RHB RCS in Nellore Road fromDistrict R&B road to Venkata reddy palem in Eath work in progress Nellore District. Road from Ponnapudi R & B road to Ponnapudi CC pavement completd in Nellore District. Road Ponnapudi R&B Road to Ramachendrapuram in Nellore District. GSB completed

Page 82 of 130

Name of the District: SPSR NELLORE


Sl. No 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 Project catag Code ory Y2-431 Y2-430 Y2-433 Y2-429 Y2-426 Y2-432 Y2-248 Y2-431 Y2-430 Y2-433 Y2-429 Y2-240 Y2-240 Y2-430 Y2-431 Y2-428 Y2-429 Y2-250 Y2-425 Y2-427 Y2-430 Y2-431 Y2-428 Y2-429 Y2-250 RHB RHB RHB Name of work visited Ponnapudi R & B road to Venkata narayana puram in Nellore District. Road from Ponnapudi Utukur R&B road to Prasanthigiri colony in Nellore District. Work stage GSB Completed,WMM in progress GSB completed,WMM in progress Date of visit 10.07.2013 10.07.2013 10.07.2013 10.07.2013 10.07.2013 10.07.2013 10.07.2013 10.07.2013 10.07.2013 10.07.2013 10.07.2013 12.07.2013 12.07.2013 16.07.2013 16.07.2013 16.07.2013 16.07.2013 16.07.2013 16.07.2013 16.07.2013 16.07.2013 16.07.2013 16.07.2013 16.07.2013 16.07.2013 Total visits 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1

Road from Mypadu R&B Road to Kollimittapalem GSB completed,WMM is in in Nellore District. progress GSB Completed. Road from R&B road to Venkata reddy palem in Eath work in progress Nellore District. Road from Ponnapudi R & B road to Ponnapudi CC pavement completd in Nellore District. Road Ponnapudi R&B Road to Ramachendrapuram in Nellore District. Ponnapudi R & B road to Venkata narayana puram in Nellore District. Road from Ponnapudi Utukur R&B road to Prasanthigiri colony in Nellore District. GSB completed GSB Completed,WMM in progress GSB completed,WMM in progress

RHB Ponnapudi Utukur R&B road To Kothuru RHB RHB RCS RHB RHB RHB

Road from Mypadu R&B Road to Kollimittapalem GSB completed,WMM is in in Nellore District. progress GSB Completed. WBM Gr-II progress WBM Gr-II progress GSB completed,WMM in progress GSB Completed,WMM in progress Road from @ Km 65/4 of C K Road to Tada Kuppam Cyclone Shelter in Nellore District Road from @ Km 65/4 of C K Road to Tada Kuppam Cyclone Shelter in Nellore District Road from Ponnapudi Utukur R&B road to Prasanthigiri colony in Nellore District Ponnapudi R & B road to Venkata narayana puram in Nellore District

RHB Ponnapudi Utukur R&B road To Kothuru RCS RCS RHB RHB RHB RHB RCS RHB

Road from Ponnapudi Utukur Road to sub grade is in progress Srigowripuram in Vidavalur Mandal of Nellore dt Road from Ponnapudi Utukur R&B road to Kothuru in Vidavalur Mandal of Nellore district Road from Ponnapudi R&B Road to Lakshimipuram in Nellore District. Ponnapudi-Utukurroad To Pattapupalem. Road from Ponnapudi Utukur R&B road to Prasanthigiri colony in Nellore District Ponnapudi R & B road to Venkata narayana puram in Nellore District GSB Completed. sub grade completed. CC road in progress Eath work in progress sub grade is in progress GSB completed,WMM in progress GSB Completed,WMM in progress

RHB Ponnapudi R&B Road To Anjaneyapuram. RHB RHB RHB RHB RCS

Road from Ponnapudi Utukur Road to sub grade is in progress Srigowripuram in Vidavalur Mandal of Nellore dt Road from Ponnapudi Utukur R&B road to Kothuru in Vidavalur Mandal of Nellore district. Road from Ponnapudi R&B Road to Lakshimipuram in Nellore District. GSB Completed. sub grade completed. CC road in progress

Page 83 of 130

Name of the District: SPSR NELLORE


Sl. No 47 48 49 50 51 52 53 54 55 56 57 58 59 60 61 62 63 64 65 66 67 68 69 70 71 72 73 Project catag Code ory Y2-425 Y2-427 Y2-433 Y2-245 Y2-433 Y2-245 Y2-420 Y2-422 Y2-421 Y2-419 Y2-242 Y2-420 Y2-422 Y2-421 Y2-419 Y2-242 Y2-431 Y2-249 Y2-247 Y2-425 Y2-427 Y2-431 Y2-249 Y2-247 Y2-425 Y2-427 Y2-420 Name of work visited Work stage Eath work in progress sub grade is in progress Date of visit 16.07.2013 16.07.2013 17.07.2013 17.07.2013 17.07.2013 17.07.2013 22.07.2013 22.07.2013 22.07.2013 22.07.2013 22.07.2013 22.07.2013 22.07.2013 22.07.2013 22.07.2013 22.07.2013 23.07.2013 23.07.2013 23.07.2013 23.07.2013 23.07.2013 23.07.2013 23.07.2013 23.07.2013 23.07.2013 23.07.2013 25.07.2013 Total visits 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1

RHB Ponnapudi-Utukurroad To Pattapupalem. RHB Ponnapudi R&B Road To Anjaneyapuram. RHB RCS RHB RCS RHB

Road from Mypadu R&B Road to Kollimittapalem GSB completed,WMM is in in Nellore District progress Road from Korutur to Pattapupalem in Ipet Mandal in Nellore district, CD works complete Gsb progress,

Road from Mypadu R&B Road to Kollimittapalem GSB completed,WMM is in in Nellore District progress Road from Korutur to Pattapupalem in Ipet Mandal in Nellore district, Salt Road from Iskapalli to Salt fields at Kotha Kurrupattapupalem in Nellore District. CD works complete Gsb progress, GSB completed,WMM progress GSB completed,WMM progress

RHB Road from R&B Road to Zuvvagu in Nellore Dt. RHB RHB

Road from R&B road to Zuvvagu Lakshmipuram GSB progress in Nellore District. Road from R.I Road to C.R. Palem (via) Sambhunipalem in Nellore District Salt Road from Iskapalli to Salt fields at Kotha Kurrupattapupalem in Nellore District. Vented road dam is progress CC pavement is progress GSB completed,WMM progress GSB completed,WMM progress

RCS Approach road to Labbipalem in Nellore Dt. RHB

RHB Road from R&B Road to Zuvvagu in Nellore Dt. RHB RHB

Road from R&B road to Zuvvagu Lakshmipuram GSB progress in Nellore District. Road from R.I Road to C.R. Palem (via) Sambhunipalem in Nellore District Ponnapudi R & B road to Venkata narayana puram in Nellore District Ponnapudi R&B road to Busagadipalem in Nellore Distric Vented road dam is progress CC pavement is progress GSB Completed,WMM in progress GSB progress GSB is progress Eath work in progress sub grade is in progress GSB Completed,WMM in progress GSB progress GSB is progress Eath work in progress sub grade is in progress GSB completed,WMM progress

RCS Approach road to Labbipalem in Nellore Dt. RHB RCS

RCS Road from R&B road to Utukur - Pallipalem RHB Ponnapudi-Utukurroad To Pattapupalem RHB Ponnapudi R&B Road To Anjaneyapuram RHB RCS Ponnapudi R & B road to Venkata narayana puram in Nellore District Ponnapudi R&B road to Busagadipalem in Nellore Distric

RCS Road from R&B road to Utukur - Pallipalem RHB Ponnapudi-Utukurroad To Pattapupalem RHB Ponnapudi R&B Road To Anjaneyapuram RHB Salt Road from Iskapalli to Salt fields at Kotha Kurrupattapupalem in Nellore District.

Page 84 of 130

Name of the District: SPSR NELLORE


Sl. No 74 75 76 77 78 79 80 81 82 83 84 85 86 87 88 89 90 91 92 93 94 Project catag Code ory Y2-422 Y2-424 Y2-246 Y2-436 Y2-426 Y2-430 Y2-421 Y2-250 Y2-420 Y2-422 Y2-424 Y2-246 Y2-436 Y2-426 Y2-430 Y2-421 Y2-250 Y2-244 Y2-434 Y2-244 Y2-434 Name of work visited Work stage GSB completed,WMM progress Date of visit 25.07.2013 25.07.2013 25.07.2013 25.07.2013 25.07.2013 25.07.2013 25.07.2013 25.07.2013 25.07.2013 25.07.2013 25.07.2013 25.07.2013 25.07.2013 25.07.2013 25.07.2013 25.07.2013 25.07.2013 30.07.2013 30.07.2013 30.07.2013 30.07.2013 Total visits 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1

RHB Road from R&B Road to Zuvvagu in Nellore Dt. RHB RCS

Road from Pedapattapupalem to Nandempuram Gsb completed,WMM in Nellore District. progress Road from 230/6 Km of M.C Raod to Pedapattapupalem in Nellore District. GSB completed.

Road from R&B road Kothapatnam to RHB Yamadinnepalem (via) Srinivasasatram in GSB completed Nellore District Road from R&B road to Venkata reddy palem in RHB Eath work in progress Nellore District. RHB RHB RCS RHB RHB RHB RCS Road from Ponnapudi Utukur R&B road to Prasanthigiri colony in Nellore District. GSB completed,WMM in progress

Road from R&B road to Zuvvagu Lakshmipuram GSB progress in Nellore District. Road from Ponnapudi R&B Road to Lakshimipuram in Nellore District Salt Road from Iskapalli to Salt fields at Kotha Kurrupattapupalem in Nellore District. Road from R&B Road to Zuvvagu in Nellore District. sub grade completed. CC road in progress GSB completed,WMM progress GSB completed,WMM progress

Road from Pedapattapupalem to Nandempuram Gsb completed,WMM in Nellore District progress Road from 230/6 Km of M.C Raod to Pedapattapupalem in Nellore District GSB completed. GSB completed

Road from R&B road Kothapatnam to RHB Yamadinnepalem (via) Srinivasasatram in Nellore District RHB RHB RHB RCS

Road from R&B road to Venkata reddy palem in Eath work in progress Nellore District. Road from Ponnapudi Utukur R&B road to Prasanthigiri colony in Nellore District. GSB completed,WMM in progress

Road from R&B road to Zuvvagu Lakshmipuram GSB progress in Nellore District. sub grade completed. CC road in progress GSB is progress

Road from Ponnapudi R&B Road to Lakshimipuram in Nellore District Road from Ramudupalem on R&B road to RCS Pallipalem

Road from Nellore Mypadu R&B Road to West RHB Pattapupalem in Nellore District GSB is in progress Road from Ramudupalem on R&B road to RCS Pallipalem RHB GSB is progress

Road from Nellore Mypadu R&B Road to West GSB is in progress Pattapupalem in Nellore District

Page 85 of 130

NCRMP WORKS - ABSTRACT OF TPQA (SOCIAL & ENV) INSPECTION STATUS UP TO JULY 2013 PR
MPCS Cummulative During this Month Up to last month Sl. No. District Works RCS Cummulative During this Month Up to last month RHB Cummulative During this Month Up to last month R&B BRIDGES Cummulative During this Month Up to last month I & CADD Total Visits SALINE EMBANKMENTS Cummulative During this Month Up to last month

Works

Works

Works

Works

1 Srikakulam 2 Vizianagaram 3 Visakhapatnam 4 East Godavari 5 West Godavari 6 Krishna 7 Guntur 8 Prakasam 9 Nellore Total

22 1 1 5 0 0 2 0 0 31

0 0 0 0 0 0 0 0 0 0

14 0 0 0 0 0 0 0 0 14

14 0 0 0 0 0 0 0 0 14

11 5 4 9 9 26 3 11 18 96

0 0 4 0 0 0 0 2 12 18

5 0 0 0 0 0 0 0 0 5

5 0 4 0 0 0 0 2 12 23

10 0 5 8 24 23 1 23 19 113

0 0 5 0 0 0 0 16 12 33

4 0 0 0 0 0 0 0 0 4

4 0 5 0 0 0 0 16 12 37

0 0 0 2 0 0 1 1 0 4

0 0 0 0 0 0 0 0 0 0

0 0 0 0 0 0 0 0 0 0

0 0 0 0 0 0 0 0 0 0

0 0 0 0 0 2 0 0 0 2

0 0 0 0 0 0 0 0 0 0

0 0 0 0 0 1 0 0 0 1

0 0 0 0 0 1 0 0 0 1

23 0 9 0 0 1 0 18 24 75

Page 86 of 130

TPQA SITE INSPECTIONS DURING THE MONTH OF JULY, 2013.


Sl. No 1 2 Dist Category rict MPCS MPCS Project Code Y-2-001 Y-2-030 Name of work visited Construction of CS at Kollipadu Construction of CS at Akkuvaram Work stage Final stage Earth work in progress Date of visit 05.07.2013 05.07.2013 Total visits 1 1 Observations / Remarks Barricading shall be provided to the worksite. NCR already given by the concerned TPQA site engineer. Barricading shall be provided to the worksite. 1. The Social and Environmental Model plan is given to the line department and explanation was also given on various items in the plan.The line department is now helping the contractor to prepare the plan. Within few days the plan will be submitted by the contractor. 2. NCR issued for not obtaining permission to use water from local source. 1. The Social and Environmental Model plan is given to the line department and explanation was also given on various items in the plan.The line department is now helping the contractor to prepare the plan. Within few days the plan will be submitted by the contractor. 2. No caution boards are provided near the culverts under construction. Suggested the line department to take necessary action. 3. Caution boards shall be provided at the " S " curves in the entire stretch of the road. The Social and Environmental Model plan is given to the line department and explanation was also given on various items in the plan.The line department is now helping the contractor to prepare the plan. Within few days the plan will be submitted by the contractor. The Worksite is not cleared. Trees are there in the site. The line department take immediate action to clear the site. Barricading shall be provided to protect the the worksite. Housekeeping shall be maintained properly. Barricading shall be provided to the worksite Rain Gullies are there on the shoulder in the entire strethch of the road. Necessary action shall be taken to avoid accidents.

RCS

Y-2-257

Road from R&B Road to Akkuvaram

GSM stage

05.07.2013

Srikakulam

RHB

Y-2-273

DPN road to D.L.Puram Jn via Sub grade stage Koduru, Magathapadu, Guppidipeta

05.07.2013

RHB

Y-2-274

Guppidipeta road to chinnakoviripeta

Sub grade stage

05.07.2013

6 7 8 9

MPCS MPCS MPCS RCS

Y-2-036 Y-2-010 Y-2-029 Y-2-148

Construction of CS Jungle clearance in Bonthalakoduru is in Proogress Construction of Bypalli Earth work CS completed Construction of PCC Completed Bandravanipeta CS Road from Kothapeta Road Widening is Road to Sainooru CS in progress

05.07.2013 05.07.2013 05.07.2013 06.07.2013

1 1 1 1

Page 87 of 130

TPQA SITE INSPECTIONS DURING THE MONTH OF JULY, 2013.


Sl. No Dist Category rict Project Code Name of work visited Work stage Date of visit Total visits Observations / Remarks

10

RHB

Y-2-270

Road from DPN Road Road Widening is to Gangaram village in progress and via palatalagamm bridge earth work srikrishnapuram is in progress Road from R&B Road to Marripadu. Road from R&B Road to S.J Puram Road widening is in progress GSB layer completed

06.07.2013

Land acquistion problem was resolved with the cooperation of Villagers.

11 12 13 Srikakulam

RHB RCS RCS

Y-2-266 Y-2-147 Y-2-145

06.07.2013 06.07.2013 07.07.2013

1 1 1

Land acquisiton problem for 100 mts is resolved by the consultations with the villagers by the TPQA consultant at Km 0/0. The three eletrical poles in obstruction shall be shifted from the shoulders to avoid accidents in Km 0.3 . Necessary action shall be taken for the temple and tap in obstruction on the shoulder on RHS of the road in Km 0.1. 1.The electrical lines are lying low and the height shall be raised to avoid accidents on the shoulder on LHS of the road from Km 0.800 to Km 0.900. Barricading shall be provided to protect the trees around the worksite. The compound wall of the school and the coconut tree adjascent to the CS shall be removed for constrcution of CS. Barricading shall be provided to the worksite. Barricading shall be provided to the worksite. Barricading shall be provided to the worksite. Barricading shall be provided to the worksite. Barricading shall be provided to the worksite.

Road from Chinavanka Road widening is to Gopaladavooru in progress Road from R& B road to Pathadibbapalem Construction of Chinavaka CS Construction of Chinnakothuru CS Construction of Jaganathapuram CS Construction of Kalingapatnam CS Construction of Kommaravanipeta CS Construction of Kothamukkam CS Road widening is in progress Earth work completed Earth work completed Jungle clearance is in Progress PCC Completed Jungle clearance is in Progress Jungle clearance is in Progress

14 15 16 17 18 19 20

RCS MPCS MPCS MPCS MPCS MPCS MPCS

Y-2-158 Y-2-011 Y-2-012 Y-2-031 Y-2-028 Y-2-018 Y-2-032

07.07.2013 08.07.2013 08.07.2013 08.07.2013 08.07.2013 08.07.2013 08.07.2013

1 1 1 1 1 1 1

Page 88 of 130

TPQA SITE INSPECTIONS DURING THE MONTH OF JULY, 2013.


Sl. No 21 MPCS Srikakulam Y-2-025 Dist Category rict Project Code Name of work visited Construction of Metturu CS Work stage Date of visit Total visits Observations / Remarks 3 temples adjascent to the worksite shall be protected. PCC Completed 08.07.2013 1 Barricading shall be provided to protect the the worksite. Housekeeping shall be maintained properly. Barricading shall be provided to the worksite. Barricading shall be provided to the worksite. Caution board is required at the worksite. 2 electric poles are in obstruction shall be shifted to avoid accidents in km 0.300 No Issues identified till date No Issues identified till date No Issues identified till date No Issues identified till date No Issues identified till date 22 electric poles are in obstrcution. Water supply pipes are there at the length of 70.2 mts. No Issues identified till date

22 23 24 25 26 27 28 29 30 31

MPCS MPCS RCS RCS RCS RCS

Y-2-037 Y-2-027 Y-2-189 Y-2-192 Y-2-194 Y-2-202 Y-2-199 Y-2-328 Y-2-350 Y-2-353

RCS RHB RHB RHB

Construction of Earth work in Pathadibbapalem CS progress Construction of Jungle clearance Reddica Sunnapalli CS is in Progress Road from R &B road W/M First layer to CS at Ullipalem completed Road from R&B road GSM stage to Ramakrishnapuram Road from R&B to CS Earth work in Padalavaripalem progress Road from Slab culvert Gullalamoda R& B to completed. Etimoga Road from Nali R&B Scarifying work road to Barrankula CS completed Road from R&B road W/M Second to Narsimhapuram layer completed Road from R &B road Earth work in to Bolugondi progress Road from B.L.Road to Sub-grade stage Matlam completed

08.07.2013 08.07.2013 27.07.2013 27.07.2013 27.07.2013 27.07.2013 27.07.2013 27.07.2013 27.07.2013 27.07.2013

1 1 1 1 1 1 1 1 1 1

Krishna

Page 89 of 130

NCRMP Works - Abstract of TPQA (Electrical Engineer) Inspection Status up to July 2013 PR
Sl. No. District Works Up to last month MPCS During this Month Cummulative

1 2 3 4 5 6 7 8 9

Srikakulam Vizianagaram Visakhapatnam East Godavari West Godavari Krishna Guntur Prakasam Nellore Total

22 1 1 5 0 0 2 0 0 31 9 9 6 3 6 3 0 12 6 0 0 0 0 0 18

Page 90 of 130

TPQA SITE (ELECTRICAL) INSPECTIONS DURING THE MONTH OF JULY 2013


Sl. No District Project Code Name of work visited Work stage Date of visit Remarks if any

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16

Visakhapatnam Visakhapatnam Visakhapatnam Visakhapatnam Visakhapatnam East Godavari East Godavari East Godavari Visakhapatnam Visakhapatnam Visakhapatnam Visakhapatnam Visakhapatnam Visakhapatnam Srikakulam Srikakulam

Y2-043 Y2-044 Y2-045 Y2-046 Y2-047 Y2-060 Y2-061 Y2-062 Y2-043 Y2-044 Y2-045 Y2-046 Y2-047 Y2-048 Y2-001 Y2-002

Construction of MPCS at patimeda Construction of MPCS at Mullaparra Construction of MPCS at Bangaranpeta Construction of MPCS at Gajapathi Nagaram Construction of MPCS at Ratnayampeta Construction of MPCS at Avulamanda Construction of MPCS at Laxmanudipeta Construction of MPCS at Pedaraghavulupeta Construction of MPCS at patimeda Construction of MPCS at Mullaparra Construction of MPCS at Bangaranpeta Construction of MPCS at Gajapathi Nagaram Construction of MPCS at Ratnayampeta Construction of MPCS at Venkayyapalem Construction of MPCS at Kollipadu Construction of MPCS at Runku

Finishing stage Finishing stage Finishing stage Finishing stage Finishing stage Finishing stage Finishing stage work in progress work completed work completed work completed work completed work completed work in progress work in progress work in progress

3/7/2013 3/7/2013 3/7/2013 3/7/2013 3/7/2013 4/7/2013 4/7/2013 5/7/2013 18/7/2013 18/7/2013 18/7/2013 18/7/2013 18/7/2013 18/7/2013 19/7/2013 19/7/2013 Report submitted Report submitted Report submitted Report submitted Report submitted

Page 91 of 130

Annexure - E
Surprise Visits by TPQA

Page 92 of 130

Abstract details of Surprise Inspections carried out by TPQA Consultant up to end of July 2013 Sl. No. 1 2 3 4 5 6 7 8 9 Surprise visits District
Up to Last month During this Month Cummulative

Srikakulam Vizianagaram Visakhapatnam East Godavari West Godavari Krishna Guntur Prakasam Nellore Total

14 3 16 3 6 15 9 19 22 107

10 4 6 3 5 30 3 27 12 100

24 7 22 6 11 45 12 46 34 207

Page 93 of 130

Annexure - F
Audit Reports submitted by TPQA Consultant

Page 94 of 130

QCRs submitted in the month of July-2013


Package Number NCRMP/BW/AP/RHB/PRED/ 01/Polaki/007 NCRMP/B-W/AP/MPCS/PRED/ 01/Gara/015 NCRMP/BW/AP/RHB/PRED/ 01/Santhabommali/001B NCRMP/B-W/AP/RCS/PRED/ 02/Bhogapuram/001 NCRMP/B-W/AP/RCS/PRED/ 02/Bhogapuram/001 NCRMP/B-W/AP/RCS/PRED/ 02/Bhogapuram/001 NCRMP/B-W/AP/MPCS/PRED/ 02/Pusapatirega/003 NCRMP/B-W/AP/RHB/PRED/ 03/Payakaraopeta/005 NCRMP/B-W/AP/RHB/PRED/ 03/Payakaraopeta/008 NCRMP/B-W/AP/RHB/PRED/ 05/Narsapur/012 NCRMP/B-W/AP/RHB/PRED/ 05/Narsapur/012 NCRMP/B-W/AP/RHB/PRED/ 05/Narsapur/013 NCRMP/B-W/AP/RHB/PRED/ 05/Narsapur/013 NCRMP/B-W/AP/RHB/PRED/ 05/Mogaltur/008 NCRMP/B-W/AP/RHB/PRED/ 05/Mogaltur/008 NCRMP/B-W/AP/RCS/PRED/ 06/Machilipatnam/008 NCRMP/B-W/AP/RHB/PRED/ 08/Chinaganjam/012 NCRMP/B-W/AP/RHB/PRED/ 08/Kothapatnam/020 NCRMP/B-W/AP/RCS/PRED/ 08/Ulavapadu/009 NCRMP/B-W/AP/RHB/PRED/ 08/Tangutur/021 NCRMP/B-W/AP/RHB/PRED/ 08/Kothapatnam/019 NCRMP/B-W/AP/RHB/PRED/ 08/Kothapatnam/020 NCRMP/B-W/AP/RHB/PRED/ 08/Kothapatnam/020 Name of Work Road from Guppidipeta Road to Chinnakoviripeta in Polaki Mandal Construction of Cyclone Shelter at Calingapatnam in Gara Mandal Road from DPN road to Gangaram via Srikrishnapuram, Palatalagam in Santhabommali Mandal Road from R & B Road to B.V.Peta Cyclone Shelter in Pusapatirega Mandal Road from R&B Road to Chinapathiwada Cyclone Shelter in Pusapatirega Mandal Road from R&B Road to Roluchappidi Cyclone Shelter in Pusapatirega Mandal Construction of CS at Boddugurayyapeta Village in Pusapatirega Mandal Road from Rajala R&B road to Rajaraidupalem of Payakaraopeta Mandal Road from ZP Road Palmanpeta to Korlayyapeta in Payakaraopeta Mandal SP R&B road to Pedathota of Turputallu of Narsapur Mandal R&B Road to Pedathota of Turputallu in Narsapur Mandal R&B road to Guttulavarimeraka Road from R&B Road to Pedaedigapalem in Narsapur Mandal Road from Narsapur Perupalem R&B Road to Melamvaripalem Perupalem (S) in Mogaltur Mandal Road from Perupalem Mollaparru R&B road via Sattinenivarimeraka to K.D. Pallavapalem in Mogaltur Mandal Road from Kammavaricheruvu R&B Road to Venkatadurgambapuram in Machilipatnam Mandal Road from R&B Road to Kothapalem in Chinaganjam Mandal Salt Road from Madnur ZP Road to Thotagunta yanadi colony in Kothapatnam Mandal Road from ZP Road to Srirampattapupalem in Ulavapadu Mandal Road from Tangutur to Tallapalem via Velagapudi (Km 4/5 to 7/465) in Tangutur Mandal Road from KEM R&B Road to Vajjireddypalem in Kothapatnam Mandal Road from Madnur ZP Road to Swarnandhrapattapupalem in Kothapatnam Mandal, Road from KEM R & B road to Chinapattapupalem in Kothapatnam Mandal District Srikakulam Srikakulam Srikakulam Vizianagaram Vizianagaram Vizianagaram Vizianagaram Visakhapatnam Visakhapatnam West Godavari West Godavari West Godavari West Godavari West Godavari West Godavari Krishna Prakasam Prakasam Prakasam Prakasam Prakasam Prakasam Prakasam

Page 95 of 130

Package Number NCRMP/B-W/AP/RHB/PRED/ 08/Kothapatnam/020 NCRMP/B-W/AP/RCS/PRED/ 09/Allur/012 NCRMP/B-W/AP/RCS/PRED/ 09/Kota/016 NCRMP/BW/AP/RHB/PRED/ 09/I.Peta/027 NCRMP/B-W/AP/RCS/PRED/ 09/T.P.Gudur & Muthukur/019 NCRMP/B-W/AP/RCS/PRED/ 09/T.P.Gudur & Muthukur/019 NCRMP/BW/AP/RHB/PRED/ 09/Vidavalur/026 NCRMP/BW/AP/RHB/PRED/ 09/Kota/022 NCRMP/B-W/AP/RCS/PRED/ 09/Vidavalur/021 NCRMP/BW/AP/RHB/PRED/ 09/Vidavalur/026 NCRMP/BW/AP/RHB/PRED/ 09/Vidavalur/026

Name of Work Salt Road from Madnur ZP Road to Namburi Yanadi colony in Kothapatnam Mandal Approach Road to Labbipalem in Allur Mandal Road from R&B Road to Doruvuketta Road via Allampadu, Deyyaladibba of Kota Mandal Road from Mypadu R&B Road to Kollimittapalem in I.Peta Mandal Road from C.S Puram to Eduru Pattapupalem in T.P.Gudur Mandal Road from Mahlakshmi puram to Sagara Sangamam via Muthyalathopu Pattapupalem in T.P.Gudur Mandal Road from Ponnapudi Utukur R&B Road to Kothuru in Vidavalur Mandal Road from R&B road Kothapatnam to Yamadinnepalem (via) Srinivasasatram of Kota Mandal Road from Ponnapudi R&B Road to Lakshmipuram in Vidavalur Mandal Road from Ponnapudi R&B Road to Venkatanarayanapuram in Vidavalur Mandal Road from Ponnapudi- Utukur R&B Road to Prasanthagiri Colony in Vidavalur Mandal

District Prakasam SPSR Nellore SPSR Nellore SPSR Nellore SPSR Nellore SPSR Nellore SPSR Nellore SPSR Nellore SPSR Nellore SPSR Nellore SPSR Nellore

Page 96 of 130

Final QARs submitted in the month of July-2013


Package Number NCRMP/B-W/AP/RCS/PRED/ 07/Bapatla/004 NCRMP/B-W/AP/RCS/PRED/ 07/Bapatla/004 NCRMP/B-W/AP/RCS/PRED/ 07/Karlapalem/001 NCRMP/B-W/AP/RHB/PRED/ 08/S.Konda/002 NCRMP/B-W/AP/RHB/PRED/ 08/S.Konda/002 NCRMP/B-W/AP/RHB/PRED/ 08/S.Konda/002 NCRMP/B-W/AP/RHB/PRED/ 08/S.Konda/002 NCRMP/B-W/AP/RCS/PRED/ 09/Kavali/006 Name of Work Road from R&B Road to Hanumanthanagar in Bapatla Mandal Road from R&B Road to Adarshnagar in Bapatla Mandal Road from R&B Road to Kesavapuri ST Colony in Karlapalem Mandal Road from NH5 to Mulaguntapadu village in Singarayakonda Mandal Road from R&B Road to Chalivendradibba in Singarayakonda Mandal Road from Pakala R&B road to Mosanaladinne in Singarayakonda Mandal Road from R&B Road to Binginapalli Harijanawada Cyclone Shelter Road Connecting R&B Road through Votturu Village in Kavali Mandal District Guntur Guntur Guntur Prakasam Prakasam Prakasam Prakasam SPSR Nellore

Page 97 of 130

Env & Social QCRs submitted in the month of July-2013


Package Number NCRMP/B-W/AP/RCS/PRED/ 01/Polaki/018 NCRMP/B-W/AP/MPCS/PRED/ 01/Santhabommali /005 NCRMP/B-W/AP/RCS/PRED/ 01/Mandasa/010 NCRMP/B-W/AP/RCS/PRED/ 01/Polaki /007 NCRMP/B-W/AP/RCS/PRED/ 01/Polaki /007 NCRMP/B-W/AP/MPCS/PRED/ 01/Etcherla/017A NCRMP/B-W/AP/MPCS/PRED/ 01/V.Kothuru /004 NCRMP/B-W/AP/MPCS/PRED/ 01/Gara /015 NCRMP/B-W/AP/MPCS/PRED/ 01/V.Kothuru /004 NCRMP/B-W/AP/MPCS/PRED/ 01/V.Kothuru/004 NCRMP/B-W/AP/MPCS/PRED/ 01/Rangasthalam/016 NCRMP/B-W/AP/MPCS/PRED/ 01/AGara /015 NCRMP/B-W/AP/MPCS/PRED/ 01/Rangasthalam/008 NCRMP/B-W/AP/MPCS/PRED/ 01/Rangasthalam/016 NCRMP/B-W/AP/MPCS/PRED/ 01/V.Kothuru /013 NCRMP/B-W/AP/MPCS/PRED/ 01/Etcherla/017A NCRMP/B-W/AP/MPCS/PRED/ 01/Santhabommali/018 NCRMP/B-W/AP/RCS/PRED/ 01/V.Kothuru /010 NCRMP/B-W/AP/RCS/PRED/ 01/Ehterla & Rangasthalam/012 NCRMP/B-W/AP/RCS/PRED/ 01/V.Kotturu/001 NCRMP/B-W/AP/RCS/PRED/ 01/V.Kotturu/001 NCRMP/B-W/AP/RHB/PRED/ 01/Santhabommali /001A NCRMP/B-W/AP/RHB/PRED/ 01/Santhabommali /001B Name of Work Construction of cyclone shelter in Akkuvarm Construction of cyclone shelter Kollipadi Road from R&B road to Akkuvarm DPN Road to D.L.Puram Jn.Via Koduru, Magathapadu, Guppidipeta Guppidipeta Road to Chinnakoviripeta Construction of cyclone shelter in Bonthalakoduru Construction of cyclone shelter in Bypalli Construction of cyclone shelter in Bandravanipeta Construction of cyclone shelter in Chinavaka Construction of cyclone shelter in Chinakothuru Construction of cyclone shelter in Jaganathapuram Construction of cyclone shelter in Kalingapatnam Construction of cyclone shelter in Kommaravanipeta Construction of cyclone shelter in Kothamukkam Construction of cyclone shelter in Metturu Construction of cyclone shelter in Pathadibbapalem Construction of cyclone shelter in Reddica sunnapalli Road from Kothapeta Road to Sainooru cyclone shelter Road from R&B Road to Pathadibbapalem Road from R&B road to S.J.Puram Road from Chinavanka to Gopalavooru Road from R&B Road to Marripadu DPN Road to Gangaram village via palatalagam, srikrishnapuram District Srikakulam Srikakulam Srikakulam Srikakulam Srikakulam Srikakulam Srikakulam Srikakulam Srikakulam Srikakulam Srikakulam Srikakulam Srikakulam Srikakulam Srikakulam Srikakulam Srikakulam Srikakulam Srikakulam Srikakulam Srikakulam Srikakulam Srikakulam

Page 98 of 130

Eelectrical QCRs submitted in the month of July -2013


Package Number NCRMP/B-W/AP/MPCS/PRED/ 01/Santhabommali/005 NCRMP/B-W/AP/MPCS/PRED/ 01/Santhabommali/005 NCRMP/B-W/AP/MPCS/PRED/ 03/Nakkapalli/002 NCRMP/B-W/AP/MPCS/PRED/ 03/Nakkapalli/002 NCRMP/B-W/AP/MPCS/PRED/ 03/Nakkapalli/002 NCRMP/B-W/AP/MPCS/PRED/ 03/Payakaraopeta/003 NCRMP/B-W/AP/MPCS/PRED/ 03/Payakaraopeta/003 NCRMP/B-W/AP/MPCS/PRED/ 03/Rambilli/004 NCRMP/B-W/AP/MPCS/PRED/ 04/Thondangi /001 NCRMP/B-W/AP/MPCS/PRED/ 04/Thondangi /001 NCRMP/B-W/AP/MPCS/PRED/ 04/Uppalagutham/002 Name of Work Construction of Cyclone Shelter at Kollipadu in Santhabommali Mandal. Construction of Cyclone Shelter at Runku in Santhabommali Mandal. Construction of Cyclone Shelter at Patimeda in Nakkapalli Mandal Construction of Cyclone Shelter at Mullaparra in Nakkapalli Mandal Construction of Cyclone Shelter at Bangarampeta in Nakkapalli Mandal Construction of Cyclone Shelter at Gajapathinagaram in Payakaraopeta Mandal Construction of Cyclone Shelter at Ratnayampeta in Payakaraopeta Mandal Construction of Cyclone Shelter at Venkayyapalam in Rambilli Mandal Construction of Cyclone Shelter at Avulamanda in Thondangi Mandal Construction of Cyclone Shelter at Laxmanudipeta in Thondangi Mandal Construction of Cyclone Shelter at Pedaraghavulapeta in Uppalagutham Mandal District Srikakulam Srikakulam Visakhapatnam Visakhapatnam Visakhapatnam Visakhapatnam Visakhapatnam Visakhapatnam East Godavari East Godavari East Godavari

Page 99 of 130

Annexure - G
Photo Documentation

Page 100 of 130

Page 101 of 130

Page 102 of 130

Page 103 of 130

Page 104 of 130

Page 105 of 130

Page 106 of 130

Page 107 of 130

Page 108 of 130

Page 109 of 130

Page 110 of 130

Page 111 of 130

TPQA-NCRMP inspection Road from Kammavaricheruvu R&B road to Venkata durgambapuram as on 06.07.13 in Machilipatnam mandal in krishna dt GSB width and Thickness Verified

TPQA-NCRMP inspection Road from Kammavaricheruvu R&B road to Venkata durgambapuram as on 06.07.13 in Machilipatnam mandal in krishna dt GSB width and Thickness Verified

TPQA-NCRMP inspection Road from Kammavaricheruvu R&B road to Venkata durgambapuram as on 06.07.13 in Machilipatnam mandal in krishna dt GSB Layer completed

TPQA-NCRMP inspection Road from Kammavaricheruvu R&B road to Venkata durgambapuram as on 06.07.13 in Machilipatnam mandal in krishna dt GSB Layer completed

Page 112 of 130

Page 113 of 130

Page 114 of 130

Page 115 of 130

Page 116 of 130

Page 117 of 130

Page 118 of 130

Page 119 of 130

Page 120 of 130

Page 121 of 130

Page 122 of 130

Page 123 of 130

Page 124 of 130

Page 125 of 130

Page 126 of 130

Page 127 of 130

Page 128 of 130

Page 129 of 130

Page 130 of 130

You might also like