You are on page 1of 69

Project

Location
Procuring Entity
Date of Bid

:
:
:
:

MAGULON BHS
Magulon, Lamut, Ifugao
Provincial Local Government Unit of Ifugao
__________________________________

Description

Item
I

II

III

IV

Unit

Quantity

Preliminaries/General requirements:
1. Project Billboard

lot

1.00

CIVIL WORKS
a. Earthworks
a.1. Site Preparation
a.2. Structure Excavation
a.3. Backfilling & Compaction
a.4. Gravel Bedding

m
m
m
m

8.40
39.49
34.20
7.99

b. Concreting Works

29.97

c. Rebar Works & Tie Wire

kgs

4,435.48

d. Formworks & Scaffolding


d.1. Scaffolding/Falseworks
d.2. Formworks

bd.ft
m

1,250.00
197.59

e. Carpentry Works
e.1 Door Jamb
e.2 Wood Ventilation Louver
e.3 Counter Top(Midwife Station)

bd.ft
sets
lot

150.22
2.00
1.00

f. Roof Framing
f.1 Truss
f.2 Rafter
f.3 Purlins

bd.ft
bd.ft
m

326.00
206.00
110.00

g. Roofing Works
g.1 Corrugated GI Roof

110.00

h. Masonry Works

184.78

i. Plastering & Finishing


i.1 Septic Vault Walls

14.56

j. Doors & Windows


j.1 Doors
j.2 Windows

m
m

14.70
6.12

SANITARY WORKS
a.1 Sewerage System
a.2 Water Lines & Fittings
a.3 Sanitary Fixtures & Accessories

lot
lot
lot

1.00
1.00
1.00

ELECTRICAL WORKS

lot

1.00

TOTAL ESTIMATED COST =

Prepared by :
Signature:

Unit
Cost (P)

Total (P)

Project
Location
Procuring Entity
Date of Bid

:
:
:
:

MAGULON BHS
Magulon, Lamut, Ifugao
Provincial Local Government Unit of Ifugao
__________________________________

Description

Item
Name:
Designation:
Construction Firm:
Address:

Unit

Quantity

Unit
Cost (P)

Total (P)

Republic of the Philippines


Province of Ifugao
OFFICE OF THE PROVINCIAL ENGINEER
Lagawe, Ifugao
13 January, 2011
DATE
PROGRAM OF WORK
NAME OF CONTRACT :

Type of Project

Building

Construction of Magulon BHS

Type of Structure/s
Project Length

Split Type

9.00 m

Location of Contract
Magulon,
:
Lamut, Ifugao

Project Width

7.00 m

Source of Fund

DOH-HFEP
:

Floor Area/Area

63.00 sq.m

Appropriation

Php
: 1,000,000.00

No. of Culverts

Limits

Mode of Implementation :
Contract Brief:

No. of Span/Storey
Straight Contract

Duration

2.00
118 CD

Construction of Barangay Health Station


EQUIPMENT REQUIREMENT

DESCRIPTION

available

required

One Bagger Concrete Mixer

Dumptruck

Item
No.
I

available required

ESTIMATED PROJECT COST


WORK TO BE DONE

%TAGE

UNIT

QUANTITY

UNIT COST

0.13

lot

a.1. Site Preparation

0.24

a.2. Structure Excavation

1.39

a.3. Backfilling & Compaction


a.4. Gravel Bedding
b. Concreting Works

19.33

c. Rebar Works & Tie Wire

23.10

d.1. Scaffolding/Falseworks

5.76

bd.ft

d.2. Formworks

7.20

e.1 Door Jamb

1.12

e.2 Wood Ventilation Louver


e.3 Counter Top(Midwife Station)

AMOUNT

1.00

1,286.00

8.40

289.75

2,434.00

39.49

350.84

13,856.00

1.31

34.20

383.27

13,108.00

1.45

7.99

1,814.47

14,500.00

29.97

6,449.28

193,298.00

kgs

4,435.48

52.08

231,000.00

1,250.00

46.04

57,550.00

197.59

364.47

72,017.00

bd.ft

150.22

74.83

11,242.00

0.31

sets

2.00

1,526.86

3,054.00

0.47

lot

1.00

4,663.21

4,664.00

f.1 Truss

2.47

bd.ft

326.00

75.83

24,721.00

f.2 Rafter

1.58

bd.ft

206.00

76.83

15,827.00

f.3 Purlins

1.82

110.00

165.88

18,247.00

Preliminaries/General requirements:
1. Project Billboard

II

DESCRIPTION

1,286.00

CIVIL WORKS
a. Earthworks

d. Formworks & Scaffolding

e. Carpentry Works

f. Roof Framing

g. Roofing Works
3.82

110.00

347.53

38,229.00

h. Masonry Works

13.64

184.78

738.30

136,424.00

i. Plastering & Finishing

0.00

i.1 Septic Vault Walls

0.65

14.56

449.22

6,541.00

g.1 Corrugated GI Roof

j. Doors & Windows

III

0.00

j.1 Doors

3.97

14.70

2,698.09

39,662.00

j.2 Windows

2.71

6.12

4,433.44

27,133.00

SANITARY WORKS

IV

a.1 Sewerage System

1.97

lot

1.00

19,709.97

19,710.00

a.2 Water Lines & Fittings

1.34

lot

1.00

13,439.36

13,440.00

a.3 Sanitary Fixtures & Accessories

2.96

lot

1.00

29,645.28

29,646.00

1.26

lot

1.00

12,410.92

12,411.00

ELECTRICAL WORKS

BREAKDOWN OF ESTIMATES
EXPENDITURES

COST

% TAGE

EXPENDITURES

1.

Material Cost

A. Estimated Contract Cost

2.

Equipment Expense

(Direct Cost + Indirect Cost)

3.

Labor Cost

B. Estimated Prov'l. Gov't. Expenses:

4.

Hauling Cost

B.1 Administrative Overhead

5.

Mob./Demob. Cost

B.2 Engineering Overhead

6.

Total Contract Cost

B.3 Quaity Control

7.

Prov'l. Gov't. Expenses

B.4 ROW/Site Acquisition

8.

Reserve/Contingency

B.5 Contingencies/Reserved

9. Appropriation

D. Total Estimated Project Cost

1,000,000.00

1,000,000.00

1266

1266

1266

43898

43898

43898

193298

193298

2434

211750

211750

13856

140754

140754

13108

18960

18960

14500

58795

58795

193298

38229

38229

211750

136424

136424

140754

6541

6541

59415

74878

74878

81339

62796

62796

12411

12411

18960
11242
3054
4664
58795
24721
15827
18247
38229
38229
136424
6541
6541
74,878.00
44,873.00
30005
62796

19710
13440
29646
12411

1000000

Republic of the Philippines


Provincial Local Government Unit of Ifugao

OFFICE OF THE PROVINCIAL ENGINEER


Lagawe, Ifugao

APPROVED BUDGET FOR THE CONTRACT (ABC)


Name of Contract: Construction of Magulon BHS
Location
: Magulon, Lamut, Ifugao

ITEM
No.
(1)

DESCRIPTION

(2)
Preliminaries/General requirements:
1. Project Billboard

II

Date :
Duration (CD) :

Contract No.:

Wt. %tage QUANTITY

(3)
0.13

UNIT

ESTIMATED
Mob./
DIRECT COST
Demob.
(EDC)
%

INDIRECT COST
OCM

Profit

(in percent of EDC)


Total

Tax

VALUE

(5)

(6)

(7a)

(7b)

(7c)

(7d)

(7)

(8)

1.00

lot

1,000.00

12

8.5

26.5

265.00

(4)

CIVIL WORKS
a. Earthworks
a.1. Site Preparation

0.24

8.40

1,924.00

12

8.5

26.5

509.86

a.2. Structure Excavation

1.39

39.49

10,953.00

12

8.5

26.5

2,902.55

a.3. Backfilling & Compaction

1.31

34.20

10,362.00

12

8.5

26.5

2,745.93

a.4. Gravel Bedding

1.45

7.99

11,462.00

12

8.5

26.5

3,037.43

b. Concreting Works

19.33

29.97

152,804.00

12

8.5

26.5

40,493.06

c. Rebar Works & Tie Wire

23.10

4,435.48

kgs

182,626.04

12

8.5

26.5

48,395.90

d.1. Scaffolding/Falseworks

5.76

1,250.00

bd.ft

45,499.00

12

8.5

26.5

12,057.24

d.2. Formworks

7.20

197.59

56,930.00

12

8.5

26.5

15,086.45

d. Formworks & Scaffolding

e. Carpentry Works

0.00

e.1 Door Jamb

1.12

150.22

bd.ft

8,886.00

12

8.5

26.5

2,354.79

e.2 Wood Ventilation Louver

0.31

2.00

sets

2,414.00

12

8.5

26.5

639.71

e.3 Counter Top(Midwife Station)

0.47

1.00

lot

3,686.33

12

8.5

26.5

976.88

f.1 Truss

2.47

326.00

bd.ft

19,543.00

12

8.5

26.5

5,178.90

f.2 Rafter

1.58

206.00

bd.ft

12,512.00

12

8.5

26.5

3,315.68

f.3 Purlins

1.82

110.00

14,424.00

12

8.5

26.5

3,822.36

f. Roof Framing

g. Roofing Works
g.1 Corrugated GI Roof
h. Masonry Works

0.00
3.82

110.00

30,220.00

12

8.5

26.5

8,008.30

13.64

184.78

107,844.51

12

8.5

26.5

28,578.79

0.65

14.56

5,170.50

12

8.5

26.5

1,370.18

i. Plastering & Finishing


i.1 Septic Vault Walls

j. Doors & Windows

III

IV

j.1 Doors

3.97

14.70

31,353.30

12

8.5

26.5

8,308.62

j.2 Windows

2.71

6.12

21,448.75

12

8.5

26.5

5,683.92

a.1 Sewerage System

1.97

1.00

lot

15,581.00

12

8.5

26.5

4,128.97

a.2 Water Lines & Fittings

1.34

1.00

lot

10,624.00

12

8.5

26.5

2,815.36

a.3 Sanitary Fixtures & Accessories

2.96

1.00

lot

23,435.00

12

8.5

26.5

6,210.28

1.26

1.00

lot

9,811.00

12

8.5

26.5

SANITARY WORKS

ELECTRICAL WORKS

TOTAL =

100.00

790,513.43

2,599.92
209,486.06

13 January, 2011
118

TOTAL
COST

UNIT
COST

TOTAL
ADJUSTED
COST

(9)

(10)

(11)

1,265.00

1,286.00

2,433.86

289.75

2,434.00

13,855.55

350.84

13,856.00

13,107.93

383.27

13,108.00

14,499.43

1,814.47

14,500.00

193,297.06

6,449.28

193,298.00

231,021.94

52.08

231,000.00

57,556.24

46.04

57,550.00

72,016.45

364.47

72,017.00

11,240.79

74.83

11,242.00

3,053.71

1,526.86

3,054.00

4,663.21

4,663.21

4,664.00

24,721.90

75.83

24,721.00

15,827.68

76.83

15,827.00

18,246.36

165.88

18,247.00

1,286.00

38,228.30

347.53

38,229.00

136,423.30

738.30

136,424.00

6,540.68

449.22

6,541.00

39,661.92

2,698.09

39,662.00

27,132.67

4,433.44

27,133.00

19,709.97

19,709.97

19,710.00

13,439.36

13,439.36

13,440.00

29,645.28

29,645.28

29,646.00

12,410.92

12,410.92

12,411.00
1,000,000.00

999,999.49

Name of Project :
Location

Construction of Magulon BHS


Magulon,
:
Lamut, Ifugao

BAR CHART
Item
Activities
no.

Amount

Mobilization/Demobilization
I

2.00

Preliminaries/General requirements:
1. Project Billboard

II

DURATION IN WEEKS

Calendar Days

1,286.00

1.00

CIVIL WORKS
a. Earthworks

43,898.00

20.00

b. Concreting Works

193,298.00

38.00

c. Rebar Works & Tie Wire

231,000.00

12.00

d. Formworks & Scaffolding

129,567.00

25.00

e. Carpentry Works

18,960.00

4.00

f. Roof Framing

58,795.00

11.00

g. Roofing Works

38,229.00

7.00

h. Masonry Works

136,424.00

15.00

6,541.00

2.00

j. Doors & Windows

66,795.00

4.50

III

SANITARY WORKS

62,796.00

11.00

IV

ELECTRICAL WORKS

12,411.00

5.00

Total

1,000,000.00

i. Plastering & Finishing

14

21

28

35

42

49

56

63

70

77

84

Republic of the Philippines


Provincial Local Government of Ifugao

OFFICE OF THE PROVINCIAL ENGINEER


Lagawe, Ifugao

Namen of Project :
Location

Item
Activities
no.

Upgrading of Camandag BHS


: Camandag, Asipulo, Ifugao

Amount

Working
Days

Item
Activities
no.

Amount

5. Interior ceiling moulding


6. Roof framing

10

11

12

13

14

15

16

17

18

2.50

106,008.34

15.50

95,579.26

7.00

1. Doors

40,470.11

6.00

2. Windows

72,180.49

6.00

#REF!

#REF!
Roofing

IX

Working
Days

Doors/Windows & Glass

#REF!
1. Iron window grill

5.50
55,311.67

2.00

Finishes
X

1. Painting
1.a perimeter wall 6" CHB

2.00

1.b Interior wall (4" CHB)

4.00

1.c interior ceiling

4.00

1.d Exterior ceiling

2.00

1.e Doors

2.00

1.f Door and Window jams

3.00

1.g Base cabinets

4.00

2.1 floor

5.00

2.2 floor @ CR

0.50

2.3 Wall @ CR

1.50

2.4 Countertops/backsplash

1.00

2. tileworks

XII

Hardwares

XIII

Sanitary & plumbing


1. Water supply

1.00

7,209.24

4.00

12,575.31

3.50

1. Common Excavation

#REF!

2.00

2. Rebars

#REF!

1.00

3. Concrete(3000 psi)

#REF!

0.50

4. CHB wall (6")

#REF!

1.50

5. Plastering (1/2" thk)

#REF!

1.50

6. accessories

#REF!

1.00

2. sanitary
XIV

39,153.03

Special Construction(septic vault)

Total
Prepared by:

GEORGE A. DAULAYAN JR.

84

Reviewed by:

JONATHAN D. PAHIGON

91

98

105

112

Submitted by:

JULIAN B. DULAWWAN JR.

35

42

49

56

Approval Recommended:

ORLANDO D. SAROL

Project Engineer

Engineer III

Ass't. Provincial Engineer

Provincial Engineer

IN WEEKS
9

10

11

12

13

118

119

84

91

98

105

112 118

DURATION IN WEEKS

18

56

19

63

18

56

Approved by:

19

63

19

63

20

70

ApprovedApproved
by:
by:

TEODORO B. BAGUILAT
TEODORO
JR.B. BAGUILAT JR.

12

77

Provincial Governor

12

Name of Project : MAGULON BHS


Location
: Magulon, Lamut, Ifugao
Appropriation
: Php 1,000,000.00
Source of Fund : DOH-HFEP
DETAILED ESTIMATES
Item no.
I
Preliminaries/General requirements:
QTY =
1. Project Billboard
Unit
Qty
lot
1
Direct Cost =
II

Amount
1,000.00

1,000.00

CIVIL WORKS
a. Earthworks
a.1. Site Preparation

QTY =
Basement Floor =

1 lot
Unit Price
1000

8.40 m

8.40 m

Labor Cost:
Prod. Rate =
Employ =
=
Duration =
Description
Foreman
Laborers

2.5 m/man-day
1 Foreman
2 Laborers
1.68
say
No.
1
2

Rate
452
255

Direct Cost =
a.2. Structure Excavation
Column Footing =
Wall Footing =
Stair Footing =
Septic Tank =

No. of Days
2
2

Amount
904.00
1,020.00
1,924.00

1,924.00
QTY =

18.96
7.80
0.42
12.31
39.49

2 days

39.49 m

m
m
m
m
m

Labor Cost:
Prod. Rate =
Employ =
=
Duration =
Description
Foreman
Laborers

1.5 m/man-day
1 Foreman
3 Laborers
8.78
say
No.
1
3

Rate
452
255

Direct Cost =
a.3. Backfilling & Compaction
Labor Cost:(Placing)
Prod. Rate =
Employ =
=
Duration =
Description
Foreman
Laborers

No. of Days
9
9

Amount
4,068.00
6,885.00
10,953.00

10,953.00
QTY =

2.75 m/man-day
1 Foreman
5 Laborers
2.49
say
No.
1
5

9 days

Rate
452
255

34.20 m

2.5 days
No. of Days
2.5
2.5

Amount
1,130.00
3,187.50
4,317.50

Labor Cost:(Compaction)
Prod. Rate =
Employ =
=
Duration =
Description
Foreman

2 m/man-day
1 Foreman
5 Laborers
3.42
say
No.
Rate
1
452

3.5 days
No. of Days
3.5

Amount
1,582.00

Laborers

255

Direct Cost =
a.4. Gravel Bedding
Material Cost:
Description
Gravel

Unit
m

Qty
8

4 m/man-day
1 Foreman
2 Laborers
1
say
Rate
452
255

No.
1
2

Direct Cost =

QTY =

Material Cost:
Description
Portland Cement
Sand(S-1)
Gravel(G-1)
Water

7.99 m
Unit Cost
1312.50

1 days
No. of Days
1
1

Amount
10,500.00

Amount
452.00
510.00
962.00

11,462.00

b. Concreting Works
Column footing =
Wall footing =
Stair footing & pedestal =
Column =
Basement floor slab =
Ground floor slab =
Ground floor beams =
Roof beams =
Lintel beams =
Cantilever beam =
Stair 1 and landing(above) =
Stair 2 =
Lavatory Counter =
Septic tank's slab and cover =

4,462.50
6,044.50

10,362.00
QTY =

Labor Cost:(Placing & Compaction)


Prod. Rate =
Employ =
=
Duration =
Description
Foreman
Laborers

3.5

29.97 m

m
m
m
m
m
m
m
m
m
m
m
m
m
m
29.97 m
4.39
2.94
0.26
5.69
2.20
5.63
2.60
2.51
0.96
0.21
1.15
0.63
0.37
0.43

Unit
bags
m
m
drums

Qty
273
15
26
28

Unit Cost
252.00
1212.50
1312.50
50.00

Amount
68,796.00
18,187.50
34,125.00
1,400.00
122,508.50

Labor Cost:
Prod. Rate =
Employ =

0.66
1
2
3
9.08

Duration =
Description
Foreman
Mason
Laborers
Equipment Cost:
Description
1 Bagger Mixer

9.5 days

No.
1
2
3

Rate
452
362
255

No. of Days
9.5
9.5
9.5

Amount
4,294.00
6,878.00
7,267.50
18,439.50

No.
1

Rate
1,248

No. of Days
9.5

Amount
11,856.00

Direct Cost =
c. Rebar Works & Tie Wire

m/man-day
Foreman
Mason
Laborers
say

152,804.00
QTY =

4,435.48 kgs

Column footing =
Wall footing =
Stair footing & pedestal =

20
28
4
2
96
125
18
50
35
8
8
26
18
19
61
19
28
89

Column =
Basement floor slab =
Ground floor slab =
Basement Floor Beams(Tie Beams)=

Ground floor beams =

Roof beams =

Lintel beams =

10
13
7
8
9
8
24
10
11

Cantilever beam =
Stair 1 and landing(above) =

Lavatory Counter =
Septic tank's slab and cover =
Material Cost:
Description
16mm RSB
12mm RSB
10mm RSB
Ga #16 Tie Wire

Unit
kg
kg
kg
kg

-16x6m=
-10x6m=
-12x6m=
-10x6m=
-16x6m=
-10x6m=
-10x6m=
-12x6m=
-10x6m=
-16x6m=
-16x7.5m=
-10x6m=
-16x6m=
-16x7.5m=
-10x6m=
-16x6m=
-16x7.5m=
-10x6m=

-16x6m=
-10x6m=
-16x6m=
-10x6m=
-16x6m=
-12x6m=
-10x6m=
-10x6m=
-12x6m=

Qty
2,422.09
389.09
1,587.30
66

189.40
103.60
21.32
7.40
909.12
462.50
66.60
266.50
129.50
75.76
94.72
96.20
170.46
224.96
225.70
179.93
331.52
329.30

kgs
kgs
kgs
kgs
kgs
kgs
kgs
kgs
kgs
kgs
kgs
kgs
kgs
kgs
kgs
kgs
kgs
kgs

94.70
48.10
66.29
29.60
85.23
42.64
88.80
37.00
58.63
4,435.48

kgs
kgs
kgs
kgs
kgs
kgs
kgs
kgs
kgs
kgs

Unit Cost
35.50
35.50
35.50
74.00

Amount
85,984.20
13,812.70
56,349.15
4,884.00
156,146.04

Labor Cost:
Prod. Rate =
Employ =

Duration =
Description
Foreman
Steelmen
Laborers

75
1
1
2
19.71
No.
1
1
2
Direct Cost =

d. Formworks & Scaffolding


d.1. Scaffolding/Falseworks
Material Cost:
Description
2"x2"x10'
2"x3"x10'
Assorted CWN

kg/man-day
Foreman
Steelmen
Laborers
say
Rate
452
362
255

Labor Cost: (False works Installation)


Prod. Rate =
Employ =

Duration =

Qty
450
800
15

50
1
2
2
5

Amount
9,040.00
7,240.00
10,200.00
26,480.00

182,626.04
QTY =

Unit
b.f.
b.f.
kg

20 days
No. of Days
20
20
20

bd.ft./man-day
Foreman
Carpenter
Laborers
say

1,250 bd.ft

Unit Cost
25.00
25.00
79.00

Amount
11,250.00
20,000.00
1,185.00
32,435.00

5 days

Description
Foreman
Carpenter
Laborers

No.
1
2
2

Labor Cost: (False works removal)


Prod. Rate =
Employ =

100
1
1
2
3.13

Duration =
Description
Foreman
Carpenter
Laborers

Rate
452
362
255

No.
1
1
2

bd.ft/man-day
Foreman
Carpenter
Laborers
say
Rate
452
362
255

Direct Cost =

QTY =

Material Cost:
Description
1/4" Ordinary plywood
2"x2"x10'
Assorted CWN

Amount
1,582.00
1,267.00
1,785.00
4,634.00

197.59 m

m
m
m
m
m
m
m
m
m
197.59 m
72.72
56.28
25.00
13.60
10.64
2.51
9.21
3.42
4.22

Unit
pcs
b.f.
kg

Qty
62
497
15

Labor Cost: (Formworks fabrication & installation)


Prod. Rate =
3.46
Employ =
1
2
2
Duration =
11.42
Description
No.
Foreman
1
Carpenter
2
Laborers
2
Labor Cost: (Formworks removal)
Prod. Rate =
Employ =

16
1
2
2
2.47

Duration =
Description
Foreman
Carpenter
Laborers

3.5 days
No. of Days
3.5
3.5
3.5

Amount
2,260.00
3,620.00
2,550.00
8,430.00

45,499.00

d.2. Formworks
Column =
Ground floor slab =
Ground floor beams =
Roof beams =
Lintel beams =
Cantilever beam =
Stair 1 and landing =
Lavatory Counter =
Septic tank's slab and cover =

No. of Days
5
5
5

No.
1
2
2
Direct Cost =

Unit Cost
318.00
25.00
79.00

m/man-day
Foreman
Carpenter
Laborers
say
Rate
452
362
255

11.5 days
No. of Days
11.5
11.5
11.5

m/man-day
Foreman
Carpenter
Laborers
say
Rate
452
362
255

2.5 days
No. of Days
2.5
2.5
2.5

Amount
19,716.00
12,425.00
1,185.00
33,326.00

Amount
5,198.00
8,326.00
5,865.00
19,389.00

Amount
1,130.00
1,810.00
1,275.00
4,215.00

56,930.00

e. Carpentry Works
QTY =

e.1 Door Jamb

Material Cost:
Description

Unit

Qty

150.22 bd.ft
Unit Cost

Amount

D-1 (1.4mX2.1m)
D-2 (1mX2.1m)
D-3 (0.8mX2.1m)
D-4 (0.8mX2.1m)
Note: D-5 is incorporated in the door(item j.1)

sets
sets
sets
sets

1200
1000
1000
1000

1
2
2
2

1,200.00
2,000.00
2,000.00
2,000.00
7,200.00

Labor Cost:
Prod. Rate =
Employ =
=
=
Duration =
Description
Foreman
Carpenter
Laborers

40
1
2
2
0.94
No.
1
2
2

bd.ft/man-day
Foreman
Carpenter
Laborers
say
Rate
452
362
255

Direct Cost =

Material Cost:
Description

Unit
set

Ventilation

No. of Days
1
1
1

Amount
452.00
724.00
510.00
1,686.00

8,886.00
QTY =

e.2 Wood Ventilation Louver

1 days

Qty
2

2.00 sets
Unit Cost
800

Amount
1,600.00

Labor Cost:
Prod. Rate =
Employ =
=
Duration =
Description
Foreman
Carpenter

No.
1
1

2 sets/man-day
1 Foreman
1 Carpenter
1
say
Rate
452
362

Direct Cost =
e.3 Counter Top(Midwife Station)
Material Cost:
Description
2"x5"x8' Jambs
1"x12"x8'
Quarter Round Moulding
1/4" thk Clear Glass
Assorted CWN
Labor Cost: (Fabrication & Installation)
Description
Foreman
Carpenter
Laborer

Amount
452.00
362.00
814.00

2,414.00
QTY =

1.00 lot

Unit
b.f.
b.f.

Qty
13
8

Unit Cost
25.00
25.00

pcs
sq.ft.
kg

2
16
1

50.00
52.25
79.00

100.00
836.00
79.00
1,548.33

No.
1
1
1

Rate
452
362
255

No. of Days
2
2
2

Amount
904.00
724.00
510.00
2,138.00

Direct Cost =
f. Roof Framing
f.1 Truss
Material Cost:
Description
4pcs- 2"x"6"x16' Top Chord
8pcs- 2"x6"x14' Bottom Chord
1pc-2"x6"x10' King Post
Web Members
2pcs- 2"x6"x12'
2pcs- 2"x6"x10'
2pcs- 2"x6"8'
2pcs- 2"x6"x10' Collar Plate

1 days
No. of Days
1
1

Amount
333.33
200.00

3,686.33

QTY =

326.00 bd.ft

Unit
b.f.
b.f.
b.f.

Qty
64
112
10

Unit Cost
25.00
25.00
25.00

Amount
1,600.00
2,800.00
250.00

b.f.
b.f.
b.f.
b.f.

24
16
20
20

25.00
25.00
25.00
25.00

600.00
400.00
500.00
500.00

2pcs-2"x6"x8' Wood Block


3pcs-2"x6"x10' Truss support
1pc- 2"x8"x10' Base plate
Assorted CWN
5/8"x10" Machine Bolts w/ nuts & washer
5/8"x8" Machine Bolts w/ nuts & washer

6mm thk metal strap

b.f.
b.f.
b.f.
kg
pcs
pcs
pcs

Labor Cost: (fabrication & installation)


Prod. Rate =
Employ =

27
1
1
2
4.02

Duration =
Description
Foreman
Carpenter
Laborers

16
30
14
5
16
52
8

No.
1
1
2
Direct Cost =

f.2 Rafter
Material Cost:
Description
10pcs- 2"x"6"x16' Top Chord
3pcs- 2"x6"x10' Collar Plate
1pc- 2"x8"x12' Base plate
Assorted CWN

bd.ft/man-day
Foreman
Carpenter
Laborers
say
Rate
452
362
255

5/8"X10" anchor bolts w/ N&W


1/2"X8" anchor bolts w/ N&W
5/8"X3" machine bolts w/ N&W

6mm thk metal strap


Labor Cost: (fabrication & installation)
Prod. Rate =
Employ =
=
=
Duration =
Description
Foreman
Carpenter
Laborers

Qty
160
30
16
4
24
20
6
12

40
1
1
2
1.72
No.
1
1
2
Direct Cost =

f.3 Purlins
Material Cost:
Description
64pcs- 2"x"3"x10' Purlins
12pcs- 2"x2"x10' Cleats
Assorted CWN

bd.ft/man-day
Foreman
Carpenter
Laborers
say
Rate
452
362
255

Amount
2,034.00
1,629.00
2,295.00
5,958.00

206.00 bd.ft
Unit Cost
25.00
25.00
25.00
79.00
70.00
54.00
21.00
126

2 days
No. of Days
2
2
2

Amount
4,000.00
750.00
400.00
316.00
1,680.00
1,080.00
126.00
1,512.00
9,864.00

Amount
904.00
724.00
1,020.00
2,648.00

12,512.00
QTY =

Unit
b.f.
b.f.
kg

4.5 days
No. of Days
4.5
4.5
4.5

400.00
750.00
350.00
395.00
1,120.00
2,912.00
1,008.00
13,585.00

19,543.00
QTY =

Unit
b.f.
b.f.
b.f.
kg
pcs
pcs
pcs
pcs

25.00
25.00
25.00
79.00
70
56
126

Qty
320
40
10

110.00 m
Unit Cost
25.00
25.00
79.00

Amount
8,000.00
1,000.00
790.00
9,790.00

Labor Cost:
Prod. Rate =
Employ =
=
=
Duration =
Description
Foreman
Carpenter
Laborers

11.5
1
1
2
3.19
No.
1
1
2

m/man-day
Foreman
Carpenter
Laborers
say
Rate
452
362
255

3.5 days
No. of Days
3.5
3.5
3.5

Amount
1,582.00
1,267.00
1,785.00
4,634.00

Direct Cost =
g. Roofing Works
g.1 Corrugated GI Roof
Material Cost:
Description

14,424.00
QTY =

Ga #26 Corrugated GI Roofing(10ft length)


Ga #26 Corrugated GI Roofing(8ft length)
Ga #26 Prefab. Ridge Roll(15"x8')

Umbrella Nail

Unit
lin.ft
lin.ft
pcs
kgs

Qty
320
256
6
12

110.00 m
Unit Cost
32.50
32.50
162.00
105.00

Amount
10,400.00
8,320.00
972.00
1,260.00
20,952.00

Labor Cost:
Prod. Rate =
Employ =

5.3
1
1
2
6.92

Duration =
Description
Foreman
Carpenter
Laborers

m/man-day
Foreman
Carpenter
Laborers
say

No.
1
1
2

Rate
452
362
255

Direct Cost =
h. Masonry Works
Basement Floor Wall(6" CHB) =
Basement Floor Wall(4" CHB) =
Ground Floor Walls(4"CHB) =
Lavatory (6" CHB) =
Septic Vault (4" CHB) =
Material Cost:
Description
4" CHB
6" CHB
Portland Cement
Sand(S-1)

12mm(Horizontal & Vertical bars)


10mm(Horizontal & Vertical bars)
Ga #16 Tie Wire
Water

Unit
pcs
pcs
bags
m
kg
kg
kg
drums

No. of Days
7
7
7

Amount
3,164.00
2,534.00
3,570.00
9,268.00

30,220.00
QTY =

36.67
24.14
107.85
2.40
13.72
184.78

7 days

184.78 m

m
m
m
m
m
m
Qty
1913
513
117
10
37.31
313.5
7
12

Unit Cost
10.00
13.75
252.00
1212.50
35.50
35.50
74.00
50

Amount
19,130.00
7,053.75
29,484.00
12,125.00
1,324.51
11,129.25
518.00
600.00
81,364.51

Labor Cost: (4"CHB)


Prod. Rate =
Employ =

Duration =
Description
Foreman
Mason
Laborers

3
1
1
2
14.67
No.
1
1
2

m/man-day
Foreman
Mason
Laborers
say
Rate
452
362
255

15 days
No. of Days
15
15
15

2.5
1
1
2
4.89

m/man-day
Foreman
Mason
Laborers
say

5 days

Amount
6,780.00
5,430.00
7,650.00
19,860.00

Labor Cost: (6"CHB)


Prod. Rate =
Employ =

Duration =
Description
Foreman
Mason
Laborers

No.
1
1
2

Rate
452
362
255

No. of Days
5
5
5

Amount
2,260.00
1,810.00
2,550.00

6,620.00
Direct Cost =
i. Plastering & Finishing
i.1 Septic Vault Walls
Septic Vault inside walls=
Material Cost:
Description
Portland Cement
Sand

Water

107,844.51
QTY =

14.56 m

14.56 m
Unit
bags
pcs
drums

Qty
5
1
1

Unit Cost
252.00
1212.50
50

Amount
1,260.00
1,212.50
50.00
2,522.50

Labor Cost:
Prod. Rate =
Employ =

4
1
1
2
2

Duration =
Description
Foreman
Mason
Laborers

m/man-day
Foreman
Mason
Laborers
say

No.
1
1
2

Rate
452
362
255

Direct Cost =

2 days
No. of Days
2
2
2

Amount
904.00
724.00
1,020.00
2,648.00

5,170.50

j. Doors & Windows


QTY =

j.1 Doors

2.94
2.10
3.36
3.36
2.94
14.7

D-1(2.1mx1.4m) =
D-2(2.1mx1.0m) =
D-3(2.1mx0.8m) =
D-4(2.1mx0.8m) =
D-5(2.1mx0.7m) =

Material Cost:
Description
D-1(2.1mx1.4m Panel Type Door)
D-2(2.1mx1.0m Panel Type Door)
D-3(2.1mx0.8m Flush Type Door w/ fixed glass)
D-4(2.1mx0.8m Flush Door)
D-5(2.1mx0.7m PVC type w/ jamb)
4"x4" Loose Pin Hinges
Door Knob

Unit
sets
sets
sets
sets
sets
pcs
sets

Labor Cost: (Installation of doors,hinges & door knob)


Prod. Rate =
2
Employ =
1
=
1
=
2
Duration =
2.45
Description
Foreman
Carpenter
Laborers

Qty
1
1
2
2
2
21
9

m/man-day
Foreman
Carpenter
Laborers
say

No.
1
1
2

Rate
452
362
255

Direct Cost =
j.2 Windows
W-2(1.5mx1.2m) =
W-4(0.6mx0.6m) =

Material Cost:
Description
W-2(1.5mx1.2m Steel Casement Window)
W-4(0.6mx0.6m Steel Casement Window)

14.70 m

m
m
m
m
m
m

31,353.30
QTY =

Unit Cost
6000
4000
2800
2200
1365
53.00
466.70

Amount
6,000.00
4,000.00
5,600.00
4,400.00
2,730.00
1,113.00
4,200.30
28,043.30

2.5 days
No. of Days
2.5
2.5
2.5

Amount
1,130.00
905.00
1,275.00
3,310.00

6.12 m

5.40 m
0.72 m
6.12 m
Unit
sq.ft
sq.ft

Qty
58.10
7.75

Unit Cost
210.00
210.00

Amount
12,201.00
1,627.50

sq.ft
pcs
pcs

1/8" Clear Glass


Silicon
Silicon Gun

65.85
20
1

25.00
158.00
166.00

1,646.25
3,160.00
166.00
18,800.75

Labor Cost:
Prod. Rate =
Employ =
=
=
Duration =
Description
Foreman
Welders
Laborers

1.6
1
1
2
1.28
No.
1
1
2
Direct Cost =

III

SANITARY WORKS
a.1 Sewerage System
Material Cost:
Description
100mmx3.0m PVC pipe(Orange)
100mmx100mm wye
100mmx50mm wye reducer
100mmx45 deg elbow
100mm dia. clean out
50mmx 3.0m pvc pipe
50mmx50mm Tee
50mmx90 deg elbow
50mmx45 deg elbow
50mm p-trap
100mm x 100mm stainless, floor drain
Teflon tape
Solvent
Labor Cost:
Description
Foreman
Plumber
Laborer

Labor Cost:
Description
Foreman
Plumber
Laborer

Rate
452
362
255

2 days
No. of Days
2
2
2

Amount
904.00
724.00
1,020.00
2,648.00

21,448.75

QTY =

1.00 lot

Unit
pcs
pcs
pcs
pcs
pcs
pcs
pcs
pcs
pcs
pcs
pcs
pcs
liter

Qty
6
1
8
5
2
3
7
8
19
4
2
5
2

Unit Cost
578.00
189.00
189.00
189.00
100.00
368.00
79.00
47.00
47.00
79.00
95.00
26.00
180.00

Amount
3,468.00
189.00
1,512.00
945.00
200.00
1,104.00
553.00
376.00
893.00
316.00
190.00
130.00
360.00
10,236.00

No.
1
1
1

Rate
452
362
255

No. of Days
5
5
5

Amount
2,260.00
1,810.00
1,275.00
5,345.00

Direct Cost =
a.2 Water Lines & Fittings
Material Cost:
Description
13mmx6m G.I. Pipe(sch. 40)
13mm coupling
13mm union
13mm dia. tee
13mm dia. X 90 deg elbow
13mm dia. gate valve
13mmx300mm nipple
Wall faucet
Gooseneck Spout Faucet
Teflon tape

m/man-day
Foreman
Welders
Laborers
say

15,581.00
QTY =

1.00 lot

Unit
pcs
pcs
pcs
pcs
pcs
pcs
pcs
pcs
pcs
pcs

Qty
5
2
2
14
11
1
9
2
5
5

Unit Cost
299.00
42.00
37.00
16.00
11.00
214.00
45.00
210.00
850.00
26.00

Amount
1,495.00
84.00
74.00
224.00
121.00
214.00
405.00
420.00
4,250.00
130.00
7,417.00

No.
1
1
1

Rate
452
362
255

No. of Days
3
3
3

Amount
1,356.00
1,086.00
765.00

3,207.00
Direct Cost =
a.3 Sanitary Fixtures & Accessories
Material Cost:
Description
Lavatory(Stainless) & Accessories
Lavatory(ceramic) wall hang
Water closet

QTY =

3/8mm (1 1/2") x 0.60m stainless steel grab bar

Tissue holder
Soap holder
Hose bib

Labor Cost:
Description
Foreman
Plumber
Laborer

ELECTRICAL WORKS
Material Cost:
Description
13mm dia. pvc pipe(Mark Certified)
32mm dia pvc pipe(Mark Certified)
50mm x 100mm utility box (deep type)
Junction box

1.00 lot

Unit
sets
sets
sets
sets
pcs
pcs
pcs

Qty
3
2
2
2
2
2
2

Unit Cost
2100.00
924.00
5040.00
350.00
280.00
280.00
90.00

No.
1
1
1

Rate
452
362
255

No. of Days
3
3
3

Direct Cost =
IV

10,624.00

1.00 lot

Unit
pcs
pcs
pcs
pcs

Qty
80
1
32
4

Unit Cost
45
150
19
27

Amount
3,600.00
150.00
608.00
108.00
4,466.00

No.
1
1
1

Rate
452
362
255

No. of Days
5
5
5

Amount
2,260.00
1,810.00
1,275.00
5,345.00

Direct Cost =

9,811.00

DERIVATION OF UNIT COST OF MATERIALS


A. TRANSHIPMENT OF CEMENT
Source: Lamut
Road condition
Paved road at 7%-12% Grade
Unpaved road at 7%-12% Grade
Manuevering time/ Slack Time
Loading Time
Loaded Travel Time
Unloaded Travel Time
Unloading Time

Ave.Hauling
Dist. (Kms)
1
13
=
=
=
=
=

Using 1 Unit Dumptruck with capacity of 120bags


Working hours/day
=
Rate per day
=
Total cycle time
=
Transhipment Cost/bag =

Php. =
B. TRANSHIPMENT OF SAND AND GRAVEL
Source: Ongto
Road condition

Amount
1,356.00
1,086.00
765.00
3,207.00

23,435.00
QTY =

Labor Cost:
Description
Foreman
Electrician
Laborer

Amount
6,300.00
1,848.00
10,080.00
700.00
560.00
560.00
180.00
20,228.00

Loaded
Speed(Kph)
15
5
6
30
160
81
30
307

Unloaded
Speed(Kph)
20
10
mins
mins
mins
mins
mins
mins

8 hrs
4800 php
307 mins
307 mins x 4,800/day x 1 day/8hrs x 1hr/60mins.
120 bags
25.58
say
26.00 /bag

Ave.Hauling
Dist. (Kms)

Loaded
Speed(Kph)

Unloaded
Speed(Kph)

Paved road at 7%-12% Grade


Unpaved road at 7%-12% Grade (single lane)
Manuevering time/ Slack Time
Loading Time
Loaded Travel Time
Unloaded Travel Time
Unloading Time

10
13
=
=
=
=
=

15
5
6
10
196
108
5
325

20
10
mins
mins
mins
mins
mins
mins

Using 1 Unit Dumptruck with capacity of 4.00 Cu.m Dump truck


Working hours/day
=
8 hrs
Rate per day
=
4800 php
Total cycle time
=
325 mins
Transhipment Cost/m =
325 mins x 4,800/1day x 1 day/8hrs x 1hr/60mins.
4 m
812.50
say
812.50 /m
Php. =
DERIVED UNIT COST OF MATERIALS
Description
Unit
Pick-up Price
Transhipment
Unit Cost
Portland Cement
Bag
226
26.00
252.00
Sand
Cu.m
400
812.50
1212.50
Gravel
Cu.m
500
812.50
1312.50

SUMMARY
Item

I
II

Description

Preliminaries/General requirements:
1. Project Billboard
CIVIL WORKS
a. Earthworks
a.1. Site Preparation
a.2. Structure Excavation
a.3. Backfilling & Compaction
a.4. Gravel Bedding

b. Concreting Works
c. Rebar Works & Tie Wire
d. Formworks & Scaffolding
d.1. Scaffolding/Falseworks
d.2. Formworks
e. Carpentry Works
e.1 Door Jamb
e.2 Wood Ventilation Louver
e.3 Counter Top(Midwife Station)
f. Roof Framing
f.1 Truss
f.2 Rafter
f.3 Purlins
g. Roofing Works
g.1 Corrugated GI Roof
h. Masonry Works
i. Plastering & Finishing
i.1 Septic Vault Walls
j. Doors & Windows
j.1 Doors
j.2 Windows
III SANITARY WORKS
a.1 Sewerage System
a.2 Water Lines & Fittings
a.3 Sanitary Fixtures & Accessories

IV ELECTRICAL WORKS

% Wt

Quantity

Unit

DC

0.13

1.00

lot

1,000.00

0.24
1.39
1.31
1.45

8.40
39.49
34.20
7.99

m
m
m
m

1,924.00
10,953.00
10,362.00
11,462.00

19.33
23.10

29.97
4,435.48

m
kgs

152,804.00
182,626.04

5.76
7.20

1,250.00
197.59

bd.ft
m

45,499.00
56,930.00

1.12
0.31
0.47

150.22
2.00
1.00

bd.ft
sets
lot

8,886.00
2,414.00
3,686.33

2.47
1.58
1.82

326.00
206.00
110.00

bd.ft
bd.ft
m

19,543.00
12,512.00
14,424.00

3.82
13.64

110.00
184.78

m
m

30,220.00
107,844.51

0.65

14.56

5,170.50

3.97
2.71

14.70
6.12

m
m

31,353.30
21,448.75

1.97
1.34
2.96
1.24

1.00
1.00
1.00
1.00

lot
lot
lot
lot

15,581.00
10,624.00
23,435.00
9,811.00

Total Direct Cost (TDC) =


790,513.43
Indirect Cost (26.5% of TDC) =
209,486.06
Total Project Cost (TDC+IC)=
999,999.49
say 1,000,000.00

Prepared by:

Checked by:
RODERICK D. DOMINONG
Engineer I

Recommending Approval:

JULIAN B. DULAWAN JR.


Assistant Provincial Engineer

JONATHAN D. PAHIGON
Engineer III

Approved:

ORLANDO D. SAROL
Provincial Engineer

16.96

56,930.00
170.8275821

Computations for CHB & bars:


Width
Basement:(6"CHB) 2.7
3.7
2.7
3.2
Basement:(4"CHB)

No. of wall/
Height
door/window
3.20
2
3.20
1
1.80
1
3.20
1

17.28
11.84
2.43
5.12
36.67
17.28
11.84
2.10
2.88
24.14

2.7
3.7
less doors/windows 1
1.2

3.20
3.20
2.10
1.20

2
1
1
2

Ground Floor:

3.7
2.7
2.7

2.70
2.70
2.70

2
9
3

19.98
65.61
21.87

3.4
2.8
1.9
1.85
less doors/windows 2.1
2.1
0.6
1.2

3.00
3.00
3.00
3.00
1.40
1.00
0.60
1.20

1
1
1
1
1
1
2
1

10.20
8.40
5.70
5.55
2.94
2.10
0.72
1.44
107.85

Septic Vault:

1.3
1
3.1

1.40
1.40
1.40

2
1
2

3.64
1.40
8.68
13.72

lavatory:

0.6

0.80

2.40

Computations for wall plastering:

No. of faces

Width
Ground Floor(toilet): 1.5
2.7
less doors/windows 2.1

Height
1.50
1.50
0.70

4
2
2

9.00
8.10
2.94
14.16

Septic Vault:

1.1
1
2

1.40
1.40
1.40

4
2
2

Lavatory =

3.9
1.8
1.5
3.9
1.8
1.5

0.60
0.60
0.60
0.20
0.20
0.20

1
1
1
1
1
1

6.16
2.80
5.60
14.56
2.34
1.08
0.90
0.78
0.36
0.30

2.6
3.7
2.7
3.4
1.8
0.8

2.70
2.70
2.70
2.70
1.50
2.10

1
1
1
1
1
1

7.02
9.99
7.29
9.18
2.70
1.68

2.7
1.2
0.7

2.70
1.50
2.10

4
2
1

29.16
3.60
1.47

Ward Room:

Treatment room:

31472
30810
662

2,648.00
2529
119.00
(543.00)
504
(39.00)

Days

2.00
9.00
2.50
1.00
9.50
20.00
5.00
11.50
1.00
1.00
2.00
4.50
2.00
3.50
7.00
15.00
2.00
2.50
2.00
5.00
3.00
3.00
5.00

75,205.53
999,970.00
0.51

Ver
5 pcs X
7 pcs X

3.20
3.20

m
m

=
=

29.5 m
40.9 m

5 pcs X
7 pcs X

3.20
3.20

m
m

=
=

29.5 m
40.9 m

m
m
m

7 pcs X
5 pcs X
5 pcs X

2.70
2.70
2.70

m
m
m

=
=
=

37.4 m
27 m
27 m

m
m
m
m
m
m
m
m
m
m
m
m
m
m

6
5
4
4

3.00
3.00
3.00
3.00

m
m
m
m

=
=
=
=

m
m
m
m
m
m
m
m
m
m

pcs X
pcs X
pcs X
pcs X

35
29
21.5
21.25
338.95
372.845

m
m
m
m
m
m

x 0.617kg/m=

258 kgs

You might also like