Fabrication and Installation of Piping ES-14-602-01

This is a Controlled Document that complies with Wesfarmers Chemicals, Energy & Fertilisers formatting and Quality Control standards. Please check that this is the latest available version before use. Title: Number: Version Number: Date Revised: Owner: Authoriser: Reasons for Creating or Amending Document Actual Change Details:

FABRICATION AND INSTALLATION OF PIPING ES-14-602-01


12.0 19 December 2012 Harish Chopra Manoj Thakur

Full Review of Document

Links updated and working

TABLE OF CONTENTS

1. 1.1 1.2 2. 2.1 2.2 2.3 3. 3.1 3.2 3.3 4. 4.1 4.2 4.3 4.4 4.5 4.6 4.7

GENERAL ................................................................................................................................. 3 SCOPE................................................................................................................................... 3 DEFINITION OF TERMS .................................................................................................... 3 STANDARDS ............................................................................................................................ 4 REQUIREMENTS ................................................................................................................ 4 STANDARDS ....................................................................................................................... 4 DEVIATIONS ....................................................................................................................... 4 DESCRIPTION ......................................................................................................................... 5 MATERIALS ........................................................................................................................ 5 DRAWINGS ......................................................................................................................... 5 ACCURACY ......................................................................................................................... 5 FABRICATION REQUIREMENTS ....................................................................................... 7 MARKING AND IDENTIFICATION.................................................................................. 7 TRACEABILITY OBJECTIVES.......................................................................................... 7 TRACEABILITY REQUIREMENTS .................................................................................. 7 STORAGE ............................................................................................................................. 7 CUTTING AND BEVELLING ............................................................................................. 7 END PREPARATION .......................................................................................................... 8 WELDING PROCEDURES, SPECIFICATIONS AND PROCEDURE QUALIFICATIONS .............................................................................................................. 9

Version No. 12.0

Page 1 of 26

Document last modified: 19 December 2012. PDF created: 23 April 2013.

Fabrication and Installation of Piping ES-14-602-01

4.8 4.9 4.10 4.11 4.12 4.13 4.14 4.15 5. 5.1 6.

THREADING ...................................................................................................................... 17 FLANGING ......................................................................................................................... 17 FIT-UP................................................................................................................................. 17 BRANCH CONNECTIONS ............................................................................................... 18 PIPE BENDING .................................................................................................................. 18 STEAM TRACED PIPING ................................................................................................. 18 STEAM JACKETED PIPING............................................................................................. 18 ELECTRICAL TRACING .................................................................................................. 18

PROTECTION ........................................................................................................................ 18 PIPE SPOOLS ..................................................................................................................... 18 ERECTION ............................................................................................................................. 19 6.1 6.2 6.3 6.4 6.5 6.6 6.7 6.8 6.9 6.10 6.11 6.12 IDENTIFICATION ............................................................................................................. 19 STORAGE AND HANDLING ........................................................................................... 19 ASSEMBLY/INSTALLATION .......................................................................................... 20 FLANGED CONNECTIONS ............................................................................................. 20 BOLTING ........................................................................................................................... 21 CONNECTION TO EQUIPMENT ..................................................................................... 22 THREADED JOINTS ......................................................................................................... 22 TEMPORARY STRAINERS .............................................................................................. 22 VALVE INSTALLATION.................................................................................................. 22 UNDERGROUND PIPING ................................................................................................ 23 INSTALLATION OF EXPANSION JOINTS .................................................................... 23 TESTING OF PIPEWORK ................................................................................................. 23

7. 7.1 7.2 8.

PIPE SUPPORTS .................................................................................................................... 23 STANDARD PIPE SUPPORTS ......................................................................................... 23 SPRING HANGERS ........................................................................................................... 24 AS-BUILT DATA AND RECORDS...................................................................................... 24

APPENDIX 1 - TYPICAL PROCEDURE QUALIFICATION RECORD (PQR) ....................... 25 APPENDIX 2 - TYPICAL WELDING PROCEDURE SPECIFICATION (WPS) ...................... 26

FIGURE
Figure 1 Piping Fabrication Tolerances ...................................................................................... 6

Version No. 12.0

Page 2 of 26

Document last modified: 19 December 2012. PDF created: 23 April 2013.

Fabrication and Installation of Piping ES-14-602-01

1.
1.1

GENERAL
SCOPE

This Standard covers the minimum requirements and acceptance criteria for: a. b. c. Fabrication of piping (both in situ and/or at Workshops as assemblies/sub assemblies). Installation. Certification and records keeping.

It is to be used together with ASME B31.3 Chemical Plant and Petroleum Refinery Piping Code, all Government Statutory requirements and referenced standards. Should there be conflict between the Works, this Standard, Local Codes, Statutory Requirements or the latest issue of the Code and other referenced standards, the Contractor shall notify the Superintendent in writing for resolution. In general the most stringent requirement will prevail.

1.2

DEFINITION OF TERMS

Contractor/Vendor The Company, which provides the equipment and services, needed. Sub-Contractor A third party to be employed by the Contractor/Vendor who has been approved by the Superintendent in writing. Superintendent CSBP Limited or authorised representative. For internal works, the Superintendent shall be the Responsible Officer. CSBP CSBP Limited. Works The scope of work that a Contractor is or may be required to execute under an agreement including variations and remedial work. Code Throughout this standard, the words The Code shall mean ASME B31.3 Chemical Plant and Petroleum Refinery Piping.

Version No. 12.0

Page 3 of 26

Document last modified: 19 December 2012. PDF created: 23 April 2013.

Fabrication and Installation of Piping ES-14-602-01

2.
2.1

STANDARDS
REQUIREMENTS

The Contractor shall perform the Works in accordance with the requirements of: a. b. c. The Statutory Authorities. The Code and other referenced standards. This Standard

2.2

STANDARDS

Standards Association of Australia AS1210 AS2022 AS2205 AS4041 SAA Unfired Pressure Vessel Code including Supplement 1 SAA Anhydrous Ammonia Code Methods of Destructive Testing of Welds in Metal Pressure Piping

American National Standards Institute (ANSI) American Society of Mechanical Engineers (ASME) ANSI/ASME B16.11 ANSI/ASME B16.20 ANSI/ASME B16.21 ANSI/ASME B16.25 ASME Forged Fittings, Socket-Welding and Threaded Metallic Gaskets for Pipe Flanges - Ring joint, Spiral Wounds and Jacketed Non-metallic Flat Gaskets for Pipe Flanges Buttwelding Ends Boiler and Pressure Vessel Code Section V Non-destructive Examination Section VIII Boiler and Pressure Vessels - Divisions 1 & 2 Section IX Welding and Brazing Qualifications Chemical Plant and Petroleum Refinery Piping Metallic Gaskets for Refinery Piping (Double Jacketed Corrugated and Spiral Wound) Protective Coatings Insulation of Piping and Equipment Basis of Design - Piping Inspection and Testing of Piping Systems Underground Piping Piping Material Specifications Valve Specifications for Process Isolation Steam Tracing Manufacturers Data Report (MDR) Plant Projects

ASME B31.3 API 601

American Petroleum Institute

CSBP Engineering Standards ES-14-102-12 ES-14-102-14 ES-14-601-01 ES-14-602-02 ES-14-602-05 ES-14-603-01 ES-14-603-02 ES-14-603-14 EP-08-030-37

2.3

DEVIATIONS

There shall be no deviation from the requirements of this Standard unless previous written approval has been obtained from the Superintendent.

Version No. 12.0

Page 4 of 26

Document last modified: 19 December 2012. PDF created: 23 April 2013.

Fabrication and Installation of Piping ES-14-602-01

3.
3.1

DESCRIPTION
MATERIALS

The piping materials covered in this Engineering Standard are Carbon Steel, Low Alloy Steel and Stainless Steel. These are identified in the CSBP Engineering Standard Piping Material Specifications (ES-14-603-01). This Engineering Standard shall be used whenever it is relevant to do so for non-metallic pipework including PVC, HDPE, ABS, Polypropylene and FRP. All such pipework shall be installed, inspected and tested strictly in accordance with the manufacturers instructions and the relevant Australian Standard.

3.2

DRAWINGS

Piping General Arrangement drawings will be provided showing equipment location and piping configuration. These drawings shall be adhered to for the erection and installation of pipe spools. Fabrication of pipe spools shall be in accordance with the Piping Isometric drawings which will be provided for all lines size DN 50 and above. Small bore piping DN 40 and below shall be field run in accordance with the General Arrangement drawings. Pipe support location plans may be provided for complex piping systems but generally pipe supports will be located on General Arrangement drawings and Isometric drawings. The pipe supports shown will be a minimum requirement. Additional supports may be required to comply with standards and codes. Where pipe supports need to be manufactured detail drawings will be provided. Fabrication of pipe spools and supports shall only commence after issue of Approved for Construction (AFC) drawings. Subsequent revisions of AFC drawings will supersede all previous drawings and the Contractors procedures shall ensure all fabrication is carried out in accordance with latest revision of each drawing.

3.3

ACCURACY

The Contractor shall verify drawing information and confirm all dimensions before commencing fabrication. Dimensional tolerances for completed fabricated piping shall conform to the requirements listed on Figure 1.

Version No. 12.0

Page 5 of 26

Document last modified: 19 December 2012. PDF created: 23 April 2013.

Fabrication and Installation of Piping ES-14-602-01

+ 3mm MAX FROM INDICATED DIMENSIONS FOR FACE TO FACE, CENTRE TO FACE, LOCATION OF ATTACHMENTS, ETC

10% MAX (FOR INTERNAL PRESSURE) 3% MAX (FOR EXTERNAL PRESSURE) FLATTENING MEASURED AS DIFFERENCE BETWEEN THE MAXIMUM & MINIMUM O.D. AT ANY CROSS SECTION. + 2mm MAX LATERAL TRANSLATION OF BRANCHES OR CONNECTIONS

+ 1mm MAX ROTATION OF FLANGES FROM THE INDICATED POSITION, MEASURED AS SHOWN.

1mm MAX OUT OF ALIGNMENT OF FLANGES FROM THE INDICATED POSITION MEASURED ACROSS ANY DIAMETER.

Figure 1

Piping Fabrication Tolerances

The Contractor shall ensure the piping meets final assembly requirements as specified on the piping layout drawings. Dimensions to tie-in points shall have tolerances in accordance with the following: a. b. c. Linear dimensions 1.5mm

Nozzles orientation and rotation 030 (Flange bolt holes shall be aligned within 3mm maximum offset) Angular alignment of flange and branch welding ends 3mm per 1000mm

Version No. 12.0

Page 6 of 26

Document last modified: 19 December 2012. PDF created: 23 April 2013.

Fabrication and Installation of Piping ES-14-602-01

4.
4.1

FABRICATION REQUIREMENTS
MARKING AND IDENTIFICATION

Items shall be marked for identification and traceability in accordance with Section 4.3. Items marked for identification shall maintain the marking through all manufacturing stages including final assembly.

4.2

TRACEABILITY OBJECTIVES

Items and documents shall be marked to ensure means of: a. b. Note: Locating the item (traceability record). Locating the quality records generated from purchasing, inspection and testing of the item. As a minimum the Contractors system shall enable traceability between the items and quality records.

4.3

TRACEABILITY REQUIREMENTS

The Contractors fabrication procedures shall ensure that correct materials are used during fabrication and these shall be submitted to the Superintendent for approval. Note: Periodic audits may be carried out by the Superintendent to ensure compliance.

4.4

STORAGE

The Contractor shall be responsible for material and equipment received from the Superintendent or warehouse stocks until the same is installed. Where Superintendent supplied materials are delivered to the Contractor with documentation such as mill certificates, these shall be incorporated into the Contractors quality records. Materials received from the warehouse or Superintendent, are to be stored off the ground on temporary racks or docks to prevent any deterioration until fabricated. Pipes, fittings, valves and speciality items shall be suitably blanked to protect the ends from damage and to prevent entry of foreign material. Flanged openings shall be protected as detailed in Section 5.1.2. Stainless steel material shall be kept separate from carbon steel during storage and transport.

4.5

CUTTING AND BEVELLING

Pipe shall be cut accurately to the measurements on the drawings or field fit conditions and shall be worked into place without springing or forcing.

Version No. 12.0

Page 7 of 26

Document last modified: 19 December 2012. PDF created: 23 April 2013.

Fabrication and Installation of Piping ES-14-602-01

Stainless steel material shall be segregated from other piping materials during all stages of machining and fabrication to prevent surface contamination with carbon steel leading to localised corrosion. Cutting of pipes shall preferably be done by mechanical means. Flame cutting is acceptable within the limits as listed below: a. For carbon steel, flame (or arc) cutting and bevelling is acceptable only if the cut is reasonably smooth and true and all oxides are removed from the flame-cut surface by grinding. For alloy steel, flame-cut bevels are acceptable only where machine cutting is not feasible. After flame cutting approximately 2mm of material must be removed from the surface of the bevel by grinding. Bevelling by mechanical means (ie. shearing) requires work hardened areas to be removed as in b. above. Stainless steel and non-ferrous metals shall be prepared by machining, grinding or plasma arc cutting and grinding.

b.

c. d.

Grinding of stainless steel and non-ferrous metals shall be done with a non-carbonaceous, iron free non sulphur bonded grinding wheel. Chipping, filing, cutting with hacksaws or wire brushing using carbon steel brushes is not permitted on stainless steel. Burrs and other objectionable defects shall be removed by reaming, machining or grinding. All cuts shall be made at right angles to the longitudinal axis of the pipe. All pipe ends shall be remade to the full bore of the pipe. All cuts shall be carefully bevelled and accurately matched to form a suitable groove for welding and to permit complete penetration of the welds at all points. Reference is to be made to the relevant section of the Code. Defective or damaged weld ends shall be examined in order to determine the nature and extent of damage. Any bevelled edge of pipe that has been damaged shall be machined to minimum tolerances. All bevels shall be cleaned to bright metal finish. Repairs shall not be made on weld preparation of pipes or fittings without written permission from the Superintendent. Repairs to weld preparations shall only be carried out using repair procedures which have been reviewed and approved by the Superintendent. Repair procedures must be submitted in writing for the Superintendents review and approval.

4.6
4.6.1

END PREPARATION
General

Surfaces to be welded shall be ground free of rust. Grinding is to extend 10mm past the toe of the weld preparation and is to be done immediately prior to welding.

Version No. 12.0

Page 8 of 26

Document last modified: 19 December 2012. PDF created: 23 April 2013.

Fabrication and Installation of Piping ES-14-602-01

4.6.2

Butt Welding

End preparation for butt-welding shall be in accordance with ANSI/ASME B16.25. Cleaning and end preparation shall be in accordance with the Code and in accordance with this Standard. Stainless steel materials shall be cleaned using degreasing compounds free of chlorides and sulphur for a distance of 75mm from the prepared edge of inside and outside surfaces. Stainless steel wire brushes shall not be used for carbon steels. 4.6.3 Fillet Welds

Pipes for insertion in slip-on flanges and for socket-weld joints shall be cut square, to within the tolerances specified in ANSI/ASME B16.11. Prior to welding of socket connections, the pipe shall be backed off 1.5mm from the seat of the socket. Socket welds and the external welds of field welded slip-on-flanges shall always be carried out using a minimum of two passes with staggered stops and starts. Shop welded slip on flanges may require two passes on the external weld, depending on the welding process, to ensure good root fusion.

4.7
4.7.1

WELDING PROCEDURES, SPECIFICATIONS AND PROCEDURE QUALIFICATIONS


General

Welding Procedure Specifications (WPS), Procedure Qualification Records (PQR) and the Welding Procedure Register (WPR) shall be submitted to the Superintendent and approval obtained before any welding is begun. The WPR shall identify all WPS necessary for the intended scope of work. Refer to Appendix 1 and Appendix 2 for sample formats of WPS and PQR forms. 4.7.2 Welding Procedure Specification

Each WPS shall exhibit the name of the originating Contractor and shall be uniquely identified. The WPS revision number and data shall be included. The technical requirements of this Standard shall be adhered to in preparing WPS. Manual, semi-automatic, or automatic electric arc welding processes shall be used on all piping. The preparation and procedure for welding shall conform to the requirements of the Code. Welding of carbon steel pipe shall be performed by either: Submerged Arc (SAW), Manual Metal Arc (MMAW), Gas Tungsten Arc (GTAW), or a combination of these processes. Flux Cored Arc (FCAW) maybe used for workshop welding only. Welding processes other than these are prohibited. Semi automatic and fully automatic welds shall be made with a multi pass technique.

Version No. 12.0

Page 9 of 26

Document last modified: 19 December 2012. PDF created: 23 April 2013.

Fabrication and Installation of Piping ES-14-602-01

Weld passes thicker than 10mm are prohibited. Welding of stainless steel or alloy shall be performed by either Gas Tungsten Arc, or Manual Metal Arc Welding, or a combination of these processes. Root pass must be made using Gas Tungsten Arc process with inert gas purge on inside of pipe. Flux Cored (FCAW) and GTAW wire (brand name TGX) may be used at the discretion of the Superintendent. Procedure for welding dissimilar metals (e.g. carbon steel to stainless steel 304L or 316L, etc) shall be submitted to the Superintendent and approval obtained prior to any welding. Welders qualified, as per Section 4.7.7 of this Standard shall perform all welding. 4.7.3 Qualification of Welding Procedure

All WPS shall be qualified in accordance with the Code and ASME Section IX and this Standard. Previously qualified WPS may be submitted for the Superintendents approval. Qualification shall be performed on pipe, not plate. If a weld procedure includes PWHT, the weld procedure qualification tests shall include a hardness survey. Acceptance criteria shall be the same as described in Section 4.7.13. The hardness survey shall be performed using a 5-kg Vickers tester in accordance with AS2005. 4.7.4 Welding Procedure Essential Variables

In addition to the essential and supplementary essential variables listed in ASME Section IX articles 2 and 4, the following shall be deemed essential variables: a. For welding procedures qualified for low temperature carbon steel (impact tested carbon steels) and low temperature low alloy steels (also impact tested) and any change in welding consumable brand name, manufacturer, classification or country/region for base metals. Any change in wire flux combination for SAW. Any decrease in preheat for material thicknesses greater than 6mm. Any change in current clarity or type (AC or DC). The omission of back gouging or back grooving. Variables during welding must remain same as used during procedure qualification (ie. parameters I, V (speed) and U shall remain constant). For P3 and P4 materials, hardness test on site shall be in accordance with those values obtained or recorded during procedure qualification. Impact Test Requirements

b. c. d. e. f.

4.7.5

Welding procedures for all P1 Group 1 and Group 2 steels developed for use in low temperature service (less than 0C design minimum temperature as specified by the applicable piping class) shall include qualification by impact test. Impact test specimens shall be tested at a calculated temperature, using an assumed design temperature of minus (-) 46C, whilst all other test requirements shall be in accordance with the Code. Three specimens shall be tested from each

Version No. 12.0

Page 10 of 26

Document last modified: 19 December 2012. PDF created: 23 April 2013.

Fabrication and Installation of Piping ES-14-602-01

sample area and the average energy value obtained from them shall be at least equivalent of 20 joules obtained from full size specimens. One specimen may show a lower equivalent value, but this shall not be lower than 16 joules. Impact tests for welding procedures for other materials, the assumed minimum design temperature used for determining the impact test temperature shall be (-) 46C or the piping minimum design temperatures whichever is lower. Weld metal specimens shall be located as near as possible to the pipe surface. Two specimens shall be located near the surface containing the last pass of the weld, and one specimen near the opposite surface. The specimen location shall be identified in the report. Specimen sides, which are perpendicular to the base of the notch, shall be 10mm. Depth of side containing the base of the notch shall be the greatest possible of 10mm, 7.5mm, 5mm and 2.5mm depending on the pipe wall thickness. Test temperature of sub-size specimen shall comply with the Code. The notch shall be contained in the weld metal at approximately the centreline of the weld and the base of the notch shall be perpendicular to the surface of the plate. Before machining the notch, the specimen shall be etched to distinguish the weld metal from the parent metal and to ensure that the notch is correctly located. Machining of the bottom of the notch shall be done with care. The Superintendent shall witness impact testing of welding procedure qualification specimens. 4.7.6 Weld Maps

Weld maps shall be prepared for each assembly/sub-assembly fabricated identifying the welder, date welded, nature and extent of NDE performed, defects/re-welds, re-examination, if any, results of NDE for each weld of the assembly/sub-assembly. Weld maps shall also contain information on hydrostatic testing viz. test pressure, medium, date and duration of testing and the results. All the above information shall be properly documented and up-to-date records maintained by the Contractor. Final copies of all the above referenced documents shall be issued to the Superintendent within seven (7) days of completion of fabrication. 4.7.7 Qualification of Welders and Operators

All welders and welding operators shall be qualified in accordance with the requirements of ASME Section IX and this Standard prior to commencing any work including tack welds or temporary attachments. The performance test must include 6G position. Welder qualification certificates including evidence of re-qualification and revalidation shall be maintained for the Superintendents approval and inspection. All welder qualification tests must be carried out to an approved welding procedure specification (WPS). Previous qualifications may be submitted for approval provided that the holder(s) of the qualification(s) have carried out similar work within the last six months.

Version No. 12.0

Page 11 of 26

Document last modified: 19 December 2012. PDF created: 23 April 2013.

Fabrication and Installation of Piping ES-14-602-01

Each welder shall be assigned a unique symbol which will identify, on a weld map, all welds performed by that welder. 4.7.8 Welding Types

All welds shall be full penetration welds except: a. b. c. reinforcing pad, peripheral fillet welds, structural attachment fillet welds and socket welds, which shall be welded to the Code.

All butt welds DN 50 and below shall be made with the Gas Tungsten Arc process. 4.7.9 Welding Proximity and Location

The number of welds in the fabricated spools shall be kept to a minimum by using the longest practical pipe lengths. The minimum distance between girth welds, shall be six times the pipe wall thickness or 100mm, whichever is lesser. Seam orientation of welded straight pipe to pipe and pipe to fittings shall be such that at circumferential welds, the longitudinal welds shall be staggered, by 30 degrees left and right of the centre line. As a minimum the circumferential distance between the staggered joints shall be 50mm or 6 times the pipe wall thickness, whichever is lesser. Attachment welds, should be separated from pressure welds by a distance not less than 50mm, weld toe to toe. Welds for non-pressure attachments should not cross- existing main pressure welds. Where this is unavoidable, the main pressure weld shall be ground back flush with the parent pipe and the area examined for defects, using MPI/DPI inspection procedures. Subject to satisfactory acceptance of the inspection, fabrication of the attachment weld shall be carried out in accordance with welding procedures as approved for the main pressure weld. Attachment welds shall not penetrate through the pressure pipe. 4.7.10 Preparation for Welding and Alignment Earth connections shall be located as close as possible to the joint to be welded. G type welding clamps shall be used for connecting pipe to earth. The ends of pipe and fittings shall be accurately aligned and properly spaced as indicated in the appropriate welding procedure. A pipe clamp or other device shall be used as required to obtain accurate alignment and spacing. The bore alignment for the butt joints shall be in accordance with the Code except that the maximum internal trimming shall be 1:4. Preference shall be given to the use of line-up clamps or bridge pieces for assembling components to be welded.

Version No. 12.0

Page 12 of 26

Document last modified: 19 December 2012. PDF created: 23 April 2013.

Fabrication and Installation of Piping ES-14-602-01

In addition to the requirements of the Code, all pipe joint preparations and welds shall be subject to the following: a. b. Backing rings are not permitted. Back welds shall be examined visually for defects and, if found to be defective, shall be removed.

Branch connection joints shall be prepared so as to permit full penetration welds of a quality comparable to the circumferential welds in the same piping system. When thermal cutting is performed to prepare edges, to remove attachments or defective material, or for any other purpose, the material shall be reheated using the preheat schedules established in the qualified welding procedures. Welding shall not be carried out when the surfaces to be welded are wet from any cause. Galvanised flanges, supports, clips and the like shall not be welded to or come into direct contact with stainless steel. All valves, piping speciality items, equipment and instruments which may be damaged by the heat of welding shall be protected by dismantling and be re-assembled upon completion of welding and heat treatment. All sections of tacked or welded pipe shall be sealed prior to installation to prevent foreign matter from entering such sections. A qualified welder using the qualified welding procedure, which will be utilised for full welding of the joint, shall make tack welds. Temporary tack welds shall not touch the root gap or root face and shall not be part of a final joint weld up. Line-up clamps shall not be removed until the root pass has been completed. There shall be no field-welded attachments to stainless steel or alloy piping or to any vessels without Superintendents approval and an approved welding procedure as described. c. Cold spring is permitted only if it is shown on piping isometrics. If shown on piping isometrics, this operation shall be withheld until the entire line between anchors has been connected together in all directions up to the last closing length of pipe at the anchor and all guides and supports are in place. The cold spring shall be pulled at one anchor with the pipe firmly secured at the anchor on the opposite side of the section to the cold spring. Cold springing is not permitted at rotating equipment nozzles. Anchors/welded attachments on pipes shall be in accordance with Standard Pipe Support Details and the respective piping isometrics.

d.

Each welding bead shall be thoroughly cleaned of all scale and slag by chipping and/or grinding and wire brushing immediately after completion of the weld and prior to the application of succeeding beads. The width of the completed weld shall extend a minimum of 3mm greater than the width of the original groove. For reinforcement, the bead shall extend not less than 1.5mm and not more than 3mm above the surface of the pipe. Penetration of depth of fusion shall extend the full depth of the pipe wall, including both the bevelled and straight portions. The bead shall be

Version No. 12.0

Page 13 of 26

Document last modified: 19 December 2012. PDF created: 23 April 2013.

Fabrication and Installation of Piping ES-14-602-01

smooth in appearance and contain no valleys, indentations or undercut on the crest or at the edge. The completed weld and adjacent pipe shall be cleaned of all oxide, slag and spatter to allow proper application of protective coating. The entire root bead shall be made with the pipe in a stationary position. Movement of the pipe during manual welding of the root beads shall be kept to an absolute minimum. Welding shall be a continuous operation. Welding should not be discontinued before the root run and the next two successive passes are complete. If welding has to be interrupted the welds area shall be covered to permit slow cooling. Before resumption of welding on a weld cooled to ambient temperature the area shall be inspected visually for the presence of cracks. The welds shall be subjected to magnetic particle or dye penetrant examination to determine acceptability. Cracks shall be completely removed prior to any further welding. All welding necessary for in-place assembly and erection shall be in accordance with applicable paragraphs of this Standard. The areas from which temporary attachments have been removed shall be dressed smooth. Stray arc strikes are forbidden. 4.7.11 Welding Consumable Control and Handling The Contractor shall establish and implement procedures for receiving, storing, conditioning and issuing consumables. 4.7.11.1 Receipt Storage and Identifications

All consumables shall be received and clearly identified in sealed containers. The consumables shall be stored in sealed, moisture proof containers at a protected convenient dry location at a temperature of not less than 20C. Consumables shall be identified at all times during storage, conditioning, distribution and at weld stations. Identification shall include manufacturer, grade and batch number. 4.7.11.2 Drying of Electrodes

Prior to use, MMAW electrodes shall be dried in accordance with the manufacturers recommendations. After drying, the electrodes shall be transferred to heat storage cabinets maintained at 120C minimum for later use. No electrodes shall be redried more than twice.

Version No. 12.0

Page 14 of 26

Document last modified: 19 December 2012. PDF created: 23 April 2013.

Fabrication and Installation of Piping ES-14-602-01

4.7.12 Protection of the Welding Environment The welding area shall be protected at all times against adverse environment conditions, water spray, mist, drips or wind exceeding 8kph. Welding shall not proceed when the work is exposed to such conditions. Prefabrication areas for carbon and stainless steel shall be physically separated to prevent contamination of stainless steels. When grinding or welding carbon steel pipe and supports protection of any adjacent stainless steel shall be provided. 4.7.13 Heat Treatment of Welds Heat treatment procedures, pre-heat and post-heat shall comply with the Code requirements. In the case of Ammonia Liquid, Chlorine-Dry Liquid, Chlorine-Dry Gas, and Synthesis Gas services, heat treatment procedures shall comply with AS4041 or the Code, whichever is more stringent. Details shall be included in the Weld Procedures. All welds on carbon steel and low alloy steel piping for the following services shall be heat-treated after welding. Note: Ammonia Liquid at any temperature. Chlorine-Dry Liquid at any temperature. Chlorine-Dry Gas at any temperature. Synthesis Gas services at any temperature. Ammonia Gas services where there is a possibility condensate will form under normal operating conditions. Sodium Hydroxide (Caustic Soda) of 30% to 50% strength at any temperature. Sodium Hydroxide (Caustic Soda) less than 30% strength if the normal operating temperature is greater than 60C. 30% Sodium Cyanide Solution if the normal operating temperature is greater than 60C. Where heat treatment is recommended for a particular service and material combinations covered by NACE or other anti-corrosion standards, heat treatment shall be performed in accordance with the standard.

Heat treatment shall be in accordance with the requirements of the Code clause 331.1.7 and the following: a. All hardness tests on stress relieved welds shall be carried out using a standard Equip tester. A qualified metallurgist or an experienced tester approved by the Superintendent shall perform the tests. The criteria for hardness tests on local and shop stress relieved welds shall be as per the Code plus the following: (i) (ii) P1 materials shall not exceed 225 Brinell for ammonia and chlorine service and 248 Brinell for other services. For P4, P5 and P6 alloy steels, where the wall thickness is less than that for which a maximum hardness is specified, the maximum hardness shall be specified as for the material with the thicker walls.

b.

Version No. 12.0

Page 15 of 26

Document last modified: 19 December 2012. PDF created: 23 April 2013.

Fabrication and Installation of Piping ES-14-602-01

(iii)

For service and material combinations covered by NACE or other anticorrosion standards and not covered by (i) and (ii) above, the hardness limits in these standards shall apply. For other materials and services not covered by (i) to (iii) above, the maximum hardness shall not exceed 248 Brinell.

(iv)

Note:

For b. (iii) the hardness limit may also apply to piping and welds which are not heat treated. If heat treated in a furnace, all piping shall be properly supported in the furnace during heat treatment to eliminate warpage and other distortion. The cooling rate from the stress relieving temperature shall be in accordance with the requirement of ASME Section VIII. All machined surfaces shall be protected by a suitable paint or compound or by any other method (eg. gasket and a counter flange for flanged surface) to prevent damage from scaling. Unless otherwise approved in writing by Superintendent, no welding, hammering or cold forming is permitted following heat treatment. All valves, piping specialties, equipment and instruments, which may be damaged by the heat from heat treatment, shall be protected by dismantling and be re-assembled upon completion of heat treatment. Valve bodies (2 or 3 piece ball valves) or bonnets to be removed shall be match-marked prior to disassembly to ensure that they are reassembled back into the same location and orientation. Seats shall be gently lapped where necessary to remove any scale and new bonnet/body gaskets fitted when reassembling the valves.

c. d. e.

f. g.

All welds or attachments required including pipe supports or reinforcing plates, etc, shall be made before heat treatment. No welding is permitted after heat treatment. 4.7.14 Filler Materials All filler materials shall deposit an alloy whose chemical, physical and corrosion resistance properties correspond to the base material and shall satisfy requirements of the Code Standards. Consumables for use on carbon steel lines for sodium cyanide solution shall have low sulfur content. 4.7.15 Weld Repairs No repair shall be undertaken without first notifying the Superintendent of the requirement to repair, and seeking his approval of the proposed repair procedure. Repair of welds shall be done in such a manner as not gouge, groove, or otherwise reduce the adjacent base metal thickness.

Version No. 12.0

Page 16 of 26

Document last modified: 19 December 2012. PDF created: 23 April 2013.

Fabrication and Installation of Piping ES-14-602-01

Repairs or replacement welds shall be performed in accordance with the original welding procedure, including pre-heat and post weld heat treatment if originally required. Inspection and NDT of repairs shall be as originally required for the initial welds. A weld defect that has to be repaired shall be removed to sound metal. Repair welds shall be made by qualified welders Welding procedures used shall be in accordance with the Code and ASME Section IX. 4.7.16 Inspection and Testing/Welds Non-destructive examination of welds shall be carried out in accordance with the requirements detailed in CSBP Engineering Standard Inspection and Testing of Piping Systems (ES-14-602-02).

4.8

THREADING

The minimum pipe schedule for threading pipe shall be Sch 80. For carbon steel and low alloy steel threaded nipples the pipe schedule shall be Sch 160 minimum. Stainless steel threaded nipples shall be Sch 80 minimum. Threading of steel pipe shall preferably be done after bending, forging, heat treating or welding operations. Where post-fabrication threading is very difficult and threads are cut first, they shall be fully protected during such operations. Threads shall be concentric with the outside pipe and shall conform to ANSI B1.20.1 (NPT). Screwed pipe shall be reamed after cutting and threading. The threads shall be full cut and after a tight connection is made, no more than three threads shall remain exposed. All cutting oil and metal chips shall be cleared off the pipe prior to assembly. Screwed pipe joints shall be made up using a suitable tape, which has been approved in writing by the Superintendent. Screwed connections shall not be back welded unless specified on designs drawings, or approved by the Superintendent. It is recommended that back welded threaded connections be replaced with socket weld connections if possible.

4.9

FLANGING

Flange bolt holes shall straddle the principal centre lines, unless other orientation is shown on the design drawings.

4.10

FIT-UP

Misalignment or poor fit-up in excess of the values specified in Section 3.3 is not acceptable. For compression-type fittings, use proper tools and torques as specified by the manufacturer to ensure a leak-tight joint. To avoid damage or distortion of the fitting, do not over-torque the fitting nut.

Version No. 12.0

Page 17 of 26

Document last modified: 19 December 2012. PDF created: 23 April 2013.

Fabrication and Installation of Piping ES-14-602-01

4.11

BRANCH CONNECTIONS

Lines that connect to the main line or header, including instrument connections, vents and drains are considered branch lines. All branch connections shall be made in accordance with the respective Piping Material Specification. All stub-ins shall meet the requirements of the Code.

4.12

PIPE BENDING

Piping shall be bent only at locations shown on isometric drawings. In all other cases welding elbows shall be used. If the pipe to be bent contains a longitudinal weld, this weld shall be located in the neutral zone (pipe central axis). Pipe bending shall be in accordance with Code requirements. A minimum bend radius of five (5) diameters shall be used. Wall thickness of completed bends shall not be less than that required for the pressure and temperature plus any corrosion allowance. Bends are permitted provided tensile and impact properties are not impaired by the bending operation. Butt weld joints shall not be located in the curved section of bent pipe. Weld repair of cracks in pipe bends will not be accepted. Cold bending of pipe DN 40 and smaller is permitted. Induction bends for larger pipes may only be used with the approval of the Superintendent.

4.13

STEAM TRACED PIPING

Steam traced piping shall be fabricated and installed in accordance with CSBP Engineering Standard Steam Tracing (ES-14-603-14).

4.14

STEAM JACKETED PIPING

Steam jacketed piping shall be fabricated and installed in accordance with the design drawings.

4.15

ELECTRICAL TRACING

Electrical tracing and its associated electrical supply and control shall be installed in accordance with the design drawings and manufacturers instructions.

5.

PROTECTION

In general, all pipes, fittings, valves, instruments and all other equipment including all accessories, issued to the Contractor for erection shall be protected from normal weather conditions, corrosion or damage, prior to mechanical completion

5.1

PIPE SPOOLS

.After fabrication and inspection, all pipe spools shall be protected in the following manner: 5.1.1 Pipework Painting

On completion of fabrication and workshop examination and inspection and before erection all pipework shall be surface prepared and prime painted in accordance with the specified Painting System. General conditions for painting and cleaning shall be as per Specification.

Version No. 12.0

Page 18 of 26

Document last modified: 19 December 2012. PDF created: 23 April 2013.

Fabrication and Installation of Piping ES-14-602-01

Patch priming of field welds and any abraded or damaged portions shall be carried out on completion of erection, pressure testing and any other examinations and inspections, which may be required prior to finish coating. Pipelines and valves shall be finish coated in accordance with the specified Painting System and colour specific in CSBP Engineering Standard Protective Coatings (ES-14-102-12). Cold insulated services piping shall be primed in accordance with the painting Specification. 5.1.2 Flanges

Flange faces shall be protected by coating with a removable rust preventative and blanked with 6mm thick exterior quality plywood covers, or proprietary plastic flange guard covers no smaller than the flange OD. The flange cover shall be retained by a minimum of four bolts or by polyethylene lock plugs. 5.1.3 Connections

Threaded connections shall be fitted with line specification steel pipe plugs or treated protectors. Socket weld connections shall be fitted with taped polyethylene caps or plugs. All end connections, including branch openings shall be protected with a plastic sheet, wired or taped securely to the spool to prevent entry or dirt or moisture into the spool. 5.1.4 Stainless Steel Components

In order to minimise the possibility of stress cracking, all stainless steel valves, spools, pipe and connections shall be stored out of contact with the ground and properly sheltered from rain. Closures should be examined to ensure moisture cannot enter this material. All austenitic stainless steel subject to welding or mechanical abrasion shall be passivated to reinstate the protective oxide layer. Stainless steel piping subject to annealing or heat treatment shall be pickled in an acid/water solution comprising nitric and hydrofluoric acid to remove oxide scale.

6.
6.1

ERECTION
IDENTIFICATION

All materials issued by Principal or supplied by the Contractor shall be identified in accordance with the respective piping class/piping material specification, and shall be stored and handled in such a manner as to assure proper identification.

6.2

STORAGE AND HANDLING

All fabricated pipe and equipment shall be stored off the ground until finally installed.

Version No. 12.0

Page 19 of 26

Document last modified: 19 December 2012. PDF created: 23 April 2013.

Fabrication and Installation of Piping ES-14-602-01

Care shall be exercised, in the storage and handling of all piping materials and pre-fabricated assemblies, so that contamination by grease, moisture or other foreign matter does not occur. End seals of pipe, flange covers, valve covers, and similar protections shall not be removed until necessary for fabrication or erection. The Contractor shall ensure that all piping is protected, as per Section 4.4 at all times. All care shall be taken when pipe sections are moved from one place to another to avoid bending or over-straining.

6.3

ASSEMBLY/INSTALLATION

All piping shall be installed in accordance with the latest revision of the Piping drawings as per Section 3.2. All assembled piping shall be installed without springing or forcing. Cutting or other weakening of structural members to facilitate piping installation shall not be permitted. All piping shall be installed to permit free expansion and contraction without damage to joints or supports. A visual inspection of all pipe and pipe spools shall be made to ensure they are free of all internal loose rust, scale, soil and debris before assembly. A straight run of pipe shall contain the minimum number of welds. The use of off-cuts in straight piping runs shall be avoided wherever possible. Special precautions shall be taken during carbon steel piping erection in close vicinity of stainless steel piping as direct contact between carbon steel and stainless steel is not permitted. Carbon steel slings, etc, shall not be used during fabrication and installation of stainless steels. Stainless steel piping shall be covered up with tarpaulins or similar where carbon steel piping is being erected or worked on such that, stainless steel cannot come in contact with carbon steel. Neither shall stainless steel or non-ferrous materials be contaminated with grinding or welding particles. Tools shall be identified for stainless steel work only. All stainless steel piping and fittings shall be stored away from areas where carbon steel is being worked on. All materials used for assembly and erection must conform to the appropriate Piping Class Specification in CSBP Engineering Standard Piping Material Specifications (ES-14-603-01). Hydrotest vents and drains shall be installed in accordance with the Piping GAs and Isometrics. The Contractor shall install any additional vents and drains required for testing purposes.

6.4

FLANGED CONNECTIONS

Precautions shall be taken throughout fabrication and erection to protect the gasket face of flanges. Flanges repaired by grinding will be rejected. Flanged connections shall be assembled with new gaskets and stud bolts as specified in the CSBP Engineering Standard Piping Material Specifications (ES-14-603-01). Bolts shall show at least one, but no more than three threads beyond the nuts after assembly.

Version No. 12.0

Page 20 of 26

Document last modified: 19 December 2012. PDF created: 23 April 2013.

Fabrication and Installation of Piping ES-14-602-01

Gaskets shall be centred on the flange faces and shall not project into the bore. Gaskets with correct inside diameter shall be used on slip on flanges. The clearance between flange faces shall permit the connection to be gasketed and bolted without imposing undue strain on the piping system. Flanged piping connections to vessels or equipment shall be correctly aligned before bolting up. 6.4.1 Protection from Leaking Flanges

In the event of a flange leak, to prevent personnel being sprayed from substances that are hazardous because of their chemical and or physical properties, flange protection shall be provided at locations where: there is a high level of Operator interface, flanges are adjacent to walkways or designated accessways, directed by the Superintendent or the applicable business unit Process/Maintenance Manager. Hazardous substances requiring flange protection are: All acids Sodium Hydroxide (Caustic Soda) Ammonium Nitrate Sodium Cyanide Solution, and Other fluids, as specified by the Superintendent or the applicable business unit Process or Maintenance Manager.

The type of flange protection to be used shall be specified by the Superintendent or the applicable business unit Process/Maintenance Manager. Typically this will be in the form of either: a. or b. Wrapping of the flange joint with Herculite. The material is to overlap itself and extend over the pipe with sufficient material so that is can be securely held in place with 3mm Terylene rope or another Superintendent approved method. A ring of stainless steel cladding that is securely held in place with stainless steel banding straps. A drainage/vent hole shall be provided in the underside of the flange guard.

6.5

BOLTING

Prior to installation, all bolting shall be lubricated with an approved anti-seize compound. Protective grease shall be removed from flange gasket faces prior to bolt-up. Flange faces shall be parallel and aligned in horizontal and vertical planes. Non-uniform bolt loading will be rejected. Dirt at the mating surfaces shall be removed and scratched surfaces shall be repaired. Flange stud bolts shall be tightened evenly and sequentially to impose equal pressure on gaskets to avoid distortion or over stressing. Hydraulically operated tensioning equipment shall be used on stud bolts 1 diameter (M33) or over. These stud bolts shall be supplied one diameter overlength to allow for bolt tensioning equipment.

Version No. 12.0

Page 21 of 26

Document last modified: 19 December 2012. PDF created: 23 April 2013.

Fabrication and Installation of Piping ES-14-602-01

Insulating flange kits shall be installed between mating carbon steel and stainless steel piping. Gasket compound shall not be used.

6.6

CONNECTION TO EQUIPMENT

Piping connections to equipment shall be installed such that no stresses shall be transferred from the piping system to the equipment at the time of installation.

6.7

THREADED JOINTS

Back welding of threaded joints is not permitted unless specified on design drawings or approved by the Superintendent. It is recommended that back welded threaded connections be replaced with socket weld connections if possible. Backing off of made-up threaded joints to facilitate fit-up or alignment is not permitted. Joints shall be made using approved sealing tape and care taken to avoid over tightening.

6.8

TEMPORARY STRAINERS

Temporary strainers must be installed in the suction piping to all pumps, compressors and other places as indicated on drawings. Break-out spools shall be installed as required for easy removal of strainers.

6.9

VALVE INSTALLATION

Valves shall be installed as indicated on the GAs and Isometrics and in accordance with CSBP Engineering Standard Basis for Design - Piping (ES-14-601-01). Should valve orientation not be detailed the following guidelines should be used: a. b. Valves shall be installed so that their handwheels or handles are accessible and can be operated between full open and full closed positions without obstructions. Valve location and orientation shall be such that a person can operate the valve handwheel or handle from a safe position and in a comfortable posture. Extensions or chain wheels shall be provided if required. Valves in horizontal lines, with the exception of block valves at pressure relief valves, shall be installed with valve stems oriented as follows, in order of preference: 1. 2. 3. d. Vertically upwards Horizontally Upwards at 45

c.

Gate valves installed upstream and or downstream of pressure relief valves shall be installed with the valve spindle oriented horizontally or downwards, to prevent blockage of the line by a disconnected gate in the valve.

Version No. 12.0

Page 22 of 26

Document last modified: 19 December 2012. PDF created: 23 April 2013.

Fabrication and Installation of Piping ES-14-602-01

6.10

UNDERGROUND PIPING

Fabrication, laying, corrosion protection, inspection and testing of underground piping shall be in accordance with the CSBP Engineering Standard Underground Piping (ES-14-602-05).

6.11

INSTALLATION OF EXPANSION JOINTS

Specific instructions for installing expansion joints shall be included in the Project documentation, however the following general guidance apply: a. b. c. Expansion joints shall be the final unit(s) installed in any piping systems. Before installation of any expansion joint, all piping shall be accurately aligned without restraints and properly anchored. The space allowed in the piping for insertion of an expansion joint shall be equal to the insertion dimension specified on drawings (plus or minus 1.5mm), including cold springing, if specified. Spacer bars supplied by the manufacturer for shipping purposes shall not be adjusted or removed from expansion joints until after joints are in place. Shipping spacer bars must be removed before testing. No adjustment shall be made to tie rods provided by the manufacturer to control alignment and end thrust; these tie rods shall remain part of the unit. No attempt shall be made to correct misalignment of piping, caused by incorrect installation of the piping or its associated equipment, by modification to any device provided to control expansion, or the method in which that device is designed to be installed. Such misalignment must be corrected by other means which will in no way affect the workability of the expansion device.

d. e. f. g.

6.12

TESTING OF PIPEWORK
Pressure testing of pipework shall be carried out in accordance with CSBP Engineering Standard Inspection and Testing of Piping Systems (ES-14-602-02).

7.
7.1

PIPE SUPPORTS
STANDARD PIPE SUPPORTS

All pipework shall be supported in accordance with the Code. Support locations, type and serial number will be shown on the piping drawings. Refer to Section 3.2. Unless otherwise indicated on piping drawings, no pipe shall be supported from another pipe.

Version No. 12.0

Page 23 of 26

Document last modified: 19 December 2012. PDF created: 23 April 2013.

Fabrication and Installation of Piping ES-14-602-01

7.2
7.2.1

SPRING HANGERS
General

Spring hangers, as required, shall be supplied by the Contractor and shall be installed as indicated on piping drawings. 7.2.2 Constant Support Hangers

Installation instructions are as follows: a. b. c. d. e. f. Securely attach the hanger to the structure at a point where the load coupling is directly over the desired point of attachment. Make certain that the moving parts of the hanger will be unobstructed. Make certain that the rod has enough thread engagement before taking up the load. Turn the load coupling until the travel stop is free. Prior to the final start-up/commissioning, the travel stops shall be removed After the line is in operation, check the hanger for indicated hot position. If necessary, make the adjustment by turning the load coupling to bring the indicator to the required position. No other adjustment is normally required, since the load as calibrated at the factory is equal to the load that has to be supported. Variable Support Hangers

7.2.3

The installation instructions shall be as follows: Securely attach the hanger to the structure. Turn the turnbuckle until the Variable Spring Hanger or load column of the spring support respectively reaches the desire cold load marking. No other adjustment is necessary. The travel stops shall be removed before the piping is put into operation

8.

AS-BUILT DATA AND RECORDS

On completion of the work, the Contractor shall supply to the Superintendent, as a properly indexed and compiled package, full details of the Welder Qualified records, fabrication records and as-built data. This package shall be compiled in accordance with CSBP Engineering Standard Inspection and Testing of Piping Systems (ES-14-602-02).

Version No. 12.0

Page 24 of 26

Document last modified: 19 December 2012. PDF created: 23 April 2013.

Fabrication and Installation of Piping ES-14-602-01

APPENDIX 1 - TYPICAL PROCEDURE QUALIFICATION RECORD (PQR)


PURCHASE ORDER No: PROCESS: MANUAL/AUTO/SEMI-AUTO DATE WELDED JOINT: PQR No: WPS No: MATERIAL SPEC: HEAT No: SERIAL No: THICKNESS: DIAMETER: ELECTRODE/WIRE: TYPE: BATCH No: WELDING PROCESS: WELDING POSITION: ELECTRODE STICKOUT: MAX. BEAD WIDTH: INTERPASS CLEANING: PREHEAT TEMP: PREHEAT METHOD: TRAVEL HEAT INTERPAS ELECTRODE/WIRE GAS SPEED INPUT S MM/MIN KJ/MM TEMP C NAME SIZE FLOW MM RATE L/MIN

GROOVE ANGLE: ROOT FACE: ROOT GAP: PASS PROCES No S

POLARIT Y

AMPS A

VOLTS V

MAXIMUM THICKNESS OF DEPOSITED WELD FOR EACH PROCESS: GAS

TUNGSTEN METAL AND SIZE:

TYPE

PERCENTAGE COMPOSITION (MIXTURE)

GAS CUP SIZES: POSTWELD HEAT TREATMENT: TEMPERATURE TIME: OTHER:

GAS(ES) SHIELDIN G: TRAILING: BACKING: VERIFIED BY VENDOR QC NAME: SIGNATURE: CSBP INSPECTOR DATE: NAME: SIGNATURE:

DATE:

Version No. 12.0

Page 25 of 26

Document last modified: 19 December 2012. PDF created: 23 April 2013.

Fabrication and Installation of Piping ES-14-602-01

APPENDIX 2 - TYPICAL WELDING PROCEDURE SPECIFICATION (WPS)


VENDOR: PURCHASE ORDER No: EQUIPMENT DESCRIPTION: APPLICATION OF WPS: STANDARD PREPARATION: WELD TYPICAL WELD SEQUENCE: WPS No: REV: PQR No: DATE: PAGE OF

MATERIAL SPECIFICATION: THICKNESS RANGE: BASE METAL: DIAMETER RANGE: POSITION: PROGRESSION CONSUMABLE: TREATMENT: EDGE PREP METHOD: PREHEAT TEMP:

REFER ATTACHED SHEETS No OF PASSES MAY VERY FOR ACCORDING TO THICKNESS/ VARIATIONS: POSITION

PREHEAT METHOD:

RETENTION TIME: TEMP CHECK METHOD: MAX INTERPASS TEMP: GOUGE METHOD: GOUGE CHECK METHOD:

MAXIMUM THICKNESS OF DEPOSITED WELD METAL FOR INTERPASS CLEANING: EACH PROCESS: TACKING METHOD: WELD FINISH: PASS No.. PROCES S +AMP RANGE VOLT RANGE TRAVEL RANGE MM/MIN MAXIMUM BEAD WIDTH: ELECTRODE STICK OUT: SIZE MM FLUX/GAS TRADE NAME SPEC/FLOWRATE

PROCESS: AWS SPEC: AWS CLASS: A No: F No: PWHT REQUIRED: GOVERNING CODES CONSUMABLE TRADE NAMES:

TUNGSTEN TYPE & SIZE: GAS CUP SIZES: BACKING: GAS: FOR VENDOR PREPARED BY: APPROVED BY: DATE: DATE: TYPE: RATE: DURATION

Version No. 12.0

Page 26 of 26

Document last modified: 19 December 2012. PDF created: 23 April 2013.