You are on page 1of 2

RENCANA ANGGARAN BIAYA

PROGRAM
KEGIATAN
PEKERJAAN
TAHUN

: PENINGKATAN KESEMPATAN KERJA PADA DINAS SOSIAL


TENAGA KERJA DAN TRANSMIGRASI KABUPATEN KLUNGKUNG
: PENERAPAN TENAGA KERJA DENGAN POLA PADAT KARYA
: PEMBUKAAN DAN PELEBARAN JALAN DUSUN SOMPANG
DESA BUNGA MEKAR
:
2013

No.

URAIAN

1
2
3
4
5
6
7
8

Semen PC 50 Kg.
Pasir Pasang
Batu Gunung Lokal
Pasir Beton
Batu Pecah 1-2
Besi Beton
Kayu Perancah
Paku

VOLUME

1,418.80
115.97
463.87
0.75
1.05
226.80
0.19
4.74

SAT.

HARGA
SATUAN
( Rp. )

Sak.
M
M
M
M
Kg
M
Kg

73,000.00
262,150.00
135,000.00
244,250.00
292,500.00
8,808.00
3,400,000.00
14,000.00

JUMLAH
TOTAL
( Rp. )
103,572,750.40
30,400,880.13
62,622,450.00
183,187.50
307,125.00
1,997,654.40
660,960.00
66,292.58
199,811,300.00

No.

URAIAN

1
2
3
4
5
6
7
8

Semen PC 50 Kg.
Pasir Pasang
Batu Gunung Lokal
Pasir Beton
Batu Pecah 1-2
Besi Beton
Kayu Perancah
Paku

VOLUME

1,313.00
107.25
429.50
0.75
1.00
226.80
0.22
6.50

SAT.

HARGA
SATUAN
( Rp. )

Sak.
M
M
M
M
Kg
M
Kg

80,000.00
306,250.00
135,000.00
294,600.00
350,000.00
8,809.00
3,400,000.00
14,000.00

JUMLAH
TOTAL
( Rp. )
105,040,000.00
32,845,312.50
57,982,500.00
220,950.00
350,000.00
1,997,881.20
739,702.69
90,953.61
199,267,300.00

2,097,200

14.4959375

1,954,000

0.09375

0.0096

1,313.00
107.25
429.50
0.75
1.00
226.80
0.22
6.50

20.25

13.41