Material Cost
Cement mortar (1:3)
1 meter cube cement = 28 bag x RM16.00 = RM448.00
3 meter cube sand = 3 meter cube x RM54.72 = RM164.16
RM612.16
Add 1/3 for wastage and shrinkage = RM204.05
Cost for 4 meter cube = RM816.21
Cost for 1 meter cube = RM204.05
Mortar Cost
General worker = 2hour x RM60.00/8 = RM15.00
Mortar cost 25mm thk/ meter sq. = (RM15.00+204.05) X 25 = RM5.48
1000
Labour Cost
General worker = 0.30 x RM60.00/8 = RM2.25
Skilled worker = 0.30 x RM113.33/8 = RM 4.25
RM11.98
Add 10% profit & O.H = RM1.20
RM13.18/m2
CEMENT AND SAND SCREED (to receive ceramic tiles(1:3))
Material cost
Tile = 12 piece x RM3.67 = RM44.04
5% wastage = RM2.20
RM46.24
Cement concentrated
1m3 cement = 28 bags x RM16.00 =RM448.00
5% wastage =RM22.40
=RM470.40
Labour cost
Mixer:
General worker = 2hour x RM60.00/8 =RM15.00
Material cost
Tile = 3 piece x RM16.06 = RM48.18
5% wastage = RM2.41
RM50.59
Cement concentrated
1m3 cement = 28 bags x RM16.00 =RM448.00
5% wastage =RM22.40
=RM470.40
Labour cost
Mixer:
General worker = 2hour x RM60.00/8 =RM15.00
Material cost
Tile = 3 piece x RM17.67 = RM53.01
5% wastage = RM2.65
RM55.66
Cement concentrated
1m3 cement = 28 bags x RM16.00 =RM448.00
5% wastage =RM22.40
=RM470.40
Labour cost
Mixer:
General worker = 2hour x RM60.00/8 =RM15.00
Material cost
Tile = 12 piece x RM3.71 = RM44.52
5% wastage = RM2.23
RM46.75
Cement concentrated
1m3 cement = 28 bags x RM16.00 =RM448.00
5% wastage =RM22.40
=RM470.40
Labour cost
Mixer:
General worker = 2hour x RM60.00/8 =RM15.00
Material cost
Tile = 12 piece x RM2.28 = RM27.36
5% wastage = RM1.37
RM28.73
Cement concentrated
1m3 cement = 28 bags x RM16.00 =RM448.00
5% wastage =RM22.40
=RM470.40
Labour cost
Mixer:
General worker = 2hour x RM60.00/8 =RM15.00
Material Cost
Timber (including overlapping) = 11.36m x RM4.50 = RM51.12
Add 10% for wastage = RM5.11
Nail = 0.55kg x RM4.50 = RM2.48
= RM58.71
Labour cost
Carpenter = RM60.00/ 8 x 0.65 hour = RM4.88
Add 10% profit and O.H = RM6.36
Rate RM69.95/m2