FLOOR FINISHES

CEMENT AND SAND PAVING (Hand Mixed)

Cement = RM16.00/ bag (50kg)


Sand = RM38.00/ 1 tonne
= RM38.00 X 1.44 = RM54.72/ meter cube

Material Cost
Cement mortar (1:3)
1 meter cube cement = 28 bag x RM16.00 = RM448.00
3 meter cube sand = 3 meter cube x RM54.72 = RM164.16
RM612.16
Add 1/3 for wastage and shrinkage = RM204.05
Cost for 4 meter cube = RM816.21
Cost for 1 meter cube = RM204.05

Mortar Cost
General worker = 2hour x RM60.00/8 = RM15.00
Mortar cost 25mm thk/ meter sq. = (RM15.00+204.05) X 25 = RM5.48
1000

Labour Cost
General worker = 0.30 x RM60.00/8 = RM2.25
Skilled worker = 0.30 x RM113.33/8 = RM 4.25
RM11.98
Add 10% profit & O.H = RM1.20
RM13.18/m2
CEMENT AND SAND SCREED (to receive ceramic tiles(1:3))

Mortar Cost/ meter cube = RM204.05


Mortar Cost 20mm thk/ meter sq. = RM204.05 x 20 = RM 4.08
1000
Labour cost
Skilled worker = 0.25 x RM113.33/8 = RM 3.54
General worker = 0.25 x RM60.00/8 = RM 1.88
RM 9.50
Add 10 % profit and O.H = RM 0.95
RM10.45/m2

CEMENT AND SAND SKIRTING (1:3)

Mortar cost / m3 = RM204.05


Mortar cost
25mm thk/m2 = RM204.05 x 25 = RM5.10
1000
25mm thk x 100mm high = RM5.10 X 100 = RM0.51
1000
Labour cost
Skilled worker = 0.38 (hour) x RM113.33/8 = RM5.38
General worker = 0.38 (hour) x RM60.00/8 = RM2.85
RM8.74
Add 10% profit and O.H =RM0.87
RM9.61/m2
Porcelain Tiles (0.3m x 0.3m) – HGN30773
RM3.67/piece

Material cost
Tile = 12 piece x RM3.67 = RM44.04
5% wastage = RM2.20
RM46.24

Cement concentrated
1m3 cement = 28 bags x RM16.00 =RM448.00
5% wastage =RM22.40
=RM470.40

Labour cost
Mixer:
General worker = 2hour x RM60.00/8 =RM15.00

Cost cement concentrated/m3


0.02 m3 concentrated cement = RM470.40 x 0.02 m3 =RM9.41

Fix tile to floor:


General worker = 0.75 hour x RM60.00/8 =RM5.63
Skill worker = 0.75 hour x RM113.33/8 =RM10.62
RM86.90
Add 10% profit and O.H = RM8.69
RM95.59/m2
Porcelain Tiles (0.6m x 0.6m) – H60019
RM16.06/piece

Material cost
Tile = 3 piece x RM16.06 = RM48.18
5% wastage = RM2.41
RM50.59

Cement concentrated
1m3 cement = 28 bags x RM16.00 =RM448.00
5% wastage =RM22.40
=RM470.40

Labour cost
Mixer:
General worker = 2hour x RM60.00/8 =RM15.00

Cost cement concentrated/m3


0.02 m3 concentrated cement = RM470.40 x 0.02 m3 =RM9.41

Fix tile to floor:


General worker = 0.75 hour x RM60.00/8 =RM5.63
Skill worker = 0.75 hour x RM113.33/8 =RM10.62
RM91.25
Add 10% profit and O.H = RM9.13
RM100.38/m2
Porcelain Tiles (0.6m x 0.6m) – H60014
RM17.67/piece

Material cost
Tile = 3 piece x RM17.67 = RM53.01
5% wastage = RM2.65
RM55.66

Cement concentrated
1m3 cement = 28 bags x RM16.00 =RM448.00
5% wastage =RM22.40
=RM470.40

Labour cost
Mixer:
General worker = 2hour x RM60.00/8 =RM15.00

Cost cement concentrated/m3


0.02 m3 concentrated cement = RM470.40 x 0.02 m3 =RM9.41

Fix tile to floor:


General worker = 0.75 hour x RM60.00/8 =RM5.63
Skill worker = 0.75 hour x RM113.33/8 =RM10.62
RM96.32
Add 10% profit and O.H = RM9.63
RM105.95/m2
Homogeneous Tiles (0.3m x 0.3m) – H30230
RM3.71/piece

Material cost
Tile = 12 piece x RM3.71 = RM44.52
5% wastage = RM2.23
RM46.75

Cement concentrated
1m3 cement = 28 bags x RM16.00 =RM448.00
5% wastage =RM22.40
=RM470.40

Labour cost
Mixer:
General worker = 2hour x RM60.00/8 =RM15.00

Cost cement concentrated/m3


0.02 m3 concentrated cement = RM470.40 x 0.02 m3 =RM9.41

Fix tile to floor:


General worker = 0.75 hour x RM60.00/8 =RM5.63
Skill worker = 0.75 hour x RM113.33/8 =RM10.62
RM87.41
Add 10% profit and O.H = RM8.74
RM96.15/m2
Porcelain Tiles (0.3m x 0.3m) – HIT30140
RM2.28/piece

Material cost
Tile = 12 piece x RM2.28 = RM27.36
5% wastage = RM1.37
RM28.73

Cement concentrated
1m3 cement = 28 bags x RM16.00 =RM448.00
5% wastage =RM22.40
=RM470.40

Labour cost
Mixer:
General worker = 2hour x RM60.00/8 =RM15.00

Cost cement concentrated/m3


0.02 m3 concentrated cement = RM470.40 x 0.02 m3 =RM9.41

Fix tile to floor:


General worker = 0.75 hour x RM60.00/8 =RM5.63
Skill worker = 0.75 hour x RM113.33/8 =RM10.62
RM69.39
Add 10% profit and O.H = RM6.94
RM76.33/m2
TIMBER AND WOODWORKS

Timber board cost (100mm x 25mm) = RM4.50/m


Nail cost: RM4.50/kg
Nail required for 1m2 of timber flooring = 0.55kg
Labour output for 1m2 of timber flooring = 0.65 hour
Tongue of board = 12mm

Material Cost
Timber (including overlapping) = 11.36m x RM4.50 = RM51.12
Add 10% for wastage = RM5.11
Nail = 0.55kg x RM4.50 = RM2.48
= RM58.71

Labour cost
Carpenter = RM60.00/ 8 x 0.65 hour = RM4.88
Add 10% profit and O.H = RM6.36
Rate RM69.95/m2