You are on page 1of 44

Project Goals

• Create a new Ardmore Transit Center with substantial private investment in


residential, retail and mixed-used development
• Revitalize Ardmore Business and Historic District into a transit-oriented,
pedestrian-friendly and accessible urban village
• Provide new parking for visitors, customers, businesses and employees
• Provide 190 new parking spaces (300 total) for SEPTA and Amtrak
commuters
• Comply with M.U.S.T. ordinance
• Construct project that enhances and preserves surrounding assets
• Minimize disruption to businesses, pedestrians and commuters during
construction
• Improve vehicular traffic infrastructure
• Complete Ardmore Station project in a timely manner
Aerial View
Street Perspective
Train Station Entrance
Main Street
Ardmore Train Platform
Parking Plan Options
Original Plan - Main Street
Updated Ardmore Station
Summary of Parking Options
• Option 1: • Option 3:
– Smallest Main Street Garage (7 – Shorter Main Street Garage (7
levels) levels)
– Keep PSB Addition – Demolish/Upgrade PSB Addition
– Large Bernicker Garage (5 levels) – Small Bernicker Garage (3 levels)

• Option 2: • Option 3A:


– Largest Main Street Garage (8 – Shorter Main Street Garage (7
levels) levels
– Demolish/Upgrade PSB Addition – Overbuild PSB Addition – requires
– No Bernicker Garage temporary relocation
– Small Bernicker Garage (3 levels)
• Option 2A:
– Largest Main Street Garage (8
levels)
– Overbuild PSB Addition – requires
temporary relocation
– No Bernicker Garage
Option 1 Components

• Smallest Main Street Garage

• Keeps Public Safety Building Addition

• Large Bernicker Garage


Option 1 – Main Street

Total Spaces: 296


Total Levels: 7
Option 1- Main Street
Option 1- Bernicker Lot

Total Spaces: 277


Total Levels: 5
Option 1- Bernicker Lot
Option 1- Pros & Cons
Pros Cons
• Additional retail on Lancaster • Commuter parking only on Main
Street - all other parking on
Avenue Bernicker
• Lower Merion employee and • Tall, less efficient garage (7
business parking is separate from levels/4 parking rows per level)
commuter parking • Large garage (5 levels) at
• Minimally disruptive to PSB Bernicker is out of scale
Addition • Building two garages is more
expensive
• Building two garages at once is
more disruptive
• Doesn’t put most new parking next
to the station
• 6 fewer new spaces than Option 2
Option 1 – Parking Costs

• Gross Parking Spaces: 573

• Net Parking Spaces: 313

• Total Parking Cost: $18.9 M

• Cost Per Net Space: $60 K


Option 2 Components

• Largest Main Street Garage

• Demolish Public Safety Building Addition

• No Bernicker Garage
Option 2

Total Spaces: 501


Total Levels: 8
Option 2 – Parking Tiers
Option 2 – Pros & Cons
Pros Cons
• Adds 4th row of parking per garage
• Tallest option for Main Street garage
level resulting in the most efficient and
(8 levels)
least cost option
• Programmatic functions in PSB
• Provides most net new parking
Addition (jail, evidence storage, sally
• Improved access to the PSB
port) to be temporarily relocated during
• Better program, more space for PSB
construction
• Meets the SEPTA commuter
requirement
• Preserves future opportunity for
Bernicker lot
• Puts the most spots adjacent to the
station and local businesses
Option 2 – Parking Costs

• Gross Parking Spaces: 501

• Net Parking Spaces: 319

• Total Parking Cost: $17.6 M

• Cost Per Net Space: $54.8 K


Option 2A Components

• Same size and height as Option 2

• Overbuild Public Safety Building Addition

• No Bernicker Garage
Option 2A

Total Spaces: 456


Total Levels: 8
Option 2A – Parking Tiers
Option 2A – Pros & Cons
Pros Cons
• Adds 4th row of parking per garage • More costly than Option 2
level resulting in the most efficient and
• Programmatic functions in PSB
least cost option
Addition (jail, evidence storage, sally
• PSB Addition remains
port) still has to be temporarily
• Improved access to the PSB relocated during construction
• Meets the SEPTA commuter parking
• 44 fewer spaces than Option 2
requirement
• No added space for PSB
• Preserves future opportunity for
Bernicker lot
• Majority of parking spaces located
adjacent to the station and local
businesses
Option 2A – Parking Costs

• Gross Parking Spaces: 503

• Net Parking Spaces: 275

• Total Parking Cost: $17.5 M

• Cost Per Net Space: $64 K


Option 3 Components

• Shorter Main Street Garage

• Demolish Public Safety Building Addition

• Small Bernicker Garage


Option 3 – Main Street

Total Spaces: 416


Total Levels: 7
Option 3 – Main Street
Option 3 – Bernicker Lot

Total Spaces: 145


Total Levels: 3
Option 3 – Pros & Cons
Pros Cons
• Height of Main Street garage • Building two garages increases
cost
decreases by one level
• Building two garages at once will
• Creates retail space on the be more disruptive
Bernicker lot • Programmatic functions in PSB
Addition (jail, evidence storage,
sally port) to be temporarily
relocated during construction
• Bernicker land redevelopment
potential is lost to relatively small
garage and retail space
• Takes surface parking from two
lots
• 18 fewer spaces than Option 2
Option 3 – Parking Costs

• Gross Parking Spaces: 561

• Net Parking Spaces: 301

• Total Parking Cost: $20.3 M

• Cost Per Net Space: $66.8 K


Option 3A Components

• Shorter Main Street Garage

• Overbuild Public Safety Building Addition

• Small Bernicker Garage


Option 3A – Main Street

Total Spaces: 372


Total Levels: 7
Option 3A – Main Street
Option 3A – Bernicker Lot

Total Spaces: 145


Total Levels: 3
Option 3A – Pros & Cons
Pros Cons
• Height of Main Street Garage • More costly than Option 3
decreases by one level • Building two garages increases
• PSB Addition does not get costs
demolished • Building two garages at once will
be more disruptive
• Creates retail space on the • Programmatic functions in PSB
Bernicker lot Addition (jail, evidence storage,
sally port) still has to be
temporarily relocated during
construction
• 44 fewer spaces than Option 3
and 63 fewer spaces than
Option 2
• Bernicker land is lost
• Takes surface parking from all lots
Option 3A – Parking Costs

• Gross Parking Spaces: 517

• Net Parking Spaces: 257

• Total Parking Cost: $19.9 M

• Cost Per Net Space: $77.4 K


Summary of Parking Options
• Option 1: • Option 3:
– Smallest Main Street Garage – Shorter Main Street Garage
– Keep PSB Addition – Demolish PSB Addition
– Large Bernicker Garage – Small Bernicker Garage

• Option 2: • Option 3A:


– Largest Main Street Garage – Shorter Main Street Garage
– Demolish PSB Addition – Overbuild PSB Addition
– No Bernicker Garage – Small Bernicker Garage

• Option 2A:
– Largest Main Street Garage
– Overbuild PSB Addition
– No Bernicker Garage
Summary of Parking Costs
• Option 1: • Option 3:
– Net Parking Spaces: 313 – Net Parking Spaces: 301
– Total Parking Cost: $18.9 M – Total Parking Cost: $20.3 M
– Cost Per Net Space: $60 K – Cost Per Net Space: $66.8 K

• Option 2: • Option 3A:


– Net Parking Spaces: 319 – Net Parking Spaces: 257
– Total Parking Cost: $17.6 M – Total Parking Cost: $19.9 M
– Cost Per Net Space: $54.8 K – Cost Per Net Space: $77.4 K

• Option 2A:
– Net Parking Spaces: 275
– Total Parking Cost: $17.5 M
– Cost Per Net Space: $64 K
Critical Next Steps
• 15% Design Completion – July/August 2009. Timely decision needed to
secure additional funding and move project forward.

• Amtrak Agreement – July/August 2009

• Township/Dranoff Development Agreement – September 2009

• 45% Design, Engineering and Station Architecture – November/December


2009

• 90% Design Review – June 2010

• Goal to begin construction: Late 2010/Early 2011


Economic Revitalization Committee
June 10, 2009
• Seek public input and ideas

• Address questions

• Determine Option to recommend to


Board of Commissioners

You might also like