You are on page 1of 6

Appendix B: Building Systems Sequence of Operations - Template

The Building Systems Sequence of Operations outlines the as-operating sequence of operations for the HVAC and lighting control systems, as well as integration of the fire/life safety and HVAC systems if applicable. At a minimum, this document should describe in detail any sequence of operations that were revised during the retrocommissioning process. Note that it may be necessary to completely

document all of the as-operated sequences in order to satisfy LEED-EB Energy & Atmosphere prerequisite and credit requirements. As a side note, it may be necessary to update the as-built control drawings as well if significant
modifications or additions are made to the control system. However, that is beyond the scope of this document.

[BUILDING NAME] SEQUENCE OF OPERATION INDEX

[Insert a Table of Contents with links to each section heading] -

Ongoing Commissioning Plan Appendix B Sequence of Operation Template

AIR HANDLING SYSTEM DESCRIPTION AND CONTROL


[Brief System Description]

COLD-DECK AIR HANDLERS: [


[Brief System Description] Fan OFF condition [Sequence Description] Fan Start-up or Shut-down [Sequence Description] Return Fan Volume Control [Sequence Description] Discharge Air Temperature Controls [Sequence Description] Duct Static Pressure Controls [Sequence Description] Building Static Pressure Controls [Sequence Description] Warm-up Control [Sequence Description] Night Low Limit [Sequence Description] Night purge [Sequence Description] Alarms and Safeties [Sequence Description] Manual smoke pressurization system [Sequence Description]

] THROUGH [

DEDICATED VENTILATION AIR FANS: [


[Brief System Description] [Sequence Description]

] THROUGH [

Ongoing Commissioning Plan Appendix B Sequence of Operation Template

HOT DECK AIR HANDLERS: [


[Brief System Description] Fan OFF condition: [Sequence Description] Fan Start-up or Shut-down: [Sequence Description] Discharge Air Temperature Controls [Sequence Description] Static Pressure Controls [Sequence Description] Warm-up Control [Sequence Description] Night Low Limit [Sequence Description] Alarms and Safeties [Sequence Description]

] AND [

VAV BOX DESCRIPTION AND CONTROL


[Brief System Description]

STRATEGY FOR SPECIAL-AREA VAV BOXES


[Brief System Description] [Area X] is Occupied (during normal building operating hours) [Sequence Description] [Area X] is Unoccupied (during normal building operating hours) [Sequence Description] Building is Unoccupied [Sequence Description]

DUAL DUCT VAV BOXES


[Brief System Description]

Ongoing Commissioning Plan Appendix B Sequence of Operation Template

Occupied Condition [Sequence Description] Unoccupied Conditions [Sequence Description]

COOLING-ONLY VAV BOXES


[Brief System Description] Occupied Condition [Sequence Description] Unoccupied Conditions [Sequence Description]

CHILLED WATER SYSTEM DESCRIPTION AND CONTROL


[Brief System Description]

CHILLERS AND PRIMARY / SECONDARY PUMP CONTROL


[Brief System Description] EMCS Control Points [Points List] [Brief Description] Chilled water supply (CHWS) temperature reset strategy and schedule [Sequence Description] Chilled Water System Enable [Sequence Description] Chiller Staging [Sequence Description] Primary Chilled Water Pumps [Sequence Description] Secondary Chilled Water Pumps [Sequence Description]

Ongoing Commissioning Plan Appendix B Sequence of Operation Template

CONDENSING WATER AND COOLING TOWER CONTROL


[Brief System Description] Cooling Tower Operation [Sequence Description] Condenser Water Pumps for Chillers [Sequence Description] Condenser Water Pumps for the Heat Exchanger (cooling tower side) [Sequence Description] Distribution Water Pumps for the Heat Exchanger (Liebert side) [Sequence Description]

HEATING WATER SYSTEM DESCRIPTION AND CONTROL


[Brief System Description]

GENERAL SYSTEM CONTROL


[Brief System Description] System start-up [Sequence Description] System Shutdown [Sequence Description]

CONDENSING BOILER CONTROL


[Sequence Description]

NON-CONDENSING BOILER CONTROL


[Sequence Description]

DISTRIBUTION WATER LOOP CONTROL


[Sequence Description]

GENERAL CONTROL FEATURES


[Sequence Description]

Ongoing Commissioning Plan Appendix B Sequence of Operation Template

GARAGE EXHAUST FAN (EF-1) CONTROL


[Brief System Description] [Sequence Description]

GENERAL EXHAUST FAN CONTROL


[Brief System Description] [Sequence Description]

LIGHTING CONTROL
[Brief System Description] Lighting control for each zone-type is outlined below. Parking Area [Sequence Description] General Public and Jury Assembly Areas [Sequence Description] Office Spaces [Sequence Description] Mechanical Rooms [Sequence Description] Courtrooms Rooms and Judges Chambers [Sequence Description]

FIRE/LIFE SAFETY SYSTEM CONTROL


[Brief System Description and how the fire/life safety and HVAC systems should interact] [Sequence Description]

Ongoing Commissioning Plan Appendix B Sequence of Operation Template

You might also like