The service (s) that has potential for none or very few CMLs on circuit

1. 2.

Olefin Cold Side, Anhydrous Ammonia


Answer found API 570: 5.6.2

Term 2

Definition 2

Service (s) that Valves should be inspected for thermal fatigue

Cat Reformer
See API 570 section 5.10

Term 3

Definition 3

1.

Service(s) with reatively uniform


www.flashcardmachine.com/print/?topic_id=2599382

2.

Sulfidation, Sour Water


1/45

9/5/13

Printable Flash Cards

corrosion

Answer found API 570: 5.6.3

www.flashcardmachine.com/print/?topic_id=2599382

2/45

9/5/13

Printable Flash Cards

Term 4

Definition 4

JOC J= one who is autherized by the Jurisdiction


What class abbreviation is used to help define the API 570 Repair Organization

O= Owner/User who repairs thier


own equipment

C= Contractor that is acceptble to


Owner/User

Term 5

Definition 5 570: 3.1.79 Answer found in API

JUIC

J= Inspection Org. of the Jurisdiction What class abbreviation is used to help define the U = Owner/User who maintians API 570 Authorized Inspection Agency inspection Org. (AI's Employer) I = Inspection Org. of an Insurance Company C= Contractor employed by Owner Definition 6 /User Answer found in API 570: 3.1.6 The class abbreviation that is used to O= Owners Experience, help: P= Published Data, or Determine of corrosion Rate for New
www.flashcardmachine.com/print/?topic_id=2599382

Term 6

SOPI

S= Same or Similar Service,

3/45

9/5/13

Printable Flash Cards

Service or Change in Service is?

I= Inspection in 3 months
Answer found in API 570:7.1.2

www.flashcardmachine.com/print/?topic_id=2599382

4/45

9/5/13

Printable Flash Cards

Term 7

Definition 7

TIE
What is the Class Abbreviation to T= Testing I= Inspection help reminber the Primary Resonsiblities of API 570 E= Examination Authorized Inspector
Answer found in API 570: 4.3.4

Term 8

Definition 8

AIRRis the Class Abbreviation for?

API 570 Scope which is: A = Alteration, I = Inspection, R = Repair, R = Rerate.

Answer found in API 570: 1.1.1

Term 9

Definition 9

Min of a 1" Radius On repairs the minimum radius of an


www.flashcardmachine.com/print/?topic_id=2599382

Answer found
5/45

9/5/13

Printable Flash Cards

insert patch is

API 570: 8.1.4.2.c/ Fig C.2

www.flashcardmachine.com/print/?topic_id=2599382

6/45

9/5/13

Printable Flash Cards

Term 10

Definition 10

When performing NDE inspection what is the maximum diameter of the CML examination point for lines equal to or less than 10 NPS

max dia. of 2" Answer found API 570 : 3.1.20

Term 11

Definition 11

When performing NDE examinations of lines greater than 10 NPS what is the maximum diameter of the CML

Max dia. of 3" Answer found API 570 : 3.1.20

Term 12

Definition 12

For partially buried pipe What is the soil-to-air distance above the soil
www.flashcardmachine.com/print/?topic_id=2599382

6" above soil interace shall be considered


7/45

9/5/13

Printable Flash Cards

interface that is considered for corrosion

Answer found API 570:3.1.87

www.flashcardmachine.com/print/?topic_id=2599382

8/45

9/5/13

Printable Flash Cards

Term 13

Definition 13

What is the distance below the soil interface to dig when inspecting for soil-to-air corrosion

dig 6"-12" when inspection for soil-toair corrosion Answer found API 570: 7.4.5

Term 14

Definition 14

For partially buried pipe What is the soil-to-air distance below the soil interface that is to be considered for corrosion

12" below soil interface

Answer found API 570: 3.1.87

Term 15

Definition 15

At an Injection point curcuit what is the minimum 12" upsteam of the injection nozzle shall be examined minimum upsteam limit of a more
www.flashcardmachine.com/print/?topic_id=2599382 9/45

9/5/13

Printable Flash Cards

extensive examination. Answer found API 570: 5.5.9

www.flashcardmachine.com/print/?topic_id=2599382

10/45

9/5/13

Printable Flash Cards

Term 16

Definition 16

For underground piping what is the minimum length of buried pipe to expose when excavating for inspection

6 to 8 feet will need to be excavated for inspection Answer found API 570: 9.3.6

Term 17

Definition 17

Alteration is a Physical change in any component that has design implications.

Difine:

ALTERATION

Note: Comparable or duplicate replacements and the addition of small-bore attachments that do not require reinforcement or additional support are not considered an alteration Answer found in API 570: 3.1.2

Term 18

Definition 18

Define:
www.flashcardmachine.com/print/?topic_id=2599382

Restore to Suitable condiction for safe operation at designed condition


11/45

9/5/13

Printable Flash Cards

Repair

Answer found in API 570: 3.1.78

www.flashcardmachine.com/print/?topic_id=2599382

12/45

9/5/13

Printable Flash Cards

Term 19

Definition 19

Define:

Defect

Defect is difined as An Inperfection that exceeds acceptance criteria


Answer found in API 570: 3.1.17

Term 20

Definition 20

Define:

Inperfection

Discontinuity that may or may not exceed the acceptance criteria


Answer found in API 570: 3.1.30

Term 21

Definition 21

1. Probability of failure
www.flashcardmachine.com/print/?topic_id=2599382 13/45

9/5/13

Printable Flash Cards

RBI's two Primary factors are?

2. Consequence of failure Answer found in API 570:5.2

www.flashcardmachine.com/print/?topic_id=2599382

14/45

9/5/13

Printable Flash Cards

Term 22

Definition 22

Represent-ative
What word is used to define the number of CML's to obtain thickness readings during NDE inspection
Representative sampling should include data for all the various types of components and orientations found in each cicuit. Answer found in API 570: 6.5

Term 23

Definition 23

CML's that shall be measured during a Thickness NDE Inspections, are?

CMLs with the earliest renewal date as of the previous inspection


Answer found in API 570: 6.5

Term 24

Definition 24

Performance
Intervals for Pressure-relieving
www.flashcardmachine.com/print/?topic_id=2599382

The API 570 sec 6.7.3.1 states that PRD's shall be tested and inspected at
15/45

9/5/13

Printable Flash Cards

devices (PRD's) are determined by:

intervals that are frequent enough to verify that the valves perform reliably in the particular service conditions. Answer found in API 570: 6.7.3.1

www.flashcardmachine.com/print/?topic_id=2599382

16/45

9/5/13

Printable Flash Cards

Term 25

Definition 25

API 570 Piping Classification Inspection scheme in section 6.3.4 is based on:

Consequence of failure
See API 570 6.3.1

Term 26

Definition 26

Auto-Refigeration
Corrosion -Method by which process leaks can lead to brittle failure is
API 570 section 6.3.4.2.a

Term 27

Definition 27

Low Resistivity
Crrosion- Type of soil that is most
www.flashcardmachine.com/print/?topic_id=2599382 17/45

9/5/13

Printable Flash Cards

corrosive is soil with

Answer found in API 570 section 9.2.4

www.flashcardmachine.com/print/?topic_id=2599382

18/45

9/5/13

Printable Flash Cards

Term 28

Definition 28

Representative
Number of Repairs of new flange assemblies to be inspected during repairs and alterations is refered to as
API 570 section 5.12 States: The markings on a representative sample of newly installed fasteners and gaskets should be examined to determine whether they meet the material specification. Answer found API 570: 5.12
Term 29 Definition 29

What pipe size is RT preferred for thickness readings

1 NPS 570: 5.7.1

Term 30

Definition 30

What is the pipe size where UT thickness reading may require


www.flashcardmachine.com/print/?topic_id=2599382

2 NPS
19/45

9/5/13

Printable Flash Cards

specialized UT equipment

570 5.7.1

www.flashcardmachine.com/print/?topic_id=2599382

20/45

9/5/13

Printable Flash Cards

Term 31

Definition 31

The term small bore piping refers to piping that is

2 NPS 570 3.1.86

Term 32

Definition 32

What P-numbers allow the use of preheat in lieu of PWHT

P1 & P3 570: 8.2.3.2

Term 33

Definition 33

-1 For flanges, the thread engagement


www.flashcardmachine.com/print/?topic_id=2599382

570: 5.12
21/45

9/5/13

Printable Flash Cards

acceptance criteria is

B31.3:335.2.3

www.flashcardmachine.com/print/?topic_id=2599382

22/45

9/5/13

Printable Flash Cards

Term 34

Definition 34

What is the minimum # of thremocouples required when performing a local PWHT instead of a 360 degree band

2 570:8.2.3.3.d

Term 35

Definition 35

When performing an Internal Inspection on piping, What code should be followed ?

API 510
Pressure Vessel Inspection Code
Answer found API 570 5.5.1

Term 36

Definition 36

API 578
What recommended practice is used for
www.flashcardmachine.com/print/?topic_id=2599382

The Recommedned Pratice for:


23/45

9/5/13

Printable Flash Cards

Positive Meterial Indentification (PMI)

Material Verification Program for New and Existing Piping Systems


Answer can be found in API 570 sec 5.9

www.flashcardmachine.com/print/?topic_id=2599382

24/45

9/5/13

Printable Flash Cards

Term 37

Definition 37

API 579 What Standard is used for Fitness for Service (FFS)
Answer is found in API 570: 7.4

Term 38

Definition 38

What Recommended Practice covers Risk based Inspections

API 580

Answer found API 570: 5.2

Answer found in API 570: 5.2

Term 39

Definition 39

API 598 Which standard covers


www.flashcardmachine.com/print/?topic_id=2599382 25/45

9/5/13

Printable Flash Cards

Valve Inspection and Testing

Answer is found API 570: 5.10

www.flashcardmachine.com/print/?topic_id=2599382

26/45

9/5/13

Printable Flash Cards

Term 40

Definition 40

API 651 What is the Recommended Practice for Cathodic Protection

Cathodic Protection of aboveground Petroleum Storage Tanks Answer found in API 570: 9.3.5

Term 41

Definition 41

API 2201 Safe Hot Tapping Practices in the When Welding on In-Service Equipment Protroleum and Petrochemical Industries containing Flammbles, What Publication shall be followed? Answer found in
API 570: 8.2.1

Term 42

Definition 42

120F What is the minimum flash point temp


www.flashcardmachine.com/print/?topic_id=2599382 27/45

9/5/13

Printable Flash Cards

of hydrocorbons used for leak testing

Answer found API 570: 5.8.1

www.flashcardmachine.com/print/?topic_id=2599382

28/45

9/5/13

Printable Flash Cards

Term 43

Definition 43

At what temperature are special procedures needed for UT thickness readings

>150F Answer found API 570 5.7.1

Term 44

Definition 44

300F When welding, What minimum pre-heat temp is substituted for PWHT API 570: 8.2.3.2

Term 45

Definition 45

What is the minimum pre-heat temperature, when a local PWHT is


www.flashcardmachine.com/print/?topic_id=2599382

300F
29/45

9/5/13

Printable Flash Cards

substituted for a full encirclement PWHT

570: 8.2.3.3.c

www.flashcardmachine.com/print/?topic_id=2599382

30/45

9/5/13

Printable Flash Cards

Term 46

Definition 46

When developing a Inspection plan, at what operating temperature should a Corrosion Specialist be consulted

>750F 570:5.1.1.1

Term 47

Definition 47

What is the Minimum base metal temp during pressure testing when the wall thickness is 2" thick

(Minimum design metal temperature) MDMT + 10F

570:5.8.3

Term 48

Definition 48

What is the Minimum base metal temp during pressure testing when the wall
www.flashcardmachine.com/print/?topic_id=2599382

(Minimum design metal temperature) MDMT + 30F


31/45

9/5/13

Printable Flash Cards

thickness is > 2" thick 570:5.8.3

www.flashcardmachine.com/print/?topic_id=2599382

32/45

9/5/13

Printable Flash Cards

Term 49

Definition 49

Whats the minimum duration of a hydro test to evluate integrity of buried pipe

8 hr's 570: 9.3.7

Term 50

Definition 50

Whats the Maximum time for obtaining thickness reading when corrosion rate on new pipe is not known (no other data available)

3 months API 570: 7.1.2.c

Term 51

Definition 51

Whats the suggested interval for above-grade Visual surveillance of


www.flashcardmachine.com/print/?topic_id=2599382

6 months
33/45

9/5/13

Printable Flash Cards

buried pipe

570: 9.3.1

www.flashcardmachine.com/print/?topic_id=2599382

34/45

9/5/13

Printable Flash Cards

Term 52

Definition 52

What is the length of time a API 570 AI must recertify

3 years API 570 A.3.1

Term 53

Definition 53

What is the max thickness inspection interval for an injection point

Lesser 3yrs or 1/2 life

Term 54

Definition 54

What is the Max External Inspection interval for


www.flashcardmachine.com/print/?topic_id=2599382

5 Years
35/45

9/5/13

Printable Flash Cards

Class 1 & 2 Piping

API 570 6.7.3.2

www.flashcardmachine.com/print/?topic_id=2599382

36/45

9/5/13

Printable Flash Cards

Term 55

Definition 55

What is the Maximum Interval for Relief devices in fouling or corrosive service

5 years API 570: 6.7.3.2

Term 56

Definition 56

What is the suggested interval for closed-interval Potential Survey of buried pipe with poor CP

5 Years API 570: 9.3.2

Term 57

Definition 57

What the suggested interval fo evaluation of Soil Corrosivity for


www.flashcardmachine.com/print/?topic_id=2599382

5 years
37/45

9/5/13

Printable Flash Cards

buried pipe with no CP

API 570 9.3.4

www.flashcardmachine.com/print/?topic_id=2599382

38/45

9/5/13

Printable Flash Cards

Term 58

Definition 58

What is the max thickness inspection interval for Class 1 Piping

Lesser of 5 years or 1/2 life 570 table 2

Term 59

Definition 59

What is the maximum interval for Relief devices in non- fouling or no-corrosive srvice

10 years 570: 6.7.3.2

Term 60

Definition 60

Whats is the Maximum External


www.flashcardmachine.com/print/?topic_id=2599382

10 years
39/45

9/5/13

Printable Flash Cards

Inspection interval for Class 3 Piping

570: Table 2

www.flashcardmachine.com/print/?topic_id=2599382

40/45

9/5/13

Printable Flash Cards

Term 61

Definition 61

Whats the maximum Thickness Inspection interval for Class 3 piping

10 years 570: table 2

Term 62

Definition 62

What the maximum interval for RBI Reassessment

Per table 2 570: 5.2.4

Term 63

Definition 63

When should temporary welded


www.flashcardmachine.com/print/?topic_id=2599382

Next Opportunity
41/45

9/5/13

Printable Flash Cards

piping repairs be replaced

570: 8.1.4.1

www.flashcardmachine.com/print/?topic_id=2599382

42/45

9/5/13

Printable Flash Cards

Term 64

Definition 64

When shall non-welded repairs & temporary leak sealing devices be removed and pipe repaired

Next turnaround 570: 8.1.5

Term 65

Definition 65

What is the maximum size fillet weld patch on pipe repairs

Size of a the fillet weld patch should not exceed 1/2" the pipe diameter Answer found API 570: Fig C.2

Term 66

Definition 66

At an Injection point curcuit what is the 12" or 3 pipe dia. whichever is greater minimum upsteam limit that is to be
www.flashcardmachine.com/print/?topic_id=2599382 43/45

9/5/13

Printable Flash Cards

examined

Answer found API 570: 5.5.9

www.flashcardmachine.com/print/?topic_id=2599382

44/45

9/5/13

Printable Flash Cards

Term 67

Definition 67

At an Injection point curcuit what is the minimum downstream limit of a more extensive examination

10 pipe dia. downstream of the injection point

Term 68

Definition 68

What is the minimum downstream limit of an Injection point curcuit

Lesser of: 1st change in direction + 25' or 2nd change in direction API 570: 5.5.9