West Irving Library

Schematic Design Review

Supporting Goals 
#2 ‐ Nurture and Promote Vital, Vibrant Neighborhoods
#7 – Promote Excellence in Irving’s Cultural, Recreational and Educational Environments
#10 – Become a Successful Environmentally Sustainable Community 1
6.17.09
West Irving Library

Purpose: Acquire City Council Consensus of


the $8.0 Million Schematic Design for the
Northwest Library

¾ Objectives
¾ Site Analysis
¾ Schematic Site Plans
¾ Schematic Floor Plan
¾ Exterior Elevation
¾ Next Steps

2
6.17.09
West Irving Library

Project Objectives
¾ Enhance and expand library services in west and central
Irving area.
¾ Create a State-of-the-Art destination for residents.
¾ Achieve LEED Certification resulting in reduced utilities cost.
¾ Enhance the site by using native plants and public art.
¾ Integrate the interior spaces of the building and the site
enhancements through the use of glass to maximize views.
¾ House the Bookmobile for a more central service location.

3
6.17.09
West Irving Library
Site Analysis

R
ƒ NEW RESIDENTIAL
ƒ CONVENIENT TO
NEIGHBORHOODS

ƒ 32 Feet of Fall from SE


to the NW corner

ƒ 6.50 Acre Site = ƒ NEW FIRE STATION


283,140 SF ƒ TO W. T. HANES
(New Library Site) ELEMENTARY
and NORTHWEST
ƒ WATER TOWER R PARK RECRE.
R CENTER

ƒ OLD POLICE TRAINING


ƒ NEW RESIDENTIAL ACADEMY

ƒ ISLAMIC CENTER of IRVING

69.09

4
6.17.09
West Irving Library
Site Plan

SOLAR PANELS

SITE PLAN “POCKET PARKS” Main Entry


ƒ GATEWAY ENTRY ƒ RETENTION POND ƒ SCULPTURE Exterior drive-up
ƒ NATIVE PLANTS ƒ SCREEN / RETAINING WALLS ƒ OUTDOOR PLAZAS Book Drop
ƒ GATHERING AREAS ƒ VISUAL IMPACTS ƒ PEDESTRIAN PATHS
5
6.17.09
West Irving Library Native Stone
Special Amenities Walls

Photovoltaic
Panels

Public Art

Outside Reading
Areas

Retention
Pond
6.17.09 Outdoor Activity Spaces 6
West Irving Library
Floor Plan
TEEN’S CHILDREN’S
ADULT

MULTI-
PURPOSE
ROOM

QUIET
READING

COMPUTER
LAB
Main Entry
Exterior drive-up
Book Drop STAFF

FLOOR PLAN ƒ Multipurpose Meeting Room ƒ Children’s Collec. and Storytime ƒ Adult Collection
ƒ 25,000 SF ƒ Lobby / Vending Area ƒ Craft Room / Puppet Stage ƒ Quiet Reading
ƒ Interior Book Drop ƒ TEEN Area ƒ Study Rooms
ƒ Staff Work Area ƒ Computer Lab ƒ Business Center
7
6.17.09
West Irving Library
North Elevation

8
6.17.09
West Irving Library
West Elevation

9
6.17.09
West Irving Library

Next Steps
¾ Construction Documents complete October 13th
¾ Open Bids – Early November 2009
¾ Contract Award – Late November 2009
¾ Begin Construction – December 2009
¾ Grand Opening & Dedication – Early 2011

10