You are on page 1of 78

HBC 8D Process for Problem Solving

Finding and eliminating (forever) the root cause of a problem.

Course Duration: 4.0 hours

Training Materials For Reference Only

Slide 1

Course Objectives

At Completion YOU should: Understand HBCs 8D process Know when to use the 8D Process Be able to write an 8D Summary Report Be comfortable using typical problem solving tools Know how to get additional help/training
I hear...I forget I see...and I remember I do...and I understand Ancient Chinese Proverb

Training Materials For Reference Only

Slide 2

Agenda

Origin of HBCs 8D process Fit with:


Hawker Beechcraft Performance System (HBPS) Initiatives Existing processes

Overview of the 8 Steps


0 - Decide to use the HBC 8D Process 1 - Describe the Problem 2 - Assemble a Team 3 - Implement Interim Containment 4 - Find Root Cause 5 - Develop Corrective Action 6 - Implement Permanent Fix 7 - Prevent Recurrence 8 - Recognize the Team

Additional Information contacts, reference material


Training Materials For Reference Only Slide 3

Round Robin Introductions Your Name Where you work position/responsibilities Personal objectives for this course

Training Materials For Reference Only

Slide 4

Definitions
Root Cause: The very basic reason why, how, & when the condition occurred.
A Root Cause Mentality: An insatiable desire to understand why things go wrong, why people do what they do, and how things got into their present state. (C. Robert Nelms)
This takes persistence

Interim Containment Action: This is the action taken which should address and correct the actual nonconforming condition. Permanent Corrective Action: This should address the root cause of a nonconformance and prevent future occurrences of the problem which caused the nonconformance. Contributing Cause: This factor contributed to the problem, but it is not the root cause. Keep going to get to Root Cause. Verification: Making sure that something is going to work prior to implementation. Validation: Checking to make sure that the change is working (after implementation)
Training Materials For Reference Only Slide 5

More on Root Cause


Root Cause / Corrective Action (RCCA) is: A systematic approach to effectively identify the cause chain of a nonconformance and to permanently eliminate the source(s) of problems. Directed at reducing, and if possible eliminating, quality system escapes and the costs associated with poor quality.

Training Materials For Reference Only

Slide 6

Origin of HBCs 8D Process


8D (8 Disciplines) first standardized by the U.S. government during World War 2
Military Standard 1520: Corrective action and disposition system for nonconforming material

Popularized by Ford Motor Company in the 1960s and 1970s (called Global 8D or G8D) 8D now a standard in the Auto Industry 8D fills a void we currently have at HBC
We reference root cause (internally, with our suppliers and customers)
BUT, we dont provide a standard process to get to root cause

HBC 8D a Structured Process (and Tool Set) for Root Cause Corrective Action
Training Materials For Reference Only Slide 7

HBPS Initiative Positioning


Goal solve the problem
Smooth land (drain the lake, remove boulders) No leaks in the boats (rental income while lake is here)

Pick the best fit methodology


Drain the lake (remove waste) use LEAN Six Sigma Remove boulders (variation reduction) use Lean SIX SIGMA Leaks (immediate problems that must be fixed) use HBC 8D

Use the right tools for the job


Common tools will be used by all methodologies
This Analogy: Bucket can be used to empty the lake, remove rubble, and bail out the boat

In general, Lean Six Sigma projects take longer; 8D is for everyday, immediate problems.
Training Materials For Reference Only Slide 8

HBPS Initiative Positioning (alt. view)


Planning Control (During Production)

Sporadic Spike (Special Cause: HBC 8D)


40

Special cause (assignable) variation

Common cause (random) variation/waste (LEAN Six Sigma)

Significant Shift AND/OR Variation Reduction (Lean SIX SIGMA)

0 0

Time Lessons Learned

Training Materials For Reference Only

Slide 9

8D Process Fit
Policy & Procedures 12 0008 Corrective Action System

Quality Assurance Instruction (QAI) -- QAI 03-01-015 Corrective Action Response and Review Requirements

Corrective Action requests resulting from:


Nonconforming material Out of control processes Internal audits Supplier issues Customer complaints Operator self-verification process Other nonconformances in product or process PCAS - Production Corrective Action System FCAS - Field Corrective Action System IQAG - Internal Quality Audit Group OSV - Operator Self Verification + Management Directive

Via:

8D adds structure (defined steps, language) to what we already have.


Training Materials For Reference Only Slide 10

8D Process Fit (cont.)


Changes being made to:
WI 04-09-009 Creating and Updating Corrective Action Records in SAP WI 04-09-014 Responding to the Corrective Action in SAP WI 04-14-005 issuing Corrective Action Requests for Major Noncompliances Q1 Customer Complaint Q2 Vendor Product Non-Conformance Q3 HBC Product Non-Conformance Q4 Vendor Product CA Q5 HBC Product CA Q6 Vendor Audit CA/PA Q7 HBC Audit CA/PA

Documents Created in SAP:


HBC 8D form will be attached to the appropriate Q1-Q7 record in SAP


Reference Hard Copy of HBC 8D Form handouts

Work Instructions are being modified now to incorporate 8D.


Training Materials For Reference Only Slide 11

What is 8D?

1. Corporate Standard 2. Standardized Problem Solving Process


Language, Methodology

3.

Reporting Format

Training Materials For Reference Only

Slide 12

8 Disciplines (8Ds)
D-0 D-1 D-2 D-3 D-4 D-5 D-6 D-7 D-8 Decide to use the 8D Process existing processes Describe Problem Establish Team Implement Interim Containment Find Root Cause Choose Corrective Action Implement Permanent Corrective Action Prevent Recurrence Congratulate Team

Training Materials For Reference Only

Slide 13

What can trigger an 8D analysis?


Problem with Cause Unknown Need to Cure - Not Mask Problem Justifies a Structured/Team Approach
Factors Severity, Cost, Time, etc.
When do we use the 8D Process?

Examples:

Whenever you open a QN, ask yourself if Root Cause/8D should be done.
Training Materials For Reference Only Slide 14

Who can initiate an 8D analysis?


Request for an 8D analysis can be made by:
Customer
Current Sales/Support Interface

HBC Employee
Initially, by contacting QA reps Eventually, anyone
Working out details defining when it makes sense Not all problems need an 8D level of analysis

HBC Supply Chain


Supplier will perform the 8D

Management

Anyone can use the process. Using SAP makes sure we capture/share knowledge.
Training Materials For Reference Only Slide 15

Place in 8D Process
D-0 Decide to use the 8D Process

D-1 DESCRIBE THE PROBLEM


Why is it important for a Problem Solving team to start with Describe the Problem?

Training Materials For Reference Only

Slide 16

8D Step 1 Describe the Problem


What is the problem? This should be a short, simple and concise definition. REMEMBER: IF YOU CANNOT SAY IT SIMPLY, YOU DO NOT UNDERSTAND THE PROBLEM
A problem well stated is a problem half solved!

Training Materials For Reference Only

Slide 17

Information about the problem

What is the problem? Where was it detected? How serious is the problem? How many occurrences? Who is affected? When did it surface?

Remember:

on the problem.

Training Materials For Reference Only

Slide 18

Problem Definition/Analysis Prompts Who?


Who notified you of the problem? - Manufacturing, Engineering, SAP QN Review, QA Audit, etc. Who are the people involved with the problem? (for step 2 team formation) - Supplier, customer, material handlers, assemblers, supervisors, engineers, QA personnel, etc.

High Level information belongs in the Problem Description, Investigate all others in Step 3 & 4.
Training Materials For Reference Only Slide 19

Problem Definition/Analysis Prompts What?


What is the part name/number/other identification? What type of product or process? - Detail, assembly, vendor part - Part manufacturing process, assembly process? What is the type of nonconformance? - Scratch, Dent, Oversize hole, Fit? - Lack of communication, waiting too long for info/parts? What characteristic of the part/process is having the failure - hole radius, linear dimension? - manufacture of the part, movement, inspection? What method of measurement was used to identify the failure? What are special circumstances surrounding the problem? - new personnel, equipment move, new tool, etc.? What environmental conditions existed? - extremely cold/hot, rainy, humidity, lighting, etc.? What is the design/nonconformance criteria in question? - Drawing, Spec, Task Planning, Policy, Process? What training has been done or is available? What hardware or software is associated with the issue? Have there been recent administrative, program or equipment changes?
Training Materials For Reference Only Slide 20

Problem Definition/Analysis Prompts When?


When in the build process/production schedule/work shift did the problem occur? - note: occurrence point and detection point may (and usually arent) at the same time When in the task did the problem occur? (what step?) When in the functional test did the problem occur (what step?) When in the day, week, month did it/has it occurred (patterns)?

Training Materials For Reference Only

Slide 21

Problem Definition/Analysis Prompts Where?


Where is the part being contained? Where is the part being used? Where is the geographical location of the failure? What plant/line/station cell? Is the problem in-house or external (supplier) or external (in the field)? Where are similar nonconformance records located?

Training Materials For Reference Only

Slide 22

Problem Definition/Analysis Prompts Impact?


How many times and in what period? Cost of nonconformance in dollars? Safety impact? Cost of delay? Warranty cost? Impact to worker morale/productivity? Has this issue been fixed before? Impact on Business processes? - production - delivery - product use - field reliability Impact on Customer Satisfaction?

Training Materials For Reference Only

Slide 23

Importance of Problem Description

Focuses team on same objective Direction set here is used throughout the HBC 8D process (foundation) Forces all to agree on the scope and goal Note: Operational Definitions MUST accompany the Problem Description
What does failure mean? What is bad? What does success look like?
Ice-scraping video

Training Materials For Reference Only

Slide 24

Tool: Is/Is Not for Problem Definition

Reasons to use IS - IS NOT


Establishes points of comparison Leads to a more complete problem description Provides a Test base for Root Cause Gives you a fingerprint of the problem Draws better boundaries around the problem
SCOPE whats in, whats out

Training Materials For Reference Only

Slide 25

Tool: Is/Is Not for Problem Definition


Development of IS: Identity - What is the problem? Space - Where is the problem? Time When is the problem happening?
(also When did it start?) Mass -

How Big is the problem?

Training Materials For Reference Only

Slide 26

Development of IS NOT
IS IS NOT

(What, Where, When, How Big) would you EXPECT to.. SEE, HEAR, FEEL, SMELL, OBSERVE . . . .....but DO NOT? (close cousins)

<<<<<<<<<<<<<<<<>>>>>>>>>>>>>>>>>>>>>>>>>>
(What, Where, When, How Big) IS it? (What, Where, When, How Big) could it be but it IS NOT?

Once you have the Problem Defined, get feedback from others (coworkers, manager, others) who have done 8D/RCCA
Training Materials For Reference Only Slide 27

Reasons to use IS - IS NOT

Establishes points of comparison Leads to a more complete problem description Provides a Test base for Root Cause Gives you a fingerprint of the problem Draws better boundaries around the problem
SCOPE whats in, whats out

Training Materials For Reference Only

Slide 28

Document Your Work


1) Open a QN in SAP 2) Fill Out Section 1 of the 8D Summary Report - go to the Quality Forms link on the QA home page 3) Attach the 8D Summary Report file to the QN

Training Materials For Reference Only

Slide 29

Step 2 in the HBC 8D Process

D-0 Decide to use the 8D Process

D-1 Define the Problem

D-2 Form the Team

Training Materials For Reference Only

Slide 30

8D - Step 2: Form a Team


A Team may be:
formal (scheduled meetings, for ex.) or informal (consulted as needed)

Agree on work group guidelines


Customer Complaint

Training Materials For Reference Only

Slide 31

Advantages/Disadvantages of Teams

WHAT ARE THE BENEFITS OF A TEAM APPROACH?

WHY DO TEAMS FAIL?

What have been your experiences with teams??


Training Materials For Reference Only Slide 32

Major Problems with Team Problem Solving


Problem incorrectly described ! ! !
(biggest inhibitor)

Make sure Problem Description is accurate and team members agree

Problem solving process rushed Poor team participation No logical (group) process Lack of technical skills Management impatience Permanent Corrective Action Not Implemented

Training Materials For Reference Only

Slide 33

Typical Team Organization Champion/Sponsor Leader Recorder rotate this role Team Members
(SMEs - Subject Matter Experts)

Are we having fun yet?

Facilitator (optional) Customer/Supplier

Recommend: 4-7 members (10 max.) <4, consider leader driving results by consulting with SMEs >10, consider subteams

Ask the initial team: Who else needs to be involved, but isnt here?
Training Materials For Reference Only Slide 34

Step 3 in the HBC 8D Process

D-0 Decide to use 8D Process D-1 Define the Problem D-2 Establish a Team

D-3 CHOOSE, IMPLEMENT AND VERIFY INTERIM CONTAINMENT ACTION - basically youre Dispositioning the QN

Training Materials For Reference Only

Slide 35

8D Step 3: Implement Interim Containment Action


Decide whether you need to use one Choose the best (benefits vs. risks)
Tools
Brainstorming to generate ideas Pros/Cons lists; Effort (or cost or time) vs. Benefit (or risk) graphic. Action Plan L Effort Ideal

H L Benefit H

Test feasibility of the containment action (Verify it will work) Commit to it Implement Validate containment action effectiveness

Action Plan

ALWAYS +s and s to every decision. BALANCE (and action) are the Keys!
Training Materials For Reference Only Slide 36

Purpose of Interim Containment


Used to buy time to find root cause while protecting your customer (external or downstream operation) from the problem Authorized first aid, but. . . . .
can be costly attacks symptoms (not the cause) has a masking effect

Purpose of this step:


Enforce SCOPE and EFFECTIVENESS of customer protection needed
Its OK to not have containment, its NOT OK to not THINK about it.
Training Materials For Reference Only Slide 37

Int. Cont. Action vs. Typical BAND AID


Interim Containment Action BANDAID

__X__ __X__ __X__ __X__ __X__ __X__

Attacks Symptoms Added Costs Monitored while being used Documented &Data Collected Verified for effectiveness Replaced by Perm. Correction

__X__ __X__ _____ _____ _____ _____

Training Materials For Reference Only

Slide 38

Key Points of Step 3: Interim Containment


Act quickly (and carefully) Use the team to come up with the list of potential actions
Minimizes risk, results in better ideas

Pick the best overall Containment Action(s) Consider actions that may be needed to address other areas:
Product in the field WIP Work In Process Product in transit/at the Supplier Spares

Use Action Plan to make sure nothing falls through the cracks
Examples:
VERIFICATION and VALIDATION Airworthiness Directives Service Bulletins Kits for field

Action Plan

DONT STOP HERE!!!

X
Slide 40

Training Materials For Reference Only

Fill Out Section 3 of the 8D Summary Report

Training Materials For Reference Only

Slide 41

BREAK FOR 10 MINUTES

Training Materials For Reference Only

Slide 42

Where are We?


Place in the HBC 8D Process
D-0 Decide to use 8D Process D-1 Define the Problem D-2 Establish a Team D-3 Choose, Implement and Verify Interim Containment Action (I.C.A.)

D-4 FIND ROOT CAUSE

Training Materials For Reference Only

Slide 43

Root Cause Analysis Common Tools


Your Brain
Especially the Collective Brain of your team

Data Thought Map Process Map Brainstorming 5 Whys Cause and Effect (Fishbone) Diagram Graphical Analysis (misc. graphs) +
Thought Map

What tool to use? Problem ->Questions->Data/Tools ->More QuestionsROOT CAUSE


Training Materials For Reference Only Slide 44

General Information about Step 4


OUR DESIRE TO ACT, OVERPOWERS OUR NEED TO UNDERSTAND
(Brad Baker, CONOCO)

Dont try to do solutions before the analysis is complete. It is futile to continue doing things the same way while expecting different results. Dont fall into the trap of jumping to conclusions.

This cant be a part time job. Assign a Point Of Contact (POC) to focus on closure. The RCCA response ECD must be based on a planned list of things to do (Action Item Lists).
Training Materials For Reference Only Slide 45

Data Collection
Insufficient data can result in solving only the specific instance. 1. 2. 3. 4. 5. 6. 7. 8. 9. Types of data to collect: Location: where problem was detected Personnel: who found problem Specifications: what are the requirements Environment: noise, lighting, temperature, etc Sequence of events Challenge the basis for why its been Equipment determined to be an isolated event and why it couldnt potentially be a Training systemic problem Other occurrences Recent changes: personnel, process, weather

Training Materials For Reference Only

Slide 46

Tools: Thought Map


Once the problem is defined, natural tendency is to rush forward RESIST THE URGE!! Take a few minutes to plan your journey to root cause 1) 2) Write your Problem Statement at the top of the page Capture questions that you have
Assumptions, potential causes, sources of the problem that dont belong in the problem statement SHOULD be captured as questions

3) 4) 5)

Answer each question with data Questions (and data) will lead to more questions Capture dead-ends as well as fruitful paths
1) Why?

NOTE: Review the Problem Definition (Step 1) often!


Used: When? ________________________ Why?__________________
Training Materials For Reference Only Slide 47

Thought Map example: Drill Bit Quality


LEGEND: Dashed Lines Indicate Links Is the perceived bit quality difference real or just perception?
What specific features of the bit performance are perceived as the problem?
1 - Penetration Sharpness 2 - Straightness 3 - Centering Bruckner provides a standard, such as Michigan Twist

What is the current bit brand and quality used?

What is considered the premium bit?


1 Number of holes drilled 2 - Straightness 3 Centering 4 Penetration What 5 QNs Resulting

What other factors contribute to manual, hand drilling performance?

What are the bit performance indicators?

Precision Twist Brand

is the difference in cost for the bits?

Is there a statistically significant difference in the number of holes drilled before dull?

Is it possible to attribute QNs and other sheet metal defects to bit quality?

How much is the difference?

Training Materials For Reference Only

Slide 48

Tools: Process Mapping/Value Stream Mapping


Outputs Inputs
Transport

Storage

Machine

Transport

Assembly

Transport Inspection

Graphical Depiction of How Its Done Terminator (start/stop) Process Step Decision Point Connector (off-page) General Rules:
Left to Right Yess/Nos consistent

? ?

? ?

How would you map out the process for 8D so far? Used: When? ________________________ Why?__________________
Training Materials For Reference Only Slide 49

Tools: 5 (OK, maybe just 3) Senses

Talk to, Listen to, Observe:


People performing the job Suppliers (internal/external) Customers (internal/external)

You are a root cause detective. Use all the tools you can.

Training Materials For Reference Only

Slide 50

Tools: Brainstorming
When the best solution isnt obvious, one technique for generating ideas (possible root causes, potential interim corrective or permanent actions) is brainstorming. 1. 2. 3. 4. 5. 6. Generates a large number of ideas Encourage free-thinking Dont criticize Encourage everyone to participate Record all ideas. There is no bad idea. Let ideas incubate give it a little time
A minimum group of at least three people to make this work

Used: When? ________________________ Why?__________________


Training Materials For Reference Only Slide 51

Tools: 5 Whys
An employee in the plant slipped and fell while performing their regular duties. 1. 2. 3. 4. 5. 6.
Peel the onion- challenge the basis for root cause. Most people can only support 1-2 layers of questions with their basis for root cause or corrective action.

Why? There was oil on the floor. Why? The machine in that cell was leaking oil. Why? A pressure fitting on the machine failed. Why? Inspection of hoses and fittings is not part of the preventive maintenance (PM) schedule. Why? The PM system does not consider Equipment Manufacturers recommendations to develop PM schedules. Why?- Theres check to make sure this is done.

Dont stop with Because we dont have enough people, money, time its a fact of life. Solve the problem with the people, money, time you DO HAVE.
Used: When? ________________________ Why?__________________
Training Materials For Reference Only Slide 52

Tools: Cause and Effect Diagram


A Cause-and-Effect (fishbone or Ishikawa) diagram an easily applied tool used to analyze possible causes to a problem.
Manpower
- inexperienced -not following the frozen coating parameters

Methods
- incorrect prep of metal surface -inadequate technique

MUST BE TESTED AND VERIFIED!

- inadequate training Non-conforming coating


- microscope - microscope setting not optimized to detect the smearing - poor quality of standards

Machinery

Materials

5 Ms and an E - add Measures and Environment for 6 Bones

Used: When? ________________________ Why?__________________


Training Materials For Reference Only Slide 53

Tools: Graphical Analysis

Histogram
Used to show patterns/distribution in ordered data Categories on the x-axis, # of occurrences on the y axis.

Pareto Chart (80/20 rule)


Used when many problems or causes and you want to focus on the most significant Causes on x-axis, Results on the left (primary) yaxis, Cumulative % on the right (secondary) yaxis.

Scatter Diagram
Used to illustrate relationships between 2 variables. 1 variable on each axis. "Correlation does not imply causality."
Ex. Shark Bites and Ice Cream

Purpose of Graphical Analysis: ________________________________


Training Materials For Reference Only Slide 54

Word of Caution: Stay on Track!


Use Common Sense:
1. The more significant or involved the problem, the more detail may be needed to identify the Root Cause
1. Also more advanced tools
Side Issue Side Issue Side Issue

Goal

2.

Avoid data that leads to other problems.


1. Dont get sidetracked
1. Review Step 1 Problem Description. Start

2. Use the Thought Map


Complex problems usually require at least a fishbone diagram of the potential root causes sorted from the brainstorm list Define the actions to validate or dismiss each one Technical problems usually require a structured FMEA
Training Materials For Reference Only Slide 55

Document Your Findings

Fill Out Section 4 of the 8D Summary Report

Training Materials For Reference Only

Slide 56

8D Step 5: Choose Corrective Action


Place in the HBC 8D Process:
D-0 Decide to use 8D Process D-1 Define the Problem D-2 Establish a Team D-3 Choose, Implement and Verify Interim Containment Action (I.C.A.) D-4 Find Root Cause

D-5 DETERMINE PERMANENT CORRECTIVE ACTION

Training Materials For Reference Only

Slide 57

Decision Making Steps (note: can also be used in Step 3)


1.

Define end result (action verb & object)


Eliminating/Preventing/Reducing (verbs) Errors/Safety Incidents/QN/s (objects)

2.

List decision criteria


GIVENS - Mandatory WANTS - Desirable

3. 4. 5. 6.

Decide relative importance of wants 1-10 Identify the possible choices Compare possible choices against the decision criteria Analyze risk
IF/THEN terms:
If we choose to___________, Then _________ will happen.

7.

Make the final BALANCED choice and VERIFY

Action Plan

NOTE: Use the Action Item Tracking Sheet to Capture and Track Actions
ALWAYS +s and s to every decision. BALANCE (and action) are the Keys!
Training Materials For Reference Only Slide 58

Track Action Items to Completion and Summarize Results

Use the Corrective Action Plan Worksheet in the 8D File and Summarize in Section 5 of the 8D Summary Report

Training Materials For Reference Only

Slide 59

8D - Step 6: Implement the Fix


Place in the HBC 8D Process:
D-0 D-1 D-2 D-3 D-4 D-5 Decide to use D8 Process Choose team members Define problem Choose Interim Corrective Action(s) & verify Find Root Cause Choose & verify Permanent Corrective Action

D-6 IMPLEMENT PERMANENT CORRECTIVE ACTION

Training Materials For Reference Only

Slide 60

Goals of Permanent Corrective Action


Permanent Corrective Action MUST:
Address the systemic problem (in addition to this specific instance) Eliminate the Root Cause Prevent recurrence Be implemented in a timely manner Include a detailed plan (especially if it will take considerable time and people) Be comparable to the risk involved
Risk to the customer, employee, organization, public, etc.

Be verified Objectively
Three knowledgeable people must agree

Training Materials For Reference Only

Slide 61

Keys to Successful Corrective Action

Persistence
Natural Tendency to slack off once the Fix is determined and partially implemented Follow the Action Plan to Completion

Involve Do-It-Level people


Key to preventing recurrence

Review Interim Containment Action(s)


Remove/discontinue any not needed adds cost, time, etc.

VERIFY IT!!! VALIDATE IT!!!

Action Plan

Training Materials For Reference Only

Slide 62

More than Just Do It


Why should we do planning and NEW problem prevention when considering implementing a permanent corrective action for THIS problem? see next slide.

Training Materials For Reference Only

Slide 63

Why Planning and Problem Prevention?


Many of our current problems are the result of not following through with previous plans Must allocate limited resources effectively
Optimize implementation
Dont waste Time/$$

Prevent other problems from occurring


With change comes risk of creating NEW problems Control Mr. Murphy

Training Materials For Reference Only

Slide 64

Summarize the Key Permanent Corrective Actions Fill Out Section 6 of the 8D Form

Training Materials For Reference Only

Slide 65

8D - Step 7: Prevent Recurrence


D-0 D-1 D-2 D-3 D-4 D-5 D-6 Decide to use D8 Process Choose team members Define problem Choose Interim Containment Action(s) & verify Find Root Cause Choose & verify permanent corrective action Implement Permanent Corrective Action(s)

D-7 PREVENT RECURRENCE

Training Materials For Reference Only

Slide 66

Steps to Preventing Recurrence


Identify what systems, practices, or procedures allowed the problem to occur
The whys

Identify and implement improvements VALIDATE the results

Training Materials For Reference Only

Slide 67

Tool: Mistake-Proofing
Poka-yoke is the Japanese term that means fail-safing or "mistake-proofing" Examples:
Cant start car until in park, Child-proof caps, laser beam shutoffs for machinery Others??

One of the best ways to prevent problems from occurring/recurring Use mistake-proofing techniques when there are:
Process steps where human intervention is required Decision points in the process Repetitive tasks where physical manipulation of objects is required Steps where errors are known to occur Opportunities for predictable errors to occur
Training Materials For Reference Only Slide 68

Mistake-Proofing Levels of Prevention

More Proactive

Defect is the evidence of an error

Training Materials For Reference Only

Slide 69

Beware of Root cause was Human Error


HUMAN ERRORS do not make a root cause How does HBC approach human error? Positive
Defects can be eliminated Create a mistake-proof environment Ask Why?
Focus on the Process/Product NOT the Person

Apply Mistake-Proofing device for 100% inspection

Negative
Defects are inevitable People make mistakes Place blame Detect at final inspection Sampling inspection Some are bound to reach the customer

Training Materials For Reference Only

Slide 70

Once Root Cause is Determined, Broaden your Thinking


How Can We Standardize Lessons Learned & System Improvements?

Communication Same/similar problem other plants Same/similar problem different systems Effect Content Quality Appropriate Quantity Potential Causes
Root Cause Current/Future Problems in other areas

Training Materials For Reference Only

Slide 71

Fill Out Section 7 of the 8D Form Prevention of Recurrence

Training Materials For Reference Only

Slide 72

8D - Step 8: Congratulate the Team


D-0 D-1 D-2 D-3 D-4 D-5 D-6 D-7 Decide to use D8 Process Choose team members Define problem Choose I.C.A., verify Find Root Cause Choose & verify P.C.A. Implement P.C.A.(s) Prevent recurrence

D-8 CONGRATULATE THE TEAM


Training Materials For Reference Only Slide 73

How to Congratulate the Team


Review significance of contribution Provide appropriate recognition for all members Document the efforts & results Celebrate successful completion

Celebrations dont have to be elaborate/expensive Be creative

Training Materials For Reference Only

Slide 74

How Would You Congratulate Your Team? What are some things that have worked well in the past? What are some things that didnt?

5 minutes
Training Materials For Reference Only Slide 75

Fill Out Section 8 of the 8D Form (and attach completed file to the appropriate QN)

Training Materials For Reference Only

Slide 76

Comments, Suggestions?? Please fill out class/instructor Evaluation Forms

Training Materials For Reference Only

Slide 77

Reference Material

Training Materials For Reference Only

Slide 78

QA Intranet Website

Training Materials For Reference Only

Slide 79