INTERNAL FINISHING WORKS FOR THE SECOND FLOOR (ROOF) OF OCHA

Jerusalem

Bill of Quantities

August 2008

OCHA Roof Floor Cost Estimation

August 2008

Item No

Description

Unit

Quantity Rate (US$)

Amount (US$)

Bill No 1 Cleaning, Demolishing & Dismantling Works: Demolishing for any kind of block, concrete, wood, and metal works, etc. needed to clean the area and not affecting the stability of the wood structure of the cieling. Leveling the ground and complete cleaning for the roof floor from all types of soil, wood, metals and unnecessary materials. All as per the approval of the Engineer.

1-1

Demolishing all the existing concrete blocks on the partitions and the windows and moving all the surplus to a location where the Engineer instruct, removing all the garbage, sand, cocrete blocks and stones on the roof floor, and all surplus debris material from the roof floor and from the working area in preparation for works. Unit rate shall also include removing damaged stone walls, damaged ceilings, damaged floor tiles, dismantling existing wooden, metal or other elements, wire mesh, cables, metal sheets and all related elements. Then, all the working area should be cleaned and prepared for finishing works, taking into consideration to keep and maintain the wood structure and supporting it properly. All as directed by the Engineer.

JOB

1-2

Cleaning all the roof floor and the roof tiles completely, and removing all the birds nests and all related birds products, disinfecting all the floor, walls and ceiling with required insect disinfectants, and preparing the windows, floor and ceiling for the next works. All as directed by the Engineer. Cleaning all the internal stone works on the walls and removing the old pointings and all the stuck concrete, wood or metal peices from the stone walls completely. All as directed by the Engineer.

JOB

1-3

JOB

Total Bill NO. 1 Sum Of Items [(1-1) - (1-3)] carried to summary

UNDP - PAPP Engineering Unit

1 - 21

OCHA Roof Floor Cost Estimation

August 2008

Item No

Description

Unit

Quantity Rate (US$)

Amount (US$)

Bill No 2 Maintenance Works: Maintenance includes, fixing all the damaged needed items and maintaining floor and ceiling in good condition. All as per the approval of the Engineer. 2-1 Complete maintenance for the floor, including supplying and casting concrete where needed and maintain the floor slab in level and ready for tiling and other partision works. All as directed by the Engineer. Complete maintenance for the ceiling, including dismantling all roof tiles and store them in a safe place, supplying and installing special wood beams to support the roof tiles, reinforcing all the wooden structure with special fixing elements from bolts and metal elements; price includes changing any broken wooden beam or any damaged roof tile or any related item with new ones. In addition, solving the rain water leakage in the roof tiles and supporting the tiles properly and supply and performing the required materials and water proof materials to fix all the leakage and support problems after implementing item 8.2. All as directed by the Engineer.

JOB

2-2

JOB

Total Bill NO. 2 Sum Of Items [(2-1) - (2-2)] carried to summary

UNDP - PAPP Engineering Unit

2 - 21

OCHA Roof Floor Cost Estimation

August 2008

Item No

Description

Unit

Quantity Rate (US$)

Amount (US$)

Bill No 3 Concrete Blocks Works: PREAMBLE. All works of this bill shall be of Concrete blocks Grade 35 of high quality standards and as per specifications. Block works shall be measured in meter square. The net measurement of the seen elevations, excluding all openings and voids more than 0.1 M. S. in area. No allowance for thickness used other than those shown in the drawings. Rates of Block works include: Vertical and horizontal joints. Cement and mortar, Galvanized angles and butter fly ties. Closed end blocks at all ends, door and window jambs, reveals and the like. Pointing of the uncovered block surfaces. Concrete filling including reinforcing steel to cavities at quoins and door and window openings. Lintels and bond beams to the full length of the wall, 20 cm. high and in the same wall thickness of reinforced concrete grade B-200 with due reinforcement steel, on top of doors and windows or at the height of 2.00 M. and all needed to complete job as per drawings and specifications.

3-1

Supply and Build Concrete Block Walls, 'Grade 35' of any size blocks. A. Hollow Blocks B. Hollow Blocks ( 10 Ten) cm. thick . (20 Twenty) cm. thick. M2 M2 205 40

Total Bill NO. 3 Sum Of Item [(3-1)] carried to summary

UNDP - PAPP Engineering Unit

3 - 21

OCHA Roof Floor Cost Estimation

August 2008

Item No

Description

Unit

Quantity Rate (US$)

Amount (US$)

Bill No 4 Plastering and Pointing: PREAMBLE. Plastering to all areas shall be measured net, including openings which are less than 0.25 Meter Sq. The price shall include for running rules , all narrow widths, for taking out joints on block walls or backing concrete face for key, for making good to frames around pipes and other fittings , plastering to jambs and reveals of openings, side of columns, window sills; all of which shall be measured as plastering . Price shall also include Expanded metal lath, angle beads at all corners and plaster stops at opening edges, expansion joints, sills, labor, curing, erecting and dismantling of scaffoldings, additives, pigments and all incidentals required as 4-1 Supply and apply Two Coats of Cement and Sand Plaster over one slurry coat to walls and ceilings and where required including metal Lath ,angle beads , plaster stops and all required as per Specs and drawings . A.Three coats Internal plaster. 4-2 Supply and apply Two Coats of Cement and Sand Plaster over one slurry coat to walls and ceilings and where required including metal Lath ,angle beads , plaster stops and all required as per Specs and drawings . Supply and apply pointing to all the internal wall stone, including all the required works to complete the job as per the approval of the Engineer. M2 210

M2

250

4-3

JOB

Total Bill NO. 4 Sum Of Item [(4-1) - (4-3)] carried to summary

UNDP - PAPP Engineering Unit

4 - 21

OCHA Roof Floor Cost Estimation

August 2008

Item No

Description

Unit

Quantity Rate (US$)

Amount (US$)

Bill No 5 Tiling, Flooring and Marble Works: PREAMBLE. 1. All tilling works ( terrazzo, ceramics and marble ) shall be measured net in square meters. deducting all opening and voids more than 0.25 m.s. 2. Skirting shall be measured in leaner meter. 3. Marble works for steps and treads of stairs shall be measured in linear meter. The tread and the riser shall be measured as a single unit. 4. Marble works for window sills and other openings shall be measured in squared meter . 5. Parapet copping shall be measured in squared meter. 6. Marble works for stair flights skirting shall be measured in linear meter. 7. Rate shall include preparation of surfaces under tiles, Finnish to falls and cross falls, special tile peaces for edges and the like, tile surface finishing, Plastic spacers. Pointing and cleaning and all incidental as per specifications. 8. Rates shall include also providing and mounting in place Title Marble Plate of white clear local marble polished, finished and engraved according to the design provided by UNDP.

5-1

Supply, Install and finish Pre-cast Terrazzo Tiles Size ( 30 x 30 x 2.7 ) cm, with Italian marble chipping # 6. Price to include, bedding and jointing in cement and sand mortar, pointing with white cement, required sand fill, and on site grinding, polishing and cleaning and skirting size (30*7.5*1.5)cm Supply and Install Local Marble Sills, Thresholds and Parapet Coping. ( 3 cm. thick ). Set in cement mortar bedding price to include grouting, polishing of face and chamfered edges . A. Window Sills Size( 15 - 37.5 x 3 ) cm. B. Kitchenette Sink Size( 50- 60 x 3 ) cm.

M2

95

5-2

M2 M2

5 0.5

5-3

Supply and Install White Porcelain Glazed Wall Tiles, class "A" free from all defects. (Spanish or Italian high quality make or equivalent). Ditto but non slippery tiles for the W.C floor.

M2

5-4

M2

Total Bill NO. 5 Sum Of Item [(5-1)-(5-4)] carried to summary

UNDP - PAPP Engineering Unit

5 - 21

OCHA Roof Floor Cost Estimation

August 2008

Item No

Description

Unit

Quantity Rate (US$)

Amount (US$)

Bill No 6 Carpentry And Joinery Works: PREAMBLE. Sizes of carpentry works given in the Bills of Quantities are finished sizes and shall be as per Drawings. Sizes of doors and other items mentioned in the Bills of Quantities shall allow for tolerance to suit the structural openings shown in the Drawings. Wooden doors and pair of doors shall be measured in number for each structural opening, unless stated otherwise in the Bills of Quantities. Rates for carpentry and joinery work shall include : a) Shop and coordinated drawings. b) Cutting and fitting around obstructions, Bedding and painting. c) Grounds, blocking and backings. d) Plugging concrete, block work, and stone work , and making good. e) Ironmongery including cylindrical locks, handles, stoppers, screws, temporary fixing, refixing, oiling and adjusting. f) Providing two keys for each lock including tagging. g) Providing and fixing Room Title Plat, Painted Steel (30*20) cm. mounted on wooden plate (35*25) with varnish finish. h) Steel legs, brackets, bearers and other supports including painting. i) Glass and glazing including cutting to size and putty. j) Fly screening including cutting to size. k) Preparing surfaces to receive finishes. l) Painting, varnishing, polishing, oiling, and the like, to any area or width in any location including work in multicolor and cutting in edges and putty.

UNDP - PAPP Engineering Unit

6 - 21

OCHA Roof Floor Cost Estimation

August 2008

Item No 6-1

Description Supply and Fix Flush Panel Solid Core Doors 4.5 cm Thick single or double sashes of size 210x90 cm. with ( Frame ). (4.5*10) cm. Edge strip banding of Hardwood ( Swedish ) , with 5 mm. thick plywood veneer on both sides, door paneling to be of soft wood 3.5*3.5 cm. each 2.5 cm. , frames of hardwood ( Swedish) width according to the wall thickness and Allowance of 4 - 6 cm, clearence from tiles to be 2 cm. thickness for plastering and tiling purposes, emerged in wood preservative before erection then embedded completely in sand - cement mortar and completely anchored as per specification . Price shall include Domicile or equally approved door handles, cylinder & lock. All as per the approval of the Engineer.

Unit

Quantity Rate (US$)

Amount (US$)

No.

6-2 6-3

Ditto, but size 210x80 cm. Supply and install lower Kitchen Cupboard cosisting of the neccessary doors, drawers of different depths and shelves; of hight 90 cm and depth of 60 cm. Exterior and interior Formica covering and all hardware hinges, handles, telescopic drawer rails, shelf brackets. The unit price shall also include cost of local marble topping 3 cm thick and making the neccessary openings for installing the sink and other services. All as directed and approved by the engineer.

M2

Unit

Total Bill NO. 6 Sum Of Item [(6-1)-(6-3)] carried to summary

UNDP - PAPP Engineering Unit

7 - 21

OCHA Roof Floor Cost Estimation

August 2008

Item No Bill No 7 Metal Works:

Description

Unit

Quantity Rate (US$)

Amount (US$)

Preamble. Metal works shall be measured in number. Rates for metalwork shall include for : Preparing shop drawings, Drilling, counter sinking, screwing, bolting and riveting. Sub frames, including galvanized steel frames for Aluminum windows and architrave. Lugs, plugs, holdfasts and the like. Gaskets, sashes, double weather strips and external and internal approved quality silicon filling around frames. Ironmonger including cylindrical locks (Union or equal) , stoppers, handles, temporarily fixing, refitting, oiling and adjusting. Providing two keys for each lock and padlock including tagging. Hardware including cramps, dowels and the like. Glass and glazing including cutting to size, putty and rubber. Preparing surfaces for and painting one coat of primer before fixing. Painting one undercoat and two finish paint. Sealing and Painting to any area or width in any location including work in multicolor and cutting in edges. All other accessories and incidentals required to execute the work. 7-1 Supply and install Mul-T-Lock door of size 210X90 cm to seperate the working area from the other roof floor area. Price includes the required frame and accessories, locks, handles and hinges, the needed support with ground, fine welding with the security metal frame and the direct support to the steel columns and the top edje of the steel structure where needed. All as per drawings and to the approval of the Engineer.

NO.

216.00

216.00

7-2

Supply and install metal stair rails (same as existing) for the roof staircase including all fixation elements and welding needed to fix the rails with the walls and ground. Price to include painting the rails with anti-rust coat and then oil painting of the collor choosen by the Engineer. All works are done according to Engineer's instruction.

MR

Total Bill NO. 7 Sum Of Item [(7-1) - (7-2)] carried to summary

UNDP - PAPP Engineering Unit

8 - 21

OCHA Roof Floor Cost Estimation

August 2008

Item No

Description

Unit

Quantity Rate (US$)

Amount (US$)

Bill No 8 Gypsum Boards and False Ceiling Works: Preamble. The contractor shall, when pricing the rates of this bill, take into consideration including and allow for the costs or expenses of all requirements stipulated in the preambles, drawings and technical specification of the contract. Rates for all suspended ceilings works includes suspension system with anchors to the structure, L& Z, main & main profiles, omega profiles. clips, gaskets and all necessary fittings in accordance to the manufacture technical data and related standards covering this type of works, The rate includes also cutting and preparation for installing lighting fixtures, ceiling recess, maintenance openings, grills, ceiling utilities... etc. 8-1 Supply and install vertical and horizontal gypsum boards 12mm thick fire and water proof for ceiling cladding and for other decorative works. The price shall include all decorative beams, edges, recessed slab, squares, cuts, suspension& structural profiles, fixing with the wooden structure and extra support where required-- etc to any shape and patterns to complete the works. The unit rate shall also include acoustic and thermal rock wool mats, 25mm thick and 25kg/m3 density, wrapped in black non inflammable dust proof sags in accordance with specifications and the related Standards. as approved by the Engineer. Supply and install Galvanized steel sheets to cover the lower edge of the ceiling wooden frame to forbid leaking rain water to get down to the roof floor. The unit rate shall include storm water collectors on the edges of the building and also include acoustic and thermal rock wool mats between metal sheets and roof tiles, 25mm thick and 25kg/m3 density, wrapped in black non inflammable dust proof sags in accordance with specifications and the related Standards. The galvanized sheets should be spread on all the brick tiles until the external edges where storm water collectors are installed and draged to the corners of the building. All works shall be done as per the instructions of the Engineer.

M2

105

8-2

M2

300

Total Bill NO. 8 Sum Of Item [(8-1) - (8-2)] carried to summary

UNDP - PAPP Engineering Unit

9 - 21

OCHA Roof Floor Cost Estimation

August 2008

Item No Bill No 9 Painting Works:

Description

Unit

Quantity Rate (US$)

Amount (US$)

Preamble. Painting and decorating to walls, ceilings and the like shall be measured net in meter square. Painting to other works shall be included in the related items. Paints shall be supplied to site in sealed container, as approved by the Engineer, and site mixing shall not be permitted. The Contractor rates shall include for supply of all materials, workmanship, samples, primers , surface preparation , protection of painted surfaces , application to all heights as required of works, repair of all damaged surface at the contractor's expenses , and all other requirements as stated in the Specifications .

9-1

Supply and paint high quality Emulsion PVABased Paint, for internal walls. Price includes one priming coat and two finishing coats , for application to walls , using putty from Delux or equivalent Supply and paint Polycide paint for gypsun boards ceilings, price shall include painting and putty. All as directed and approved by the Engineer.

M2

300

9-2

M2

95

Total Bill NO. 9 Sum Of Item [(9-1)-(9-2)] carried to summary

UNDP - PAPP Engineering Unit

10 - 21

OCHA Roof Floor Cost Estimation

August 2008

Item No Bill No 11 Electrical Works:

Description

Unit

Quantity Rate (US$)

Amount (US$)

Preamble. All items price to include Supply, Installing, Connecting and testing unless otherwise indicated, the contractor are requested to have approved full coordinated work shop drawings before starting contract activities, the price also includes all works necessary to implement electrical works in approved manner. The contractor intended to order main and final distribution panel boards according to approved manufacturer drawings. The price to include submittals, catalogs, any manufacturer instruction . The contractor should install and construct all works according to drawings , specification tender documents, and requirement of Electrical Co. Contractor should also test & submit the electrical Work to the Electricity Co. & Municipality.

11.1 a

Electrical Points: The electrical power supply from electrical switchboard to first point in circuit shall be included in the unit price of that point (by means of wires, cables or leads in self extinguishing conduits and cables). All as per specifications and as required. All wiring accessories shall be as made by Legrand or equivalent. Supply, install , connect ,and test a standard lighting point internal or external, in slab or over false ceiling, to include a 16 mm diameter conduit, 1.5 or 2.5 sq. mm crosssection leads or cable, and, as required single, double, two way or push bottom lighting switch Legrand type or equivalent, and outlet for luminare with junction box and terminals. Ditto but for emergency lighting point No. 55

b. 11.1.1

11.1.2

No.

UNDP - PAPP Engineering Unit

11 - 21

OCHA Roof Floor Cost Estimation

August 2008

Item No 11.1.3

Description

Unit

Quantity Rate (US$)

Amount (US$)

Supply, install , connect,and test a 16A wall socket point - to include a 16 mm dia. Conduit, (3x2.5) sq. mm cross-section leads or cables, and as required 16 A wall socket Legrand type or equivalent approved. Ditto as item 14.1.3 but double socket. Ditto as item 14.1.3 but with water proof cover. Ditto as item 14.1.4 but with water proof cover. UPS Power Supply Socket Supply, install , connect and test Fire Alarm connection point (Price includes 16 mm diameter conduit with cable, leading from point to the LV box or to the nearest point). Supply, install , connect and test TV connection point (Price includes 23 mm diameter conduit with cable, boxes, and the socket outlet leading from point to the LV box). Supply, install ,connect and test Computer socket point in a 23 mm conduit - to include a 23 mm diameter conduit . Supply, install, connect ,and test a Three phase 25A Isolator Switch .The price include the conduits , cable , cable tray and any accessories needed, all according to drawings and specifications for the exhaust fans and splits units. Conduit, Rigid Piping and Excavation Works:

No.

11.1.4 11.1.5 11.1.6 11.1.7 11.1.9

No. No. No. No. No.

15 3 1 14 16

11.1.10

No.

11.1.11

No.

15

11.1.12

No.

11.2

UNDP - PAPP Engineering Unit

12 - 21

OCHA Roof Floor Cost Estimation

August 2008

Item No

Description

Unit

Quantity Rate (US$)

Amount (US$)

Supply, install, connect and test Selfextinguishing type plastic conduit, processed over or under plaster or inside castings, including junction boxes, unions, connectors, etc. including excavation, backfilling , sand , tape , and galvanized draw-strings, ready for use (for works not included in points works).

11.2.1 11.2.2 11.2.3 11.2.4 11.3

23 mm diameter. 29 mm diameter. 36 mm diameter. 50 mm diameter. Cables: Supply, install, connect and test XLPE nonarmored type thermoplastic copper cables, including insertion into conduit or attachment to structural elements or laying in ductwork, including all associated materials, insulation materials, unions,Z construction, ladders, cable shoes and connection of cable at both ends.

ML ML ML ML

30 30 45 30

11.3.1 11.4 a.

3x35+16 sq.mm cross section+16 Cu.. Electrical Switchboards: Supply, install, connect and test the electrical switchboards to the site, including all associated materials and labour, as described in the technical specifications. Cabinets with no access from the rear, made up of transparent polycarbonate cells, or sheet-metal cabinets with a 25% surplus space. The switchboards are to be placed on the floor, in a niche against the wall. Main supply lines enter from the switchboard bottom, top or side, while outgoing lines exit the switchboard from both its bottom and top sides.

M.L.

50

b.

c. d.

UNDP - PAPP Engineering Unit

13 - 21

OCHA Roof Floor Cost Estimation

August 2008

Item No e.

Description

Unit

Quantity Rate (US$)

Amount (US$)

Price to include all structural elements required in order to install the switchboard, including bus-bars, terminals, wiring, bolts, clamps, etc. and for the equipment listed below. The switchboards shall contain accessories made by one of the following manufacturers: SIMENS, MERLIN GERIN, KLOCKNERMOELLER or Equal Approved. Prices for supply, installation and connection of various accessories including all associated labour and materials such as bus-bars, terminals, wiring reinforcements, mounts, engraved "sandwich" type identification plates, etc. including connection to mains supply - complete ready for use. DBR Lighting Fixture: Supply, install ,connect and, test of lighting fixtures as described below, including all necessary accessories, required in order to light it with lamps and electronic rapid starter, complete, similar to Philips or approved equal and according to the following: All lamps shall be of the energy-saving type (135, 18,36, 58 Watts). Type (A)1X8W emergency EXIT sign for 3 hours duration Maintained Wall Mounted. Type (B) 2x13W downlight horizontal mounting with a cover. Type(BE) Ditto,but with emergency Kitt 3 hours backup battery and charger. Type (C) 2D 28W surface mounted circular luminarie with white base and white polycarbonate diffuser IP54. Type (D) 4X18W surface mounted light fixture with double parabolic Aluminum Louver. Unit 1 Unit 1

f.

g.

11.4.1 11.5 a.

b. 11.5.1

11.5.2 11.5.3 11.5.4

Unit Unit Unit

5 0 2

11.5.5

Unit

38

UNDP - PAPP Engineering Unit

14 - 21

OCHA Roof Floor Cost Estimation

August 2008

Item No 11.5.6

Description

Unit

Quantity Rate (US$)

Amount (US$)

Type (DE) 4X18W surface mounted light fixture with double parabolic aluminum louver with 3 hours backup battery and charger. Type (O) 250 watt metal halide projector Fire Alaram System: Supply, install , connect and test complete in place and in an operable manner the fire alarm system. The work is to include the supply of the equipment specified, installation of same connection, wiring, cables, commissioning and all of the details and connecting to the existing system as specified in the technical specifications and drawing type to be similar to Telefire or equal approved.

Unit

11.5.7 11.6

Unit

11.6.1 11.6.2 11.6.3 11.6.4 11.6.5 11.7

Intelligent manual call point. Indoor fire alarm siren Intelligent photo electric smoke detector, complete with base Intelligent heat detector, complete with base Outdoor fire alarm siren LV Boxes: Supply, install,connect and test the following LV boxes. Rate to include all required materials, conduits, wires, cables and accessories manufacturing from galvanized sheet metal sheets , painted with the same color of the switch boards all as specified in the technical specification and drawings.

Unit Unit Unit Unit Unit

3 3 11 2 1

11.7.1

LVB Approximate dim.( 60x60x25) cm

No.

Total Bill NO. 12 Sum Of Bills [(11-1)-(11-7)] carried to summary

UNDP - PAPP Engineering Unit

15 - 21

OCHA Roof Floor Cost Estimation

August 2008

Item No

Description

Unit

Quantity Rate (US$)

Amount (US$)

Bill No 12 Plumbing, Sanitary And Mechanical Works: Preamble: The measurement for the supply and installation of the mechanical works items shall be as stipulated below: All water supply valves, faucets and fixtures shall be measured by number. Domestic water supply network pipes and fittings (excluding valves) from roof tanks to water collector shall be measured in linear meter. Water tanks shall be measured by number. Sanitary fixtures, including PVC syphon, pedestals, fixing screws, and all required fixation gadgets, shall be measured by number. Floor drains, floor traps, clean outs, rain water roof drains shall be measured by number. Vents and vertical stacks shall be measured in linear meter. Manholes and gulleys shall be measured by number. External and internal sewer pipes shall be measured in linear meter for each individual Rates of all fittings , fixtures , appliances and pipe laying shall include:Supply of material, workmanship, installation, testing and commissioning. Supply, install and testing of pexgol pipes including all the needed fittings, sleeves, (excluding valves) between water collectors and fixtures. Rates to include also all pieces and fittings, including by-passes , floats, automatic vents, stack covers, valves and non return valves, tees, joints, tee bolts and rods, brackets, elbows, reducers, fixing materials and all the required elements needed to complete the works as per specifications. Insulation and painting shall be done as called for in the specifications. Rates shall include excavation and cutting for all pipe laying works, bedding, back filling and all works connected with pipe laying. Rates to include workmanship, storing, correspondences, shop drawings and as-built drawings, all as approved by the Engineer.

UNDP - PAPP Engineering Unit

16 - 21

OCHA Roof Floor Cost Estimation

August 2008

Item No 12-1

Description Supply and install 4" UPVC pipes (UAP, Royal, or equally approved) for internal sewage network, vent pipes, and rain water drain pipes. Price includes all kinds of excavation in any type of soil and rock, backfilling, digging in concrete slabs and walls, supports, hangers and all rubber joints and sealants. All done as per specifications, drawings and the approval of the Engineer.

Unit

Quantity Rate (US$)

Amount (US$)

MR

12-2 12-3 12-4

Ditto but 2" UPVC pipes for the Sanitary fixtures. Ditto but 1 1/4" UPVC pipes for Air Conditioning d i Supply , install and test heavy duty chrome plated 4" floor drain with mesh cover, as made by Ritco or equivalent, including 4" syphon trap as made by Royal, UAP, or equivalent, all complete with the required fittings and connections, as per the specifications, drawings, and the approval of the Engineer.

MR MR

6 20

NO

12-5

Supply , install and test heavy duty chrome plated 4" clean-out with air tight cover , as made by Ritco or equivalent, complete with all required fittings and connections. Supply and install porcelain kitchen sink of size 55 x 45 cm from Ideal Standard/Egypt, Vetara/Turkey, Shona/India as shown on drawings, to be placed on the Marble platform. Price shall include all fixation and hanging bracket, sealants, support, PVC syphon, and all other required materials, including connection to floor drain system. Supply and install Chrome plated gear type mixer of Ideal Standard/Egypt, Lirane or equal for kitchen. Price shall include, connections to water pipes outlets, angle valves and wall sockets. All as specifications, drawings and the approval of the site Engineer.

NO

12-6

NO

12-7

NO

UNDP - PAPP Engineering Unit

17 - 21

OCHA Roof Floor Cost Estimation

August 2008

Item No 12-8

Description Supply and install plated gear type mixer of Ideal Standard/Egypt, Lirane or equal for bathroom. Price shall include, connections to water pipes outlets, angle valves and wall sockets. All as specifications, drawings and the approval of the site Engineer. Supply and install porcelain W.C. bowl class "A" white color of Ideal Standard/Egypt, Vetara/Turkey, Shona/India, with heavy duty white seat and cover. Price includes flush tank, hanging iron steel bracket, bolts and nuts, as well as flexible flush hand hose and valve and all fixing materials. Supply and install porcelain wall hung wash basin white color of size 45 x 35 cm such as Ideal Standard/Egypt, Vetara/Turkey, Shona/India. Price shall include all fixation and hanging bracket, white plastic syphon and all other required materials, including connection to drainage system. Supply, install and test Schedule 40 galvanized steel pipes "Akko make or equal" at riser, roof piping, sanitary block, etc. Price includes all necessary fittings such as elbows Tees, unions, air vents, supports, hangers, shields, saddles, etc. All pipes imbedded in walls shall be coated with 3layers of extruded polyethylene. All pipe joints imbedded in walls shall be coated with thick asphalt layer. All done as per specifications, drawings and the approval of the Engineer.

Unit

Quantity Rate (US$)

Amount (US$)

NO

12-9

NO

12-10

NO

12-11

a- 3/4" b- 1" c- 1 1/4" d- 2"

diameter pipe diameter pipe diameter pipe diameter pipe

MR MR MR MR

20 10 5 10

UNDP - PAPP Engineering Unit

18 - 21

OCHA Roof Floor Cost Estimation

August 2008

Item No 12-12

Description Supply, install and test Copper Collectors 3/4" dia., as made by NTM / Italy or equivalent. Price shall be per opening (eye), and shall include the required copper glands, and air vents all the required fittings, price also includes wooden closet as required and approved. Collectors shall be installed and fixed in recessions on walls by adequate hangers and tees, as shown on drawings in the corridor. The work shall be completed as specified and according to the Engineer's instructions.

Unit

Quantity Rate (US$)

Amount (US$)

Eye

12-13

Supply, install and test Pexgol pipes 16mm dia. Price to include copper glands, connectors, elbows, and all needed fittings and external protective sleeve of 25mm dia. Supply and Install of forward curve ducted split unit heat pump made by York, Daikin, Carrier or Equally approved (condenser and evaporator) of size 8.4 kw. The unit shall be a single coil with drain pan made of stainless steel and with all parts such as copper valves, washable flat filter, multi speed electric motor and room thermostat with three speed switch (wall mounted), distance remote controll. The rate includes drilling and diggings needed, concrete works, copper pipes of proper diametres with 9 mm insulation and 10 cm plastic wrap strips, all the required fittings internally and externally, flexible pipe for drain water to be connected to the PVC A/C drain pipe in wall, electrical control cable. Price also include all flexible ducts between the unit and the diffusers of different sizes as shown in the drawings, all done as per specifications and the approval of the Engineer. Supply and Install supply air aluminum ceiling diffusers made by cooling industries or Equally approved, square four-way type , with removable core, key operated opposed-blade volume damper and equalizing grid, suitable for mounting flush with false ceiling. The unit price shall include connection to duct, and all accessories and works required to complete the work. All done according to drawings specifications and approval of the Engineer. Size 12"X12"

MR

30

12-14

No.

12-15

No.

UNDP - PAPP Engineering Unit

19 - 21

OCHA Roof Floor Cost Estimation

August 2008

Item No 12-16

Description Supply and Install return air aluminum grilles of size 24"X24" made by cooling industries or Equally approved, fixed 45-degree blades, double deflection, 1" thick frame, 3/4" spacing. The unit price shall include connection to duct, and all accessories and works required to complete the work. All done according to drawings specifications and approval of the Engineer. Supply and Install Wall mounted fire cabinet 120x80x30 cm type Lahavot or equally approved of cabinet thickness 2mm equiped with 1" swinging hose reel 30 m polystrene hose 1" aluminum nozzle, 12 kg powder extinguisher, 2" linen hose (2 x 25 m) with quick coupling, 2" nozzle, 2" landing valve, and all required fittings and valves.

Unit

Quantity Rate (US$)

Amount (US$)

No.

12-17

No.

Total Bill NO. 12 Sum Of Item [(12-1)-(12-17)] carried to summary

UNDP - PAPP Engineering Unit

20 - 21

OCHA Roof Floor Cost Estimation

August 2008

Summary
Item No Description Bill 1 Bill 2 Bill 3 Bill 4 Bill 5 Bill 6 Bill 7 Bill 8 Bill 9 Bill 11 Bill 12 Cleaning, Demolishing & Dismantling Works: Maintenance Works: Concrete Blocks Works: Plastering and Pointing: Tiling, Flooring and Marble Works: Carpentry And Joinery Works: Metal Works: Gypsum Boards and False Ceiling Works: Painting Works: Electrical Works: Plumbing, Sanitary And Mechanical Works: CONTINGENCIES ( ____%) Grand Total Discount Discount Amount Net Total Total

NET TOTAL SUM (in words ) : SIGNED AND SEALED AUTHOURIZED : TITLE : SIGNATURE : DATE : :

UNDP - PAPP Engineering Unit

SUMMARY