[Module Study Area 2011/2012] ENM305 - Online Distance *: Quiz for Topic 10 (Graded by First Attemp

User Policy and Data Protection Robert Gordon University 2011 My Profile My Calendar Library Study Skills Learner Services IT Helpdesk Student Involvement Student Portal Student Services >> INFOZONE Counselling and Wellbeing Turnitin Plagiarism Service Facebook Twitter You Tube LinkedIn RGU RSS RGU Web Help
CampusMoodle [Module Study Area 2011/2012] ENM305 - Online Distance * Quizzes Quiz for Topic 10 (Graded by First Attempt and limited to 40 minutes) Review of attempt 1

Hi, NATARAJAN Update profile | Logout

Quiz for Topic 10 (Graded by First Attempt and limited to 40 minutes) Review of attempt 1
Finish review

Started on Completed on Time taken Marks Grade Feedback

Sunday, 22 July 2012, 08:24 AM Sunday, 22 July 2012, 09:04 AM 39 mins 25 secs 6/14 43 out of a maximum of 100 (43%)
Online: 12 Not so good - you should consider further reading of the material.
1/5

campusmoodle.rgu.ac.uk/mod/quiz/review.php?attempt=217356&showall=true

7/22/12

[Module Study Area 2011/2012] ENM305 - Online Distance *: Quiz for Topic 10 (Graded by First Attemp

Q1. For maintenance planning and scheduling purposes it is assumed that a maintenance technician works a standard 150 hours per month. This standard Marks: 1 working time is termed as a Full Time Equivalent or FTE. If a maintenance department expends 26,250 hours in a given month, what is the FTE number?

Choose one answer.

a. 90 b. 145 c. 120 d. 175

Answer 26,250/150 = 175 FTE Correct


Marks for this submission: 1/1.

2
Marks: 1

Q2. If the maintenance department has an actual technician headcount of 140, how much overtime was worked during the month expressed as a percentage? Choose one answer. a. 12% b. 28% c. 25% d. 18% Answer: 26,250/140 = 187.5 hours/man therefore % Overtime is (187.5-150)/150 = 25% Correct
Marks for this submission: 1/1.

Q3. If a maintenance department has a work delivery budget of 25 million and historically 40% of this budget is expended on establishment, materials and 3rd Marks: 1 party costs. What is the notional target FTE for the department if the average inclusive rate for a technician is 30/hour?

Choose one answer.

a. 346 b. 278 c. 323 d. 225

campusmoodle.rgu.ac.uk/mod/quiz/review.php?attempt=217356&showall=true

2/5

7/22/12

[Module Study Area 2011/2012] ENM305 - Online Distance *: Quiz for Topic 10 (Graded by First Attemp

Answer: 25m x 0.6 = 15m 15m / 30 = 500,000 hours 500,000 / 12 = 41,666 hours/month 41,666 / 150 = 278 FTE Incorrect
Marks for this submission: 0/1.

Marks: 5 heat exchanger (it is

Q4. A maintenance planner receives a work order requisition to repair a leaking suspected that the exchanger has multiple tube failures). The operating plant has identified a Basic Start Date of the 2nd May 2012 and a required Basic Finish Date of the 7th June 2012. The maintenance planner has a standing instruction to plan all work on standard day shift hours (Monday Friday @ 7.5 hours per day). 4.1) How many days are available to complete the work? A) 27 days.

4.2) The planner identifies a resource requirement to complete the work order of 5.5 FTE for the duration of the work. What is the total number of Planned Hours for the work order? C) 1114 hours. 4.3) The operations team notify the planner that they now believe the tube leak to be more significant and request that the work goes to 24 hour continuous working. What is the earliest Basic Finish Date available for this mode of maintenance working? A) 9 May 2012 4.4) How many premium time hours were expended on this maintenance work order? D) 784 Hours. 4.5) If the inclusive rate for a maintenance technician is 30/hour and the cost differential between a standard hour and an average premium time hour is 12. What is percentage increase in cost does this change in working mode incur.
B) 28%

Partially correct
Marks for this submission: 3/5.

5
campusmoodle.rgu.ac.uk/mod/quiz/review.php?attempt=217356&showall=true 3/5

7/22/12

[Module Study Area 2011/2012] ENM305 - Online Distance *: Quiz for Topic 10 (Graded by First Attemp

Marks: 6

Q5. A Maintenance Manager undertakes a detailed review of his groups weekly performance data, shown in Table 1.
Work Order Completed by Basic Finish Date

Work Order

Planned Hours

Earned Hours Actual Hours

3,000

3,000

2,850

Yes

850

600

950

No

1,250

1,250

1,150

Yes

650

650

600

Yes

500

500

520

Yes

250

250

300

Not due.

2500

2,500

2600

Yes

700

350

330

No

125

125

150

Yes

10

450

300

450

No

5.1) What is the monthly On Time in Full percentage? A) 65% B) 67% C) 70% 5.2) What is the monthly Plan Attainment percentage? A) 85% B) 87% the monthly Full Time Equivalent number? A) 55.5 B) 66
campusmoodle.rgu.ac.uk/mod/quiz/review.php?attempt=217356&showall=true

C) 93% 5.3) What is C) 70.5


4/5

7/22/12

[Module Study Area 2011/2012] ENM305 - Online Distance *: Quiz for Topic 10 (Graded by First Attemp

5.4) What is the notional Productivity Rate? Answer: Productivity = Earned Hours / A) 0.96 Actual Hours = 9,525 / 9,900 = 0.96

B) 1.04

C) 1.1

5.5) Work Order


A) 2

requires further investigation, because Planned hours are more than actual Partially correct
Marks for this submission: 1/6.

Finish review

Privacy Policy My Moodle Main Menu Stay Connected User Policy and Data Protection Robert Gordon University 2011 My Profile My Calendar Library Study Skills Learner Services IT Helpdesk Student Involvement Student Portal Student Services >> INFOZONE Counselling and Wellbeing Turnitin Plagiarism Service Facebook Twitter You Tube LinkedIn RGU RSS RGU Web