You are on page 1of 10

Act ID

Description

Orig Dur

Early Start

Early Finish

2009 2010 2011 2012 MAY J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M

Design / Preconstruction - Airport Site Programming / Schematic Design 1270 Schematic Design & Precon - Airport Site Design Development 1260 Design Development & Precon - Airport Site Design / Preconstruction - Skyco Site Programming / Schematic Design 1000 Programming / Schematic Design 1010 State Review - Submit SD to SCO 1020 CM Prepare and Submit SD Estimate Design Development 1030 1040 1032 1035 1060 1065 1067 1080 100% DD Development Geotechnical Contract Modify Bldg Envelope Design (Fragnet) CM Prepare and Submit DD Estimate State Review - Submit DD to SCO DD Brainstorming Session DD Written Cost Study Analysis CM Pro / Con Evaluation of DD Cost Studies 200d 24AUG05 A 23AUG06 A 200d 24AUG06 A 23AUG07 A

122d 01MAY09 A 31AUG09 A 31d 31AUG09 A 01OCT09 A 31d 14SEP09 A 16OCT09 A 110d 46d 0 28d 30d 0 14d 14d 01SEP09 A 16OCT09 A 20NOV09 A 10FEB10 A 10FEB10 A 22MAR10 A 22MAR10 A 22MAR10 A 10FEB10 A 19NOV09 A 07JAN10 A 05MAR10 A 12MAR10 A 05APR10 A 05APR10 A

Programming / Schematic Design State Review - Submit SD to SCO CM Prepare and Submit SD Estimate 100% DD Development Geotechnical Contract Modify Bldg Envelope Design (Fragnet) CM Prepare and Submit DD Estimate State Review - Submit DD to SCO DD Brainstorming Session DD Written Cost Study Analysis CM Pro / Con Evaluation of DD Cost Studies Formal Presentation of DD Cost Studies 50% Construction Documents 50% CD Value Analysis Study 90% Construction Documents 90% CD Value Analysis Study 100% Construction Documents State Review - Submit 100% CD to SCO Revisions to Construction Docs State Review - Final Approval Prepare GMP Submit GMP (on or before) SCO Prepare Construction Contract Early Site Package Decission by CSI SCO Authorization to Proceed with Early Site Transfer Environmental Permits to State Early Site Package (Alb & Ass / CAMA) Submit Civil Plans to Dare Co. Planning Bd Early bar Progress bar Critical bar Summary bar Start milestone point Finish milestone point

1090 Formal Presentation of DD Cost Studies Construction Documents 1100 1110 1120 1130 1150 1160 1170 1180 GMP 1190 1200 1210 Civil Permits 1240 1253 1050 1243 1263 Start date Finish date Data date Run date Page number 50% Construction Documents 50% CD Value Analysis Study 90% Construction Documents 90% CD Value Analysis Study 100% Construction Documents State Review - Submit 100% CD to SCO Revisions to Construction Docs State Review - Final Approval Prepare GMP Submit GMP (on or before) SCO Prepare Construction Contract Early Site Package Decission by CSI SCO Authorization to Proceed with Early Site Transfer Environmental Permits to State Early Site Package (Alb & Ass / CAMA) Submit Civil Plans to Dare Co. Planning Bd 01MAY09 20AUG12 06APR10 13APR10 1A

0 06APR10 A 35d 10FEB10 A 16APR10 14d 16APR10 30APR10 51d 14d 34d 60d 14d 14d 16APR10 06JUN10 06JUN10 11JUL10 09SEP10 23SEP10 06JUN10 20JUN10 11JUL10 09SEP10 23SEP10 07OCT10 23OCT10 23OCT10 22NOV10

30d 23SEP10 0 30d 23OCT10 0 1d 30d 90d 0

30NOV09 A 30NOV09 A 19JAN10 A 15DEC09 A 30MAR10 A 19JAN10 A 20APR10 15FEB10 A

The Whiting-Turner Contracting Co. Coastal Studies Institute Work Breakdown Structure

Primavera Systems, Inc.

Act ID 1273 1283 1140 1250 Bid & Award

Description Plan Board Review of Civil Plans Board of Commissioners Review of Civil Plans Express Review - CAMA Major Permit SCO Review Early Site Package

Orig Dur

Early Start

Early Finish 08MAR10 A 05APR10 * 25MAY10 30MAY10 29JUN10 08OCT10

2009 2010 2011 2012 MAY J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M

0 0 50d 06APR10 A 40d 20APR10 30d 30MAY10 100d 29JUN10 0 22NOV10

Plan Board Review of Civil Plans Board of Commissioners Review of Civil Plans Express Review - CAMA Major Permit SCO Review Early Site Package Early Site Package (ESP) Advertise & Bid ESP - Bulkheads & Canal Grading NTP / Construction Start

1218 Early Site Package (ESP) Advertise & Bid 1219 ESP - Bulkheads & Canal Grading 1220 NTP / Construction Start Construction - Sitework, Site Utilities & Marina Sitework & Site Utilities 1280 Establish Sediment & Erosion Control 1290 Clear & Grub Site 1300 Perform Site Grading 1310 Bring Building Pads to Elevation 1330 Install Site Stormwater Piping 1360 Install Stone Base for Site Roads 1400 Install Bulkheads at Canal 1340 Install Site Sanitary Sewer Piping 1390 Install Underground Cistern 1410 Install Mooring Piles and Docks 1320 Install Site Water Service 1350 Install Site Wastewater Treatment Plant 1370 Install Site Hardscape 1420 Install Jib Crane at Dock 1430 Install Pump Station at Dock 1440 Install Fueling Station at Dock 1380 Install Landscaping Construction - Research Building Foundations 1450 Install Compacted Aggregate Piers 1460 Install Concrete Foundations & Retaining Walls Superstructure 1470 1480 2990 1482 1510 2020 1490 1500 Start date Finish date Data date Run date Page number Install Slab On Grade Pour Concrete Superstructure Install Masonry Walls - 1st Floor Pour Concrete Stairs Install Misc. Metals Install Masonry Elevator Shaft Install Masonry Walls & Parapet Install Structural Steel 01MAY09 20AUG12 06APR10 13APR10 2A

10d 10d 25d 10d 25d 20d 25d 25d 15d 25d 25d 60d 80d 15d 15d 10d 40d

22NOV10 02DEC10 12DEC10 13DEC10 07JAN11 07JAN11 07JAN11 01FEB11 01FEB11 01FEB11 26FEB11 26FEB11 27AUG11 15NOV11 15NOV11 15NOV11 09APR12 *

02DEC10 12DEC10 07JAN11 23DEC10 01FEB11 27JAN11 01FEB11 26FEB11 16FEB11 26FEB11 23MAR11 27APR11 15NOV11 30NOV11 30NOV11 25NOV11 01JUN12

Establish Sediment & Erosion Control Clear & Grub Site Perform Site Grading Bring Building Pads to Elevation Install Site Stormwater Piping Install Stone Base for Site Roads Install Bulkheads at Canal Install Site Sanitary Sewer Piping Install Underground Cistern Install Mooring Piles and Docks Install Site Water Service Install Site Wastewater Treatment Plant Install Site Hardscape Install Jib Crane at Dock Install Pump Station at Doc Install Fueling Station at Do

30d 23DEC10 25d 23JAN11 10d 180d 10d 25d 20d 10d 20d 10d 17FEB11 27FEB11 27FEB11 28MAY11 07AUG11 17AUG11 27AUG11 27AUG11

23JAN11 17FEB11 27FEB11 27AUG11 09MAR11 22JUN11 27AUG11 27AUG11 16SEP11 06SEP11

Install Compacted Aggregate Piers Install Concrete Foundations & Retaining Walls Install Slab On Grade Pour Concrete Superstructure Install Masonry Walls - 1st Floor Pour Concrete Stairs Install Misc. Metals Install Masonry Elevator Shaft Install Masonry Walls & Parapet Install Structural Steel Early bar Progress bar Critical bar Summary bar Start milestone point Finish milestone point

The Whiting-Turner Contracting Co. Coastal Studies Institute Work Breakdown Structure

Primavera Systems, Inc.

Act ID

Description

Orig Dur

Early Start

Early Finish 26SEP11 19FEB11 26SEP11 16OCT11 06OCT11 26OCT11 21OCT11 26OCT11 05NOV11 05DEC11 05DEC11 25DEC11 05NOV11 15NOV11 07DEC11 15JAN12 10JAN12 03JAN11 03JAN11 03JAN11 21FEB11 17JAN11 03MAR11 27AUG11 19MAR11 24MAR11 14MAR11 03APR11 25NOV11 30NOV11 10NOV11 10NOV11 31OCT11 05NOV11 10JAN12 20NOV11 25JAN12 30JAN12

2009 2010 2011 2012 MAY J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M

1520 Install Metal Roof Trusses Building Envelope 1630 Install Waterproofing at Elevator Pit 1550 Install Exterior Metal Stud Framing 1560 Install Exterior Sheathing (Densglass) 1610 Install Wood Blocking at Roof 1530 Install Standing Seam Roof 1540 Install Single Ply Roofing 1570 Install Exterior Air Barrier 1542 Install Terrace Roof 1580 Install Exterior Wood Siding 1582 Install Exterior Fiber Cement Siding 1590 Install Curtainwall Glazing 1620 Install Exterior Caulking 1544 Install Garden Roof 1660 Install Overhead Door 1600 Install Sunshades and Aerofoils 1650 Install Exterior Doors & Frames Plumbing, Mechanical & Electrical 1670 1680 1690 1770 1840 1780 1700 1790 1800 1820 1870 1710 1720 1722 1730 1810 1890 1760 1830 1740 1750 Start date Finish date Data date Run date Page number Install Underslab Drain Waste & Vent Install Underslab Water Lines Install Underslab Electric Install Geothermal Wells Install Transformer Install Ground Source Header Perform Elevated Slab Rough-in - PM&E Install Multi Stack Air Handler Install Cistern Pumps / Valves / Treatment Install Hot Water Heater Trim Out Mechanical Rooms Install In-Wall Plumbing Install In-Wall Electric Install In-Wall Tele - Data Install In-Wall / Chase HVAC Install Rooftop Unit (Split System and EF) Install Data Center HVAC Install Above Ceiling HVAC Install Generator Install Above Ceiling Plumbing Install Above Ceiling Electric 01MAY09 20AUG12 06APR10 13APR10 3A

20d 06SEP11 2d 30d 20d 10d 20d 15d 10d 15d 40d 40d 60d 10d 10d 2d 20d 15d 10d 10d 10d 45d 10d 10d 180d 10d 15d 5d 15d 40d 40d 20d 20d 10d 5d 60d 5d 60d 60d 17FEB11 27AUG11 26SEP11 26SEP11 06OCT11 06OCT11 16OCT11 21OCT11 26OCT11 26OCT11 26OCT11 26OCT11 05NOV11 05DEC11 25DEC11 25DEC11 23DEC10 23DEC10 23DEC10 07JAN11 07JAN11 21FEB11 27FEB11 09MAR11 09MAR11 09MAR11 19MAR11 16OCT11 21OCT11 21OCT11 21OCT11 21OCT11 31OCT11 10NOV11 15NOV11 25NOV11 30NOV11

Install Metal Roof Trusses

Install Waterproofing at Elevator Pit Install Exterior Metal Stud Frami Install Exterior Sheathing (Den Install Wood Blocking at Roof Install Standing Seam Roof Install Single Ply Roofing Install Exterior Air Barrier Install Terrace Roof Install Exterior Wood Sidin Install Exterior Fiber Ceme Install Curtainwall Glazin Install Exterior Caulking Install Garden Roof Install Overhead Door Install Sunshades and Install Exterior Doors &

Install Underslab Drain Waste & Vent Install Underslab Water Lines Install Underslab Electric Install Geothermal Wells Install Transformer Install Ground Source Header Perform Elevated Slab Rough-in Install Multi Stack Air Handler Install Cistern Pumps / Valves / Treatment Install Hot Water Heater Trim Out Mechanical Rooms Install In-Wall Plumbing Install In-Wall Electric Install In-Wall Tele - Data Install In-Wall / Chase HVAC Install Rooftop Unit (Split Sys Install Data Center HVAC Install Above Ceiling H Install Generator Install Above Ceiling P Install Above Ceiling Early bar Progress bar Critical bar Summary bar Start milestone point Finish milestone point

The Whiting-Turner Contracting Co. Coastal Studies Institute Work Breakdown Structure

Primavera Systems, Inc.

Act ID

Description

Orig Dur 25d 20d 25d 15d 20d 5d 21d 21d 21d 21d 10d 10d 21d 40d 5d 25d 10d 5d 25d 25d 10d 20d 15d 20d 7d 25d 10d 10d 10d 5d 15d 20d 5d 5d 5d 5d 10d 2d 5d

Early Start 14FEB12 29FEB12 14MAR12 14MAR12 28MAR12 06APR12 25APR12 25APR12 25APR12 25APR12 24MAY12 24MAY12 24MAY12 22JUN12 27AUG11 26SEP11 10JAN12 10JAN12 20JAN12 14FEB12 14FEB12 29FEB12 14MAR12 28MAR12 28MAR12 19APR12 25APR12 25APR12 25APR12 25APR12 09MAY12 30MAY12 30MAY12 30MAY12 30MAY12 30MAY12 30MAY12 30MAY12 20JUN12

Early Finish 14MAR12 28MAR12 18APR12 04APR12 25APR12 13APR12 24MAY12 24MAY12 24MAY12 24MAY12 07JUN12 07JUN12 22JUN12 20AUG12 01SEP11 21OCT11 20JAN12 15JAN12 14FEB12 14MAR12 24FEB12 28MAR12 04APR12 25APR12 06APR12 24MAY12 09MAY12 09MAY12 09MAY12 02MAY12 30MAY12 27JUN12 06JUN12 06JUN12 06JUN12 06JUN12 13JUN12 01JUN12 27JUN12

2009 2010 2011 2012 MAY J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M

1850 Install Switchgear 1761 Install Above Ceiling Sprinkler 1860 Install Electrical Sub Panels & Transformers 1880 Trim Out Electrical Room 1762 Install Above Ceiling Tele - Data 1776 Sprinkler Trim Out 1764 Plumbing Trim Out 1766 Electric Trim Out 1768 HVAC Trim Out 1769 Tele - Data Trim Out 1786 Fire Alarm Trim Out 1900 Install Data Center Racks 3520 Complete Controls 2150 Perform Testing Adjusting & Balancing Finishes and Fit-Out 2030 1916 1910 2140 1920 1930 2130 1950 1960 1940 2980 2110 1990 2000 2010 2040 1970 1980 2050 2060 2070 2080 2090 2100 2120 Start date Finish date Data date Run date Page number Stain / Seal Concrete Install Interior Metal Studs Install In-Wall Insulation Install Wood Blocking Install Interior Drywall Mud & Finish Interior Drywall Install Ornamental Metals Install Acoustical Ceiling Grid Paint Prime Coat Install Drywall Ceilings & Finish Install Acoustical Ceiling Tile Install Elevators Install Tile at Restrooms Install Epoxy Flooring at Labs Install Carpet Install VCT & Rubber Base Paint Finish Coats Install Casework Install Toilet Partitions Install Signage Install Marker Boards & Tack Boards Install Projectors & Projection Screens Install Window Treatment Install Controlled Environmental Room Install Interior Caulking 01MAY09 20AUG12 06APR10 13APR10 4A

Install Switchgear Install Above Ce Install Electric Trim Out Electr Install Above Sprinkler Trim Plumbing T Electric Trim HVAC Trim Tele - Data

Stain / Seal Concrete Install Interior Metal Studs Install In-Wall Insulatio Install Wood Blocking Install Interior Drywa Mud & Finish Inte Install Ornamental Install Acoustica Paint Prime Co Install Drywal Install Acoustic Install Elev Install Tile at Install Epoxy Install Carpe Install VCT & Paint Finis

The Whiting-Turner Contracting Co. Coastal Studies Institute Work Breakdown Structure

Primavera Systems, Inc.

Early bar Progress bar Critical bar Summary bar Start milestone point Finish milestone point

Act ID Commissioning

Description

Orig Dur 15d 15d 0 5d 10d 25d 10d 30d 0 0 0 0 0 0 0 0

Early Start 22MAR10 A 06MAY10 12DEC10 27APR11 26OCT11 24MAY12 24MAY12 22JUN12

Early Finish 08APR10 21MAY10 02MAY11 05NOV11 28JUN12 07JUN12 06AUG12 03JAN11 30NOV11 10JAN12 28MAR12 24MAY12 07JUN12 22JUN12 20AUG12 07MAR12 07JUN12 16JUL12 09AUG12 20AUG12

2009 2010 2011 2012 MAY J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M

2160 SD / DD Design Review of PM&E Systems 2170 CD Design Review of PM&E System 2180 Construction Kick-Off Meeting 2190 Commission Wastewater Treatment Plant 2230 Commission Thermal Envelope 2210 Commission Plumbing Systems 2220 Commission Electrical Systems 2200 Commission Mechanical System Major Inspections 2260 Underground Inspections 2270 In-Wall Inspections 3810 Building Dry-In 2280 Above Ceiling Inspections 2290 Elevator Inspections - DOL 2250 Life Safety Inspections 2300 Mechanical Systems Inspection - DOL 2310 State Construction Office Final Inspections Training, Punchlist & Completion 2340 Submit Operation & Maintenance Manuals 2320 Certificate of Occupancy 2350 Perform Owner Training 2240 Punchlist 2330 Project Complete Construction - Marine Service Building Foundations 1640 Install Concrete Foundations 2410 Install Masonry Foundations Superstructure 2360 Install Concrete Superstructure 2370 Install Slab on Grade 2380 Install Masonry Walls 2390 Install Steel Superstructure Building Envelope 2400 2500 3820 2440 2450 2480 Start date Finish date Data date Run date Page number Install Exterior Metal Stud Framing Install Wood Blocking at Roof Install Single Ply Roofing Install Exterior Sheathing (Densglass) Install Exterior Air Barrier Install Curtainwall Glazing 01MAY09 20AUG12 06APR10 13APR10 5A

SD / DD Design Review of PM&E Systems CD Design Review of PM&E System Construction Kick-Off Meeting Commission Wastewater Treatment Plant Commission Thermal Envelo

Underground Inspections

In-Wall Inspections Building Dry-In Above Ceiling I

35d 30JAN12 0 15d 22JUN12 30d 27JUN12 0

Submit Operation

21d 23DEC10 14d 14JAN11 28d 10d 15d 14d 21d 5d 21d 14d 14d 14d 14JAN11 28JAN11 28JAN11 11FEB11 25FEB11 25FEB11 25FEB11 18MAR11 01APR11 15APR11

14JAN11 28JAN11 11FEB11 07FEB11 12FEB11 25FEB11 18MAR11 02MAR11 18MAR11 01APR11 15APR11 29APR11

Install Concrete Foundations Install Masonry Foundations Install Concrete Superstructure Install Slab on Grade Install Masonry Walls Install Steel Superstructure Install Exterior Metal Stud Framing Install Wood Blocking at Roof Install Single Ply Roofing Install Exterior Sheathing (Densglass) Install Exterior Air Barrier Install Curtainwall Glazing Early bar Progress bar Critical bar Summary bar Start milestone point Finish milestone point

The Whiting-Turner Contracting Co. Coastal Studies Institute Work Breakdown Structure

Primavera Systems, Inc.

Act ID

Description

Orig Dur 21d 21d 14d 7d 7d 10d 7d 7d 7d 14d 14d 14d 7d 14d 14d 14d 14d 14d 14d 14d 14d 7d 7d 7d 14d 7d 7d 21d 3d 2d 14d 7d 2d 3d 7d 7d 2d

Early Start 29APR11 29APR11 29APR11 29APR11 29APR11 20MAY11 14JAN11 14JAN11 14JAN11 25MAR11 25MAR11 25MAR11 15APR11 15APR11 15APR11 15APR11 15APR11 15APR11 29APR11 29APR11 29APR11 06MAY11 06MAY11 13MAY11 13MAY11 20MAY11 20MAY11 23MAY11 23MAY11 07FEB11 25FEB11 18MAR11 25MAR11 29APR11 02MAY11 09MAY11 09MAY11

Early Finish 20MAY11 20MAY11 13MAY11 06MAY11 06MAY11 30MAY11 21JAN11 21JAN11 21JAN11 08APR11 08APR11 08APR11 22APR11 29APR11 29APR11 29APR11 29APR11 29APR11 13MAY11 13MAY11 13MAY11 13MAY11 13MAY11 20MAY11 27MAY11 27MAY11 27MAY11 13JUN11 26MAY11 09FEB11 11MAR11 25MAR11 27MAR11 02MAY11 09MAY11 16MAY11 11MAY11

2009 2010 2011 2012 MAY J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M

2460 Install Exterior Wood Siding 2470 Install Exterior Fiber Cement Siding 2490 Install Sunshades and Aerofoils 2510 Install Exterior Caulking 2530 Install Exterior Doors & Frames 2540 Install Overhead Door Plumbing, Mechanical & Electrical 2700 2710 2720 2730 2740 2750 2830 2840 2850 Install Underslab Drain Waste & Vent Install Underslab Water Lines Install Underslab Electric Install In-Wall Plumbing Install In-Wall Electric Install In-Wall Tele - Data Tele - Data Trim Out Install Cistern Pumps / Valves / Treatment Install Switchgear

Install Exterior Wood Siding Install Exterior Fiber Cement Siding Install Sunshades and Aerofoils Install Exterior Caulking Install Exterior Doors & Frames Install Overhead Door Install Underslab Drain Waste & Vent Install Underslab Water Lines Install Underslab Electric Install In-Wall Plumbing Install In-Wall Electric Install In-Wall Tele - Data Tele - Data Trim Out Install Cistern Pumps / Valves / Treatment Install Switchgear Install Electrical Sub Panels & Transformers Trim Out Mechanical Rooms Trim Out Electrical Room Install Above Ceiling Plumbing Install Above Ceiling Electric Install Above Ceiling HVAC Install Above Ceiling Sprinkler Install Above Ceiling Tele - Data HVAC Trim Out Fire Alarm Trim Out Plumbing Trim Out Electric Trim Out Perform Testing Adjusting & Balancing Sprinkler Trim Out Stain / Seal Concrete Install Trolley Hoist Install Interior Metal Studs Install Wood Blocking Install In-Wall Insulation Install Interior Drywall Mud & Finish Interior Drywall Paint Prime Coat Early bar Progress bar Critical bar Summary bar Start milestone point Finish milestone point

2860 Install Electrical Sub Panels & Transformers 2870 Trim Out Mechanical Rooms 2880 Trim Out Electrical Room 2760 Install Above Ceiling Plumbing 2770 Install Above Ceiling Electric 2780 Install Above Ceiling HVAC 2784 Install Above Ceiling Sprinkler 2790 Install Above Ceiling Tele - Data 2820 HVAC Trim Out 3020 Fire Alarm Trim Out 2800 Plumbing Trim Out 2810 Electric Trim Out 2890 Perform Testing Adjusting & Balancing 3030 Sprinkler Trim Out Finishes and Fit-Out 2650 2900 2556 2690 2550 2560 2570 2600 Start date Finish date Data date Run date Page number Stain / Seal Concrete Install Trolley Hoist Install Interior Metal Studs Install Wood Blocking Install In-Wall Insulation Install Interior Drywall Mud & Finish Interior Drywall Paint Prime Coat 01MAY09 20AUG12 06APR10 13APR10 6A

The Whiting-Turner Contracting Co. Coastal Studies Institute Work Breakdown Structure

Primavera Systems, Inc.

Act ID

Description

Orig Dur 7d 7d 7d 3d 3d 5d 2d 5d 2d 2d 15d 15d 7d 7d 7d 7d 0 0 0 0 0 0 0

Early Start 13MAY11 13MAY11 20MAY11 20MAY11 27MAY11 27MAY11 27MAY11 27MAY11 30MAY11 01JUN11 29MAR10 A 06MAY10 15APR11 20MAY11 27MAY11 27MAY11

Early Finish 20MAY11 20MAY11 27MAY11 23MAY11 30MAY11 01JUN11 29MAY11 01JUN11 01JUN11 03JUN11 17APR10 21MAY10 22APR11 27MAY11 03JUN11 03JUN11 21JAN11 08APR11 29APR11 20MAY11 27MAY11 27MAY11 13JUN11 13MAY11 27MAY11 17JUN11 05JUL11 05JUL11

2009 2010 2011 2012 MAY J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M

2580 Install Drywall Ceilings 2590 Install Acoustical Ceiling Grid 2610 Paint Finish Coats 3830 Install Acoustical Ceiling Tile 2620 Install Casework 2630 Install Tile at Restrooms 2670 Install Signage 2910 Install Window Treatment 2680 Install Interior Caulking 2660 Install Toilet Partitions Commissioning 3000 SD / DD Design Review of PM&E Systems 3010 CD Design Review of PM&E System 3070 Commission Thermal Envelope 3040 Commission Mechanical System 3050 Commission Plumbing Systems 3060 Commission Electrical Systems Major Inspections 3090 Underground Inspections 3100 In-Wall Inspections 3840 Building Dry-In 3110 Above Ceiling Inspections 3080 Life Safety Inspections 3130 Mechanical Systems Inspection - DOL 3140 State Construction Office Final Inspections Training, Punchlist & Completion 3180 Submit Operation & Maintenance Manuals 3160 Certificate of Occupancy 3190 Perform Owner Training 3150 Punchlist 3170 Project Complete Construction - Residential Buildings Foundations 3200 Install Compacted Aggregate Piers 3210 Install Concrete Foundations & Retaining Walls Superstructure 3220 3230 3250 Start date Finish date Data date Run date Page number Install Slab On Grade Pour Concrete Superstructure Install CMU Stair & Elevator Shaft 01MAY09 20AUG12 06APR10 13APR10 7A

Install Drywall Ceilings Install Acoustical Ceiling Grid Paint Finish Coats Install Acoustical Ceiling Tile Install Casework Install Tile at Restrooms Install Signage Install Window Treatment Install Interior Caulking Install Toilet Partitions SD / DD Design Review of PM&E Systems CD Design Review of PM&E System Commission Thermal Envelope Commission Mechanical System Commission Plumbing Systems Commission Electrical Systems

Underground Inspections In-Wall Inspections Building Dry-In Above Ceiling Inspections Life Safety Inspections Mechanical Systems Inspection - DOL State Construction Office Final Inspection Submit Operation & Maintenance Manuals Certificate of Occupancy Perform Owner Training Punchlist Project Complete

35d 08APR11 0 14d 03JUN11 21d 13JUN11 0

21d 23JAN11 28d 13FEB11 10d 27MAR11 21d 06APR11 40d 27APR11

13FEB11 13MAR11 06APR11 27APR11 06JUN11

Install Compacted Aggregate Piers Install Concrete Foundations & Retaining Walls Install Slab On Grade Pour Concrete Superstructure Install CMU Stair & Elevator Shaft Early bar Progress bar Critical bar Summary bar Start milestone point Finish milestone point

The Whiting-Turner Contracting Co. Coastal Studies Institute Work Breakdown Structure

Primavera Systems, Inc.

Act ID

Description

Orig Dur 90d 7d 7d 14d 3d 30d 14d 14d 7d 14d 45d 45d 28d 14d 14d 14d 14d 14d 14d 14d 14d 14d 21d 21d 21d 14d 10d 21d 14d 14d 14d 14d 14d 14d 14d 14d 28d

Early Start 27APR11 06JUN11 13JUN11 13JUL11 10MAR11 27JUL11 27JUL11 27JUL11 27JUL11 26AUG11 09SEP11 09SEP11 09SEP11 23SEP11 23SEP11 13MAR11 13MAR11 13MAR11 23SEP11 23SEP11 23SEP11 23SEP11 07OCT11 07OCT11 07OCT11 07OCT11 07OCT11 07OCT11 07OCT11 07OCT11 28OCT11 09DEC11 12DEC11 16DEC11 16DEC11 19DEC11 30DEC11

Early Finish 27JUL11 13JUN11 20JUN11 27JUL11 13MAR11 26AUG11 10AUG11 10AUG11 03AUG11 09SEP11 24OCT11 24OCT11 07OCT11 07OCT11 07OCT11 27MAR11 27MAR11 27MAR11 07OCT11 07OCT11 07OCT11 07OCT11 28OCT11 28OCT11 28OCT11 21OCT11 17OCT11 28OCT11 21OCT11 21OCT11 11NOV11 23DEC11 26DEC11 30DEC11 30DEC11 03JAN12 28JAN12

2009 2010 2011 2012 MAY J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M

3270 Install Wood Superstructure 2430 Install Pan Stairs 3240 Pour Concrete Pan Stairs 3260 Erect Structural Steel Building Envelope 3380 Waterproof Elevator Pit 3280 Install Exterior Sheathing 3350 Install Standing Seam Roofing 3360 Install Single Ply Roofing 3370 Waterproof Exterior Elevated Floors 3290 Install Exterior Air Barrier 3300 Install Exterior Wood Siding 3310 Install Exterior Fiber Cement Siding 3320 Install Storefront Glazing 3330 Install Exterior Caulking 3340 Install Exterior Doors & Frames Plumbing, Mechanical & Electrical 3600 Install Underslab Drain Waste & Vent 3610 Install Underslab Water Lines 3620 Install Underslab Electric 3660 Install Above Ceiling Plumbing 3680 Install Above Ceiling HVAC 3690 Install Above Ceiling Sprinkler 3700 Install Above Ceiling Tele - Data 3630 Install In-Wall Plumbing 3640 Install In-Wall Electric 3650 Install In-Wall Tele - Data 3750 Install Cistern Pumps / Valves / Treatment 3760 Install Switchgear 3770 Install Electrical Sub Panels & Transformers 3780 Trim Out Mechanical Rooms 3790 Trim Out Electrical Room 3670 Install Above Ceiling Electric 3740 Tele - Data Trim Out 3720 Electric Trim Out 3710 Plumbing Trim Out 3730 HVAC Trim Out 3850 Fire Alarm Trim Out 3800 Perform Testing Adjusting & Balancing Finishes and Fit-Out Start date 01MAY09 Finish date 20AUG12 Data date 06APR10 Run date 13APR10 Page number 8A Primavera Systems, Inc.

Install Wood Superstructure Install Pan Stairs Pour Concrete Pan Stairs Erect Structural Steel

Waterproof Elevator Pit Install Exterior Sheathing Install Standing Seam Roofing Install Single Ply Roofing Waterproof Exterior Elevated Floors Install Exterior Air Barrier Install Exterior Wood Siding Install Exterior Fiber Cement S Install Storefront Glazing Install Exterior Caulking Install Exterior Doors & Frames

Install Underslab Drain Waste & Vent Install Underslab Water Lines Install Underslab Electric Install Above Ceiling Plumbing Install Above Ceiling HVAC Install Above Ceiling Sprinkler Install Above Ceiling Tele - Dat Install In-Wall Plumbing Install In-Wall Electric Install In-Wall Tele - Data Install Cistern Pumps / Valves Install Switchgear Install Electrical Sub Panels & Trim Out Mechanical Rooms Trim Out Electrical Room Install Above Ceiling Electric Tele - Data Trim Out Electric Trim Out Plumbing Trim Out HVAC Trim Out Fire Alarm Trim Out Perform Testing Adju Early bar Progress bar Critical bar Summary bar Start milestone point Finish milestone point

The Whiting-Turner Contracting Co. Coastal Studies Institute Work Breakdown Structure

Act ID

Description

Orig Dur 7d 21d 21d 40d 10d 21d 7d 14d 21d 7d 14d 7d 7d 3d 7d 7d 7d 15d 15d 7d 7d 7d 7d 0 0 0 0 0 0 0 0

Early Start 06APR11 07OCT11 28OCT11 28OCT11 08NOV11 18NOV11 09DEC11 09DEC11 16DEC11 16DEC11 16DEC11 23DEC11 23DEC11 23DEC11 23DEC11 23DEC11 23DEC11 29MAR10 A 06MAY10 09SEP11 26DEC11 30DEC11 30DEC11

Early Finish 13APR11 28OCT11 18NOV11 07DEC11 18NOV11 09DEC11 16DEC11 23DEC11 07JAN12 23DEC11 30DEC11 30DEC11 30DEC11 26DEC11 30DEC11 30DEC11 30DEC11 17APR10 21MAY10 16SEP11 03JAN12 07JAN12 07JAN12 27MAR11 07OCT11 28OCT11 11NOV11 07DEC11 30DEC11 03JAN12 28JAN12 02DEC11 03JAN12 07JAN12 18FEB12 18FEB12

2009 2010 2011 2012 MAY J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M

3480 Stain / Seal Concrete 3410 Install Drywall Ceilings 3400 Install Interior Drywall 3570 Install Elevators 3390 Install In-Wall Insulation 3420 Mud & Finish Interior Drywall 3440 Paint Prime Coat 3450 Paint Finish Coats 3470 Install Tile at Restrooms 3510 Install Interior Caulking 3530 Install VCT & Rubber Base 3460 Install Casework 3490 Install Toilet Partitions 3500 Install Signage 3540 Install Window Treatment 3550 Install Kitchen Equipemnt 3560 Install Laundry Equipment Commissioning 5000 SD / DD Design Review of PM&E Systems 5010 CD Design Review of PM&E System 5050 Commission Thermal Envelope 5040 Commission Electrical Systems 5020 Commission Mechanical System 5030 Commission Plumbing Systems Major Inspections 4110 Underground Inspections 4170 Building Dry-In 4120 In-Wall Inspections 4130 Above Ceiling Inspections 4140 Elevator Inspections - DOL 4150 Mechanical Systems Inspection - DOL 4100 Life Safety Inspections 4160 State Construction Office Final Inspections Training, Punchlist & Completion 4010 3590 4020 3580 4000 Construction Start date Finish date Data date Run date Page number Submit Operation & Maintenance Manuals Certificate of Occupancy Perform Owner Training Punchlist Project Complete Boat Storage 01MAY09 20AUG12 06APR10 13APR10 9A

Stain / Seal Concrete Install Drywall Ceilings Install Interior Drywall Install Elevators Install In-Wall Insulation Mud & Finish Interior Dryw Paint Prime Coat Paint Finish Coats Install Tile at Restroom Install Interior Caulking Install VCT & Rubber Ba Install Casework Install Toilet Partitions Install Signage Install Window Treatme Install Kitchen Equipem Install Laundry Equipme SD / DD Design Review of PM&E Systems CD Design Review of PM&E System

Commission Thermal Envelope Commission Electrical S Commission Mechanica Commission Plumbing

Underground Inspections Building Dry-In In-Wall Inspections Above Ceiling Inspections Elevator Inspections - DO Mechanical Systems In Life Safety Inspections State Construction O

35d 28OCT11 0 0 21d 28JAN12 0

Submit Operation & Mainte Certificate of Occupanc Perform Owner Trainin Punchlist Project Complete Early bar Progress bar Critical bar Summary bar Start milestone point Finish milestone point

The Whiting-Turner Contracting Co. Coastal Studies Institute Work Breakdown Structure

Primavera Systems, Inc.

Act ID Foundations

Description

Orig Dur

Early Start

Early Finish 07JAN11 14JAN11 21JAN11 04FEB11 18FEB11 18FEB11 18FEB11 04MAR11 06MAR11

2009 2010 2011 2012 MAY J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M

2420 Install Concrete Foundations 2520 Install Masonry Foundations Superstructure 2920 Install Masonry Walls 2930 Install Wood Superstructure 2640 Install Gravel Base Building Envelope 2940 Install Cedar Facade 2950 Install Singly Ply Roofing 2960 Install Exterior Doors Finishes and Fit-Out 2970 Install Signage

14d 23DEC10 7d 07JAN11 7d 14JAN11 14d 21JAN11 3d 15FEB11 14d 04FEB11 14d 04FEB11 14d 18FEB11 2d 04MAR11

Install Concrete Foundations Install Masonry Foundations Install Masonry Walls Install Wood Superstructure Install Gravel Base Install Cedar Facade Install Singly Ply Roofing Install Exterior Doors Install Signage

Start date Finish date Data date Run date Page number

01MAY09 20AUG12 06APR10 13APR10 10A

The Whiting-Turner Contracting Co. Coastal Studies Institute Work Breakdown Structure

Primavera Systems, Inc.

Early bar Progress bar Critical bar Summary bar Start milestone point Finish milestone point

You might also like