NCT BACK-UP PROJECT, CHITTAGONG Work Program,2nd July, 2011

S.l. No. Description


1 2 3 4 5 6 7 8 9 10 11 Segment 1A Segment 2A (part) Segment 3 (part) Segment 4 (part)

Work Program of 2nd July, 2011


Regular Settlement Record 150mm Local sand filling Clearing & Grubbing. Sub-grade Preparation

Achievement of 1st July, 2011


Regular Settlement Record in progress 150mm Local sand filling in progress Clearing & Grubbing in progress. Sub-grade Preparation in progress

Remarks

Open Deep Drain(CH 600-650) Bracing placement & finishing casting Road Work Culvert (rail) RCC pipe Shore Pile Interlocking Block Dismantling work Earth Excavation of Road type-1 Rebar fabrication & Shuttering of wall Concrete pouring Concrete Pouring ILB plant shift CC/RCC Dismantling work at Segment 3 & 4 Rebar fabrication & Shuttering of wall in progress Concrete pouring in progress Rebar fabrication & Shuttering . ILB plant shift in progress CC/RCC Dismantling work at Segment 3 & 4 in progress

(Engr.Nityananda Nandi) Project Manager

NCT BACK-UP PROJECT, CHITTAGONG Work Program,3rd July, 2011

S.l. No. Description


1 2 3 4 5 6 7 8 9 10 11 Segment 1A Segment 2A (part) Segment 3 (part) Segment 4 (part)

Work Program of 3rd July, 2011


Regular Settlement Record 150mm Local sand filling Clearing & Grubbing. Sub-grade Preparation

Achievement of 2nd July, 2011


Regular Settlement Record in progress 150mm Local sand filling in progress Clearing & Grubbing in progress. Sub-grade Preparation in progress Bracing placement & finishing casting Earth Excavation of Road type-1 in progress Rebar fabrication & Shuttering of wall Concrete pouring in progress Rebar fabrication & Shuttering . ILB plant shift in progress CC/RCC Dismantling work at Segment 3 & 4 in progress

Remarks

Open Deep Drain(CH 600-650) Bracing placement & finishing casting Road Work Culvert (rail) RCC pipe Shore Pile Interlocking Block Dismantling work Earth Excavation of Road type-1 Concrete pouring of wall(1st lift) Concrete pouring Concrete Pouring ILB plant shift CC/RCC Dismantling work at Segment 3 & 4

(Engr.Nityananda Nandi) Project Manager

NCT BACK-UP PROJECT, CHITTAGONG Work Program,5th July, 2011

S.l. No. Description


1 2 3 4 5 Segment 1A Segment 2A (part) Segment 3 (part) Segment 4 (part)

Work Program of 5th July, 2011


Regular Settlement Record 150mm Local sand filling Clearing & Grubbing. Sub-grade Preparation

Achievement of 4th July, 2011


Regular Settlement Record in progress 150mm Local sand filling in progress Clearing & Grubbing in progress. Sub-grade Preparation in progress Bracing placement & finishing casting CC Executed Earth Excavation of Road type-1 in progress Concrete pouring of wall(1st lift) Rebar fabrication & Shuttering . ILB plant shift in progress CC/RCC Dismantling work at Segment 3 & 4 in progress

Remarks

Open Deep Drain(CH 600-650) Bracing placement & finishing casting Open Deep Drain(CH 500-525) Rebar fabrication of Base

6 7 8 9 10

Road Work Culvert (rail) Shore Pile Interlocking Block Dismantling work

Earth Excavation of Road type-1 Shuttering & Rebar fabrication Concrete Pouring ILB plant shift CC/RCC Dismantling work at Segment 3 & 4

(Engr.Nityananda Nandi) Project Manager

NCT BACK-UP PROJECT, CHITTAGONG Work Program,7th July, 2011

S.l. No. Description


1 2 3 4 5 Segment 1A Segment 2A (part) Segment 3 (part) Segment 4 (part)

Work Program of 7th July, 2011


Regular Settlement Record 300mm Sand Blanket Clearing & Grubbing. 150mm Sand filling

Achievement of 6th July, 2011


Regular Settlement Record in progress 150mm Local sand filling finished Clearing & Grubbing in progress. 150mm Sand filling in progress Bracing placement & finishing casting Rebar binding & Shuttering of wall in progress Earth Excavation finished Shuttering & Rebar fabrication of wall in progress Rebar fabrication & Shuttering . ILB plant shift in progress CC/RCC Dismantling work at Segment 3 & 4 in progress

Remarks

Open Deep Drain(CH 600-650) Bracing placement & finishing casting Open Deep Drain(CH 500-525) Rebar binding & Shuttering of wall

6 7 8 9 10

Road Work (Type-1) Culvert (rail) Shore Pile Interlocking Block Dismantling work

300mm sand Filling Shuttering & Rebar fabrication of wall Concrete Pouring ILB plant shift CC/RCC Dismantling work at Segment 3 & 4

(Engr.Nityananda Nandi) Project Manager

NCT BACK-UP PROJECT, CHITTAGONG Work Program,8th July, 2011

S.l. No. Description


1 2 3 4 5 Segment 1A Segment 2A (part) Segment 3 (part) Segment 4 (part)

Work Program of 8th July, 2011


Regular Settlement Record 300mm Sand Blanket Clearing & Grubbing. 150mm Sand filling

Achievement of 7th July, 2011


Regular Settlement Record in progress 150mm Local sand filling finished Clearing & Grubbing in progress. 150mm Sand filling in progress Bracing placement & finishing casting Rebar binding & Shuttering of wall in progress Earth Excavation finished Shuttering & Rebar fabrication of wall in progress Rebar fabrication & Shuttering . ILB plant shift in progress CC/RCC Dismantling work at Segment 3 & 4 in progress

Remarks

Open Deep Drain(CH 600-650) Bracing placement & finishing casting Open Deep Drain(CH 500-525) Rebar binding & Shuttering of wall

6 7 8 9 10

Road Work (Type-1) Culvert (rail) Shore Pile Interlocking Block Dismantling work

300mm sand Filling Shuttering & Rebar fabrication of wall Concrete Pouring ILB plant shift CC/RCC Dismantling work at Segment 3 & 4

(Engr.Nityananda Nandi) Project Manager

NCT BACK-UP PROJECT, CHITTAGONG Work Program,9th July, 2011

S.l. No. Description


1 2 3 4 5 Segment 1A Segment 2A (part) Segment 3 (part) Segment 4 (part)

Work Program of 9th July, 2011


Regular Settlement Record 300mm Sand Blanket Clearing & Grubbing. 150mm Sand filling

Achievement of 8th July, 2011


Regular Settlement Record in progress 150mm Local sand filling finished Clearing & Grubbing in progress. 150mm Sand filling in progress Bracing placement & finishing casting Concrete Pouring of 1st wall executed Sub grade Preparation Executed Shuttering & Rebar fabrication of wall in progress Rebar fabrication & Shuttering . ILB plant shift in progress CC/RCC Dismantling work at Segment 3 & 4 in progress

Remarks

Open Deep Drain(CH 600-650) Bracing placement & finishing casting Open Deep Drain(CH 500-525) Concrete Pouring of 2nd wall

6 7 8 9 10

Road Work (Type-1) Culvert (rail) Shore Pile Interlocking Block Dismantling work

300mm sand Filling Shuttering & Rebar fabrication of wall Concrete Pouring ILB plant shift CC/RCC Dismantling work at Segment 3 & 4

(Engr.Nityananda Nandi) Project Manager