Professional Documents
Culture Documents
CPM is a project-management technique that lays out all the activities needed to complete a task, the time it will take to complete each activity and the relationships between the activities. In the process of preparing 6 Tola jewelry set, following activities are involved: 1. 2. 3. 4. 5. 6. 7. 8. 9. Purchase of raw gold 24 k Conversion of gold into 22 k Wax Mold making Melting of gold Structure making Designing Stone cutting Stone setting in jewelry Polishing
1. Conversion of Gold:
The purest form of Gold is considered 24k which is equal to roughly 99.9 percent purity. It is converted into 22k for making jewelry. When we say 24k or 24k Gold jewelry, we mean that all the 24 parts in the gold are just pure gold without traces of any other metal. The main reason behind converting 24 k gold into 22k is that the 22k gold is soft it cannot be used for making the jewelry because the jewelry made by 24 k losses its real shape.
2. Melting of Gold:
In this process the 22k gold is melted and converted into gold plates than gold wires are made out of these gold wires and jewelry structure is made by pouring gold into wax. In melting process gold is place in crucible. Since gold melts at almost 2000 degrees Fahrenheit, you need a container that won't melt before the gold does. In melting of gold an acetylene torch is used.
3. Structure Making:
In this process jewels wax is used. In this process wax is being slice half width wise to create identical halves. Wax file is being used to create an even surface on our wax halves then pattern is created equal to length and size and alternatively we can use another mold (if available) or a copy of the jewelry to make and press it down into softened wax to make an impression. Then we will pour the molten gold into wax mold.
1|Page
4. Designing :
In this process the structured jewelry is designed.
6. Polishing:
In this process jewelry is being polished. The process of polishing is consisting of chemical polishing, brushing, drum machine, color balancing. In polishing process jewelry gets the shine.
Activity list:
Activity Activity Description
Purchase of raw gold Conversion of gold into 22 k Wax mold Melting Structure making Designing Stone cutting Stone setting in jewelry Polishing
Immediate predecessor
-------A A B C,D E E F,G
B C D E F G H
1 3 1 2 2 1 1
2|Page
PERT/CPM Network:
A [0, 2] B [2, 3] D [3, 4] E [5, 7]
1 2 [0, 2]
1 [3, 4] C [2, 5]
3 1 [4, 5]
5 2 [5, 7]
4
6
4
3 [2, 5]
2[7, 9] F [7, 9]
1 [8, 9] G [7, 8]
7
4
8
4
I [10, 12]
9 2[10, 12]
4
10
Activity Schedule:
Activity Earliest Start Latest Start (ES) in hrs. (LS) In hrs.
0 2 2 3 5 0 3 2 4 5
Critical Path
YES --YES --YES
A B C D E
3|Page
F G H I
7 7 9 10
7 8 9 10
9 8 10 12
9 9 10 12
0 1 0 0
Activities A, C, E, F, H, and I are critical activities and cannot be delayed because delay in any of these activities can result in the whole delay of process of making jewelry set.
Optimistic, Most Probable and Pessimistic Activity Time Estimates [in Hours]:
Activity
A B C D E F G H I
Optimistic (a)
1.50 0.50 2.50 0.50 1.50 1.50 0.50 0.50 1.50
Pessimistic (b)
8.50 1.50 3.50 1.50 2.50 2.50 1.50 1.50 2.50
After that expected time of each activity is calculated by using the following formula:
t = a + 4m +b / 6 With uncertain activity time we can use the common statistical measure of variance to describe the dispersion or variation in the activity time value. The variance the activity time is given by the following formula:
4|Page
Variance
1.3611 0.0278 0.0278 0.0278 0.0278 0.0278 0.0278 0.0278 0.0278
TOTAL
16 hours
5|Page
A B C D E F G H I Total
3 1 3 1 2 2 1 1 2 16
330,300 26,000 750 300 1,500 4,000 200 500 3,000 366,550
Critical in Path
YES ---YES ---YES
A B C D E
6|Page
F G H I
8 8 10 11
8 9 10 11
10 9 11 13
10 10 11 13
0 1 0 0
Budgeted Costs for an Earliest Starting Time Schedule [in Hours, in Rs.]:
Activity A B C D E F G H I Hourly cost Total process cost
110,100 110,100 110,100 26,250 550 250 750 750 2,200 2,000 500
1
110,100
2
110,100
3
110,100
10
11
12
13
26,000
250
250
250
300
750
750
2,000
2,000
200
500
1,500
1,500
1,500
1,500
110,100
220,200
330,300
356,550
357,100
357,350
358,100
358,850
361,050
363,050
363,550
365,050
366,550
7|Page
Budgeted Costs for Latest Starting Time Schedule [in Hours] [Rs.]:
Activity 1 A B C D E F G
250 110,100
2
110,100
3
110,100
10
11
12
13
26,000
250
250
300
750
750
2,000
2,000
200
500
1,500
1,500
Hourly Cost
110,100
110,100
110,100
250
26,250
550
750
750
2,000
2,200
500
1,500
1,500
110,100
220,200
330,300
330,350
356,800
357,350
358,100
358,850
360,850
363,050
363,550
365,050
366,550
8|Page
800,000 700,000 600,000 500,000 400,000 300,000 200,000 100,000 0 1 2 3 4 5 6 7 8 9 10 11 12 13 Latest Start Time Budgeted Cost Schedule Earliest Start Time Budgeted Cost Schedule Schedule
800000 700000 600000 500000 400000 300000 200000 100000 0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 Budgeted Total Cost Schedule for earliest Starting Time Budgeted Total Cost Schdule for latest Staritng Time
9|Page