Sub-Contract Procurement Schedule

Contract Name:-3 Villas @ Jaffliya Based on Programme No. Work Package Preliminary Design Info. Issued By Design Team Design Information Issued Clients Comments to Client for Received Comment Prepared by :Waseem Rajah No: Date Programme Requirements 1 Last Updated Placing Details Date Subcontract Returned

Package Number

Work Package Description

Comments/Notes

Subcontractors

Information Issued by Design Team

S/C Enquiry Issue Date

Actual Issue Date

Tender period

Evaluation Period

Authorisation Required By

Actual Date Authorised

Order to be Placed By

Actual Order Issue Date

Lead-in Period Commencement on site (Weeks)

Sub-contractor Appointed

Trades 1 GI Pipe railing, painted finish in roof Omitted in latest drawing Silver Crown Silver Crown submittal sent to GSG consultant on 13/09/2012 for Bin Ghurair approval Prometal One quotation from Ferforge received 3 Supplying & Fixing of 38mm thick Galvanized steel cat ladder Fer Forge Standard Fabricators AMW Rigid Metal Works Silver Crown Al Karam Phoeinix technical submittal sent to consultant for approval on 12/09/2012 Consent Phoeinix Juma Al Majid Apex Precast Embarqoh 6 External Plaster Received one quote from Khalfan Al Falasi Emerald Castle Technical Khalfan Al Falasi Sandoos Technical Unique Paints TS Paints 7 Primer Colour Coats Al Safa Contracting Jotun Paints Plus Paints Unique Paints TS Paints 8 Heavy Texture 4 coats solvent based epoxy paint system for all exposed surface Colour Coats Al Safa Contracting Jotun Paints Plus Paints John Aluminium Standard Fabricators Aluminium Doors & Windows 9 Golden Tower Prequalification Golden Tower Al Fahya Aluminium sent to consultant on 12/09/2012 for approval Al Reyami

Steel Doors

Interlock Pavers

Prime Cost Items

Stair Case Railing(Excluded)

excluded in the scope

One quotation from Ferforge received 10 Balcony Railing

Fer Forge Standard Fabricators AMW Rigid Metal Works Silver Crown Al Karam

11

Roof Railing

Omitted in latest drawing

One quotation from Ferforge received 12 Supply and fix wrought iron grill to basement window

Fer Forge Standard Fabricators AMW Rigid Metal Works Silver Crown Al Karam

13

Natural Stone Cladding to wall

14

Pitched Roof

Page 1 of 2

Sub-Contract Procurement Schedule


Contract Name:-3 Villas @ Jaffliya Based on Programme No. Work Package Preliminary Design Info. Issued By Design Team Design Information Issued Clients Comments to Client for Received Comment Prepared by :Waseem Rajah No: Date Programme Requirements 1 Last Updated Placing Details Date Subcontract Returned

Package Number

Work Package Description

Comments/Notes

Subcontractors

Information Issued by Design Team

S/C Enquiry Issue Date

Actual Issue Date

Tender period

Evaluation Period

Authorisation Required By

Actual Date Authorised

Order to be Placed By

Actual Order Issue Date

Lead-in Period Commencement on site (Weeks)

Sub-contractor Appointed

Provisional Sums 02 No of Supply & installation of Galvanised steel spiral stair case as per the drawing

15

Omitted in latest drawing o

16

GRC Works One quotation from Ferforge received Fer Forge Standard Fabricators AMW Rigid Metal Works Silver Crown Al Karam

17

Wrought Iron Grill, gate for boundary Wall

18

Electrically operated roof skylights