You are on page 1of 0

Factory Acceptance Testing

Guideline
Process Industry
IEC 61511
Version: 1.0 Last Edited:2006-08-25


www.sp.se/safeprod
-1-















Factory Acceptance Testing
Guideline












Comments on this report are gratefully received by
Johan Hedberg
at SP Swedish National Testing and Research Institute
mailto:johan.hedberg@sp.se











Factory Acceptance Testing
Guideline
Process Industry
IEC 61511
Version: 1.0 Last Edited:2006-08-25


www.sp.se/safeprod
-2-

Summary
According to the standard IEC 61551 the factory acceptance test (FAT) is not a requirement but is
necessary to carry out if the application software of the logic solver is complex or if the architecture is
using redundant arrangements. The general questions in the planning phase of the FAT concern the
tests to be performed and how to deal with the tests. The FAT is a practical way to test and verify the
correct operation of the safety instrumented system.
Factory Acceptance Testing
Guideline
Process Industry
IEC 61511
Version: 1.0 Last Edited:2006-08-25


www.sp.se/safeprod
-3-

Table of contents
1. Introduction..................................................................................................................................... 4
1.1. Purpose................................................................................................................................... 4
1.2. References.............................................................................................................................. 4
1.3. Scope...................................................................................................................................... 4
2. Definitions and abbreviations.......................................................................................................... 4
3. Factory acceptance test (FAT)......................................................................................................... 6
3.1. Planning................................................................................................................................. 6
3.2. Test activities......................................................................................................................... 7
3.3. Test result............................................................................................................................... 8
3.4. Checklist................................................................................................................................ 9
FAT specification form......................................................................................................................... 11



Factory Acceptance Testing
Guideline
Process Industry
IEC 61511
Version: 1.0 Last Edited:2006-08-25


www.sp.se/safeprod
-4-
1. Introduction
1.1. Purpose
The aim of this document is to try to describe the requirements concerning factory acceptance testing,
FAT, according to the standard IEC 61511. The FAT is a customized testing procedure for different
types of systems and the tests are executed before the final installation at the plant. The FAT is not a
requirement but recommended to be carried out, according to the standard IEC 61511, if the
application software of the logic solver is fairly complex or if the architecture of the safety
instrumented system is using redundant arrangements. In many cases it is difficult to predict the
correct operation of the safety instrumented system or consequences due to failures in some parts of
the safety instrumented system. For that reason the FAT is a valuable check of the safety issues. The
test cases are selected during the planning phase in order to test the safety measures as far as possible.

1.2. References
[1] IEC 61511-1 Functional safety- Safety instrumented systems for the process
industry sector, Part 1: Framework, definitions, system, hardware and software requirements
[2] IEC 61511-2 Functional safety- Safety instrumented systems for the process
industry sector- Part 2: Guidelines for the application of IEC 61511-1
[3] IEC 61511-3 Functional safety- Safety instrumented systems for the process
industry sector- Part 3: Guidance for the determination of the required safety integrity level

1.3. Scope
This document covers the parts in IEC 61511 concerning the FAT. The FAT can be used as an
integration test or during validation of the safety instrumented system.

2. Definitions and abbreviations

basic process control system (BPCS)
system which responds to input signals from the process, its associated equipment, other
programmable systems and/or an operator and generates output signals causing the process
and its associated equipment to operate in the desired manner but which does not perform
any safety instrumented functions with a claimed SIL 1 (3.2.3 in IEC 61511-1)

fault
abnormal condition that may cause a reduction in, or loss of, the capability of a functional unit
to perform a required function (3.2.21 in IEC 61511-1)

failure
termination of the ability of a functional unit to perform a required function (3.2.20 in IEC 61511-1)

error
discrepancy between a computed, observed or measured value or condition and the true,
specified or theoretically correct value or condition (3.2.18 in IEC 61511-1)

hazard
Factory Acceptance Testing
Guideline
Process Industry
IEC 61511
Version: 1.0 Last Edited:2006-08-25


www.sp.se/safeprod
-5-
potential source of harm (3.2.31 in IEC 61511-1)

hazardous situation
circumstance in which a person is exposed to hazard(s) (3.1.3 in IEC 61508-4)

hazardous event
hazardous situation which results in harm (3.1.4 in IEC 61508-4)

harm
physical injury or damage to the health of people, either directly or indirectly, as a result of
damage to property or to the environment (3.2.30 in IEC 61511-1)

instrument
apparatus used in performing an action (typically found in instrumented systems) (3.2.38 in IEC
61511-1)
NOTE Instrumented systems in the process sector are typically composed of sensors (for example,
pressure, flow, temperature transmitters), logic solvers or control systems (for example, programmable
controllers, distributed control systems), and final elements (for example, control valves). In special
cases, instrumented systems can be safety instrumented systems (see 3.2.72 in IEC 61511-1).

process risk
risk arising from the process conditions caused by abnormal events (including BPCS
malfunction)
NOTE 1 The risk in this context is that associated with the specific hazardous event in which SIS are
to be used to provide the necessary risk reduction (i.e., the risk associated with functional safety).
(3.2.54 in IEC 61511-1)

safety instrumented function (SIF)
safety function with a specified safety integrity level which is necessary to achieve functional
safety and which can be either a safety instrumented protection function or a safety
instrumented control function (3.2.71 in IEC 61511-1)
Factory Acceptance Testing
Guideline
Process Industry
IEC 61511
Version: 1.0 Last Edited:2006-08-25


www.sp.se/safeprod
-6-
3. Factory acceptance test (FAT)
The main objective of the FAT is to test the safety instrumented system (logic solver and associated
software together). The tests are normally executed during the final part of the design and engineering
phase before the final installation at the plant. The FAT is a customized procedure of checking the
safety instrumented system and the safety instrumented functions according to the safety requirements
specification, see figure 1.



Figure 1. Factory acceptance testing

The FAT includes appropriate general testing procedures for verification of the correct operation of
the safety instrumented system. Since the testing activities are general methods the FAT is applicable
to programmable or non programmable safety instrumented systems. The most important part of the
FAT addresses specification of the test cases i.e. clear description of the test cases, well structured test
procedures and relevant test cases.
3.1. Planning
The planning presents a set op of the appropriate tests to be carried out and who is responsible for
developing the test cases. Appropriate levels of competence and independence of assessors are
required. The realization of tests shall be described as well as the personnel responsible to carry out
the test. The test protocol is developed during the planning and furthermore who is responsible to
attest the test protocol.

The procedures to carry out the FAT shall be well defined and documented in a proper way. Each test
procedure shall be described in a logical sequence i.e. how to test the application software and
hardware. The needed competence for involved test personnel is described during the planning. It is
recommended that personnel with experience suitable for the intended process application and safety
instrumented system deals with the FAT planning. Experience form different areas such as process
Factory Acceptance Testing
Guideline
Process Industry
IEC 61511
Version: 1.0 Last Edited:2006-08-25


www.sp.se/safeprod
-7-
design, hardware design, and software design will contribute the FAT planning with relevant test
cases. The content of the FAT tests shall be appropriate for the intended safety instrumented system.

The planning includes procedures for corrective action in case of discovered failure during execution
of the tests. The test planning shall also include the test criteria on which the completion of the tests
shall be judged. The safety instrumented systems physical location and the function dependency of
other systems or interfaces are issues that are specified during the planning phase.

The configuration of the logic solver is needed during the planning in order to prepare the tests.

In order to develop integration tests it may be required to contact the supplier of the logic solver or
other relevant suppliers for the included units in the safety instrumented system.
3.2. Test activities
The FAT is normally performed at the manufacturers work shop. The manufacturer checks that the
safety instrumented system works as intended and according to the requirements stated in the safety
requirements specification, SRS. During the FAT the manufacturer checks as far as possible that:
the used equipment are according to the specification e.g. compatible HW and SW versions
the used equipment are installed according to manufacturers specification
the inputs and the outputs are connected according to the drawings
the calibration of the equipment are correct
the trip points operate according to the requirements in the SRS
the logic solver and associated software operate according to the requirements in the SRS
the outputs and their actions behave according to the SRS
the reset functions operate according to the SRS
the alarms operate according to the SRS
the operator functions operate according to the SRS
the bypass functions operate according to the SRS
the manual shutdown functions operate according to the SRS
the diagnostic alarm functions operate according to the SRS


The outputs from the safety instrumented function are examined during different test cases e.g.
simulation of inputs in order to verify that the safety instrumented functions meet the requirements in
the safety requirements specification.

If the FAT reveals weaknesses in the design and engineering phase or in the safety requirements
specification phase these phases have to be modified according to the result of the FAT. In order to
check the modifications the safety instrumented system has to be re- tested.

The FAT should take place on a defined version of the logic solver and the configuration of the logic
solver has to be specified in order to establish relevant test cases.

In order to perform the tests the need of tools is described and also a description of the test
environment.

Any modifications or change should be subject to a safety analysis in order to determine the extent of
the impact on each safety instrumented function and the extent of re-test should be defined and
implemented.

Factory Acceptance Testing
Guideline
Process Industry
IEC 61511
Version: 1.0 Last Edited:2006-08-25


www.sp.se/safeprod
-8-


3.3. Test result
All the test cases of the FAT shall be described in the documentation and furthermore if the objectives
and criteria of the tests have been met or not. Discovered failures during the test are documented and
the reasons for the failures are also documented supported by necessary actions to correct the failures.

If there are modifications of the safety instrumented system it is necessary to carry out a safety
analysis in order to determine if the safety is affected and if re- testing is necessary.


Factory Acceptance Testing
Guideline
Process Industry
IEC 61511
Version: 1.0 Last Edited:2006-08-25


www.sp.se/safeprod
-9-
3.4. Checklist
FAT checklist
Yes/No Comments
Is the FAT necessary?


Is the FAT planning performed?


Are personal skills considered?


Are all test cases described?


Are corrective actions in case of
failures considered?


Are the expected test results for
each test case described?


Are the procedures to carry out
the FAT well defined and
documented in a proper way?


Are the CE requirements
fulfilled?


Are all HW and SW parts
delivered according to the
specification?


Are all the safety instrumented
functions identified?


Have skills and competence
resources been considered of
the involved personnel?


Are all modes of operation
identified?


Are the safe states identified?


Are process inputs, trip points
and normal operating range
identified?



Are all equipment installed
according to manufacturers
specification?


Factory Acceptance Testing
Guideline
Process Industry
IEC 61511
Version: 1.0 Last Edited:2006-08-25


www.sp.se/safeprod
-10-
Are process inputs identified
and their trip points tested,
according to the SRS?


Are process outputs identified
and their actions tested
according to the SRS?


Are relationships between
inputs and outputs tested and
behave according to the SRS?


Are computations by the SIS
performed correct?


Is the response time tested and
according to the SRS?


Are reset functions tested and
behave according to the SRS?


Are operator functions tested
and behave according to the
SRS?


Are alarms tested and behave
according to the SRS?


Is degraded mode of operation
tested e.g. missing air supply,
missing electrical supply?


Are bypass functions working
properly and according to the
SRS?


Is manual shutdown working
properly and according to the
SRS?


Are diagnostic alarm functions
working properly and according
to the SRS?







www.sp.se/safeprod
-11-

Factory Acceptance Testing

FAT specification form ver: 1.0
Page
11
FAT ID:

SIS name:
FAT specification form



A. Document issued for:
Project:



Company:



Process:



Plant / Site:



SIS Safety Instrumented System:




SIF Safety Instrumented Function(s):












www.sp.se/safeprod
-12-

Factory Acceptance Testing

FAT specification form ver: 1.0
Page
12
FAT ID:

SIS name:


B. Document sources:
Safety Requirements Specification: Organization: Date/version:











Risk assessment by:










Organization: Date/version:


C. Related documents:
Type: Document ID: Rev: Comments:































www.sp.se/safeprod
-13-

Factory Acceptance Testing

Test case
Page
13
FAT ID: SIS name:
Test case no (SIF id and nr):



1A General information for test cases
The test case concerns SIF (name):

Name of the test case:

The objectives and criteria of the test:



The test case concerns SIF:


Physical location (process part)

Developer of the test case:
(Name and Company)

Responsible to carry ot the test case:
(Name and Company)

Responsible to attest the test protocol:
(Name and Company)

Test environment (used test equipment):



Description of configuration of the logic solver:
Including components ( e.g. type, brand)
Software:

Version number

HW parts Version number



www.sp.se/safeprod
-14-

Factory Acceptance Testing

Test case
Page
14
FAT ID: SIS name:
Test case no (SIF id and nr):




1B. Logical description
Logical description of the test cases:




www.sp.se/safeprod
-15-

Factory Acceptance Testing

Test case
Page
15
FAT ID: SIS name:
Test case no (SIF id and nr):







1C. Expected result
Description:
1D. Corrective action on failure of the test
Description:





www.sp.se/safeprod
-16-

Factory Acceptance Testing

Test case
Page
16
FAT ID: SIS name:
Test case no (SIF id and nr):









Date: ...............................................


Name..................................................................................................................................
(Responsible to attest the test protocol)


Company.............................................................................................................................
1E. FAT Result
The test criteria have been met or not (Yes/No): Date and signature:
Description of the test result:

Date and signature

Remaining actions: Date and signature

You might also like