SCOPE OF WORK & TECHNICAL SPECIFICATIONS FOR

REPLACEMENT OF HVAC SYSTEM AT EASTERN OPERATING AREA IN 18 SUBSTATIONS (SUBSTATION PORTION)

PTS14ED416
DISTRIBUTION ENGINEERING DEPARTMENT-EAST SAUDI ELECTRICITY COMPANY

CERT.

SAUDI ELECTRICITY COMPANY


```` .

DESCRIPTION

CHKD

APPD

NO.

SCOPE OF WORK AND TECHNICAL SPECIFICATIONS


3 2

REVISIONS

DRAWN BY DATE CHKD BY

FOR

REPLACEMENT OF HVAC SYSTEM AT EASTERN


APPROVED ENGINEERING DEPT.

OPERATING AREA SUBSTATIONS

ADC / DVD

OPERATING DEPT.

PTS-14ED416 ( DRAFT )
CERTIFIED BY: :

MQQ

THIS DRAWING IS NOT TO BE USED FOR CONSTRUCTION OR FOR ORDERING MATERIALS UNTIL CERTIFIED AND DATED

[[PTS- 14ED416 doc. MQQ/ADC/DVD) November 2013 ]


PLANT NO. INDEX PTS NO. PAGE NO. REV.

SCOPE OF WORK AND TECHNICAL SPECIFICATIONS


JOB ORDER NO.

1-- 1443026 111

FOR REPLACEMENT OF HVAC SYSTEM AT EASTERN OPERATING AREA SUBSTATION

D047

PTS-14ED416

SAUDI ARABIA

1 OF 77

CERT.

SAUDI ELECTRICITY COMPANY


TABLE OF CONTENTS

CHKD

APPD

SECTION I INTRODUCTION 1.01 1.02 1.03 1.04


3 2 1

PAGE 4-19 4 4 4 19 20-39 20 21 21 22 22 23 24 35 35 36 36 37 39 39 39 41- 50

DESCRIPTION

GENERAL PROJECT DESCRIPTION PROJECT SUMMARY ABBREVIATION

NO.

REVISIONS

II

BASIC REQUIREMENTS AND GUIDELINES 2.01 2.02 2.03 2.04 2.05 2.06 2.07 2.08 2.09 2.10 2.11 2.12 2.13 2.14 2.15 GENERAL CONDITIONS KICK OFF MEETING BASE DESIGN PHASE BASE DESIGN REVIEW PROJECT DRAWINGS PROGRESS REPORTING QA/QC REQUIREMENTS COMMISSIONING, OPERATION AND MAINTENANCE MANUALS TECHNICAL DATA MANUALS TEST RECORD BOOK PLANT TAGGING OF EQUIPMENT AND INDEPENDENT COMPONENTS LOSS PREVENTION REQUIREMENTS NAMEPLATE DATA REMOVAL/DISMANTLE OF EXISTING EQUIPTMENT SHUTDOWN & OUTAGE COORDINATION

DRAWN BY DATE CHKD BY

APPROVED ENGINEERING DEPT.

ADC / DVD

OPERATING DEPT.

CERTIFIED

BY: :

MQQ

III

SCOPE OF WORK

THIS DRAWING IS NOT TO BE USED FOR CONSTRUCTION OR FOR ORDERING MATERIALS UNTIL CERTIFIED AND DATED

3.01 GENERAL 3.02 MECHANICAL WORKS 3.03 41


[[PTS- 14ED416 doc. MQQ/ADC/DVD) November 2013 ]
PLANT NO. INDEX

41 41 WORKS

ELECTRICAL

PTS NO.

PAGE NO.

REV.

SCOPE OF WORK AND TECHNICAL SPECIFICATIONS


JOB ORDER NO.

1-- 1443026 111

FOR REPLACEMENT OF HVAC SYSTEM AT EASTERN OPERATING AREA SUBSTATION

D047

PTS-14ED416

SAUDI ARABIA

2 OF 77

CERT.

SAUDI ELECTRICITY COMPANY


WORK 45

APPD

3.05

3.04 CIVIL 44 PROJECT DESIGN DOCUMENTS, CALCULATIONS AND DRAWINGS STANDARDS, CODES AND SPECIFICATION

CHKD

3.06
DESCRIPTION

47 50-74

IV

EQUIPMENT/MATERIALS & TECHNICAL SPECIFICATIONS

REVISIONS

4.01 4.02 4.03 4.04 V

GENERAL HVAC SYSTEM REQUIREMENTS ELECTRICAL SYSTEM REQUIREMENTS CIVIL / STRUCTURAL REQUIREMENTS

50 50 61 62 75 75 75

NO.

DRAWN BY DATE CHKD BY

COMMISIONING TESTS 5.01 5.02 GENERAL SUBSTATION EQUIPTMENT

APPROVED ENGINEERING DEPT.

ADC / DVD

APPENDICES

OPERATING DEPT.

APPENDIX 1

- TABLE -1: LIST OF EXISTING HVAC UNITS

APPENDIX II
CERTIFIED

- DRAWING CONTROL SHEET (ET-800489 )

APPENDIX III

- MATERIAL DATA SCHEDULES

BY: :

MQQ

APPENDIX IV

- TECHNICAL DATA MANUAL

THIS DRAWING IS NOT TO BE USED FOR CONSTRUCTION OR FOR ORDERING MATERIALS UNTIL CERTIFIED AND DATED

[[PTS- 14ED416 doc. MQQ/ADC/DVD) November 2013 ]


PLANT NO. INDEX PTS NO. PAGE NO. REV.

SCOPE OF WORK AND TECHNICAL SPECIFICATIONS


JOB ORDER NO.

1-- 1443026 111

FOR REPLACEMENT OF HVAC SYSTEM AT EASTERN OPERATING AREA SUBSTATION

D047

PTS-14ED416

SAUDI ARABIA

3 OF 77

CERT.

SAUDI ELECTRICITY COMPANY

CHKD

APPD

SECTION I - INTRODUCTION
DESCRIPTION

1.01 GENERAL This Scope of WORK and Technical Specification (PTS-14ED416 ) describe the specific scope of WORK that the CONTRACTOR is required to carry out on Lump Sum Turnkey (LSTK) basis until the successful commissioning, completion and final acceptance of the required WORK by Saudi Electricity Company - Eastern Region Branch (SEC-ERB).

NO.

REVISIONS

DRAWN BY DATE CHKD BY

1.02 PROJECT DESCRIPTION COMPANY requires removing the old existing HVAC Equipment, Design and installing new Air Conditioning Units with sufficient capacities capable of handling the cooling/heating load requirement for the whole Bldg. For the Eighteen (18) Substation in the Eastern Operating Area.

APPROVED ENGINEERING DEPT.

ADC / DVD

1.03 PROJECT SUMMARY The CONTRACTOR shall perform on LSTK basis, the Engineering Design, Material Procurement, Quality Management, Factory Inspection/Testing, Transport and Delivery to Site, Construction, Survey and Site inspection, Testing and Commissioning, and all associated WORK (as applicable) and services until final handing over of the system in a satisfactorily working and operating condition to the COMPANY as specified in this Scope of WORK and Technical Specifications. The PROJECT shall comprise of Eastern Operating Area Substation as follows:

OPERATING DEPT.

CERTIFIED

BY: :

MQQ

A. Aziziyah 69/13.8 kV Substation Substation


1. Removal of existing old Two (2) Packaged Type A/C Units, A/C Air Supply/Return Ducts and all accessories. . 2. Design, Supply and Installation of two (2) New Sets of Packaged Type A/C units, with 100% capacity each capable of handling the whole Building Total Cooling and Heating Load including Room extension . The Contractor shall provide design calculation for the new A/C units as per requirement. 3. Design, Fabricate and install new Air Supply and Return Air Duct , diffusers, grilles, dampers, duct heater, duct detectors and all accessories for Air Distribution System for proper cooling and Air Balancing .
[[PTS- 14ED416 doc. MQQ/ADC/DVD) November 2013 ]
PLANT NO. INDEX PTS NO. PAGE NO. REV.

THIS DRAWING IS NOT TO BE USED FOR CONSTRUCTION OR FOR ORDERING MATERIALS UNTIL CERTIFIED AND DATED

SCOPE OF WORK AND TECHNICAL SPECIFICATIONS


JOB ORDER NO.

1-- 1443026 111

FOR REPLACEMENT OF HVAC SYSTEM AT EASTERN OPERATING AREA SUBSTATION

D047

PTS-14ED416

SAUDI ARABIA

4 OF 77

CERT.

SAUDI ELECTRICITY COMPANY

CHKD

APPD

4. Provide and Install Digital Direct Control (DDC) Panel for the HVAC System and interfaced to SCADA and FACP. A dedicated alarm for HVAC system fail "HVAC SYSTEM FAIL" shall be provided . This alarm shall be wired/terminated to the existing spare point of SCADA RTU. The contractor shall commission and test the alarm system with company representative. 5. Provide and install new Main Distribution Panels, Main Circuit Breaker, Disconnect switch, Control Panel, Wirings/Cables and all accessories for the new HVAC Units 6. Removal of existing HVAC Equipment Concrete Foundation and design and Construction of new Foundation. Foundation shall be painted as per Company Standard.

NO.

DESCRIPTION 3

REVISIONS

7. Fabrication and Installation of Pipe Barrier, Steel Sunshade Cover and Support for the new HVAC Equipment

DRAWN BY DATE CHKD BY

8. Installation of new Condensate Drainage Piping System and Construction of Seepage pit. 9. Restoration Works. All areas affected by the works shall be repaired, restored to a clean ,operational status, and all opening shall be cover with the same Building Materials. 10. Painting of Mechanical Room flooring, ceiling and walls as per Company Standard

APPROVED ENGINEERING DEPT.

ADC / DVD

B.
OPERATING DEPT.

Kaab 69/13.8kV Substation


1. Removal of existing two(2) Split Type A/C Units , Air Supply/Return Air Ducts and all accessories . 2. Design, Supply and Installation of two (2) New Split Type A/C units with 100% capacity each capable of handling the whole Building Total Cooling and Heating Load including extension Rooms . The Contractor shall provide design calculation for the new A/C units as per requirement. 3. Design, Fabricate and install new Air Supply and Return Air Duct , diffusers, grilles, dampers, duct heater, duct detectors and all accessories for Air Distribution System for proper cooling and Air Balancing . 4. Provide and Install Digital Direct Control (DDC) Panel for the HVAC System and interfaced to SCADA and FACP. A dedicated alarm for HVAC system fail "HVAC SYSTEM FAIL" shall be provided. This alarm shall be wired/terminated to the existing spare point of SCADA RTU. The contractor shall commission and test the alarm system with company representative.

CERTIFIED

BY: :

MQQ

THIS DRAWING IS NOT TO BE USED FOR CONSTRUCTION OR FOR ORDERING MATERIALS UNTIL CERTIFIED AND DATED

[[PTS- 14ED416 doc. MQQ/ADC/DVD) November 2013 ]


PLANT NO. INDEX PTS NO. PAGE NO. REV.

SCOPE OF WORK AND TECHNICAL SPECIFICATIONS


JOB ORDER NO.

1-- 1443026 111

FOR REPLACEMENT OF HVAC SYSTEM AT EASTERN OPERATING AREA SUBSTATION

D047

PTS-14ED416

SAUDI ARABIA

5 OF 77

CERT.

SAUDI ELECTRICITY COMPANY

APPD

5. Provide and install new Distribution Panel, Main Circuit Breaker, Circuit Breaker, Disconnect switch, Control Panel , Wirings/Cables and all accessories for the new HVAC Units. 6. Removal of existing HVAC Equipment Concrete Foundation and design and Construction of new Foundation. Foundation shall be painted as per Company Standard.

DESCRIPTION

CHKD

7. Fabrication and Installation of Pipe Barrier, Steel Sunshade Cover and Support for the new HVAC Equipment

NO.

REVISIONS

8. Installation of new Condensate Drainage Piping System and Construction of Seepage pit. 9. Restoration Works. All areas affected by the works shall be repaired, restored to a clean ,operational status, and all opening shall be cover with the same Building Materials. 10. Painting of Mechanical Room flooring, ceiling and walls as per Company Standard.

DRAWN BY DATE CHKD BY

APPROVED ENGINEERING DEPT.

C. National Guard Substation


ADC / DVD

1. Removal of Existing Two (2) Split Type A/C Units, Air Supply/Return Ducts and all accessories .
OPERATING DEPT.

2. Design, Supply and Installation of two (2) New Sets of Split Type or Packaged Type A/C units wich ever is applicable in the Substation Area, with 100% capacity each capable of handling the whole Building Total Cooling and Heating Load including Room extension . The Contractor shall provide design calculation for the new A/C units as per requirement. 3. Design, Fabricate and install new Air Supply and Return Air Duct , diffusers, grilles, dampers, duct heater, duct detectors and all accessories for Air Distribution System for proper cooling and Air Balancing . 4. Provide and Install Digital Direct Control (DDC) Panel for the HVAC System and interfaced to SCADA and FACP. A dedicated alarm for HVAC system fail "HVAC SYSTEM FAIL" shall be provided. This alarm shall be wired/terminated to the existing spare point of SCADA RTU. The contractor shall commission and test the alarm system with company representative.

CERTIFIED

BY: :

MQQ

THIS DRAWING IS NOT TO BE USED FOR CONSTRUCTION OR FOR ORDERING MATERIALS UNTIL CERTIFIED AND DATED

5. Provide and install new Distribution Panel, Main Circuit Breaker, Circuit Breaker, Disconnect switch, Control Panel, Wirings/Cables and all accessories for the new HVAC Units.

[[PTS- 14ED416 doc. MQQ/ADC/DVD) November 2013 ]


PLANT NO. INDEX PTS NO. PAGE NO. REV.

SCOPE OF WORK AND TECHNICAL SPECIFICATIONS


JOB ORDER NO.

1-- 1443026 111

FOR REPLACEMENT OF HVAC SYSTEM AT EASTERN OPERATING AREA SUBSTATION

D047

PTS-14ED416

SAUDI ARABIA

6 OF 77

CERT.

SAUDI ELECTRICITY COMPANY

APPD

6. Removal of existing HVAC Equipment Concrete Foundation and design and Construction of new Foundation. Foundation shall be painted as per Company Standard.

CHKD

DESCRIPTION

7. Fabrication and Installation of Pipe Barrier, Steel Sunshade Cover and Support for the new HVAC Equipment

8. Installation of new Condensate Drainage Piping System and Construction of Seepage pit. 9. Extention or adjustment of concrete gutter for access road that will be affected by the new HVAC Units.

NO.

REVISIONS

DRAWN BY DATE CHKD BY

10. Restoration Works. All areas affected by the works shall be repaired, restored to a clean ,operational status, and all opening shall be cover with the same Building Materials. 11. Painting of Mechanical Room flooring, ceiling and walls as per Company Standard.

APPROVED ENGINEERING DEPT.

D. Muraikabat 69/13.8 kV Substation


ADC / DVD

1. Removal of existing two (2) Split Type A/C Units Air Supply/Return Ducts and all accessories.
OPERATING DEPT.

2. Design, Supply and Installation of Two (2) New Split Type A/C Units with 100% capacity each capable of handling the Total Cooling and Heating Load of the whole Bldg. including Room extension . The Contractor shall provide design calculation for the new A/C units as per requirement. 3. Design, Fabricate and install new Air Supply and Return Air Duct , diffusers, grilles, dampers, duct heater, duct detectors and all accessories for Air Distribution System for proper cooling and Air Balancing . 4. Provide and Install Digital Direct Control (DDC) Panel for the HVAC System and interfaced to SCADA and FACP. A dedicated alarm for HVAC system fail "HVAC SYSTEM FAIL" shall be provided. This alarm shall be wired/terminated to the existing spare point of SCADA RTU. The contractor shall commission and test the alarm system with company representative. 5. Provide and install new Main Distribution Panel, Main Circuit Breaker, Circuit Breaker, Disconnect switch,Contro Panel , Wirings/Cables and all accessories for the new HVAC Units. 6. Modification of existing HVAC Equipment ( ACCU & AHU ) Concrete Foundation . Foundation shall be painted as per Company Standard.
[[PTS- 14ED416 doc. MQQ/ADC/DVD) November 2013 ]
PLANT NO. INDEX PTS NO. PAGE NO. REV.

CERTIFIED

BY: :

MQQ

THIS DRAWING IS NOT TO BE USED FOR CONSTRUCTION OR FOR ORDERING MATERIALS UNTIL CERTIFIED AND DATED

SCOPE OF WORK AND TECHNICAL SPECIFICATIONS


JOB ORDER NO.

1-- 1443026 111

FOR REPLACEMENT OF HVAC SYSTEM AT EASTERN OPERATING AREA SUBSTATION

D047

PTS-14ED416

SAUDI ARABIA

7 OF 77

CERT.

SAUDI ELECTRICITY COMPANY

APPD

CHKD

7. Removal/Repainting and re-installation of Pipe Barrier and design and Construction of Steel Sunshade Cover and Support for the new HVAC Equipment

8. Installation of new Condensate Drainage Piping System and Construction of Seepage pit.
DESCRIPTION

9. Restoration Works. All areas affected by the works shall be repaired, restored to a clean ,operational status, and all opening shall be cover with the same Building Materials. 10. Painting of Mechanical Room flooring, ceiling and walls as per Company Standard .

NO.

REVISIONS

E. Nabia 69/13.8 kV Substation


DRAWN BY DATE CHKD BY

1. Removal of existing two (2) Split Type A/C Units , Air Supply/Return Ducts and all accessories . 2. Design, Supply and Installation of two (2) New Split Type A/C units, with 100% capacity each capable of handling the Total Cooling and Heating Load of the whole bldg. including Room extension. The Contractor shall provide design calculation for the new A/C units as per requirement. 3. Design, Fabricate and install new Air Supply and Return Air Duct , diffusers, grilles, dampers, duct heater, duct detectors and all accessories for Air Distribution System for proper cooling and Air Balancing .

APPROVED ENGINEERING DEPT.

ADC / DVD

OPERATING DEPT.

4. Provide and Install Digital Direct Control (DDC) Panel for the HVAC System and interfaced to SCADA and FACP. A dedicated alarm for HVAC system fail "HVAC SYSTEM FAIL" shall be provided. This alarm shall be wired/terminated to the existing spare point of SCADA RTU. The contractor shall commission and test the alarm system with company representative.
CERTIFIED

BY: :

MQQ

5. Provide and install new Main Distribution Panel, Main Circuit Breaker, Circuit Breaker, Disconnect Switch, Control Panel, wirings/cables and all accessories for the new HVAC Units. 6. Modification of existing HVAC Equipment Concrete Foundation as per requirement of new HVAC Units. Foundation shall be painted as per Company Standard. 7. Removal/repainting and re-installation of existing Pipe Barrier and design and construction of Steel Sunshade Cover and Support for the new HVAC ACCU Equipment.

THIS DRAWING IS NOT TO BE USED FOR CONSTRUCTION OR FOR ORDERING MATERIALS UNTIL CERTIFIED AND DATED

8. Installation of new Condensate Drainage Piping System and Construction of Seepage pit.

[[PTS- 14ED416 doc. MQQ/ADC/DVD) November 2013 ]


PLANT NO. INDEX PTS NO. PAGE NO. REV.

SCOPE OF WORK AND TECHNICAL SPECIFICATIONS


JOB ORDER NO.

1-- 1443026 111

FOR REPLACEMENT OF HVAC SYSTEM AT EASTERN OPERATING AREA SUBSTATION

D047

PTS-14ED416

SAUDI ARABIA

8 OF 77

CERT.

SAUDI ELECTRICITY COMPANY

APPD

9. Restoration Works. All areas affected by the works shall be repaired, restored to a clean ,operational status, and all opening shall be cover with the same Building Materials. 10. Painting of Mechanical Room flooring, ceiling and walls as per Company Standard

DESCRIPTION

CHKD

F. Qatif 69/13.8kV Grid Station


1. Removal of all existing two (2) Packaged Type A/C Units or Split . Air Supply/Return Ducts and all accessories. 2. Removal of existing Window Type A/C units and cover opening with the same Building materials. 3. Design, Supply and Installation of two (2) New Sets of Packaged Type A/C units or Split Type A/C Units wich ever is applicable in the Substation Area, with 100% capacity each capable of handling the Total Cooling and Heating Load of the whole bldg. including Room extension. The Contractor shall provide design calculation for the new A/C units as per requirement. 4. Design, Fabricate and install new Air Supply and Return Air Duct , diffusers, grilles, dampers, duct heater, duct detectors and all accessories for Air Distribution System for proper cooling and Air Balancing . 5. Provide and Install Digital Direct Control (DDC) Panel for the HVAC System and interfaced to SCADA and FACP. A dedicated alarm for HVAC system fail "HVAC SYSTEM FAIL" shall be provided. This alarm shall be wired/terminated to the existing spare point of SCADA RTU. The contractor shall commission and test the alarm system with company representative. 6. Provide and install nee Distribution Panels, Main Circuit Breakers, Circuit Breaker, Disconnect switch, Control Panel , wirings/cables and all accessories for the new HVAC Units. 7. Removal of existing HVAC Equipment Concrete Foundation and design and Construction of new Foundation. Foundation shall be painted as per Company Standard. 8. Fabrication and Installation of New Removable Pipe Barrier, Steel Sunshade Cover and Support for the new HVAC Equipment
THIS DRAWING IS NOT TO BE USED FOR CONSTRUCTION OR FOR ORDERING MATERIALS UNTIL CERTIFIED AND DATED

NO.

REVISIONS

DRAWN BY DATE CHKD BY

APPROVED ENGINEERING DEPT.

ADC / DVD

OPERATING DEPT.

CERTIFIED

BY: :

MQQ

9. Installation of new Condensate Drainage Piping System and Construction of Seepage pit. 10. Restoration Works. All areas affected by the works shall be repaired, restored to a clean ,operational status, and all opening shall be cover with the same Building Materials.
[[PTS- 14ED416 doc. MQQ/ADC/DVD) November 2013 ]
PLANT NO. INDEX PTS NO. PAGE NO. REV.

SCOPE OF WORK AND TECHNICAL SPECIFICATIONS


JOB ORDER NO.

1-- 1443026 111

FOR REPLACEMENT OF HVAC SYSTEM AT EASTERN OPERATING AREA SUBSTATION

D047

PTS-14ED416

SAUDI ARABIA

9 OF 77

CERT.

SAUDI ELECTRICITY COMPANY

CHKD

APPD

11. .Painting of Mechanical Room flooring, ceiling and walls as per Company Standard

DESCRIPTION

G. Al-Rabwah 69/13.8kV Substation


1. Removal of existing Two (2) Split Type A/C Units , Air Supply/Return Ducts and all accessories. 2. Design, Supply and Installation of two (2) New Sets of Split Type A/C units, with 100% capacity each capable of handling the Total Cooling and Heating Load of the whole building including Room extension. The Contractor shall provide design calculation for the new A/C units as per requirement. 3. Design, Fabricate and install new Air Supply and Return Air Duct , diffusers, grilles, dampers, duct heater, duct detectors and all accessories for Air Distribution System for proper cooling and Air Balancing ..

NO.

REVISIONS

DRAWN BY DATE CHKD BY

APPROVED ENGINEERING DEPT.

ADC / DVD

4. Provide and Install Digital Direct Control (DDC) Panel for the HVAC System and interfaced to SCADA and FACP. A dedicated alarm for HVAC system fail "HVAC SYSTEM FAIL" shall be provided. This alarm shall be wired/terminated to the existing spare point of SCADA RTU. The contractor shall commission and test the alarm system with company representative. 5. Provide and install new Distribution Panels, Main Breakers, Circuit Breaker, Disconnect switch, Control Panel , wirings/cables and all accessories for the new HVAC Units. 6. Modification/Extension of existing HVAC Equipment Concrete Foundation as per requirement. Foundation shall be painted as per Company Standard.

OPERATING DEPT.

CERTIFIED

BY: :

MQQ

7. Fabrication and Installation of Steel Sunshade Cover and Support for the new HVAC Equipment and Removal/ Repainting and re-installation of existing Pipe Barrier.

8. Installation of new Condensate Drainage Piping System and Construction of Seepage pit. 9. Restoration Works. All areas affected by the works shall be repaired, restored to a clean ,operational status, and all opening shall be cover with the same Building Materials. 10. Painting of Mechanical Room flooring, ceiling and walls as per Company Standard

THIS DRAWING IS NOT TO BE USED FOR CONSTRUCTION OR FOR ORDERING MATERIALS UNTIL CERTIFIED AND DATED

[[PTS- 14ED416 doc. MQQ/ADC/DVD) November 2013 ]


PLANT NO. INDEX PTS NO. PAGE NO. REV.

SCOPE OF WORK AND TECHNICAL SPECIFICATIONS


JOB ORDER NO.

1-- 1443026 111

FOR REPLACEMENT OF HVAC SYSTEM AT EASTERN OPERATING AREA SUBSTATION

D047

PTS-14ED416

SAUDI ARABIA

10 OF 77

CERT.

SAUDI ELECTRICITY COMPANY

CHKD

APPD

H. Bayouniyah 69/13.8kV Substation 1. Removal of existing Split Type A/C Units (2 Nos. ), Air Supply/Return air Ducts and all accessories. 2. Design, Supply and Installation of two (2) New Split Type A/C units, with 100% capacity each capable of handling the Total Cooling and Heating Load of the Room Extension and the area cover by the existing units. The Contractor shall provide design calculation for the new A/C units as per requirement. 3. Design, Fabricate and install new Air Supply and Return Air Duct , diffusers, grilles, dampers, duct heater, duct detectors and all accessories for Air Distribution System for proper cooling and Air Balancing .
3 2 1

NO.

DESCRIPTION

REVISIONS

DRAWN BY DATE CHKD BY

4. Provide and Install Digital Direct Control (DDC) Panel for the HVAC System and interfaced to SCADA and FACP. A dedicated alarm for HVAC system fail "HVAC SYSTEM FAIL" shall be provided . This alarm shall be wired/terminated to the existing spare point of SCADA RTU. The contractor shall commission and test the alarm system with company representative. 5. Provide and install new Main Distribution Panel, Main Breaker, Circuit Breaker, Disconnect switch, Control Panel, wirings/cables and all accessories for the new HVAC Units . 6. Removal of existing HVAC Equipment Concrete Foundation and design and Construction of new Foundation. Foundation shall be painted as per Company Standard. 7. Fabrication and Installation of new Removable Pipe Barrier, Steel Sunshade Cover and Support for the new HVAC Equipment

APPROVED ENGINEERING DEPT.

ADC / DVD

OPERATING DEPT.

8. Installation of new Condensate Drainage Piping System and Construction of Seepage pit. 9. Restoration Works. All areas affected by the works shall be repaired, restored to a clean ,operational status, and all opening shall be cover with the same Building Materials. 10. Painting of Mechanical Room flooring, ceiling and walls as per Company

CERTIFIED

BY: :

MQQ

Standard
.

I. Ittisalat 69/13.8kV Substation


THIS DRAWING IS NOT TO BE USED FOR CONSTRUCTION OR FOR ORDERING MATERIALS UNTIL CERTIFIED AND DATED

1.

Remove all existing two(2) Split Type A/C Units , Air Supply/Return Ducts and all accessories.

2. Design, Supply and Installation of two (2) New Sets of Split


[[PTS- 14ED416 doc. MQQ/ADC/DVD) November 2013 ]
PLANT NO. INDEX PTS NO. PAGE NO. REV.

SCOPE OF WORK AND TECHNICAL SPECIFICATIONS


JOB ORDER NO.

1-- 1443026 111

FOR REPLACEMENT OF HVAC SYSTEM AT EASTERN OPERATING AREA SUBSTATION

D047

PTS-14ED416

SAUDI ARABIA

11 OF 77

CERT.

SAUDI ELECTRICITY COMPANY

APPD

3. 000000000000000000000000000000000000000000000000000000000000000000 Type A/C units, with 100% capacity each capable of handling the Total Cooling and Heating Load of Room extension and area cover by existing Units. The Contractor shall provide design calculation for the new A/C units as per requirement. 4. Design, Fabricate and install new Air Supply and Return Air Duct , diffusers, grilles, dampers, duct heater, duct detectors and all accessories for Air Distribution System for proper cooling and Air Balancing 5. Provide and Install Digital Direct Control (DDC) Panel for the HVAC System and interfaced to SCADA and FACP. A dedicated alarm for HVAC system fail "HVAC SYSTEM FAIL" shall be provided. This alarm shall be wired/terminated to the existing spare point of SCADA RTU. The contractor shall commission and test the alarm system with company representative.
3 2 1

NO.

DESCRIPTION

CHKD

REVISIONS

DRAWN BY DATE CHKD BY

6. Provide and install new Main Distribution Panels, Main Breaker, Circuit Breaker, Disconnect switch, Control Panel, wirings/cables and all accessories for the new HVAC Units. 7. Removal of existing HVAC Equipment Concrete Foundation and design and Construction of new Foundation. Foundation shall be painted as per Company Standard. 8. Fabrication and Installation of Pipe Barrier, Steel Sunshade Cover and Support for the new HVAC Equipment

APPROVED ENGINEERING DEPT.

ADC / DVD

9. Installation of new Condensate Drainage Piping System and Construction of Seepage pit. 10. Restoration Works. All areas affected by the works shall be repaired, restored to a clean ,operational status, and all opening shall be cover with the same Building Materials. 11. Painting of Mechanical Room flooring, ceiling and walls as per Company

OPERATING DEPT.

Standard
CERTIFIED

BY: :

MQQ

J. Riyadh Water Pump Substation


1. Remove all existing two(2) Split Type A/C Units, Air Supply/Return Ducts and all accessories . 2. Design, Supply and Installation of two (2) New Sets of Packaged Type A/C units, with 100% capacity each capable of handling the Total Cooling and Heating Load of the whole bldg . The Contractor shall provide design calculation for the new A/C units as per requirement. 3. Fabricate and install new Air Supply and Return Air Duct , diffusers, grilles, dampers, duct heater, duct detectors and all accessories for Air Distribution System for proper cooling and Air Balancing
[[PTS- 14ED416 doc. MQQ/ADC/DVD) November 2013 ]
PLANT NO. INDEX PTS NO. PAGE NO. REV.

THIS DRAWING IS NOT TO BE USED FOR CONSTRUCTION OR FOR ORDERING MATERIALS UNTIL CERTIFIED AND DATED

SCOPE OF WORK AND TECHNICAL SPECIFICATIONS


JOB ORDER NO.

1-- 1443026 111

FOR REPLACEMENT OF HVAC SYSTEM AT EASTERN OPERATING AREA SUBSTATION

D047

PTS-14ED416

SAUDI ARABIA

12 OF 77

CERT.

SAUDI ELECTRICITY COMPANY

APPD

. 4. Provide and Install Digital Direct Control (DDC) Panel for the HVAC System and interfaced to SCADA and FACP. A dedicated alarm for HVAC system fail "HVAC SYSTEM FAIL" shall be provided. This alarm shall be wired/terminated to the existing spare point of SCADA RTU. The contractor shall commission and test the alarm system with company representative. 5. Provide and install new Main Distribution Panel,, Main Breaker, Circuit Breaker, Disconnect switch, Control Panel , wirings/cables and all accessories for the new HVAC Units. 6. Removal of existing HVAC Equipment Concrete Foundation and design and Construction of new Foundation. Foundation shall be painted as per Company Standard.
3 2 1

NO.

DESCRIPTION

CHKD

REVISIONS

7. Fabrication and Installation of New Removable Pipe Barrier, Steel Sunshade Cover and Support for the new HVAC Equipment

DRAWN BY DATE CHKD BY

8. Installation of new Condensate Drainage Piping System and Construction of Seepage pit. 9. Remove and Replace existing Exhaust Fan with explosion proof type exhaust fan in Battery Room Area. 10. Removal and replacement of all Ceiling Acoustic Tiles, runner, steel support, and accessories. 11. Removal and replacement of all Lighting fixtures and all accessories.

APPROVED ENGINEERING DEPT.

ADC / DVD

OPERATING DEPT.

12. Construct and install partition and access door for Battery Room. Materials shall be the same of existing wall. 13. Restoration Works. All areas affected by the works shall be repaired, restored to a clean ,operational status, and all opening shall be cover with the same Building Materials.

CERTIFIED

BY: :

MQQ

K. Al-Hada 69/13.8kV Substation


1. Remove all existing two (2) Split Type A/C Units, Air Supply/Return Ducts and all accessories. . 2. Design, Supply and Installation of two (2) New Split Type A/C Units with 100% capacity each capable of handling the Total Cooling and Heating Load of the whole Bldg including Room extension if any. The Contractor shall provide design calculation for the new A/C units as per requirement.

THIS DRAWING IS NOT TO BE USED FOR CONSTRUCTION OR FOR ORDERING MATERIALS UNTIL CERTIFIED AND DATED

[[PTS- 14ED416 doc. MQQ/ADC/DVD) November 2013 ]


PLANT NO. INDEX PTS NO. PAGE NO. REV.

SCOPE OF WORK AND TECHNICAL SPECIFICATIONS


JOB ORDER NO.

1-- 1443026 111

FOR REPLACEMENT OF HVAC SYSTEM AT EASTERN OPERATING AREA SUBSTATION

D047

PTS-14ED416

SAUDI ARABIA

13 OF 77

CERT.

SAUDI ELECTRICITY COMPANY

APPD

3. Fabricate and install new Air Supply and Return Air Duct , diffusers, grilles, dampers, duct heater, duct detectors and all accessories for Air Distribution System for proper cooling and Air Balancing

CHKD

4. Provide and Install Digital Direct Control (DDC) Panel for the HVAC System and interfaced to SCADA and FACP. A dedicated alarm for HVAC system fail "HVAC SYSTEM FAIL" shall be provided. This alarm shall be wired/terminated to the existing spare point of SCADA RTU. The contractor shall commission and test the alarm system with company representative. 5. Provide and install new Main Distribution Panels, Main Circuit Breaker, Circuit Breaker, Disconnect switch, Control Panel, wirings/cables and all accessories for the new HVAC Units.
3 2 1

NO.

DESCRIPTION

REVISIONS

DRAWN BY DATE CHKD BY

6. Modified existing HVAC Equipment (ACCU & AHU ) Concrete Foundation as required for the New A/C Units. Foundation shall be painted as per Company Standard. 7. Removal/Repainting and re- Installation of Pipe Barrier, Design and Construction of Steel Sunshade Cover and Support for the new HVAC Equipment.

APPROVED ENGINEERING DEPT.

8. Installation of new Condensate Drainage Piping System and Construction of Seepage pit. 9. Restoration Works. All areas affected by the works shall be repaired, restored to a clean ,operational status, and all opening shall be cover with the same Building Materials. 10. Painting of Mechanical Room flooring, ceiling and walls as per Company Standard

ADC / DVD

OPERATING DEPT.

L. Al-Nakheel 69/13.8kV Substation.


CERTIFIED

1. Remove all existing two (2) Split Type A/C Units, Air Supply/Return Air Ducts and all accessories .. 2. Design, Supply and Installation of two (2) New Sets of Split Type A/C units, with 100% capacity each capable of handling the Total Cooling and Heating Load of the whole Bldg. and Equipments . The Contractor shall provide design calculation for the new A/C units as per requirement. 3. Fabricate and install new Air Supply and Return Air Duct , diffusers, grilles, dampers, duct heater, duct detectors and all accessories for Air Distribution System for proper cooling and Air Balancing 4. Provide and Install Digital Direct Control (DDC) Panel for the HVAC System and interfaced to SCADA and FACP. A dedicated alarm for HVAC system fail "HVAC SYSTEM FAIL" shall be provided. This alarm shall be wired/terminated to the
[[PTS- 14ED416 doc. MQQ/ADC/DVD) November 2013 ]
PLANT NO. INDEX PTS NO. PAGE NO. REV.

BY: :

MQQ

THIS DRAWING IS NOT TO BE USED FOR CONSTRUCTION OR FOR ORDERING MATERIALS UNTIL CERTIFIED AND DATED

SCOPE OF WORK AND TECHNICAL SPECIFICATIONS


JOB ORDER NO.

1-- 1443026 111

FOR REPLACEMENT OF HVAC SYSTEM AT EASTERN OPERATING AREA SUBSTATION

D047

PTS-14ED416

SAUDI ARABIA

14 OF 77

CERT.

SAUDI ELECTRICITY COMPANY

APPD

CHKD

existing spare point of SCADA RTU. The contractor shall commission and test the alarm system with company representative. 5. Provide and install new Main Distribution Panels, Main Circuit Breaker, Circuit Breaker, Disconnect switch, Control Panel, wirings/cables and all accessories for the new HVAC Units.

DESCRIPTION

6. Modification of existing HVAC Equipment ( ACCU & AHU ) Concrete Foundation . Foundation shall be painted as per Company Standard. 7. Resurface, Retouch and Repaint existing Mechanical room 8. Removal/Repainting and re -Installation of Pipe Barrier, Design and Construction of Steel Sunshade Cover and Support for the new HVAC Equipment
3 2 1

NO.

REVISIONS

9. Installation of new Condensate Drainage Piping System and Construction of Seepage pit. 10. Restoration Works. All areas affected by the works shall be repaired, restored to a clean ,operational status, and all opening shall be cover with the same Building Materials.

DRAWN BY DATE CHKD BY

APPROVED ENGINEERING DEPT.

M. Tubaishi Substation
ADC / DVD

1. Remove all existing Split Type A/C Units (2) and Packaged Type A/C Units and all accessories and cover all openings with the same Building Materials. 2. Design, Supply and Installation of two (2) New Sets of Packaged Type A/C Units and Two (2) Split Type A/C Units wich with 100% capacity each capable of handling the Total Cooling and Heating Load of the whole Building including Room extension and Capacitor Bank Room. Each Units shall be design to cover the total load of each designated area. The Contractor shall provide design calculation for the new A/C units as per requirement. 3. Removal of existing all Air Supply Duct, Return Air Duct , Grilles, Diffusers, Fresh Air Make Up Grilles, dampers, duct heater and all accessories in the whole building. 4. Design,Fabricate and install new Air Supply and Return Air Duct , diffusers, grilles, dampers, duct heater, duct detectors and all accessories for Air Distribution System for proper cooling and Air Balancing 5. Provide and Install Digital Direct Control (DDC) Panel for the HVAC System and interfaced to SCADA and FACP. A dedicated alarm for HVAC system fail "HVAC SYSTEM FAIL" shall be provided. This alarm shall be wired/terminated to the existing spare point of SCADA RTU. The contractor shall commission and test the alarm system with company representative.

OPERATING DEPT.

CERTIFIED

BY: :

MQQ

THIS DRAWING IS NOT TO BE USED FOR CONSTRUCTION OR FOR ORDERING MATERIALS UNTIL CERTIFIED AND DATED

[[PTS- 14ED416 doc. MQQ/ADC/DVD) November 2013 ]


PLANT NO. INDEX PTS NO. PAGE NO. REV.

SCOPE OF WORK AND TECHNICAL SPECIFICATIONS


JOB ORDER NO.

1-- 1443026 111

FOR REPLACEMENT OF HVAC SYSTEM AT EASTERN OPERATING AREA SUBSTATION

D047

PTS-14ED416

SAUDI ARABIA

15 OF 77

CERT.

SAUDI ELECTRICITY COMPANY

APPD

6. Provide and install new Main Distribution Panels, Main Circuit Breaker, Circuit Breaker, Disconnect switch, Control Panel, wirings/cables and all accessories for the new HVAC Units. 7. Removal of existing HVAC Equipment Concrete Foundation and design and Construction of new Foundation. Foundation shall be painted as per Company Standard. 8. Resurface, Retouch and Repainting of Mechanical Room beside Control Room and Battery Room. 9. Fabrication and Installation of Pipe Barrier, Steel Sunshade Cover and Support for the new HVAC Equipment
3 2 1

NO.

DESCRIPTION

CHKD

REVISIONS

10. Installation of new Condensate Drainage Piping System and Construction of Seepage pit. 11. Restoration Works. All areas affected by the works shall be repaired, restored to a clean ,operational status, and all opening shall be cover with the same Building Materials.

DRAWN BY DATE CHKD BY

APPROVED ENGINEERING DEPT.

N. Ummal Substation
ADC / DVD

1. Removal of existing old Pacakged Type A/C Units, Air Supply/Return Ducts, Diffusers, grilles, dampers, duct heater , duct detectors and all accessories. 2. Removal of existing Window Type A/C unit and cover opening with the same Building Materials. 3. Design, Supply and Installation of two (2) New Sets of Pacakged Type A/C units, with 100% capacity each capable of handling the Total Cooling and Heating Load of the whole building. The Contractor shall provide design calculation for the new A/C units as per requirement.

OPERATING DEPT.

CERTIFIED

BY: :

MQQ

Design, Fabricate and install new Air Supply and Return Air Duct , diffusers, grilles, dampers, duct heater, duct detectors and all accessories for Air Distribution System for proper cooling and Air Balancing. Provide and Install Digital Direct Control (DDC) Panel for the HVAC System and interfaced to SCADA and FACP. A dedicated alarm for HVAC system fail "HVAC SYSTEM FAIL" shall be provided. This alarm shall be wired/terminated to the existing spare point of SCADA RTU. The contractor shall commission and test the alarm system with company representative.

THIS DRAWING IS NOT TO BE USED FOR CONSTRUCTION OR FOR ORDERING MATERIALS UNTIL CERTIFIED AND DATED

Provide and install new Main Distribution Panels, Main Circuit Breaker, Circuit Breaker, Disconnect switch, Control Panel, wirings/cables and all accessories for the new HVAC Units.

[[PTS- 14ED416 doc. MQQ/ADC/DVD) November 2013 ]


PLANT NO. INDEX PTS NO. PAGE NO. REV.

SCOPE OF WORK AND TECHNICAL SPECIFICATIONS


JOB ORDER NO.

1-- 1443026 111

FOR REPLACEMENT OF HVAC SYSTEM AT EASTERN OPERATING AREA SUBSTATION

D047

PTS-14ED416

SAUDI ARABIA

16 OF 77

CERT.

SAUDI ELECTRICITY COMPANY

APPD

CHKD

Fabrication and Installation of new Pipe Barrier, Steel Sunshade Cover and support for the new HVAC Units. Removal of existing HVAC Units Foundation and Design and Construction of new Foundation. Foundation shall be painted as per Standard.

DESCRIPTION

Installation of new Condensate Drainage Piping System and Construction of Seepage pit. Restoration Works. All areas affected by the works shall be repaired, restored to a clean ,operational status, and all opening shall be cover with the same Building Materials. Retouch and Repainting of Mechanical Room flooring, ceiling and walls as per Company Standard.

NO.

REVISIONS

DRAWN BY DATE CHKD BY

O. KFIA Substation.
1. Removal of existing old Pacakged Type A/C Units, Air Supply/Return Ducts, Diffusers, Grilles, dampers, duct heater, duct detectors, and all accessories. 2 Design, Supply and Installation of two (2) New Sets of Pacakged Type A/C units, with 100% capacity each capable of handling the Total Cooling and Heating Load of the whole building. The Contractor shall provide design calculation for the new A/C units as per requirement.

APPROVED ENGINEERING DEPT.

ADC / DVD

OPERATING DEPT.

3. Design, Fabricate and install new Air Supply and Return Air Duct , diffusers, grilles, dampers, duct heater , duct detectors,and all accessories for proper Air Distribution System and Air Balancing 3 Provide and Install Digital Direct Control (DDC) Panel for the HVAC System and interfaced to SCADA and FACP. A dedicated alarm for HVAC system fail "HVAC SYSTEM FAIL" shall be provided. This alarm shall be wired/terminated to the existing spare point of SCADA RTU. The contractor shall commission and test the alarm system with company representative. Provide and install new Main Distribution Panels, Main Circuit Breaker, Circuit Breaker, Disconnect switch, Control Panel, wirings/cables and all accessories for the new HVAC Units. Fabrication and Installation of new Pipe Barrier, Steel Sunshade Cover and support for the new HVAC Units. Removal of existing HVAC Units Foundation and Design and Construction of new Foundation. Foundation shall be painted as per Standard.

CERTIFIED

BY: :

MQQ

5
THIS DRAWING IS NOT TO BE USED FOR CONSTRUCTION OR FOR ORDERING MATERIALS UNTIL CERTIFIED AND DATED

Installation of new Condensate Drainage Piping System and Construction of Seepage pit.

[[PTS- 14ED416 doc. MQQ/ADC/DVD) November 2013 ]


PLANT NO. INDEX PTS NO. PAGE NO. REV.

SCOPE OF WORK AND TECHNICAL SPECIFICATIONS


JOB ORDER NO.

1-- 1443026 111

FOR REPLACEMENT OF HVAC SYSTEM AT EASTERN OPERATING AREA SUBSTATION

D047

PTS-14ED416

SAUDI ARABIA

17 OF 77

CERT.

SAUDI ELECTRICITY COMPANY

CHKD

APPD

Restoration Works. All areas affected by the works shall be repaired, restored to a clean ,operational status, and all opening shall be cover with the same Building Materials.

NO.

DESCRIPTION

9. Retouch and Repainting of Mechanical Room flooring, ceiling and walls as per Company Standard

P. AL-Bayyat 69/13.8 kV Substation

REVISIONS

DRAWN BY DATE CHKD BY

Removal of existing two (2) Split Type A/C Units Air Supply/Return Ducts and all accessories. Design, Supply and Installation of Two (2) New Split Type A/C Units with 100% capacity each capable of handling the Total Cooling and Heating Load of the whole Bldg. including Room extension . The Contractor shall provide design calculation for the new A/C units as per requirement. Design, Fabricate and install new Air Supply and Return Air Duct , diffusers, grilles, dampers, duct heater, duct detectors and all accessories for Air Distribution System for proper cooling and Air Balancing . Provide and Install Digital Direct Control (DDC) Panel for the HVAC System and interfaced to SCADA and FACP. A dedicated alarm for HVAC system fail "HVAC SYSTEM FAIL" shall be provided. This alarm shall be wired/terminated to the existing spare point of SCADA RTU. The contractor shall commission and test the alarm system with company representative. Provide and install new Main Distribution Panel, Main Circuit Breaker, Circuit Breaker, Disconnect switch, Control Panel, Wirings/Cables and all accessories for the new HVAC Units. Modification of existing HVAC Equipment ( ACCU & AHU ) Concrete Foundation . Foundation shall be painted as per Company Standard. Removal/Repainting and re-installation of Pipe Barrier and design and Construction of new Steel Sunshade Cover and Support for the new HVAC Equipment

2
APPROVED ENGINEERING DEPT.

ADC / DVD

OPERATING DEPT.

5
CERTIFIED

BY: :

MQQ

THIS DRAWING IS NOT TO BE USED FOR CONSTRUCTION OR FOR ORDERING MATERIALS UNTIL CERTIFIED AND DATED

Installation of new Condensate Drainage Piping System and Construction of Seepage pit. Restoration Works. All areas affected by the works shall be repaired, restored to a clean ,operational status, and all opening shall be cover with the same Building Materials.

[[PTS- 14ED416 doc. MQQ/ADC/DVD) November 2013 ]


PLANT NO. INDEX PTS NO. PAGE NO. REV.

SCOPE OF WORK AND TECHNICAL SPECIFICATIONS


JOB ORDER NO.

1-- 1443026 111

FOR REPLACEMENT OF HVAC SYSTEM AT EASTERN OPERATING AREA SUBSTATION

D047

PTS-14ED416

SAUDI ARABIA

18 OF 77

CERT.

SAUDI ELECTRICITY COMPANY

CHKD

APPD

10 Painting of Mechanical Room flooring, ceiling and walls as per Company Standard .
Q. General All Substation

DESCRIPTION

1. Air Supply and Return Distribution Duct including Branch Air Duct can be modified and utilized. 2. Main Air Ducts shall be totally replaced as per new Air Supply/Return requirement. 3. Exact location of the new proposed HVAC Units shall be located and proposed by the Contractor to be approved by SEC Representative.

NO.

REVISIONS

4. Contractor in some congested areas can proposed Packaged Type or Split Type A/C Units whichever is applicable on site condition. 5. All New Pipe Barriers shall be of removable-Type as per drawing standard TA800133..

DRAWN BY DATE CHKD BY

APPROVED ENGINEERING DEPT.

1.04 ABBREVIATIONS Terms, abbreviations and/or expressions frequently used, herein and after, shall have the following meaning:

ADC / DVD

OPERATING DEPT.

Term, Abbreviation or Expression COMPANY or SEC PROJECT CONTRACTOR LSTK S/S SOW/TS PTS A/C HVAC PACU CAD NEMA ACI SASO SCS TES SMSS TMSS

MEANING Saudi Electricity Company Installation of HVAC at Five Substations in Eastern Operating Area Substation. Contractor, responsible for the execution of the WORK as described in this PTS. Lump Sum Turnkey Substation Scope of Work and Technical Specifications Project Technical Specification Air Conditioning Heating, Ventilating & Air Conditioning Package Air Conditioning Unit Computer Aided Design National Electrical Manufacturers Association American Concrete Institute Saudi Arabian Standards Organization SEC-EOA Construction Standards SEC Transmission Engineering Standards SEC-EOA Materials Standard Specifications SEC Transmission Materials Standard Specifications

CERTIFIED

BY: :

MQQ

THIS DRAWING IS NOT TO BE USED FOR CONSTRUCTION OR FOR ORDERING MATERIALS UNTIL CERTIFIED AND DATED

[[PTS- 14ED416 doc. MQQ/ADC/DVD) November 2013 ]


PLANT NO. INDEX PTS NO. PAGE NO. REV.

SCOPE OF WORK AND TECHNICAL SPECIFICATIONS


JOB ORDER NO.

1-- 1443026 111

FOR REPLACEMENT OF HVAC SYSTEM AT EASTERN OPERATING AREA SUBSTATION

D047

PTS-14ED416

SAUDI ARABIA

19 OF 77

CERT.

SAUDI ELECTRICITY COMPANY

APPD

DESCRIPTION

ASTM PVC NFPA UL QA/QC NCR DDC

American Society for Testing and Materials Polyvinyl Chloride National Fire Protection Association Underwriters Laboratories Quality Assurance/Quality Control Non-Conformance Report Direct Digital Control *** END OF SECTION I ****

CHKD

NO.

SECTION II - BASIC REQUIREMENTS AND GUIDELINES 2.01 GENERAL CONDITIONS A. All components and accessories required for the completion and successful operation of the WORK covered under the scope of this PROJECT, either specified in detail or not, shall be supplied and installed by the CONTRACTOR as necessary. B. The engineering design and specifications of equipment/materials supplied under this PROJECT shall be in accordance with this Scope of WORK and Technical Specifications and COMPANY Standards. If the equipment either does not conform to specifications or is not acceptable to COMPANY based on past operating experience/any other reason, the CONTRACTOR shall propose alternative equipment for review and acceptance by COMPANY. However, in case of a conflict in the requirements, the CONTRACTOR shall bring this to the attention of the COMPANY and shall obtain such applicable requirements for this PROJECT in writing from the COMPANY. The CONTRACTOR shall have no right to decide on his own the requirements in case of such a conflict, and in case of such an eventuality, he will be doing so at his own risk and cost as the COMPANY reserves the right to reject any or the complete part of such WORK arising out of the CONTRACTOR's own decision. Engineering and design work shall be carried out by an Engineering and Design Consultancy Firm who has valid registration in the Kingdom of Saudi Arabia to carry out the similar job. Said Firm shall be from SEC-ERB approved list of Engineering and Design Consultants. C. The drawings enclosed with this Scope of WORK and Technical Specifications are only conceptual for the information of the CONTRACTOR and are to be read in conjunction with this Scope of WORK and Technical Specifications. CONTRACTOR shall develop detailed design drawings for construction based on these drawings.

REVISIONS

DRAWN BY DATE CHKD BY

APPROVED ENGINEERING DEPT.

ADC / DVD

OPERATING DEPT.

CERTIFIED

BY: :

MQQ

THIS DRAWING IS NOT TO BE USED FOR CONSTRUCTION OR FOR ORDERING MATERIALS UNTIL CERTIFIED AND DATED

D. Copies of existing drawings, design calculations, technical reports as deemed appropriate by the COMPANY may be provided to the request, if available. However, if such information is not CONTRACTOR should be responsible for the independent information required to complete the PROJECT specified.
[[PTS- 14ED416 doc. MQQ/ADC/DVD) November 2013 ]
PLANT NO. INDEX

and other information CONTRACTOR upon available, then the development of the

PTS NO.

PAGE NO.

REV.

SCOPE OF WORK AND TECHNICAL SPECIFICATIONS


JOB ORDER NO.

1-- 1443026 111

FOR REPLACEMENT OF HVAC SYSTEM AT EASTERN OPERATING AREA SUBSTATION

D047

PTS-14ED416

SAUDI ARABIA

20 OF 77

CERT.

SAUDI ELECTRICITY COMPANY

CHKD

APPD

E. The specifications of equipment and materials specified herein are to be considered as the minimum requirements, and the bidders shall carry out their own basic and detailed design necessary for their proposed specifications. The base design shall be finalized at base design review meeting based on the guideline drawings issued hereof, manufacturer's drawings, calculations and data sheets, and detailed design shall be finalized based on the base design review and other required information. All documents, drawings data and instruction books to be submitted by the CONTRACTOR shall be written in English language and Metric Unit system.

NO.

DESCRIPTION 3

F.

REVISIONS

The submission of final detailed drawings shall be progressive and phased out to give sufficient review time to COMPANY.

DRAWN BY DATE CHKD BY

G. COMPANY's acceptance of the CONTRACTOR's design does not relieve him of any part of his obligations to meet all the requirements of the CONTRACT nor the responsibility for the correctness of the design and construction drawings of the PROJECT. H. All WORK, including services for the test and inspections required by the COMPANY and demonstrations, if any, for familiarization of operation of new HVAC equipment to the COMPANY personnel shall be done by the CONTRACTOR. I. Any WORK which requires shutdown of transmission/distribution feeders or substation shall be closely coordinated with COMPANY. All outages shall be scheduled at least one (1) month in advance. The CONTRACTORs organizational chart shall be per CONTRACTORs key personnel form attached with Instruction to bidders.

APPROVED ENGINEERING DEPT.

ADC / DVD

OPERATING DEPT.

J.

2.02 KICK-OFF MEETING


CERTIFIED

BY: :

MQQ

A Kick-Off Meeting will be held in COMPANY Headquarters shortly after award of the CONTRACT. This meeting will cover PROJECT implementation, the Scope of WORK, and Schedule and will give the CONTRACTOR an opportunity to discuss all matters related to carrying out his responsibilities. 2.03 BASE DESIGN PHASE A. The base design phase of the PROJECT is a 10-12 week period of preliminary engineering following the kick-off meeting. The purpose of the base design phase is to completely define the PROJECT in enough details to satisfy the COMPANY that all requirements are being incorporated. Information developed during the base design shall be used as a guide throughout the PROJECT and shall be considered binding on both parties, unless operational difficulties or design flaws observed during detailed design review are noted and mandate change.
[[PTS- 14ED416 doc. MQQ/ADC/DVD) November 2013 ]
PLANT NO. INDEX PTS NO. PAGE NO. REV.

THIS DRAWING IS NOT TO BE USED FOR CONSTRUCTION OR FOR ORDERING MATERIALS UNTIL CERTIFIED AND DATED

SCOPE OF WORK AND TECHNICAL SPECIFICATIONS


JOB ORDER NO.

1-- 1443026 111

FOR REPLACEMENT OF HVAC SYSTEM AT EASTERN OPERATING AREA SUBSTATION

D047

PTS-14ED416

SAUDI ARABIA

21 OF 77

CERT.

SAUDI ELECTRICITY COMPANY

CHKD

APPD

Coordination meetings will be conducted with the CONTRACTOR's Design Team on regular basis until the design work is completed. B. The CONTRACTOR shall submit eight (8) sets of the base design document at least four (4) weeks ahead of the base design review meeting which shall include, but not limited to the following: 1. 2. Major Materials Purchase Requisitions (Preliminary) Design Calculations, Design Drawings and other documents. The base design submittal shall be submitted fully complete, containing all discipline drawings and calculations as stated. Partial submittals or packages are unacceptable and will be rejected outright.

NO.

DESCRIPTION 3

REVISIONS

DRAWN BY DATE CHKD BY

2.04 BASE DESIGN REVIEW After completing the Base Design, the CONTRACTOR shall present the Base Design Package for technical review along with the Drawing Control Sheet. CONTRACTOR's PROJECT Manager, PROJECT Engineer and the Design/Construction Engineer in each field of specification shall attend the presentation meeting. During this meeting, the COMPANY's comments on the base design package will be reviewed and discussed in detail to finalize the base design for the PROJECT. Minutes of the meeting shall be prepared by the CONTRACTOR to be concurred by the COMPANY REPRESENTATIVE. 2.05 PROJECT DRAWINGS

APPROVED ENGINEERING DEPT.

ADC / DVD

OPERATING DEPT.

A. General 1. The CONTRACTOR shall provide all drawings required for this PROJECT covering all substations in accordance with the requirements of the COMPANY Turnkey PROJECT Drawings, EDSD Specification No. 2. The drawings shall be assigned with drawing numbers and indexed as outlined in the above procedure. A block of drawing numbers shall be provided by the COMPANY for all drawings. 2. Drawings shall be of uniform size in each discipline as much as possible and ISO scales shall be 1:10, 1:50, 1:100 and 1:1200. The existing system drawings of the source substation are generally available with the COMPANY in digital format (TIFF-GROUP-4 *.tif or *.DGN which can be opened through Windows Micro station *.DGN). Copies of existing available drawings shall be provided on CONTRACTORs written request. However, if any related information is not available, the CONTRACTOR shall be responsible to

CERTIFIED

BY: :

MQQ

3.
THIS DRAWING IS NOT TO BE USED FOR CONSTRUCTION OR FOR ORDERING MATERIALS UNTIL CERTIFIED AND DATED

[[PTS- 14ED416 doc. MQQ/ADC/DVD) November 2013 ]


PLANT NO. INDEX PTS NO. PAGE NO. REV.

SCOPE OF WORK AND TECHNICAL SPECIFICATIONS


JOB ORDER NO.

1-- 1443026 111

FOR REPLACEMENT OF HVAC SYSTEM AT EASTERN OPERATING AREA SUBSTATION

D047

PTS-14ED416

SAUDI ARABIA

22 OF 77

CERT.

SAUDI ELECTRICITY COMPANY

APPD

CHKD

develop all the required drawings in COMPANY standard format to satisfy the PROJECT requirements. 4. The drawings involving modification of the existing system in source substation shall cover the details of the existing system and interface. The drawings in general shall be computer-drafted (Micro station- *.DGN) CAD system.

DESCRIPTION

B. Vendor Drawings Vendor drawings are manufacturers' drawings, data schedules, specification sheets, installation and operating instructions and any other data required for material or equipment. Requirements of such information are an integral part of the purchase order and shall be specified by the CONTRACTOR.
3 2 1

NO.

REVISIONS

DRAWN BY DATE CHKD BY

Assignment of vendor drawing numbers shall be in accordance with COMPANY Procedure No. EDSD DR-8 and EDSD Specification No. 2. All vendor drawings shall be subject to review and approval by the COMPANY at various stages (bid/base design/detail design/construction) of the CONTRACT. C. Base Design Drawings

APPROVED ENGINEERING DEPT.

The CONTRACTOR shall submit base design drawings to the COMPANY with his Base Design Package per Section 2.03. D. Final Detail Design/Construction Drawings The CONTRACTOR shall submit point-wise compliance statement to COMPANYs comments and shall obtain approval for all final detail design drawings after incorporating COMPANY comments. After receiving the approval, the CONTRACTOR shall submit to the COMPANY eight (8) complete sets of all interconnected drawings issued for construction in one (1) submittal. These drawings shall be submitted to the COMPANY at the same time the drawings are issued to the CONTRACTOR's construction team, but in no case less than fourteen (14) days prior to the start of construction activity. No WORK shall be started at site unless all interconnected drawings for a particular WORK has been fully reviewed and agreed upon by the COMPANY and final construction drawings are available at WORK SITE and with the COMPANY. Final detailed design drawings shall be submitted fully complete, by discipline representing fully the part of the PROJECT to be constructed and all the related drawings. Partial submittals are not acceptable and will be rejected.

ADC / DVD

OPERATING DEPT.

CERTIFIED

BY: :

MQQ

THIS DRAWING IS NOT TO BE USED FOR CONSTRUCTION OR FOR ORDERING MATERIALS UNTIL CERTIFIED AND DATED

E. As-Built Drawings The CONTRACTOR shall provide all 'As-Built' drawings required for this PROJECT in accordance with the requirements of SEEDS-II.

[[PTS- 14ED416 doc. MQQ/ADC/DVD) November 2013 ]


PLANT NO. INDEX PTS NO. PAGE NO. REV.

SCOPE OF WORK AND TECHNICAL SPECIFICATIONS


JOB ORDER NO.

1-- 1443026 111

FOR REPLACEMENT OF HVAC SYSTEM AT EASTERN OPERATING AREA SUBSTATION

D047

PTS-14ED416

SAUDI ARABIA

23 OF 77

CERT.

SAUDI ELECTRICITY COMPANY

APPD

CHKD

2.06 PROGRESS REPORTING A. The CONTRACTOR shall submit Bi-Weekly PROJECT Progress Reports, in COMPANY-approved formats for the PROJECT to the responsible COMPANY REPRESENTATIVE. For this purpose, the total WORK shall be divided into: 1. 2. Engineering and Design. Procurement/Manufacture/Fabrication Inspection and Delivery of Equipment. Construction and Installation. Testing and Commissioning. Materials/

DESCRIPTION

3.
NO. 3 2 1

4.

REVISIONS

DRAWN BY DATE CHKD BY

B. The following information shall be included in the Progress Reports: 1. Percent of WORK completed as compared to the weighted schedule used to assess WORK progress. Statement of items worked on and/or completed during the period. Statement of items to be worked on and/or completed during the following period. Problem areas which can have an adverse effect on the schedule. Safety statistics and minutes of construction safety meeting and progress meeting. Manpower and equipment availability against the schedule requirement.

APPROVED ENGINEERING DEPT.

2. 3.

ADC / DVD

4. 5.
OPERATING DEPT.

6.

C. The CONTRACTOR shall carry out PROJECT planning/scheduling by using MS PROJECT computer software. All PROJECT schedules shall be submitted in CD's.
CERTIFIED

BY: :

MQQ

D. Bi-Weekly Progress Meeting shall be conducted between the COMPANY and the CONTRACTOR during the entire CONTRACT duration of the PROJECT. Other coordination and interface meetings will be conducted, as required. The CONTRACTOR shall prepare the minutes of all meetings. The initial draft shall be submitted by the CONTRACTOR to the COMPANY REPRESENTATIVE for review and concurrence. The CONTRACTOR shall then incorporate the required corrections and submit to the COMPANY one (1) original and two (2) copies after they are duly signed by the authorized representative of the CONTRACTOR. The COMPANY shall sign one (1) copy in acceptance and furnish it to the CONTRACTOR and retain the original. In addition, a Weekly Construction Safety Meeting shall be conducted by the CONTRACTOR's Safety Engineer or PROJECT Engineer. Minutes of meeting shall be forwarded to the COMPANY. 2.07 QUALITY ASSURANCE/QUALITY CONTROL REQUIREMENTS
[[PTS- 14ED416 doc. MQQ/ADC/DVD) November 2013 ]
PLANT NO. INDEX PTS NO. PAGE NO. REV.

THIS DRAWING IS NOT TO BE USED FOR CONSTRUCTION OR FOR ORDERING MATERIALS UNTIL CERTIFIED AND DATED

SCOPE OF WORK AND TECHNICAL SPECIFICATIONS


JOB ORDER NO.

1-- 1443026 111

FOR REPLACEMENT OF HVAC SYSTEM AT EASTERN OPERATING AREA SUBSTATION

D047

PTS-14ED416

SAUDI ARABIA

24 OF 77

CERT.

SAUDI ELECTRICITY COMPANY

CHKD

APPD

A. Quality Management CONTRACTOR shall implement an effective quality management which addresses all direct and indirect activities related to the PROJECT to ensure that all contractual conditions are met. Quality planning, quality control, quality assurance and quality improvement shall be part of CONTRACTOR's quality management. To effectively manage the PROJECT quality, CONTRACTOR shall develop a clearly defined PROJECT Quality Plan/Quality Program. The PROJECT Quality Plan/Quality Program shall be implemented from PROJECT start until completion and communicated at different levels of the PROJECT organization. In addition, CONTRACTOR shall also require manufacturers/suppliers to develop and implement Quality Control Plan/ Inspection and Test Plan for each major material/equipment.
3 2

NO.

DESCRIPTION

REVISIONS

DRAWN BY DATE CHKD BY

B. PROJECT Quality Plan / Quality Program 1. The PROJECT Quality Plan/Quality Program shall set out the specific quality procedures and practices, resources, and all activities (in sequence) relevant to this PROJECT. The PROJECT Quality Plan/Quality Program shall address all QA/QC activities during design, procurement, manufacturing/fabrication, delivery, storage, construction, installation, testing and commissioning of all items of WORK and materials/equipment per Scope of WORK and Technical Specification. The PROJECT Quality Plan/Quality Program shall be submitted to the COMPANY as part of the base design package for review and approval. The PROJECT Quality Plan/Quality Program shall clearly define and address the following: a. The quality objectives to be attained and CONTRACTORs commitment to achieve the objectives in the form of a signed policy statement. The policy statement shall be signed by CONTRACTORs management personnel not lower than the person who signed this CONTRACT. Detailed PROJECT organizational chart and specific allocations of responsibilities and authorities during the different phases of the PROJECT. CONTRACTOR shall include in the PROJECT organizational chart QA/QC engineers and inspectors dedicated to quality assurance and quality control (QA/QC). The QA/QC engineers and inspectors shall report directly to the overall PROJECT Manager. The QA/QC engineers and inspectors shall have adequate experience in their area of responsibility and shall be responsible for ensuring that all phases of the PROJECT are built, tested and commissioned in accordance with the requirements of the PROJECT
[[PTS- 14ED416 doc. MQQ/ADC/DVD) November 2013 ]
PLANT NO. INDEX PTS NO. PAGE NO. REV.

APPROVED ENGINEERING DEPT.

ADC / DVD

OPERATING DEPT.

2.

3.

CERTIFIED

BY: :

MQQ

b.

THIS DRAWING IS NOT TO BE USED FOR CONSTRUCTION OR FOR ORDERING MATERIALS UNTIL CERTIFIED AND DATED

SCOPE OF WORK AND TECHNICAL SPECIFICATIONS


JOB ORDER NO.

1-- 1443026 111

FOR REPLACEMENT OF HVAC SYSTEM AT EASTERN OPERATING AREA SUBSTATION

D047

PTS-14ED416

SAUDI ARABIA

25 OF 77

CERT.

SAUDI ELECTRICITY COMPANY

APPD

Scope of WORK and Technical Specifications. The CONTRACTORs Chief QA/QC engineer shall interface directly with the COMPANY REPRESENTATIVE. CONTRACTOR shall use QA/QC personnel other than those performing or directly supervising the WORK. The QA/QC personnel shall not report directly to immediate supervisors responsible for producing the WORK being inspected. CONTRACTORs QA/QC personnel shall be kept free from the pressures of cost, schedule and production and shall be given the necessary authority and independence to perform their roles effectively. c. Procurement Control CONTRACTORs PROJECT QA/QC engineers shall review all products and services prior to procurement to ensure conformance to specified requirements. Procurement control shall include source evaluation and selection, source inspection and evaluation of objective evidence of quality furnished by a supplier against the PROJECT specification. These products shall cover major materials/equipment and other items including but not necessarily limited to testing services, fill materials, Portland cement concrete and additives, steel structures, HVAC materials and equipment, electrical materials, and formwork materials, etc.

NO.

DESCRIPTION 3

CHKD

REVISIONS

DRAWN BY DATE CHKD BY

APPROVED ENGINEERING DEPT.

ADC / DVD

d.
OPERATING DEPT.

Quality Audit CONTRACTOR shall conduct its own internal quality surveillance at appropriate stages (e.g. design, procurement, construction, installation and commissioning stage) of the PROJECT to determine compliance to and the effectiveness of the PROJECT Quality Plan/Quality Program. Each element of the PROJECT Quality Plan/Quality Program shall be assessed at least once during the life of the PROJECT. The schedule and frequency should be adjusted if one or more of the following conditions exist: i. Result of previous surveillance indicate a need to perform them more frequently. Significant changes are made in the PROJECT Quality Plan/Quality Program. Safety, performance or reliability of an item is questionable due to nonconformance. Verification of corrective action implementation.

CERTIFIED

BY: :

MQQ

ii.

iii.
THIS DRAWING IS NOT TO BE USED FOR CONSTRUCTION OR FOR ORDERING MATERIALS UNTIL CERTIFIED AND DATED

iv.

[[PTS- 14ED416 doc. MQQ/ADC/DVD) November 2013 ]


PLANT NO. INDEX PTS NO. PAGE NO. REV.

SCOPE OF WORK AND TECHNICAL SPECIFICATIONS


JOB ORDER NO.

1-- 1443026 111

FOR REPLACEMENT OF HVAC SYSTEM AT EASTERN OPERATING AREA SUBSTATION

D047

PTS-14ED416

SAUDI ARABIA

26 OF 77

CERT.

SAUDI ELECTRICITY COMPANY

APPD

Personnel conducting the quality surveillance shall be independent of those having direct responsibility for the specific activities or areas being evaluated or assessed. e. Non-Conformance Control CONTRACTOR shall ensure that items and services which do not conform to specified requirement are controlled in accordance with documented procedures to prevent unintended use. CONTRACTOR shall identify, document, segregate, evaluate and dispose non-conforming items and services after proper notification of concerned personnel within the CONTRACTORs organization. CONTRACTORs QA/QC engineer/inspector shall re-inspect repaired and reworked non-conforming items. CONTRACTOR shall not use any repaired item or product unless approved by the COMPANY.
3 2 1

NO.
DATE

DESCRIPTION

CHKD

REVISIONS

DRAWN BY

CHKD BY

Under this clause, the following definitions apply: i. Repair - Action taken on a non-conforming product so that it will fulfill the intended usage requirements although it may not conform to the original specified requirements (ISO 8402). Rework - Action taken on a non-conforming product so that it will fulfill the specified requirement (ISO 8402).

APPROVED ENGINEERING DEPT.

ADC / DVD

ii.

OPERATING DEPT.

CONTRACTOR shall develop non-conformance report (NCR) form and submit it to the COMPANY for review and comment. CONTRACTORs QA/QC engineers/inspectors shall have the freedom to issue NCRs, verify implementation of corrective actions and prevent use of non-conforming items until the deficiency has been satisfactorily resolved. CONTRACTORs Chief QA/QC engineer shall submit bi-weekly site QA/QC reports to COMPANY REPRESENTATIVE about non-compliances. f. Corrective Action CONTRACTOR shall develop, document and implement a system for determining the root cause of non-conformities and identifying the required corrective actions. New procedures or changes to existing procedures resulting from identification of the root cause and potential root cause of non-conformances shall be documented and implemented. Follow-up action shall be taken to verify effective implementation of corrective action. The identified cause and corrective action should be included in the bi-weekly site QA/QC reports that are required to be submitted to the COMPANY REPRESENTATIVE. g. Quality Records

CERTIFIED

BY: :

MQQ

THIS DRAWING IS NOT TO BE USED FOR CONSTRUCTION OR FOR ORDERING MATERIALS UNTIL CERTIFIED AND DATED

[[PTS- 14ED416 doc. MQQ/ADC/DVD) November 2013 ]


PLANT NO. INDEX PTS NO. PAGE NO. REV.

SCOPE OF WORK AND TECHNICAL SPECIFICATIONS


JOB ORDER NO.

1-- 1443026 111

FOR REPLACEMENT OF HVAC SYSTEM AT EASTERN OPERATING AREA SUBSTATION

D047

PTS-14ED416

SAUDI ARABIA

27 OF 77

CERT.

SAUDI ELECTRICITY COMPANY

APPD

DESCRIPTION

CONTRACTOR shall develop and maintain a system for preparation, maintenance, protection and preservation of quality records. Documents such as inspection reports, field inspection checklist, factory test reports, laboratory test reports, witnessed test reports, inspection logbooks, equipment calibration records/certificates, construction drawings and specifications, approved submittals and non-conformance reports are part of these records. All quality records shall be available at WORKSITE for use and/or reference by CONTRACTOR and COMPANY REPRESENTATIVE. h. Control of Inspection, Measuring and Testing Equipment All measuring and testing equipment and devices which can affect the quality of construction shall be controlled and maintained. CONTRACTOR shall develop and implement a documented calibration control program indicating equipment calibration schedule and identifying those who are responsible for control of the equipment. CONTRACTOR shall ensure that only properly identified and calibrated measuring and testing equipment are used in the PROJECT. Equipment calibration certificates shall be made available to COMPANY REPRESENTATIVE upon request. i. Document Control CONTRACTOR shall develop and maintain a documented control program for the review, approval, revision and distribution of documents for the activities affecting quality. Responsible personnel for revision, issuance and approval of documents shall be identified. Control shall ensure that all pertinent and current issues of appropriate documents are available at locations where they are essential and obsolete or superseded documents are promptly removed. CONTRACTOR shall list all the documents that have to be controlled and shall include PROJECT Quality Plan/Quality Program, Quality Control Plan/Inspection and Test Plan, construction and design drawings, calculations, correspondence, inspection and test reports, field inspection checklist, etc. j. Material/Equipment Handling, Storage, Identification and Control CONTRACTOR shall verify that material/equipment meet prescribed contractual requirements and are properly handled, identifiable, traceable, cleaned, preserved and stored. k. Control of interface and interaction between the COMPANY and CONTRACTOR and between the CONTRACTOR and its SUBCONTRACTORS, manufacturers/suppliers, QA/QC Services CONTRACTOR(s) [Independent Inspection Agency (ies)] and Independent Testing Laboratories. Any other applicable QA/QC activity (ies) for the PROJECT.

NO.

CHKD

REVISIONS

DRAWN BY DATE CHKD BY

APPROVED ENGINEERING DEPT.

ADC / DVD

OPERATING DEPT.

CERTIFIED

BY: :

MQQ

THIS DRAWING IS NOT TO BE USED FOR CONSTRUCTION OR FOR ORDERING MATERIALS UNTIL CERTIFIED AND DATED

l. 4.

Design Control
PLANT NO. INDEX PTS NO. PAGE NO. REV.

[[PTS- 14ED416 doc. MQQ/ADC/DVD) November 2013 ]

SCOPE OF WORK AND TECHNICAL SPECIFICATIONS


JOB ORDER NO.

1-- 1443026 111

FOR REPLACEMENT OF HVAC SYSTEM AT EASTERN OPERATING AREA SUBSTATION

D047

PTS-14ED416

SAUDI ARABIA

28 OF 77

CERT.

SAUDI ELECTRICITY COMPANY

CHKD

APPD

a.

DESCRIPTION

If the CONTRACTOR is responsible for any design activity, CONTRACTOR shall describe the design control program that will be applied on this PROJECT whether the design activity is to be done by the CONTRACTORs own personnel or by design consultants. All design input and output shall be reviewed prior to release to the next stage. Hold points shall be shown or indicated in the PROJECT Quality Plan. In addition to design review, design verification shall be conducted to ensure that the design stage output meets the design stage input requirements. CONTRACTOR shall ensure that all design computations, design drawings and other design documents are properly controlled and checked prior to submission to the COMPANY. Design documents shall be signed by the person(s) who prepared and checked them. COMPANY reserves the right to return design documents without the proper signature of the responsible person(s).

b.
NO.

REVISIONS

DRAWN BY DATE CHKD BY

5.

Field Testing/Inspection and Construction/Installation Control CONTRACTOR shall establish and document all procedures and WORK instructions to ensure that the construction and installation processes are performed in a controlled manner. The necessary qualification of personnel and procedure for activities such as welding, non-destructive examination, heat treatment, civil/concrete WORKS, etc. shall be defined. WORK instructions and procedures shall be adhered to by the CONTRACTORs personnel. CONTRACTOR shall conduct inspection and testing activities at all phases and quality audit at appropriate stages of the PROJECT construction/installation. CONTRACTORs QA/QC engineers/inspectors shall develop and use field inspection checklist to facilitate checking of a process, activity, material or equipment. The field inspection checklist shall state the characteristic to be verified, inspection method, acceptance criteria and clause reference of the `applicable standard or specification. The checklist shall have provision for writing the result of inspection, date of inspection and name and signature of the QA/QC engineer/inspector. Such activities where inspection checklists are required shall include but not necessarily limited to all pre-commissioning and commissioning checks and tests, material/equipment receiving inspection, concrete pre-pour inspection, pressure testing of equipment and lines and air balancing and leak testing of HVAC system. All inspection and testing results shall be reviewed, safely stored and maintained by the CONTRACTOR. Typical checklist shall be provided to the COMPANY for review and comment. CONTRACTOR shall develop and implement the use of inspection logbook for use by the CONTRACTORs QA/QC engineers/inspectors in recording their comments and observations as a result of their inspection. CONTRACTORs personnel responsible for rectifying any observed deficiency or non-conformance shall also writ CONTRACTORs QA/QC engineers/inspectors shall ensure that all unsatisfactory observations e their reply in the logbook stating the actions taken to

APPROVED ENGINEERING DEPT.

ADC / DVD

OPERATING DEPT.

CERTIFIED

BY: :

MQQ

THIS DRAWING IS NOT TO BE USED FOR CONSTRUCTION OR FOR ORDERING MATERIALS UNTIL CERTIFIED AND DATED

[[PTS- 14ED416 doc. MQQ/ADC/DVD) November 2013 ]


PLANT NO. INDEX PTS NO. PAGE NO. REV.

SCOPE OF WORK AND TECHNICAL SPECIFICATIONS


JOB ORDER NO.

1-- 1443026 111

FOR REPLACEMENT OF HVAC SYSTEM AT EASTERN OPERATING AREA SUBSTATION

D047

PTS-14ED416

SAUDI ARABIA

29 OF 77

CERT.

SAUDI ELECTRICITY COMPANY

APPD

CHKD

correct the deficiency. CONT on an item are cleared before any activity proceeds to the succeeding stage of that item. C. Quality Control Plan/Inspection and Test Plan

NO.

DESCRIPTION

1.

CONTRACTOR shall submit to the COMPANY the Quality Control Plan/Inspection and Test Plan for each major material/equipment of the PROJECT. The quality activities including but not necessarily limited to, inspection and testing, for the material/equipment shall be planned and documented in the form of a Quality Control Plan/Inspection and Test Plan. The Quality Control Plan/Inspection and Test Plan shall be submitted to the COMPANY together with the PROJECT Quality Plan/Quality Program. The essential features of the required Quality Control Plan/Inspection and Test Plan are as follows: a. b. It is specifically identified to a particular material/equipment. It has provision for revisions to be made and is assigned a unique document number. It lists all the inspection and testing activities sequentially. It states the location at which the activity is to be carried out. It identifies the applicable standard, test procedure to be followed and the acceptance criteria for the inspection or test activity. It identifies the extent of inspection, or extent of check. It identifies the hold point, witness point and surveillance point. It identifies the record document to be generated, reviewed and retained.

2.

REVISIONS

DRAWN BY DATE CHKD BY

APPROVED ENGINEERING DEPT.

c. d.

ADC / DVD

e. f.
OPERATING DEPT.

g. h. 3.
CERTIFIED BY: :

The Quality Control Plan/Inspection and Test Plan shall indicate the scheduled dates of testing and inspection at the designated location.

MQQ

D. Manufacturers/Suppliers 1. CONTRACTOR shall procure all major material items for the PROJECT from COMPANY qualified and approved sources. CONTRACTOR shall ensure that purchase orders to manufacturers/suppliers contain all the applicable industry and COMPANY developed standards and specifications. CONTRACTOR shall ensure that Purchase Order(s) to approved manufacturers/ suppliers are not re-assigned or sub-contracted to other manufacturers/suppliers without COMPANYs written consent.

2.
THIS DRAWING IS NOT TO BE USED FOR CONSTRUCTION OR FOR ORDERING MATERIALS UNTIL CERTIFIED AND DATED

3.

[[PTS- 14ED416 doc. MQQ/ADC/DVD) November 2013 ]


PLANT NO. INDEX PTS NO. PAGE NO. REV.

SCOPE OF WORK AND TECHNICAL SPECIFICATIONS


JOB ORDER NO.

1-- 1443026 111

FOR REPLACEMENT OF HVAC SYSTEM AT EASTERN OPERATING AREA SUBSTATION

D047

PTS-14ED416

SAUDI ARABIA

30 OF 77

CERT.

SAUDI ELECTRICITY COMPANY

CHKD

APPD

E. Quality Assurance and Quality Control Services CONTRACTOR(s) [Independent Inspection Agency] 1. CONTRACTOR shall CONTRACT COMPANY approved Quality Assurance and Quality Control Services CONTRACTOR(s) to provide quality control/quality assurance monitoring of all quality activities related to procurement of materials and equipment to be used in this PROJECT. CONTRACTOR shall instruct the contracted Quality Assurance and Quality Control Services CONTRACTOR(s) to provide directly to COMPANY REPRESENTATIVE, by express mail or fax, four (4) copies of material status, quality surveillance reports, inspection and test reports within seven (7) days after the inspection. All pages of the inspection and test reports shall be reviewed, signed and stamped by the approved inspector from the Quality Assurance and Quality Control Services CONTRACTOR. CONTRACTORs Quality Assurance and Quality Control Services CONTRACTOR shall not re-assign or sublet portion of their contracted quality control/quality assurance monitoring WORK. CONTRACTOR shall provide the COMPANY a copy of the Scope of WORK issued to the Quality Assurance and Quality Control Services CONTRACTOR. CONTRACTOR shall instruct the Quality Assurance and Quality Control Services CONTRACTOR to verify and check each material/equipment for conformance against the PROJECT Scope of WORK and Technical Specification and each clause of the applicable SEC-ERB Material Standard Specification (SMSS) and report all deviations that are not included in the COMPANY issued clarifications. The report of the Quality Assurance and Quality Control Services CONTRACTOR shall include the following: a.
CERTIFIED

DESCRIPTION

2.

NO.

REVISIONS

DRAWN BY DATE CHKD BY

3.

APPROVED ENGINEERING DEPT.

4.

ADC / DVD

5.

OPERATING DEPT.

PROJECT title, CONTRACT number Complete description of the inspected material/equipment. Report number and date Place and date of inspection, scope of inspection Documents used during inspection. Manufacturer and plant location where the equipment was manufactured. Detailed description of the inspection and testing activities and their results, deviations to specification, manufacturers explanation to the deviations, visual inspection result, packing and marking inspection result, conclusion and copy of the outline drawing of the inspected material/equipment.

b. c. d. e. f.

BY: :

MQQ

THIS DRAWING IS NOT TO BE USED FOR CONSTRUCTION OR FOR ORDERING MATERIALS UNTIL CERTIFIED AND DATED

g.

[[PTS- 14ED416 doc. MQQ/ADC/DVD) November 2013 ]


PLANT NO. INDEX PTS NO. PAGE NO. REV.

SCOPE OF WORK AND TECHNICAL SPECIFICATIONS


JOB ORDER NO.

1-- 1443026 111

FOR REPLACEMENT OF HVAC SYSTEM AT EASTERN OPERATING AREA SUBSTATION

D047

PTS-14ED416

SAUDI ARABIA

31 OF 77

CERT.

SAUDI ELECTRICITY COMPANY

APPD

CHKD

Witnessed tests and reviewed test data shall be clearly identified in the inspection reports. h. Name of the inspector(s)

DESCRIPTION

6.

CONTRACTOR shall furnish copies of the following document to the Quality Assurance and Quality Control Services CONTRACTOR(s) contracted to perform quality assurance and quality control monitoring of each material and equipment before surveillance: a. Purchase Order placed to the manufacturer/supplier. Relevant section of PROJECT Scope of WORK and Technical Specification Applicable COMPANY developed standard and specification. Manufacturers Technical Specifications and COMPANY approved design drawings. COMPANYs approval of material/equipment and applicable clarifications issued by the COMPANY COMPANY approved test program, manufacturing quality control plan or inspection and test plan.

NO.

b.
3 2 1

REVISIONS

c. d.

DRAWN BY DATE CHKD BY

e.
APPROVED ENGINEERING DEPT.

f.
ADC / DVD

7.
OPERATING DEPT.

CONTRACTOR shall send to the COMPANY, copy (ies) of all technical correspondence exchanged between CONTRACTOR and Quality Assurance and Quality Control Services CONTRACTOR. CONTRACTOR shall obtain approval from COMPANY before allowing any personnel of the Quality Assurance and Quality Control Services CONTRACTOR to perform quality assurance and quality control monitoring activities related to procurement of materials to be used in this PROJECT. The specific material/equipment to be inspected, manufacturer and location of manufacturing plant shall be identified for each proposed inspector of the Quality Assurance and Quality Control Services CONTRACTOR. Employment by CONTRACTOR of a Quality Assurance and Quality Control Services CONTRACTOR shall in no way relieve the CONTRACTOR of any obligation set forth in this CONTRACT.

8.

CERTIFIED

BY: :

MQQ

9.

F.
THIS DRAWING IS NOT TO BE USED FOR CONSTRUCTION OR FOR ORDERING MATERIALS UNTIL CERTIFIED AND DATED

Release for Shipment Certificate 1. Release for Shipment Certificate is a certificate issued by the CONTRACTOR to the supplier/manufacturer to release the described material for shipment after recommendation by the Quality Assurance and Quality Control Services CONTRACTOR and approval by the COMPANY.

[[PTS- 14ED416 doc. MQQ/ADC/DVD) November 2013 ]


PLANT NO. INDEX PTS NO. PAGE NO. REV.

SCOPE OF WORK AND TECHNICAL SPECIFICATIONS


JOB ORDER NO.

1-- 1443026 111

FOR REPLACEMENT OF HVAC SYSTEM AT EASTERN OPERATING AREA SUBSTATION

D047

PTS-14ED416

SAUDI ARABIA

32 OF 77

CERT.

SAUDI ELECTRICITY COMPANY

APPD

CHKD

2.

CONTRACTOR shall ensure that all material requiring inspection and/or quality surveillance at the supplier/manufacturers facility are not shipped to the WORK SITE without a Release for Shipment Certificate. CONTRACTOR acknowledges that material shipped without approved Release for Shipment Certificate is subject to rejection and return at the CONTRACTORs expense. CONTRACTOR shall ensure that all inspection and surveillance reports and any other requirements are satisfactorily completed before requesting the COMPANY to approve the Release for Shipment Certificate.

3.
DESCRIPTION

4.

NO.

G. Receipt Inspection
3 2 1

REVISIONS

1.

DRAWN BY DATE CHKD BY

CONTRACTOR shall conduct receipt inspection of major material and equipment after delivery at the WORKSITE and shall submit a copy of the report to the COMPANY. CONTRACTOR shall promptly report to the COMPANY any shipment and transportation damage.

2.

APPROVED ENGINEERING DEPT.

H. Independent Testing Laboratory 1. CONTRACTOR shall contract COMPANY approved Laboratory for material and field testing services. Independent Testing

ADC / DVD

2.
OPERATING DEPT.

CONTRACTOR shall instruct the contracted Independent Testing Laboratory to provide four (4) copies of the test results and reports directly to COMPANY REPRESENTATIVE within three (3) days of the test completion. Test reports shall indicate the tested characteristics, test methods, acceptance criteria and applicable standard. The PROJECT Contract Number shall be used as reference on all reports. CONTRACTOR shall ensure that contracted Independent Testing Laboratory does not re-assign or sublet any portion of their contracted testing WORK. CONTRACTOR shall provide the COMPANY a copy of the Scope of WORK issued to and finalized with the Independent Testing Laboratory. CONTRACTOR shall make reasonable effort to obtain timely access by the COMPANY REPRESENTATIVE to the Independent Testing Laboratorys facility, should the COMPANY REPRESENTATIVE exercise the option to witness any or all the tests and verify the calibration status of the testing equipment. 6. Employment by CONTRACTOR of an Independent Testing Laboratory shall in no way relieve CONTRACTOR of any obligation set forth in this CONTRACT. 7.

3.
CERTIFIED BY: :

MQQ

4.

5.

THIS DRAWING IS NOT TO BE USED FOR CONSTRUCTION OR FOR ORDERING MATERIALS UNTIL CERTIFIED AND DATED

[[PTS- 14ED416 doc. MQQ/ADC/DVD) November 2013 ]


PLANT NO. INDEX PTS NO. PAGE NO. REV.

SCOPE OF WORK AND TECHNICAL SPECIFICATIONS


JOB ORDER NO.

1-- 1443026 111

FOR REPLACEMENT OF HVAC SYSTEM AT EASTERN OPERATING AREA SUBSTATION

D047

PTS-14ED416

SAUDI ARABIA

33 OF 77

CERT.

SAUDI ELECTRICITY COMPANY

APPD

CHKD

I.

Inspection by COMPANY REPRESENTATIVE 1. COMPANY REPRESENTATIVE will conduct routine and/or periodic inspection of the WORK. CONTRACTOR shall provide facilities and access to COMPANY REPRESENTATIVE to inspect the WORK and witness the tests. CONTRACTOR shall advise the COMPANY REPRESENTATIVE in writing the schedule of any field or laboratory testing to be conducted for this PROJECT showing the dates and location of testing. CONTRACTOR shall attach a copy of the Completed Inspection Checklist or final/in-process inspection report by the CONTRACTORs QA/QC engineer/inspector on every Inspection Request submitted to the COMPANY. Contractor shall attach and submit Testing and Balancing Procedure and List of Testing Equipment with latest Calibration Certification with the Inspection Request for review by the Company Representative. CONTRACTORs QA/QC engineer/inspector shall ensure that the items for inspection covered by the CONTRACTORs Inspection Request are ready and in accordance with the CONTRACT requirements prior to inspection by COMPANY REPRESENTATIVE. Inspection and witnessing of testing at site by COMPANY REPRESENTATIVE shall be within the regular working hours of the COMPANY. CONTRACTORs schedule for inspection and witnessing of testing at site by COMPANY REPRESENTATIVE outside of the regular COMPANY working hours shall have prior approval from the COMPANY REPRESENTATIVE.

DESCRIPTION

2.

3.
NO.

REVISIONS

4.

DRAWN BY DATE CHKD BY

5.

APPROVED ENGINEERING DEPT.

ADC / DVD

OPERATING DEPT.

J.

COMPANYs Quality Assessment (Audit) Right 1. COMPANY reserves the right to conduct scheduled and/or unscheduled quality assessment of CONTRACTORs Quality System, PROJECT Operation, and PROJECT Quality Plan implementation. The results of such assessments (audits) shall be confidential between CONTRACTOR and COMPANY. CONTRACTOR shall provide all access and assistance in a timely manner to COMPANY personnel who will perform the quality assessment (audit). The CONTRACTOR shall implement corrective actions on all deficient areas discovered during the quality assessment (audit) within a mutually agreeable time frame. All costs (except cost of wages, transportation and lodging of COMPANY Quality Assessors) incurred during the quality assessment (audit) shall be borne by the CONTRACTOR. 2. CONTRACTOR shall include the following conditions on purchase order placed with the manufacturers/suppliers:

CERTIFIED

BY: :

MQQ

THIS DRAWING IS NOT TO BE USED FOR CONSTRUCTION OR FOR ORDERING MATERIALS UNTIL CERTIFIED AND DATED

[[PTS- 14ED416 doc. MQQ/ADC/DVD) November 2013 ]


PLANT NO. INDEX PTS NO. PAGE NO. REV.

SCOPE OF WORK AND TECHNICAL SPECIFICATIONS


JOB ORDER NO.

1-- 1443026 111

FOR REPLACEMENT OF HVAC SYSTEM AT EASTERN OPERATING AREA SUBSTATION

D047

PTS-14ED416

SAUDI ARABIA

34 OF 77

CERT.

SAUDI ELECTRICITY COMPANY

CHKD

APPD

NO.

COMPANY reserves the right to perform plant survey, quality assessment (audit), and quality surveillance activities and to inspect material at the suppliers/ manufacturers facility to verify compliance with the terms and conditions of the purchase order and its related documents. COMPANY reserves the right to witness any and all tests specified and to perform such visual examination (inspection) at the suppliers/manufacturers facility. COMPANY reserves the right to require certificates and data from the supplier/manufacturer on any pertinent aspect of the manufacturing process, including but not limited to, mill test reports, heat treatment certificates, welders and welding procedure qualification records, non-destructive examination records, test records and quality control manual that will form part of the non-material requirement that shall be shipped to COMPANY as a document package.
3 2 1

DESCRIPTION

REVISIONS

K. Additional Requirements The final COMPANY approved protection and control drawings with latest revision numbers shall be the only drawings used by the independent inspection agency for testing and acceptance of protection and control equipment. The acceptance criteria shall include individual device testing and complete functional and point to point wiring check of the panels in conjunction with the composite AC and DC schematics and the rear view panel wiring diagrams. Each check shall refer to specific drawing and revision number. This shall be implemented immediately after base design meeting.

DRAWN BY DATE CHKD BY

APPROVED ENGINEERING DEPT.

ADC / DVD

L.
OPERATING DEPT.

Quality Control on CONTRACTORS Workmanship Workmanship of the CONTRACTOR personnel in various tasks during the project shall be thoroughly monitored by the COMPANY REPRESENTATIVES. Task skill and pattern of handling shall be the key points of this check. In case of poor performance is observed, COMPANY will stop the WORK immediately and take corrective measures in order to maintain the PROJECTS quality.

CERTIFIED

BY: :

MQQ

2.08 COMMISSIONING, OPERATION AND MAINTENANCE MANUALS A. The CONTRACTOR shall submit to the COMPANY Commissioning, Operation and Maintenance Manuals, along with Pre-commissioning and Procedures Manuals, consisting of, as a minimum, the following documents: 1. Detailed manufacturer's instruction manuals applicable to each equipment installed. These manuals shall contain all information (including any special design and/or construction or operation feature) which may be required by the COMPANY for safe operation and maintenance of the new equipment and shall describe fully erection, commissioning, operation and maintenance procedures including mechanical/electrical tolerances for maintenance/repair purposes.

THIS DRAWING IS NOT TO BE USED FOR CONSTRUCTION OR FOR ORDERING MATERIALS UNTIL CERTIFIED AND DATED

[[PTS- 14ED416 doc. MQQ/ADC/DVD) November 2013 ]


PLANT NO. INDEX PTS NO. PAGE NO. REV.

SCOPE OF WORK AND TECHNICAL SPECIFICATIONS


JOB ORDER NO.

1-- 1443026 111

FOR REPLACEMENT OF HVAC SYSTEM AT EASTERN OPERATING AREA SUBSTATION

D047

PTS-14ED416

SAUDI ARABIA

35 OF 77

CERT.

SAUDI ELECTRICITY COMPANY

APPD

CHKD

2. 3.

Manufacturer's instruction manuals applicable to each particular test apparatus. Complete sets of exploded view drawings with comprehensive parts identification for each device to enable the COMPANY to catalogue and order. Interconnection and Schematic Diagrams. Setting and Calibration Procedures and Instructions.

DESCRIPTION

4. 5.

B. The submission schedule for commissioning, operation and maintenance manuals as detailed in (A) above, shall be as given below:
NO.

1.
3 2

Six (6) sets for preliminary review by COMPANY as to adequacy, completeness, and legibility at least eight (8) weeks before commencing commissioning tests. Four (4) complete sets of fully revised manuals (original and no photo copies) incorporating the COMPANY's comments to the full satisfaction of the COMPANY before mechanical completion of the PROJECT.

REVISIONS

2.
DRAWN BY DATE CHKD BY

APPROVED ENGINEERING DEPT.

2.09 TECHNICAL DATA MANUALS A. The CONTRACTOR shall provide technical data manuals for the HVAC equipment, specialties and controls installed under the scope of this PROJECT as indicated in the attached Appendix III. The manuals binders shall have COMPANY logo, binder number and PROJECT title, and CONTRACT Number on the front cover. 2.10 TEST RECORD BOOK A. The CONTRACTOR shall provide a "Test Record Book" which shall include the following: 1. 2. Factory test report of each particular equipment installed. Field test report, which shall include the following: a. Description of Equipment Tested and Manufacturer's Nameplate Data b. c. d. Description of Test List of Apparatus with Calibration Data Test Results Conclusions and Recommendations Appendix, including test forms

ADC / DVD

OPERATING DEPT.

CERTIFIED

BY: :

MQQ

THIS DRAWING IS NOT TO BE USED FOR CONSTRUCTION OR FOR ORDERING MATERIALS UNTIL CERTIFIED AND DATED

e. f.

[[PTS- 14ED416 doc. MQQ/ADC/DVD) November 2013 ]


PLANT NO. INDEX PTS NO. PAGE NO. REV.

SCOPE OF WORK AND TECHNICAL SPECIFICATIONS


JOB ORDER NO.

1-- 1443026 111

FOR REPLACEMENT OF HVAC SYSTEM AT EASTERN OPERATING AREA SUBSTATION

D047

PTS-14ED416

SAUDI ARABIA

36 OF 77

CERT.

SAUDI ELECTRICITY COMPANY

APPD

B. Each test form where applicable shall include a column quoting the acceptable maximum and minimum limits of the test in terms of voltage, current, frequency, time, etc. and include As Found and As Left values. C. Four (4) copies of the "Test Record Book" are to be submitted within thirty (30) days after completion of the PROJECT. 2.11 PLANT TAGGING OF EQUIPMENT AND INDEPENDENT COMPONENTS A. The CONTRACTOR shall affix Plant Tag to each and every individual equipment including independent components to be installed under this CONTRACT which have a material value of Five Thousand Saudi Riyals (SR 5,000), or more. The CONTRACTOR shall install Plant Tags adjacent to the Manufacturer's Data Plate or at any other place approved by the COMPANY REPRESENTATIVE. The CONTRACTOR shall affix Plant Tags by bolts and nuts, or rivets or welds, or adhesives, as instructed in writing by the COMPANY REPRESENTATIVE, depending on the type of equipment to be tagged. The CONTRACTOR shall complete Plant Tagging before Mechanical Completion. B. At least sixty (60) days before completion of the installation of all equipment covered under this CONTRACT, CONTRACTOR shall submit to COMPANY a list of all equipment and independent components to be tagged, using the format of COMPANY Form No. 16511 (2/10) Exhibit I to the Job Specifications. Based on this list, COMPANY shall assign Plant Tag Number to each item and CONTRACTOR shall install the Plant Tags in accordance with this list. COMPANY will, within one (1) month from the date of receipt of the list, issue to CONTRACTOR the Plant Tags together with the list showing assigned Plant Tag Numbers. C. The CONTRACTOR shall, if required, assist the COMPANY REPRESENTATIVE in locating all equipment identified by Plant Tag Numbers in accordance with the list provided by the CONTRACTOR. 2.12 LOSS PREVENTION REQUIREMENTS The CONTRACTOR and/or CONTRACTORs SUBCONTRACTOR(s) shall strictly comply with the following Loss Prevention requirements, in addition to the stipulations in Schedule A - General Terms and Conditions of CONTRACT: A. General Requirements 1. Strict adherence to all applicable provisions of the COMPANY Accident Prevention Manual and Construction Safety Manual (ISD Special Manual No. 6.483). 2. Compliance with the provisions of the COMPANY General Instructions on WORK Permit and Clearance Procedure (G.I. # 06011-0011). The CONTRACTOR shall have an authorized employee with certificate to receive WORK Permit. If the CONTRACTOR has no authorized employee, or has an employee with expired certificate, he shall be responsible to coordinate with the COMPANY REPRESENTATIVE for scheduling of WORK Permit training course. All activities

NO.

DESCRIPTION 3

CHKD

REVISIONS

DRAWN BY DATE CHKD BY

APPROVED ENGINEERING DEPT.

ADC / DVD

OPERATING DEPT.

CERTIFIED

BY: :

MQQ

THIS DRAWING IS NOT TO BE USED FOR CONSTRUCTION OR FOR ORDERING MATERIALS UNTIL CERTIFIED AND DATED

[[PTS- 14ED416 doc. MQQ/ADC/DVD) November 2013 ]


PLANT NO. INDEX PTS NO. PAGE NO. REV.

SCOPE OF WORK AND TECHNICAL SPECIFICATIONS


JOB ORDER NO.

1-- 1443026 111

FOR REPLACEMENT OF HVAC SYSTEM AT EASTERN OPERATING AREA SUBSTATION

D047

PTS-14ED416

SAUDI ARABIA

37 OF 77

CERT.

SAUDI ELECTRICITY COMPANY

APPD

CHKD

of the CONTRACTOR near or inside the substation shall be allowed only after securing WORK Permit. 3. The CONTRACTOR shall submit his Loss Prevention Program to the COMPANY sufficiently in advance to obtain COMPANY approval prior to commencement of WORK at site. The Loss Prevention Programs shall contain the following: a. Cover Page complete with references, as follows: b. CONTRACTORs Name Title of Submittal PROJECT Title and Location CONTRACT Number COMPANYs Name

NO.

DESCRIPTION 3

REVISIONS

Table of Contents CONTRACTORs COMPANY Safety Policy Statement complete with signature over printed name and title of CONTRACTORs Management REPRESENTATIVE.

DRAWN BY DATE CHKD BY

c.

APPROVED ENGINEERING DEPT.

d.
ADC / DVD

Specific program items (suitable for the SOW) that the CONTRACTOR proposes to implement during the CONTRACT execution. Attachments necessary to supplement the program. PROJECT Table of Organization Construction Schedule CONTRACTORs standard forms for safety related reports.

e.
OPERATING DEPT.

4.

The CONTRACTOR shall provide necessary personal protective clothing (i.e. head, eye, face, hand, and foot protection) and respiratory protective equipment including personal protective equipment for fall protection such as safety belts and lifelines, and implement wearing them. The CONTRACTOR shall provide and use adequate and suitable safety/warning signs, cordon tapes, portable barricades, warning lights and personnel protective equipment at the JOB SITE to protect the safety of COMPANY and CONTRACTOR personnel and the public, and to prevent damage to property. The CONTRACTOR shall provide first aid facilities and must have a certified employee to administer first aid and Cardio-Pulmonary Resuscitation (CPR). The CONTRACTOR shall refrain from using mechanized excavation equipment within restricted areas unless cleared and permitted to do so. The CONTRACTOR shall request in advance a clearance for de-energizing the interfacing points and observe grounding procedures.

CERTIFIED

5
BY: :

MQQ

6.

THIS DRAWING IS NOT TO BE USED FOR CONSTRUCTION OR FOR ORDERING MATERIALS UNTIL CERTIFIED AND DATED

7.

8.

[[PTS- 14ED416 doc. MQQ/ADC/DVD) November 2013 ]


PLANT NO. INDEX PTS NO. PAGE NO. REV.

SCOPE OF WORK AND TECHNICAL SPECIFICATIONS


JOB ORDER NO.

1-- 1443026 111

FOR REPLACEMENT OF HVAC SYSTEM AT EASTERN OPERATING AREA SUBSTATION

D047

PTS-14ED416

SAUDI ARABIA

38 OF 77

CERT.

SAUDI ELECTRICITY COMPANY

APPD

CHKD

9.

The CONTRACTOR shall obtain from the COMPANY, ID cards for his employees and stickers for his vehicles/equipment prior to mobilization to site. In order to prevent theft/loss of materials/equipment, the CONTRACTOR shall take the necessary measures and precautions including but not limited to the following: a. All materials provided or used in this CONTRACT shall be stored by the CONTRACTOR in safe and secured locations even if stored for short period of time. If the equipment/materials are to be stored in the substation area for a prolonged period, the CONTRACTOR shall ensure that they are kept in locked containers or any other appropriate method of storage such that the materials/equipment are not easily noticeable by people with intention of theft or pilferage. Moreover, such containers shall be placed at a distance from the fence/boundary wall. The CONTRACTOR shall also consider all the storage requirements (i.e. temperature, humidity) of the materials/equipment being stored in containers, to avoid any damage during such storage period.

10.
DESCRIPTION

b.
NO. 3 2 1

REVISIONS

DRAWN BY DATE CHKD BY

c.

APPROVED ENGINEERING DEPT.

B. PROJECT Involving Elevated WORKS


ADC / DVD

1.

All Cranes, Lifting Gears and Bucket Truck to be used for the project by Contractor shall have a Valid Load Testing Certificate and Sticker issued by an Accredited Independent Testing Agency.. The CONTRACTORs ladders shall conform to OSHA (Occupational Safety and Health Administration) standard. Safety practices shall be followed in positioning ladders. Scaffolds shall be designed, built and inspected by a competent engineer prior to its use.

OPERATING DEPT.

2.

CERTIFIED

C. PROJECT Involving Welding and Cutting Operations 1. The CONTRACTOR shall provide suitable fire extinguishers to be used in case of fire emergencies. The CONTRACTOR shall provide the welding gas cylinders with suitable rack that is equipped with security chain(s).

BY: :

MQQ

2.

D.
THIS DRAWING IS NOT TO BE USED FOR CONSTRUCTION OR FOR ORDERING MATERIALS UNTIL CERTIFIED AND DATED

PROJECT near Energized Lines or Equipment Observe working clearances when working near or about energized line or equipment as per COMPANYs Accident Prevention Manual. PROJECT Requiring the Use of Chemical(s)

E.

[[PTS- 14ED416 doc. MQQ/ADC/DVD) November 2013 ]


PLANT NO. INDEX PTS NO. PAGE NO. REV.

SCOPE OF WORK AND TECHNICAL SPECIFICATIONS


JOB ORDER NO.

1-- 1443026 111

FOR REPLACEMENT OF HVAC SYSTEM AT EASTERN OPERATING AREA SUBSTATION

D047

PTS-14ED416

SAUDI ARABIA

39 OF 77

CERT.

SAUDI ELECTRICITY COMPANY

APPD

CHKD

Submit material safety data sheets (MSDS) of chemicals required or which are to be used in the execution of the PROJECT. 2.13 NAMEPLATE DATA

DESCRIPTION

Contractor shall provide digital images of nameplate of all new HVAC equiptment in all substation including relays. Minimum three (3) copies in CD'S to Concerned Department with a Project information label written. 2.14 REMOVAL/DISMANTLE OF EXISTING EQUIPTMENT Contractor shall follow Company Procedures of Concerned Proponent Department in the Company for Dismantled Materials before removing/dismantling any equiptment from existing facility. The Contractor shall submit complete Materials Disposition Request for old HVAC Units before removal from S/S Area and deliver to SEC Reclamation Yard.

NO.

REVISIONS

DRAWN BY DATE CHKD BY

2.15 SHUTDOWN/OUTAGE COORDINATION


APPROVED ENGINEERING DEPT.

Planned outages of existing equipment which are required for CONTRACTORs installation of new equipment, or movement/relocation of existing equipment shall be minimized by CONTRACTOR during his PROJECT execution. Where outages of existing equipment cannot be avoided, CONTRACTOR shall coordinate all details of planned outages through the COMPANY REPRESENTATIVE with initial coordination occurring during the base design stage of the PROJECT. As part of the CONTRACTORs coordination activity (for the planned outage), CONTRACTOR shall provide reasons, plans and detailed schedule for the planned outages that will be subjected to COMPANYs review and approval. COMPANYs approval of planned outages shall be based solely on COMPANYs operational considerations. CONTRACTOR shall note that, as a minimum requirement, COMPANY will consider approval of CONTRACTORs proposed planned outages during low load periods (beginning of November to start of April), and when CONTRACTOR shall provide enough manpower at the outage site(s) to minimize the planned outage time. No unplanned outages/disruptions of COMPANYs equipment or systems shall be allowed to support the CONTRACTORs installation of any new equipment, or CONTRACTORs movement/relocation of existing equipment at any site.

ADC / DVD

OPERATING DEPT.

CERTIFIED

BY: :

MQQ

THIS DRAWING IS NOT TO BE USED FOR CONSTRUCTION OR FOR ORDERING MATERIALS UNTIL CERTIFIED AND DATED

*** END OF SECTION II ****

[[PTS- 14ED416 doc. MQQ/ADC/DVD) November 2013 ]


PLANT NO. INDEX PTS NO. PAGE NO. REV.

SCOPE OF WORK AND TECHNICAL SPECIFICATIONS


JOB ORDER NO.

1-- 1443026 111

FOR REPLACEMENT OF HVAC SYSTEM AT EASTERN OPERATING AREA SUBSTATION

D047

PTS-14ED416

SAUDI ARABIA

40 OF 77

CERT.

SAUDI ELECTRICITY COMPANY

NO.

DESCRIPTION 3

CHKD

APPD

REVISIONS

DRAWN BY DATE CHKD BY

APPROVED ENGINEERING DEPT.

ADC / DVD

OPERATING DEPT.

CERTIFIED

BY: :

MQQ

SECTION III - SCOPE OF WORK 3.01 GENERAL The WORK shall include the Design, supply of labor , materials and tools/equipment for the installation of new HVAC units / removing retired HVAC units, Design and Installation of Air Supply and Return Air duct and Accessories, related Electrical and civil works, replacement of control systems, equipment start-up and commissioning ,testing ,adjusting and balancing of all HVAC systems and to execute other related services for the safe , efficient and reliable performance and complete installation of this PROJECT to the satisfaction of the COMPANY in conformance with the requirements of applicable Company and International Standards as prescribed below.

THIS DRAWING IS NOT TO BE USED FOR CONSTRUCTION OR FOR ORDERING MATERIALS UNTIL CERTIFIED AND DATED

[[PTS- 14ED416 doc. MQQ/ADC/DVD) November 2013 ]


PLANT NO. INDEX PTS NO. PAGE NO. REV.

SCOPE OF WORK AND TECHNICAL SPECIFICATIONS


JOB ORDER NO.

1-- 1443026 111

FOR REPLACEMENT OF HVAC SYSTEM AT EASTERN OPERATING AREA SUBSTATION

D047

PTS-14ED416

SAUDI ARABIA

41 OF 77

CERT.

SAUDI ELECTRICITY COMPANY

APPD

CHKD

3.02 MECHANICAL WORK A. Heating, Ventilating and Air Conditioning (HVAC) System 1. General

DESCRIPTION

NO.

The WORK shall include Design, supply of equipment, materials, labor and tools for the dismantling of the existing units as mentioned herein and installation of new equipment. The WORK shall also include equipment start-up, testing and commissioning and air balancing for the systems and to execute other related services for the safe, efficient and reliable performance and complete WORK of this PROJECT to the satisfaction of the COMPANY in conformance with the requirements as prescribed below.
3 2

REVISIONS

2. Existing Systems
DRAWN BY DATE CHKD BY

The WORK shall include, but not limited to the following. a. Furnish all labor and tools/equipment to remove existing Air Conditioning Units for all S/S then transport the same to the location as designated by COMPANY Representative. b. Furnish all labor, materials and tools/equipment to remove the control system including its control panel and wiring, then transport the same to the location as designated by COMPANY Representative. c. Furnish all labor and tools/equipment to close all wall/floor openings due to removal of A/c Units, pipe, electrical wiring penetrations and their openings necessary to prevent air infiltration shall also be sealed. d. Furnish all labor and tools/equipment to replace any material or equipment being damaged resulting from the above WORK.
CERTIFIED

APPROVED ENGINEERING DEPT.

ADC / DVD

OPERATING DEPT.

BY: :

MQQ

e. Remove all debris, rubbish and other materials resulting from above WORK, then transport and dispose to location as directed by the COMPANY REPRESENTATIVE. f. Installation of Temporary A/C Units as a Replacement to cool the Substation during Dismantling of Existing Units and Installation of New A/C Units

THIS DRAWING IS NOT TO BE USED FOR CONSTRUCTION OR FOR ORDERING MATERIALS UNTIL CERTIFIED AND DATED

3. New Systems Heating, Ventilating and Air Conditioning (HVAC) System to provide round the year cooling, dehumidifying, heating and ventilating for all substation as follows:

[[PTS- 14ED416 doc. MQQ/ADC/DVD) November 2013 ]


PLANT NO. INDEX PTS NO. PAGE NO. REV.

SCOPE OF WORK AND TECHNICAL SPECIFICATIONS


JOB ORDER NO.

1-- 1443026 111

FOR REPLACEMENT OF HVAC SYSTEM AT EASTERN OPERATING AREA SUBSTATION

D047

PTS-14ED416

SAUDI ARABIA

42 OF 77

CERT.

SAUDI ELECTRICITY COMPANY

APPD

DESCRIPTION

CHKD

a.

The Contractor shall gathered all the required Data on site ( Bldg, Existing Equiptment,Lightings, etc. ) for the Design and Load Calculation of the Required Capacity of each unit consisting of Two (2) direct expansion type Single Packaged Air Conditioning Units (PACU) and Two (2) Split Type A/C Units and as per 73-TMSS-01 in diffferent location.

b. Design, Fabrication and Installation of New Air Supply and Return Duct, Diffuser and other accessories for Air distribution System in the building. c. New HVAC DDC Control System d. Testing, Adjusting and Balancing of HVAC System.

NO.

REVISIONS

e. Provide Training for SEC Representative of three (3) Person for three (3) working days for HVAC Units and DDC Control Panel Operation. f. For other Mechanical Works, see Section 1.03

DRAWN BY DATE CHKD BY

APPROVED ENGINEERING DEPT.

3.03 ELECTRICAL WORK A. General:

ADC / DVD

OPERATING DEPT.

1. The CONTRACTOR shall carry out the replacement WORKS consisting of the following major equipments/systems indicated in this section. All components and accessories required for the satisfactory operation of the new facilities of the PROJECT, whether specified in detail or not, shall be supplied and installed as necessary. 2. The Bidder/CONTRACTOR shall visit the site and make be aware of the existing system/facilities.

CERTIFIED

BY: :

MQQ

B. Electrical Equipment and Facilities

1. All Substation ( Typical ) a. Provide and Install New HVAC DDC Control System, Main Circuit Breaker Inside Control Room, New Main Distribution Panel, New Main Control Panel complete with all accessories, Circuit Breakers,Disconnect Switch, new cable and control wirings required for new HVAC Unit . Sized and Capacity shall be as as per NEC and as per Manufacturer Recommendation. Power Source shall be terminated at Control Relay Room.

THIS DRAWING IS NOT TO BE USED FOR CONSTRUCTION OR FOR ORDERING MATERIALS UNTIL CERTIFIED AND DATED

[[PTS- 14ED416 doc. MQQ/ADC/DVD) November 2013 ]


PLANT NO. INDEX PTS NO. PAGE NO. REV.

SCOPE OF WORK AND TECHNICAL SPECIFICATIONS


JOB ORDER NO.

1-- 1443026 111

FOR REPLACEMENT OF HVAC SYSTEM AT EASTERN OPERATING AREA SUBSTATION

D047

PTS-14ED416

SAUDI ARABIA

43 OF 77

CERT.

SAUDI ELECTRICITY COMPANY

APPD

b. Cabling shall be carried out as per the requirements for new breakers and also for control supply feeders. New direct buried conduit shall be provided for new LV power cables as required. c. New Smoke Duct Detectors similar to or compatible with existing duct smoke detectors or existing system shall be installed and connected to the existing Fire Alarm Control Panel. Motorized Fire/Smoke Damper shall be installed and connected to the HVAC Panel Interlock with FACP. All other wirings/connections that will be removed/relocated as a result of activities related to the project shall be reinstalled to ensure normal / satisfactory operation of the system.

NO.

DESCRIPTION

CHKD

2. GENERAL a. All existing and new 220/127 control wirings and auxiliaries shall be fed from the new Control Panel. Existing wiring, conduit etc. from contactors for shutdown signal to existing A/C units from Fire Alarm Control Panel shall be disconnected and connect to new A/C units. New wirings and conduit shall be place up to the new A/C units. Cabling shall be carried out as per the requirements for new breakers and also for control supply feeders. New direct buried conduit shall be provided for new LV power cables. For other Electrical Works see Section 1.03. The Contractor shall be responsible for testing and commisioning of all newly installed equiptment and devices, including HVAC system start-up and shutdown to ensure that the system is in good operating condition prior to turn over to the Company (SEC ).
New HVAC Control System (DDC ) shall be installed to be interfaced to SCADA and FACP. A dedicated alarm for HVAC system fail "HVAC SYSTEM FAIL" shall be provided . This alarm shall be wired/terminated to the existing spare point of SCADA RTU. The contractor shall commission and test the alarm system with company representative.

REVISIONS

DRAWN BY DATE CHKD BY

b.

APPROVED ENGINEERING DEPT.

c.
ADC / DVD

d.
OPERATING DEPT.

e.

CERTIFIED

f.

BY: :

MQQ

3. Riyadh Water Pump Substation.


a) Removal and Replacement of existing Lighting Fixtures, wirings, condiuts and all accessories inside Substation. b) Removal and replacement of existing Exhaust Fan with Explosion Proof Type Exhaust Fan and all accessories in Battery room Area. Exhaust System shall be ducted with stainsteel sheet and with louver (2 Nos. )
[[PTS- 14ED416 doc. MQQ/ADC/DVD) November 2013 ]
PLANT NO. INDEX PTS NO. PAGE NO. REV.

THIS DRAWING IS NOT TO BE USED FOR CONSTRUCTION OR FOR ORDERING MATERIALS UNTIL CERTIFIED AND DATED

SCOPE OF WORK AND TECHNICAL SPECIFICATIONS


JOB ORDER NO.

1-- 1443026 111

FOR REPLACEMENT OF HVAC SYSTEM AT EASTERN OPERATING AREA SUBSTATION

D047

PTS-14ED416

SAUDI ARABIA

44 OF 77

CERT.

SAUDI ELECTRICITY COMPANY

CHKD

APPD

3.04 CIVIL WORKS AND MINIMUM REQUIREMENTS. The CONTRACTOR shall be responsible for following civil works.

DESCRIPTION

1. Dismantling/demolishing/modification of the existing HVAC equipment foundations. 2. Design and construction of new concrete foundations for HVAC equipment 3. Construction and Installation of new access Road inside the Substation 4. Design and construction of Removable-Type Steel Pipe Crash Barrier with chain link

NO.

for the new HVAC units. Crash barrier shall be connected to grounding system.
3 2 1

REVISIONS

5. Design, fabrication and installation of HVAC Equiptment Steel Structure Sunshade

DRAWN BY DATE CHKD BY

Cover ,Steel Support and its foundation and shall be provided with grounding system.
6. Replace any materials damaged/undersized resulting from installation of new HVAC

units
APPROVED ENGINEERING DEPT.

7. Furnish all labor, materials and tools/equipment to cover the wall of similar materials

ADC / DVD

and restore walls where equipment, etc. mentioned above are removed, then paint the walls as required. All other openings necessary to prevent air infiltration shall also be sealed.
8. Removal and replacement of Existing Acoustic Ceiling Tiles, T-Runner, Steel

OPERATING DEPT.

Support and all accessories inside Riyadh Water Pump Substation Room. Construction of 200mm thick plastered CMU wall painted with semi-gloss acid resistant coating to enclosed battery room. Installation of (200 x 200 mm) acid resistant tiles inside the battery room. Repair, refurnishing, and recoating with floor hardener epoxy coating of the substation switchgear/control room flooring. All other openings necessary to prevent air infiltration shall also be sealed.
9. Line and grade restoration. Gravel mulch-laying and restoration of asphalt and

CERTIFIED

BY: :

MQQ

concrete pavement, concrete gutter around the new HVAC equipment and extension of access road.
10. Perform soil and base-course compaction on excavated area. Compaction density

test shall be conducted by laboratory agency approved by the COMPANY. Testing should be witnessed by COMPANY REPRESENTATIVE.
11. Prior to concrete pouring for lean concrete, any direct burried underground cables
THIS DRAWING IS NOT TO BE USED FOR CONSTRUCTION OR FOR ORDERING MATERIALS UNTIL CERTIFIED AND DATED

encountered on site shall be encased with concrete duct bank with PVC sleeves in reference to minimum electrical requirements for duct banks. Provide minimum reinforcement connected to grounding system for this concrete encased duct bank.
12. Top of foundation edge shall be provided with 20x20mm champer. Exposed

concrete for the equipment foundation shall be coated with 2-coats UV resistant
[[PTS- 14ED416 doc. MQQ/ADC/DVD) November 2013 ]
PLANT NO. INDEX PTS NO. PAGE NO. REV.

SCOPE OF WORK AND TECHNICAL SPECIFICATIONS


JOB ORDER NO.

1-- 1443026 111

FOR REPLACEMENT OF HVAC SYSTEM AT EASTERN OPERATING AREA SUBSTATION

D047

PTS-14ED416

SAUDI ARABIA

45 OF 77

CERT.

SAUDI ELECTRICITY COMPANY

APPD

DESCRIPTION

polyurethane coating (gray color). And for concrete in contact with soil shall be coated with 3 coats- bituminous coal tar coating. Laying of lean concrete shall be provided with 2 layer of 3-mil polyethylene vapor barrier. Equipment concrete foundation shall be provided with minimum of 16mm Reinforcement bar , with a spacing base on equipment weight and structural design and calculation results and requirements to be submitted by CONTRACTOR.
13. Perform concrete testing to be conducted by third party laboratory agency approved

CHKD

by COMPANY. All reports, tests results including equipment calibration certificate shall be submitted to the COMPANY.
14. Restoration works. Removal of all debris, rubbish and other materials resulting from

above WORK and transport to the location designated by the COMPANY REPRESENTATIVE.
15. Old A/C Units removed shall be transport by the Contractor to Dharan Central

NO.

REVISIONS

DRAWN BY DATE CHKD BY

Yard or to the location designated by the company

APPROVED ENGINEERING DEPT.

3.05 PROJECT DESIGN DOCUMENTS, CALCULATIONS AND DRAWINGS


ADC / DVD

A. The CONTRACTOR shall submit all design documents, calculations, studies, drawings and compliance statement at various stages of the PROJECT as per Table 3.01, as a minimum. Table 3.01
INDEX A TITLE Equipment/Materials LV Cables Disconnect Switches Grounding Conductor and Accessories Conduits Cable Trays HVAC Equipment Design Calculations, Test & Procedure Calculations for Grounding Conductor Sizing & System Design LV Cable Sizing Calculations for PACU Design calculation for PACU foundation HVAC System Design Calculations Drainage System Design Calculations PROJECT PERT/CPM Schedule for Monitoring and Control of Activities CONTRACTORs Loss Prevention Program Site Security Plan
[[PTS- 14ED416 doc. MQQ/ADC/DVD) November 2013 ]
PLANT NO. INDEX PTS NO. PAGE NO. REV.

OPERATING DEPT.

Bid Stage

Base Design Stage X X X X X X

Detail & Construct. Stage X, I X, VI, IV, I X, II X, II X, II X, IV X, II X, II X, I X, V X, V

AsBuilt Stage

CERTIFIED

BY: :

MQQ

X X X

X X X X X

THIS DRAWING IS NOT TO BE USED FOR CONSTRUCTION OR FOR ORDERING MATERIALS UNTIL CERTIFIED AND DATED

X X X X X X

SCOPE OF WORK AND TECHNICAL SPECIFICATIONS


JOB ORDER NO.

1-- 1443026 111

FOR REPLACEMENT OF HVAC SYSTEM AT EASTERN OPERATING AREA SUBSTATION

D047

PTS-14ED416

SAUDI ARABIA

46 OF 77

CERT.

SAUDI ELECTRICITY COMPANY


QA/QC Plan Inspection and Test Plan Factory Test Procedure Site Test Procedure A schedule showing the outages requirements for the PROJECT on the existing facilities Design Drawings Abbreviations, Symbols and Legend Cable and Conduit Schedule Single Line Diagrams Vendor Schematic Diagrams Equipment Layout of Substation Revision of Existing System Drawings HVAC Plan and Sections HVAC Details Drainage Layout and Details General Notes (Design Methodology, Design Data, Concrete, Rebars, Formwork, etc.) PACU foundation details and Rebar Details Consolidated Drawing Control List


X X X X X X X X X X X X X X X X, IV X, IV X X, IV X, IV X, IV X, V X, V X, V X, I X,II X, I X X X X X X X X X X X X

CHKD

APPD

DESCRIPTION

K
NO. 3 2 1

REVISIONS

L Q
R

DRAWN BY DATE CHKD BY

X - indicates requirement for submission. Partial submittal of calculations/drawings in any group will not be accepted.
1. Base Design Stage

APPROVED ENGINEERING DEPT.

ADC / DVD

The following shall be provided for each indicated item in the table: Design Calculations Design Drawings Vendor Drawings and Literatures Inspection and test plan Data schedules duly signed, stamped, dated by the equipment/material manufacturer and CONTRACTOR. - Clause by Clause compliance statements duly signed, stamped, dated by the equipment/material manufacturer and CONTRACTOR.
2. Final (Detail) Design and Construction Drawings Stage a. Final Design Drawings

OPERATING DEPT.

CERTIFIED

BY: :

MQQ

THIS DRAWING IS NOT TO BE USED FOR CONSTRUCTION OR FOR ORDERING MATERIALS UNTIL CERTIFIED AND DATED

- Final Design Drawings shall be provided for each indicated item in the table. - Final design calculation for the project and additional calculations, if required. - Final approval of Design Drawings, after incorporating all comments of COMPANY, shall be obtained. - Vendor Drawings
b. Construction Drawings
[[PTS- 14ED416 doc. MQQ/ADC/DVD) November 2013 ]
PLANT NO. INDEX PTS NO. PAGE NO. REV.

SCOPE OF WORK AND TECHNICAL SPECIFICATIONS


JOB ORDER NO.

1-- 1443026 111

FOR REPLACEMENT OF HVAC SYSTEM AT EASTERN OPERATING AREA SUBSTATION

D047

PTS-14ED416

SAUDI ARABIA

47 OF 77

CERT.

SAUDI ELECTRICITY COMPANY

APPD

- Final Construction Drawings shall be provided for each indicated item in the table. - Revised final Construction Drawings shall be provided, if required. 3. As-Built Stage - As-built Drawings shall be provided for each indicated item in the table. B. Along with the base design/final detail design/construction/as-built drawings package, CONTRACTOR shall submit the following in Adobe Portable Document Format (PDF) files: 1. 2. 3. 4. Base design/Final detail design/As-built Drawings Design Calculations Equipment Catalogue Material data schedules

NO.

DESCRIPTION 3

CHKD

REVISIONS

DRAWN BY DATE CHKD BY

The revision numbers and notes reflecting the changes made throughout the design shall be retained in the submitted final detail design drawings. Also, the input and output files for design calculations carried out by computer programs shall be furnished. All PDF files shall have the following document security level: (1) without open password, (2) allowing for printing and (3) allowing for text and graphics selection. 3.06 STANDARDS, CODES AND SPECIFICATIONS All WORKS equipment and material covered by this document shall conform to the latest edition of the COMPANY's Material Standard Specifications supplemented with latest applicable industry Standards, Codes and Specifications. The latest edition of each Standard and Specification shall mean the latest edition specified hereunder. The CONTRACTOR shall strictly comply with the following Standards, Codes and Specifications, and no deviation shall be accepted unless otherwise accepted by a written waiver from COMPANY. The CONTRACTOR may propose "equivalent" Standards and Specifications if such standards and specifications are equal to or better than those specified herein, and shall be subject to prior approval of the COMPANY. A. COMPANY Materials Standard Specifications 01-TMSS-01 (Rev. 4) General Requirements for All Equipment/Materials

APPROVED ENGINEERING DEPT.

ADC / DVD

OPERATING DEPT.

CERTIFIED

BY: :

MQQ

THIS DRAWING IS NOT TO BE USED FOR CONSTRUCTION OR FOR ORDERING MATERIALS UNTIL CERTIFIED AND DATED

11-TMSS-11 (Rev. 2) 11-TMSS-12 (Rev. 6)

Instrumentation Cables, Shielded

Power and/or Control Cable, CU or AL Conductor 600/1000 V Rating

[[PTS- 14ED416 doc. MQQ/ADC/DVD) November 2013 ]


PLANT NO. INDEX PTS NO. PAGE NO. REV.

SCOPE OF WORK AND TECHNICAL SPECIFICATIONS


JOB ORDER NO.

1-- 1443026 111

FOR REPLACEMENT OF HVAC SYSTEM AT EASTERN OPERATING AREA SUBSTATION

D047

PTS-14ED416

SAUDI ARABIA

48 OF 77

CERT.

SAUDI ELECTRICITY COMPANY

APPD

CHKD

23-TMSS-1 (Rev. 2) 25-TMSS-1 (Rev 4)

PVC Conduits and fittings for Underground ducts

Duct Sealing Units

DESCRIPTION

31-TMSS-7 40-TMSS-2 70-TMSS-03 (Rev. 1)

Auxiliary AC/DC Panels Metering Devices Normal Weight Ready- Mixed Portland Cement Concrete

NO.

REVISIONS

73-TMSS-01 (Rev. 1)

Air Conditioning Units, Packaged and Split Type A/C Units.

DRAWN BY DATE CHKD BY

COMPANY Engineering Standards TES-H-001 (Rev. 3) TES-H-001.01 (Rev. 3) TES-H-107 (Rev. 0) Painting Standards

APPROVED ENGINEERING DEPT.

Painting Color Codes and Standards

ADC / DVD

Paints and coatings

OPERATING DEPT.

TES-K-100 (Rev. 2)

HVAC Systems Design

TES-P-104 Underground Cable Engineering Standards (Control sheet Issue 6)


CERTIFIED

TES-W-1
BY: :

General Welding Criteria Fire Alarm

MQQ

TES-B-001

TES-P-119.21 - Fire and Loss Prevention Requirement TES-P-119


THIS DRAWING IS NOT TO BE USED FOR CONSTRUCTION OR FOR ORDERING MATERIALS UNTIL CERTIFIED AND DATED

Substation Design Standards

B. COMPANY Construction Standards TCS-K-100 (Rev. 1) HVAC Systems and Equipment Installation

[[PTS- 14ED416 doc. MQQ/ADC/DVD) November 2013 ]


PLANT NO. INDEX PTS NO. PAGE NO. REV.

SCOPE OF WORK AND TECHNICAL SPECIFICATIONS


JOB ORDER NO.

1-- 1443026 111

FOR REPLACEMENT OF HVAC SYSTEM AT EASTERN OPERATING AREA SUBSTATION

D047

PTS-14ED416

SAUDI ARABIA

49 OF 77

CERT.

SAUDI ELECTRICITY COMPANY

APPD

CHKD

TCS-Q-001 (Rev. 2)

Paving, Asphalt Concrete

TCS-P-104 Underground Cable Construction Standards (Control sheet Issue 5)


DESCRIPTION

TCS-Q-113.02 (Rev. 0) TCS-Q-113.03 (Rev. 0)

Earthworks

Cast-In-Place Concrete

NO.

TCS-Q-113.04
3 2 1

Precast Concrete Works Reinforced Concrete Masonry

REVISIONS

TCS-Q-113.05

DRAWN BY DATE CHKD BY

C. Other Standards SEEDS II


APPROVED

Saudi Electricity Company Engineering Drawings Standard National Electric Code National Electric Code
STEEL BARS FOR REINFORCEMENT OF OF CONCRETE

ENGINEERING DEPT.

NFPA 70 NFPA 72

ADC / DVD

SASO / SSA-2/79
OPERATING DEPT.

ACI ASTM

AMERICAN CONCRETE INSTITUTE.

American Society for Testing and Materials

CERTIFIED

BY: :

MQQ

*** END OF SECTION III ****

THIS DRAWING IS NOT TO BE USED FOR CONSTRUCTION OR FOR ORDERING MATERIALS UNTIL CERTIFIED AND DATED

SECTION IV - EQUIPMENT/MATERIALS, DESIGN CRITERIA AND TECHNICAL SPECIFICATIONS

[[PTS- 14ED416 doc. MQQ/ADC/DVD) November 2013 ]


PLANT NO. INDEX PTS NO. PAGE NO. REV.

SCOPE OF WORK AND TECHNICAL SPECIFICATIONS


JOB ORDER NO.

1-- 1443026 111

FOR REPLACEMENT OF HVAC SYSTEM AT EASTERN OPERATING AREA SUBSTATION

D047

PTS-14ED416

SAUDI ARABIA

50 OF 77

CERT.

SAUDI ELECTRICITY COMPANY

APPD

CHKD

4.01 GENERAL This Section outlines broadly the technical specifications of the major equipment/ materials required for the complete installation of the PROJECT. The specifications outlined herein shall be read in conjunction with the COMPANY Material Standard Specifications and the associated International Standards and Codes. The ratings and specific requirements of the various equipment shall be as indicated in Data Schedule of COMPANY Material Standard Specifications, and the CONTRACTOR shall ensure full conformity with the same.

DESCRIPTION

4.02 HVAC SYSTEM REQUIREMENTS


NO. 3 2 1

A. General 1. Heating, Ventilating and Air Conditioning System shall be provided to maintain the desired indoor temperature and environmental condition for efficient equipment operation. HVAC System shall conform to the applicable requirements of SECERB Std. TES-P-119.19 Rev. 2. All units shall be mounted on the reinforced concrete pads with the necessary vibration isolators. Air distribution (supply and return) system shall be through externally insulated rectangular ductwork. Airflow direction shall be marked-up on outdoor ducts for easy identification. Exposed duct insulation shall be protected from all weather conditions and provided with aluminum cladding that is resistant to ultraviolet radiation. In case of disconnection of any existing duct detectors or any part of the fire alarm system, ISD/FF&LPD should be notified. Also, after the installation of the new duct detectors or any part of the fire alarm system, a test should be conducted and attended by ISD/FF&LPD representative. Contractor shall provide all materials required for the relocation of fire alarm system devices if required. All fresh air make-up shall be through sand trap louver with air filtration, volume control damper and removable 13mm wire mesh screen. Design Calculation and Equipment Selection shall be performed by the CONTRACTOR. Ambient and Indoor conditions to be considered in design/calculation of HVAC cooling load and selection of the equipment shall be per TES-K-100, latest revision.

REVISIONS

DRAWN BY DATE CHKD BY

APPROVED ENGINEERING DEPT.

2.

3.
ADC / DVD

OPERATING DEPT.

4.

CERTIFIED

BY: :

MQQ

5.

6.

THIS DRAWING IS NOT TO BE USED FOR CONSTRUCTION OR FOR ORDERING MATERIALS UNTIL CERTIFIED AND DATED

B. HVAC Control System

[[PTS- 14ED416 doc. MQQ/ADC/DVD) November 2013 ]


PLANT NO. INDEX PTS NO. PAGE NO. REV.

SCOPE OF WORK AND TECHNICAL SPECIFICATIONS


JOB ORDER NO.

1-- 1443026 111

FOR REPLACEMENT OF HVAC SYSTEM AT EASTERN OPERATING AREA SUBSTATION

D047

PTS-14ED416

SAUDI ARABIA

51 OF 77

CERT.

SAUDI ELECTRICITY COMPANY

APPD

CHKD

1.

The Direct Digital Control (DDC) system shall be compact module type 24V DC shall contain digital and analogue for input and output points as specified below: a. All alarms and indications (such as pre-filter, bag filter, exhaust fans, etc.) shall be consider as input points in DDC system. Compact module DDC shall be at least 16 points input and 16 points output. DDC shall be ready to communicate with computer system to building B.M.S. in the future. DDC compact module shall be at least 20% free points spare. DDC test set shall be provided by the CONTRACTOR for maintenance purposes. Portable operators terminal shall be provided.

DESCRIPTION

b. c. d.

NO.

e. f. 2.

REVISIONS

DRAWN BY DATE CHKD BY

Control system shall also be provided with all the necessary pressure and temperature control protective devices. Provide duct smoke detectors complete with response indicator and shall be connected to the fire alarm control panel under separate zone. Reprogram the Existing Fire Alarm Control Panel for the address of the new Duct Smoke Detectors.

APPROVED ENGINEERING DEPT.

3.

ADC / DVD

C. HVAC Equipment and Materials


OPERATING DEPT.

1.

Packaged Air Conditioning Units Self-contained , single packaged , pre-wired units and pre-charged with refrigerant complying to 73-TMSS-1, Rev. 4 . Condenser coils shall be copper tube with copper fins sprayed with anti-corrosion or protective coating.

CERTIFIED

The unit shall be fully charged with Non- Ozone depleting refrigerant such as R-134a, R-407C, and R-410A.
2. Split Type Air Conditioning Units Split Type A/C units shall be complete consisting of evaporator unit ( indoor unit ) and remote air cooled condencing unit ( outdoor unit ) complying to 73-TMSS-1. Rev. 4. Compressor motor shall be semi hermitically sealed machine in accordance with ARI 520. Condencer Coils shall be copper tube with copper fins sprayed with anti-corrosion or protective coating. All evaporator section shall be of double walled type with fiberglass or any approved insluation materalias of the required thickness applied between the outer and inner panels.

BY: :

MQQ

THIS DRAWING IS NOT TO BE USED FOR CONSTRUCTION OR FOR ORDERING MATERIALS UNTIL CERTIFIED AND DATED

The unit shall be fully charged with Non- Ozone depleting refrigerant such as R-134a, R-407C, and R-410A.
[[PTS- 14ED416 doc. MQQ/ADC/DVD) November 2013 ]
PLANT NO. INDEX PTS NO. PAGE NO. REV.

SCOPE OF WORK AND TECHNICAL SPECIFICATIONS


JOB ORDER NO.

1-- 1443026 111

FOR REPLACEMENT OF HVAC SYSTEM AT EASTERN OPERATING AREA SUBSTATION

D047

PTS-14ED416

SAUDI ARABIA

52 OF 77

CERT.

SAUDI ELECTRICITY COMPANY

CHKD

APPD

3.

Air Cleaning a. High Efficiency Air Filters (Bag Filters) i. - Media: Ultra-fine fiberglass. - Holding Frame: Galvanized Steel. ii. Performance Rating: - ASHRAE 52-76/EUROVENT 4/5 Test Method Average Efficiency: 92.5%

NO.

DESCRIPTION 3

REVISIONS

b.

Rated Air Flow Capacity at 152 Pa: 1180 L/sec. Recommended Final Resistance: 250 Pa.

DRAWN BY DATE CHKD BY

Washable Permanent Panel Filters i. Media: 14 mesh aluminum, alternate layers of flat and herringbone crimp, four layers per inch (25mm), rod reinforced. Frame: 16 gage (1.5mm) galvanized steel. Thickness: 50mm thick

APPROVED ENGINEERING DEPT.

ADC / DVD

ii.
OPERATING DEPT.

Performance Rating: Initial resistance at 2.54 m/sec. Face velocity: 25 Pa w.g. Recommended final resistance: 2.54 m/sec. Face velocity: 125 Pa w.g.

CERTIFIED

c.
BY: :

Filter Gages i. Direct Reading Dial: 90mm diameter diaphragm actuated dial in metal case, vent valves, black figures on white background, front recalibration adjustment, range 0-125 Pa, 2% of full scale accuracy.

MQQ

ii.
THIS DRAWING IS NOT TO BE USED FOR CONSTRUCTION OR FOR ORDERING MATERIALS UNTIL CERTIFIED AND DATED

Accessories: Static pressure probes with integral compression fittings, 6mm aluminum or plastic tubing, 2-way or 3-way vent valves.

4.

Ductwork a. Galvanized Steel Ducts

[[PTS- 14ED416 doc. MQQ/ADC/DVD) November 2013 ]


PLANT NO. INDEX PTS NO. PAGE NO. REV.

SCOPE OF WORK AND TECHNICAL SPECIFICATIONS


JOB ORDER NO.

1-- 1443026 111

FOR REPLACEMENT OF HVAC SYSTEM AT EASTERN OPERATING AREA SUBSTATION

D047

PTS-14ED416

SAUDI ARABIA

53 OF 77

CERT.

SAUDI ELECTRICITY COMPANY

APPD

CHKD

ASTM A653 hot dipped galvanized steel sheet, lock-forming quality, having G60 zinc coating in conformance with ASTM A90 b. Insulated Flexible Ducts Two-ply vinyl film supported by helically wound spring steel wire, fiberglass insulation, and polyethylene vapor barrier film. i. ii. iii. 5.
3 2 1

DESCRIPTION

Pressure Rating: 2.50 kPa positive and 250 Pa negative. Maximum Velocity: 2.03 m/sec Temperature Range: -23C to 71C

NO.

Ductwork Accessories a. Air Turning Devices/Extractors i. Fabricate in accordance with SMACNA HVAC Duct Construction Standards. Multi-blade device with blades aligned in short dimension, steel construction, with individually adjustable blades, mounting straps. Multi-blade device with radius blades attached to pivoting frame and bracket, steel construction, with push/pull operator strap with 450 mm long removable key operator.

REVISIONS

DRAWN BY DATE CHKD BY

ii.
APPROVED ENGINEERING DEPT.

iii.
ADC / DVD

b.
OPERATING DEPT.

Motorized Volume Damper i. Multi-Blade Damper: Fabricate of opposed blade pattern with maximum blade sizes 200 x 1825mm. Assemble center and edge crimped blades in prime coated or galvanized channel frame with suitable hardware. End Bearings: Except in round ductwork 300mm and smaller, provide end bearings. On multiple blade dampers, provide oil impregnated nylon or sintered bronze bearings. Operators: UL listed and labeled spring return electric type suitable for 220 volts, single phase, 60 Hz. Provide end switches to indicate damper position. Locate damper operator on exterior of duct and link to damper operating shaft.

CERTIFIED

ii.

BY: :

MQQ

iii.

THIS DRAWING IS NOT TO BE USED FOR CONSTRUCTION OR FOR ORDERING MATERIALS UNTIL CERTIFIED AND DATED

c.

Combination Fire and Smoke Dampers

[[PTS- 14ED416 doc. MQQ/ADC/DVD) November 2013 ]


PLANT NO. INDEX PTS NO. PAGE NO. REV.

SCOPE OF WORK AND TECHNICAL SPECIFICATIONS


JOB ORDER NO.

1-- 1443026 111

FOR REPLACEMENT OF HVAC SYSTEM AT EASTERN OPERATING AREA SUBSTATION

D047

PTS-14ED416

SAUDI ARABIA

54 OF 77

CERT.

SAUDI ELECTRICITY COMPANY

APPD

CHKD

i. ii. iii.

Fabricate in accordance with NFPA 90A. Provide factory sleeve and collar for each damper. Multiple Blade Dampers: Fabricate with 16 gage (1.5mm) galvanized steel frame and blades, oil impregnated bronze or stainless sleeve bearings and plated steel axles, stainless steel jamb seals, 3.2 x 13 mm plated steel concealed linkage, stainless steel closure spring, blade stops and lock, and 13 mm actuator shaft. Operators: UL listed and labeled spring return electric type suitable for 220 volts, single phase, 60 Hz. Provide end switches to indicate damper position. Locate damper operator on exterior of duct and link to damper operating shaft. Combination fire and smoke damper shall comply with the requirements of UL 555 and UL 555S. The fire rating shall be 3 hours as per NFPA-90A. Fusible Links: UL listed and labeled, UL 33, separate on 71 C with adjustable link straps.
o

DESCRIPTION

iv.
NO.

REVISIONS

v.
DRAWN BY DATE CHKD BY

vi.
APPROVED ENGINEERING DEPT.

d.
ADC / DVD

Duct Access Doors i. Fabricate in accordance with SMACNA HVAC Duct Construction Standards - Metal and Flexible and UMC. Fabrication: Rigid and close fitting of galvanized steel with self oiling hinges, sealing gaskets and quick fastening locking devices. For insulated ductwork, install minimum 25mm thick insulation with sheet metal cover. Less than 300mm square: Secure with sash locks. Up to 450mm square: Provide two (2) hinges and two (2) sash locks. Up to 600 x 1200mm: Three (3) hinges and two (2) compression latches with outside and inside handles. Larger sizes: Provide an additional hinge.

ii.
OPERATING DEPT.

CERTIFIED

BY: :

MQQ

iii.
THIS DRAWING IS NOT TO BE USED FOR CONSTRUCTION OR FOR ORDERING MATERIALS UNTIL CERTIFIED AND DATED

Access doors with sheet metal screw fasteners are not acceptable.

e.

Duct Test Holes Drill test holes in accordance with TAB CONTRACTORs requirements: Cap with neat patches, neoprene plugs, threaded plugs, or threaded or twist on metal caps.

[[PTS- 14ED416 doc. MQQ/ADC/DVD) November 2013 ]


PLANT NO. INDEX PTS NO. PAGE NO. REV.

SCOPE OF WORK AND TECHNICAL SPECIFICATIONS


JOB ORDER NO.

1-- 1443026 111

FOR REPLACEMENT OF HVAC SYSTEM AT EASTERN OPERATING AREA SUBSTATION

D047

PTS-14ED416

SAUDI ARABIA

55 OF 77

CERT.

SAUDI ELECTRICITY COMPANY

APPD

CHKD

f.

Fire Dampers i. ii. Fabricate in accordance with NFPA 90A. Horizontal Dampers: Galvanized Steel, 22 gage (0.76 mm) frame, stainless steel closure spring. Curtain Type Dampers: Galvanized Steel with interlocking blades. Provide stainless steel closure springs and latches for closure under air flow conditions. Configure with blades out of air stream except for 250 Pa pressure class ducts up to 300mm in height. Multiple Blade Dampers: 16 gage (1.5mm) galvanized steel frame and blades, oil impregnated bronze or stainless steel sleeve bearings and plated steel axles, 3.2 x 13 mm plated steel concealed linkage, stainless steel closure spring, blade stops and lock.Fire Dampers shall be 3 hours Fire Rating. Fusible Links: UL listed and labeled, UL 33, separate on 71C with adjustable link straps for combination fire/balancing dampers.

DESCRIPTION

iii.

NO.

iv.
3 2

REVISIONS

DRAWN BY DATE CHKD BY

v.

APPROVED ENGINEERING DEPT.

g.

Flexible Duct Connections i. Fabricate in accordance with SMACNA HVAC Duct Construction Standards - Metal and Flexible. Connector: Fabric crimped into metal edging strip. Fabric: UL listed fire retardant neoprene coated woven glass fiber fabric to NFPA 90A, minimum density 1.0 kg/sq.m. Net fabric width shall be approximately 75 mm.

ADC / DVD

ii.
OPERATING DEPT.

iii.
CERTIFIED

Materials: Flame spread/smoke developed rating of 25/50 or less in accordance with NFPA 255 and UL 723.

BY: :

MQQ

h.

Manual Volume Control Dampers i. Fabricate in accordance with SMACNA Standards - Metal and Flexible. HVAC Duct Construction

ii. iii.
THIS DRAWING IS NOT TO BE USED FOR CONSTRUCTION OR FOR ORDERING MATERIALS UNTIL CERTIFIED AND DATED

Single Blade Dampers: Fabricate for duct sizes up to 150 x 760 mm. Multi-Blade Damper: Fabricate of opposed blade pattern with maximum blade sizes 200 x 1825mm. Assemble center and edge crimped blades in prime coated or galvanized channel frame with suitable hardware.

[[PTS- 14ED416 doc. MQQ/ADC/DVD) November 2013 ]


PLANT NO. INDEX PTS NO. PAGE NO. REV.

SCOPE OF WORK AND TECHNICAL SPECIFICATIONS


JOB ORDER NO.

1-- 1443026 111

FOR REPLACEMENT OF HVAC SYSTEM AT EASTERN OPERATING AREA SUBSTATION

D047

PTS-14ED416

SAUDI ARABIA

56 OF 77

CERT.

SAUDI ELECTRICITY COMPANY

APPD

CHKD

iv.

End Bearings: Except in round ductwork 300mm and smaller, provide end bearings. On multiple blade dampers, provide oil impregnated nylon or sintered bronze bearings. Quadrants: Provide locking, indicating quadrant regulators on single and multi-blade dampers.

v.
DESCRIPTION

NO.

i.
3 2 1

Where rod lengths exceed 750 mm provide regulator at both ends. Back Draft Damper i. Fabrication in accordance with SMACNA HVAC Duct Construction Standards - Metal and Flexible. Channel Frame: Galvanized steel gauge 16, 50mm width x 13mm height. Shafting: 12.7mm dia. round rod, 1 continuous length per blade. Blades: motorized blades made of galvanized steel gauge 26 with sponge foam gasket on edges. Blade Stopper: Made of gauge 18 galvanized steel. Type of Construction Duct mounted.

REVISIONS

DRAWN BY DATE CHKD BY

ii.

APPROVED ENGINEERING DEPT.

iii. iv.

ADC / DVD

v. vi.

OPERATING DEPT.

6.

Air Outlets/Inlets

a.
CERTIFIED

Sand Trap Louver i. Designed for intake application to separate sand from intake air. Test dust distribution efficiency at 80% on 20 to 200 microns and 50% on 1 to 70 microns. Aluminum Construction: Frame 2mm thick, blades 4mm thick. Provided with self-emptying sand drain holes from the base and aluminum wire bird screen. Size: Designed at 1.52 m/s maximum face air velocity.

BY: :

MQQ

ii.

iii.
THIS DRAWING IS NOT TO BE USED FOR CONSTRUCTION OR FOR ORDERING MATERIALS UNTIL CERTIFIED AND DATED

7.

Instrumentation a. Pressure Gauge

[[PTS- 14ED416 doc. MQQ/ADC/DVD) November 2013 ]


PLANT NO. INDEX PTS NO. PAGE NO. REV.

SCOPE OF WORK AND TECHNICAL SPECIFICATIONS


JOB ORDER NO.

1-- 1443026 111

FOR REPLACEMENT OF HVAC SYSTEM AT EASTERN OPERATING AREA SUBSTATION

D047

PTS-14ED416

SAUDI ARABIA

57 OF 77

CERT.

SAUDI ELECTRICITY COMPANY

APPD

Glacier filled, ASME B40.1, 65mm diameter drawn steel case, phosphor bronze bourdon tube, rotary brass movement, brass socket, with front recalibration adjustment, black scale on white background, 1% mid-scale accuracy, scale calibrated in both psi and kPa.

DESCRIPTION

CHKD

b.

Temperature and Humidity Indicators (Combination) Wall mount, 300mm diameter dial, for indoor and outdoor service, bi-metal sensing mechanism protected by weatherproof aluminum case, temperature range -46 to 54C relative humidity range 20 to 90%.

NO.

c.

Thermostat Low voltage, adjustable to control compressor stages and heating stages in sequence with delay. Minimum two (2) stages for cooling and two (2) stages for heating.

REVISIONS

DRAWN BY DATE CHKD BY

d.
APPROVED ENGINEERING DEPT.

Humidistat 3-point, control heating or, in conjunction with an impulse relay, floating step control. Low voltage.

ADC / DVD

e.

Duct Type Thermometer (for Main Supply, Return & Fresh Air Ducted) 100 mm dial face with raised black numbers on silver face, with red pointer. Scale ranges shall be 5 oC to 85 oC.

OPERATING DEPT.

8.

Ductwork Insulation a. Materials Flame spread/smoke developed rating of 25/50 or less in accordance with NFPA 255 and UL 723. b. Type Glass fiber board, rigid. c. Insulation ASTM C612, non-combustible. i. ii. Thermal Conductivity: 0.33w/m C at 24 C mean temperature. Maximum Service Temperature: 121C.

CERTIFIED

BY: :

MQQ

THIS DRAWING IS NOT TO BE USED FOR CONSTRUCTION OR FOR ORDERING MATERIALS UNTIL CERTIFIED AND DATED

[[PTS- 14ED416 doc. MQQ/ADC/DVD) November 2013 ]


PLANT NO. INDEX PTS NO. PAGE NO. REV.

SCOPE OF WORK AND TECHNICAL SPECIFICATIONS


JOB ORDER NO.

1-- 1443026 111

FOR REPLACEMENT OF HVAC SYSTEM AT EASTERN OPERATING AREA SUBSTATION

D047

PTS-14ED416

SAUDI ARABIA

58 OF 77

CERT.

SAUDI ELECTRICITY COMPANY

APPD

CHKD

iii. iv. v.

Maximum Moisture Absorption: 0.20% by volume. Thickness: 25mm. Density: 56 kg/m3

DESCRIPTION

d.

Facing Factory applied foil reinforced kraft (FRK) vapor barrier.

e.
NO. 3 2 1

Adhesive Waterproof, fire retardant type (apply vapor-seal pressure sensitive patches and joint sealing tape.

REVISIONS

DRAWN BY DATE CHKD BY

f.

Joint and Protrusion 75mm wide tape shall be used.

APPROVED ENGINEERING DEPT.

9.

Vibration Isolators a. Materials Composed of i. ii. Restrained spring mounting. Adjustment or cap screw. Neoprene vertical limit stops. Neoprene acoustical cup. Non-skid neoprene friction isolation pad.

ADC / DVD

OPERATING DEPT.

iii. iv. v. b.

CERTIFIED

BY: :

MQQ

A minimum clearance of 13mm shall be maintained around restraining bolts and between the housing and the spring so as not to interfere with the spring action.

10.

Exhaust Fan Exhaust Fan shall be Wall Mounted , Explosion Proof Type and UL Listed.

D.
THIS DRAWING IS NOT TO BE USED FOR CONSTRUCTION OR FOR ORDERING MATERIALS UNTIL CERTIFIED AND DATED

Submittals 1. Submit diagrams indicating mechanical system controlled, HVAC unit hydronic and refrigerant piping schematic diagram, piping layout and control system components. Label with settings, adjustable range of control and limits. Include written description of control sequence of operation.

[[PTS- 14ED416 doc. MQQ/ADC/DVD) November 2013 ]


PLANT NO. INDEX PTS NO. PAGE NO. REV.

SCOPE OF WORK AND TECHNICAL SPECIFICATIONS


JOB ORDER NO.

1-- 1443026 111

FOR REPLACEMENT OF HVAC SYSTEM AT EASTERN OPERATING AREA SUBSTATION

D047

PTS-14ED416

SAUDI ARABIA

59 OF 77

CERT.

SAUDI ELECTRICITY COMPANY

APPD

CHKD

2. 3.

Include flow diagrams for each control system, graphically depicting control logic. Shop drawings indicating components, assembly, dimensions, weights and loadings, required clearances, location and size of filed connections. Submit product data indicating rated capacities, performance data/curves, dimensions, weights specialties and accessories, electrical nameplate data and wiring diagrams.

DESCRIPTION

4.

5.
NO.

Submit test reports. Indicate pressure tests performed. Include data section tested, test pressure and leakage rate following SMACNA HVAC Air Duct Leakage Test Manual.

REVISIONS

E.
DRAWN BY DATE CHKD BY

Execution and Installation 1. General a. Install equipment in accordance with TCS-K-100, TES-P-119.19 and manufacturers instructions. Install each A/C unit on reinforced concrete pad with vibration isolation. Provide access around equipment manufacturers minimum requirement. for service, not less than the

APPROVED ENGINEERING DEPT.

b.
ADC / DVD

c.

d.
OPERATING DEPT.

Sleeve duct passing through walls and floors.

2.

Ductwork and Duct Accessories a. Perform WORK in accordance with SMACNA HVAC Duct Construction Standards - Metal and Flexible, NFPA 90A Standards and SCS-K-100. Fabricate and support in accordance with SMACNA HVAC Duct Construction Standards - Metal and Flexible. Provide motorized combination fire and smoke dampers in the main supply and return duct penetrations through the walls/roof. Provide access doors for inspection and cleaning, before and after filters, coils, fans, automatic dampers, fire dampers, combination fire and smoke dampers, electric duct heater and elsewhere as required. Provide duct test holes where required for testing and balancing purposes.

CERTIFIED

b.
BY: :

MQQ

c.

d.
THIS DRAWING IS NOT TO BE USED FOR CONSTRUCTION OR FOR ORDERING MATERIALS UNTIL CERTIFIED AND DATED

e.

[[PTS- 14ED416 doc. MQQ/ADC/DVD) November 2013 ]


PLANT NO. INDEX PTS NO. PAGE NO. REV.

SCOPE OF WORK AND TECHNICAL SPECIFICATIONS


JOB ORDER NO.

1-- 1443026 111

FOR REPLACEMENT OF HVAC SYSTEM AT EASTERN OPERATING AREA SUBSTATION

D047

PTS-14ED416

SAUDI ARABIA

60 OF 77

CERT.

SAUDI ELECTRICITY COMPANY

CHKD

APPD

3.

Ductwork Insulation a. Verify that ductwork has been air leak and lighting tested before applying insulation materials. Provide ductwork with external insulation with vapor barrier jackets. Use 25 mm thick insulation for ducts installed inside the building and 50 mm thk. Insulation with aluminum cladding for outside ducts.

DESCRIPTION

b.

4.
NO.

Vibration Isolation Provide Spring Type vibration isolation for HVAC Units.

REVISIONS

5.

Mechanical Identification Identify PACU, ACCU, AHU, ductworks, control panels and major control components outside panels with plastic nameplates.

DRAWN BY DATE CHKD BY

6.
APPROVED ENGINEERING DEPT.

Air Cleaning Install filter gage static pressure tips upstream and downstream of filters. Mount filter gages on outside of filter housing or filter plenum, in accessible position. Adjust and level.

ADC / DVD

F.
OPERATING DEPT.

Testing, Adjusting and Balancing 1. Submit name of Testing, Adjusting and Balancing (TAB) agency for approval within thirty (30) days after award of CONTRACT. Such agency shall be company specializing in Testing, Adjusting and Balancing of systems with minimum three(3) years-documented experience. Perform WORK under supervision of NEBB or any other Certified TAB Supervisor acceptable to the COMPANY. Total system balance shall be performed in accordance with SCS-K-100. Contractor shall submit Testing Procedure for review and approval of the Company prior to Testing, Adjusting, Commissioning and Balancing of the System. Prior to commencing WORK, submit draft reports on NEBB form indicating adjusting, balancing and equipment data required. Submit draft copies of report for review prior to final acceptance of PROJECT. Provide final copies to COMPANY REPRESENTATIVE and for inclusion in operating and maintenance manuals. Provide reports in soft cover, letter size, 3-ring binder manuals, complete with index page and indexing tabs, with cover identification at front and side. Include set of reduced drawings with air outlets and equipment identified to correspond with data sheets and indicating thermostat locations.
PLANT NO. INDEX PTS NO. PAGE NO. REV.

CERTIFIED

2.

BY: :

MQQ

3.

4.
THIS DRAWING IS NOT TO BE USED FOR CONSTRUCTION OR FOR ORDERING MATERIALS UNTIL CERTIFIED AND DATED

5.

[[PTS- 14ED416 doc. MQQ/ADC/DVD) November 2013 ]

SCOPE OF WORK AND TECHNICAL SPECIFICATIONS


JOB ORDER NO.

1-- 1443026 111

FOR REPLACEMENT OF HVAC SYSTEM AT EASTERN OPERATING AREA SUBSTATION

D047

PTS-14ED416

SAUDI ARABIA

61 OF 77

CERT.

SAUDI ELECTRICITY COMPANY

CHKD

APPD

6.

The WORK shall also include the following tests: Duct Leakage, Sound test, Vibration Tests and commissioning for fire alarm system. Include detailed procedures, agenda, sample report forms prior to commencing any test. Upon completion of installation and before the system is energized or accepted, tests shall be carried out by the CONTRACTOR to demonstrate that each installation is functioning in accordance with the specifications. The CONTRACTOR shall test each circuit for grounds and shorts by means of a megger insulation testing instrument which shall impress a voltage of not less than 500 Volts upon the circuit under test. Any circuit showing an insulation resistance less than the minimum values given in the NEC shall be investigated and weak points corrected. All circuits under megger insulation test shall be connected to respective final terminals with switches or breakers in the OFF position. The CONTRACTOR shall correct or replace any current carrying circuit which is defective or grounded. The CONTRACTOR shall correct deficiencies encountered during the testing. Following established procedure, equipment will be energized upon certification that installation is satisfactory. Final operational tests shall determine that wiring connections are correct.

7.
DESCRIPTION

8.

9.
NO. 3 2 1

REVISIONS

DRAWN BY DATE CHKD BY

10.

APPROVED ENGINEERING DEPT.

11.
ADC / DVD

G.
OPERATING DEPT.

Warranty Warranty for Air Conditioning Compressors should be for five (5) years for all units.

CERTIFIED

4.03 ELECTRICAL SYSTEM REQUIREMENTS A. GENERAL

BY: :

MQQ

THIS DRAWING IS NOT TO BE USED FOR CONSTRUCTION OR FOR ORDERING MATERIALS UNTIL CERTIFIED AND DATED

The specifications outlined herein shall be read in conjunction with the attached COMPANY Material Standard Specifications and the associated International Standards and Codes. The ratings and specific requirements of the various electrical equipment shall be as indicated in Data Schedule of COMPANY Material Standard Specifications, and the CONTRACTOR shall ensure full conformity with the same. In association with implementing this PROJECT, all necessary miscellaneous electrical WORKs, such as dismantling and disconnection of existing units and power distribution panels shall be carried out by the CONTRACTOR.
[[PTS- 14ED416 doc. MQQ/ADC/DVD) November 2013 ]
PLANT NO. INDEX PTS NO. PAGE NO. REV.

SCOPE OF WORK AND TECHNICAL SPECIFICATIONS


JOB ORDER NO.

1-- 1443026 111

FOR REPLACEMENT OF HVAC SYSTEM AT EASTERN OPERATING AREA SUBSTATION

D047

PTS-14ED416

SAUDI ARABIA

62 OF 77

CERT.

SAUDI ELECTRICITY COMPANY

APPD

CHKD

All dismantled equipment shall be packed and transported to COMPANY warehouse.

B
DESCRIPTION

All new HVAC units and additional panels shall be bonded to existing grounding system as per NEC/NFPA 70 and TES-P-119.10 (rev.01). All other electrical equipments, pipe barriers and non-current carrying equipments shall also be properly bonded to existing grounding system.

4.04 CIVIL/STRUCTURAL REQUIREMENTS


NO.

A.
3 2

GENERAL The specifications outlined herein shall be read in conjunction with the attached COMPANY Material Standard Specifications and the associated International Standards and Codes. The Specific requirements of the various Civil /Structural WORKS shall be as indicated in Technical specifications and of COMPANY Material Standard Specifications, and the CONTRACTOR shall ensure full conformity with the same.

REVISIONS

DRAWN BY DATE CHKD BY

APPROVED ENGINEERING DEPT.

B. 1.

REINSTATEMENT OF ASPHALT CONCRETE PAVING The excavation, sub-base course and base course placement and compaction and related works shall be as per the requirements of TCS-Q-113.02. Asphalt Concrete works shall be as per the requirements of TCS-Q-113.01. STEEL SUNSHADE AND STEEL SUPPORT STRUCTURES CONTRACTOR shall design, fabricate and erect HVAC equipment steel sunshade and support structures as per COMPANY standard . Contractor shall provide drawing to be used for general arrangement, concept and guidance. CONTRACTOR shall provide the design calculations for COMPANY review and approval.

ADC / DVD

2.
OPERATING DEPT.

C. 1.

CERTIFIED

BY: :

MQQ

2. Anchor bolts to be used for fixing HVAC equipment structures to the reinforced concrete foundations shall be Type-3 as per COMPANY standard , other type of anchor bolts can be used depending upon the requirements and acceptance of the COMPANY REPRESENTATIVE. D. CAST-IN-PLACE CONCRETE REQUIREMENTS

THIS DRAWING IS NOT TO BE USED FOR CONSTRUCTION OR FOR ORDERING MATERIALS UNTIL CERTIFIED AND DATED

The requirements of cast-in-place concrete shall be per the requirements of TCS-Q-113.03 E. CONCRETE COVER Concrete cover shall be as per the recommendations of TCS-Q-113.03
[[PTS- 14ED416 doc. MQQ/ADC/DVD) November 2013 ]
PLANT NO. INDEX PTS NO. PAGE NO. REV.

SCOPE OF WORK AND TECHNICAL SPECIFICATIONS


JOB ORDER NO.

1-- 1443026 111

FOR REPLACEMENT OF HVAC SYSTEM AT EASTERN OPERATING AREA SUBSTATION

D047

PTS-14ED416

SAUDI ARABIA

63 OF 77

CERT.

SAUDI ELECTRICITY COMPANY

CHKD

APPD

F.

CONCRETE PROTECTION Concrete surface, except grade slab, shall be coated in accordance with the following:

DESCRIPTION

1.

Concrete Surfaces in contact with soil Concrete shall be coated with coal tar epoxy after thirty five (35) days of concrete placement. Minimum number of coats shall be three (3) or the dry film thickness shall not be less than 600 microns, whichever produces higher thickness.

2.
NO. 3 2 1

Concrete Surfaces Above Grade After a minimum of thirty-five (35) days of concrete placement for severe exposure concrete, all exposed concrete surfaces (above grade) shall be coated with an elastomeric polyurethane waterproofing material. The coating application shall extend continuously 300mm below grade after curing of first coat of coal tar epoxy coating. The minimum dry film thickness of elastomeric polyurethane coating shall be 1mm. The interface of concrete and steel shall also be coated and the coating shall extend 300mm above the interface point over the steel members. The primer shall be suitably selected for concrete and steel surfaces.

REVISIONS

DRAWN BY DATE CHKD BY

APPROVED ENGINEERING DEPT.

3.
ADC / DVD

Concrete Interior Surfaces All interior surfaces (wall and base slab) of concrete (manholes, hand holes, trenches and cable basement/cable entry room) shall be coated with two (2) coats of elastomeric cementitious impermeable membrane after thirty-five (35) days of concrete placement. The total wet film thickness shall not be less than 1mm (minimum).

OPERATING DEPT.

G. PROTECTIVE COATING REQUIREMENTS AND APPLICATION 1.


CERTIFIED

General Manufacturer's recommendations shall be strictly followed in all aspects of surface preparation, priming, coating application (first and succeeding coats and intervals therein, etc.), and curing time and safety practices. The coating on the exterior concrete surfaces shall be carried out after a minimum of fourteen (14) days following the curing period. The coating shall form and maintain a continuous film over the concrete. The coating material shall penetrate into the concrete and adhere to it effectively. This is to afford protection to the concrete against the entry of oxygen, moisture and aggressive ions. The recommended procedure for protective coating application is outlined in the subsequent sub-sections.

BY: :

MQQ

THIS DRAWING IS NOT TO BE USED FOR CONSTRUCTION OR FOR ORDERING MATERIALS UNTIL CERTIFIED AND DATED

[[PTS- 14ED416 doc. MQQ/ADC/DVD) November 2013 ]


PLANT NO. INDEX PTS NO. PAGE NO. REV.

SCOPE OF WORK AND TECHNICAL SPECIFICATIONS


JOB ORDER NO.

1-- 1443026 111

FOR REPLACEMENT OF HVAC SYSTEM AT EASTERN OPERATING AREA SUBSTATION

D047

PTS-14ED416

SAUDI ARABIA

64 OF 77

CERT.

SAUDI ELECTRICITY COMPANY

APPD

CHKD

2.

Surface Preparation The surface to be coated shall be prepared prior to the application of the coating material. If any, surface cracks; shallow spalls and holes on the concrete surface shall be filled with a concrete surface. These regions shall be repaired in a manner prescribed below: a. b. Where cracks are present, cut V grooves using chisel or a similar tool. Presoak with specified potable water the region for at least the last eight- (8) hours before filling the cracks. Fill the cracks with the specified concrete surface. Cure with specified potable waters the repaired region continuously for time period as recommended by manufacturer, but in any case not less than seven (7) days. Dirt and other loose material, laitance, oil, grease, wax, black-white carbonate deposits and yellow-white sulfate deposits shall be removed from the surface to reach solid gray concrete underneath. The concrete surface shall be scrubbed by steel bristled brushes, followed by blowing of compressed air (free of oil). Alternatively, a brush-off blast procedure may be adopted (the sandblasting gun is held at a distance from the surface and the surface is swept with the blast stream). The compressed air shall be free of oil and water as visually indicated by a collector (absorbent or non-absorbent), following the standard test procedure ASTM D4285. Further, ASTM standard practices for surface cleaning and abrading of concrete surface prior to coating application clean the newly exposed roughened concrete surface by water blasting, using potable water. If the corrosion products are observed on the metallic structure and/or associated hardware immediately above the concrete, sandblast and clean 300mm length above the concrete. This shall be done by abrasive blasting, employing 60-80 meshes sand or mineral grit to a white metal blast finish as described in Section 4.2.7 of SES-H-001. Care shall be taken to ensure avoidance of any damage of the thread of the bolts. At the time of application of coating material, the surface shall be clean, dry and shall have adequate roughness for effective bonding of the costing material to the prepared substrate. Manufacturers recommendation shall be strictly followed in all aspects of surface preparation, priming as applicable to concrete and steel substrates, coating application (first and succeeding coats and intervals therein, etc.), curing time and safety practices. The coating work shall be carried out after a minimum of 14 days following the completion of curing period. The coating shall form and maintain a continuous film

NO.

DESCRIPTION 3

REVISIONS

c. d.

DRAWN BY DATE CHKD BY

APPROVED ENGINEERING DEPT.

ADC / DVD

OPERATING DEPT.

CERTIFIED

BY: :

MQQ

THIS DRAWING IS NOT TO BE USED FOR CONSTRUCTION OR FOR ORDERING MATERIALS UNTIL CERTIFIED AND DATED

[[PTS- 14ED416 doc. MQQ/ADC/DVD) November 2013 ]


PLANT NO. INDEX PTS NO. PAGE NO. REV.

SCOPE OF WORK AND TECHNICAL SPECIFICATIONS


JOB ORDER NO.

1-- 1443026 111

FOR REPLACEMENT OF HVAC SYSTEM AT EASTERN OPERATING AREA SUBSTATION

D047

PTS-14ED416

SAUDI ARABIA

65 OF 77

CERT.

SAUDI ELECTRICITY COMPANY

APPD

CHKD

over the concrete surface and over the steel-concrete interface. The coating material shall penetrate into the concrete and adhere to it effectively.

DESCRIPTION

3.

Coating 1. General a. Coating material application shall be carried out according to the manufacturer's recommendations. In case of any conflict between this specification and the manufacturer's recommendations, the conflict shall be resolved by a meeting of the COMPANY REPRESENTATIVE and the manufacturer's REPRESENTATIVE prior to any application. Coating material, which has gelled or otherwise deteriorated during storage, shall not be used. However, thixotropic materials, which may be stirred to obtain normal consistency, shall be acceptable. Coating materials containing heavy or metallic pigments that have a tendency to settle must be kept in suspension in the pressure pot by a mechanical stirrer. c. Only thinners as specified by the manufacturer shall be used. Mixing and thinning directions as furnished by the manufacturer shall be followed. If a coating material requires the addition of a catalyst, the pot life under application conditions shall be clearly stated on the label. The pot life must not be exceeded. When the pot life limit is reached, the spray pot must be emptied, the material discarded, the equipment cleaned and new material catalyzed. Each coat shall be allowed to dry thoroughly and at least for the specified time (as recommended by the manufacturer) prior to the application of a succeeding (follow-on) coat. No coating application shall be done during a sandstorm and on windy and rainy days. In case of an unanticipated occurrence of any of the above conditions, the wet coat shall be protected (covered) properly. The completed (cured) coating shall be free from defects such as runs, sags, pinholes, voids, bubbles or other "Holidays."

NO.

REVISIONS

b.
DRAWN BY DATE CHKD BY

APPROVED ENGINEERING DEPT.

ADC / DVD

OPERATING DEPT.

CERTIFIED

BY: :

MQQ

THIS DRAWING IS NOT TO BE USED FOR CONSTRUCTION OR FOR ORDERING MATERIALS UNTIL CERTIFIED AND DATED

2.

Coating Application a. Priming

[[PTS- 14ED416 doc. MQQ/ADC/DVD) November 2013 ]


PLANT NO. INDEX PTS NO. PAGE NO. REV.

SCOPE OF WORK AND TECHNICAL SPECIFICATIONS


JOB ORDER NO.

1-- 1443026 111

FOR REPLACEMENT OF HVAC SYSTEM AT EASTERN OPERATING AREA SUBSTATION

D047

PTS-14ED416

SAUDI ARABIA

66 OF 77

CERT.

SAUDI ELECTRICITY COMPANY

APPD

CHKD

DESCRIPTION

NO.

The prepared surfaces shall be coated with the primer specified, within the time limits as may be specified by the manufacturer, and prior to sunset of that day. The prepared, dried concrete surfaces shall be primed with a highly penetrating priming coat. The primer shall be applied by brush and shall be applied rather heavily for penetration. However, any excess shall be removed from the surface so that no heavy areas or puddles are formed. Regions of metallic members and hardware cleaned of any corrosion products, as mentioned in surface preparation above shall be coated with sacrificial specified zinc primer. This shall be done immediately after cleaning. After curing of that sacrificial zinc primer, apply the elastomeric coating material. The priming coat shall be applied on the steel surfaces and the steel concrete interface such that there is no air or water pockets. Care shall be taken to ensure proper coating at sharp corners, edges, bolts, hidden recesses and in-accessible areas.

REVISIONS

DRAWN BY DATE CHKD BY

b.
APPROVED ENGINEERING DEPT.

Coating WORK Coating material shall be either spray-applied or brush-applied.

ADC / DVD

3.

Spray Application Lines and pots shall be thoroughly cleaned before the addition of new materials. The spray gun shall always be held at right angles to the surface and shall be held no closer than 450mm nor more than 600mm from the surface for the airless spray gun method, or no closer than 150mm nor more than 250mm from the surface for air spray equipment. Even, parallel passes shall be made with the spray gun. In application of material, each spray shall overlap the previous pass by 50%. Large surfaces shall always receive passes in two directions at right angles to each other. Spray width adjustment on the gun shall be made and the readjustment of atomizing pressure at the regulators shall be made until the desired spray pattern is obtained. Each coat is to be applied uniformly and completely over the entire surface. All runs and sags shall be brushed out immediately or the paint shall be removed and the surface re-sprayed. Before spraying each coat, all areas such as corners, edges and interstices shall be precoated by brush to ensure that these areas have at least the minimum specified film thickness. Spray application from a single position will not be permitted. A supply of tips with varying spray angles and washers, as recommended by the supplier for each specific configuration to be coated, shall be available at site.

OPERATING DEPT.

CERTIFIED

BY: :

MQQ

THIS DRAWING IS NOT TO BE USED FOR CONSTRUCTION OR FOR ORDERING MATERIALS UNTIL CERTIFIED AND DATED

[[PTS- 14ED416 doc. MQQ/ADC/DVD) November 2013 ]


PLANT NO. INDEX PTS NO. PAGE NO. REV.

SCOPE OF WORK AND TECHNICAL SPECIFICATIONS


JOB ORDER NO.

1-- 1443026 111

FOR REPLACEMENT OF HVAC SYSTEM AT EASTERN OPERATING AREA SUBSTATION

D047

PTS-14ED416

SAUDI ARABIA

67 OF 77

CERT.

SAUDI ELECTRICITY COMPANY

CHKD

APPD

4.

Brush Application The coating material shall be brushed on to all areas, which cannot be properly spray coated for any reason. Surfaces not accessible to brushes shall be coated by other suitable means to ensure a uniform film of adequate thickness. Brushes used in coating application shall be of a style and quality that will permit proper application. Round or oval brushes generally are considered most suitable for rivets, bolts, and irregular surfaces. Wide flat brushes are suitable for large flat areas, but they shall not have a width of over 120mm. No extending handles shall be allowed on brushes. The brushing shall be done such that a smooth coat, as nearly uniform in thickness as possible, is obtained. There shall be no deep or detrimental brush marks. The coating material shall be worked into all crevices and corners. Runs or sags shall be brushed out. In brush application of any of the solvent-type coatings, care must be taken so that no lifting of former coats occurs. During application of each coat, all areas such as corners, edges and interstices shall receive additional coating material to ensure that these areas have at least the minimum specified film thickness and to ensure continuity of the coating.

NO.

DESCRIPTION 3

REVISIONS

DRAWN BY DATE CHKD BY

APPROVED ENGINEERING DEPT.

ADC / DVD

5.
OPERATING DEPT.

Film Thickness and Testing: The total dry film thickness (DFT) that shall be obtained upon application and subsequent curing shall be: a. b. Above Grade Application: 1mm for polyurethane material. Below Grade Application: 0.60mm for the material coal tar epoxy. Concrete Interior Surfaces: 1mm (wet film thickness) for material cementitionus elastomeric.

CERTIFIED

c.

BY: :

MQQ

The coating dry film thickness limit must be adhered to strictly; the film thickness shall be checked with the calibrated film thickness gauges supplied by the CONTRACTOR. Where the film thickness does not meet this specification, additional coating material shall be applied. In order to achieve the specified dry film thickness, frequent checks on wet film thickness shall be carried out by the CONTRACTOR. In case of concrete surfaces, coupons of the dried film shall be cut out from the coated surface, at locations where lesser film thickness is suspected. The cut out region shall be re-coated, as specified herein.
[[PTS- 14ED416 doc. MQQ/ADC/DVD) November 2013 ]
PLANT NO. INDEX PTS NO. PAGE NO. REV.

THIS DRAWING IS NOT TO BE USED FOR CONSTRUCTION OR FOR ORDERING MATERIALS UNTIL CERTIFIED AND DATED

SCOPE OF WORK AND TECHNICAL SPECIFICATIONS


JOB ORDER NO.

1-- 1443026 111

FOR REPLACEMENT OF HVAC SYSTEM AT EASTERN OPERATING AREA SUBSTATION

D047

PTS-14ED416

SAUDI ARABIA

68 OF 77

CERT.

SAUDI ELECTRICITY COMPANY

APPD

CHKD

A dry film, magnetic type thickness gauge (for steel surfaces) shall be calibrated and made available at the site. In case of concrete surfaces, coupons of the dried film shall be cutout from the coated surfaces at locations where lesser film thickness is suspected. The cutout region shall be re-coated, as outlined herein.

DESCRIPTION

4.

Repair of Defects a. General Before application of any further coat of material, all damages to previous coats shall be repaired. b. Inadequate Coating Thickness Areas with inadequate coating thickness shall be thoroughly cleaned and, if necessary, abraded, and additional compatible coats applied until they meet this specification. These additional coats shall blend in with the final coating on adjoining areas. c. Coating Damage not exposing the Substrate Surfaces to be over coated, which become contaminated or damaged, shall be cleaned by lightly brush-blasting (sweep-blasting) the surface free of all contamination prior to applying the following coats. After brush blasting, any residual contaminants shall be removed by dry compressed air or wiped by hand with clean, dry rags. The coating around the damaged area shall be chamfered, using an approved method, to ensure continuity of the patch coati. The full coating system shall then be reapplied strictly in accordance with this specification. d. Coating Damage Exposing the Substrate The damaged area shall be re-cleaned as originally specified for that item and the full coating system reapplied in accordance with the manufacturer's recommendations. The re-cleaning shall carry over on to the secure surrounding coating (properly adhering to the substrate) for not less than 25mm all around and the edges shall be duly chamfered.

NO.

REVISIONS

DRAWN BY DATE CHKD BY

APPROVED ENGINEERING DEPT.

ADC / DVD

OPERATING DEPT.

CERTIFIED

BY: :

MQQ

5.
THIS DRAWING IS NOT TO BE USED FOR CONSTRUCTION OR FOR ORDERING MATERIALS UNTIL CERTIFIED AND DATED

Inspection a. The COMPANY shall have the right to inspect at all times any tools, interments, materials or equipment used in the performance of the coating application. The CONTRACTOR shall make all parts of the WORK accessible for these inspections.

[[PTS- 14ED416 doc. MQQ/ADC/DVD) November 2013 ]


PLANT NO. INDEX PTS NO. PAGE NO. REV.

SCOPE OF WORK AND TECHNICAL SPECIFICATIONS


JOB ORDER NO.

1-- 1443026 111

FOR REPLACEMENT OF HVAC SYSTEM AT EASTERN OPERATING AREA SUBSTATION

D047

PTS-14ED416

SAUDI ARABIA

69 OF 77

CERT.

SAUDI ELECTRICITY COMPANY

APPD

CHKD

The COMPANY will designate a REPRESENTATIVE who will act for the COMPANY to: 1. Observe all application procedures during the time the WORK is in progress. Approve the surface preparation prior to the application of any coating. Approve condition of each coat prior to the application of the following coat. Film continuity verification on concrete substrate may be done by following the standard practice ASTM D4787, utilizing high voltage start testing. Film continuity over the steel concrete interfaces shall be following mentioned.
3 2 1

DESCRIPTION

2. 3.

NO.

REVISIONS

b.

DRAWN BY DATE CHKD BY

c.

APPROVED ENGINEERING DEPT.

The COMPANY shall have the right to condemn (reject) any and all tools, instruments, materials, equipment or WORK, which does not conform to the specifications. Condemned areas of coating applications shall be marked (for indication only) with a compatible paint of contrasting color. Any condemned coating applications, defective preparatory WORK or any defective WORK not conforming to this specification shall be rectified by the CONTRACTOR at no additional cost to the COMPANY. Any condemned tools, instruments, materials or equipment shall be replaced or rectified at no additional cost to the COMPANY.

ADC / DVD

d.
OPERATING DEPT.

After completion of the WORK, all surplus materials and waste from the coating WORK shall be collected and disposed of outside the working area. Overruns, droppings and smears shall be removed.

H.

ASPHALT CONCRETE PAVING The area to be reinstated asphalt shall be paved with a minimum of 102mm thick asphalt concrete (38mm thick wearing course and 64 thick binder course) on a 300mm thick base course (Class C) in accordance with TCS-Q-113.01.

CERTIFIED

BY: :

MQQ

I. CONCRETE FOUNDATIONS FOR STEEL SUPPORT STRUCTURES. Concrete foundations shall be provided to support all the necessary galvanized steel structures. Top of concrete foundations for support structure shall be of the same elevation, with the top of concrete at 150mm (minimum) to 450mm (maximum).

THIS DRAWING IS NOT TO BE USED FOR CONSTRUCTION OR FOR ORDERING MATERIALS UNTIL CERTIFIED AND DATED

Design criteria for the design of foundations shall be in accordance with TES-P-119.19 and TES-P-119.18.

J.

DEMOLITION WORK

[[PTS- 14ED416 doc. MQQ/ADC/DVD) November 2013 ]


PLANT NO. INDEX PTS NO. PAGE NO. REV.

SCOPE OF WORK AND TECHNICAL SPECIFICATIONS


JOB ORDER NO.

1-- 1443026 111

FOR REPLACEMENT OF HVAC SYSTEM AT EASTERN OPERATING AREA SUBSTATION

D047

PTS-14ED416

SAUDI ARABIA

70 OF 77

CERT.

SAUDI ELECTRICITY COMPANY

APPD

CHKD

1.

Procedures for any demolition and removal WORK shall be submitted to the COMPANY for approval before any WORK is started. The procedure shall include the detailed description of the methods and equipment to be used for each operation and sequence of operations. The CONTRACTOR shall construct temporary wall panels to separate the existing energized equipment from the ongoing construction. Care shall be taken to ensure that no damage is caused to the existing utilities while demolition is taking place. CONTRACTOR shall provide all necessary protection to ensure that damage or malfunction of the equipment due to vibration, dust and debris do not occur. The CONTRACTOR shall protect, support and relocate (if necessary) all utilities, which may be uncovered or otherwise, are affected by the WORK. The CONTRACTOR shall exercise caution, familiarize himself, and investigate the WORK SITE thoroughly prior to the actual commencement of WORK. If any utility is encountered unexpectedly, the COMPANY REPRESENTATIVE shall be notified immediately. Emergency rectification WORK as deemed necessary shall be put in hand without delay and without prejudice to the indemnity of the COMPANY. CONTRACTOR shall protect the existing utilities and shall be responsible for repairing any damage to the existing facilities at no cost to the COMPANY if such damage is caused during the course of execution by the CONTRACTOR or his SUBCONTRACTORS. Special care shall be taken in operating machinery close to power line, fences and other vital equipment.

DESCRIPTION

2.

3.

NO.

4.
3 2

REVISIONS

DRAWN BY DATE CHKD BY

5.

APPROVED ENGINEERING DEPT.

6.

ADC / DVD

OPERATING DEPT.

7.

CONTRACTOR shall transport all removed materials to the designated COMPANY Warehouse. Due to demolition WORK, if the stability of the nearby structure is in danger, CONTRACTOR shall reinforce the same. CONTRACTOR shall submit the detailed design calculations and construction procedure to COMPANY for review and approval before any loads to be applied or modification to be done.

8.
CERTIFIED

BY: :

MQQ

9.

CONTRACTOR shall provide the entire temporary supporting structure.

THIS DRAWING IS NOT TO BE USED FOR CONSTRUCTION OR FOR ORDERING MATERIALS UNTIL CERTIFIED AND DATED

10. All WORKS shall be performed in a manner least likely to interfere with the operation of the existing facilities. 11. It is the CONTRACTORs responsibility to visit the WORKSITE and to satisfy himself as to the extent of WORK, location and all the condition under which the WORK will be carried out. No claims based on the lack of any such knowledge shall be entertained.

[[PTS- 14ED416 doc. MQQ/ADC/DVD) November 2013 ]


PLANT NO. INDEX PTS NO. PAGE NO. REV.

SCOPE OF WORK AND TECHNICAL SPECIFICATIONS


JOB ORDER NO.

1-- 1443026 111

FOR REPLACEMENT OF HVAC SYSTEM AT EASTERN OPERATING AREA SUBSTATION

D047

PTS-14ED416

SAUDI ARABIA

71 OF 77

CERT.

SAUDI ELECTRICITY COMPANY

APPD

12. For demolition/construction WORK, CONTRACTOR shall use only that equipment that produces minimum vibration, and their use shall not have detrimental effect on the functioning of the existing energized equipment. The equipment used for demolition and construction shall be proposed for approval of COMPANY before the start of the WORK. As far as feasible, CONTRACTOR shall used those modern techniques for demolition/construction WORK that requires least time, manpower, and shall not produce any detrimental effect or malfunctioning of the existing energized equipment. 13. CONTRACTOR shall identify those existing facilities (lighting poles, etc.), which may come in the way of demolition/construction WORK, and the same shall be informed to COMPANY REPRESENTATIVE in writing, all such facilities shall be relocated to a suitable location along with their associated cables. 14. CONTRACTOR shall identify all the existing underground facilities (cables, pipes, etc.), and the same shall be shown on the drawings at the base design stage.

NO.

DESCRIPTION 3

CHKD

REVISIONS

DRAWN BY DATE CHKD BY

K.
APPROVED ENGINEERING DEPT.

MATERIALS SPECIFICATIONS AND TECHNICAL SPECIFICATIONS

1. CONCRETE a. Concrete shall confirm to the requirements of 70-TMSS-03.

ADC / DVD

OPERATING DEPT.

b. Concrete below asphalt finished grave level and directly in contact with the soil including concrete encased ductbanks shall be severe exposure condition per 70TMSS-03. c. A lean concrete 75mm thick shall be provided under structural concrete. Lean concrete shall be normal condition; minimum strength shall be 17Mpa(2500 psi). A vapor barrier, two (2) layers of 150 microns each, polyethylene sheet, shall be placed under the lean concrete.

CERTIFIED

BY: :

MQQ

d. A vapor barrier, two (2) layers of 150 microns each, polyethylene sheet, shall be provided under concrete.

2. REINFORCING STEEL a. Reinforcing steel shall conform to SASO SSA 2, hot rolled medium tensile deformed steel with a minimum yield strength of 350MPa(50.0 ksi) and 422MPa(60.0 ksi).
THIS DRAWING IS NOT TO BE USED FOR CONSTRUCTION OR FOR ORDERING MATERIALS UNTIL CERTIFIED AND DATED

b. Reinforcing steel fastening ties shall be made using 1.5mm diameter wire with at least two (2) wraps and twists. Tie spacing along the line of any bar shall not exceed 600mm horizontally or vertically. Wire tied splices shall be made with a minimum of two (2) separate ties.

[[PTS- 14ED416 doc. MQQ/ADC/DVD) November 2013 ]


PLANT NO. INDEX PTS NO. PAGE NO. REV.

SCOPE OF WORK AND TECHNICAL SPECIFICATIONS


JOB ORDER NO.

1-- 1443026 111

FOR REPLACEMENT OF HVAC SYSTEM AT EASTERN OPERATING AREA SUBSTATION

D047

PTS-14ED416

SAUDI ARABIA

72 OF 77

CERT.

SAUDI ELECTRICITY COMPANY

APPD

CHKD

c. Welded wire fabric shall conform to SASO SSA 224; cold drawn, steel wires with minimum yield strength of 240MPa(34.8 ksi). d. Splices in welded wire fabric shall be made by lapping a minimum of one spacing of outermost cross wires of each fabric sheet plus 50mm.

DESCRIPTION

e. All reinforcement shall be bend cold. Once steel has been bent it shall not be rebent. f. Welding shall not be permitted unless the mill test reports are furnished and show that steel has been modified for weldability. Welding shall be done in accordance with SES-W.1. g. All reinforcement accessories (spacers, chairs, etc.) required for spacing, assembling and supporting reinforcement in lace shall be plastic (PVC or HDPE) accessories and shall be subject to approval. 3. STRUCTURAL STEEL a. Structural steel shall confirm to the latest revision of ASTM A36. b. Bolts, nuts and washers shall conform to the latest revision of ASTM A394, ASTM A563M and ASTM F436. c. Structural steel shall be hot-dip galvanized after fabrication in accordance with the requirements of 01-TMSS-01. Bolts, nuts, washers and palnuts shall be galvanized in accordance with the requirements of 01-TMSS-01. d. Welding shall conform to COMPANY Engineering Standards for "General Welding Criteria" TES-W-1. e. Anchor bolts shall conform to SC-036128. Full length of anchor bolts shall be hot-dip galvanized in accordance with 01-TMSS-01. f. Design, fabrication and erection of the steel structures shall be in accordance with latest revision of AISC Manual of Steel Construction. g. Design, fabrication and erection of the Latticed steel structures shall be in accordance with latest revision of AISC Manual of Steel Construction. h. CONTRACTOR shall submit all fabrication and erection drawings for COMPANY review and comments. No fabrication shall commence until all fabrication drawings are approved and marked "Issued for Construction".

NO.

REVISIONS

DRAWN BY DATE CHKD BY

APPROVED ENGINEERING DEPT.

ADC / DVD

OPERATING DEPT.

CERTIFIED

BY: :

MQQ

THIS DRAWING IS NOT TO BE USED FOR CONSTRUCTION OR FOR ORDERING MATERIALS UNTIL CERTIFIED AND DATED

i. All steel structures shall be fabricated from the COMPANY approved steel fabricator. CONTRACTOR shall submit assembly and fabrication drawings for COMPANY review and comments in coordination with steel fabricator. Assembly and fabrication drawings shall be signed and stamped by CONTRACTOR as well as steel fabricator.

[[PTS- 14ED416 doc. MQQ/ADC/DVD) November 2013 ]


PLANT NO. INDEX PTS NO. PAGE NO. REV.

SCOPE OF WORK AND TECHNICAL SPECIFICATIONS


JOB ORDER NO.

1-- 1443026 111

FOR REPLACEMENT OF HVAC SYSTEM AT EASTERN OPERATING AREA SUBSTATION

D047

PTS-14ED416

SAUDI ARABIA

73 OF 77

CERT.

SAUDI ELECTRICITY COMPANY

APPD

CHKD

Fabrication shall not commence until all fabrication drawings are approved and marked "Issued for Construction". 4. ASPHALT CONCRETE

DESCRIPTION

Asphalt concrete materials shall be in accordance with TCS-Q-113.01.

5. PIPE BARRIERS a. Material Provide concrete filled G.I.Pipe bumper post (6) 150mm by 1000mm clear height, ( 500mm embedded on concrete foundation ) near A/C platform. The foundation of crush barrier pipe shall be 350mm by 600 mm depth. reinforced concrete. Distance between each pipe Barrier shall be 1.5 meters maximum. Bumper guard post shall be epoxy painted with black and canary-yellow stripes. Material shall be carefully handled to avoid any damages & shall conform to American Society for Testing Materials, ASTM A36, steel pipe Schedule 80. b. Shop Fabrication i. Quality
ADC / DVD

NO.

REVISIONS

DRAWN BY DATE CHKD BY

APPROVED ENGINEERING DEPT.

Items to be fabricated in a shop shall be strictly in accordance with the drawings prepared by the contrator. Component parts and members shall be properly aligned. All edges shall be true and cleanly cut.

OPERATING DEPT.

ii. Rust Prevention Steel shall be properly protected against rusting. After inspection and approval and before leaving the shop all steel WORK shall be thoroughly cleaned by effective means of all loose mill scale, rust, spatter, slag or flux deposit, oil, dirt, or other foreign matter. iii. Rust and/or Defective Materials The use of heavily corroded materials shall be avoided. No deformed material shall be accepted for installation. Any material deformed or damaged upon arrival shall be replaced by new.

CERTIFIED

BY: :

MQQ

THIS DRAWING IS NOT TO BE USED FOR CONSTRUCTION OR FOR ORDERING MATERIALS UNTIL CERTIFIED AND DATED

5.

NON-SHRINK GROUT Grout shall cement based fully complying with the requirements of ASTM C1107. Grout shall be non-shrink, non-metallic & chloride free, high performance, free flowing, noncatalyzed, shrinkage compensated and hydrogen free system. The non-shrink grout shall have following specifications:

[[PTS- 14ED416 doc. MQQ/ADC/DVD) November 2013 ]


PLANT NO. INDEX PTS NO. PAGE NO. REV.

SCOPE OF WORK AND TECHNICAL SPECIFICATIONS


JOB ORDER NO.

1-- 1443026 111

FOR REPLACEMENT OF HVAC SYSTEM AT EASTERN OPERATING AREA SUBSTATION

D047

PTS-14ED416

SAUDI ARABIA

74 OF 77

CERT.

SAUDI ELECTRICITY COMPANY


Values at 20C at twenty-eight (28) days age 60 MPa 10 MPa Remarks Application, formwork, mixing, consistency of mixed grout, placing, curing and cleaning, storage, handling of the grout must be in strict accordance with the manufacturers instructions.

CHKD

APPD

Specifications Compressive Strength Flexural Strength

DESCRIPTION

REVISIONS

DRAWN BY DATE CHKD BY

Coefficient of Thermal 11 X 10-6/C Expansion Modulus of Elasticity 29,000 MPa Mixing water shall be free for oils, acids organic matter or other deleterious substances and shall not contain more than 500 parts per million (ppm) of total dissolved solids. Minimum time of initial setting shall not be less than 3 hours Minimum time of final setting shall not exceed 8 hours Fluidity of grouts shall be high fluidity, 10-30 seconds flow when tested in accordance with ASTM C939.

NO.

APPROVED ENGINEERING DEPT.

6.

COAL TAR EPOXY A two-component, high-build, high-solids (at least 90%) coal tar and epoxy resin with the following properties: Property Typical Value Standard Bond Strength to Concrete 3 MPa Bond Strength to Steel (Sandblast) 7.5 MPa Heat Deflection Temperature ASTM D648 60C or above Potential Health Hazard during application None and in-service Priming coat shall be suitably selected, separately, for steel and concrete, and approval shall be obtained from the COMPANY.

ADC / DVD

OPERATING DEPT.

CERTIFIED

BY: :

MQQ

THIS DRAWING IS NOT TO BE USED FOR CONSTRUCTION OR FOR ORDERING MATERIALS UNTIL CERTIFIED AND DATED

**** END OF SECTION IV & SOW/TS ****

[[PTS- 14ED416 doc. MQQ/ADC/DVD) November 2013 ]


PLANT NO. INDEX PTS NO. PAGE NO. REV.

SCOPE OF WORK AND TECHNICAL SPECIFICATIONS


JOB ORDER NO.

1-- 1443026 111

FOR REPLACEMENT OF HVAC SYSTEM AT EASTERN OPERATING AREA SUBSTATION

D047

PTS-14ED416

SAUDI ARABIA

75 OF 77

CERT.

SAUDI ELECTRICITY COMPANY

NO.

DESCRIPTION 3

CHKD

APPD

REVISIONS

DRAWN BY DATE CHKD BY

SECTION V COMMISIONING TEST 5.01 GENERAL


APPROVED

ENGINEERING DEPT.

A. A list, giving the details of the commissioning and site tests shall be prepared by the CONTRACTOR and submitted to the COMPANY for review and approval not less than two (2) months before the schedule date of tests. B. The CONTRACTOR shall be responsible for providing all the appropriate tools, test equiptment and temporary A/C and D/C power needed to perform the commissioning and site tests. All tests shall be performing in accordance with the applicable IEC and ANSI Standards and established practices and procedures. C. The CONTRACTOR shall furnish a schedule date of tests with a list of test and commissioning equiptment to be used for the PROJECT. The list shall indicate wether each equiptment is owned or rented.

ADC / DVD

OPERATING DEPT.

CERTIFIED

D. The CONTRACTOR shall be responsible for conducting additional test if recommended by the equiptment manufacturers or by the COMPANY. E. The CONTRACTOR shall be responsible for commissioning the existing protection scheme involved with the scope of the subject PROJECT. F. The CONTRACTOR shall be responsible to carry out all tests in safe manner and with pre- determined safe working procedure submitted to the COMPANY.

BY: :

MQQ

THIS DRAWING IS NOT TO BE USED FOR CONSTRUCTION OR FOR ORDERING MATERIALS UNTIL CERTIFIED AND DATED

G. The mechanical check and visual inspection as required in COMPANY Standard TCS-P105 shall be carried out prior to any electrical test. H. All sites testing and commissioning shall be done under COMPANY witness. Witnessing of testing/commissioning by COMPANY does not mean acceptance of test
[[PTS- 14ED416 doc. MQQ/ADC/DVD) November 2013 ]
PLANT NO. INDEX PTS NO. PAGE NO. REV.

SCOPE OF WORK AND TECHNICAL SPECIFICATIONS


JOB ORDER NO.

1-- 1443026 111

FOR REPLACEMENT OF HVAC SYSTEM AT EASTERN OPERATING AREA SUBSTATION

D047

PTS-14ED416

SAUDI ARABIA

76 OF 77

CERT.

SAUDI ELECTRICITY COMPANY

APPD

CHKD

results. Test result will be review and approved by COMPANY separately after CONTRACTOR submits the same for review and approval. I. Field tests and commissioning results shall be submitted to the COMAPNAY not later than two (2) days after completion of tests for review prior to 15 days before final energization.

DESCRIPTION

J. The CONTRACTOR shall handover all special test equiptment, if any, used for testing and commissioning to the COMPANY. 5.02 SUBSTATION EQUIPTMENT The CONTRACTOR shall perform all applicable Site commissioning tests of the new equiptment installed under this PROJECT in accordance with applicable sections of the COMPANY Standard TCS-P-105, "Pre- Commissioning Test/Procedures for SEC Transmission Electrical Installation. **** END OF SECTION V **

NO.

REVISIONS

DRAWN BY DATE CHKD BY

APPROVED ENGINEERING DEPT.

ADC / DVD

OPERATING DEPT.

CERTIFIED

BY: :

MQQ

THIS DRAWING IS NOT TO BE USED FOR CONSTRUCTION OR FOR ORDERING MATERIALS UNTIL CERTIFIED AND DATED

[[PTS- 14ED416 doc. MQQ/ADC/DVD) November 2013 ]


PLANT NO. INDEX PTS NO. PAGE NO. REV.

SCOPE OF WORK AND TECHNICAL SPECIFICATIONS


JOB ORDER NO.

1-- 1443026 111

FOR REPLACEMENT OF HVAC SYSTEM AT EASTERN OPERATING AREA SUBSTATION

D047

PTS-14ED416

SAUDI ARABIA

77 OF 77

CERT.

SAUDI ELECTRICITY COMPANY

DESCRIPTION

CHKD

APPD

APPENDICES
NO. 3 2

REVISIONS

TO
DRAWN BY DATE CHKD BY

SCOPE OF WORK & TECHNICAL SPECIFICATIONS FOR REPLACEMENT OF HVAC SYSTEM AT EASTERN OPERATING AREA SUBSTATION

APPROVED ENGINEERING DEPT.

ADC / DVD

OPERATING DEPT.

PTS 14ED416

( DRAFT )
CERTIFIED MQQ BY:

DATE:

THIS DRAWING IS NOT TO BE USED FOR CONSTRUCTION OR FOR ORDERING MATERIALS UNTIL CERTIFIED AND DATED

[PTS-.doc. / (ADC/DVD) 11/28/2013

PLANT NO.
JOB ORDER NO.

INDEX

PTS NO.

PAGE NO.

REV.

SCOPE OF WORK AND TECHNICAL SPECIFICATIONS FOR REPLACEMENT OF HVAC SYSTEM AT EASTERN OPERATING AREA SUBSTATION SAUDI ARABIA

PTS-14ED416

CERT.

SAUDI ELECTRICITY COMPANY

CHKD

APPD

TABLE OF CONTENTS
DESCRIPTION

APPENDIX I

TABLE -1: LIST OF EXISTING A/C UNITS

NO.

APPENDIX II

DRAWING CONTROL SHEET ( ET 800489 )

REVISIONS

DRAWN BY DATE CHKD BY

APPENDIX III

MATERIAL DATA SCHEDULES

APPENDIX IV
APPROVED ENGINEERING DEPT.

TECHNICAL DATA MANUALS

APPENDIX V
ADC / DVD

OPERATIONAL SPARE PARTS

OPERATING DEPT.

CERTIFIED

MQQ BY:

DATE:

THIS DRAWING IS NOT TO BE USED FOR CONSTRUCTION OR FOR ORDERING MATERIALS UNTIL CERTIFIED AND DATED

[PTS-.doc. / (ADC/DVD) 11/28/2013

PLANT NO.
JOB ORDER NO.

INDEX

PTS NO.

PAGE NO.

REV.

SCOPE OF WORK AND TECHNICAL SPECIFICATIONS FOR REPLACEMENT OF HVAC SYSTEM AT EASTERN OPERATING AREA SUBSTATION SAUDI ARABIA

PTS-14ED416

CERT.

SAUDI ELECTRICITY COMPANY

NO.

DESCRIPTION 3

CHKD

APPD

REVISIONS

DRAWN BY DATE CHKD BY

APPENDIX I

APPROVED ENGINEERING DEPT.

TABLE-1
ADC / DVD

LIST OF EXISTING HVAC UNITS


OPERATING DEPT.

CERTIFIED

MQQ BY:

DATE:

THIS DRAWING IS NOT TO BE USED FOR CONSTRUCTION OR FOR ORDERING MATERIALS UNTIL CERTIFIED AND DATED

[PTS-.doc. / (ADC/DVD) 11/28/2013

PLANT NO.
JOB ORDER NO.

INDEX

PTS NO.

PAGE NO.

REV.

SCOPE OF WORK AND TECHNICAL SPECIFICATIONS FOR REPLACEMENT OF HVAC SYSTEM AT EASTERN OPERATING AREA SUBSTATION SAUDI ARABIA

PTS-14ED416

CERT.

SAUDI ELECTRICITY COMPANY

CHKD

APPD

APPENDIX - I
DESCRIPTION

TABLE 1 LIST OF EXISTING A/C UNITS IN 18-SUBSTATIONS AT DAMMAM EOA AREAS

NO.

REVISIONS

ITEM NO.

AREA SERVED

DESCRIPTION

REMARKS

DRAWN BY DATE CHKD BY

APPROVED ENGINEERING DEPT.

Aziziyah 69/13.8 kv Substation

1.0

ADC / DVD

OPERATING DEPT.

Packaged Type A/C Units. ( 2 Units ) Capacity Tons ( Verify on Site ) ManufacturerModel # Electrical Data: Volts 380 Volts Ph - 3Ph Hz -60 Hz

Replaced existing PACU Type two (2) A/C Units with new Packaged Type Air Condition Units. ( 1 Stand By 1 Duty )

CERTIFIED

MQQ BY:

Kaab 69/13.8 kv Substation 2.0

Split Type A/C Units. Capacity Tons ( Verify on Site) ManufacturerModel # Electrical Data: Volts 380 Volts Ph - 3Ph Hz -60 Hz

Replaced existingSplit Type A/C units with new two (2) Split Type Air Condition Units. ( 1 Stand By 1 Duty )

DATE:

THIS DRAWING IS NOT TO BE USED FOR CONSTRUCTION OR FOR ORDERING MATERIALS UNTIL CERTIFIED AND DATED

3.0

National Guard 69/13.8 kv

Split Type A/C Units Capacity Tons (Verify on Site )

Replaced Existing Split Type A/C Units with new two (2) Split Type Air Condition Units. ( 1 Stand By 1 Duty )
INDEX PTS NO. PAGE NO. REV.

[PTS-.doc. / (ADC/DVD) 11/28/2013

PLANT NO.
JOB ORDER NO.

SCOPE OF WORK AND TECHNICAL SPECIFICATIONS FOR REPLACEMENT OF HVAC SYSTEM AT EASTERN OPERATING AREA SUBSTATION SAUDI ARABIA

PTS-14ED416

CERT.

SAUDI ELECTRICITY COMPANY


ManufacturerHauler Model # Electrical Data: Volts 380 Volts Ph - 3Ph Hz -60 Hz

APPD

DESCRIPTION

CHKD

Substation

REVISIONS

Muraikabat 69/13.8 kv Substation

DRAWN BY DATE CHKD BY

Split Type A/C Units. Capacity Tons ( Verify on Site ) Manufacturer- Zamil Model # Electrical Data: Volts Ph - 3Ph Hz -60 Hz

NO.

Replace existing Split Type A/C Units with two ( 2 ) new Split Type A/C Units ( 1-Stand By-1Duty )

APPROVED ENGINEERING DEPT.

ADC / DVD

OPERATING DEPT.

Nabia 69/13.8 kv Substation

CERTIFIED

Split Type A/C Units Capacity Tons (Verify on Site ) Manufacturer Model # Electrical Data: Volts Verify on Site Ph - 3Ph Hz -60 Hz

Replace existing Split Type A/C Units with new two (2) Split Type A/C Units ( 1-Stand By-1Duty )

MQQ BY:

DATE:

Qatif 69/13.8 kv Substation

THIS DRAWING IS NOT TO BE USED FOR CONSTRUCTION OR FOR ORDERING MATERIALS UNTIL CERTIFIED AND DATED

Packaged Type A/C Units. ( 2 Units ) Capacity Tons ( Verify on Site ) ManufacturerModel # Electrical Data: Volts 380 Volts Ph - 3Ph Hz -60 Hz

Remove existing Window Type A/C And Replace existing Packaged Type A/C units with Packaged Type A/C Units or Split Type A/c units whichever is applicable in the Area. ( 1 Stand By 1 Duty Unit )

[PTS-.doc. / (ADC/DVD) 11/28/2013

PLANT NO.
JOB ORDER NO.

INDEX

PTS NO.

PAGE NO.

REV.

SCOPE OF WORK AND TECHNICAL SPECIFICATIONS FOR REPLACEMENT OF HVAC SYSTEM AT EASTERN OPERATING AREA SUBSTATION SAUDI ARABIA

PTS-14ED416

CERT.

SAUDI ELECTRICITY COMPANY

CHKD

APPD

7
DESCRIPTION

Rabwah 69/13.8 kv Substation

SplitType A/C Units Capacity Tons ( Verify on Site ) Manufacturer Model # Electrical Data: Volts -380 V Ph - 3Ph Hz -60 Hz

Replace existing Split Type A/C Units with new two (2)Split Type A/C Units ( 1-Stand By-1Duty )

NO.

REVISIONS

DRAWN BY DATE CHKD BY

Bayouniyah 69/13.8 kv Substation

APPROVED ENGINEERING DEPT.

Split Type A/C Units. Capacity Tons ( Verify On Site ) Manufacturer- Zamil Model # Electrical Data: Volts Ph - 3Ph Hz -60 Hz

Replace existing Split Type A/C Units with two ( 2 ) new Packaged Type A/C Units ( 1-Stand By-1Duty )

ADC / DVD

Ittisalat 69/13.8 kv Substation

OPERATING DEPT.

Split Type A/C Units. Capacity Tons (Verify On Site ) Manufacturer Model # Electrical Data: Volts Ph - 3Ph Hz -60 Hz

Replace existing Split Type A/C Units with two ( 2 ) new Packaged Type A/C Units ( 1-Stand By-1Duty )

CERTIFIED

MQQ BY:

DATE:

10

Riyadh Water Pump 69/13.8 kv Substation

THIS DRAWING IS NOT TO BE USED FOR CONSTRUCTION OR FOR ORDERING MATERIALS UNTIL CERTIFIED AND DATED

Split Type A/C Units Capacity Tons ( Verify on Site ) Manufacturer Model # Electrical Data: Volts Verify on Site Ph - 3Ph Hz -60 Hz

Replace existing Split Type A/C Units with new two (2) Packaged Type A/C Units ( 1-Stand By-1Duty )

[PTS-.doc. / (ADC/DVD) 11/28/2013

PLANT NO.
JOB ORDER NO.

INDEX

PTS NO.

PAGE NO.

REV.

SCOPE OF WORK AND TECHNICAL SPECIFICATIONS FOR REPLACEMENT OF HVAC SYSTEM AT EASTERN OPERATING AREA SUBSTATION SAUDI ARABIA

PTS-14ED416

CERT.

SAUDI ELECTRICITY COMPANY

CHKD

APPD

11
DESCRIPTION

Al-Hada 69/13.8 kv Substation

Split Type A/C Units Capacity Tons ( Verify on Site ) Manufacturer Model # Electrical Data: Volts Verify on Site Ph - 3Ph Hz -60 Hz

Replace existing Split Type A/C Units with new two (2) Split Type A/C Units ( 1-Stand By-1Duty )

NO.

REVISIONS

Split Type A/C Units


Al-Nakheel 69/13.8 kv Substation Capacity Tons ( Verify on Site ) Manufacturer Model # Electrical Data: Volts 380 V Ph - 3Ph Hz -60 Hz Replace existing Split Type A/C Units with new two (2) Split Type A/C Units ( 1-Stand By-1Duty )

DRAWN BY DATE CHKD BY

12

APPROVED ENGINEERING DEPT.

ADC / DVD

OPERATING DEPT.

13

Tubaishi 69/13.8 kv Substation

CERTIFIED

MQQ BY:

DATE:

14

Ummal 69/13.8 kv Substation

THIS DRAWING IS NOT TO BE USED FOR CONSTRUCTION OR FOR ORDERING MATERIALS UNTIL CERTIFIED AND DATED

Packaged Type A/C Units Capacity - Tons ( Verify ) Manufacturer Model Electrical Data: Volts Verify on Site Ph 3Ph Hz-60 Hz Packaged Type A/C Units Capacity - Tons ( Verify ) Manufacturer Model Electrical Data: Volts Verify on Site Ph 3Ph Hz-60 Hz

Replace existing Packaged Type A/C Units with new two (2) Packaged Type A/C Units ( 1-Stand By-1Duty )

Removal of Window Type A/C and Replace existing Packaged Type A/C Units with new two (2) Packaged Type A/C Units ( 1-Stand By-1Duty )

[PTS-.doc. / (ADC/DVD) 11/28/2013

PLANT NO.
JOB ORDER NO.

INDEX

PTS NO.

PAGE NO.

REV.

SCOPE OF WORK AND TECHNICAL SPECIFICATIONS FOR REPLACEMENT OF HVAC SYSTEM AT EASTERN OPERATING AREA SUBSTATION SAUDI ARABIA

PTS-14ED416

CERT.

SAUDI ELECTRICITY COMPANY


Replace existing PackagedType A/C Units with two ( 2 ) new Packaged Type A/C Units ( 1-Stand By-1Duty )

CHKD

APPD

15
DESCRIPTION

KFIA 69/13.8 kv Substation

PackagedType A/C Units Capacity Tons Manufacturer Model # Electrical Data: Volts Ph - 3Ph Hz -60 Hz

NO.

REVISIONS

16

Al-Bayyat 69/13.8 kv Substation

Split Type A/C Units


Capacity Tons ( Verify on Site ) Manufacturer Model # Electrical Data: Volts 380 V Ph - 3Ph Hz -60 Hz

Replace existing Split Type A/C Units with new two (2) Split Type A/C Units ( 1-Stand By-1Duty )

DRAWN BY DATE CHKD BY

APPROVED ENGINEERING DEPT.

ADC / DVD

OPERATING DEPT.

CERTIFIED

MQQ BY:

DATE:

THIS DRAWING IS NOT TO BE USED FOR CONSTRUCTION OR FOR ORDERING MATERIALS UNTIL CERTIFIED AND DATED

[PTS-.doc. / (ADC/DVD) 11/28/2013

PLANT NO.
JOB ORDER NO.

INDEX

PTS NO.

PAGE NO.

REV.

SCOPE OF WORK AND TECHNICAL SPECIFICATIONS FOR REPLACEMENT OF HVAC SYSTEM AT EASTERN OPERATING AREA SUBSTATION SAUDI ARABIA

PTS-14ED416

CERT.

SAUDI ELECTRICITY COMPANY

NO.

DESCRIPTION 3

CHKD

APPD

REVISIONS

DRAWN BY DATE CHKD BY

APPROVED ENGINEERING DEPT.

APPENDIX - II
ADC / DVD

DRAWING CONTROL SHEET ( ET-800489 )


OPERATING DEPT.

CERTIFIED

MQQ BY:

DATE:

THIS DRAWING IS NOT TO BE USED FOR CONSTRUCTION OR FOR ORDERING MATERIALS UNTIL CERTIFIED AND DATED

[PTS-.doc. / (ADC/DVD) 11/28/2013

PLANT NO.
JOB ORDER NO.

INDEX

PTS NO.

PAGE NO.

REV.

SCOPE OF WORK AND TECHNICAL SPECIFICATIONS FOR REPLACEMENT OF HVAC SYSTEM AT EASTERN OPERATING AREA SUBSTATION SAUDI ARABIA

PTS-14ED416


Saudi Electricity Company
DRAWING CONTROL SHEET
PROJECT TITLE PROJECT MANAGER / ENGINEER CONTRACT NO. JOB ORDER NO. CLIENT


Eastern Operating Area

REPLACEMENT OF HVAC SYSTEM AT EASTERN OPERATING AREA IN 18 SUBSTATIONS


DAMMAM / QATIF
DRAWING NO. NO. OF SHEET INITIAL REV. NO.

MAZEN AL-QURTAS / ADC


SAUDI ARABIA
FURTHER REV. NO. DATE

SEC-EOA

DRAWING TITLE

REMARKS

INDEX - X
ET-800489 1 of 1 0 DRAWING CONTROL SHEET

INDEX - A
PTS-13ED426 TO 1 SCOPE OF WORK AND TECHNICAL SPECIFICATIONS

INDEX - K
ET-800490 ET-800490 ET-800491 ET-800491 ET-800492 ET-800492 ET-800493 ET-800493 ET-800494 ET-800494 ET-800495 ET-800495 ET-800496 ET-800496 ET-800497 ET-800497 ET-800498 ET-800498 1 2 1 2 1 2 1 2 1 2 1 2 1 2 1 2 1 2 of of of of of of of of of of of of of of of of of of 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 EXISTING EQUIPMENT LAYOUT - AZIZIYAH SUBSTATION PROPOSED EQUIPMENT LAYOUT - AZIZIYAH SUBSTATION EXISTING EQUIPMENT LAYOUT - MODA/KAAB SUBSTATION PROPOSED EQUIPMENT LAYOUT - MODA/KAAB SUBSTATION EXISTING EQUIPMENT LAYOUT - NATIONAL GUARD SUBSTATION PROPOSED EQUIPMENT LAYOUT - NATIONAL GUARD SUBSTATION EXISTING EQUIPMENT LAYOUT - MURAIKABAT SUBSTATION PROPOSED EQUIPMENT LAYOUT - MURAIKABAT SUBSTATION EXISTING EQUIPMENT LAYOUT - NABIAH SUBSTATION PROPOSED EQUIPMENT LAYOUT - NABIAH SUBSTATION EXISTING EQUIPMENT LAYOUT - QATIF SUBSTATION PROPOSED EQUIPMENT LAYOUT - QATIF SUBSTATION EXISTING EQUIPMENT LAYOUT - AL-RABWAH SUBSTATION PROPOSED EQUIPMENT LAYOUT - AL-RABWAH SUBSTATION EXISTING EQUIPMENT LAYOUT - OLD BAYOUNIYAH SUBSTATION PROPOSED EQUIPMENT LAYOUT - OLD BAYOUNIYAH SUBSTATION EXISTING EQUIPMENT LAYOUT - ITTISILAT SUBSTATION PROPOSED EQUIPMENT LAYOUT - ITTISILAT SUBSTATION
PROJECT COMPLETION DATE PLANT NOS. INDEX DRAWING NO. SHEET NO. REV. NO.

AS BUILT BY

D050

ET-800489

OF

00
EXCEL

THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ELECTRICITY CO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE W RITTEN CONSENT OF ITS OWNER.


Saudi Electricity Company
DRAWING CONTROL SHEET
PROJECT TITLE PROJECT MANAGER / ENGINEER CONTRACT NO. JOB ORDER NO. CLIENT


Eastern Operating Area

REPLACEMENT OF HVAC SYSTEM AT EASTERN OPERATING AREA IN 18 SUBSTATIONS


DAMMAM / QATIF
DRAWING NO. NO. OF SHEET INITIAL REV. NO.

MAZEN AL-QURTAS / ADC


SAUDI ARABIA
FURTHER REV. NO. DATE

SEC-EOA

DRAWING TITLE

REMARKS

ET-800499 ET-800499 ET-800499 ET-800500 ET-800500 ET-800501 ET-800501 ET-800502 ET-800502 ET-800503 ET-800503 ET-800504 ET-800504 ET-800505 ET-800505 ET-800506 ET-800507 ET-800507 ET-800508 ET-800508 ET-800509

1 2 3 1 2 1 2 1 2 1 2 1 2 1 2 1 1 2 1 2 1

of of of of of of of of of of of of of of of OF of of of of OF

3 3 3 2 2 2 2 2 2 2 2 2 2 2 2 1 2 2 2 2 1

0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

EXISTING EQUIPMENT LAYOUT - RIYADH WATER PUMP SUBSTATION PROPOSED EQUIPMENT LAYOUT - RIYADH WATER PUMP SUBSTATION EXISTING CEILING LAYOUT - RIYADH WATER PUMP SUBSTATION EXISTING EQUIPMENT LAYOUT -AL-HADA SUBSTATION PROPOSED EQUIPMENT LAYOUT - AL-HADA SUBSTATION EXISTING EQUIPMENT LAYOUT - AL-NAKHEEL SUBSTATION PROPOSED EQUIPMENT LAYOUT - AL-NAKHEEL SUBSTATION EXISTING EQUIPMENT LAYOUT - TUBAISHI SUBSTATION PROPOSED EQUIPMENT LAYOUT - TUBAISHI SUBSTATION EXISTING EQUIPMENT LAYOUT - UMMAL SUBSTATION PROPOSED EQUIPMENT LAYOUT - UMMAL SUBSTATION EXISTING EQUIPMENT LAYOUT - KFIA SUBSTATION PROPOSED EQUIPMENT LAYOUT - KFIA SUBSTATION EXISTING EQUIPMENT LAYOUT - AL-BAYAT SUBSTATION PROPOSED EQUIPMENT LAYOUT - AL-BAYAT SUBSTATION HVAC EQUIPTMENT FOUNDATION AND PIPE BARRIER HVAC SYSTEM SCHEMATIC DAIGRAM HVAC SYSTEM SCHEMATIC DAIGRAM HVAC CONTROL BLOCK DIAGRAM HVAC CONTROL BLOCK DIAGRAM TYPICAL CONTROL WIRING DIAGRAM INDEX - K

AS BUILT BY

PROJECT COMPLETION DATE

PLANT NOS.

INDEX

DRAWING NO.

SHEET NO.

REV. NO.

D050

ET-800489

OF

00
EXCEL

THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ELECTRICITY CO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE W RITTEN CONSENT OF ITS OWNER.

CERT.

SAUDI ELECTRICITY COMPANY

NO.

DESCRIPTION 3

CHKD

APPD

REVISIONS

DRAWN BY DATE CHKD BY

APPROVED ENGINEERING DEPT.

APPENDIX - IIl MATERIAL DATA SCHEDULE

ADC / DVD

OPERATING DEPT.

CERTIFIED

MQQ BY:

DATE:

THIS DRAWING IS NOT TO BE USED FOR CONSTRUCTION OR FOR ORDERING MATERIALS UNTIL CERTIFIED AND DATED

APPENDIX - III
[PTS-.doc. / (ADC/DVD) 11/28/2013

PLANT NO.
JOB ORDER NO.

INDEX

PTS NO.

PAGE NO.

REV.

SCOPE OF WORK AND TECHNICAL SPECIFICATIONS FOR REPLACEMENT OF HVAC SYSTEM AT EASTERN OPERATING AREA SUBSTATION SAUDI ARABIA

PTS-14ED416

CERT.

SAUDI ELECTRICITY COMPANY


Pag e 1 of 1

APPD

CHKD

MATERIAL DATA SCHEDULES

DESCRIPTION

The following COMPANY Materials Standard Specifications Data Schedules are attached. The CONTRACTOR shall fill out the Data Schedules indicating the technical particulars of the equipment offered by him: 1. 2. 3 11-TMSS-10 11-TMSS-11 23-TMSS-02 24-TMSS-01 31-TMSS-02 70-TMSS-03 73-TMSS-01Rev.1 75-TMSS-1 Power and/or Control Cable, Cu. or Al. Conductor, 600/1000V Rating Shielded Instrumentation Cables Duct Sealing Units Metallic Cable Tray System Auxiliary AC/DC Panels Normal Weight Ready-Mixed Portland Cement Concrete Packaged Air Conditioning Units

NO.

REVISIONS

4. 5.

DRAWN BY DATE CHKD BY

6. 7.

APPROVED ENGINEERING DEPT.

8.
ADC / DVD

Plastic Piping for Plumbing System

All blanks on the Data Schedules, Inquiry Information (for SMSS/TMSS) shall be properly filledOPERATING DEPT.

up by the CONTRACTOR (as required) without omission and shall be submitted as part of the CONTRACTORS Technical Proposal.

Any exception or non-conformance items which the CONTRACTOR wishes to propose shall
CERTIFIED

be clearly stated in the bid proposals and in Data Schedules, together with reason(s) or justification(s), and the paragraphs of the specification to which the exceptions or nonconformance items apply.

MQQ BY:

DATE:

THIS DRAWING IS NOT TO BE USED FOR CONSTRUCTION OR FOR ORDERING MATERIALS UNTIL CERTIFIED AND DATED

[PTS-.doc. / (ADC/DVD) 11/28/2013

PLANT NO.
JOB ORDER NO.

INDEX

PTS NO.

PAGE NO.

REV.

SCOPE OF WORK AND TECHNICAL SPECIFICATIONS FOR REPLACEMENT OF HVAC SYSTEM AT EASTERN OPERATING AREA SUBSTATION SAUDI ARABIA

PTS-14ED416

CERT.

SAUDI ELECTRICITY COMPANY

NO.

DESCRIPTION 3

CHKD

APPD

REVISIONS

DRAWN BY DATE CHKD BY

APPENDIX - IV TECHNICAL DATA MANUALS

APPROVED ENGINEERING DEPT.

ADC / DVD

OPERATING DEPT.

CERTIFIED

MQQ BY:

DATE:

THIS DRAWING IS NOT TO BE USED FOR CONSTRUCTION OR FOR ORDERING MATERIALS UNTIL CERTIFIED AND DATED

[PTS-.doc. / (ADC/DVD) 11/28/2013

PLANT NO.
JOB ORDER NO.

INDEX

PTS NO.

PAGE NO.

REV.

SCOPE OF WORK AND TECHNICAL SPECIFICATIONS FOR REPLACEMENT OF HVAC SYSTEM AT EASTERN OPERATING AREA SUBSTATION SAUDI ARABIA

PTS-14ED416

CERT.

SAUDI ELECTRICITY COMPANY

CHKD

APPD

APPENDIX - IV TECHNICAL DATA MANUALS


1.
Page 1 of 1

Technical Data Manuals The CONTRACTOR shall provide Technical Data Manuals as applicable for the substation equipment installed under the PROJECT. The CONTRACTOR shall submit at least two (2) sets of manuals for review and approval by the COMPANY at least two (2) months prior to the mechanical completion date of the PROJECT. After COMPANYS approval, the CONTRACTOR shall submit three (3) sets of final approved manuals two (2) weeks before mechanical completion date of the PROJECT. Substation Equipment The Technical Data Manuals for the substation equipment, as applicable, shall include the following information as a minimum, pertaining to the major substation equipment installed under the PROJECT. Equipment for which SMSS/TMSS Data Schedules are available A copy of manufacturers nameplate of the equipment. Name of the manufacturer and equipment serial number shall be specified in the attached Form No. PTD-EQP DS1. Updated Data Schedules attached to the COMPANYs Material Standard Specification (SMSS) after manufacturer of the equipment, and stamped by the manufacturer. The technical data is required for the following substation equipment: Disconnects/Ground Switches Station Service Transformers 380 V Switchgear Panels

DESCRIPTION

NO.

2.

REVISIONS

DRAWN BY DATE CHKD BY

APPROVED ENGINEERING DEPT.

ADC / DVD

OPERATING DEPT.

CERTIFIED

MQQ BY:

DATE:

THIS DRAWING IS NOT TO BE USED FOR CONSTRUCTION OR FOR ORDERING MATERIALS UNTIL CERTIFIED AND DATED

[PTS-.doc. / (ADC/DVD) 11/28/2013

PLANT NO.
JOB ORDER NO.

INDEX

PTS NO.

PAGE NO.

REV.

SCOPE OF WORK AND TECHNICAL SPECIFICATIONS FOR REPLACEMENT OF HVAC SYSTEM AT EASTERN OPERATING AREA SUBSTATION SAUDI ARABIA

PTS-14ED416

CERT.

SAUDI ELECTRICITY COMPANY

NO.

DESCRIPTION 3

CHKD

APPD

REVISIONS

DRAWN BY DATE CHKD BY

APPENDIX - V
APPROVED ENGINEERING DEPT.

OPERATIONAL START UP SPARE PARTS


ADC / DVD

OPERATING DEPT.

CERTIFIED

MQQ BY:

DATE:

THIS DRAWING IS NOT TO BE USED FOR CONSTRUCTION OR FOR ORDERING MATERIALS UNTIL CERTIFIED AND DATED

[PTS-.doc. / (ADC/DVD) 11/28/2013

PLANT NO.
JOB ORDER NO.

INDEX

PTS NO.

PAGE NO.

REV.

SCOPE OF WORK AND TECHNICAL SPECIFICATIONS FOR REPLACEMENT OF HVAC SYSTEM AT EASTERN OPERATING AREA SUBSTATION SAUDI ARABIA

PTS-14ED416

CERT.

SAUDI ELECTRICITY COMPANY

CHKD

APPD

APPENDIX V

OPERATIONAL START- UP SPARE PARTS

DESCRIPTION

A.

REQUIREMENTS 1. Contractor shall provide Operational Start Up Spare Parts information in Excel sheet as per Schedule C. The list shall include manufacturer name and part number in particular and other relevant information as well. The Excel sheet submittal shall be in hard copy and soft copy to Concerned Proponent Department in the Company. Contractor shall provide Filled in Cataloging Data Modules to Concerned Departments in the Company for their review and comments. The Cataloging Data Formats and Modules are available with either Concerned Departments in the Company. Concerned Departments in the Company shall provide necessary clarifications to contractor for filling up Cataloging Data Modules.

NO.

2.

REVISIONS

DRAWN BY DATE CHKD BY

3.

APPROVED ENGINEERING DEPT.

ADC / DVD

OPERATING DEPT.

CERTIFIED

MQQ BY:

DATE:

THIS DRAWING IS NOT TO BE USED FOR CONSTRUCTION OR FOR ORDERING MATERIALS UNTIL CERTIFIED AND DATED

[PTS-.doc. / (ADC/DVD) 11/28/2013

PLANT NO.
JOB ORDER NO.

INDEX

PTS NO.

PAGE NO.

REV.

SCOPE OF WORK AND TECHNICAL SPECIFICATIONS FOR REPLACEMENT OF HVAC SYSTEM AT EASTERN OPERATING AREA SUBSTATION SAUDI ARABIA

PTS-14ED416