METHOD STATEMENT FOR ERECTION AND INSTALLATION OF FIXED ROOF STORAGE TANK

PROJECT. NO. REVISION NO. PAGE NO.

: : :

K1202107 0 1 of 12

METHOD STATEMENT FOR ERECTION AND INSTALLATION OF FIXED ROOF STORAGE TANK T-49-11 DIESEL OIL STORAGE TANK

0 Rev.

19/10//2013 Date

Hairol Zoll Prepared By

Edy Melchor Checked By

Edy Melchor Approved By

KNM Petrosab Engineering Sdn Bhd

METHOD STATEMENT FOR ERECTION AND INSTALLATION OF FIXED ROOF STORAGE TANK

PROJECT. NO. REVISION NO. PAGE NO.

: : :

K1202107 0 2 of 12

REVISION HISTORY SECTION PARA DESCRIPTION PREPARED BY

KNM Petrosab Engineering Sdn Bhd

METHOD STATEMENT FOR ERECTION AND INSTALLATION OF FIXED ROOF STORAGE TANK

PROJECT. NO. REVISION NO. PAGE NO.

: : :

K1202107 0 3 of 12

TABLE OF CONTENTS

SECTION 1.0 2.0 3.0 4.0 5.0 6.0 6.1 6.2 6.3 6.4 6.5 SCOPE

DESCRIPTION

PAGE 4 4 4 4 4 6 6 7 9 10 10

APPLICABLE CODES, STANDARDS AND REFERENCES DEFINITIONS LIST OF EQUIPMENT PREPARATORY WORKS TANK ERECTION METHOD ERECTION OF BOTTOM PLATES ERECTION OF SHELL PLATES INSTTALATION OF ROOF STRUCTURE INSTALLATION OF ACCESSORIES & TANK APPURTENANCES ASSEMBLING OF STEEL STRUCTURES & APPURTENANCES

7.0 8.0 9.0 10.0

WELDING SEQUENCE INSPECTION LEAKAGE TESTING APPENDIX

11 11 11 12

KNM Petrosab Engineering Sdn Bhd

METHOD STATEMENT FOR ERECTION AND INSTALLATION OF FIXED ROOF STORAGE TANK
1.0 SCOPE

PROJECT. NO. REVISION NO. PAGE NO.

: : :

K1202107 0 4 of 12

1.1 This procedure describes the sequence and methods to perform site erection and fabrication of Fixed Roof Storage Tank for Knock Down (KD) Tank for Sabah Ammonia Urea (SAMUR) Project2.0 APPLICABLE CODES, STANDARDS AND REFERENCES 2.1 API 650 Welded Steel Tank for Oil Service (revision 11, 2010) 2.2 PTS 34.51.01.31: Standard Vertical Tanks - Selection, Design & Fabrication 2.3 PTS 64.51.01.31: Standard Vertical Tanks - Field Erection & Testing 2.4 PTS 20.156A: Standard Tanks, Volume 1 - Part 1 2.5 PTS 20.156B: Standard Tanks, Volume 1 - Part 2 2.6 Approved Drawings 2.7 BS 2654 cross reference with EN1491 3.0 DEFINITIONS 3.1 KNM PETROSAB : Contractor 3.2 Consortium : AIT 3.3 PCSB : OWNER 4.0 LIST OF EQUIPMENT 4.1 FCAW/ SMAW / SAW welding machines 4.2 Hand Grinder 4.3 Hot Air Blower 4.4 Spreader Bar 4.5 Webbing Sling 6meter, 3000kg 4.6 Webbing Sling 12m, 4000kg 4.7 Robin water pump 4.8 Portable electrode rod dryer 4.9 Mobile Crane 25 & 45 ton 4.10 Diesel water pump 4.11 Welding rectifier 4.12 Electric cut-off machine 4.13 Horizontal lifting clamp 4.14 Lifting clamp 4.15 Gauging machine 4.16 Vacuum 4.17 SLR-0365 G210 Screw Pin Chain Shackle '7/8' (6.5T) 4.18 Electrode Baking & Holding Ovens 4.19 Flux Oven 4.20 Wind girder 4.21 Welder Buggy 4.22 Panel Boards

KNM Petrosab Engineering Sdn Bhd

METHOD STATEMENT FOR ERECTION AND INSTALLATION OF FIXED ROOF STORAGE TANK
5.0 PREPARATORY WORKS 5.1

PROJECT. NO. REVISION NO. PAGE NO.

: : :

K1202107 0 5 of 12

A 25 ton and 50 ton hydraulic Rough Terrain type crane will be positioned around the tank foundation (100 ton and above crane only for erection of roof structure assembly). If unfavourable soil conditions exist, pouring of gravel materials or laying out of thick wooden planks or steel plates will used to support the ground and crane stability. Before using the crane for lining operations, the inspection will be carried out for proper functioning and verify all the safety devices (e.g. overload protection) are operating satisfactorily. Test certificate should be available for inspection. Scaffoldings and welding buggy will be used to facilitate erection and welding works. Proper permit will be secured prior to erection of scaffoldings and welding buggy on site. All the erection aids such as clamps, wedges, shims, spacer plates and other devices for aligning the welding joints will be provided on site including all lifting tackles. AFC drawing checked and verified by KNMPESB shall be used. Prior to erection, the centre slope shall be checked as per approved drawing. The dimensions and elevations of the tank foundation as well as the correct orientation for starting point shall be checked. Ensure that the foundation work has been formally accepted by KNMPESB and AIT before proceeding with the tank erection. A release note shall be obtained from civil discipline on the handover of tank foundation. Prior to erection the centreline of the tank will be marked on the foundation as well as the four points along the circumference at 0, 90, 180 and 270 degrees by AIT surveyor. Elevation reference benchmark will be establish and set out on site. Plates and structural materials intended for tank erection will be laid properly on the ground with proper support and protection for not direct contact to the ground. All the plate material shall be check for dimensional accuracy and reported in the Applicable Inspection Report (Appendix I)

5.2

5.3

5.4

5.5 5.6

5.7

5.8

5.9

KNM Petrosab Engineering Sdn Bhd

METHOD STATEMENT FOR ERECTION AND INSTALLATION OF FIXED ROOF STORAGE TANK
5.10

PROJECT. NO. REVISION NO. PAGE NO.

: : :

K1202107 0 6 of 12

Before tanks erection started, foundation shall be checked by the tank builder with foundations contractor, and CLIENT to make sure that the foundation are according to specification requirement. If there were some obstacles on foundation to erecting of the tank, such foundation should be repaired by foundation contractor. The foundation shall be marked on four position (0, 90, 180 and 270) and will be done by foundation contractor or CLIENT. The item to be inspection of foundation are Dimension, Flatness, Levelness and sump location.

6.0 TANK ERECTION METHOD 6.1 Erection of Bottom Plate

6.1.1

The bottom plate shall be arranged in accordance with Bottom Plate Drawing and Orientation Drawing. First Lay down, the sketches plate, start from centre through to the four direction angle (0, 90, 180 & 270). The bottom centre plate shall be laid on the centre point which had been marked by stretching piano wires crosswise above the foundation. Centre bottom plates which will be basis for laying other plates.

6.1.2

6.1.3

6.1.4 The arrangement of bottom plates shall be laid out from centre to outward and tack-welded in surface to be straight as shown attached figure. Tack welds shall be 1.18 inch long or more on 1ft - 7.68 inch pitch. 6.1.5 For three laps joint, after finished first layer welding, checked welding line using Dye Penetrate Test or Vacuum Box Test (Section V, article 6, of the ASME Code). Bottom plates shall be assembled and tack-welded using special jigs for anti-distortion if necessary. Weld sketches plates which shell plate will be laid long of weld 7.87 inch (min.) from out to inward.

6.1.6 At the proper welding, the Vertical joints of 'V' blocks shall be welded first. Lapped plates shall be in close contact during welding. After the Vertical joints of 'V' blocks are welded, the Horizontal joints 'H' blocks shall be made.

KNM Petrosab Engineering Sdn Bhd

METHOD STATEMENT FOR ERECTION AND INSTALLATION OF FIXED ROOF STORAGE TANK

PROJECT. NO. REVISION NO. PAGE NO.

: : :

K1202107 0 7 of 12

6.1.7 Care shall be exercised during welding of bottom plates to assure minimum distortion and uniform lapping with as possible, plates shall be held in close construction at all lap joint. 6.1.8 After completion of welding works of bottom, tested using Vacuum Box and Soap suds to all welding line with a vacuum of 5 to 7 psi. 6.2 Erection of Shell Plate 6.2.1 First Course The shell circle line for erection shall be drawn on the bottom plates and punched equally by number of shell plates.

6.2.2 When the assembling of the first ring have completed, the vertical joints shall be tack-welded from inside to outside. 6.2.3 After completion of the tack-welded on the vertical joints, the level of top edge and plumbness shall be inspected with an instrument theodolite. 6.2.4 Check the item horizontal measuring position should be After Temporary Assembling of 1st Course. 6.2.5 The first continuous welding shall be made from the outside for vertical joints and back weld from inside. The Welding from down to up .The strong back or key plates shall be installed at right angle with the weld line to prevent plate distortion during welding. 6.2.6 Prior to application of the first bead to the inside welding, the strong back or key plates shall be removed and welded joints shall be cleaned thoroughly in a manner that will leave the exposed surface satisfactory for fusion the weld metal to be added. This cleaning shall be made from inside by arc-air gouging and/ or grinding to evenly and smoothly.
KNM Petrosab Engineering Sdn Bhd

METHOD STATEMENT FOR ERECTION AND INSTALLATION OF FIXED ROOF STORAGE TANK
6.2.7

PROJECT. NO. REVISION NO. PAGE NO.

: : :

K1202107 0 8 of 12

Second Course, the scaffolding board shall be arranged with lugs and brackets on both side of the first course. When the traveling scaffolding is used the scaffolding shall be installed. Vertical joints of the second course shall be assembled with the match mark, which had stamped on the first course. Vertical joints shall be matched accurately and retained in position with spacers and stiffeners. Horizontal joints between first and second course shall be matched to inside of each plates and retained in position with spacers and stiffeners. After completion of second course installed, start welding of vertical joints of second course in the same manner as the first course.

6.2.9

6.2.10

6.2.11 The welding of horizontal joints between first course and second course shall be made the outside first, and being the stiffeners removed. If there were some defect at first layer which shall be hindrance to welding from inside, after that the reverse side of horizontal joints shall be welded. 6.2.12 The fillet weld joint between shell plate and bottom plate shall be welded after second or third course shell plate is assembled. Third and Upper Course, third and upper course shall be assembled in the same manner as the second course. The temporary assembling of each course shall be completed in the day, and the maximum allowable numbers of shell course to be assembled temporarily shall be 3 (three) courses in case of the plate used 8 (eight) feet width and 4 (four) courses in case of the plates used 6 (six) feet width. The vertical joints of third course shall be welded before the welding of horizontal joints between second and third course. Owing to circumstances of erection schedule, welding of vertical joints of 2 (two) or 3 (three) courses may be proceeded prior to welding of horizontal joints. Assembling and welding of other upper courses shall be made as the same manner as stated before. In principle, shell plates which is higher than 5th courses shall be assembled and welded one by one course.If there were some undesirable phenomenon like a settlement of foundation during the shell assembling and welding, the level should be measured.

6.2.13

6.2.14

6.2.15

KNM Petrosab Engineering Sdn Bhd

METHOD STATEMENT FOR ERECTION AND INSTALLATION OF FIXED ROOF STORAGE TANK
6.2.16

PROJECT. NO. REVISION NO. PAGE NO.

: : :

K1202107 0 9 of 12

Provision for Wind Load, whenever the strong winds is foreknow to blow during temporary assembling, following provisions shall be made. 6.2.17 When the typhoon is anticipated to approaching during the assembling of the shell plates higher than 4th course, the plates higher than 4th course to be assembled temporarily shall be taken down to the ground. If the shell plate have been assembled up to 4th course, the channel stiffener ring shall be installed by clamping on the top periphery. The plate shall also be tied to supports on grounds by wire ropes. Top Angle, top angle shall be assembled and tack-welded after the welding of vertical joints of the shell finally and grind smoothly of vertical weld to pass through top angle. The horizontal joints between top angle and shell shall be welded finally.

6.2.18

6.2.19

6.3

INSTALLATION ROOF STRUCTURE 6.3.1 Installation of Cone Roof Installation of Rafter Lug: Mark the position of rafter lug on internal surface of top course shell plate and then welded there to. Roof Plates, roof plates shall be installed in accordance with drawing after all roof structure bolted and welded completely. Roof plates shall be laid out and tack-welded using special jigs for anti-- distortion if necessary. Tack-welds shall be made not less than 1 inch long on 20 inch center. At the continuous welding, transverse joints shall be welded first. The welding shall be started at the center of plate width and proceeded outwards symmetrically. When all transverse joints are welded, welding of the longitudinal joints shall be made from center to outward in a same manner as the transverse joints, circumferential joints between roof plates and top angle shall be welded finally.

6.3.2

6.3.3

6.3.4

KNM Petrosab Engineering Sdn Bhd

METHOD STATEMENT FOR ERECTION AND INSTALLATION OF FIXED ROOF STORAGE TANK
6.4

PROJECT. NO. REVISION NO. PAGE NO.

: : :

K1202107 0 10 of 12

INSTALLATION OF ACCESSORIES & TANK APPURTENANCES

Each tank accessories and appurtenances shall be assembled and installed in accordance with the applicable construction drawings which it have an Approval for Construction status. 6.4.1 Nozzles & Manhole

Lay out position of Nozzles/Manhole on the shell plate and roof plate. Check orientation, elevation and radius/diameter every nozzles. After approved by inspector, cut the marked area and set up reinforcing plate for each nozzles Fit up Nozzles and use temporary support for neck nozzles and also check projection flange from shell plate. Weld joint neck nozzles to shell from inside and outside tank and weld reinforcing plate to shell plate 6.4.2 Roof Handrail

Lay out position of all post handrail at around top roof plate, set up and weld each post handrail to roof plate, set up and weld pipe handrail (already bended) on the top post handrail. Set up and weld pipe handrail as middle handrail on the middle of the post handrail. Set up and weld flat bar as bottom handrail with distance 100 mm from roof plate on the bottom post handrail.

6.5

ASSEMBLING OF STEEL STRUCTURES AND APPURTENANCES

6.5.1

All appurtenances will be assembled and installed in accordanc with AFC drawing within tolerance specified in PTS 64.51.01.31 (Standard Vertical Tanks Field Erection & Testing).

6.5.2 The shell manhole opening will be made after adjustment of the level, verticality and roundness are completed, prior to the installation of 2nd course shell plates. 6.5.3 Cutting of holes for nozzles will be made upon completion of the welding of bottom to shell plate and upon approval by AIT representative after inspection.

6.5.4 When welding the manhole and nozzles, the shell plate will be reinforced with strong back to avoid possible distortion and deformation.

KNM Petrosab Engineering Sdn Bhd

METHOD STATEMENT FOR ERECTION AND INSTALLATION OF FIXED ROOF STORAGE TANK
7.0 WELDING SEQUENCE 7.1

PROJECT. NO. REVISION NO. PAGE NO.

: : :

K1202107 0 11 of 12

Welding sequence of bottom plates, shell plates and roof plates shall be as per AFC drawings.

8.0 INSPECTION 8.1 Inspection shall be carried as per Inspection and Test Plan and other applicable Procedures.

9.0 LEAK TEST 9.1 Leak test shall be carried out as per approved Hydrotest Procedure (KPE1011020Q-P-006).

KNM Petrosab Engineering Sdn Bhd

APPENDIX I (APPLICABLE INSPECTION FORMS)

KNM Petrosab Engineering Sdn Bhd

APPENDIX II (SKETCHES ATTACHMENT)

KNM Petrosab Engineering Sdn Bhd

APPENDIX III (STRUCTURAL CACULATION FOR GONDOLA CAGE)

KNM Petrosab Engineering Sdn Bhd