You are on page 1of 88

TECHNICAL SPECIFICATIONS

TABLE OF CONTENTS

DIVISION 2 - SITE WORK 02110 02200 02280 02400 Clearing of Site Earthwork Termite Proofing Site Drainage

DIVISION 3 - CONCRETE 03100 03160 03200 03300 03451 Concrete Form work Structural decking Concrete Reinforcement Cast-in-place Concrete Architectural Precast Fiber Concrete Wall panels

DIVISION 4 - MASONRY 04100 04200 Mortar Unit Masonry

DIVISION 5 - METALS 05100 05170 Structural Steel Miscellaneous Metal

DIVISION 6 - CARPENTRY 06100 06220 On-Site Carpentry Millworks

DIVISION 7 - THERMAL & MOISTURE PROTECTION 07100 07320 07400 Waterproofing Tiled Roofing Metal roofing

DIVISION 8 - DOORS & WINDOWS 08100 08510 08200 08520 08710 08730 08800 Steel Window Steel Doors Wood Doors Aluminum Windows Finish Hardware Weather Stripping Glass and Glazing

DIVISION 9 - FINISHES 09220 09310/90 09340 09390 09610 09650 09900 Cement Finishes Ceramic & Cement Tilework Marble Finish Cement Tile Pebble Washout Finish Vinyl Floor Finish Painting

DIVISION 10 - SPECIALTIES 10521 10820 Fire Extinguishers Toilet Accessories

DIVISION 11 - MECHANICAL 11320 11400 Laboratory Gas Piping System Plumbing Works

DIVISION 1 2 - ELECTRICAL WORKS

DIVISION 2 - SITEWORK

SECTION 02110 PART 1 1.01

CLEARING OF SITE GENERAL SCOPE Furnish equipment and perform labor required to complete removal of salvage materials, disposal of resulting trash, waste, timber stumps, and other vegetation. See drawing for area covering of work involved.

1.02

PERMITS Secure and pay for all necessary permits required for the work.

1.04

PROTECTION Protect adjacent properties, persons, shrubs, trees, lawn, structures, and utilities therein against harm or damage.

PART 2 2.01

EXECUTION DEMOLITION a. Demolish and remove from site existing structures and other obstructions within the building area as indicated in the plans. Where existing concrete on ground is to be demolished. Remove all existing concrete and other obstructions to a depth of 0.60 meter below grade. Cap all existing utility lines, consult owner before commencing work.

b.

c. 2.02

CLEARING AND GRUBBING a. Uproot trees or cut down as shown in the plans or as directed by the Architect.

2.03

REPAIRS a. Repair damages done to property of any person or persons or off the premises, by reason of the required work for demolition, Clearing and Grubbing.

54

SECTION 02200 PART 1 1.01

EARTHWORK GENERAL SCOPE a. Furnish material and equipment and perform labor required to complete Stripping Site grading Excavation Trenching Backfilling Compaction Dewatering b. See drawings for location and extend of work required.

1.02

VERIFICATION OF EXISTING CONDITIONS a. Verify and examine the site of work to familiarize with the character of materials to be encountered and all other existing conditions affecting the work.

1.03

PROTECTION a. Provide adequate protection measures to protect materials, men and adjoining property. Provide shoring, sheeting and bracing to prevent carving, erosion or gullying of sides of excavation. Provide for surface drainage during the period of construction in such manner as to avoid creating a nuisance to adjacent areas. Keep all excavation free of water at all times.

b.

c.

PART 2 2.01

PRODUCTS MATERIALS a. Select fill material shall be laboratory approved from off site source, passing a 75 mm (3 in.) sieve. The fraction passing a C.425 mm (No. 40) sieve shall have a liquid limit not exceeding 35% and a plasticity index not exceeding 12% Granular fill gravel base to form a capillary water barrier shall be clean crushed non-porous rock; crushed or uncrushed gravel,

b.

55

uniformly graded and of a size which will pass a 1-inch mesh screen and be retained on a No. 4 mesh screen. c. Excavated material approved for use as backfill shall be free of stones larger than 50 mm in longest dimension, roots and organic materials.

PART 3 3.01

EXECUTION STRIPPING a. Strip top soil only in areas required as shown in the plans. Remove top soil to depths indicated or as required by the Architect but in no case less than 100 mm in depth, prior to start of regular excavation or backfilling work. Stock pile the removed top soil separate from other excavated materials in locations designated by the Architect and or spread and compact with a light roller in areas indicated in the plans or where directed by the Architect.

b.

3.02

SITE GRADING a. Cut & fill and machine grade the site area. Deposit materials in horizontal layer not exceeding 200 mm in depth and compact in accordance with method A of ASTM D 1557-667. Rough grade elevations and levels shall be approximately 150 mm below the bottom of the slabs on grade, 250 mm below finish grades in areas to be lawn seeded or landscaped.

3.03

STAKES AND BATTER BOARDS a. b. Stake out building accurately and establish grades. Batter boards and reference shall be erected at location where they will not be disturbed during the construction. Construct two permanent bench marks of previously known elevations near the site of construction.

c.

3.04

EXCAVATION a. Excavate to the dimensions and elevations indicated on the drawings. Carry excavation to depths directed by the Architect should unsuitable bearing be encountered at elevations indicated. Excavation carried to a greater depth or size indicated or required through error, shall be corrected by filling such additional depth or size with lean concrete.

b.

56

c.

Bottoms of excavation shall be level, free from loose material, and brought to indicated or required levels in undisturbed earth or in compacted fill. Excavate with proper allowance made for floor slabs, form erection, shoring, drain tile, waterproofing, masonry and adequate space for inspection of foundations.

d.

3.05

DEWATERING a. Control grading around building so that ground is pitched to prevent water from running into excavated areas of buildings or damaging other structures. Pump water out of excavate areas throughout the construction, water shall not be conduced into adjacent developed property.

b.

3.06

TRENCHING FOR SUB-DRAINAIGE a. Excavate trenches for underground utility system and drain grade and tamp to provide firm bed trenches for drain lines. lines,

b.

When rock is encountered, excavate to a depth of 150 mm below the bottom elevation of the pipe and fill with sand and gravel or crushed stones thoroughly compacted before laying pipe.

3.07

BACKFILLING a. Prior to backfilling around structures, remove all forms, trash and debris. Use only approved backfill material and place symmetrically on all sides in layers, moistened in accordance with item 3.09 of this section. Backfill around structures only after the concrete has attained sufficient strength to resist lateral pressure resulting from the backfill.

b.

3.08

SOIL COMPACTION a. All existing earth within building lines that has been disturbed shall be placed in 150 mm layers and compacted to 95% of maximum density at optimum moisture content required for fill in accordance to AASHO method.

3.09

DISPOSAL OF EXCAVATED MATERIAL a. Surplus material resulting from all earthwork operations not required or unsuitable for fill or backfill shall be disposed off.

57

PART 4 4.01

SOIL BEARING CAPACITY If during excavation, conditions discovered at the site does not conform to the findings of the "SOILS INVESTIGATIONS REPORT" submitted by the soil engineer, the owner shall immediately notify the architect or his representative, in writing, of such conditions. The soil engineer and the structural engineer shall visit the site and make the changes in foundation design as necessary. No footing shall rest on fill unless directed otherwise by the structural engineer.

4.02

4.03

58

SECTION 02280 PART 1

TERMITE PROOFING : Bukbok Proofing GENERAL SCOPE OF WORK The owner shall hire the services of the specified pesticide company to furnish all labor, materials, equipment, tools, plants, and services to complete the termite proofing and bukbok proofing work hereinafter described.

PART 2

PRODUCTS CHEMICALS AND EQUIPMENT For termites, use only "CHLORDANE" diluted with water at the proportion of ONE (1) PART CHLORDANE to FIFTY (50) parts water. Dilution shall be done at the job site in the present of the owner's Project Engineer or the Architect. Use MOTORIZED POWER SPRAYERS ONLY. For bukbok, use pentachlorophenon (with organs chlorine) colorless, and at ratio 1:100.

PART 3 3.01

EXECUTION APPLICATION AND TREATMENT a. Foundation Treatment Prior to pouring foundations, apply ONE (1) gallon of the prepared mixture per linear meter of all excavations for footings, foundations, around sewer pipes, conduits and other concrete works. b. Backfill Treatment Apply another ONE (1) gallon per linear meter of all backfill materials as it is being replaced into the trenches after the footing slab are poured. c. Floor Slab Treatment Prior to pouring concrete slabs apply ONE (1) gallon per square meter as an overall treatment. d. Other Areas Treat all voids found in masonry walls such as in concrete blocks and to all surfaces as in concrete blocks and to all surfaces before veneer finishes are place with ONE (1) gallon per linear meter. PVC pipes should be treated with powder form Aldrin.

59

e.

Wood Drenching Ceiling joists, runners, nailers, etc. wherein untreated lumber is used shall receive treatment as deemed necessary by the termite proofing subcontractor.

f.

Termite Mounds Demolish and treat all termite mounds within the property if any.

g.

Bukbok Proofing Kiln dried wood, plywood, tanguile, lauan, apitong, cabinets, dividers and paneling shall be brush with bukbok proofing chemicals before painting or varnishing.

3.02

WARRANTY The termite proofing work herein called for shall be guaranteed for a minimum of FIVE (5) years with free semi-annual check-ups and retreatment in case of infestation.

60

SECTION 02400 PART 1 1.01

SITE DRAINAGE GENERAL SCOPE Furnish materials and equipment and perform labor required to complete the storm drainage external to the building.

1.02

PROTECTION Protect materials from loss, injury or defacement. Lost or damaged materials shall be replaced by the contractor at his own expense.

PART 2 2.02

PRODUCTS MATERIALS a) Drainage pipes: 1. Plain concrete drain pipe and fittings 10 in. and below in diameter: T & G conforming to ADTM C-14-59. Reinforced concrete drain pipes fittings 12 in. and bigger: Centrifugally cast or vibrated, T & G conforming t o - A S T M C-76-59 T.

2.

b) c)

Joining material - one part cement to two parts sand. Building storm drain connection to main-concrete wye branch and clean out, T & G or used junction boxes. Area drain catch basin - load - bearing 4.8 Mpa (700 PSI) concrete hollow blocks (CHB) or reinforced concrete as indicated in the drawings with steel grating.

d)

PART 3 3.01

EXECUTION EXCAVATION a) Excavation trenches for all underground pipe lines to required depths, slope and trades. Rest/pipes on well tamed solid bedding along its entire length. Lay water and sewer pipes in separate trenches. See SECTION 02200 : EARTHWORK, ITEM 3.06.

b) c) d)

61

3.02

BACKFILLING a) Pipe lines shall be tested by contractor and by Owner's representative prior to backfilling. Clean and free all excavation from trash and debris. Backfill shall consist of the same material excavated or other approved materials. Free backfill of the debris and big stones. Place backfill in horizontal layers not exceeding 300 mm or as indicated or directed. Properly moisten each backfill layer and compact by hand or machine to an optimism density that will prevent excessive settlement and shrinkage.

b) c)

e)

62

DIVISION 3

CONCRETE

SECTION 03100 PART 1 1.01

CONCRETE FORMWORK GENERAL SCOPE a. Furnish materials and equipment and perform labor required to complete all cast-in place concrete form work. All work shall be done in accordance with the minimum requirements of the AMERICAN CONCRETE INSTITUTE BUILDING CODE FOR REINFORCED CONCRETE ACI 318-88 except as modified herein. Refer to the general conditions for all pertinent provisions.

b.

c. 1.02

PROTECTION a. Provide adequately braced forms that will produce correctly aligned concrete, able to meet the specific weights and side pressure of newly placed concrete. Choose form fittings that are adequate to the purpose. Exercise care in the choice of the surface forms and form fittings that will be in contact with concrete.

b. c.

PART 2

PRODUCTS MATERIALS Forms 1. Use the plywood, metal, or surfaced lumber forms where it will best give the most advantage in the specific concrete work involved. For the beams and columns, use not less than (12mm thick) plywood forms for exposed concrete and 20mm T & G for covered concrete.

2.

PART 3 3.01

EXECUTION PREPARATION a. Check all forms to the shape, lines and dimensions of the members as called for in the plans.

63

b. c.

Check all formwork for plumbness and correct alignment. Provide openings in column forms for cleaning and inspection preferably at lowest points of pour lifts. Provide camber for cantilever and long spans or as indicated in the construction notes. Coat all forms with form oil before reinforcement is placed. Remove all surplus oil on forms.

d.

e.

3.02

FORMS AND SHORING a. Removal Removal forms only upon approval of the Engineer in such manner and at such time as to insure the complete safety of the structure. In no case shall the supporting forms and shorings be removed until the members have attained sufficient strength to support safely their weight and load thereon. The results of suitable control tests shall be used as evidence that the concrete has attained sufficient strength to permit removal of shorings and supporting forms. Cylinders required for control tests shall be made in addition to those required by this specifications.

3.03

TOLERANCE LIMITS a. Set and maintain concrete forms so as to insure completed work within the following tolerance limits. Variation from the plumb In the lines and surfaces of columns, piers, walls and rises: In 3 meters In any storey or 6m max II 6mm 10mm

1.

For exposed corner columns, control joints, groves and other conspicuous lines: 6mm 12mm

In any way 6m or more In 12m or more

64

2.

Variation from the level or from the grades indicated on the drawings: I. In floors (before removal of forms), ceiling beams, soffits and rises: 6mm 10mm 10mm

In 3m In any way or 6m max In 12m or more 3.

Variation of the linear building lines from the established position in plan and related position of columns, walls and partitions: In any way or 6m max In 12m or more 12mm 25mm

4.

Variation in the sizes and location of sleeves, floor openings and in thickness of slabs and wall openings . . . . 6mm Variation in cross-sectional dimensions of columns and beams and in thickness of slabs and walls: Minus Plus 6mm 12mm

5.

6.

Footings I. Minus Plus Variation of dimensions in plan 12mm 50mm

(applies to concrete only and not to reinforcing bars or dowels.) II. Misplacements of eccentricity, 5% at the footing width in the direction of misplacement but not to exceed 50mm (applies to concrete only and not to reinforcing steel and dowels) Reduction in thickness: 5% of specified thickness

III. Minus 7.

Variation in steps: I. Rise . . Thread In a flight of steps: 3mm 6mm

65

II. Rise Thread

In Consecutive steps: 2mm 3mm

DIVISION 3 - CONCRETE

SECTION 03160 PART 1 1.01

STRUCTURAL DECKING GENERAL SCOPE a. Furnish materials and equipment and perform labor required to complete all structural decking for all suspended slab in accordance with the drawings. All work shall be done in accordance with the minimum requirements of the AMERICAN INSTITUTE BUILDING CODE FOR REINFORCED CONCRETE ACI 318-88 as positive reinforcement for composite slab and as per Manufacturer's specifications.

b.

1.02

PROTECTION Handling and Storage a. b. Stack panels clear of the guard of the ground with a fall or drainage. Protect panels with waterproof covering ensuring space is left between the cover and panels to allow air to circulate.

c.

Care must be taken when lifting long length bundles and it is recommended that several lifting points be utilized to prevent buckling. When removing individual sheets from bundles, they should be lifted directly and not dragged. Provide adequate protection against corrosion through painting of corrosion inhibiting coats such as epoxy polyurethane type.

d.

PART 2

PRODUCTS MATERIALS The decking shall be cold formed section manufactured from high strength hot dipped zinc galvanized steel of 0.75mm thickness in accordance with ASTM A446 Grade E and ASTM A525 G90. The base steel shall have a minimum yield stress of 550 Mpa and minimum coating mass of 275 gsm. - 0.75mm thick CONDECK Panels by Construction Decking System International Corporation or equivalent. In case of other systems, submit technical literature and sample to the Engineer for review and

67

appropriate design modification. PART 3 3.01 EXECUTION INSTALLATION

Cutting and Openings Structural decking can be cut using a power saw with suitable disk. When cutting, the panels should be turned over with the ribs downward. If holes or openings are required, these are classified as follows: a. Less than 250mm (measured at right angles) requires no special treatment. These holes or openings are usually for passage of other trades or alternately they can be formed prior to the concrete pour, and once the concrete has attained 70% of its design strength, the panel can then be cut out by a hole saw or drill. For openings of 250-750mm the decking can be reinforced prior to the concrete pour by using reinforcing bars or small channels, welded to the panel around the perimeter of the opening; this distributes the loads to the adjoining panels. For large predetermined openings greater than 750mm, such as for stairs, elevators, etc., the most practical method generally is to supply supplemental framing to the support system for the structural decking.

b.

c.

Fixings Deckings shall be accurately aligned, side laps fully lapped and the gap between the abutting ends kept to a minimum. Panels should be aligned over the support ensuring a minimum end bearing of 50mm by sliding them into place with adjacent panels hard up against the precious one and the rib overlapping the adjacent panel's rib. After panels have been placed over the supports, they should be secured immediately against wind lift. Where panels are acting as a work platform, care should be taken not to overload panel after they have been erected. Heavy points should be distributed by means of timber planking. Fix panels by use of nail directly to beam formwork. Propping One or two lines of temporary props may be required in accordance with manufacturer's recommendation or as shown in the drawings. Propping shall consist of timber supported by a line of props adjusted to prevent settlement during the concrete placement and curing. The propping must be designed to support the weight of wet concrete plus a temporary construction load.

68

Provide caneite or similar materials between the props and panels to reduce the effect of propping line since the exposed soffit will be used as ceiling. Propping may be erected before or after the installation of the decking and should be left until the concrete has reached sufficient strength of at least 70% of its design strength. Side Lap Joints Side lap shall be fastened by 16mmXgalO Hex head self drilling and tapping screws which can be placed either through the side or through the top of the ribs at quarter points of the span. 3.02 Negative and Secondary Reinforcements Negative and secondary reinforcements shall be provided in accordance with the drawings. Sufficient tied lap splices shall be provided in both direction. 3.03 Inspection No concreting shall begin until lapping, reinforcement placement and connectors have been inspected and approved by the Engineer. 3.04 Concrete Placing Decking panels must be clear of grease, oil and dirt. The concrete should be placed continuously and if the placing is interrupted, the construction joints should be provided by stop boards located over supporting beams. The concrete should be placed in accordance with Section 03300 of this specifications. In addition, pouring shall be done parallel to the panels, this is very important!

69

SECTION 03200 PART 1 1.01

CONCRETE REINFORCEMENT GENERAL SCOPE a. Furnish materials and equipment and perform labor required to complete steel reinforcing bars bars supports and miscellaneous reinforcement accessories b. All pertinent provisions of the General Conditions form part of this section.

1.02

PROTECTION AND STORAGE Protect steel reinforcement adequately from rusting and store under cover.

1.03

TESTING Test shall conform to ASTM Designation of specified materials.

PART 2 2.01

PRODUCTS MATERIALS a. Steel Bars 1. 2. Shall be new and free from rust, oil, grease, defects or kinks. Shall conform to the latest edition of ASTM Designation A615 Specification for Deformed Billet Steel Bars for Concrete Reinforcement. Minimum yield strength shall be 275 Mpa for main bars including column ties, slab rebars and 230 Mpa for beam stirrups of 10mm dia. and lower.

PART 3 3.01

EXECUTION PREPARATION a. Before placing reinforcement and before pouring of concrete, remove all loose rust, mill scale, oil, or other adhering materials which tend to reduce or destroy bond between concrete and reinforcement. All bars shall be bent cold. Bends for stirrups and ties shall shall be made around pins with & diameter of at least twice the thickness of

b.

70

the bars; for bars 25mm and smaller, six times the thickness; for larger bars, eight times the thickness. 3.02 PLACING REINFORCEMENT a. Metal Reinforcement 1. Placing shall be in accordance with the plans furnished. Refer to the Engineer in case of doubt in placing of steel. Reinforcing bars shall be accurately placed and adequately secured with concrete metal wires, or metal chair spacers. Wire mesh reinforcement where shown in slabs shall be secured in position by spacer bars and chairs. Spacer bars shall be lapped not less than 125mm. In slabs on ground, precast concrete blocks may be substituted for chairs.

2.

3.

b.

Bar Spacing 1. Spacing of bars shall be done in accordance with the ACI Building Code or as follows: Clear distance between parallel bars shall be one and one half (1 Vi) times the diameter of the bars. 2. Clear distance shall not be less than 11/3 times the maximum size of aggregate, nor less than 25mm. Where bars are used in two or more layers, the bars in the upper layers shall be placed directly above those in the lower layers at a clear distance of not less than 25mm.

3.

3.03

OFFSET AND SPLICE REINFORCEMENT a. Splices 1. Generally, avoid splices in slabs, beams and girders at points of maximum stress. Splices may be allowed only as shown or noted in the plans. Splices in adjacent bars shall be staggered a minimum distance of forty (40) bar diameters.

2.

b.

Offsets Where changes in cross section of columns occurs, longitudinal bars shall be offset in a region where lateral support is afforded.

71

Where offset, the slope of the included portion shall not be more than one on six (1:6) and in case of tied columns, the ties shall be spaced 75mm on center for a distance of 300mm below and above the point of offset.

72

SECTION 03300 PART 1 1.01

CAST-IN PLACE CONCRETE GENERAL SCOPE a. Furnish material and equipment and perform labor required to complete proportioning mixing placement curing and finishing of concrete b. All pertinent provisions of the General Conditions form part of this section.

1.02

PROTECTION & STORAGE a. b. Cement - Store dry, watertight, properly ventilated structure. Aggregate - prevent from inclusion of foreign matter. Maintain storage piles in a manner that will afford good drainage. Prevent segregation of particle size.

1.03

DESIGN STRENGTH OF CONCRETE All strength of concrete shall be at least 24 Mpa for slabs, stairs, beams, columns, tie beams, and footings, and 21 Mpa for slab on fill, and 10 Mpa for temporary encasement of dowel bars for all roof/floor/tie beams towards phase 2 area, or as indicated on the Construction Notes.

1.04

TESTING AND ACCEPTANCE Testing and acceptance shall conform to applicable sections of ACI 318-88 and as specified below.

PART 2 2.01

PRODUCTS MATERIALS a. Cement Use only one brand of cement throughout. Portland cement shall conform to the Standard Specifications for Portland Cement (ASTM Designation C-150-latest revision) for type 1 Portland Cement.

73

b.

Concrete Aggregates 1. Use well graded, clean hard particles or gravel or crushed rock conforming to the "STANDARD SPECIFICATIONS FOR CONCRETE AGGREGATES" (ASTM Designation C-33 latest revision). Maximum size of aggregate shall not be larger than 1/5 of the narrowest dimension between sides of the forms nor larger than 3/4 of the maximum clear spacing between reinforcing bars, and in no case larger than 33mm in diameter. Refer to Construction Notes.

2.

c.

Water Use water that is clean and free from injurious amounts of oils, acids, alkali, organic materials or other deleterious substances.

d.

Concrete Additives Additives shall subject to approval of the Engineer. Submit technical specifications of the proposed additives.

2.02

METHOD OF DETERMINING CONCRETE STRENGTH AND PROPORTIONS a. Submit mix designs obtained from samples made in accordance with "STANDARD METHOD OF MAKING AND CURING CONCRETE COMPRESSION AND FLEXURE SPECIMENS" (ASTM Designation C192) and "STANDARD METHOD OF TEST COMPRESSIVE STRENGTH OF MOLDED CONCRETE CYLINDERS" (ASTM Designation C-39) for each strength required stating the proposed slump and the proportional weights of cement, saturated surface dry aggregates, and water. These mixes shall be proved by preliminary tests sufficient time before concreting and shall show a 28 day strength of 15 percent higher than the ultimate required. No substitution shall be made in the materials or mix without additional tests to show that the quality of concrete is satisfactory.

2.03

CONCRETE PROPORTIONS AND ACCURACY a. Cement and Aggregates Make proportions so as to produce a concrete mixture which work readily into the corners and angles of the forms and around reinforcement with the method of placing materials to avoid segregation or accumulation of excess free water on the surface.

74

b.

Measurement 1. Measure concrete materials such that the proportions can be accurately controlled and easily checked at any time during work. Conform measurement of materials for ready mixed concrete to STANDARD SPECIFICATIONS FOR READY-MIXED CONCRETE. ASTM Designation C-94, where applicable. Never exceed the water content by 6 U.S gallons per bag of cement for all portions in the structure. Allow the job mix adjustment of water content only on permission of the Architect provided that cement is also added to keep the original water-cement ratio of the design mix. Limit slumps to the following: Portion of Structures Columns, beams, slabs Foundation elements, bedded slabs and cantilevered beams and slabs. Slump (mm) 75-150 50-125

2.

3.

2.04

MIXING CONCRETE a. No hand mixing shall be allowed except in case of emergency such as mixer breakdown during pouring operations and shall stop at first allowed construction joint. All concrete shall be machine mixed for at least 1 >2 minutes after all materials including water are in the drum. Let the mixer be of an approved size and type which will insure a uniform distribution of material throughout the mass. Equip it with a DEVICE FOR ACCURATELY MEASURING AND CONTROLLING THE AMOUNT OF MIXING WATER IN EACH BATCH. Place the materials in mixer in such a way that first batch of concrete materials shall contain sufficient excess of cement, sand, and water to coat the inside of the drum without reducing the cement content of the mix to be discharged. Never permit retempering of concrete.

b.

c.

d. PART 3 3.01

EXECUTION PREPARATION a. Inspect and clean all forms and check all installations before placing

75

concrete. b. c. Wet surfaces thoroughly and grout before placing concrete. Clean all laitance from previous pouring and possibly before renewing pouring. aggregates

3.02

DEPOSITING CONCRETE a. Do depositing without segregation, rehandling or flowing of concrete. Do it with the use of buggies, buckets, or wheelbarrows. Never allow use of chutes except to transfer concrete from hoppers to buggies, wheelbarrows or buckets in which case shall not exceed 6m in aggregate length. In placing concrete, never let it drop freely for a height exceeding 1.5m. Keep conveyors full of concrete and keep ends buried in the newly placed concrete as pouring progresses. Never allow placing of concrete without vibrators. Avoid segregation due to over vibration. Construction Joints 1. If possible, do concreting continuously, until section is complete. When stoppage of concrete operations occur, place construction joints either horizontally or vertically as indicated by the Engineer and be provided with shear keys or dowels to develop bond. Consult drawings and/or Engineer as to details of construction joints.

b.

c.

d.

e.

2.

3.03

CURING CONCRETE a. Finished Surface 1. Keep concrete continuously wet or moist for at least one week after placing. Begin curing as soon as concrete has attained initial set. Spray floors and vertical surface with an approved curing compound.

2. 3.

b.

Use curing additives for a minimum of 48 hours.

76

3.04

REPAIR OF CONCRETE a. Imperfections 1. 2. 3. Complete repair within 24 hours after removal of forms. Remove fins neatly from exposed surfaces. Removed damaged or honeycombed concrete and replace with drypack, rich mortar or concrete with pea gravel to produce a sound one.

b.

Large Bulges Remove large bulges and abrupt irregularities by bush hammering and grinding.

c.

Drypack Filling 1. Use for holes having at least one surface dimension less than the depth of the hole. Fill with drypack holes left by the removal of fasteners from the ends of tie rods; for grout and pipe recess; and for narrow slots cut for repair of cracks. Never use drypack for filling behind reinforcement and for filling holes that extend completely through the concrete.

2.

3.

d.

Use mortar filling placed under impact of mortar gun as drypack filling for holes to shallow for concrete filling and these holes should be no deeper that the far side of the reinforcement nearest the surface. Concrete filling shall be used for: holes extending entirely through the concrete for holes which are greater in the are than 1,000 square centimeter and deeper than 10 centimeter and for holes in reinforced concrete which are greater in area than 500 square centimeters and which extend beyond reinforcement. All materials, procedures and operations used in the repair of concrete shall be as directed. Fillings shall be bonded tightly to the surfaces of the holes and shall be sound and free from shrinkage, cracks and dummy areas, after the fillings have been cured and dried.

e.

f.

g.

77

3.05

FLOOR FINISHES Prepare slabs suitable in surface and elevation to receive finishes. Consult Division 9 for finishes and its application.

3.06

TEST OF CONCRETE A number of tests on concrete is required during the progress of the work. At least four cylindrical specimens shall be made for each test of which two shall be reserved for the 28-day test. At least one test shall be made for each day's concreting. Samples shall be secured and molded in accordance with ASTM Specification C172 and C31. The average strength of test samples representing each class of concrete shall be equal to or greater than the specified strength and not more than one test in ten shall have an average value less than 90% of the specified strength.

78

DIVISION 4 - MASONRY

SECTION 04100 PART 1 1.01

MORTAR GENERAL SCOPE Furnish materials and equipment and perform labor required to complete plaster, masonry work and patching mortar as shown in the drawings and specified in the Summary of Materials and Finishes herewith.

PART 2 2.01

PRODUCTS MATERIALS a. b. c. Sand: ASTM 35-67 Portland Cement: ASTM C-150-67, Type 1 Water: clean and free from deleterious substances.

2.02

MIXES Cement 1 part Portland Cement 2 parts sand, but not more than 1 part Portland cement 3 parts sand

PART 3

EXECUTION Installation a. 1. Application of Cement Plaster Scratch Coat: Apply with sufficient force and materials to form full keys or bond. Cross scratch as soon as scratch has attained initial set and apply brown coat as soon as practicable. Brown Coat: Scratch or broom for bond of finish coat and allow to set hard. Keep brown coat moist until finish coat is applied.

2.

79

3.

Finish Coat: Bring to true, even surface with rods, dries and trowel smooth, leaving finished surface free from tool marks and blemishes. Keep cement plaster moist for at least 3 days and protect against rapid drying until cured. Application of masonry mortar Lay all solid and structural red bricks with 10mm thick horizontal and vertical mortar joints.

b.

c. 1.

Application of patching mortar Provide the same mixture of gray and white cements for patching mortar used to fill holes and imperfections, but should be a stiffer mixture and the cement and sand proportions should be the same as those used in the concrete. Never steel trowel patches, but finish with wood or cork floats. Allowing the mixed patching mortar to stand for an hour or two before using it reduces the amount of shrinkage but never add water in remix it.

2. 3.

80

SECTION 04200 PART 1 1.01

UNIT MASONRY GENERAL SCOPE Furnish materials and equipment and perform labor required to complete unit masonry as indicated in the drawings, but not necessarily limited to interior and exterior concrete block walls.

1.02

HANDLING AND STORAGE a. b. Handle in a manner to prevent undue chipping and breakage. Provide platforms to protect bottom piles from contact with soil.

1.03

SUBMITTALS : a. Samples: Within 35 days after award of contract, and before any concrete unit masonry materials are delivered to the jobsite, submit one sample of the proposed concrete masonry units with the name and address of the manufacturer to the Architect for his approval. b. Certification : Upon delivery of concrete unit masonry to the jobsite, deliver to the Architect a copy of the manufacturer's invoice stating among others, quantity and designed strengths of the concrete masonry units delivered to the jobsite.

PART 2 2.01

PRODUCTS MATERIALS 1. NON-LOAD BEARING CONCRETE HOLLOW BLOCKS : All non-load bearing concrete hollow blocks used in non-load bearing masonry shall conform to the requirements of ASTM C-129-39, with a minimum compressive strength of 400 psi. a. b. 150 X 200 X 400mm CHB 100 X 200 X 400mm CHB

81

2.

MORTAR All mortar for concrete block shall conform to ASTM C-476-71, 2500 psi in 28 days, and shall consist of one part portland cement by volume, 1/4 part hydrated lime, and 3 parts of damp, loose sand, plus water.

3.

REINFORCEMENT STEEL: All reinforcement steel for concrete masonry units shall be structural grade, billet steel deformed bars conforming to the requirements of ASTM A-615 with yield strength of 230 Mpa.

4.

WATER : Water used in mixing mortar shall be clean and free from injurious amounts of oils, acids, alkalies, salts, organic materials, or other substances that may be deleterious to concrete or steel.

5.

GROUT: All grout shall be machine-mixed in accordance with ASTM C-94 and shall consist of one part portland cement, 2 1/2 parts sand, 2 parts pea gravel, and adequate water to produce a concrete of approximately ten inches slump, and shall have an ultimate compressive strength of 2000 psi in 28 days.

6.

ADMIXTURES: Admixtures may be used only with the written approval of the Architect.

PART 3 3.01

EXECUTION MIXING MORTAR : a. 1. 2. General: Use a mechanical mixer of one bag minimum capacity. Mix mortar at least three minutes after all materials have been added. The actual mixing shall not be less than two minutes. Mix only as much mortar as can be used in one hour after water has been first mixed into the batch.

3.

82

b.

Retempering: Do not retemper mortar.

3.02

INSTALLATION : a. 1. General: Lay up all walls in running bond, plumb, level, and true to the lines and dimensions indicated on the Drawings. Do not used chipped or broken units; if any such units are discovered in the finished wall, the Architect may require their immediate removal and replacement with new units at no additional cost to the Owner. Dampening: Dampen, but do not saturate, immediately before installation. c. 1. 2. Laying Up : Place all units in mortar with full shoved bed and head joints. Align all vertical cells to maintain a clear, unobstructed system of flues. Provide clean-outs at the bottom of each cell for removing mortar droppings; do not close the clean-outs until they have been inspected and approved by the Architect. Reinforcement : Install all reinforcement as indicated on the Drawings. Embed reinforcement in grout, not in mortar or mortar joints. Tooling: Tool all joints to a dense, smooth surface. all concrete masonry units,

2.

b.

3.

d. 1. 2. e.

83

3.03

GROUTING : a. General: Perform wall grouting in strict accordance with the provisions for high lift grouting as described in Chapter 24 of the Uniform Building Code, 1970 edition. b. Timing: Do not grout until masonry has cured at least 24 hours. Consolidation: Consolidate all grout at time of pouring by puddling with steel rod, filling all cells of the masonry, and then reconsolidating later by puddling before the plasticity is lost.

c.

3.04

CLEANING UP : a. Inspection and Adjustment: Upon completion of the work of this Section, make a thorough inspection of all installed concrete unit masonry and verify that all units and all joints have been installed in accordance with the provisions of this Section; make all necessary adjustments. b. 1. Cleaning: Clean all surfaces of the concrete unit masonry as required for proper application of the specified finishes. Upon completion of all work of this Section, promptly remove from the jobsite all mortar droppings, broken units, debris arising from work of this Section, and all tools and equipment of this Section, leaving all areas in a neat and orderly condition to the approval of the Architect.

2.

84

DIVISION 5 - METALS

SECTION 05100 PART 1 1.01

STRUCTURAL STEEL GENERAL SCOPE Furnish material and equipment and perform labor and services required to complete fabrication and erection of all structural steel.

1.02

SHOP DRAWINGS a. In accordance with the requirements of the General Conditions, furnish complete detailed fabrication and erection shop drawings including details of all connections for review and approval of the Architect.

PART 2 2.01

PRODUCTS MATERIALS a. Conform all materials and workmanship to the requirements of the American Institute of Steel Construction, "Specifications for Design, Fabrication and Erection of Structural Steel for Buildings" as amended to date or as may be specifically modified by the drawings or by these specifications. Conform structural steel plates and shapes to ASTM Designation A33 with a specified yield point of 230 Mpa. Conform welding electrodes for manual shielded metal-arc welding to E60 series of ASTM Specifications A233 and to AWS Specification A5.1 & A5.5. Conform bolts to the specification for Low Carbon Steel Externally and Internally Threaded Standard Fasteners, ASTM A307. Use only approved brand of red lead paint and linseed oil for all shop painting for structural steel.

b.

c.

d.

e.

85

PART 3 3.01

EXECUTION WELDING TECHNIQUE a. Conform the technique of welding employed, the appearance and quality of welds made, the methods used in correcting defective work to the requirements of the Standard Code for Welding in Building Construction of the American Welding Society. Make surface to be welded free from scale, slag, rust, grease, paint and any other foregoing material except that mill scale which withstands vigorous wire brushing may remain. Prepare edges by gas cutting, whenever practicable, cut by a mechanically guided torch. Let gas cut edges which will be subjected to substantial stress or which are to have weld metal deposited on them be free from gouges. Remove by grinding any gouges that remain from cutting. Shape all re-entrant corners notch free to be a radius of at least 12mm. Bring in to a close contact as practicable parts to be fillet welded and in no event separate by more than 5mm. If the separation is 1.5mm or greater, increase the size of the fillet welds by the amount of the separation. Never exceed the separation between laying surfaces of lap joints and butt joints on a backing structure by 1.5mm. Bring the fit of joints at contact surfaces which are not completely sealed by welds, close enough to exclude water after painting. Align all abutting parts to be welded carefully. Correct misalignment greater than 3mm and in making the correction, never draw parts into a slope sharper than two (2) degrees (11mm in 300mm). Position the work for flat welding whenever practicable. In assembling and joining parts of structure or of built-up members, avoid needless distortion and minimize shrinkage stresses. Where it is impossible to avoid high residual stresses in the closing welds of a rigid assembly, make closing welds in compression elements. In the fabrication of cover plated beams and build-up members, make all shop splices in each component part before such component part is welded to other parts of the member.

b.

c.

d.

e.

f.

g.

h.

i.

j. k.

I.

86

m.

Let all complete penetration butt welds by manual welding except when produced with the aid of backing material or welded in the flat position from both sides in square-edge material not more than 8mm thick with opening not less than one-half the thickness of the thinner parts joined, have the root of the initial layer gouged out on the back side before welding is started on that side. Weld so as top secure sound metal and complete fusion throughout the entire crosssection. With butt welds made with use of a backing of the same material as the base metal, have the weld metal thoroughly fused with the backing material. Backing strips may be removed by gouging or gas cutting after welding is completed, provided no injury is done to the base metal and weld metal. Terminate butt welds at the ends of a joint in a manner that will ensure soundness. Where possible, do by the use of extension bars or run-off plates. Remove extension bars or run-off plates upon completion of the weld. Make the ends of the weld smooth and flushed with abutting parts.

n.

o.

3.02

BOLTS a. Tighten all bolts to a bolt tension not less than the proof load given in the applicable ASTM Specifications for the type of bolt used. Do not tightening with properly calibrated wrenches or by the turn-of-nut method.

b.

3.03

TOLERANCES a. Let all structural members of single rolled shape and built-up members fabricated by riveting or welding, unless otherwise specified, be straight within the tolerances allowed by ASTM Specification A6. Never let compression members deviate from straightness by more than 1/100 of the axial length between points which are to be laterally supported. Let completed members be free from twists, bends and opens joints. Sharp kinks or bends shall be the cause of rejection of materials.

b.

c.

3.04

SHOP PAINTING a. Clean all steelwork specified for painting by hardware brushing, or other methods chosen by the fabricator for cleaning loose mill scale, loose rust, weld slag, or flux deposit, dirt and other foreign matter

87

after inspection, approval, and before leaving the shop. b. Give all steelwork except those to be encased in concrete one coat of shop paint. Remove oil grease deposits by solvent. Do not paint steelwork that is to be encased in concrete. Clean oil or grease or with solvent cleaners. Remove dirt and foreign materials by thorough sweeping with a fiber brush.

c. d.

3.05

INSPECTION a. Subject material and workmanship at all times to the inspection of the Architect. Inspection of welding shall be performed in accordance with the provisions of Section 6 of the Standard Code for Welding in Building Construction of the American Welding Society. Test - Non destructive tests shall be used if necessary to determine the distribution of weld defects. 1. Radiographic inspection or Ultrasonic inspection.

b.

c.

3.06

IDENTIFICATION a. Mark to identify components. the ASTM Specifications of steel for main

b.

Identify such steel in completed members or assemblies by painting the designation of the piece over any shop coat of paint, prior to shipment from fabricator's plant.

88

SECTION 05170 PART 1 1.01

MISCELLANEOUS METALS GENERAL SCOPE Furnish material and equipment and perform labor required to complete all metal work which include: a. b. c. d. Steel gussets, sag rods, turnbuckles, shear plates, erection plates and angles, etc. for roof framing system Steel windows and grilles Steel Frames and facing for doors Handrails and railings

See drawings for sizes, details and location of work required. PART 2 2.01 2.02 PART 3 3.01 PRODUCTS Rolled Steel Plates and Sections - ASTM Specification A33 Refer to Summary of Materials and Finishes EXECUTION WORKMANSHIP a. Make all work well formed to shape and size shown and assemble as detailed. Cut, shear and punch to produce clean, true line and surfaces with burrs removed. Weld or bolt connections as indicated. Use countersunk screws in recessed work where possible. Make all details of assembly strong with sufficient stiffness. Form joints exposed to weather in a manner to exclude water. Provide all work with proper clearances. Fabricate and install in a manner to provide for expansion and contraction but will insure rigidity and provide close fitting of sections. Fabricate and install as directed by the Manufacturer. Provide a protective coating which is resistant to alkaline, mortar and plaster to be applied to all sections after fabrication.

b.

c.

d.

e. f.

89

DIVISION 6 - CARPENTRY

SECTION 06100 PART 1 1.01

ON-SITE CARPENTRY GENERAL SCOPE a. Furnish materials and equipment and perform labor required to complete wooden framings and related rough carpentry work as indicated in the drawings and/or specified herein. Include in the works, nailing strips scaffolding, plates, straps, joists, hangers, rods, dowels, rough hardware, fasteners and other miscellaneous iron and steel items pertinent to rough carpentry work.

b.

1.02

STORAGE AND PROTECTION a. Stack farming lumber to insure against deformation and maintain proper ventilation. Protect lumber from elements. Lumber in contact with concrete or masonry shall be coated with 2 (two) coats of asphalt, applied hot. Temporary protection Provide and maintain temporary protection of the work as required to safeguard completed or partially completed work during the progress of the construction. Provide all the necessary rough stairs ladders, runaways, for convenient access to all parts of the building until other permanent facilities are in place.

b. c.

d. 1.

2.

PART 2 2.01

PRODUCTS LUMBER a. b. Moisture Content Not to exceed 18 percent. All lumber, excluding scaffoldings, to be pressure treated, conforming to 67% stress grade lumber in accordance to the requirements of the Philippines National Building Code, latest edition.

90

c. d.

Refer to drawings showing Materials and Finishes. Substitution of Lumber Any lumber equally good for the purpose intended may be substituted for kinds specified, provide, however, that the substitution be authorized in writing by the Architect.

2.02

ROUGH HARDWARE AND METAL FASTENERS Plates, straps, nails, spikes, bolts , joists, hangers, rods, dowels, fasteners and miscellaneous iron and steel items shall be of sizes and types to rigidly secure member in place.

PART 3

EXECUTION a. Fit carefully mortise and tenon joints of all framings including tongues and grooves of sheathing. Anchor all frames coming in contact with concrete, unless otherwise specified, by means of 20 D nails,, spaced the contact surfaces. Plane and dress side of frames that will receive the wallboards of sidings. Wood nailers shall be in accordance with detail drawings. Where not indicated on the drawings or mentioned herein, nailing strips shall be 1" x 2" space at 0.40 m. on centers both ways. Fasten securely by expansion bolts or other approved device at every 0.6 m. on center. Make all exposed nails countersunk. Do scribbling, mitering and joining accurately and neatly to conform to details.

b.

c.

91

SECTION 06220 PART 1 1.01

MILLWORKS GENERAL SCOPE Furnish materials and equipment and perform labor required to complete Wood jambs Wood shelvings Cabinets Wood slats Ceiling boards and wall panels Wood trims And related finish carpentry work as indicated on the drawings and/or specified herein. Coordinate work will all other related trades.

1.02

STORAGE AND PROTECTION a. b. Protect millwork against dampness during and after delivery. Do not bring in interior finish, including doors, into building until plaster is thoroughly dry.

PART 2 2.01

PRODUCTS LUMBER In dried quarter sawn containing not more than 14% moisture, free from imperfections impairing its strength and finish.

2.02

PLYWOOD For interior plywood, use Class A plywood whose specie and thickness shall conform to schedule and drawings.

2.03

FINISH HARDWARE For cabinet, see SECTION 08710 FINISH HARDWARE

2.04

Refer to Summary of Materials and Finishes.

92

PART 3 3.01

EXECUTION WORKMANSHIP a. Make all wood finish, and millwork true to details, clean and sharply defined. Set panels to allow for free movement in case of swelling or shrinkage. Conceal means of fastening various parts together.

b.

c. 3.02 FINISH a.

Mill, fabricate and erect interior finish as indicated on the drawings. Machined sand at the mill and manual smooth at the job. Separate with % inch stone-cut joints all interior trims set against concrete, masonry or wood. Make joints tight and in a manner to conceal shrinkage. Secure trim with fine finishing nails, screws, or glue where required. Set nails for putty stopping. Make window and door trim single length. Miter mouldings at corner, cope at angles.

b.

c.

d. e. f. 3.03

WOOD JAMBS a. b. Set doorframes plumb and level and brace until built-in. Anchor wood frames to masonry with approved metal anchors on each side of jamb. Place top and bottom anchors (0.2m) 8 inches from head and floor.

3.04

WOOD SHELVING a. b. Each shelf shall be supported on a continuous wood cleat walls. Secure cleats to masonry walls by expansion bolt or approved fastening devise.

3.05

BUILT-IN CABINETS AND CLOSETS a. Fabricate cabinets and closets in accordance with details.

93

b. c. 3.06

Use sound kiln-dried lumber or plywood. Erect cabinets straight level and plumb and securely anchor in place.

CEILING BOARDS Cut sheets to dimensions as specified in the drawings and nail on to 60 x 60mm ceiling joist spaced at 600 mm on center both ways or as shown in drawings.

3.07

HARDWARE a. b. Accurately fit and install all required finish hardware items. If surface-applied hardware is fitted and applied before painting, remove all such items, except butts, and reinstall after painting work is completed

94

DIVISION 7 - T H E R M A L & MOISTURE PROTECTION SECTION 07100 PART 1 1.01 WATERPROOFING GENERAL SCOPE Furnish all materials and equipment complete: 1. and perform labor required to

Integral waterproofing for all concrete flashing of metal and clay tile roofing. Water proofing of all concrete gutter, planter box, and suspended floor slab of toilets and all roof decks.

2.

See drawings and details for location and extent of the waterproofing requirements. PART 2 2.01 PRODUCT MATERIALS Refer to detailed drawings showing Materials and Finishes -Waterproofing Membrane PART 3 3.01 EXECUTION Deliver waterproofing materials to the site in original sealed containers or packages bearing the manufacturer's name and brand designation, specification number, type and class. Store and protect waterproofing materials from damage, weather moisture and extreme temperature with extraordinary care. Clean, free from holes and projections, smooth and dry all surfaces to receive waterproofing materials. The Contractor shall perform the necessary surface preparation. Immediately before application of waterproofing, clean surface and secure approval. No application of waterproofing is permitted in wet weather. All work under this Section Manufacturer's specifications. shall be performed in accordance to

3.02

3.03

3.04

3.05

Where curing of waterproofing is required, cure strictly in accordance to the Manufacturer's specifications. Allow foot traffic only after complete curing.

95

SECTION 07320 PART 1

TILED ROOFING GENERAL SCOPE Furnish materials and equipment and perform labor required to complete. Fitting and installation of Fish-scale sheet tiles for eaves and stair roofing, wire strap/anchor units as well as the installation of supplementary materials to make the roof watertight and leakproof. See drawings and details for sizes and location of work required.

PART 2

PRODUCTS MATERIALS a. Fish-scale sheet roof tiles shall be as per specification of the Industrial Technology Development Institute, Department of Science and Technology, as manufactured by . Nominal dimension of the sheet tile shall be 15mmx200mm x380mm with breaking strength of Mpa. Anchor/strap wire ties shall be galvanized of at least gauge 16 thickness fastened securely to 25x30x3mm angular battens. At least two (2) lengths of wire should anchor a single tile or one (1) ga. 16 wire section should be provided per 0.03sqm of tile or roof cladding element (flashing or ridge cap) or provide one (1) ga. 16 wire as tie down spaced at 150 mm on centers. Anchor nails/screws shall be galvanized of sufficient size to be able to fasten effectively size to be able to fasten effectively each tile to the treated 25mmx50mm wooden battens anchored on concrete slab.

b.

c.

PART 3

EXECUTION FISH-SCALE SHEET ROOF TILES a. b. Install the first row of fish-scale roof tiles starting from the eaves. Install succeeding tiles over the previous in a staggered fashion. Refer to detailed drawings. Anchor each tile using wire ties or screws in accordance with PART 2.

c.

96

SECTION 07400 PART 1 SCOPE

METAL ROOFING GENERAL

Furnish materials and equipment and perform labor required to complete fitting and installation of ribbed metal roofing, flashing components, strap and rivet units as well as the application of supplementary materials to make the roof watertight and leakproof. See drawings and details for sizes and location of work required. PART 2 PRODUCTS MATERIALS 15 x 200x 400mm Fish Scale Roofing Tiles Substrate Metal: Galvanized steel sheet, using annealed and tempered cold rolled steel coils hot-dipped to PNS 67:1986 Standard (i.e at least 215 g/m2). Protective Coatings: Zinc phosphate of at least 0.4 microns. Primer of epoxy/urethane of at least 3.5 microns Topcoat of oil-free polyester of at least 6.0 microns All costs oven-baked to meet properties of J IS G 3312 Standard including salt spray test duration of at least 500 hours. PART 3 3.01 EXECUTION ROOFING SHEETS a. Lay down the ribbed roofing tiles starting from the end opposite the prevailing wind. Lay and install the first sheet with the turned down edge towards the outside of the area to be covered. Overlay the next sheet in such a manner that the exposed edge is turned down and the covered edge is turned up. Fix the strap according to indications shown in the manufacturer's catalogue. Fasten the roofing sheets to the steel purlins by means of straps riveted to roofing tiles and wrapped around purlins.

b.

c.

d.

e.

97

f.

Side lap fasteners shall be done by rivets and washers paced from 12" to 18" on centers.

3.02

GUTTER, FLASHING, AND COUNTER FLASHING a. Provide gutter, flashings and counter flashings, gauge 0.600mm prepainted galvanized sheets any approved equivalent, at all critical points where water may seep through. See drawings as to the counter-flashing. details of the gutter, flashing and

b.

98

DIVISION 8 - DOORS & WINDOWS

SECTION 08100/08510 PART 1 1.01

STEEL WINDOWS AND DOORS

GENERAL SCOPE Furnish materials and equipment and perform labor required to complete: A. B. Steel casement windows Wood doors

See drawings and details for sizes, location extent and other requirements. 1.02 SHOP DRAWINGS AND SAMPLES a. Submit for approval of the Architect, shop drawing of fabricated items showing sizes of all members, details of connections, fabrication and installation. Submit samples of the corner section for doors and jambs. Secure approval of all shop drawings prior work. to start of fabrication

b. c.

PART 2 2.01

PRODUCTS Steel Casement Windows All Steel casement windows shall be the sizes shown on the drawings, low carbon hot-rolled steel frame. Vent sections shall be mitered and electrically welded with exposed surfaces ground smooth. Each vent shall have a solid brass, polished, camlocking handle and strike. All steel casement windows shall be shop-finished with a dip coat of dark red primer.

2.02

Swing Tubular Steel Doors Stiles and rails shall be constructed of 14 gauged pressed steel tube with lock seam. Steel panels shall be constructed from 16 gauge annealed and patent leveled sheets. Corners shall be welded construction with all joints face welded and ground smooth. Glass panel mountings, designed for inside glazing with steel clips and bed putty, shall be securely and neatly welded to rails and stiles. All doors and frames shall be thoroughly cleaned of rust and scales and shall be giver two coat of dark red primer.

99

PART 3 3.01

EXECUTION INSTALLATION a. Erect all frames plumbs, square, and true to line and level, with secure fastening to structures and anchors. Install formed steel stiffeners and reinforcement within frames at all points where top screw fastenings are used in connections with embedded strap anchorage. Have doors installed by authorized representative manufacturer, but not before all plastering is completed. of the

b.

c.

Shop paint with two coats of air dried zinc chromate rust inhibitive primer. Clean all surfaces and test all framing and hardwares. Make all repairs and adjustment to the work, leaving it in a satisfactory condition.

d.

3.02

HARDWARE Have all metal doors and frames mortised, reinforced, drilled and tapped for mortise hardware in accordance with templates or hardware finish.

100

SECTION 08200 PART 1 1.01

WOOD DOORS GENERAL SCOPE Finish materials and equipment and perform labor required to complete: louver doors flush doors and other wood doors See drawings and details for sizes, location, extent and other requirements.

1.02

SAMPLES Submit sample corner sections of wood doors and jambs, for approval of the Architect.

1.03

PROTECTION Protect doors adequately from building paper. scratches, and other stains with heavy

PART 2 2.01

PRODUCTS MATERIALS Refer to the Summary of Materials and Finishes

2.02

FABRICATION a. Assemble joints in doors with water-resistant glue. Keep doors under pressure until glue has thoroughly set. Sand smooth finished door. Provide doors with joints and clean out cut mouldings. Keep faces from defects or machine marks that will show through the finish. Flush Doors Hollow Core: Provide doors with cross bonding and edgings. Make face veneer first quality selected plywood or lawanit as directed in the drawings or as specified herein. Provide lock blocks of size required for hardware used.

b.

c.

d.

101

PART 3 3.01

EXECUTION INSTALLATION a. b. c. Cut, trim, and fit each door to its frame and hardware accurately. Give allowance for painter's finish and possible swelling or shrinkage. Provide not more than 1/8 inch clearance at lock and hanging stiles and not more than % inch at bottom. Round all corners to 1/16 inch radius. Bevel slight lock and rail edges. All doors shall operate freely and all hardwares shall be properly adjusted and functioning.

d. e.

102

SECTION 08520 PART 1

ALUMINUM WINDOWS GENERAL

1.01 SCOPE Furnish materials and equipment and perform labor required to complete: Steel Casement Windows See drawings and schedules for size, details and location of required work. 1.02 SHOP DRAWINGS AND SAMPLES a. b. Submit shop drawings and secure Architect's approval. Submit sample corner sections, hinges, tracks, handles and all other accessories.

PART 2 2.01

PRODUCTS MATERIALS Clear Glass Steel Casement Window (5.5mm thick clear glass)

PART 3 3.01

EXECUTION FABRICATION a. Factory prefabricate all frames in accordance with the design and dimensions indicated in the drawings. Cut join and fit rails and stiles to hairlines joints securely reinforced and jointed by means of concealed fastening wherever possible. Protective Coating Clean all surface and apply a protective coating of clear, water-white methacrylate type lacquer, resistant to alkaline mortar and plaster immediately after fabrication and may not be even after completion of installation. 3.03 INSTALLATION a. Set and anchor frames as shown in details and in approved shop drawings.

b.

c.

103

b.

Set frames plumb and square and brace where necessary to prevent distortion. Wedge clear of masonry all frames set in prepared openings 3/16 to % inch to allow for caulking.

c.

3.04

ADJUSTMENTS a. b. Adjust all frames and attach hardwares before glazing. Secure all windows and doors to be watertight and all hardware operating free and easy.

104

SECTION 08710 PART 1 1.01

FINISH HARDWARE GENERAL SCOPE Furnish materials and equipment and perform labor required to complete: Finish hardware for doors and windows

1.02

SAMPLES Submit samples of locksets, hinges, door pulls, door stops, door closers and other finish hardware and accessories for Architect's approval.

PART 2 2.01

PRODUCTS MATERIALS A. Locks 1. All steel doors and other doors specified in the schedule of doors and windows shall be equipped with "ASSA" double cylinder locksets or any approved equivalent. Cylinder lock to be equipped with latch bolts operated by lever handles and dead bolt operated by key lever handles and dead bolt operated by key or thumb-turn on inside and key from outside. Other Door sashes as specified in the schedule of doors and windows shall be provided and fitted with a set of cylindrical unit lockset 26D finish and to conform to the following schedule: Lockset Types Lever Type Panic Device B. Latches Bar doors for shower and toilet compartments shall be provided and fitted with rim bolt and an indicator, chromium plated and polished. C. Hinges 1. All steel door with steel facing shall be provided with three heavy steel hinges. Function All Rooms Fire Exit Door

2.

105

2.

All steel door with glass panel shall be provided with heavy duty pivot hinges to be fixed on top and bottom rails. Butt hinges Each panel of hinged door shall hung on three (3) butts for doors 1.80 or less in height and four (4) butts for doors 2.10 m in height. The size of the butt hinges shall conform to the Schedule of Doors and Hardwares.

3.

4.

Concealed Hinges Cabinet closet and building specialties doors shall be provided and fitted with a set of concealed hinges.

2.02

MISCELLANEOUS DOOR HARDWARES a. For doors that will strike on object rubber bumper provide or door stop. Type and location of installation to be approved by the Architect. For heavy frequency door with closer and mortise locks provide stainless steel push plates. For double leaf wooden provide 2 flush bolts 18" long. For silencing the door when it strikes the stop strip and to prevent rattles, install three (3) silencers in the stop of frame.

b.

c. d.

PART 3

EXECUTION INSTALLATION Install hardware to fill details shown in the drawings and as per manufacturer's specifications. Supply all necessary templates and instructions required.

106

SECTION 08730 PART 1 1.01

WEATHER STRIPPING GENERAL SCOPE Furnish materials and equipment and perform labor required to complete: all types of weatherstripping in the form of rubber and vinyl strip and caulking

1.02 PART 2

Submit samples of weather strip elements for approval by the Architect. PRODUCTS MATERIALS Refer to the Summary of Materials and Finishes

PART 3

EXECUTION a. Install on all exterior doors and windows opening to render them watertight. Install on all interior doors to silence door.

b.

107

SECTION 08800 PART 1 1.01

GLASS AND GLAZING GENERAL SCOPE Furnish glass free from imperfection and water marks and other materials and equipment and perform labor required to complete all glass and glazing work. See drawings for size, location and details.

1.02

SAMPLES Submit samples of glass panels

1.03

PROTECTION Protect material from loss, injury, staining and breakage.

PART 2

PRODUCT

GLAZING a. 1. Glazing materials for glass installation may be: Bulk compounds such as: Mastics - elastic compounds and non skinning compound. Putties - wood sash putty, metal sash putty. Sealants - one components. 2. Performed Sealants such as: Synthetic polymer- base sealants- resilient or non- resilient type. Preformed gaskets- compression type, structural type.

PART 3 3.01

EXECUTION GLAZING a. Prevent glass from all contact with metal or any hard or sharp materials by use of resilient shims placed at quarter point.

108

b. c. d. e.

Use resilient sealants. Use stops in sizes permitting a "good grip" on the glass. Install glass only in openings that are rigid, plumb and square. Allow sufficient clearance at edges of glass to compensate for its expansion or for some settlement of the building. Clearance should be % inch from edge and 1/8 inch for face. Removal of putty or glazing compound smears from glass shall be performed by the glazing contractor during the material's normal work life. Failure to do so may result in damage to the glass.

f.

109

DIVISION 9-FINISHES

SECTION 09220 PART 1

CEMENT FINISHES GENERAL SCOPE Furnish materials and equipment and perform labor required to complete all: Plain cement plaster finish See drawings for details and location of work required.

PART 2

PRODUCT MATERIALS Refer to the Summary of Materials and Finishes

PART 3 3.01

EXECUTION PLAIN CEMENT PLASTER FINISH a. Provide all wall indicated with three coats of cement plaster (scratch coat brown coat and finish coat). Mix each coat in the proportion of one part portland cement o three parts sand by volume. Apply the scratch coat with sufficient material and pressure to ensure a good bond and then scratch to a rough surface. Provide a thickness of 3/8" for scratch boat. Dampen with water before applying brown coat. Apply brown coat, one day after applying scratch coat, with a thickness of 3/8" and level to a flat even surface. When stiff enough, trowel with a wooden float and cross hatch or broom lightly and evenly to secure a good mechanical bond for the finish coat. Wet the surface and keep from drying out for at least three (3) days. Apply finish coast seven (7) days after the application of brown coat. Provide thickness of 1/8', keep the finish coat damp but not saturated for a period of seven (7) days.

b.

c.

d.

110

SECTION 09310/09390 PART 1 1.01

CERAMIC/CEMENT TILEWORK

GENERAL SCOPE Furnish materials and equipment and perform labor required to complete all types of tile works. See drawings and details for location and extent of work required.

PART 2

PRODUCTS MATERIALS 1. 3 0 0 x 3 0 0 Unglazed Tiles 2. 3 0 0 x 3 0 0 Carpet Tiles 3. 800 x 800 Granulithic Tiles Refer to Summary of Materials and Finishes

PART 3 3.01

EXECUTION APPLICATION OF SCRATCH COAT a. Thoroughly dampen, but not saturate, surface of masonry or concrete walls before applying the scratch coat. Make surface areas appear slightly damp. Allow no free water on the surface. On masonry, first apply a thin coat with great pressure, then bring it out sufficiently to compensate for the major irregularities on the masonry surfaces to a thickness of not less than % inch at any point. Evenly rake scratch coats, but not wash coats, to provide good mechanical key for subsequent coats before the mortar has fully hardened. On surfaces not sufficiently rough to provide good mechanical key, dash on the first coat with a whisk broom or fiber brush using a strong whipping motion. Do not trowel or otherwise disturb mortar applied by dashing until it has hardened.

b.

c.

d.

3.02

FLOOR TILE INSTALLATION ON MORTAR BED a. Before spreading the setting bed, establish lines of borders and center the fieldwork in both directions to permit the pattern to be laid with a minimum of cut tiles.

I l l

b.

Clean concrete sub-floor them moisten but not soak. Afterwards sprinkle and spread the mortar on the setting bed. Mix mortar 1 part Portland Cement to 3 parts sand. Tamp to assure good bond over the entire area and screed to provide a smooth and level bed at proper height and slope. Pitch floor to drains as required. After setting bed has set sufficiently to be worked over, sprinkle dry cement over surface and lay tile. Keep tile joints parallel and straight straight edges. over the entire area by using

c.

d. e.

f.

g.

Tamp the tile solidly onto the bed, using ensure solid bedding free from depressions.

wood blocks of size to

h. 3.03

Lay tiles from center lines outward and make adjustments at walls.

WALL TILE INSTALLATON ON MORTAR BED a. Before application of mortar bed, dampen the surface of the scratch coat evenly to obtain uniform section. Use temporary or spot grounds to control the thickness of the mortar bed. Fill out the mortar bed even with the grounds and rot it to a true plane. Apply the mortar bed over an area no greater than can be covered with tile while the coat is still plastic. Allow no single application of mortar to be % inch thick. Completely immerse wall tile in clean water and soak it at least Vi hour. After removal, stack tile on edge long enough to drain off excess water. Be soak and drain individual tiles that dry along edges. Allow no free moisture to remain on the back of tile during setting. Apply bond coat 1/32 to 1/8 inch thick to the plastic setting bed or to back of each sheet or tile. Press tile firmly into the bed and beat into place within 1 hour. Lay tile fields in rectangular block areas not exceeding 24 by 24 inches. Cut the setting bed through its entire depth along the edges of each block area after placement and before subsequent blocks are installed.

b.

c.

d. e.

f.

g. h.

112

I.

Within 1 hour after installation of tile, remove strings from string-set tile and wet the faces of face-mounted tile and remove the paper and glue. Avoid using excess water. Adjust any tile that is out of alignment.

3.04

GROUTING a. After tile has sufficiently set, force a maximum of grout into joints by trowel, brush or finger application. Before grout sets, strike or tool the joints of cushion-edged tile to the depth of the cushion. Fill all joints of square-edged tile flush with the surface of the tile. Fill all gaps or sips. During grouting clean all excess grout off with clean burlap, other cloths or sponges.

b.

c.

d.

3.05

CLEANING Sponge and wash tile thoroughly with clear water after the grout has stiffened. Then clean by rubbing with damp cloths or sponges and polish clean with dry cloth.

113

SECTION 09650 PART 1

VINYL FLOOR FINISH GENERAL SCOPE Furnish materials and equipment to perform labor required to complete all: Vinyl Floors as shown in the drawings.

PART 2

PRODUCT MATERIALS Where shown or scheduled in the drawings, all floors finished with vinyl tiles shall be constructed 3mm or 4mm below the finished floor levels and shall be troweled to a smooth and even surface free from pits, visible joints, marks or other imperfections. Tiles to be used shall be Vinyl Quartz Tiles or equivalent, 3mm. In thickness and shall be of dimension, color and laying pattern to conform to the schedule as indicated in the drawings.

PART 3 A.

EXECUTION Preparation of Surfaces Clean the floor thoroughly of dirt, grease, paintdrops, etc., leaving the surface suitable for the installation of the tiles. The resulting surface shall be smooth, even thoroughly dry and clean. B. Laying Before tiles are laid, apply over the surface a coat of asphalt emulsion in accordance with the manufacturer's specifications. In laying the tiles over this emulsion coat, the edges of the tiles shall be carefully matched and the seems cut. All seams and edges shall be cemented with asphalt cement. The surface of the finished floor shall be left smooth, clean and in first class condition.

C.

Cleaning, Waxing, Polishing At completion of the work, clean all vinyl tiles and remove all cement, dirt or other foreign substance. Apply two coats of emulsion wax and polish each coat to a gloss and shiny finish.

114

SECTION 09900 PART 1 1.01

PAINTING GENERAL SCOPE Furnish materials and equipment and perform labor required to complete: all painting and varnishing work as specified herein. See drawings for location, quantity and extent or surfaces to receive paint and varnish.

1.02

TEST PANELS Prepare sample panels of selected color or shade on 2 feet by 2 feet plywood panels for approval by the Architect.

PART 2

PRODUCT MATERIALS Refer to the Summary of Materials and Finishes.

PART 3 3.01

EXECUTION WORKMANSHIP IN GENERAL a. Mix paint with proper consistency. Apply paints evenly and brush efficiently to minimize brush marks. Stir paint thoroughly to keep pigment in even suspension when paint is being applied. Except as otherwise directed by the Architect, apply all paints in three coats (priming, body and finish). Allow each coat to dry thoroughly before the succeeding coat is applied. In general, unless other side instructed by the Architect provide not less than 48 hours as the time between the application of succeeding coats. Let the Architect or his representatives inspect and approve each coat before the succeeding coat is applied. If surfaces are not fully covered or cannot be satisfactory finished in the number of coats specified, apply subsequent coats to attain the desired evenness of paint. Touch up knots, pitch streaks, sappy spots, etc. where finish calls for interior paint or enamel. For exteriors, use and approve sealer.

b.

c.

d.

e.

115

f.

Sand smooth woodwork to be finished with enamel or varnish. Use fine sandpaper between coats of enamel of varnished applied to wood or metal to produce an even smooth surface. Do not paint exterior while surface is damp or during rainy or damp weather. Do necessary putting of nail holes, cracks, etc. after the prime coat has been applied. Bring putty flush with adjoining surface in a neat, workmanlike manner. Tint undercoats of paint or enamel to same or approximate shade of final coat. protect to remove hardwares, hardware accessories, plates, lighting fixtures and other similar items during the painting operation and reinstall them after completion of work.

g.

h.

I.

j.

116

DIVISION

10-SPECIALTIES

SECTION 10521 PART 1

FIRE EXTINGUISHER GENERAL SCOPE Furnish materials and equipment and perform labor required to complete all: fire extinguishers/mounting See drawings for location of work.

PART 2

PRODUCTS Fire Extinguisher, multipurpose dry chemical type, C rated.

PART 3

EXECUTION Install items in accord manufacturer's direction and recommendations. Where details apparently require departures from these directions, secure instructions before proceeding.

117

DIVISION

10-SPECIALTIES

SECTION 10820 PART 1

TOILET ACCESSORIES GENERAL SCOPE Furnish materials and equipment and perform labor required to complete all: toilet accessories See drawings and details for sizes and locations of work required.

PART 2 2.01

PRODUCTS MATERIALS Refer to the Summary of Materials & Finishes and drawings.

PART 3

EXECUTION Furnish and install all toilet accessories true to line, plane and level, in accordance to manufacturer's specifications.

118

DIVISION 11- MECHANICAL

SECTION 11400 I.

PLUMBING WORKS

GENERAL 1. General Description - The work to be done under this Division of the specifications of the fabrication, complete in all details, of the Plumbing Works, at the subject premises and all the materials incidental to the proper completion of the installation, except those portions of the work which are expressly stated to be done by others. All works shall be in accordance with the governing Codes and Regulations and with the specifications, except where same shall conflict with such Codes, etc. which, later shall then govern. The requirements in regards to materials and workmanship specify the required standards for the furnishings of all labor, materials and appliances necessary for the completion of the work specified herein and indicated in the drawings. 2. Drawings Specification 2.1 The contract drawing and specifications are complementary to each other and any labor an materials called for by either, whether or not called for by both, if necessary for the successful operation of nay of the particular type of equipment furnished and installed without additional cost to the Owner. 2.2 All dimensions location of fixtures, equipment floor and roof drains, risers and pipe chase shall be verified on the architectural drawings and manufacturer's catalogue. 3. Intent - It is not intended that the drawings shall show every pipe, fitting, valve and appliance. All such items show whether specifically mentioned or not, or indicated on the drawings, shall be furnished and installed if necessary to complete the system in accordance with the best practice of the plumbing trade and to the satisfaction of the Architect, the Engineer and the Owner. 4. Site Investigation - The Contractor is required to visit the site and to ascertain himself as to the local conditions and facilities that may affect his work. He will be deemed to have done this before preparing his proposal and any subsequent claims on the ground of inadequate or inaccurate information will not be entertained. 5. Shop Drawing-The Contractor shall submit to the ARCHITECT and the Engineer, for approval, four (4) copies of all s hop drawings of details and connection not shown on the drawings or deviation thereof but required for the work. The Contractor shall certify that the drawings have been checked for dimensions, materials, erection details and conform to the intent of the drawings and specifications.

119

6.

Record Drawings 6.1 The Contractor shall during the progress of work, keep a record of the actual installation from that shown on the contract drawings. 6.2 Upon completion of the work, the Contractor shall submit four (4) copies of as-built drawings indicating the work as actually and finally installed.

7. Guarantee - The Contractor shall guarantee that the plumbing system is free form all defective workmanship and materials and will remain so for a period of one (1) year from the date of acceptance of the work. Any defects, appearing within the aforesaid period shall be remedied by the Contractor at his own expense. 8. Permits - The Contractor shall be responsible for securing all the required construction and operation permits and pay all necessary fees thereof. Copies of inspections shall be submitted to the Owner. 9. Codes and Standards - The work under this contract is to be installed with reference to the latest requirements of the following: 9.1 9.2 9.3 9.4 9.5 9.6 9.7 9.8 9.9 9.10 II. MATERIALS 1. Quality Assurance - All materials shall be used shall be new and shall conform with the reference codes and standards. Use or materials shall further be governed by other requirements, imposed on other sections of these specifications. Materials shall be subject to test necessary their fitness if so requires. PHILIPPINE NATIONAL BUILDING CODE REGULATION OF LOCAL WATERWORKS & SEWERAGE AUTHORITY UNIFORM PLUMBING CODE (UPC) AMERICAN SOCIETY FOR TESTING AND MATERIALS (ASTM) AMERICAN NATIONAL STANDARD INSTITUTE (ANSI) AMERICAN WATER WORKS ASSOCIATION (AWWA) NATIONAL FIRE PROTECTION ASSOCIATION (NFPA) UNDERWRITER'S LABORATORIES (UL) FACTORY MUTUAL (FM) NATIONAL ELECTRICAL MANUFACTURERS ASSOCIATION (NEMA)

120

2.

Alternate Materials - Use of any material, not specified in these specifications may be allowed provided such alternate has been approved by the Architect and Engineer and provided further that a test, if required , shall be done by an approved agency in accordance with the generally accepted standards. Identification of Materials - Each length of pipe, fittings, traps, fixtures and devise used in the plumbing systems shall be case, stamped or indelibly marked on it's manufacture trademark or name, the wight, type and classes or product when so required by the standard mentioned above. Polyvinyl Chloride Piping 4.1 4.2 4.3 Type - Polyvinyl chloride (PVC), ASTM D - 2729, schedule 40 Moldex blue or approved equal for all water line piping. Sanimold orange uPVC with exclusive O-ring or approved equal for all water lines and vents. Fittings - Polyvinyl chloride Pipe S e a l a n t - P V C chloride 75 mmO Sanimold Orange uPVC pipes or approved equal for all downspouts.

3.

4.

4.4 4.5 4.6

5.

Concrete Piping 5.1 5.2 Type - Concrete Pipes, ASTM C - 78 Minimum wall thickness - Plain concrete for 250 mmO and smaller pipes; Reinforced concrete for 300 mmO and bigger pipes, class IV Joints - Male and female groove Pipe sealant - Cement grout Application - Exterior storm drain piping

5.3 5.4 5.5 6.

Galvanized Iron Piping 6.1 6.2 6.3 Type - ERW, ASTM A - 120 or A -53 Minimum wall thickness - Schedule 40 Joints - Threaded joints for pipe sized 50mm and smaller; Welded or flanged joints for pipe sizes 65 mm and bigger.

121

6.4

Fittings - Malleable iron ASTM A - 197 for threaded fittings and steel ASTM A - 126 for flanged fittings. Valves - Bronze, ASTM B - 62, 1035 Kpa for 50 mm and smaller; All iron, bronze fitted, 1035 Kpa for 65 mm and bigger. Pipe Sealant - Teflon tape for threaded joints and rubber gasket for flanged joints. Application - Main water piping and Fire protection piping.

6.5

6.6

6.7 7. 8.

Acid Resistant Pipes - for all laboratory water pipes Pipe/Gutter Support 8.1 Pipe support shall be fabricated with flat bar, round bar and angular bar of appropriate size. Anchorage of pipe support on concrete slab or beam shall be expansion shields or it shall be directly fasten to structural steel member as shown on details or as required.

8.2

9.

Pipe Sleeves 9.1 9.2 Pipe sleeve shall be galvanized iron pipe, Sch. 40 Sleeve shall have minimum clearance of 25 mm around the pipe insulation, if any, and caulked with oakum and mastic sealant.

EQUIPMENT 1. Quality Assurance - All equipment to be used shall be new and shall conform with the reference codes and standards. The manufacturer shall provided representatives for start-up supervision. Operation & Maintenance Manual - The manufacturer shall provide four (4) copies of operation & maintenance manual, including spare parts list to the Owner. Fire Hose Cabinet 3.1 Cabinet - Fire hose cabinet shall be flushed to the wall. Frame shall be gage 16 steel with white interior and red exterior enamel paint finish over primer. Door frame shall be aluminum.

2.

3.

122

3.2

Unit shall consist of the following: One (1) - 40mm x 20 m single jacket hose with brass coupling One (1) - 40 mm combination fog and solid stream nozzle brass finish One (1) - Semi automatic rack, brass finish and hose nipple One (1) - 40 mm angle valve, brass finish, 1200 Kpa One (1) - Spanned wrench One (1) - 4.5 Kg. Dry chemical ABC extinguisher. UL/FM listed One (1) - Fire axe

4.

Fire Department Connections 4.1 Type - Threaded type to match the local fire requirement. Complete with caps and chains. Pressure Rating - 1200 Kpa Manufacturer - Similar to Elkhart model or approved equal Finish - Rough brass Uses and Sizes Siamese Twin - 75 x 65x 65 mm female connection Fire hose valve - 65 mm male connection department

4.2 4.3 4.4 4.5

INSTALLATION 1. Workmanship 1.1 The work throughout shall be executed in the best and most thorough manner to the satisfaction of the Architect and the Engineers, who will jointly interpret the meaning of the drawings and specifications and shall have power to reject any work and materials which in their judgment, are not in full accordance therewith. 1.2 This Contractor shall assume unit responsibility and shall provide the services for a qualified Engineer to supervise the complete installation of equipment and systems and who shall be available for conducting the finial acceptance tests.

123

1.3 All equipment shall be installed in accordance with the manufacturer's standard. Certificate of compliance by the manufacturer's representative shall be submitted to the Owner. 2. Excavating, Pipe Laying and Packfilling 2.1 Excavating

Trenches for all underground pipe lines shall be excavated to the required depth and grades. Bell holes shall be provided so that the pipe shall rest on well tamped solid ground for its entire length. Where rock is encountered, excavation shall extend to depth 150 mm below the pipe bottom, and before pipe is laid, the space between the bottom of pipe shall be filled with approved filling materials. 2.2 Pipe Laying

Pipes in trenches shall be laid true line and grade on a stable or suitably prepared foundation, each section of the pipe being bedded and bottom of the trench shaped to fit the lowest quadrant of the pipe circumference. Pipe shall not pass through columns, footings, beams of ribs, except where noted on the drawings. Slopes of all sewage and storm drainage pipings shall be maintained at 1% minimum unless otherwise noted or required. 2.3 Backfilling

After pipe lines have been tested, inspected and approved by the Architect and prior to backfilling, all forms and bracings shall be removed and the excavation shall be cleaned from trash and debris. Materials for backfilling shall consists of approved materials and shall be free of debris or big rocks. Backfill shall be placed in horizontal layers, properly moistened and compacted to an optimum density tat will prevent excessive settlement and shrinkage. 3. Water Piping 3.1 All piping shall be installed parallel to building line unless otherwise noted.

124

3.2

The piping shall be extended to all fixtures, outlets and equipment from the valve installed in each branch. The piping system shall be installed with a fall toward a main shut-off valve and drains. Ends of pipes to fixtures shall be capped with pipe extension of 30 cm long. All pipes embedded underground shall have at least two (2) coat of tar or carboline. All hot water piping shall be insulated except those embedded in concrete or otherwise noted. All water pipe connections to equipment shall be provided with gate valves and unions or flanges to provide access and maintenance. Provide dielectric union for joining pipes of different materials.

3.3

3.4

3.5

3.6

3.7

Clean-outs and Traps 4.1 Clean-outs - Clean-out shall be of the same size as the pipe. For pipes 100 mm and larger, use 100 mm clean-out. Trap - Each fixture trap except those cast integral or in combination with fixtures in which the trap seal is readily accessible or if the trap is removable shall have an accessible brass trap screw of ample size.

4.2

Floor, Wall and Ceiling Plates - Provide chromium plated metal plates of the same materials as the pipe for all exposed piping passes through floors, walls and ceilings. Supports, Sleeves and Hangers 6.1 Fixture Support. All fixtures and equipment shall be supported and fastened in a safe and satisfactory manner. Pipe sleeves shall be installed and properly secured in place at all points where pipes pass through masonry or concrete, except unframed floors on earth. Pipe Hangers, Supports & Inserts Horizontal runs of pipe shall be hung with adjustable pipe hangers spaced not over 3.0 meters apart, except bell and spigot pipes which shall have hangers spaced not over 1.5 meters apart and located near the bell.

6.2

6.3

125

Trapeze hangers may be used in lieu of separate hangers on pipes running parallel to and close to each other. Inserts shall be securely anchored and the anchor shall be properly slushed with mortar. Inserts shall be completely concealed when the fixtures are installed. Vertical pipe riser shall be supported at every floor unless additional supports are required. Provide isolation for pipe and hanger of different materials. Provide auxiliary structural steel members required for supporting and anchoring of pipes and accessories. 7. Cleaning and Painting 7.1 All Exposed Metal Surfaces All exposed metal surfaces shall be rid of grease, dirt or other foreign materials. All equipment, pipes, valves and fittings shall be cleaned of grease and sludge which may have accumulated. Any stoppage of discoloration or other damage to the parts of the building, its finish or furnishings due to the system shall be repaired by the Contractor. 7.2 Painting All exterior surfaces of pipings to be installed in or through concrete floor fill or the tile floors and underground shall be given one coat of acid resisting paint having a bituminous base. Pipe hangers supports and all other iron work in concealed spaces shall be thoroughly cleaned and painted with one coat of asphalt varnished. All pipings shall be painted with two coats of enamel finish paints after cleaning. Color code shall be submitted to the Engineer and Architect for approval prior to painting. Directional markers shall be spaced no more than 5.0 m apart.

126

8.

Testing and Disinfection 8.1 Testing Water line - Upon completion of the roughing in and before setting fixtures, the entire water piping system shall be tested at a hydrostatic pressure one and one-half times the expected pressure in the system when in operation or 1034 Kpa minimum, for at least 2 hours. Others - Apply the water to the system either in its entirety or in sections after rough piping has been installed. If applied to the entire system, all openings in the piping shall be tightly closed, except the highest opening, and the system filled with water to the point of overflow. Keep the water in the system or in the portion under test for at least thirty (30) minutes during which time there shall be no drop greater than 100 mm. Where portion of the piping system is to be concealed before completion, this portion shall be tested separately in a manner similar to that described for the entire system. 8.2 Disinfection The entire system shall be thoroughly flushed and disinfected with chloride before it is placed in operation. Chlorinating materials shall be introduced into the waterlines in a manner approved by the Architect and the Engineer. The chlorine dosage shall be such as to provide no less than fifty (50) parts per million of available chlorine, following a contact period of not less than sixteen (16) hours, the heavily chlorinated water shall be flushed from the system with clean water until the residual chlorine content is no greater two tenth ppm.

127

DIVISION 12 - ELECTRICAL WORKS

PARTI 1.1 The General Conditions and Provisions of the Civil Works Contract, not in conflict with these Specifications and the Drawings, form part of and are included in this Section of these Specifications. VISIT TO THE SITE The CONTRACTOR is advised to visit the site and satisfy himself as to local conditions and facilities, the nature of the soil, and ascertain such other conditions affecting his work. He will be deemed to have done this before preparing his proposal and no subsequent claims on the grounds of inadequate or inaccurate information will be entertained. 1.3 SUB-CONTRACTOR The CONTRACTOR shall not sub-contract the whole or any part of the work without the written consent of the OWNER. The CONTRACTOR as if he himself were undertaking the work. 1.4 STANDARDS AND WORKMANSHIP The CONTRACTOR shall execute all works in a neat and workmanlike manner and shall do all necessary work whether it is clearly specified on these Specifications or shown on the Drawings or not. All works shall be done in accordance with the best practices employed in modern electrical installations. The CONTRACTOR shall employ only competent and efficient workmen and shall, upon written request of the ARCHITECT, discharge or otherwise remove from work any employee who is, in the opinion of the ARCHITECT careless or incompetent or who obstruct the progress of the work or act contrary to instructions or conducts himself improperly. 1.5 STANDARDS OF MATERIALS All materials shall be new and shall conform to the Technical Specifications. All materials shall be the standard products of reputable manufacturers and shall bear the name of the manufacturers. All materials shall be subject to the approval of the ARCHITECT. This approval does not relieve the CONTRACTOR of the responsibility of inspecting such materials for defects or non-conformity of the Specifications. Where the Technical Specifications or Drawings give the name of the manufacturers and/or catalogue, number of materials, it is given as guide to the size, strength,

1.2

128

quality or class of material desired and shall be interpreted to mean that item or another fully equal for the service intended. Substitution shall be subject to the prior written approval of the ARCHITECT. The apparent silence of the Specifications and Drawings as to any detail of apparent omission from them or any detailed description concerning any material shall be regarded to mean the only materials of first class quality shall be used. The CONTRACTOR shall, within ten (10) days after the award of the Contract, submit for the approval of the ARCHITECT, a listing of the materials he proposed to use in the work including such sample catalogues, drawings or descriptive data as maybe required by the ARCHITECT or risk the subsequent rejection of the same. 1.6 REMOVAL OF DEFECTIVE OR UNAUTHORIZED WORK Any defective work, whether the result of poor workmanship, defective materials, damage through carelessness or any other cause found to exist prior to acceptance of, or final payment from the work shall be removed immediately and replace by work and materials which conform to those Specifications or shall be otherwise remedied in an acceptable manner. This clause shall have full effect regardless of the fact that the work may have been done with the full knowledge of the ARCHITECT. All materials not conforming to the requirements of the Technical Specifications shall be considered as defective. Defective materials which has been subsequently corrected shall be re-used upon approval of the ARCHITECT. 1.7 CONFORMATIVE WITH PLANS AND ALLOWANCE DEVIATIONS These Specifications and Drawings indicate the general layout of the system and the CONTRACTOR shall be responsible for the proper installation of the system without substantial alternatives or modifications. Whether field conditions or exigencies of construction make departure from these Specifications and Drawings necessary, details of such departure and reason thereof shall be submitted to the ARCHITECT for approval. 1.8 COORDINATION WITH OTHER CONTRACTORS The CONTRACTOR shall examine and shall be familiar with the Specifications and Drawings of the Civil Works, the Refrigeration Works and the Sanitary Works. He shall arrange his work and dispose his materials of other Contractors. Should the CONTRACTOR cause damage to any other Contractor on the work, the CONTRACTOR shall upon due notice settle with such Contractor by agreement or by arbitration. The CONTRACTOR shall be liable for any claims by other Contractors against the OWNER on account of such damage.

129

1.9

INSPECTIONS AND TESTS The ARCHITECT or his representative shall be allowed access to all parts of the works at all time and the CONTRACTOR shall furnish such information and assistance as maybe required to make a detailed inspection. Materials and installations shall be subjected to tests as are deemed necessary by the ARCHITECT to properly ascertain their fitness both during and after installation is completed. The cost of such tests shall be borne by the CONTRACTOR.

1.10

CUTTING AND PATCHING The CONTRACTOR shall do all cutting and patching required by the work, engaging men who are skilled in the particular trade to do all the work. Surfaces obtained by cutting and patching shall exactly match surrounding work so that there will be no evidence of laceration or patching.

1.11

INJURY TO PERSONS AND DAMAGE TO PROPERTY The CONTRACTOR shall be responsible for all injuries to persons and damage to property caused by the works or by workmen and shall be liable for any claims against the OWNER on account of such injury and/or damage. The CONTRACTOR shall likewise take necessary precautions to protect the property of the OWNER against rain or other inclemencies of the weather or theft due to the performance of his work. The CONTRACTOR shall be liable for any such damage or loss.

1.12

TEMPORARY FACILITIES The CONTRACTOR shall make all arrangements and pay for the provisions of the necessary electricity supply required for the work and shall clear away all temporary installations before and upon completion of the work.

1.13

LEAVING THE SITE The CONTRACTOR shall not withdraw from the site until the OWNER has agreed that no further work is necessary at the time.

1.14

SUSPENSION OR DELAYS The CONTRACTOR shall not suspend or fail to make proper progress with the work without justifiable cause. The OWNER, in the event of delays or suspension of the work, shall inventory all the materials on the site and make arrangements as are necessary to have the work completed by others.

1.15

CLEANING UP During the process of the work and on the completion of the project, the CONTRACTOR shall remove from the premises all dirt, debris, rubbish and waste materials caused by him in the performance of his work. He shall remove all tools,

130

scaffoldings and surplus materials after completion and acceptance of the work. All salvageable materials removed from the existing building should be turned over to the OWNER for proper inventory and disposal. 1.16 SHOP DRAWINGS AND "AS-BUILT" DRAWINGS The CONTRACTOR shall submit to the ARCHITECT with such promptness as not to cause delay in his work or that of any CONTRACTOR, two (2) copies of all shop drawings and schedules required by the work. The CONTRACTOR shall make all corrections required by the ARCHITECT and submit two (2) corrected copies and other copies as needed. The ARCHITECT'S approval of such drawings shall not relieve the CONTRACTOR of responsibility for the deviations at the time of submission, nor shall it relieve the CONTRACTOR of responsibilities for errors of any sort. Upon completion of the project , the CONTRACTOR shall submit to the OWNER three (3) sets of "AS-BUILT" drawings which shall be identical to the CONTRACT DRAWINGS except for the said changes and deviations. 1.17 CODES, PERMITS, CERTIFICATES OF FINAL INSPECTION AND APPROVAL The work under this contract shall be made in accordance with the requirements of the latest edition of the Philippine Electrical Code, the rules and regulations of the local enforcing authority and the requirements of the local power utility firm. Nothing contained in these Specifications or shown on the Drawings shall be constructed as to conflict with the national and local ordinances and laws governing the installations of electrical works, and all such laws and ordinances are hereby made part of these Specifications. The CONTRACTOR is required to meet the requirements thereof. All permits, certificates and fees required for the work shall be obtained by and at the expense of the CONTRACTOR. The CONTRACTOR shall furnish the ARCHITECT and the OWNER a copy of the Final Certificate of Electrical Inspection and Approval from the proper government authorities after the completion of the work. The CONTRACTOR shall prepare all plans and other related documents required by the approving authorities. PART 2 2.1 SPECIFIC PROVISIONS SCOPE OF WORK OF THE CONTRACTOR The work of the CONTRACTOR consists of furnishing of all plants, labor, equipment and materials and performing of all operations in connection with the electrical system shown on the Drawings, their tests and inspections, complete and in accordance with these Specifications and Drawings and subject to the terms and conditions of the Contract, and all other labor and materials not specifically mentioned under sections, to bring the electrical system to operating conditions and be ready for use by the OWNER.

131

The scope of work of the CONTRACTOR includes the ff: A. 1. 2. PART OF PACKAGE NO. 5 - SITE DEVELOPMENT Concrete pedestal as shown in the plans. Separate concrete manholes/handholes for power and communication lines from R1 to R3 and R1 to A2 as shown in the plans. Underground concrete envelope for both power and communication conduits from the concrete pedestal to R3 and A2. Underground power and communication conduits with its corresponding wiring and wiring devices from the concrete pedestal to R3 and A2 as indicated in the plans. Grounding system as shown in the plans. Testing of all installations. Securing the necessary permits and payment of fees incidental to the work. Any and all other works involved in providing the complete operations of the Electrical and Auxiliary systems and all other items not mentioned but necessary to complete the said work in accordance with the plans, specifications and other related documents. PHILIPPINE SCIENCE HIGH SCHOOL Incoming underground service entrance for power and communication lines with concrete envelope from R3 of the Site Development Plan to the Main Distribution Panel (MDP) of the building. Power and lighting distribution system including panel boards, circuit breakers and stub-out for future loads. A system of lighting and power wiring including feeders, branch circuits and connections to lighting and power outlets. Supply and installation of power and lighting fixtures and wiring devices. Conduit layout, cables, boxes and receptacles and stub-outs for the complete installation of the fire alarm system including the fire alarm equipment and the telephone system excluding the telephone equipment. Roughing-in only of the intercom system. Testing of all electrical and auxiliary installations.

3.

4.

5. 6. 7. 8.

B. 1.

2.

3.

4. 5.

6. 7.

132

8. 9.

Securing the necessary permits and payment to fees incidental to the work. Any and all other works involved in providing the complete operations of the Electrical and Auxiliary systems and all other items not mentioned but necessary to complete the said work in accordance with the plans, specifications and other related documents. ACADEMIC BUILDING (PHASE 1) Incoming underground service entrance for power and communication lines with concrete envelope from R3 of the Site Development Plan to the Main Distribution Panel (MDP) of the building. Power and lighting distribution system including panel boards, circuit breakers and stub-out for future loads. A system of lighting and power wiring including feeders, branch circuits and connections to lighting and power outlets. Supply and installation of power and lighting fixtures and wiring devices. Conduit layout, cables, boxes and receptacles and stub-outs for the complete installation of the fire alarm system including the fire alarm equipment and the telephone system excluding the telephone equipment. Roughing-in only of the intercom system. Testing of all electrical and auxiliary installations. Securing the necessary permits and payment to fees incidental to the work. Any and all other works involved in providing the complete operations of the Electrical and Auxiliary systems and all other items not mentioned but necessary to complete the said work in accordance with the plans, specifications and other related documents. WORKS NOT INCLUDED The following items shall be furnished and installed by others and are, therefore, not included in the contract. 1. 2. Air-conditioning units Telephone units

C. 1.

2.

3.

4. 5.

6. 7. 8. 9.

2.2

133

PART 3 3.1

TECHNICAL SPECIFICATIONS WIRING METHODS Wiring shall be Rigid Steel Conduit (RSC) and corrugated, flexible PVC conduit.

3.2

GROUNDING The following shall be grounded in accordance with the Drawings and the requirements of the Philippine Electrical Code and with standard grouping practices. 1. Neutral of 460/277 VAC system if any.

2. Metallic conduits and raceway system including gutters, panelboards, cabinets and equipment. 3. Non-current carrying metal parts of all electrical equipment including fixtures and motors. Ground resistance shall not exceed 0.5 ohms. Additional ground rods shall be installed when necessary to obtain this amount. Exposed or accessible ground clamps, pressure connectors and/or ground connections shall be brazed. The CONTRACTOR'S attention is especially called to the double lockout requirements of Rule 2808 of the Philippine Electrical Code for conduits containing conductors operating at more than 250 volts to ground. 3.3 SERVICE ENTRANCE Service entrance shall be laid underground and should be enveloped with concrete from MDP to the concrete pedestal as shown in the Site Development Plan and Riser Diagram. Sizes and locations are also indicated in the Plans. 3.4 PANELBOARDS AND CABINETS Panelboard and cabinets shall be specified elsewhere in these Specifications. Panelboards shall be mounted with their centers at 1.4 meters above the floor unless otherwise dictated by field conditions. 3.5 FEEDERS Distribution voltage shall be 220 VAC, single phase, 2-wire unless other wise noted in the Drawings. Feeder conductors and conduits shall be installed as shown in the Drawings and no change in sizes shall be made without the consent of the ARCHITECT.

134

Feeder conductors shall be continuous and without splices between terminals and boxes. 3.6 BRANCH CIRCUITS The DRAWINGS indicate the general methods of installations of all circuit wiring and the outlets which are to be supplied from these circuits. Branch circuit conduits shall be run from outlets to panelboards as direct as building conditions will allow. Circuit allocations shall be indicated on the Drawings. Where it becomes necessary to correct any outlet to a circuit other than shown on the Drawings, this shall be done without extra charge and only upon written consent of the ARCHITECT. No wire smaller than 3.5 mm2 (# 12 AWG) shall be used for any lighting and power circuits. 3.7 LOCATIONS OF OUTLETS AND SWITCHES The approximate location of each fixture receptacle, special purpose outlet and switch is indicated on the Drawings. The exact location is to be determined later at the site as the work progresses. The right is reserved by the ARCHITECT to change the exact location of any switch, light and power outlet installed by the CONTRACTOR in such as manner as to be out of the building construction. Its position or location shall be corrected at the expense of the CONTRACTOR and under the direction of the ARCHITECT. Mounting the heights of outlets and switches shall be as called for on the Drawings. ALL MOUNTING HEIGHTS SHALL BE VERIFIED FROM THE ARCHITEC BEFORE ACTUAL INSTALLATION OF THE OUTLET BOXES. 3.8 WIRES AND CABLES Wires, cables and boxes shall be specified elsewhere in the Specifications. No wires shall be drawn into the raceway until works which may cause injury to the wires is completed and until permission is granted by the ARCHITECT in writing. Only powdered lubricant not injurious to cable insulations and raceways shall be used only when lubrication is necessary. Solderless pressure connectors of proper sizes shall be used for terminals, tape for splices of all wires and cables except for branch circuits in which case connectors shall be surely fastened and shall be such as not to loosen under vibrations and normal strain. Branch circuit splices shall be soldered or joined by the use of insulated splicing devices (wire nuts). All soldered joints must be made mechanically strong before soldering and shall be carefully soldered without the use of acid, then taped with rubber tape to a thickness equal to the insulation and with a covering of friction tape of two layers. 3M Scotch tape may be used in lieu of insulated wire nuts. Where conductors are to be connected directly to devices without the use of lugs, such as occurs at lighting switches and convenience outlets, the wires shall be

135

formed into a clockwise loop fitted around the screws. 3.9 OUTLETS, SWITCHES AND JUNCTION BOXES The CONTRACTOR shall install standard pressed steel boxes or cast metal boxes at all outlets for lights, power and switches and other points as required by the Construction. Boxes shall be of approved design and construction, and of such form and dimension as required to serve the kind of fixtures to be used and the number, sizes and arrangement of conduits connecting thereof. The allowable conductor fill as given in Rule 2486 of the Philippine Electrical Code should not be exceeded. Deep boxes, box rings and raised pressed covers shall be used when necessary to obtain the required conductor capacity. Boxes for outlets on auxiliary systems shall be specified elsewhere in these Specifications or shown in the Drawings. All boxes of whatever kind, for all systems shall be provided with a suitable fitting which shall be either a box or other device or locknut and bushing to receive and hold and device or fitting to be mounted. All boxes shall be painted with anti-rust lead paint after installation. 3.10 CONDUIT SYSTEM Conduit system shall be as specified elsewhere in these Specifications. Not more than four 90 degrees bend shall occur in any run. When it becomes necessary to have more than four 90 degree bends in any run, an intermediate pull box shall be installed to facilitate the pulling-in of wires. All conduit runs shall be as called for in the Drawings. Conduits shall be installed in such a manner as not to weaken or interfere with structure of the building. Conduits and tubings shall be concealed within finished wall, ceilings, steel framings or floor slabs. Exposed conduits shall be run parallel to at right angles with lines of the building and shall be securely fastened to walls by means of screws or bolts with expansion sleeves. The use of wooden or lead plug is not permitted. Conduits shall be cut by hacksaw, the ends shall be reamed after firmly attached to cabinets or boxes by means of locknuts and bushings. Fieldmade bends and offsets shall be avoided when possible, but when necessary shall be made in accordance with manufacturer's recommendations. Trapped raceways shall be avoided where possible. Care shall be made to avoid lodgment of dirt or trash in the conduits, tubing, boxes, fittings and equipment during the course of the construction .

136

Conduits below grade line or installed in the ground or fill beneath the floor slab shall be encased in a rectangular concrete envelop with a minimum thickness of 75mm (3"). 3.11 WIRING DEVICES Wiring devices shall be specified elsewhere in these Specifications and installed as called for in the Drawings. 3.12 LIGHTING FIXTURES The CONTRACTOR shall furnish and install all lighting fixtures as indicated in the Drawings, including mounting channels and supports. Where the Drawings call for incandescent lighting ceiling outlets of the screw-shell type, the ceiling receptacles and lamps shall be furnished and installed by the CONTRACTOR. Lighting fixtures shall conform to appropriate sections of these Specifications.

PART 4 4.1

SPECIFICATIONS OF MATERIALS AND TESTING Rigid Steel Conduits shall be hot-dipped galvanized mild steel pipe with an interior coating and shall be 3 meter lengths including and coupling. All conduits shall be Japanese manufactured or approved equal. PVC pipes shall be corrugated flexible electrical conduit.

4.2

Wires and cables shall be insulated for 600 volts. Feeder, branch circuit and service entrance cables should be copper, soft-drawn and annealed 98 % conductivity. They should be Type TW or THW as required by the Drawings. All wires and cables shall be Phelps Dodge or approved equal subject to the approval of the ARCHITECT. Conduit fitting shall be U.S. Underwriters Laboratories (UL) listed or approved local accessories. Panelboards for light and power shall conform to the indications in the Drawings with respect to supply characteristics and rating of main lugs or main breakers, number and size of branch circuit breakers. Panelboards and cabinets shall be dead-front type factory assembled of back plan, main busses, overcurrent and switching units. Cabinets shall be fabricated with code gauge galvanized sheet steel with cover capped and approved methods of casting. Cabinets shall permit suitable wiring gutter space all around at least 100 mm (4") or wider. Panelboards and trims shall be suitable for the type of mounting shown in the Drawings. The inside and outside of the panelboard cabinets and trims shall be factory painted and having one rust-proof prime coat and one finish shop of grey enamel paint. All cabinets and enclosures shall be general purpose, NEMA Type I

4.3

4.4

137

except where specifically noted in the Drawings. Circuit breakers for panelboards shall be molded case circuit breaker with quickmade, quick-break trip free mechanisms. They maybe either plug-in or bolted Qtype. Circuit breakers shall be as manufactured by GE, ITE, Westinghouse, Mitsubishi or its equivalent. Wiring devices shall be either NATIONAL, GE, VETO or approved equal. Wall switches shall be rated at least 10 amperes, 220 volts. Switches shall be of the outlet type, spring operated and thumbler type. Wall receptacles shall be flush mounted, duplex, rated 15 amperes, 250 volts, parallel slots without grounding slots unless specified in the Plans. Fluorescent fixtures shall be surface mounted, box type, equipped with a high power factor ballast, spring loaded lamp holder and standard daylight lamp. Fixture housing shall be baked enamel, white interior, gauge 22 minimum galvanized steel. Incandescent fixtures shall be of the porcelain ceiling receptacle type. The CONTRACTOR shall submit samples of the lighting fixtures for the approval of the ARCHITECT. GROUNDING All metallic conduits, panelboards and equipment requiring ground shall be properly grounded and bonded by means of copper straps. The conduits of each system shall be grounded by connecting to the nearest water service pipe. All ground connections shall have clean contact surfaces and shall be tinned and sweated while bolting. Unless otherwise specified, exposed ground cables shall be installed in conduits and connections made readily accessible for inspections. Connections shall not be made underground or concealed in floors or walls. Connections to ground rods shall be provided with ground walls. TESTING Ground Test - The entire installation shall be free from improper grounds and short circuits. All branch circuits shall be tested for ground and short defects in the presence of the ARCHITECT or the OWNER. Each panel shall be tested with mains connected to feeders and all homeruns connected to each assigned branch circuits. Each individual power feeder shall be tested with the power equipment connected for proper and intended operation. In no case shall the insulation resistance be less than that allowed by the regulations for electrical equipment in buildings. Failures and defects shall be corrected in a manner satisfactory to the OWNER. PERFORMANCE TEST - It shall be responsibility of the CONTRACTOR to test all systems of the entire electrical installation for proper operational conditions. These

conditions shall apply to the lighting and power installation as well as low voltage and alarm control signal and communications systems. Where phase sequence requirements is needed, the CONTRACTOR shall supply lines to conform to the phase sequence of the electrical equipment of the building.

4.9

GUARANTEE The CONTRACTOR shall guarantee that the electrical system is free from defects and defective workmanship and materials, and will remain so for a period of on (1) year from date of acceptance of work. Any defects appearing within the aforesaid period shall be remedied by the CONTRACTOR at his own expense.

139

You might also like