No
Task Description
Unit
A). General A1 A2 A3 A4 Fit Ventilator Fit Lighting Remove Lighting Remove Ventilator per manhole per manhole per manhole per manhole 15 Min 15 Min 15 Min 15 Min 1 1 1 1 1 1 1 1 0.5 Hours 0.5 Hours 0.5 Hours 0.5 Hours
B). Column B1 B2 B3 B4 B5 B6 B7 B8 B9 B10 Open Tray Manway Refit / Reinstate Tray Manway Packing Removal /Unloading Reload Packing Clean Internal Shell - SSPC-SP2 - CS Clean Internal Shell - SSPC-SP2 - SS/Others Clean Internal Shell - SSPC-SP3 - CS (Weldment area) Clean Internal Shell - SSPC-SP3 - SS (Weldment area) Clean all gasket seating surface @manhole - power brush & scrapping Wire brush all bolts (full length) & apply antisieze compound - replace defective bolts per trays per trays per Drum per Drum S/M/L S/M/L S/M/L S/M/L per equip per equip per equip per equip per equip per equip per equip per equip per equip per equip per equip 15 min 15 min 0.5 Hours 15 min 15 min 15 min 15 min 15 min 15 min 15 min 15 min 15 min 15 min 15 Min 15 Min 0.5 Hours 0.5 Hours
0.5 Hours 0.5 Hours 0.5 Hours 0.5 Hours 1 Hours 1 Hours 1 Hours 1 Hours
1 1 2 2
-
1 1
-
1 1 1
-
4 4 3
3
3
3
0.5 Hours 0.5 Hours 0.5 Hours 15 min 0.5 Hours 0.5 Hours 0.5 Hours 0.5 Hours 0.5 Hours 0.5 Hours 1 Hours
1 1 1
1 1 1
B11 Pre Inspection - Internal (Confined Space Entry) B12 Pre Inspection - External B13 Post Inspection - Internal (Confined Space Entry) B14 Post Inspection - External B15 NDT - Internal (Confined Space Entry) B16 NDT - External B17 DOSH Inspection B18 Final Inspection prior to Box up B19 Housekeeping C). H/Exchanger C1 C2 C3 C4 C5 C6 C7 C8 C9 Remove Spool Reinstall Spool Remove Channel Cover Refit Channel Cover Pull Tube Bundle (Critical) Pull Tube Bundle (Non Critical) Refit Tube Bundle (Critical) Refit Tube Bundle (Non Critical) High Pressure Water Jetting
1 -
1 1 2 -
per equip per equip per channel per channel per equip per equip per equip per equip per tube hole (Min) per bundle per tube hole (Min) per tube hole (Min) S/M/L S/M/L S/M/L S/M/L per cover S/M/L S/M/L S/M/L S/M/L per unit per unit per equip per equip per equip per equip per equip per equip per equip
15 min 30 min 2 Hours 2 Hours 0.5 Hours 1Hours 0.5 Hours 1Hours
0.5 Hours 1 Hours 4 Hours 4 Hours 1 Hours 1.5 Hours 1 Hours 1.5 Hours 3 min
2 2 2 2 2 2 2 2
1 1 1 1 1 1 1 1
1 1 1 1 2 1 2 1 1 1 1 1 1 1 1 1 1 1 1 2 2 1 1 2 2 1 1 2
24 Hours 28 Hours
C10 High Pressure Water Jetting external bundle cleaning C11 Air Blow (HEX Tube) C12 Air Blow (after HPWJ) C13 Surface Cleaning for Internal shell (SSPC-SP2) CS C14 Surface Cleaning for internal shell (SSPC-SP2) SS C15 Weldment Cleaning -Int. Shell (SSPC-SP3) CS C16 Weldment Cleaning -Int. Shell (SSPC-SP3) SS C17 Clean Channel Cover - Hydrojet C18 Clean Internal Channel Cover (SSPC-SP2) CS C19 Clean Internal Channel Cover (SSPC-SP2) SS C20 Clean Internal Channel Cover (SSPC-SP3) CS C21 Clean Internal Channel Cover (SSPC-SP3) SS C22 Cleaning Tube Sheet (SSPC-SP3) CS C23 Cleaning Tube Sheet (SSPC-SP3) SS C24 Leak Test (H/Exchanger-Pull Bundle) C25 Leak Test (H/Exchanger-Fixed Tube) C26 C27 Clean all gasket seating surface @channel head, flanges power brush & scrapping Wire brush all bolts (full length) & apply antisieze compound - replace defective bolts
0.5 Hours
1 1 -
15 min 15 min 15 min 15 min 15 min 0.5 Hours 0.5 Hours 1 Hours 1 Hours 0.5 Hours 0.5 Hours 15 min 15 min 0.5 Hours
1 Hours
0.5 Hours 0.5 Hours 0.5 Hours 0.5 Hours 1 Hours 1 Hours 1 Hours 1 Hours 1 Hours 1 Hours 1.5 Hours 1.5 Hours
2 2 1 1
4 Hours 4 Hours
C28 Pre Inspection & deposit sampling C29 Post Inspection C30 NDT Inspection
1.5 Hours
PLANNING NORMS FOR TURNAROUND - EQUIPMENT JOB BASIS Direct Manhour Resources FT 1 1 1 SS RG HLP 1 2 1 2 HJT Small
No
Task Description
Unit
TARGET TIME (Hours/Min) Small Medium (Hrs) Large (Hrs) (Hrs) 5 min 0.5 Hours 15 min 0.5 Hours 0.5 Hours 1 Hours
C31 NDT Inspection (IRIS/RFET/ECT) C32 DOSH Inspection C33 Final Inspection prior to Box up C34 Housekeeping D). Vessel D1 D2 D3 D4 D5 D6 D7 D8 D9 Remove Spool/top Elbow Refit Spool/top Elbow Remove Demister (Non Critical) Remove Demister (Critical)* - 2 layers demister Cleaning Demister Refit / Reinstate Demister Non Critical) Refit / Reinstate Demister (Critical) * Clean Internal Shell - SSPC-SP2 - CS Clean Internal Shell - SSPC-SP2 - SS/Others
per tube hole (Min) per equip per equip per equip
per equip per equip per equip per equip per equip per equip per equip S/M/L S/M/L S/M/L S/M/L per equip per equip per equip per equip per equip per equip per equip per equip per equip per equip per equip
15 min 30 min
1 Hours
2 2
1 1
1 1 1 2 2 1 2 3 3 1 1 2 2 1 1 1 1 1 1 1 1 2
2 2 2 2
-
1 -
1 Hours 1 Hours
2 Hours
1 Hours
3 Hours 2 Hours
0.5 Hours 0.5 Hours 0.5 Hours 0.5 Hours 0.5 Hours 0.5 Hours 0.5 Hours 0.5 Hours
D10 Clean Internal Shell - SSPC-SP3 - CS (Weldment area) D11 Clean Internal Shell - SSPC-SP3 - SS (Weldment area) D12 D13 Clean all gasket seating surface @manhole, flanges - power brush & scrapping Wire brush all bolts (full length) & apply antisieze compound - replace defective bolts
1 1 -
D14 Pre Inspection - Internal (Confined Space Entry) D15 Pre Inspection - External D16 Post Inspection - Internal (Confined Space Entry) D17 Post Inspection - External D18 NDT - Internal (Confined Space Entry) D19 NDT - External D20 DOSH Inspection D21 Final Inspection prior to Box up D22 Housekeeping E). AFC E1 E2 E3 E4 E5 Remove Tube Plug Air Blow (AFC Tube) High Pressure Water Jetting (tube cleaning) Refit Tube Plug Leak Test/ Hydrotest Vacuum debris inside fins tubes from external E6 E7 E8 E9 Pre Inspection & deposit sampling Post Inspection (After cleaning) NDT Inspection DOSH Inspection
0.5 Hours
1 Hours 15 min
0.5 Hours
per plug (Min) per tube hole (Min) per tube hole (Min) per plug (Min) per equip per equip per equip per equip per tube hole (Min) per equip per equip per equip
1 1 1
1 1 2
0.5 Hours 0.5 Hours 1 Hours 0.5 Hours 0.5 Hours 1 Hours
1 1 1 1 1 1
E10 Final Inspection prior to Box up E11 Housekeeping F). Filter F1 F2 Remove Filter Element Refit / Reinstate Filter Remove wire mesh screen Refit wire mesh screen F3 F4 F5 F6 Unloading Media Reloading Media Clean all gasket seating surface @manhole, flanges - power brush & scrapping Wire brush all bolts (full length) & apply antisieze compound - replace defective bolts
per equip per equip per layer per layer per Drum per Drum per equip per equip
1 1
1 1 -
1 1 1 1 1 1 2 2
1 1 1 1 -
1 Hours 1 Hours
Note: Use "Vessel" as guideline for cleaning, inspection, box-up & housekeeping. G). Furnace/Boiler. G1 G2 G3 G4 Opening / Closing access door Power brush for tube external cleaning Wire brush & cotton rag for tube external cleaning Burner removing / cleaning (incl.tubing) Reformer - Propose for direct loading supply resources per access door S/M/L S/M/L per burner tip
0.5 Hours 0.5 Hours
0.5Hours
1 Hours 1 Hours 1.5 Hours 1.5 Hours
1 1
1 1 1
1 1 -
1 Hours
PLANNING NORMS FOR TURNAROUND - EQUIPMENT JOB BASIS Direct Manhour Resources FT 1 1 1 SS RG 1 1 HLP 1 1 1 HJT Small
No
Task Description
Unit
G5 G6 G7 G8 G9
Burner installation (incl.tubing) Opening convection header box cover Closing convection header box cover Debris Removal - normal removal by scooping Vacuum cleaning
TARGET TIME (Hours/Min) Small Medium (Hrs) Large (Hrs) (Hrs) 0.5 Hours 0.5 Hours 0.5 Hours
Note: Use "Vessel" as guideline for inspection, box-up & housekeeping. H). Scaffolding - to propose volume/unit rate - For scheduling purpose only H1 H2 H3 H4 Erection External Scaffolding Erection Internal Scaffolding Dismantle External Scaffolding Dismantle Internal Scaffolding I). Insulation I1 I2 Insulation Removal Insulation Reinstatement Note: Equip. size category Medium Small 0.5m < M < 1.5m Heat Exchanger (Diamater) < 0.5m 1m < M < 2.5m Column/Vessel (Diameter) <1m Furnace/Boiler/Reformer : 10m x 10m < M < 25m x 25m a) Area < 10m x 10m 10m < M < 20m b) Height < 10m 5m < M < 20m c) Diameter < 5m Safety watch - Ratio base on total man entry Fire watch - Ratio base on requirement Deblinding/Close Manhole = included factor for MTW Method Target time Planned time allows for breaking the joint, inspect & clean flange faces. Large > 1.5m > 2.5m > 25m x 25m > 20m > 20m 1m 2 1m
2
1m 3 1m 1m
3
1 1 1 1
1m 3
3
10 min 15 min. `
1 1
1 1
1 2 3
4 5 6 7
Fitter
Semi skill
1/2" 3/4" 1" 1-1/2" 2" 3" 4" 2" 3" 4" 6" 8" 10" 12" 2" 3" 4" 6" 8" 10" 12" 14" 16" 18" 20" 24" 20" 24" 14" 16" 14" 16" 18" 20" 12" 14" 8" 10" 12"
A B C D
1"
45 min
30 min
45 min
30 min
70 min
60 min
3 2
12
16
215 min
240
215 min
240
20
24" 26" 28" 30" 32" 34" 36" 38" 18" 20" 20" 24" 24" 26" 28" 30" 32" 34" 36" 38" 40" 42" 44" 46" 48"
240 min
280
240 min
280
20
24
24" 20" 24" 28" 30" 32" 26" 28" 30" 32" 34" 20" 24" 34"
300 min
330
300 min
330
28
330 min
370
330 min
370
H I J K L
32 36 40
36" 38" 40" 42" 44" 46" 48" 50" 52" 54" 56"
44
48
58" 60"
NOTE: 1. Deblinding/Close Manhole = included factor for MTW Method Target time 2. Planned time allows for breaking the joint, inspect & clean flange faces. 3. Close Manhole = included factor for Box up Target time 4. Special Lens Ring Joint = if found badly defect, required for lapping (~8hrs).
PETRONAS AMMONIA SDN BHD PASB - 4th TURNAROUND 2010 PLANNING NORMS FOR TURNAROUND - REMOVAL & REINSTATEMENT PRESSURE SAFETY VALVES (PSVs)
Flange Rating & Size Category No of Bolt 150# 300# 600# 900# TARGET TIME (Min) REMOVAL OF PSVs REINSTATEMENT OF PSVs Fitter RESOURCES Semiskill Rigger
A B C D
1/2" 3/4" 1" 1-1/2" 2" 3" 4" 6" 8" 10" 12" 14" 16" 18" 20" 24" 2" 3" 4" 6" 8" 10" 12" 14" 16" 12" 14" 16" 18" 20" 24" 26" 28" 30" 32" 34" 36" 38" 14"
70
80
1 1 2 2 2
1 2 1 2 2
1 1 2
100 120
110 120
8 12 16
180 210
200 260
20
340
400
NOTE: 1. Deblinding/Close End Flange = included factor for MTW Method Target time 2. Planned time allows for breaking the joint, inspect & clean flange faces.
Prepared By:
Reviewed By:
Approved By:
A B C D
4
2" 3"
60
70
1 1 1 1
1 1 2 2
110
2" 3" 4" 6" 8" 10" 6" 8" 10" 12" 14" 16" 18" 20" 24" 8" 10" 12"
120 160
8 12
140
220
300
12"
16
420
450
20" 24"
14" 16"
12" 14" 16" 18" 20" 24" 26" 28" 30" 32" 34" 36" 38" 14"
20
460
480
18"
20" 24"
20"
24
24" 20" 24" 26" 28" 30" 32" 34" 20" 24" 24" 26" 28" 30" 32" 34" 36" 38"
46" 48"
G H I J K
NOTE:
28
32 36 40 44
34" 36" 38" 40" 42" 44" 46" 48" 50" 52" 54"
2 2 2 -
4 4 4 -
3 3 3 -
1. Deblinding/End Flange = included factor for MTW Method Target time 2. Planned time allows for breaking the joint, inspect & clean flange faces.