ABC Project COLOMBO 1.

Renovation and Restoration of ABC Building Employer : MEP Consultant Building Description. The building consist of One(01) Basement floor, Six(06) Over ground floors including mezzanine floor. Schedule of Floor Area Item Description Floor Area(Sqft) 1 Basement Floor 6905 2 Mezzanine Floor 710 3 Ground Floor 4434 4 First Floor 6550 5 Second floor 6023 6 Third Floor 5760 7 Fourth Floor 4835 Total Floor Area 35217sqft (=3271 sqm)

DESIGN BRIEF - ELECTRICAL INSTALLATION The purpose of this report is to establish principal design criteria, which forms the basis for development of the design.

1.

SCOPE OF WORKS. The scope of the electrical installation shall consist of the following. Power receiving system(Low voltage, 400V, 3 Phase from CEB) Low voltage generator system Low voltage power distribution Interior lighting provision Lightning Protection system Telephone PABX system and Data system/ Structured Cabling Master Antenna Television System (MATV)- (optional) Security System(CCTV system) Fire Detection system

2.

CODES AND REGULATIONS IEE (UK) Wiring regulations - 17TH Edition. (BS 7671) Code of Practice of Energy efficient building in Sri Lanka- 2008 Applicable Sri LankaFire Authority regulations

3.

DESIGN DESCRIPTIONS 01. a) Power receiving System The work shall exclude high voltage incoming line and transformers form local Electrical Power Authority. The metering facility at the low voltage(400V, 3 Phase, 4W, 50Hz) intake point to be provided by the Authority.

-1-

b)

Receiving Voltage 3 phase 4 wire 400v 50hz through one feeder .

c)

Distribution Transformer The distribution transformer location shall be the meter room at ground floor as per the requirement laid down by the CEB.

d)

Estimate of Maximum Electrical Demand The maximum demand of the development is approximately 400 KVA (with 10% Spare capacity) and shall be calculated on following basis. Diversities of the loads shall be based on recoded data of the International Practice. The lighting load as per Energy Efficient Building Code- Sri Lanka General purpose outlets (GPOs) - 180 VA/per outlet Plant and mechanical loads as per the Mechanical Services Design

02

Low Voltage Generator System In the event of mains power failure one number 300 kva prime rated generator set is provided (diesel engine driven built-in radiator type) to supply power to total load of the building. The stand by generator for the development shall be interlocked with the normal main supply to sense power supply failure so that it will automatically start up. Upon restoration of the mains supply the generator sets shall automatically stop after a pre-set interval which is adjustable. A day tank (sized for 8 hrs continues operation) shall be provided for the generator.

03

Low Voltage System a) The electrical distribution system shall be designed for 400/230V 3 phase 4 wire 50hz rated voltage and all equipment shall be suitable to operate under the rated voltage. The type of the feeder cable should be as follows.

b)

i)

Sub-main feeder from MSB to SDBS & DBS

PVC/PVC-Cu or XLPE/PVC- Cu Cables through Cable tray/ladder PVC-Cu single core cables through UPVC conduit / Trunking (In concealed area)

ii)

Final circuits from DBS to lighting, switch Socket outlets

c)

Supplies shall be distributed from the main switch board at Ground floor. Vertical distribution shall be through cables installed within main electrical riser. Voltage drop in cables shall not exceed 4% according to the IEE Regulations. Power Factor correction capacitor banks shall be installed at the main switch board.

-2-

d)

The power distribution to each tenant to be separately metered serving at least three tenants per floor. All Energy meters must be clustered at ground floor or remotely located with a display being located at ground floor.

04. Interior Lighting Provision and Socket Outlet Electrical scope of work considered only for point wiring . Supply luminaries is not included to the electrical work. a) General lighting for areas such as staircases, corridors, plant rooms, car-parks and circulation areas shall have fully enclosed fluorescent luminaries and point wiring shall be carried out under electrical work. Time switch c/w manual override switch will be used to operate extension and staircase lighting during certain interval of the day.

b) Lighting for building faade, lift lobbys, function rooms, snack bar etc. Will take into consideration aesthetic aspects. The selection of special lighting fixtures for these areas shall be under the guidance of the interior designer.

c)

Maintained type emergency lighting and illuminated Exit sign shall be provided to illuminate the escape paths, staircases, public areas and toilets during power failure. Supply of emergency lighting including point wiring shall be provided to the electrical work.

d) To decide the number of lighting points required for different areas, recommended illuminance is considered as follows.

RECOMMENDED ILLUMINANCE (GENERAL LIGHTING) Recommended Illuminance (LUX) 300 200 500 150 200 300

Location/Areas Entrance Halls / Lobbies Store Rooms General Offices Circulation areas, corridors and Staircases Lift lobbies Plantroom/ Gen Room/ Meter Room e)

The wiring to lighting points shall either be using lighting trunking or through neatly arranged casing made to BS standards. f) The wiring to socket outlet shall also be through three compartment trunking along the wall in order to accommodate for ELV services. As the tenant requirement may vary from one to other trunking system shall be with modular type outlets. g) The number of socket outlet shall be so selected in order cater the tenants requirement as well as landlord common facilities.

06

Lightning Protection System

-3-

A complete lightning protection system will be installed in accordance with the relevant British Standards or French standards. The lightning protection system will consist of a network of horizontal conductors on the roof and vertical down conductors which shall be terminated to the Earth Electrodes (Ground Floor Level), through inspection pits. The earthing resistance of the earth electrodes shall not be less than ten(10) ohms. If the system follows to French standard an early streamer type lightining rod and one or two down conductors with necessary earthing shall be provided.

07

Telephone PABX System and Data system/ Structured Cabling system Multipair cat 3 telephone cabling shall be run from Main Equipment Cabinet(MEC) to Secondary Equipment Cabinet(SEC). The wiring to telephone outlet shall be using 1 pair cat3 cables or 0.5mm telephone cables All Equipment cabinet shall have sufficient space to accommodate tenants PABX and or Data Switches.

The work scope of Telephone System will cover the following. i) Provide underground pipes from the boundary of the premises to location of MDF for incoming telephone cable supplied by the authority. Wiring of the internal distribution network through vertical shaft cable Trays and conduits. The PEO TV requirement shall also be coordinated with the telecom authority if needed.

ii)

iii)

The data system in order to provide LAN and internet facilities within the facility shall be provided. The data system shall comprise of i) ii) Cat 6 cabling to RJ45 outlets from SECs Cat 6 patch panels, 19 EIA racks, cable management panels, power rails, etc

iii) iv) v) vi)

Active componenets such as data switches- By others Rack mounted UPSs Termination and Certification Provide necessary routers in order to obtain ADSL or other internet services from the telecom authority.

08

Master Antenna Television System (MATV) The MATV System shall provide effective television reception over the frequency range on various bands available, VHF, and UHF . The signal received will be amplified by the receptive channelised amplifiers housed in a head and equipment cabinet located in the Fourth/Roof Floor.

-4-

The amplified signal will be distributed to each outlet by using splitters, couplers via coaxial cables in trunking/conduits. There will be TV outlets in public areas, function room , reception etc. In addition to terrestrial broadcast signals, PEOTV or Dialog TV facility for 16 channels shall be obtained from the relevant service provider. 09 Security System(Closed Circuit television System) The following security system are recommended. Closed Circuit Television (CCTV) System

a)

CCTV System The CCTV system will comprise the following. i) CCTV Cameras will be placed un-obstructively at strategic points throughout the building. In general, cameras will be installed at selected location of public areas such as Entrance lobbys, lift lobbies, and areas where high security is concerned within respective tenants occupied areas. Monitors for the cameras will be installed in the security office. These monitors shall be LCD colour monitors and connected to respective Digital Video recorder. The Digital Video recorder shall consist of 16 channels with recording storage facility for 14 days. All cabling shall be coaxial type of RG 59 or RG 6 with suitable braiding as recommended by the respective manufacturer. As an alternative solution, an IP based CCTV system shall be proposed in order to add value to the building under consideration.

ii)

iii)

iv)

v)

10)

Fire Alarm System a) Fire Alarm System i) Fire Alarm System shall be designed and installed in accordance with the BS 5489 part 1. An Addressable fire alarm panel with respective smoke, heat detectors and manual call points, sirens shall be provided. Fire detection and alarm equipment such as manual call points, smoke detectors, heat detectors, alarm bell shall be in accordance to provided and wired to the FA panel. This requirement shall be coordinated with respective fire authority.

ii)

iii)

iv)

-5-