WEEK NO. 74 ( 21-26 JULY, 2012 ) RAS AL KHAIR DESALINATION PLANT PHASE 1 PACKAGE "D" CIVIL and BUILDING WORKS Doosan Heavy Industries & Construction. Assad Said for Contracting Co.,Ltd.
WEEK NO. 74 ( 21-26 JULY, 2012 ) RAS AL KHAIR DESALINATION PLANT PHASE 1 PACKAGE "D" CIVIL and BUILDING WORKS Doosan Heavy Industries & Construction. Assad Said for Contracting Co.,Ltd.
WEEK NO. 74 ( 21-26 JULY, 2012 ) RAS AL KHAIR DESALINATION PLANT PHASE 1 PACKAGE "D" CIVIL and BUILDING WORKS Doosan Heavy Industries & Construction. Assad Said for Contracting Co.,Ltd.
RAS AL KHAIR DESALINATION PLANT PHASE 1 PACKAGE "D" CIVIL & BUILDING WORKS Doosan Heavy Industries & Construction. Assad Said For Contracting Co.,Ltd. 1 A. B. 2 A. B. C. 3 A. 4 A Document submittal list B. Material approval list C Method of statement list D Manpower & equipment status E. One Week Forecast Weather Report 5 PHOTOS WEEK NO. 74 ( July 21,2012 - July 26,2012 ) CONSTRUCTION TABLE OF CONTENTS Civil Works QA/QA Area of Concrete ( weekly concrete casting ) MRIR Weekly Status RFI Weekly Status APPENDIX Building Works RAS AL KHAIR DESALINATION PLANT PHASE 1 PACKAGE "D" CIVIL & BUILDING WORKS EHS EHS Weekly Doosan Heavy Industries & Construction. Assad Said For Contracting Co.,Ltd. WEEK NO. 74 ( JULY 21 2012 - JULY 26,2012 ) 1. CONSTRUCTION RAS AL KHAIR DESALINATION PLANT PHASE 1 PACKAGE "D" CIVIL & BUILDING WORKS Doosan Heavy Industries & Construction. Assad Said For Contracting Co.,Ltd. A. SWITCHGEAR FOR MSF A.1 MSF 71-72 1 Switchgear Room ( North side ) ---- Final painting of walls and ceiling are completed. Also, repairing for floor prior for final coat. Switchgear Room ( South side ) ---- First painting of walls and ceiling are completed. Repairing prior to final coat is on-going 2 Transformer Foundation ---- Lean concrete & waterproofing membrane are completed. 3 Office Room ( Floor ) ---- Floor tiles are already installed last July 24, 2012 4 Staircase ( Both side ) ---- Application of putty & primer are finished. 5 I & C Room ---- Grouting for electrical channels, and some areas of wall are already applied with putty & primer. A.2 MSF 73-74 1 Parapet ---- We closed already the south side and half of west side. Starting date for shuttering is July 18,2012 2 Basement ---- Repairing/ preparation prior to application of putty & primer are completed last July 18,2012 A.3 MSF 75-76 1 Roof Beam & Slab ---- Scaffoldings & supports are completed last July 24,2012 ---- Also, fabrication of sidings & installation of bottom for beams start last July 23,2012 A.4 MSF 77-78 1 Ground Columns ---- Fabrication of reinforcement for columns are completed and ready for erection/installation ---- We already casted kickers as construction procedures last July 25,2012 ---- Fabricated column forms are available already at site. B. INTAKE CHANNEL AND PUMPING STATION B.1 SWITCHGEAR FOR SEA WATER INTAKE 1 Block Works ---- Almost 95% completed. 2 Plastering Works ( Inside ) ---- Almost 65% completed inside the building. B.2 ELECTRO-CHLORINATION BUILDING 1 Outdoor Foundation MF5 ---- Lean concrete is casted already. This area is ready for waterproofing. 2 Ground Floor ---- Preparation for hollow blocks installation started last July 26, 2012 B.3 CHEMICAL STORAGE FOR MSF 1 Foundations ---- 55% are already casted, 15% for on going formworks and 15% for rebar works and 15% for surface preparation C. REMINERALIZATION C.1 SWGR BLDG FOR POTABILIZATION 1 Parapet ---- We put inside forms already at the south side and half of west side. Starting date for installation of forms is July 16,2012 2 Basement Ceiling & Wall ---- C.2 GAS CHLORINATION BUILDING 1 Grid/Ground Beam ---- C.3 LIME STORAGE BUILDING ---- C.4 DRINKING & SERVICE WATER PUMP HOUSE ---- C.5 SHELTER FOR WATER ANALYZER ---- C.6 WAREHOUSE FOR SPARE PARTS ---- D. PARKING SHED ---- E. MISC. WORKS ---- Period Covered: Week No. 47 ( 21-26 JULY, 2012 ) RAS AL KHAIR DESALINATION PLANT PHASE 1 PACKAGE "D" CIVIL & BUILDING WORKS WEEKLY SITE ACTIVITY PROGRESS REPORT MSF Plant Civil Works BUILDING WORKS Application of first coat for ceiling & walls are completed last July 26,2012 Casting of south side completed last July 22,2012. Only balance is East side No activity N/A N/A N/A N/A N/A Doosan Heavy Industries & Construction. Assad Said For Contracting Co.,Ltd. Period Covered: Week No. 47 ( 21-26 JULY, 2012 ) RAS AL KHAIR DESALINATION PLANT PHASE 1 PACKAGE "D" CIVIL & BUILDING WORKS WEEKLY SITE ACTIVITY PROGRESS REPORT Doosan Heavy Industries & Construction. Assad Said For Contracting Co.,Ltd. A. SITE PREPARATION RGF / LAB. WORKS ---- Third Party is present upon request, concreting & testing. B. EVAPORATOR FOUNDATION Evaporator #76 Inside ---- Backfilling & Compaction of crashed stones. Balance is part 1 of evaporator 76. C. EVAPORATOR MISCELLANEOUS FOUNDATION 1 EVA. UNIT # 71 F39 Foundation ---- Soil Preparation completed. It is ready for Lean concrete. ( starting date : July 25,2012 ) 2 EVA. UNIT # 72 CEP System Foundation ( 2 Nos ) ---- Flash Tank Foundation ---- Base slab Casted last July 25,2012 Ball Cleaning Panel , Ball Cleaning skid Fdn. ---- Screed & Lean Concrete finished. F4 Foundation between 19 & 20 pedestals ---- Casted already. 3 EVA. UNIT # 73 F3, F12 ( 2 Nos. ) and F12-1 Pedestal ---- Rebars completed, ready for closure of forms. 4 EVA. UNIT # 74 F3, F2-1 , F 12 ( 2 Nos. ) Foundations ---- Lean concrete complete last July 26,2012 Ball Cleaning Panel SF1 , SF2 ---- Lean concrete complete last July 26,2012 5 EVA. UNIT # 75, 76. 77 & 78 No Activity for Misc. Foundation D. BRINE HEATER FOUNDATION 1 Flat Form F5, F6, F7, F8 , F9 @ Unit 76 ---- Lean concrete complete last July 19,2012 ( Ready for waterproofing membrane ) E. BRP/BBDP/DP PIT 1 EVA. UNIT # 71 & # 72 ---- Already installed. 2 EVA. UNIT # 73 BRP1 & BRP 2 ---- Surface preparation prior for painting, Completed 2 EVA. UNIT # 74 ---- 3 EVA. UNIT # 75 Pedestals w/ plate @ A1-B1 ---- Installation of forms/Closure , 63% completed 4 EVA. UNIT # 76 BRP 1 ( 2nd lift ) ---- Installation of corbels forms & alignment , 92% completed 5 EVA. UNIT # 77 Dearator Wall ( B2 ) ---- Rebarworks are completed. Ready for formworks/closure. Dearator Wall ( B1 ) ---- Rebarworks are completed. Ready for formworks/closure. 6 EVA. UNIT # 78 Deaerator Foundation B2 ( Base Slab ) ---- Rebarworks are completed. Ready for formworks/closure. B3 Columns ---- Scaffoldings, Completed & Rebarworks start last July 26,2012 F. SEMI GANTRY CRANE ---- G. LP STEAM FOUNDATION Pipe Rack Foundation F2 ( 4 Nos ) Pedestal ---- Casted already, Removal of forms last July 26,2012 at Unit 71 H. CHEMICAL DOSING ---- I. CIVIL WORKS FOR SW SUPPLY PIPE North of Unit 74-75 ---- SC1 Backfilling around pipes started July 25,2012, On-Going West Side of Unit 71 to MSF 71-72 Bldg. ---- Ordinary Backfilling started July 25,2012, On-Going Pipe Protection Slab Wall Type 4 ---- Pipe Protection slab ( near Electro Bldg. ) ---- Rebar works start last july 25,2012 J. CIVIL WORKS FOR DISCHARGE PIPE North of Unit 74-75 ( in between ) ---- SC1 Backfilling around pipes completed North of Unit 76 ---- SC1 beddings completed East side of Unit 73 ( beside BRP ) ---- Soil Preparation & SC1 Bedding completed No activity No activity N/A Waterproofing membarane completed Rebar works completed, 60% completed for formworks CIVIL WORKS Zone 1 MSF Plant Civil Works Period Covered: Week No. 47 ( 21-26 JULY, 2012 ) RAS AL KHAIR DESALINATION PLANT PHASE 1 PACKAGE "D" CIVIL & BUILDING WORKS WEEKLY SITE ACTIVITY PROGRESS REPORT Doosan Heavy Industries & Construction. Assad Said For Contracting Co.,Ltd. K. CIVIL WORKS FOR DISTILLATE PIPE North of Unit 74 - 75 ---- SC1 Backfilling around pipes started July 25,2012, On-Going North of Unit 73 - 74 ---- SC1 Backfilling around pipes started July 25,2012, On-Going Flushing Line ( Acid Cleaning ) ---- SC1 Bedding completed. Some area excavation started. L. CIVIL WORKS FOR EVAPORATOR CABLE ROUTE 1 EVA. UNIT # 71 DB 07 & DB 04 Bet. CP 46-48 ---- Primer for waterproofing membrane applied . Balance is membrane and protection board. Pump Pit Cover ---- Rebars, completed. Formworks is almost 65 % DB 11 Extension @ CP 48 ---- Casted July 21,2012 DB 11 Extension @ CP173 & CP174 ---- Casted already DB 11 Extension @ CP 157 ---- Casted already 2 EVA. UNIT # 72 DB 07 bet. CP55 & CP 56 ---- Waterproofing for screed completed last July 23,2012 CP 57 and CP 58 Wall ---- Rebars completed. Also 20% formworks DB 09 - 4 ( 2 Nos ) Bet. CP60 & CP 156 ---- Lean concrete casted & waterproofing membrane completed. CP63, CP64 , CP65 , CP182 , & CP 183 ---- First Coat painting applied. 3 EVA. UNIT # 73 CP-72 Wall CP-86 Wall CP 75, CP76, & CP77 Walls ---- Rebars completed, 15% for formworks F40 ---- Lean concrete casted & waterproofing membrane installed. DB-05 Bet. 141 & CP 142 ---- Casted last July 25,2012 DB 11-2 bet CP214 & CP 215 ---- Casted last July 23,2012 4 EVA. UNIT # 74 CP 85 ---- Excavation started, Preparation for lean concrete is on going. DB11-8 Extension @ CP211 ---- Casted CP 221 ---- Formworks is about 80% CP 144 Wall ---- Casted CP 190 & CP191 base slab ---- Casted Last July 21,2012 7 EVA. UNIT #75, #76 ,#77 & # 78 NO ACTIVITY For This Area 8 Other Area CP 02 & CP 05 ---- Rebars completed. Ready for formworks/closure DB 10-05 bet CP 156 & CP 178 ---- Casted July 24,2012 TRENCH #1 ---- 5% rebarworks MH 06 ( Near seawater Intake bldg. ) ---- Casted July 22,2012 M. ROAD AND PAVING FOR EVAPORATOR - N/A N. FIRE FIGHTING FOR EVAPORATOR - N/A O. LIGHTING POLE FOR EVAPORATOR - N/A P. FENCE AND GATE - N/A Q. DRAINAGE AND SEWAGE FOR EVAPORATOR - N/A R. DRAINAGE AND SEWAGE FOR POWER PLANT - N/A S. AUXILLARY PIPE FOR EVAPORATOR SF 40 ( 3 nos. ) Pedestal @ unit 71 ---- Casted SF28 ( 2 Nos ) , SF 40 ( 2 nos. ) ---- Casted SF 19 ( 2 nos. ) SF 15, 17 , 20, 21, 23, 42 ---- Casted SF 12 ---- Casted SF13 ( 2 nos ) ---- Casted T. BY PASS LINE FOR R.O. TEMPERING - N/A A1. SITE PREPARATION FOR REMIN. A1.a RGF / LAB. WORKS ---- Third Party is present upon request, concreting & testing. B1. REMINERALIZATION PLANT B1.a Limestone Filter Foundation ---- Backfilling of crashed stones completed Zone 2 **** Formworks & soil preparation is on going Period Covered: Week No. 47 ( 21-26 JULY, 2012 ) RAS AL KHAIR DESALINATION PLANT PHASE 1 PACKAGE "D" CIVIL & BUILDING WORKS WEEKLY SITE ACTIVITY PROGRESS REPORT Doosan Heavy Industries & Construction. Assad Said For Contracting Co.,Ltd. B1.b Concrete Pit For Static Mixer ---- Casted, removal of forms completed C1. CIVIL WORKS FOR REMIN. CABLE ROUTE CP 9 Wall ---- Rebar works completed , Installation of forms about 80% CP 10 Wall ---- Casted last July 25,2012 D1. ROAD AND PAVING FOR REMIN - N/A E1. FIRE FIGHTING FOR REMIN - N/A F1. LIGHTING POLE FOR REMIN - N/A G1. DRAINAGE AND SEWAGE FOR REMIN - N/A H1. AUX. PIPE FOR REMIN - N/A A2. ROAD AND PAVING FOR RO - N/A Verified by : Approved by: Engr. Aries Hernandez Office Engineer Prepared by: Engr. Roger Betania Chief-Office-Engineer Project Manager Engr. Shaik Shafiullah Zone 8 WEEK NO. 74 ( JULY 21 2012 - JULY 26,2012 ) 2. QA / QC RAS AL KHAIR DESALINATION PLANT PHASE 1 PACKAGE "D" CIVIL & BUILDING WORKS Doosan Heavy Industries & Construction. Assad Said For Contracting Co.,Ltd. Page 9 of 75 Date Time 1 MSF # 74 Sump Pit Pump Pit Unit # 74 Foundation July 21, 2012 5:45 17.00 5:45 hrs to 6:05 hrs 2 Building Gas Chlorination Gas Chlorination Bldg, Grade Beams At Grid A/3-6,B/1-8& Bet.A-B/3&6 July 21, 2012 8:00 16.00 8:00 hrs to 8:20 hrs 3 Cable Route Cable Pit Cable Pit, CP-190 & 191 Base Slab July 21, 2012 8:35 7.00 8:35 hrs to 8:45 hrs 4 Steam Pipe (Z1) AUX Steam Pipe & AUX Pipe Foundation SF15,24,27-1,29,29-1&30 (1ea.), SF28 (2nos.)&SF40(2nos) Pedestals, Unit # 72- (As Shown) July 21, 2012 10:00 15.00 10:00 hrs to 10:20 hrs 5 Cable Route Duct Bank Duct Bank, DB-11 Connection @ CP-48 South Side July 21, 2012 10:25 4.00 10:25 hrs to 10:30 hrs 6 Cable Route Duct Bank Duct Bank, DB-11 Connection @ CP-173 South Side July 21, 2012 10:35 7.00 10:35 hrs to 10:45 hrs 7 Cable Route Duct Bank Duct Bank, DB-11 Connection @ CP-174 North Side July 21, 2012 10:55 9.00 10:55 hrs to 11:05 hrs 8 MSF # 72 Misc. Misc. Foundation F1,F3&F4 At Grid B3, Unit # 72- Area B July 21, 2012 11:07 15.00 11:07 hrs to 11:20 hrs 9 Building Chemical Storage Chemical Storage Bldg. Footings At Gridline D/1-7,E&F/6-8- Foundation July 22, 2012 6:00 45.00 6:00 hrs to 8:00 hrs 10 Cable Route Cable Pit Cable Pit, CP-144 Wall July 22, 2012 9:00 7.00 9:00 hrs to 9:10 hrs 11 Steam Pipe (Z1) AUX Steam Pipe & AUX. Pipe Foundation,SF12,14&40 (1ea.) Pedestals, Unit # 71 (As Shown)- July 22, 2012 9:15 10.00 9:15 hrs to 9:25 hrs 12 MSF # 71 Pipe Rack Pipe Rack Foundation F-2 (4nos.) Pedestals, Evap # 71 (As Shown) July 22, 2012 9:30 0.50 9:30 hrs to 9:33 hrs 13 MSF # 72 Misc. Misc. Foundation F4, Bet. 19 &20 Pedestal, Unit # 72 July 22, 2012 9:40 4.00 9:40 hrs to 9:45 hrs 14 Cable Route Duct Bank Duct Bank, DB-11 Connection @ CP-157 West Side July 22, 2012 9:50 5.50 9:50 hrs to 10:00 hrs 15 Cable Route Duct Bank Duct Bank, DB-11-2 Bet. CP-214&215 July 23, 2012 6:00 9.00 6:00 hrs to 6:10 hrs 16 Cable Route Duct Bank Duct Bank, DB-11-8 Connection @ CP-211 East Side July 23, 2012 6:35 8.00 6:35 hrs to 6:45 hrs 17 MSF # 72 Flash Tank Misc. Foundation Flash Tank, Unit # 72 July 24, 2012 7:05 8.00 7:05 hrs to 7:10 hrs 18 Cable Route Cable Pit Cable Trench Arrangement Plan-B-M/H-06, Wall July 24, 2012 7:20 7.00 7:20 hrs to 7:30 hrs 19 MSF # 72 Misc. Misc. Foundation F5 (1 no) Bet. Grid 20&21, Pedestal Unit # 72 @ Precast Yard- (As Shown) July 24, 2012 9:25 2.00 9:25 hrs to 9:28 hrs 20 MSF # 72 Misc. Misc. Foundation F32 (1no.) near Grid B, Pedestal, Unit # 72 As Shown- ASC Precast Yard July 24, 2012 9:30 1.00 9:30 hrs to 9:33 hrs 21 Steam Pipe (Z1) AUX Steam Pipe & AUX Pipe Foundation SF32 (1no) Pedestal, Unit # 72- (As Shown) @ ASC Precast Yard July 24, 2012 9:36 1.00 9:36 hrs to 9:38 hrs 22 Cable Route Duct Bank Duct Bank, DB-10-5 Bet. CP-156&178 July 25, 2012 6:05 9.00 6:05 hrs to 6:15 hrs 23 Cable Route PTP Cable Pit, CP-10 Wall July 25, 2012 8:45 7.00 8:45 hrs to 8:55 hrs 24 Cable Route Duct Bank Duct Bank, DB-05 Bet. CP-141&142 July 25, 2012 9:45 20.00 9:45 hrs to 10:10 hrs 25 Building Switch Gear Bldg. SWGR Bldg. for MSF Area Kicker Columns, Unit # 77 & 78 July 25, 2012 10:15 1.00 10:15 hrs to 10:18 hrs 235.00 m 26 Cable Route Duct Bank Duct Bank, DB-09-4 Bet. CP-60&156 July 22, 2012 8:05 11 8:05 hrs to 8:15 hrs 27 Building Electro Chlorination Electro Chlorination Bldg. Out Door Foundation MF5- As Shown July 22, 2012 8:20 3 8:20 hrs to 8:25 hrs 28 Unit # 74 misc. Misc. Foundation F-3, F-12 (2 nos), F-12-1, SF-1&2 Bet. Gridline 16 to 21, Unit # 74 (As Shown)-Part 01 of 02 July 25, 2012 6:55 1 6:55 hrs to 6:58 hrs 29 Unit # 74 Misc. Misc. Foundation F-3, F-12 (2 nos), F-12-1, SF-1&2 Bet. Gridline 16 to 21, Unit # 74 (As Shown)-Part 01 of 02 July 26,2012 6:55 3 6:55 hrs to 6:58 hrs 18.00 m 30 Unit # 73 Misc. Misc. Foundation F40, Unit # 73 July 23, 2012 6:50 1 6:50 hrs to 6:53 hrs 31 Unit # 71 Trench Trench # 1 & Aux Pipe, Unit # 71 July 23, 2012 7:40 7 7:40 hrs to 7:50 hrs TOTAL Quantity : LEAN CONCRETE SCREED CONCRETE RAS AL KHAIR DESALINATION PLANT PHASE 1 PACKAGE "D" WEEKLY CONCRETE CASTING REPORT DATE COVERED :WEEK NO. 74 ( 21-26 JULY,2012 ) TOTAL Quantity : Quantity in M 3 Remark REINFORCED CONCRETE Sl. No Unit Type Of Structure Description Of work Concrete Pouring Doosan Heavy Industries & Construction. Assad Said For Contracting Co.,Ltd. Page 10 of 75 Date Time RAS AL KHAIR DESALINATION PLANT PHASE 1 PACKAGE "D" WEEKLY CONCRETE CASTING REPORT DATE COVERED :WEEK NO. 74 ( 21-26 JULY,2012 ) Quantity in M 3 Remark Sl. No Unit Type Of Structure Description Of work Concrete Pouring Doosan Heavy Industries & Construction. Assad Said For Contracting Co.,Ltd. 32 Unit # 72 Misc. Misc. Foundation Ball Cleaning & Panel, Unit # 72 July 24, 2012 7:50 0.3 7:50 hrs to 7:53 hrs 33 Cable Route Duct Bank Duct Bank, DB-07 Bet. CP-55 & 56 July 24, 2012 7:58 0.2 7:58 hrs to 8:00 hrs 34 Building Chemical Storage Chemical Storage Buildings Footings At Grid B/1-11 July 24, 2012 8:05 6.5 8:05 hrs to 8:15 hrs 15.00 m AS SUMMARY : DATE Lean Screed Structural Production per Day ( M ) July 21,2012 0 0 90 90 July 22,2012 14 0 72 86 July 23,2012 0 8 17 25 July 24,2012 0 7 19 26 July 25,2012 1 0 37 38 July 26,2012 3 0 0 3 TOTAL : 18 15 235 268 Prepared by : ENGR. ARIES HERNANDEZ Office Engineer TOTAL Quantity : ENGR. SHAIK SHAFIULLAH Project Manager ENGR. ROGER BETANIA Chief-Office-Engineer Approved by: Verified by : Page 11 of 75 Sl. DF-EF-I- Dept. Mat. No. Submit Date Location Date of Inspection Time of Inspection Item Description ITP Op. No. Doosan Point Owner Point DRAWING NO. Cont. Representative from (ASSAD SAID) Cont. Representative from (Doosan) Doosan Recd on Status ASC Recd on Concrete Casting Date Vol. of Concrete ( m ) Remark 1 5222 Civil N/A 7/19/2012 Steam Pipe & AUX Pipe Foundation SF32 (1no) Pedestal, Unit # 72- (As Shown) @ ASC Precast Yard July 21, 2012 8:15 AM Formworks/ Concreting CW03/ CW06 W W 70-UMY-CLD-002 (Rev.0a), 70-UMY-CLB-006 (Rev.0) Md. Hamza R.C.Basco 19/Jul/12 CLOSED July 24, 2012 1 2 5223 Civil N/A 7/19/2012 Cable Pit, CP-144 Wall July 21, 2012 10:00 AM Formworks/ Concreting CW03/ CW06 W W 70-UBZ-CLD-005 (Rev.3a)& 70-UBZ-CLB-017 (Rev.3a) Md. Hamza R.C.Basco 19/Jul/12 CLOSED July 22, 2012 7 3 5224 Civil N/A 7/19/2012 Duct Bank, DB-11-2 Bet. CP-214&215 July 21, 2012 10:00 AM Embedments /Formwork CW04/C W03 W W 70-UBZ-CLD-004 (Rev.3b) & 70-UBZ-CLB-011 (Rev.3a) Md. Hamza R.C.Basco 19/Jul/12 CLOSED 4 5225 Civil N/A 7/19/2012 Duct Bank, DB-11-2 Bet. CP-214&215 July 21, 2012 10:30 AM Concreting CW06 W W 70-UBZ-CLD-004 (Rev.3b) & 70-UBZ-CLB-011 (Rev.3a) Md. Hamza R.C.Basco 19/Jul/12 CLOSED July 23, 2012 9 5 5226 Civil N/A 7/19/2012 Steam Pipe & AUX. Pipe Foundation,SF12,14&40 (1ea.) Pedestals,Unit # 71 (As Shown)- July 21, 2012 10:45 AM Formworks/ Concreting CW03/ CW06 W W 70-UMY-CLD-002 Rev.0a)& 70-UMY-CLB-003/008 (Rev.0) Md. Hamza R.C.Basco 19/Jul/12 CLOSED July 22, 2012 10 6 5227 Civil N/A 7/19/2012 Cable Pits, CP-57&58 Walls July 21, 2012 11:30 AM Reinforcement /Embedments CW04/05 W W 70-UBZ-CLD-004 (Rev.3b)& 70-UBZ-CLB-017 (Rev.3a) Md. Hamza R.C.Basco 19/Jul/12 Open Not Ready 7 5228 Civil N/A 7/19/2012 Misc. Foundation F-3, F-12 (2 nos), F-12-1, SF-1&2 Bet. Gridline 16 to 21, Unit # 74 (As Shown) July 21, 2012 10:35 AM Release for Blinding Concrete CW02 W H 70-UXB-CLD-001 (Rev.1b) Md. Hamza R.C.Basco 19/Jul/12 CLOSED July 25, 2012 1 7 5229 Civil N/A July 21, 2012 Misc. Foundation CEP System Foundation (1no.), Unit # 72-As Shown July 22, 2012 8:00 AM Reinforcement /Embedments CW04/05 W W 70-UXB-CLD-002/023 (Rev.0) Md. Hamza R.C.Basco 21/Jul/12 CLOSED 8 5230 Civil N/A July 21, 2012 Steam Pipe & AUX Pipe Foundation SF40 (3nos) Pedestal, Unit # 71- (As Shown) July 22, 2012 8:15 AM Reinforcement /Embedments CW04/05 W W 70-UMY-CLD-002 (Rev.0a), 70-UMY-CLB-008 (Rev.0) Md. Hamza R.C.Basco 21/Jul/12 CLOSED 9 5231 Civil N/A July 21, 2012 Cable Pits, CP-63,64,65,182&183 July 22, 2012 8:30 AM Surface Preparation Prior to Primer or 1st Coat Application PW02 H W 70-UBZ-CLD-004 (Rev.3b) & 70-UBZ-CLB-017 (Rev.3a) Md. Hamza R.C.Basco 21/Jul/12 Open Not Ready 10 5232 Civil N/A July 21, 2012 Storm Drainage System CP36 Type(D-1) Bet. Evap # 71&72- Foundation @ ASC Precast Yard July 22, 2012 8:45 AM Reinforcement /Embedments CW04/05 W W 70-UZG-CLD-005 (Rev.0) & 70-UZG-CLB-004 (Rev.0) Md. Hamza R.C.Basco 21/Jul/12 CLOSED 11 5233 Civil N/A July 21, 2012 Cable Trench Arragement Plan-B-M/H-06, Wall July 22, 2012 9:15 AM Formworks/ Concreting CW03/ CW06 W W 70-UBZ-CLD-007 (Rev.2b) Md. Hamza R.C.Basco 21/Jul/12 CLOSED July 24, 2012 7 12 5201 (1) Civil N/A 21-Jul-12 SWGR Bldg. for Post Treatment Bldg. Parapet Walls At Grid A-C/1-9 July 22, 2012 9:30 AM Reinforcement /Embedments CW04/05 W W 85-UBX-CLC-010 (Rev.0b) & 85-UBX-CLC-017 (Rev.0) Md. Hamza R.C.Basco 21/Jul/12 Open Resubmission ( Not Ready ) 13 5234 Civil N/A July 22, 2012 Cable Pit, CP-10 Wall July 23, 2012 8:00 AM Formworks/ Concreting CW03/ CW06 W W 70-UBZ-CLD-002 (Rev.3b)& 70-UBZ-CLB-016 (Rev.2b) Md. Hamza R.C.Basco 22/Jul/12 CLOSED July 25, 2012 7 14 5235 Civil N/A July 22, 2012 Cable Pit, CP-85 July 23, 2012 8:00 AM Release for Blinding Concrete CW02 W H 70-UBZ-CLD-005 (Rev.3a) Md. Hamza R.C.Basco 22/Jul/12 CLOSED 15 5236 Civil N/A July 22, 2012 SWGR Bldg. for MSF Area SWGR Room Floor, Unit # 71 & 72 July 23, 2012 8:45 AM Surface Preparation Prior to Primer or 1st Coat Application PW02 H W 70-UBX-CLH-102/106 (Rev.1) Md. Hamza R.C.Basco 22/Jul/12 CLOSED 16 5237 Civil N/A July 22, 2012 Misc. Foundation F5 (1 no) Bet. Grid 20&21, Pedestal Unit # 72 @ Precast Yard- (As Shown) July 23, 2012 8:15 AM Formworks/ Concreting CW03/ CW06 W W 70-UXB-CLD-001 (Rev.1b),70-UXB-CLB-002 (Rev.1) Md. Hamza R.C.Basco 22/Jul/12 CLOSED July 24, 2012 1.5 17 5238 Civil N/A July 22, 2012 Misc. Foundation Flash Tank, Unit # 72 July 23, 2012 8:30 AM Reinforcement/ Embedments/ Formwork CW05/C W04/CW 03 W W 70-UXB-CLD-002 (Rev.0) & 70-UXB-CLB-021 (Rev.0) Md. Hamza R.C.Basco 22/Jul/12 CLOSED 18 5239 Civil N/A July 22, 2012 Misc. Foundation Flash Tank, Unit # 72 July 23, 2012 9:15 AM Concreting CW06 W W 70-UXB-CLD-002 (Rev.0) & 70-UXB-CLB-021 (Rev.0) Md. Hamza R.C.Basco 22/Jul/12 CLOSED July 24, 2012 8 19 5240 Civil N/A July 22, 2012 Cable Pits, CP-75,76&77 Walls July 23, 2012 8:05 AM Reinforcement/ Embedments CW04/05 W W 70-UBZ-CLD-004 (Rev.3b) & 70-UBZ-CLB-017 (Rev.3a) Md. Hamza R.C.Basco 22/Jul/12 CLOSED 20 5241 Civil N/A July 22, 2012 Misc. Foundation CEP System Foundation (1no.), Unit # 72-As Shown July 23, 2012 8:20 AM Reinforcement/ Embedments CW04/05 W W 70-UXB-CLD-002/023 (Rev.0) Md. Hamza R.C.Basco 22/Jul/12 CLOSED 21 5242 Civil N/A July 22, 2012 Storm Drainage System DMA22- Type-A-3 Bet. Evap # 71&72-@ ASC Precast Yard July 23, 2012 8:25 AM Reinforcement/ Embedments CW04/05 W W 70-UZG-CLD-005 (Rev.0) & 70-UZG-CLB-004 (Rev.0) Md. Hamza R.C.Basco 22/Jul/12 CLOSED 22 5243 Civil N/A July 23, 2012 Cable Pits, CP-02&05 Walls July 24, 2012 8:00 AM Reinforcement/ Embedments CW04/05 W W 70-UXB-CLD-002 (Rev.2c) & 70-UXB-CLB-016 (Rev.2d) Md. Hamza R.C.Basco 23/Jul/12 CLOSED 23 5244 Civil N/A July 23, 2012 Duct Bank, DB-10-5 Bet. CP-156&178 July 24, 2012 9:00 AM Reinforcement/ Embedments/Formworks CW05/C W04/CW 03 W W 70-UXB-CLD-002 (Rev.2c) & 70-UXB-CLB-011 (Rev.3a) Md. Hamza R.C.Basco 23/Jul/12 CLOSED 24 5245 Civil N/A July 23, 2012 Duct Bank, DB-10-5 Bet. CP-156&178 July 24, 2012 9:45 AM Concreting CW06 W W 70-UXB-CLD-002 (Rev.2c) & 70-UXB-CLB-011 (Rev.3a) Md. Hamza R.C.Basco 23/Jul/12 CLOSED July 25, 2012 9 25 5246 Civil N/A July 23, 2012 Deaerator Area (B2) North, East & West Sides Walls, Unit # 77 July 24, 2012 8:15 AM Reinforcement/Embedments CW04/05 W W 70-UXA-CLB-014/016 (Rev.0a),70-UXA-CLC-014 (Rev.0) & 70-UXA-CLB-015 Md. Hamza R.C.Basco 23/Jul/12 CLOSED 26 5247 Civil N/A July 23, 2012 Underground Pipeline for Flushing Line (Acid Cleaning), Unit # 74 July 24, 2012 8:00 AM Pipe Bedding Prior to Pipe Laying. 70-UG-CLD-014 (Rev.2a) Md. Hamza R.C.Basco 23/Jul/12 CLOSED PHASE 1 PACKAGE "D" WEEKLY QA/QC INSPECTION STATUS REPORT ( EXTERNAL RFI's ) DATE COVERED : WEEK NO. 74 ( 21-22 JULY,2012 ) RAS AL KHAIR DESALINATION PLANT JULY 21,2012 JULY 22,2012 JULY 23,2012 JULY 24,2012 Doosan Heavy Industries & Construction. Assad Said For Contracting Co.,Ltd. Page 12 of 75 Sl. DF-EF-I- Dept. Mat. No. Submit Date Location Date of Inspection Time of Inspection Item Description ITP Op. No. Doosan Point Owner Point DRAWING NO. Cont. Representative from (ASSAD SAID) Cont. Representative from (Doosan) Doosan Recd on Status ASC Recd on Concrete Casting Date Vol. of Concrete ( m ) Remark PHASE 1 PACKAGE "D" WEEKLY QA/QC INSPECTION STATUS REPORT ( EXTERNAL RFI's ) DATE COVERED : WEEK NO. 74 ( 21-22 JULY,2012 ) RAS AL KHAIR DESALINATION PLANT Doosan Heavy Industries & Construction. Assad Said For Contracting Co.,Ltd. 27 5248 Civil N/A July 23, 2012 Underground Piping for Discharge Pipeline, Unit # 73 July 24, 2012 8:10 AM Pipe Bedding Prior to Pipe Laying. 70-UG-CLD-014 (Rev.2a) Md. Hamza R.C.Basco 23/Jul/12 CLOSED 28 5249 Civil N/A July 23, 2012 Duct Bank, DB-05 Bet. CP-141&142 July 24, 2012 9:00 AM Embedments/Formwork CW04/C W03 W W 70-UBZ-CLD-004 (Rev.3b) & 70-UBZ-CLB-011 (Rev.3a) Md. Hamza R.C.Basco 23/Jul/12 CLOSED 29 5250 Civil N/A July 23, 2012 Duct Bank, DB-05 Bet. CP-141&142 July 24, 2012 9:30 AM Concreting CW06 W W 70-UBZ-CLD-004 (Rev.3b) & 70-UBZ-CLB-011 (Rev.3a) Md. Hamza R.C.Basco 23/Jul/12 CLOSED July 25, 2012 20 30 5251 Civil N/A July 23, 2012 Brine Heater Area F6 Foundation, Pedestal Unit # 72-ASC Precast Yard July 24, 2012 8:30 AM Formworks/ Concreting CW03/ CW06 W W 70-UXA-CLD-041 (Rev.0a) & 70-UXB-CLB-022 (Rev.0) Md. Hamza R.C.Basco 23/Jul/12 CLOSED 31 5252 Civil N/A July 24, 2012 Misc. Foundation F27 (3no.), Unit # 72- As Shown- ASC Precast Yard July 25, 2012 8:00 AM Reinforcement/Embedments/F ormwork CW05/C W04/CW 03 W W 70-UXB-CLD-001 (Rev.1b)&70-UXB-CLB-009 (Rev.1) Md. Hamza R.C.Basco 24/Jul/12 CLOSED 32 5253 Civil N/A July 24, 2012 Misc. Foundation F27 (3no.), Unit # 72- As Shown- ASC Precast Yard July 25, 2012 9:00 AM Concreting CW06 W W 70-UXB-CLD-001 (Rev.1b)&70-UXB-CLB-009 (Rev.1) Md. Hamza R.C.Basco 24/Jul/12 CLOSED 33 5254 Bldg. N/A July 24, 2012 SWGR Bldg. for MSF Area Battery Room Ceiling, Unit # 71 & 72 July 25, 2012 8:00 AM Surface Preparation Prior to Primer or 1st Coat Application PW02 H W 70-UBX-CLH-102/106 (Rev.1) Md. Hamza R.C.Basco 24/Jul/12 CLOSED 34 5227 ( 1 ) Civil N/A 7/19/2012 Cable Pits, CP-57&58 Walls July 21, 2012 11:30 AM Reinforcement /Embedments CW04/05 W W 70-UBZ-CLD-004 (Rev.3b)& 70-UBZ-CLB-017 (Rev.3a) Md. Hamza R.C.Basco 19/Jul/12 CLOSED Resubmission 35 5255 Civil N/A July 25, 2012 Cable Pit, CP-221 Wall July 26, 2012 8:15 AM Formworks/ Concreting CW03/ CW06 W W 70-UBZ-CLD-005 (Rev.3a) & 70-UBZ-CLB-018 (Rev.1a) Md. Hamza R.C.Basco 25/Jul/12 CLOSED 36 5256 Civil N/A July 25, 2012 Cable Pit, CP-72 Wall July 26, 2012 8:30 AM Reinforcement/ Embedments CW04/05 W W 70-UBZ-CLD-004 (Rev.3b)& 70-UBZ-CLB-017 (Rev.3a) Md. Hamza R.C.Basco 25/Jul/12 CLOSED 37 5201 ( 2 ) Bldg. N/A July 25, 2012 SWGR Bldg. for Post Treatment Bldg. Parapet Walls At Grid A-C/1-9 July 26, 2012 9:00 AM Reinforcement /Embedments CW04/05 W W 85-UBX-CLC-010 (Rev.0b) & 85-UBX-CLC-017 (Rev.0) Md. Hamza R.C.Basco 17/Jul/12 Open Resubmission ( Not Ready ) 38 5231 ( 1 ) Civil N/A July 21, 2012 Cable Pits, CP-63,64,65,182&183 July 26, 2012 8:30 AM Surface Preparation Prior to Primer or 1st Coat Application PW02 H W 70-UBZ-CLD-004 (Rev.3b) & 70-UBZ-CLB-017 (Rev.3a) Md. Hamza R.C.Basco 21/Jul/12 CLOSED Verified by : Office Engineer Approved by: ENGR. SHAIK SHAFIULLAH Project Manager ENGR. ROGER BETANIA Chief-Office-Engineer JULY 25,2012 JULY 26,2012 Prepared by : ENGR. ARIES HERNANDEZ Page 13 of 75 No. DF-EF-I- File No. Date Location Requested by Item Description Qt'y Shipment No. B/L No. Shop Insp. Cert. No. Packing List Material Approval No. Sub-Cont. Date Doosan Date Remarks 1 N/A 2-Aug-12 Assad Said Laydown Area Mr. Song Acid Resistant Ceramic Tile 290-2912, 15.1X15.1X0.9 cm 572.00 m 2 Attachment #1 N/A N/A AS-DF-T-0188, DS-C- 0126 Mr. P.G.Kwak 2-Aug-12 Mr. P.G.Kwak 2-Aug-12 Civil 2 N/A 2-Aug-12 Assad Said Laydown Area Mr. Song Hollow Blocks (200X200X400mm 3 Cell Strecher Block) =3032 Hollow Blocks (100X190X390mm 2 Cell Corner Block)=460 3032.00 460.00 =3492.00 Attachment #1 N/A N/A Attachment #1 DH-EF-L-0087/DS-C- 0060 Mr. P.G.Kwak 2-Aug-12 Mr. P.G.Kwak 2-Aug-12 3 N/A 31-Jul-12 Assad Said Laydown Area Mr. Song Fenomastic Pure CL ENA SG (STD 0567) 18 L 60 pcs Attachment #2 N/A N/A Attachment #1 DH-EF-L-0257/DS-C- 0127 Mr. P.G.Kwak 31-Jul-12 Mr. P.G.Kwak 31-Jul-12 Civil 4 N/A 26-Jul-12 Assad Said Laydown Area Mr. Song Fiberlon-APP Modified Bitumen Membranes 4mm Polyflame-APP Modified Btumen Waterproofing Membrance 4mm Black 3910 M2 1150 M2 Total 5060 M2 Attachment #2 N/A N/A Attachment #1 DH-EF-L-0238/0240 & DS-C-0119/0121 Mr. P.G.Kwak 26-Jul-12 Mr. P.G.Kwak 26-Jul-12 Civil 5 2349 N/A 23-Jul-12 Assad Said Laydown Area Mr. Song Nitotile 489 (12kg) Nitotile XS Grey (20kg) 88 50 Total 138 Attachment #2 N/A N/A Attachment #1 DH-EF-L-0102/103/DS-C- 0069/70 Mr. P.G.Kwak 23-Jul-12 Mr. P.G.Kwak 23-Jul-12 Civil 6 2347 N/A 19-Jul-12 Assad Said Laydown Area Mr. Song WT-200-1123,25x25x0.8 cm Tile WT-210-1124,25x33x0.8 cm Tile WT-290-0015,15.1x15.1 cm Tile G.P.240-3178, 50x50x1.0 cm Tile 66 M2 272 M2 747 M2 260 M2 Total 1345 M2 Attachment #2 N/A N/A Attachment #1 Mr. P.G.Kwak 19-Jul-12 Mr. P.G.Kwak 19-Jul-12 Civil 7 2343 N/A 17-Jul-12 Assad Said Laydown Area Mr. Song Femomastic Emulsion Primer Stucco 50 pcs 100 pcs Total 150 pcs Attachment #2 N/A Attachment #1 Attachment #1 DH-EF-L-0089/DS-C- 0063 Mr. P.G.Kwak 17-Jul-12 Mr. P.G.Kwak 17-Jul-12 Civil 8 2342 N/A 16-Jul-12 Assad Said Laydown Area Mr. Song ESSCOFOAM 35KG,50MM,1250X600 1445 pcs Attachment #2 N/A Attachment #1 Attachment #1 DF-EH-L-0267/DS-C- 0135 Mr. P.G.Kwak 16-Jul-12 Mr. P.G.Kwak 16-Jul-12 Civil 9 2341 N/A 16-Jul-12 Assad Said Laydown Area Mr. Song Femomastic Pure CL ENA SG (STD 0567) 8 pcs Attachment #2 N/A Attachment #1 Attachment #1 Mr. P.G.Kwak 16-Jul-12 Mr. P.G.Kwak 16-Jul-12 Civil 10 2301 N/A 4-Jul-12 Assad Said Laydown Area Mr. Song Hollow Blocks (200X200X400mm 3 Cell Strecher Block) Hollow Blocks (100X190X390mm 2 Cell Corner Block) 11,468 pcs 9,540 pcs Total 21,008 pcs Attachment #2 N/A Attachment #1 Attachment #1 DH-EF-L-0087/DS-C- 0060 Mr. P.G.Kwak 4-Jul-12 Mr. P.G.Kwak 4-Jul-12 Civil 11 2290 N/A 25-Jun-12 Assad Said Laydown Area Mr. Song UPVC Pipe-500mm 14.6m R/J CL-3 Pipe 400mm 11.7mm R/J CL-3 Pipe 315mm 9.2mm SCJ CL-3 Pipe 250mm 7.3mm Class-3 Pipe 200mm 5.9mm Class-3 Anger Rubber 500mm Anger Rubber 400mm 11 pcs 43 pcs 28 pcs 6 pcs 86 pcs 11 pcs 43 pcs Total 228 pcs Attachment #2 N/A Attachment #1 Attachment #1 DH-EF-L-0045/DS-C- 0039 Mr. P.G.Kwak 25-Jun-12 Mr. P.G.Kwak 25-Jun-12 Civil 12 2272 N/A 18-Jun-12 Assad Said Laydown Area Mr. Song Hollow Blocks ( 200X200X400 mm 3 Cell Strecher Block ) 5878 pcs Attachment #2 N/A Attachment #1 Attachment #1 DH-EF-L-0087/DS-C- 0060 Mr. P.G.Kwak 18-Jun-12 Mr. P.G.Kwak 18-Jun-12 Civil 13 2267 N/A 9-Jun-12 Assad Said Laydown Area Mr. Song UPVC Pipe-500mm 14.6m R/J CL-3 Pipe 160mm 4.7mm Class-3 Pipe 110mm 3.2mm Class-3 Anger Rubber 500mm 28 pcs 6 pcs 41 pcs 28 pcs Total 103 pcs Attachment #2 N/A Attachment #1 Attachment #1 DH-EF-L-0045/DS-C- 0039 Mr. P.G.Kwak 9-Jun-12 Mr. P.G.Kwak 9-Jun-12 Civil 14 2247 N/A 29-May-12 Assad Said Laydown Area Mr. Song Blue Guard-Extruded Polystyrene Insulation Boards 600 pcs 600 pcs Total 1200 pcs Attachment #2 N/A Attachment #1 Attachment #1 DH-EF-L-0195/DS-C- 0107 (A) Mr. P.G.Kwak 29-May-12 Mr. P.G.Kwak 29-May-12 Civil RAS AL KHAIR DESALINATION PLANT PHASE 1 PACKAGE "D" QA/QC MRIR REPORT DATE COVERED : As of 25 August,2012 Doosan Heavy Industries & Construction. Assad Said For Contracting Co.,Ltd. Page 14 of 75 No. DF-EF-I- File No. Date Location Requested by Item Description Qt'y Shipment No. B/L No. Shop Insp. Cert. No. Packing List Material Approval No. Sub-Cont. Date Doosan Date Remarks RAS AL KHAIR DESALINATION PLANT PHASE 1 PACKAGE "D" QA/QC MRIR REPORT DATE COVERED : As of 25 August,2012 Doosan Heavy Industries & Construction. Assad Said For Contracting Co.,Ltd. 15 2216 N/A 17-May-12 Assad Said Laydown Area Mr. Song Hollow Blocks (200X200X400mm 3 Cell Strecher Block) Hollow Blocks (100X190X390 mm 2 Cell Corner Block) 14,284 pcs 8,135 pcs Total 22,419 pcs Attachment #2 N/A Attachment #1 Attachment #1 DH-EF-L-0087/DS-C- 0060 Mr. P.G.Kwak 17-May-12 Mr. P.G.Kwak 17-May-12 Civil 16 N/A 15-Apr-12 Assad Said Laydown Area Mr. Song Nitocote EPU/ EPU RAL 7032 200 Sets Attachment #2 N/A Attachment #1 Attachment #1 DH-EF-L-0088/DS-C- 0061 A Mr. P.G.Kwak 15-Apr-12 Mr. P.G.Kwak 15-Apr-12 Civil 17 2160 N/A 31-Mar-12 Assad Said Laydown Area Mr. Song Hollow Blocks ( 200*200*400 mm 3 Cell Strecher Block ) 1300 pcs Attachment #2 N/A Attachment #1 Attachment #1 DH-EF-L-0087/DS-C- 0060 Mr. P.G.Kwak 31-Mar-12 Mr. P.G.Kwak 31-Mar-12 Civil 18 2158 N/A 31-Mar-12 Assad Said Laydown Area Mr. Song FBEC (Coated Reinforcing Steel Bars) Dia 25 mm 26 ton Attachment #2 N/A Attachment #1 Attachment #1 DF-EH-L-0006 Mr. Shaik Shafiullah 31-Mar-12 Mr. P.G.Kwak 31-Mar-12 Civil 19 2053 N/A 20-Dec-11 Assad Said Laydown Area Mr. Basco FBEC (Coated Reinforcing Steel Bars) Dia 25 mm Total 278 ton Attachment #1 N/A Attachment #1 Attachment #1 DF-EH-L-0006 Mr. Shaik Shafiullah 20-Dec-11 Mr. Rigoberto C. Basco 20-Dec-11 Civil 20 2004 N/A 19-Jul-11 Assad Said Laydown Area Mr. Basco FBEC (Coated Reinforcing Steel Bars) Dia 20 mm FBEC (Coated Reinforcing Steel Bars) Dia 25 mm 60 ton 92 ton Total 152 ton Attachment #1 N/A Attachment #1 Attachment #1 DF-EH-L-0006 Mr. Rodrigo Betania 19-Jul-11 Mr. Rigoberto C. Basco 19-Jul-11 Civil 21 2003 N/A 13-Jul-11 Assad Said Laydown Area Mr. Basco Plastic Coated Binding Wires 295 Rolls Attachment #1 N/A Attachment #2 Attachment #1 DF-EH-L-0006 Mr. Rodrigo Betania 13-Jul-11 Mr. Rigoberto C. Basco 13-Jul-11 Civil 22 2002 N/A 7-Jul-11 Assad Said Laydown Area Mr. Basco FBEC (Coated Reinforcing Steel Bars) Dia 25 mm 52 ton Attachment #1 N/A Attachment #1 Attachment #1 DF-EH-L-0006 Mr. Rodrigo Betania 7-Jul-11 Mr. Rigoberto C. Basco 7-Jul-11 Civil 23 2001 N/A 29-Jun-11 Assad Said Laydown Area Mr. Basco FBEC (Coated Reinforcing Steel Bars) Dia 10 mm FBEC (Coated Reinforcing Steel Bars) Dia 12 mm FBEC (Coated Reinforcing Steel Bars) Dia 16 mm FBEC (Coated Reinforcing Steel Bars) Dia 20 mm FBEC (Coated Reinforcing Steel Bars) Dia 22 mm 808 ton 706 ton 1,383 ton 2,844 ton 706 ton Total 6,447 ton Attachment #1 N/A Attachment #1 Attachment #1 DF-EH-L-0006 Mr. Rodrigo Betania 28-Jun-11 Mr. Rigoberto C. Basco 28-Jun-11 Civil WEEK NO. 74 ( JULY 21 2012 - JULY 26,2012 ) 3. HSE RAS AL KHAIR DESALINATION PLANT PHASE 1 PACKAGE "D" CIVIL & BUILDING WORKS Doosan Heavy Industries & Construction. Assad Said For Contracting Co.,Ltd. WEEK NO. 74 ( JULY 21 2012 - JULY 26,2012 ) 3. HSE RAS AL KHAIR DESALINATION PLANT PHASE 1 PACKAGE "D" CIVIL & BUILDING WORKS Doosan Heavy Industries & Construction. Assad Said For Contracting Co.,Ltd. Page 17 of 75 ASSAD SAID Letter No. Submittal's MS Docu.Ref.No Rev Material Ref. No Reference No. Status ASC Recd Remarks 1 AS-DS-L-0032 MS 70-GG-CDC-001 June 08, 2011 Excavation Excavation Works for Evaporator Foundation 6/8/2011 DF-EH-D-0010/019 B 1/31/2012 Vol-1 2 AS-DS-L-0035 MS 70-GG-CDC-002 June 08, 2011 Blind Concrete Concreting Works (General) 6/8/2011 DF-EH-D-0011 B 1/31/2012 Vol-1 3 AS-DS-L-0034 MS 70-GG-CDC-003 June 08, 2011 Water Proofing Works Waterproofing Membrane & Protective Coatings 6/8/2011 DF-EH-D-0013/30 B 1/31/2012 Vol-1 4 AS-DS-T-0028 MS 70-GG-CDC-004 June 25, 2011 Concrete General A Vol-1 5 AS-DF-T-0032 MS 70-GG-CDC-005 June 25, 2011 Back Filling 6/8/2011 DF-EH-D-0016 B 1/31/2012 Vol-1 6 AS-DS-L-0036 MS 70-GG-CDC-006 June 08, 2011 Dewatering & Sheet Piling Works Dewatering & Sheet Piling Works 6/8/2011 DF-EH-D-0015 B 1/31/2012 Vol-1 7 MS 70-GG-CDC-007 June 25, 2011 Deep Excavation DF-EH-D-0014 B 1/31/2012 Vol-1 8 MS 70-GG-CDC-008 June 15, 2011 BRP/FDN Excavation 8/6/2011 DF-EH-D-0022 B 1/31/2012 Vol-1 9 MS 70-GG-CDC-009 June 27, 2011 Building Works Vol-1 10 MS 70-GG-CDC-010 August 17, 2011 Formworks Vol-1 11 MS 70-GG-CDC-011 August 17, 2011 Concrete Repair Vol-1 12 AS-DS-L-0113 MS 70-GG-CDC-011 October 23, 2011 Concrete Repair Deaerator Area Unit # 71 Wall 10/23/2011 Reply NCR no. 003, Attached MS no.70- GG-CDC-011 (Concrete Repair) No Photos Attached Vol-1 13 AS-DS-L-0116 MS 70-GG-CDC-011 October 25, 2011 Concrete Repair (Deaerator Wall) Deaerator Area Unit # 71 Wall 10/25/2011 Reply NCR no. 003, Attached MS no.70- GG-CDC-011 (Concrete Repair) No Photos Attached Vol-1 14 MS 70-GG-CDC-012 August 17, 2011 Mechanical Couplers Vol-1 15 AS-DF-T-0070 MS 70-GG-CDC-013 September 25, 2011 Concrete(Thin Section) 9/25/2011 Vol-1 16 AS-DF-T-0081 MS 70-GG-CDC-013 1 October 03, 2011 Concrete(Thin Section) 10/3/2011 Vol-1 17 AS-DF-T-0099 MS 70-GG-CDC-015 November 20, 2011 Excavation-Post Treatment Sedimentation Basin 11/20/2011 Vol-1 18 AS-DF-T-0096 MS 70-GG-CDC-016 November 15, 2011 (Erection of PS-Hollow Core Slabs) 11/15/2011 Vol-1 19 AS-DF-T-0097 MS 70-GG-CDC-017 November 15, 2011 (Erection of LLC Siporex Wall Panels) 11/15/2011 Vol-1 20 AS-DF-T-0109 MS 70-GG-CDC-018 November 26, 2011 Masonry Block Work-As Permanent Form Work 11/26/2011 Vol-1 21 AS-DF-T-0137 MS 70-GG-CDC-019 March 14, 2012 CMU-Block Masonry Works-Walls 3/14/2012 Vol-1 22 AS-DF-T-0149 MS 70-GG-CDC-020 April 16, 2012 Epoxy Paint on Exposed Concrete Surface 4/16/2012 Vol-1 23 AS-DF-T-0150 MS 70-GG-CDC-021 April 28, 2012 Plastering Works for Walls 4/28/2012 Vol-1 24 AS-DF-T-0166 MS 70-GG-CDC-022 May 20, 2012 Emulsion & Enamel Paint 5/20/2012 Vol-1 25 AS-DF-T-0178 MS 71-GG-CDC-023 June 03, 2012 Roof Waterproofing System 6/3/2012 Vol-1 26 AS-DF-T-0182 MS 71-GG-CDC-023 1 June 10, 2012 Roof Waterproofing System 6/10/2012 Vol-1 27 AS-DF-T-0194 MS 71-GG-CDC-024 July 22, 2012 Tiling Works for Floors & Walls 7/22/2012 Vol-1 Verified by : Approved by: Office Engineer ENGR. ARIES HERNANDEZ ENGR. SHAIK SHAFIULLAH Project Manager ENGR. ROGER BETANIA Chief-Office-Engineer RAS AL KHAIR DESALINATION PLANT PHASE 1 PACKAGE "D" METHOD OF STATEMENT REPORT DATE COVERED : AS OF JULY 26,2012 Prepared by : S.N. DOOSAN Name of Suppliers Place of Application/Location Date of Submit Description of Material Doosan Recd File Location ASC Transmittal no. Doosan Heavy Industries & Construction. Assad Said For Contracting Co.,Ltd. Page 18 of 75 ASSAD SAID Letter No. Submittal's MS Docu.Ref.No Rev Material Ref. No Reference No. Status ASC Recd Remarks 1 AS-DS-L-0032 MS 70-GG-CDC-001 June 08, 2011 Excavation Excavation Works for Evaporator Foundation 6/8/2011 DF-EH-D-0010/019 B 1/31/2012 Vol-1 2 AS-DS-L-0035 MS 70-GG-CDC-002 June 08, 2011 Blind Concrete Concreting Works (General) 6/8/2011 DF-EH-D-0011 B 1/31/2012 Vol-1 3 AS-DS-L-0034 MS 70-GG-CDC-003 June 08, 2011 Water Proofing Works Waterproofing Membrane & Protective Coatings 6/8/2011 DF-EH-D-0013/30 B 1/31/2012 Vol-1 4 AS-DS-T-0028 MS 70-GG-CDC-004 June 25, 2011 Concrete General A Vol-1 5 AS-DF-T-0032 MS 70-GG-CDC-005 June 25, 2011 Back Filling 6/8/2011 DF-EH-D-0016 B 1/31/2012 Vol-1 6 AS-DS-L-0036 MS 70-GG-CDC-006 June 08, 2011 Dewatering & Sheet Piling Works Dewatering & Sheet Piling Works 6/8/2011 DF-EH-D-0015 B 1/31/2012 Vol-1 7 MS 70-GG-CDC-007 June 25, 2011 Deep Excavation DF-EH-D-0014 B 1/31/2012 Vol-1 8 MS 70-GG-CDC-008 June 15, 2011 BRP/FDN Excavation 8/6/2011 DF-EH-D-0022 B 1/31/2012 Vol-1 9 MS 70-GG-CDC-009 June 27, 2011 Building Works Vol-1 10 MS 70-GG-CDC-010 August 17, 2011 Formworks Vol-1 11 MS 70-GG-CDC-011 August 17, 2011 Concrete Repair Vol-1 12 AS-DS-L-0113 MS 70-GG-CDC-011 October 23, 2011 Concrete Repair Deaerator Area Unit # 71 Wall 10/23/2011 Reply NCR no. 003, Attached MS no.70- GG-CDC-011 (Concrete Repair) No Photos Attached Vol-1 13 AS-DS-L-0116 MS 70-GG-CDC-011 October 25, 2011 Concrete Repair (Deaerator Wall) Deaerator Area Unit # 71 Wall 10/25/2011 Reply NCR no. 003, Attached MS no.70- GG-CDC-011 (Concrete Repair) No Photos Attached Vol-1 14 MS 70-GG-CDC-012 August 17, 2011 Mechanical Couplers Vol-1 15 AS-DF-T-0070 MS 70-GG-CDC-013 September 25, 2011 Concrete(Thin Section) 9/25/2011 Vol-1 16 AS-DF-T-0081 MS 70-GG-CDC-013 1 October 03, 2011 Concrete(Thin Section) 10/3/2011 Vol-1 17 AS-DF-T-0099 MS 70-GG-CDC-015 November 20, 2011 Excavation-Post Treatment Sedimentation Basin 11/20/2011 Vol-1 18 AS-DF-T-0096 MS 70-GG-CDC-016 November 15, 2011 (Erection of PS-Hollow Core Slabs) 11/15/2011 Vol-1 19 AS-DF-T-0097 MS 70-GG-CDC-017 November 15, 2011 (Erection of LLC Siporex Wall Panels) 11/15/2011 Vol-1 20 AS-DF-T-0109 MS 70-GG-CDC-018 November 26, 2011 Masonry Block Work-As Permanent Form Work 11/26/2011 Vol-1 21 AS-DF-T-0137 MS 70-GG-CDC-019 March 14, 2012 CMU-Block Masonry Works-Walls 3/14/2012 Vol-1 22 AS-DF-T-0149 MS 70-GG-CDC-020 April 16, 2012 Epoxy Paint on Exposed Concrete Surface 4/16/2012 Vol-1 23 AS-DF-T-0150 MS 70-GG-CDC-021 April 28, 2012 Plastering Works for Walls 4/28/2012 Vol-1 24 AS-DF-T-0166 MS 70-GG-CDC-022 May 20, 2012 Emulsion & Enamel Paint 5/20/2012 Vol-1 25 AS-DF-T-0178 MS 71-GG-CDC-023 June 03, 2012 Roof Waterproofing System 6/3/2012 Vol-1 26 AS-DF-T-0182 MS 71-GG-CDC-023 1 June 10, 2012 Roof Waterproofing System 6/10/2012 Vol-1 27 AS-DF-T-0194 MS 71-GG-CDC-024 July 22, 2012 Tiling Works for Floors & Walls 7/22/2012 Vol-1 RAS AL KHAIR DESALINATION PLANT PHASE 1 PACKAGE "D" METHOD OF STATEMENT REPORT DATE COVERED : AS OF JULY 26,2012 S.N. DOOSAN Name of Suppliers Place of Application/Location Date of Submit Description of Material Doosan Recd File Location ASC Transmittal no. Doosan Heavy Industries & Construction. Assad Said For Contracting Co.,Ltd. Page 19 of 75 ASSAD SAID Letter No. Submittal's MS Docu.Ref.No Rev Material Ref. No Reference No. Status ASC Recd Remarks 1 AS-DS-L-0032 MS 70-GG-CDC-001 June 08, 2011 Excavation Excavation Works for Evaporator Foundation 6/8/2011 DF-EH-D-0010/019 B 1/31/2012 Vol-1 2 AS-DS-L-0035 MS 70-GG-CDC-002 June 08, 2011 Blind Concrete Concreting Works (General) 6/8/2011 DF-EH-D-0011 B 1/31/2012 Vol-1 3 AS-DS-L-0034 MS 70-GG-CDC-003 June 08, 2011 Water Proofing Works Waterproofing Membrane & Protective Coatings 6/8/2011 DF-EH-D-0013/30 B 1/31/2012 Vol-1 4 AS-DS-T-0028 MS 70-GG-CDC-004 June 25, 2011 Concrete General A Vol-1 5 AS-DF-T-0032 MS 70-GG-CDC-005 June 25, 2011 Back Filling 6/8/2011 DF-EH-D-0016 B 1/31/2012 Vol-1 6 AS-DS-L-0036 MS 70-GG-CDC-006 June 08, 2011 Dewatering & Sheet Piling Works Dewatering & Sheet Piling Works 6/8/2011 DF-EH-D-0015 B 1/31/2012 Vol-1 7 MS 70-GG-CDC-007 June 25, 2011 Deep Excavation DF-EH-D-0014 B 1/31/2012 Vol-1 8 MS 70-GG-CDC-008 June 15, 2011 BRP/FDN Excavation 8/6/2011 DF-EH-D-0022 B 1/31/2012 Vol-1 9 MS 70-GG-CDC-009 June 27, 2011 Building Works Vol-1 10 MS 70-GG-CDC-010 August 17, 2011 Formworks Vol-1 11 MS 70-GG-CDC-011 August 17, 2011 Concrete Repair Vol-1 12 AS-DS-L-0113 MS 70-GG-CDC-011 October 23, 2011 Concrete Repair Deaerator Area Unit # 71 Wall 10/23/2011 Reply NCR no. 003, Attached MS no.70- GG-CDC-011 (Concrete Repair) No Photos Attached Vol-1 13 AS-DS-L-0116 MS 70-GG-CDC-011 October 25, 2011 Concrete Repair (Deaerator Wall) Deaerator Area Unit # 71 Wall 10/25/2011 Reply NCR no. 003, Attached MS no.70- GG-CDC-011 (Concrete Repair) No Photos Attached Vol-1 14 MS 70-GG-CDC-012 August 17, 2011 Mechanical Couplers Vol-1 15 AS-DF-T-0070 MS 70-GG-CDC-013 September 25, 2011 Concrete(Thin Section) 9/25/2011 Vol-1 16 AS-DF-T-0081 MS 70-GG-CDC-013 1 October 03, 2011 Concrete(Thin Section) 10/3/2011 Vol-1 17 AS-DF-T-0099 MS 70-GG-CDC-015 November 20, 2011 Excavation-Post Treatment Sedimentation Basin 11/20/2011 Vol-1 18 AS-DF-T-0096 MS 70-GG-CDC-016 November 15, 2011 (Erection of PS-Hollow Core Slabs) 11/15/2011 Vol-1 19 AS-DF-T-0097 MS 70-GG-CDC-017 November 15, 2011 (Erection of LLC Siporex Wall Panels) 11/15/2011 Vol-1 20 AS-DF-T-0109 MS 70-GG-CDC-018 November 26, 2011 Masonry Block Work-As Permanent Form Work 11/26/2011 Vol-1 21 AS-DF-T-0137 MS 70-GG-CDC-019 March 14, 2012 CMU-Block Masonry Works-Walls 3/14/2012 Vol-1 22 AS-DF-T-0149 MS 70-GG-CDC-020 April 16, 2012 Epoxy Paint on Exposed Concrete Surface 4/16/2012 Vol-1 23 AS-DF-T-0150 MS 70-GG-CDC-021 April 28, 2012 Plastering Works for Walls 4/28/2012 Vol-1 24 AS-DF-T-0166 MS 70-GG-CDC-022 May 20, 2012 Emulsion & Enamel Paint 5/20/2012 Vol-1 25 AS-DF-T-0178 MS 71-GG-CDC-023 June 03, 2012 Roof Waterproofing System 6/3/2012 Vol-1 26 AS-DF-T-0182 MS 71-GG-CDC-023 1 June 10, 2012 Roof Waterproofing System 6/10/2012 Vol-1 27 AS-DF-T-0194 MS 71-GG-CDC-024 July 22, 2012 Tiling Works for Floors & Walls 7/22/2012 Vol-1 RAS AL KHAIR DESALINATION PLANT PHASE 1 PACKAGE "D" METHOD OF STATEMENT REPORT DATE COVERED : AS OF JULY 26,2012 S.N. DOOSAN Name of Suppliers Place of Application/Location Date of Submit Description of Material Doosan Recd File Location ASC Transmittal no. Doosan Heavy Industries & Construction. Assad Said For Contracting Co.,Ltd. Page 20 of 75 ASSAD SAID Letter No. Submittal's MS Docu.Ref.No Rev Material Ref. No Reference No. Status ASC Recd Remarks 1 AS-DS-L-0032 MS 70-GG-CDC-001 June 08, 2011 Excavation Excavation Works for Evaporator Foundation 6/8/2011 DF-EH-D-0010/019 B 1/31/2012 Vol-1 2 AS-DS-L-0035 MS 70-GG-CDC-002 June 08, 2011 Blind Concrete Concreting Works (General) 6/8/2011 DF-EH-D-0011 B 1/31/2012 Vol-1 3 AS-DS-L-0034 MS 70-GG-CDC-003 June 08, 2011 Water Proofing Works Waterproofing Membrane & Protective Coatings 6/8/2011 DF-EH-D-0013/30 B 1/31/2012 Vol-1 4 AS-DS-T-0028 MS 70-GG-CDC-004 June 25, 2011 Concrete General A Vol-1 5 AS-DF-T-0032 MS 70-GG-CDC-005 June 25, 2011 Back Filling 6/8/2011 DF-EH-D-0016 B 1/31/2012 Vol-1 6 AS-DS-L-0036 MS 70-GG-CDC-006 June 08, 2011 Dewatering & Sheet Piling Works Dewatering & Sheet Piling Works 6/8/2011 DF-EH-D-0015 B 1/31/2012 Vol-1 7 MS 70-GG-CDC-007 June 25, 2011 Deep Excavation DF-EH-D-0014 B 1/31/2012 Vol-1 8 MS 70-GG-CDC-008 June 15, 2011 BRP/FDN Excavation 8/6/2011 DF-EH-D-0022 B 1/31/2012 Vol-1 9 MS 70-GG-CDC-009 June 27, 2011 Building Works Vol-1 10 MS 70-GG-CDC-010 August 17, 2011 Formworks Vol-1 11 MS 70-GG-CDC-011 August 17, 2011 Concrete Repair Vol-1 12 AS-DS-L-0113 MS 70-GG-CDC-011 October 23, 2011 Concrete Repair Deaerator Area Unit # 71 Wall 10/23/2011 Reply NCR no. 003, Attached MS no.70- GG-CDC-011 (Concrete Repair) No Photos Attached Vol-1 13 AS-DS-L-0116 MS 70-GG-CDC-011 October 25, 2011 Concrete Repair (Deaerator Wall) Deaerator Area Unit # 71 Wall 10/25/2011 Reply NCR no. 003, Attached MS no.70- GG-CDC-011 (Concrete Repair) No Photos Attached Vol-1 14 MS 70-GG-CDC-012 August 17, 2011 Mechanical Couplers Vol-1 15 AS-DF-T-0070 MS 70-GG-CDC-013 September 25, 2011 Concrete(Thin Section) 9/25/2011 Vol-1 16 AS-DF-T-0081 MS 70-GG-CDC-013 1 October 03, 2011 Concrete(Thin Section) 10/3/2011 Vol-1 17 AS-DF-T-0099 MS 70-GG-CDC-015 November 20, 2011 Excavation-Post Treatment Sedimentation Basin 11/20/2011 Vol-1 18 AS-DF-T-0096 MS 70-GG-CDC-016 November 15, 2011 (Erection of PS-Hollow Core Slabs) 11/15/2011 Vol-1 19 AS-DF-T-0097 MS 70-GG-CDC-017 November 15, 2011 (Erection of LLC Siporex Wall Panels) 11/15/2011 Vol-1 20 AS-DF-T-0109 MS 70-GG-CDC-018 November 26, 2011 Masonry Block Work-As Permanent Form Work 11/26/2011 Vol-1 21 AS-DF-T-0137 MS 70-GG-CDC-019 March 14, 2012 CMU-Block Masonry Works-Walls 3/14/2012 Vol-1 22 AS-DF-T-0149 MS 70-GG-CDC-020 April 16, 2012 Epoxy Paint on Exposed Concrete Surface 4/16/2012 Vol-1 23 AS-DF-T-0150 MS 70-GG-CDC-021 April 28, 2012 Plastering Works for Walls 4/28/2012 Vol-1 24 AS-DF-T-0166 MS 70-GG-CDC-022 May 20, 2012 Emulsion & Enamel Paint 5/20/2012 Vol-1 25 AS-DF-T-0178 MS 71-GG-CDC-023 June 03, 2012 Roof Waterproofing System 6/3/2012 Vol-1 26 AS-DF-T-0182 MS 71-GG-CDC-023 1 June 10, 2012 Roof Waterproofing System 6/10/2012 Vol-1 27 AS-DF-T-0194 MS 71-GG-CDC-024 July 22, 2012 Tiling Works for Floors & Walls 7/22/2012 Vol-1 RAS AL KHAIR DESALINATION PLANT PHASE 1 PACKAGE "D" METHOD OF STATEMENT REPORT DATE COVERED : AS OF JULY 26,2012 S.N. DOOSAN Name of Suppliers Place of Application/Location Date of Submit Description of Material Doosan Recd File Location ASC Transmittal no. Doosan Heavy Industries & Construction. Assad Said For Contracting Co.,Ltd. Page 21 of 75 ASSAD SAID Letter No. Submittal's MS Docu.Ref.No Rev Material Ref. No Reference No. Status ASC Recd Remarks 1 AS-DS-L-0032 MS 70-GG-CDC-001 June 08, 2011 Excavation Excavation Works for Evaporator Foundation 6/8/2011 DF-EH-D-0010/019 B 1/31/2012 Vol-1 2 AS-DS-L-0035 MS 70-GG-CDC-002 June 08, 2011 Blind Concrete Concreting Works (General) 6/8/2011 DF-EH-D-0011 B 1/31/2012 Vol-1 3 AS-DS-L-0034 MS 70-GG-CDC-003 June 08, 2011 Water Proofing Works Waterproofing Membrane & Protective Coatings 6/8/2011 DF-EH-D-0013/30 B 1/31/2012 Vol-1 4 AS-DS-T-0028 MS 70-GG-CDC-004 June 25, 2011 Concrete General A Vol-1 5 AS-DF-T-0032 MS 70-GG-CDC-005 June 25, 2011 Back Filling 6/8/2011 DF-EH-D-0016 B 1/31/2012 Vol-1 6 AS-DS-L-0036 MS 70-GG-CDC-006 June 08, 2011 Dewatering & Sheet Piling Works Dewatering & Sheet Piling Works 6/8/2011 DF-EH-D-0015 B 1/31/2012 Vol-1 7 MS 70-GG-CDC-007 June 25, 2011 Deep Excavation DF-EH-D-0014 B 1/31/2012 Vol-1 8 MS 70-GG-CDC-008 June 15, 2011 BRP/FDN Excavation 8/6/2011 DF-EH-D-0022 B 1/31/2012 Vol-1 9 MS 70-GG-CDC-009 June 27, 2011 Building Works Vol-1 10 MS 70-GG-CDC-010 August 17, 2011 Formworks Vol-1 11 MS 70-GG-CDC-011 August 17, 2011 Concrete Repair Vol-1 12 AS-DS-L-0113 MS 70-GG-CDC-011 October 23, 2011 Concrete Repair Deaerator Area Unit # 71 Wall 10/23/2011 Reply NCR no. 003, Attached MS no.70- GG-CDC-011 (Concrete Repair) No Photos Attached Vol-1 13 AS-DS-L-0116 MS 70-GG-CDC-011 October 25, 2011 Concrete Repair (Deaerator Wall) Deaerator Area Unit # 71 Wall 10/25/2011 Reply NCR no. 003, Attached MS no.70- GG-CDC-011 (Concrete Repair) No Photos Attached Vol-1 14 MS 70-GG-CDC-012 August 17, 2011 Mechanical Couplers Vol-1 15 AS-DF-T-0070 MS 70-GG-CDC-013 September 25, 2011 Concrete(Thin Section) 9/25/2011 Vol-1 16 AS-DF-T-0081 MS 70-GG-CDC-013 1 October 03, 2011 Concrete(Thin Section) 10/3/2011 Vol-1 17 AS-DF-T-0099 MS 70-GG-CDC-015 November 20, 2011 Excavation-Post Treatment Sedimentation Basin 11/20/2011 Vol-1 18 AS-DF-T-0096 MS 70-GG-CDC-016 November 15, 2011 (Erection of PS-Hollow Core Slabs) 11/15/2011 Vol-1 19 AS-DF-T-0097 MS 70-GG-CDC-017 November 15, 2011 (Erection of LLC Siporex Wall Panels) 11/15/2011 Vol-1 20 AS-DF-T-0109 MS 70-GG-CDC-018 November 26, 2011 Masonry Block Work-As Permanent Form Work 11/26/2011 Vol-1 21 AS-DF-T-0137 MS 70-GG-CDC-019 March 14, 2012 CMU-Block Masonry Works-Walls 3/14/2012 Vol-1 22 AS-DF-T-0149 MS 70-GG-CDC-020 April 16, 2012 Epoxy Paint on Exposed Concrete Surface 4/16/2012 Vol-1 23 AS-DF-T-0150 MS 70-GG-CDC-021 April 28, 2012 Plastering Works for Walls 4/28/2012 Vol-1 24 AS-DF-T-0166 MS 70-GG-CDC-022 May 20, 2012 Emulsion & Enamel Paint 5/20/2012 Vol-1 25 AS-DF-T-0178 MS 71-GG-CDC-023 June 03, 2012 Roof Waterproofing System 6/3/2012 Vol-1 26 AS-DF-T-0182 MS 71-GG-CDC-023 1 June 10, 2012 Roof Waterproofing System 6/10/2012 Vol-1 27 AS-DF-T-0194 MS 71-GG-CDC-024 July 22, 2012 Tiling Works for Floors & Walls 7/22/2012 Vol-1 RAS AL KHAIR DESALINATION PLANT PHASE 1 PACKAGE "D" METHOD OF STATEMENT REPORT DATE COVERED : AS OF JULY 26,2012 S.N. DOOSAN Name of Suppliers Place of Application/Location Date of Submit Description of Material Doosan Recd File Location ASC Transmittal no. Doosan Heavy Industries & Construction. Assad Said For Contracting Co.,Ltd. Page 22 of 75 ASSAD SAID Letter No. Submittal's MS Docu.Ref.No Rev Material Ref. No Reference No. Status ASC Recd Remarks 1 AS-DS-L-0032 MS 70-GG-CDC-001 June 08, 2011 Excavation Excavation Works for Evaporator Foundation 6/8/2011 DF-EH-D-0010/019 B 1/31/2012 Vol-1 2 AS-DS-L-0035 MS 70-GG-CDC-002 June 08, 2011 Blind Concrete Concreting Works (General) 6/8/2011 DF-EH-D-0011 B 1/31/2012 Vol-1 3 AS-DS-L-0034 MS 70-GG-CDC-003 June 08, 2011 Water Proofing Works Waterproofing Membrane & Protective Coatings 6/8/2011 DF-EH-D-0013/30 B 1/31/2012 Vol-1 4 AS-DS-T-0028 MS 70-GG-CDC-004 June 25, 2011 Concrete General A Vol-1 5 AS-DF-T-0032 MS 70-GG-CDC-005 June 25, 2011 Back Filling 6/8/2011 DF-EH-D-0016 B 1/31/2012 Vol-1 6 AS-DS-L-0036 MS 70-GG-CDC-006 June 08, 2011 Dewatering & Sheet Piling Works Dewatering & Sheet Piling Works 6/8/2011 DF-EH-D-0015 B 1/31/2012 Vol-1 7 MS 70-GG-CDC-007 June 25, 2011 Deep Excavation DF-EH-D-0014 B 1/31/2012 Vol-1 8 MS 70-GG-CDC-008 June 15, 2011 BRP/FDN Excavation 8/6/2011 DF-EH-D-0022 B 1/31/2012 Vol-1 9 MS 70-GG-CDC-009 June 27, 2011 Building Works Vol-1 10 MS 70-GG-CDC-010 August 17, 2011 Formworks Vol-1 11 MS 70-GG-CDC-011 August 17, 2011 Concrete Repair Vol-1 12 AS-DS-L-0113 MS 70-GG-CDC-011 October 23, 2011 Concrete Repair Deaerator Area Unit # 71 Wall 10/23/2011 Reply NCR no. 003, Attached MS no.70- GG-CDC-011 (Concrete Repair) No Photos Attached Vol-1 13 AS-DS-L-0116 MS 70-GG-CDC-011 October 25, 2011 Concrete Repair (Deaerator Wall) Deaerator Area Unit # 71 Wall 10/25/2011 Reply NCR no. 003, Attached MS no.70- GG-CDC-011 (Concrete Repair) No Photos Attached Vol-1 14 MS 70-GG-CDC-012 August 17, 2011 Mechanical Couplers Vol-1 15 AS-DF-T-0070 MS 70-GG-CDC-013 September 25, 2011 Concrete(Thin Section) 9/25/2011 Vol-1 16 AS-DF-T-0081 MS 70-GG-CDC-013 1 October 03, 2011 Concrete(Thin Section) 10/3/2011 Vol-1 17 AS-DF-T-0099 MS 70-GG-CDC-015 November 20, 2011 Excavation-Post Treatment Sedimentation Basin 11/20/2011 Vol-1 18 AS-DF-T-0096 MS 70-GG-CDC-016 November 15, 2011 (Erection of PS-Hollow Core Slabs) 11/15/2011 Vol-1 19 AS-DF-T-0097 MS 70-GG-CDC-017 November 15, 2011 (Erection of LLC Siporex Wall Panels) 11/15/2011 Vol-1 20 AS-DF-T-0109 MS 70-GG-CDC-018 November 26, 2011 Masonry Block Work-As Permanent Form Work 11/26/2011 Vol-1 21 AS-DF-T-0137 MS 70-GG-CDC-019 March 14, 2012 CMU-Block Masonry Works-Walls 3/14/2012 Vol-1 22 AS-DF-T-0149 MS 70-GG-CDC-020 April 16, 2012 Epoxy Paint on Exposed Concrete Surface 4/16/2012 Vol-1 23 AS-DF-T-0150 MS 70-GG-CDC-021 April 28, 2012 Plastering Works for Walls 4/28/2012 Vol-1 24 AS-DF-T-0166 MS 70-GG-CDC-022 May 20, 2012 Emulsion & Enamel Paint 5/20/2012 Vol-1 25 AS-DF-T-0178 MS 71-GG-CDC-023 June 03, 2012 Roof Waterproofing System 6/3/2012 Vol-1 26 AS-DF-T-0182 MS 71-GG-CDC-023 1 June 10, 2012 Roof Waterproofing System 6/10/2012 Vol-1 27 AS-DF-T-0194 MS 71-GG-CDC-024 July 22, 2012 Tiling Works for Floors & Walls 7/22/2012 Vol-1 RAS AL KHAIR DESALINATION PLANT PHASE 1 PACKAGE "D" METHOD OF STATEMENT REPORT DATE COVERED : AS OF JULY 26,2012 S.N. DOOSAN Name of Suppliers Place of Application/Location Date of Submit Description of Material Doosan Recd File Location ASC Transmittal no. Doosan Heavy Industries & Construction. Assad Said For Contracting Co.,Ltd. Page 23 of 75 ASSAD SAID Letter No. Submittal's MS Docu.Ref.No Rev Material Ref. No Reference No. Status ASC Recd Remarks 1 AS-DS-L-0032 MS 70-GG-CDC-001 June 08, 2011 Excavation Excavation Works for Evaporator Foundation 6/8/2011 DF-EH-D-0010/019 B 1/31/2012 Vol-1 2 AS-DS-L-0035 MS 70-GG-CDC-002 June 08, 2011 Blind Concrete Concreting Works (General) 6/8/2011 DF-EH-D-0011 B 1/31/2012 Vol-1 3 AS-DS-L-0034 MS 70-GG-CDC-003 June 08, 2011 Water Proofing Works Waterproofing Membrane & Protective Coatings 6/8/2011 DF-EH-D-0013/30 B 1/31/2012 Vol-1 4 AS-DS-T-0028 MS 70-GG-CDC-004 June 25, 2011 Concrete General A Vol-1 5 AS-DF-T-0032 MS 70-GG-CDC-005 June 25, 2011 Back Filling 6/8/2011 DF-EH-D-0016 B 1/31/2012 Vol-1 6 AS-DS-L-0036 MS 70-GG-CDC-006 June 08, 2011 Dewatering & Sheet Piling Works Dewatering & Sheet Piling Works 6/8/2011 DF-EH-D-0015 B 1/31/2012 Vol-1 7 MS 70-GG-CDC-007 June 25, 2011 Deep Excavation DF-EH-D-0014 B 1/31/2012 Vol-1 8 MS 70-GG-CDC-008 June 15, 2011 BRP/FDN Excavation 8/6/2011 DF-EH-D-0022 B 1/31/2012 Vol-1 9 MS 70-GG-CDC-009 June 27, 2011 Building Works Vol-1 10 MS 70-GG-CDC-010 August 17, 2011 Formworks Vol-1 11 MS 70-GG-CDC-011 August 17, 2011 Concrete Repair Vol-1 12 AS-DS-L-0113 MS 70-GG-CDC-011 October 23, 2011 Concrete Repair Deaerator Area Unit # 71 Wall 10/23/2011 Reply NCR no. 003, Attached MS no.70- GG-CDC-011 (Concrete Repair) No Photos Attached Vol-1 13 AS-DS-L-0116 MS 70-GG-CDC-011 October 25, 2011 Concrete Repair (Deaerator Wall) Deaerator Area Unit # 71 Wall 10/25/2011 Reply NCR no. 003, Attached MS no.70- GG-CDC-011 (Concrete Repair) No Photos Attached Vol-1 14 MS 70-GG-CDC-012 August 17, 2011 Mechanical Couplers Vol-1 15 AS-DF-T-0070 MS 70-GG-CDC-013 September 25, 2011 Concrete(Thin Section) 9/25/2011 Vol-1 16 AS-DF-T-0081 MS 70-GG-CDC-013 1 October 03, 2011 Concrete(Thin Section) 10/3/2011 Vol-1 17 AS-DF-T-0099 MS 70-GG-CDC-015 November 20, 2011 Excavation-Post Treatment Sedimentation Basin 11/20/2011 Vol-1 18 AS-DF-T-0096 MS 70-GG-CDC-016 November 15, 2011 (Erection of PS-Hollow Core Slabs) 11/15/2011 Vol-1 19 AS-DF-T-0097 MS 70-GG-CDC-017 November 15, 2011 (Erection of LLC Siporex Wall Panels) 11/15/2011 Vol-1 20 AS-DF-T-0109 MS 70-GG-CDC-018 November 26, 2011 Masonry Block Work-As Permanent Form Work 11/26/2011 Vol-1 21 AS-DF-T-0137 MS 70-GG-CDC-019 March 14, 2012 CMU-Block Masonry Works-Walls 3/14/2012 Vol-1 22 AS-DF-T-0149 MS 70-GG-CDC-020 April 16, 2012 Epoxy Paint on Exposed Concrete Surface 4/16/2012 Vol-1 23 AS-DF-T-0150 MS 70-GG-CDC-021 April 28, 2012 Plastering Works for Walls 4/28/2012 Vol-1 24 AS-DF-T-0166 MS 70-GG-CDC-022 May 20, 2012 Emulsion & Enamel Paint 5/20/2012 Vol-1 25 AS-DF-T-0178 MS 71-GG-CDC-023 June 03, 2012 Roof Waterproofing System 6/3/2012 Vol-1 26 AS-DF-T-0182 MS 71-GG-CDC-023 1 June 10, 2012 Roof Waterproofing System 6/10/2012 Vol-1 27 AS-DF-T-0194 MS 71-GG-CDC-024 July 22, 2012 Tiling Works for Floors & Walls 7/22/2012 Vol-1 RAS AL KHAIR DESALINATION PLANT PHASE 1 PACKAGE "D" METHOD OF STATEMENT REPORT DATE COVERED : AS OF JULY 26,2012 S.N. DOOSAN Name of Suppliers Place of Application/Location Date of Submit Description of Material Doosan Recd File Location ASC Transmittal no. Doosan Heavy Industries & Construction. Assad Said For Contracting Co.,Ltd. Page 24 of 75 ASSAD SAID Letter No. Submittal's MS Docu.Ref.No Rev Material Ref. No Reference No. Status ASC Recd Remarks 1 AS-DS-L-0032 MS 70-GG-CDC-001 June 08, 2011 Excavation Excavation Works for Evaporator Foundation 6/8/2011 DF-EH-D-0010/019 B 1/31/2012 Vol-1 2 AS-DS-L-0035 MS 70-GG-CDC-002 June 08, 2011 Blind Concrete Concreting Works (General) 6/8/2011 DF-EH-D-0011 B 1/31/2012 Vol-1 3 AS-DS-L-0034 MS 70-GG-CDC-003 June 08, 2011 Water Proofing Works Waterproofing Membrane & Protective Coatings 6/8/2011 DF-EH-D-0013/30 B 1/31/2012 Vol-1 4 AS-DS-T-0028 MS 70-GG-CDC-004 June 25, 2011 Concrete General A Vol-1 5 AS-DF-T-0032 MS 70-GG-CDC-005 June 25, 2011 Back Filling 6/8/2011 DF-EH-D-0016 B 1/31/2012 Vol-1 6 AS-DS-L-0036 MS 70-GG-CDC-006 June 08, 2011 Dewatering & Sheet Piling Works Dewatering & Sheet Piling Works 6/8/2011 DF-EH-D-0015 B 1/31/2012 Vol-1 7 MS 70-GG-CDC-007 June 25, 2011 Deep Excavation DF-EH-D-0014 B 1/31/2012 Vol-1 8 MS 70-GG-CDC-008 June 15, 2011 BRP/FDN Excavation 8/6/2011 DF-EH-D-0022 B 1/31/2012 Vol-1 9 MS 70-GG-CDC-009 June 27, 2011 Building Works Vol-1 10 MS 70-GG-CDC-010 August 17, 2011 Formworks Vol-1 11 MS 70-GG-CDC-011 August 17, 2011 Concrete Repair Vol-1 12 AS-DS-L-0113 MS 70-GG-CDC-011 October 23, 2011 Concrete Repair Deaerator Area Unit # 71 Wall 10/23/2011 Reply NCR no. 003, Attached MS no.70- GG-CDC-011 (Concrete Repair) No Photos Attached Vol-1 13 AS-DS-L-0116 MS 70-GG-CDC-011 October 25, 2011 Concrete Repair (Deaerator Wall) Deaerator Area Unit # 71 Wall 10/25/2011 Reply NCR no. 003, Attached MS no.70- GG-CDC-011 (Concrete Repair) No Photos Attached Vol-1 14 MS 70-GG-CDC-012 August 17, 2011 Mechanical Couplers Vol-1 15 AS-DF-T-0070 MS 70-GG-CDC-013 September 25, 2011 Concrete(Thin Section) 9/25/2011 Vol-1 16 AS-DF-T-0081 MS 70-GG-CDC-013 1 October 03, 2011 Concrete(Thin Section) 10/3/2011 Vol-1 17 AS-DF-T-0099 MS 70-GG-CDC-015 November 20, 2011 Excavation-Post Treatment Sedimentation Basin 11/20/2011 Vol-1 18 AS-DF-T-0096 MS 70-GG-CDC-016 November 15, 2011 (Erection of PS-Hollow Core Slabs) 11/15/2011 Vol-1 19 AS-DF-T-0097 MS 70-GG-CDC-017 November 15, 2011 (Erection of LLC Siporex Wall Panels) 11/15/2011 Vol-1 20 AS-DF-T-0109 MS 70-GG-CDC-018 November 26, 2011 Masonry Block Work-As Permanent Form Work 11/26/2011 Vol-1 21 AS-DF-T-0137 MS 70-GG-CDC-019 March 14, 2012 CMU-Block Masonry Works-Walls 3/14/2012 Vol-1 22 AS-DF-T-0149 MS 70-GG-CDC-020 April 16, 2012 Epoxy Paint on Exposed Concrete Surface 4/16/2012 Vol-1 23 AS-DF-T-0150 MS 70-GG-CDC-021 April 28, 2012 Plastering Works for Walls 4/28/2012 Vol-1 24 AS-DF-T-0166 MS 70-GG-CDC-022 May 20, 2012 Emulsion & Enamel Paint 5/20/2012 Vol-1 25 AS-DF-T-0178 MS 71-GG-CDC-023 June 03, 2012 Roof Waterproofing System 6/3/2012 Vol-1 26 AS-DF-T-0182 MS 71-GG-CDC-023 1 June 10, 2012 Roof Waterproofing System 6/10/2012 Vol-1 27 AS-DF-T-0194 MS 71-GG-CDC-024 July 22, 2012 Tiling Works for Floors & Walls 7/22/2012 Vol-1 RAS AL KHAIR DESALINATION PLANT PHASE 1 PACKAGE "D" METHOD OF STATEMENT REPORT DATE COVERED : AS OF JULY 26,2012 S.N. DOOSAN Name of Suppliers Place of Application/Location Date of Submit Description of Material Doosan Recd File Location ASC Transmittal no. Doosan Heavy Industries & Construction. Assad Said For Contracting Co.,Ltd. Page 25 of 75 ASSAD SAID Letter No. Submittal's MS Docu.Ref.No Rev Material Ref. No Reference No. Status ASC Recd Remarks 1 AS-DS-L-0032 MS 70-GG-CDC-001 June 08, 2011 Excavation Excavation Works for Evaporator Foundation 6/8/2011 DF-EH-D-0010/019 B 1/31/2012 Vol-1 2 AS-DS-L-0035 MS 70-GG-CDC-002 June 08, 2011 Blind Concrete Concreting Works (General) 6/8/2011 DF-EH-D-0011 B 1/31/2012 Vol-1 3 AS-DS-L-0034 MS 70-GG-CDC-003 June 08, 2011 Water Proofing Works Waterproofing Membrane & Protective Coatings 6/8/2011 DF-EH-D-0013/30 B 1/31/2012 Vol-1 4 AS-DS-T-0028 MS 70-GG-CDC-004 June 25, 2011 Concrete General A Vol-1 5 AS-DF-T-0032 MS 70-GG-CDC-005 June 25, 2011 Back Filling 6/8/2011 DF-EH-D-0016 B 1/31/2012 Vol-1 6 AS-DS-L-0036 MS 70-GG-CDC-006 June 08, 2011 Dewatering & Sheet Piling Works Dewatering & Sheet Piling Works 6/8/2011 DF-EH-D-0015 B 1/31/2012 Vol-1 7 MS 70-GG-CDC-007 June 25, 2011 Deep Excavation DF-EH-D-0014 B 1/31/2012 Vol-1 8 MS 70-GG-CDC-008 June 15, 2011 BRP/FDN Excavation 8/6/2011 DF-EH-D-0022 B 1/31/2012 Vol-1 9 MS 70-GG-CDC-009 June 27, 2011 Building Works Vol-1 10 MS 70-GG-CDC-010 August 17, 2011 Formworks Vol-1 11 MS 70-GG-CDC-011 August 17, 2011 Concrete Repair Vol-1 12 AS-DS-L-0113 MS 70-GG-CDC-011 October 23, 2011 Concrete Repair Deaerator Area Unit # 71 Wall 10/23/2011 Reply NCR no. 003, Attached MS no.70- GG-CDC-011 (Concrete Repair) No Photos Attached Vol-1 13 AS-DS-L-0116 MS 70-GG-CDC-011 October 25, 2011 Concrete Repair (Deaerator Wall) Deaerator Area Unit # 71 Wall 10/25/2011 Reply NCR no. 003, Attached MS no.70- GG-CDC-011 (Concrete Repair) No Photos Attached Vol-1 14 MS 70-GG-CDC-012 August 17, 2011 Mechanical Couplers Vol-1 15 AS-DF-T-0070 MS 70-GG-CDC-013 September 25, 2011 Concrete(Thin Section) 9/25/2011 Vol-1 16 AS-DF-T-0081 MS 70-GG-CDC-013 1 October 03, 2011 Concrete(Thin Section) 10/3/2011 Vol-1 17 AS-DF-T-0099 MS 70-GG-CDC-015 November 20, 2011 Excavation-Post Treatment Sedimentation Basin 11/20/2011 Vol-1 18 AS-DF-T-0096 MS 70-GG-CDC-016 November 15, 2011 (Erection of PS-Hollow Core Slabs) 11/15/2011 Vol-1 19 AS-DF-T-0097 MS 70-GG-CDC-017 November 15, 2011 (Erection of LLC Siporex Wall Panels) 11/15/2011 Vol-1 20 AS-DF-T-0109 MS 70-GG-CDC-018 November 26, 2011 Masonry Block Work-As Permanent Form Work 11/26/2011 Vol-1 21 AS-DF-T-0137 MS 70-GG-CDC-019 March 14, 2012 CMU-Block Masonry Works-Walls 3/14/2012 Vol-1 22 AS-DF-T-0149 MS 70-GG-CDC-020 April 16, 2012 Epoxy Paint on Exposed Concrete Surface 4/16/2012 Vol-1 23 AS-DF-T-0150 MS 70-GG-CDC-021 April 28, 2012 Plastering Works for Walls 4/28/2012 Vol-1 24 AS-DF-T-0166 MS 70-GG-CDC-022 May 20, 2012 Emulsion & Enamel Paint 5/20/2012 Vol-1 25 AS-DF-T-0178 MS 71-GG-CDC-023 June 03, 2012 Roof Waterproofing System 6/3/2012 Vol-1 26 AS-DF-T-0182 MS 71-GG-CDC-023 1 June 10, 2012 Roof Waterproofing System 6/10/2012 Vol-1 27 AS-DF-T-0194 MS 71-GG-CDC-024 July 22, 2012 Tiling Works for Floors & Walls 7/22/2012 Vol-1 RAS AL KHAIR DESALINATION PLANT PHASE 1 PACKAGE "D" METHOD OF STATEMENT REPORT DATE COVERED : AS OF JULY 26,2012 S.N. DOOSAN Name of Suppliers Place of Application/Location Date of Submit Description of Material Doosan Recd File Location ASC Transmittal no. Doosan Heavy Industries & Construction. Assad Said For Contracting Co.,Ltd. Page 26 of 75 ASSAD SAID Letter No. Submittal's MS Docu.Ref.No Rev Material Ref. No Reference No. Status ASC Recd Remarks 1 AS-DS-L-0032 MS 70-GG-CDC-001 June 08, 2011 Excavation Excavation Works for Evaporator Foundation 6/8/2011 DF-EH-D-0010/019 B 1/31/2012 Vol-1 2 AS-DS-L-0035 MS 70-GG-CDC-002 June 08, 2011 Blind Concrete Concreting Works (General) 6/8/2011 DF-EH-D-0011 B 1/31/2012 Vol-1 3 AS-DS-L-0034 MS 70-GG-CDC-003 June 08, 2011 Water Proofing Works Waterproofing Membrane & Protective Coatings 6/8/2011 DF-EH-D-0013/30 B 1/31/2012 Vol-1 4 AS-DS-T-0028 MS 70-GG-CDC-004 June 25, 2011 Concrete General A Vol-1 5 AS-DF-T-0032 MS 70-GG-CDC-005 June 25, 2011 Back Filling 6/8/2011 DF-EH-D-0016 B 1/31/2012 Vol-1 6 AS-DS-L-0036 MS 70-GG-CDC-006 June 08, 2011 Dewatering & Sheet Piling Works Dewatering & Sheet Piling Works 6/8/2011 DF-EH-D-0015 B 1/31/2012 Vol-1 7 MS 70-GG-CDC-007 June 25, 2011 Deep Excavation DF-EH-D-0014 B 1/31/2012 Vol-1 8 MS 70-GG-CDC-008 June 15, 2011 BRP/FDN Excavation 8/6/2011 DF-EH-D-0022 B 1/31/2012 Vol-1 9 MS 70-GG-CDC-009 June 27, 2011 Building Works Vol-1 10 MS 70-GG-CDC-010 August 17, 2011 Formworks Vol-1 11 MS 70-GG-CDC-011 August 17, 2011 Concrete Repair Vol-1 12 AS-DS-L-0113 MS 70-GG-CDC-011 October 23, 2011 Concrete Repair Deaerator Area Unit # 71 Wall 10/23/2011 Reply NCR no. 003, Attached MS no.70- GG-CDC-011 (Concrete Repair) No Photos Attached Vol-1 13 AS-DS-L-0116 MS 70-GG-CDC-011 October 25, 2011 Concrete Repair (Deaerator Wall) Deaerator Area Unit # 71 Wall 10/25/2011 Reply NCR no. 003, Attached MS no.70- GG-CDC-011 (Concrete Repair) No Photos Attached Vol-1 14 MS 70-GG-CDC-012 August 17, 2011 Mechanical Couplers Vol-1 15 AS-DF-T-0070 MS 70-GG-CDC-013 September 25, 2011 Concrete(Thin Section) 9/25/2011 Vol-1 16 AS-DF-T-0081 MS 70-GG-CDC-013 1 October 03, 2011 Concrete(Thin Section) 10/3/2011 Vol-1 17 AS-DF-T-0099 MS 70-GG-CDC-015 November 20, 2011 Excavation-Post Treatment Sedimentation Basin 11/20/2011 Vol-1 18 AS-DF-T-0096 MS 70-GG-CDC-016 November 15, 2011 (Erection of PS-Hollow Core Slabs) 11/15/2011 Vol-1 19 AS-DF-T-0097 MS 70-GG-CDC-017 November 15, 2011 (Erection of LLC Siporex Wall Panels) 11/15/2011 Vol-1 20 AS-DF-T-0109 MS 70-GG-CDC-018 November 26, 2011 Masonry Block Work-As Permanent Form Work 11/26/2011 Vol-1 21 AS-DF-T-0137 MS 70-GG-CDC-019 March 14, 2012 CMU-Block Masonry Works-Walls 3/14/2012 Vol-1 22 AS-DF-T-0149 MS 70-GG-CDC-020 April 16, 2012 Epoxy Paint on Exposed Concrete Surface 4/16/2012 Vol-1 23 AS-DF-T-0150 MS 70-GG-CDC-021 April 28, 2012 Plastering Works for Walls 4/28/2012 Vol-1 24 AS-DF-T-0166 MS 70-GG-CDC-022 May 20, 2012 Emulsion & Enamel Paint 5/20/2012 Vol-1 25 AS-DF-T-0178 MS 71-GG-CDC-023 June 03, 2012 Roof Waterproofing System 6/3/2012 Vol-1 26 AS-DF-T-0182 MS 71-GG-CDC-023 1 June 10, 2012 Roof Waterproofing System 6/10/2012 Vol-1 27 AS-DF-T-0194 MS 71-GG-CDC-024 July 22, 2012 Tiling Works for Floors & Walls 7/22/2012 Vol-1 RAS AL KHAIR DESALINATION PLANT PHASE 1 PACKAGE "D" METHOD OF STATEMENT REPORT DATE COVERED : AS OF JULY 26,2012 S.N. DOOSAN Name of Suppliers Place of Application/Location Date of Submit Description of Material Doosan Recd File Location ASC Transmittal no. Doosan Heavy Industries & Construction. Assad Said For Contracting Co.,Ltd. Page 27 of 75 ASSAD SAID Letter No. Submittal's MS Docu.Ref.No Rev Material Ref. No Reference No. Status ASC Recd Remarks 1 AS-DS-L-0032 MS 70-GG-CDC-001 June 08, 2011 Excavation Excavation Works for Evaporator Foundation 6/8/2011 DF-EH-D-0010/019 B 1/31/2012 Vol-1 2 AS-DS-L-0035 MS 70-GG-CDC-002 June 08, 2011 Blind Concrete Concreting Works (General) 6/8/2011 DF-EH-D-0011 B 1/31/2012 Vol-1 3 AS-DS-L-0034 MS 70-GG-CDC-003 June 08, 2011 Water Proofing Works Waterproofing Membrane & Protective Coatings 6/8/2011 DF-EH-D-0013/30 B 1/31/2012 Vol-1 4 AS-DS-T-0028 MS 70-GG-CDC-004 June 25, 2011 Concrete General A Vol-1 5 AS-DF-T-0032 MS 70-GG-CDC-005 June 25, 2011 Back Filling 6/8/2011 DF-EH-D-0016 B 1/31/2012 Vol-1 6 AS-DS-L-0036 MS 70-GG-CDC-006 June 08, 2011 Dewatering & Sheet Piling Works Dewatering & Sheet Piling Works 6/8/2011 DF-EH-D-0015 B 1/31/2012 Vol-1 7 MS 70-GG-CDC-007 June 25, 2011 Deep Excavation DF-EH-D-0014 B 1/31/2012 Vol-1 8 MS 70-GG-CDC-008 June 15, 2011 BRP/FDN Excavation 8/6/2011 DF-EH-D-0022 B 1/31/2012 Vol-1 9 MS 70-GG-CDC-009 June 27, 2011 Building Works Vol-1 10 MS 70-GG-CDC-010 August 17, 2011 Formworks Vol-1 11 MS 70-GG-CDC-011 August 17, 2011 Concrete Repair Vol-1 12 AS-DS-L-0113 MS 70-GG-CDC-011 October 23, 2011 Concrete Repair Deaerator Area Unit # 71 Wall 10/23/2011 Reply NCR no. 003, Attached MS no.70- GG-CDC-011 (Concrete Repair) No Photos Attached Vol-1 13 AS-DS-L-0116 MS 70-GG-CDC-011 October 25, 2011 Concrete Repair (Deaerator Wall) Deaerator Area Unit # 71 Wall 10/25/2011 Reply NCR no. 003, Attached MS no.70- GG-CDC-011 (Concrete Repair) No Photos Attached Vol-1 14 MS 70-GG-CDC-012 August 17, 2011 Mechanical Couplers Vol-1 15 AS-DF-T-0070 MS 70-GG-CDC-013 September 25, 2011 Concrete(Thin Section) 9/25/2011 Vol-1 16 AS-DF-T-0081 MS 70-GG-CDC-013 1 October 03, 2011 Concrete(Thin Section) 10/3/2011 Vol-1 17 AS-DF-T-0099 MS 70-GG-CDC-015 November 20, 2011 Excavation-Post Treatment Sedimentation Basin 11/20/2011 Vol-1 18 AS-DF-T-0096 MS 70-GG-CDC-016 November 15, 2011 (Erection of PS-Hollow Core Slabs) 11/15/2011 Vol-1 19 AS-DF-T-0097 MS 70-GG-CDC-017 November 15, 2011 (Erection of LLC Siporex Wall Panels) 11/15/2011 Vol-1 20 AS-DF-T-0109 MS 70-GG-CDC-018 November 26, 2011 Masonry Block Work-As Permanent Form Work 11/26/2011 Vol-1 21 AS-DF-T-0137 MS 70-GG-CDC-019 March 14, 2012 CMU-Block Masonry Works-Walls 3/14/2012 Vol-1 22 AS-DF-T-0149 MS 70-GG-CDC-020 April 16, 2012 Epoxy Paint on Exposed Concrete Surface 4/16/2012 Vol-1 23 AS-DF-T-0150 MS 70-GG-CDC-021 April 28, 2012 Plastering Works for Walls 4/28/2012 Vol-1 24 AS-DF-T-0166 MS 70-GG-CDC-022 May 20, 2012 Emulsion & Enamel Paint 5/20/2012 Vol-1 25 AS-DF-T-0178 MS 71-GG-CDC-023 June 03, 2012 Roof Waterproofing System 6/3/2012 Vol-1 26 AS-DF-T-0182 MS 71-GG-CDC-023 1 June 10, 2012 Roof Waterproofing System 6/10/2012 Vol-1 27 AS-DF-T-0194 MS 71-GG-CDC-024 July 22, 2012 Tiling Works for Floors & Walls 7/22/2012 Vol-1 RAS AL KHAIR DESALINATION PLANT PHASE 1 PACKAGE "D" METHOD OF STATEMENT REPORT DATE COVERED : AS OF JULY 26,2012 S.N. DOOSAN Name of Suppliers Place of Application/Location Date of Submit Description of Material Doosan Recd File Location ASC Transmittal no. Doosan Heavy Industries & Construction. Assad Said For Contracting Co.,Ltd. Page 28 of 75 ASSAD SAID Letter No. Submittal's MS Docu.Ref.No Rev Material Ref. No Reference No. Status ASC Recd Remarks 1 AS-DS-L-0032 MS 70-GG-CDC-001 June 08, 2011 Excavation Excavation Works for Evaporator Foundation 6/8/2011 DF-EH-D-0010/019 B 1/31/2012 Vol-1 2 AS-DS-L-0035 MS 70-GG-CDC-002 June 08, 2011 Blind Concrete Concreting Works (General) 6/8/2011 DF-EH-D-0011 B 1/31/2012 Vol-1 3 AS-DS-L-0034 MS 70-GG-CDC-003 June 08, 2011 Water Proofing Works Waterproofing Membrane & Protective Coatings 6/8/2011 DF-EH-D-0013/30 B 1/31/2012 Vol-1 4 AS-DS-T-0028 MS 70-GG-CDC-004 June 25, 2011 Concrete General A Vol-1 5 AS-DF-T-0032 MS 70-GG-CDC-005 June 25, 2011 Back Filling 6/8/2011 DF-EH-D-0016 B 1/31/2012 Vol-1 6 AS-DS-L-0036 MS 70-GG-CDC-006 June 08, 2011 Dewatering & Sheet Piling Works Dewatering & Sheet Piling Works 6/8/2011 DF-EH-D-0015 B 1/31/2012 Vol-1 7 MS 70-GG-CDC-007 June 25, 2011 Deep Excavation DF-EH-D-0014 B 1/31/2012 Vol-1 8 MS 70-GG-CDC-008 June 15, 2011 BRP/FDN Excavation 8/6/2011 DF-EH-D-0022 B 1/31/2012 Vol-1 9 MS 70-GG-CDC-009 June 27, 2011 Building Works Vol-1 10 MS 70-GG-CDC-010 August 17, 2011 Formworks Vol-1 11 MS 70-GG-CDC-011 August 17, 2011 Concrete Repair Vol-1 12 AS-DS-L-0113 MS 70-GG-CDC-011 October 23, 2011 Concrete Repair Deaerator Area Unit # 71 Wall 10/23/2011 Reply NCR no. 003, Attached MS no.70- GG-CDC-011 (Concrete Repair) No Photos Attached Vol-1 13 AS-DS-L-0116 MS 70-GG-CDC-011 October 25, 2011 Concrete Repair (Deaerator Wall) Deaerator Area Unit # 71 Wall 10/25/2011 Reply NCR no. 003, Attached MS no.70- GG-CDC-011 (Concrete Repair) No Photos Attached Vol-1 14 MS 70-GG-CDC-012 August 17, 2011 Mechanical Couplers Vol-1 15 AS-DF-T-0070 MS 70-GG-CDC-013 September 25, 2011 Concrete(Thin Section) 9/25/2011 Vol-1 16 AS-DF-T-0081 MS 70-GG-CDC-013 1 October 03, 2011 Concrete(Thin Section) 10/3/2011 Vol-1 17 AS-DF-T-0099 MS 70-GG-CDC-015 November 20, 2011 Excavation-Post Treatment Sedimentation Basin 11/20/2011 Vol-1 18 AS-DF-T-0096 MS 70-GG-CDC-016 November 15, 2011 (Erection of PS-Hollow Core Slabs) 11/15/2011 Vol-1 19 AS-DF-T-0097 MS 70-GG-CDC-017 November 15, 2011 (Erection of LLC Siporex Wall Panels) 11/15/2011 Vol-1 20 AS-DF-T-0109 MS 70-GG-CDC-018 November 26, 2011 Masonry Block Work-As Permanent Form Work 11/26/2011 Vol-1 21 AS-DF-T-0137 MS 70-GG-CDC-019 March 14, 2012 CMU-Block Masonry Works-Walls 3/14/2012 Vol-1 22 AS-DF-T-0149 MS 70-GG-CDC-020 April 16, 2012 Epoxy Paint on Exposed Concrete Surface 4/16/2012 Vol-1 23 AS-DF-T-0150 MS 70-GG-CDC-021 April 28, 2012 Plastering Works for Walls 4/28/2012 Vol-1 24 AS-DF-T-0166 MS 70-GG-CDC-022 May 20, 2012 Emulsion & Enamel Paint 5/20/2012 Vol-1 25 AS-DF-T-0178 MS 71-GG-CDC-023 June 03, 2012 Roof Waterproofing System 6/3/2012 Vol-1 26 AS-DF-T-0182 MS 71-GG-CDC-023 1 June 10, 2012 Roof Waterproofing System 6/10/2012 Vol-1 27 AS-DF-T-0194 MS 71-GG-CDC-024 July 22, 2012 Tiling Works for Floors & Walls 7/22/2012 Vol-1 RAS AL KHAIR DESALINATION PLANT PHASE 1 PACKAGE "D" METHOD OF STATEMENT REPORT DATE COVERED : AS OF JULY 26,2012 S.N. DOOSAN Name of Suppliers Place of Application/Location Date of Submit Description of Material Doosan Recd File Location ASC Transmittal no. Doosan Heavy Industries & Construction. Assad Said For Contracting Co.,Ltd. Page 29 of 75 ASSAD SAID Letter No. Submittal's MS Docu.Ref.No Rev Material Ref. No Reference No. Status ASC Recd Remarks 1 AS-DS-L-0032 MS 70-GG-CDC-001 June 08, 2011 Excavation Excavation Works for Evaporator Foundation 6/8/2011 DF-EH-D-0010/019 B 1/31/2012 Vol-1 2 AS-DS-L-0035 MS 70-GG-CDC-002 June 08, 2011 Blind Concrete Concreting Works (General) 6/8/2011 DF-EH-D-0011 B 1/31/2012 Vol-1 3 AS-DS-L-0034 MS 70-GG-CDC-003 June 08, 2011 Water Proofing Works Waterproofing Membrane & Protective Coatings 6/8/2011 DF-EH-D-0013/30 B 1/31/2012 Vol-1 4 AS-DS-T-0028 MS 70-GG-CDC-004 June 25, 2011 Concrete General A Vol-1 5 AS-DF-T-0032 MS 70-GG-CDC-005 June 25, 2011 Back Filling 6/8/2011 DF-EH-D-0016 B 1/31/2012 Vol-1 6 AS-DS-L-0036 MS 70-GG-CDC-006 June 08, 2011 Dewatering & Sheet Piling Works Dewatering & Sheet Piling Works 6/8/2011 DF-EH-D-0015 B 1/31/2012 Vol-1 7 MS 70-GG-CDC-007 June 25, 2011 Deep Excavation DF-EH-D-0014 B 1/31/2012 Vol-1 8 MS 70-GG-CDC-008 June 15, 2011 BRP/FDN Excavation 8/6/2011 DF-EH-D-0022 B 1/31/2012 Vol-1 9 MS 70-GG-CDC-009 June 27, 2011 Building Works Vol-1 10 MS 70-GG-CDC-010 August 17, 2011 Formworks Vol-1 11 MS 70-GG-CDC-011 August 17, 2011 Concrete Repair Vol-1 12 AS-DS-L-0113 MS 70-GG-CDC-011 October 23, 2011 Concrete Repair Deaerator Area Unit # 71 Wall 10/23/2011 Reply NCR no. 003, Attached MS no.70- GG-CDC-011 (Concrete Repair) No Photos Attached Vol-1 13 AS-DS-L-0116 MS 70-GG-CDC-011 October 25, 2011 Concrete Repair (Deaerator Wall) Deaerator Area Unit # 71 Wall 10/25/2011 Reply NCR no. 003, Attached MS no.70- GG-CDC-011 (Concrete Repair) No Photos Attached Vol-1 14 MS 70-GG-CDC-012 August 17, 2011 Mechanical Couplers Vol-1 15 AS-DF-T-0070 MS 70-GG-CDC-013 September 25, 2011 Concrete(Thin Section) 9/25/2011 Vol-1 16 AS-DF-T-0081 MS 70-GG-CDC-013 1 October 03, 2011 Concrete(Thin Section) 10/3/2011 Vol-1 17 AS-DF-T-0099 MS 70-GG-CDC-015 November 20, 2011 Excavation-Post Treatment Sedimentation Basin 11/20/2011 Vol-1 18 AS-DF-T-0096 MS 70-GG-CDC-016 November 15, 2011 (Erection of PS-Hollow Core Slabs) 11/15/2011 Vol-1 19 AS-DF-T-0097 MS 70-GG-CDC-017 November 15, 2011 (Erection of LLC Siporex Wall Panels) 11/15/2011 Vol-1 20 AS-DF-T-0109 MS 70-GG-CDC-018 November 26, 2011 Masonry Block Work-As Permanent Form Work 11/26/2011 Vol-1 21 AS-DF-T-0137 MS 70-GG-CDC-019 March 14, 2012 CMU-Block Masonry Works-Walls 3/14/2012 Vol-1 22 AS-DF-T-0149 MS 70-GG-CDC-020 April 16, 2012 Epoxy Paint on Exposed Concrete Surface 4/16/2012 Vol-1 23 AS-DF-T-0150 MS 70-GG-CDC-021 April 28, 2012 Plastering Works for Walls 4/28/2012 Vol-1 24 AS-DF-T-0166 MS 70-GG-CDC-022 May 20, 2012 Emulsion & Enamel Paint 5/20/2012 Vol-1 25 AS-DF-T-0178 MS 71-GG-CDC-023 June 03, 2012 Roof Waterproofing System 6/3/2012 Vol-1 26 AS-DF-T-0182 MS 71-GG-CDC-023 1 June 10, 2012 Roof Waterproofing System 6/10/2012 Vol-1 27 AS-DF-T-0194 MS 71-GG-CDC-024 July 22, 2012 Tiling Works for Floors & Walls 7/22/2012 Vol-1 RAS AL KHAIR DESALINATION PLANT PHASE 1 PACKAGE "D" METHOD OF STATEMENT REPORT DATE COVERED : AS OF JULY 26,2012 S.N. DOOSAN Name of Suppliers Place of Application/Location Date of Submit Description of Material Doosan Recd File Location ASC Transmittal no. Doosan Heavy Industries & Construction. Assad Said For Contracting Co.,Ltd. Page 30 of 75 ASSAD SAID Letter No. Submittal's MS Docu.Ref.No Rev Material Ref. No Reference No. Status ASC Recd Remarks 1 AS-DS-L-0032 MS 70-GG-CDC-001 June 08, 2011 Excavation Excavation Works for Evaporator Foundation 6/8/2011 DF-EH-D-0010/019 B 1/31/2012 Vol-1 2 AS-DS-L-0035 MS 70-GG-CDC-002 June 08, 2011 Blind Concrete Concreting Works (General) 6/8/2011 DF-EH-D-0011 B 1/31/2012 Vol-1 3 AS-DS-L-0034 MS 70-GG-CDC-003 June 08, 2011 Water Proofing Works Waterproofing Membrane & Protective Coatings 6/8/2011 DF-EH-D-0013/30 B 1/31/2012 Vol-1 4 AS-DS-T-0028 MS 70-GG-CDC-004 June 25, 2011 Concrete General A Vol-1 5 AS-DF-T-0032 MS 70-GG-CDC-005 June 25, 2011 Back Filling 6/8/2011 DF-EH-D-0016 B 1/31/2012 Vol-1 6 AS-DS-L-0036 MS 70-GG-CDC-006 June 08, 2011 Dewatering & Sheet Piling Works Dewatering & Sheet Piling Works 6/8/2011 DF-EH-D-0015 B 1/31/2012 Vol-1 7 MS 70-GG-CDC-007 June 25, 2011 Deep Excavation DF-EH-D-0014 B 1/31/2012 Vol-1 8 MS 70-GG-CDC-008 June 15, 2011 BRP/FDN Excavation 8/6/2011 DF-EH-D-0022 B 1/31/2012 Vol-1 9 MS 70-GG-CDC-009 June 27, 2011 Building Works Vol-1 10 MS 70-GG-CDC-010 August 17, 2011 Formworks Vol-1 11 MS 70-GG-CDC-011 August 17, 2011 Concrete Repair Vol-1 12 AS-DS-L-0113 MS 70-GG-CDC-011 October 23, 2011 Concrete Repair Deaerator Area Unit # 71 Wall 10/23/2011 Reply NCR no. 003, Attached MS no.70- GG-CDC-011 (Concrete Repair) No Photos Attached Vol-1 13 AS-DS-L-0116 MS 70-GG-CDC-011 October 25, 2011 Concrete Repair (Deaerator Wall) Deaerator Area Unit # 71 Wall 10/25/2011 Reply NCR no. 003, Attached MS no.70- GG-CDC-011 (Concrete Repair) No Photos Attached Vol-1 14 MS 70-GG-CDC-012 August 17, 2011 Mechanical Couplers Vol-1 15 AS-DF-T-0070 MS 70-GG-CDC-013 September 25, 2011 Concrete(Thin Section) 9/25/2011 Vol-1 16 AS-DF-T-0081 MS 70-GG-CDC-013 1 October 03, 2011 Concrete(Thin Section) 10/3/2011 Vol-1 17 AS-DF-T-0099 MS 70-GG-CDC-015 November 20, 2011 Excavation-Post Treatment Sedimentation Basin 11/20/2011 Vol-1 18 AS-DF-T-0096 MS 70-GG-CDC-016 November 15, 2011 (Erection of PS-Hollow Core Slabs) 11/15/2011 Vol-1 19 AS-DF-T-0097 MS 70-GG-CDC-017 November 15, 2011 (Erection of LLC Siporex Wall Panels) 11/15/2011 Vol-1 20 AS-DF-T-0109 MS 70-GG-CDC-018 November 26, 2011 Masonry Block Work-As Permanent Form Work 11/26/2011 Vol-1 21 AS-DF-T-0137 MS 70-GG-CDC-019 March 14, 2012 CMU-Block Masonry Works-Walls 3/14/2012 Vol-1 22 AS-DF-T-0149 MS 70-GG-CDC-020 April 16, 2012 Epoxy Paint on Exposed Concrete Surface 4/16/2012 Vol-1 23 AS-DF-T-0150 MS 70-GG-CDC-021 April 28, 2012 Plastering Works for Walls 4/28/2012 Vol-1 24 AS-DF-T-0166 MS 70-GG-CDC-022 May 20, 2012 Emulsion & Enamel Paint 5/20/2012 Vol-1 25 AS-DF-T-0178 MS 71-GG-CDC-023 June 03, 2012 Roof Waterproofing System 6/3/2012 Vol-1 26 AS-DF-T-0182 MS 71-GG-CDC-023 1 June 10, 2012 Roof Waterproofing System 6/10/2012 Vol-1 27 AS-DF-T-0194 MS 71-GG-CDC-024 July 22, 2012 Tiling Works for Floors & Walls 7/22/2012 Vol-1 RAS AL KHAIR DESALINATION PLANT PHASE 1 PACKAGE "D" METHOD OF STATEMENT REPORT DATE COVERED : AS OF JULY 26,2012 S.N. DOOSAN Name of Suppliers Place of Application/Location Date of Submit Description of Material Doosan Recd File Location ASC Transmittal no. Doosan Heavy Industries & Construction. Assad Said For Contracting Co.,Ltd. Page 31 of 75 ASSAD SAID Letter No. Submittal's MS Docu.Ref.No Rev Material Ref. No Reference No. Status ASC Recd Remarks 1 AS-DS-L-0032 MS 70-GG-CDC-001 June 08, 2011 Excavation Excavation Works for Evaporator Foundation 6/8/2011 DF-EH-D-0010/019 B 1/31/2012 Vol-1 2 AS-DS-L-0035 MS 70-GG-CDC-002 June 08, 2011 Blind Concrete Concreting Works (General) 6/8/2011 DF-EH-D-0011 B 1/31/2012 Vol-1 3 AS-DS-L-0034 MS 70-GG-CDC-003 June 08, 2011 Water Proofing Works Waterproofing Membrane & Protective Coatings 6/8/2011 DF-EH-D-0013/30 B 1/31/2012 Vol-1 4 AS-DS-T-0028 MS 70-GG-CDC-004 June 25, 2011 Concrete General A Vol-1 5 AS-DF-T-0032 MS 70-GG-CDC-005 June 25, 2011 Back Filling 6/8/2011 DF-EH-D-0016 B 1/31/2012 Vol-1 6 AS-DS-L-0036 MS 70-GG-CDC-006 June 08, 2011 Dewatering & Sheet Piling Works Dewatering & Sheet Piling Works 6/8/2011 DF-EH-D-0015 B 1/31/2012 Vol-1 7 MS 70-GG-CDC-007 June 25, 2011 Deep Excavation DF-EH-D-0014 B 1/31/2012 Vol-1 8 MS 70-GG-CDC-008 June 15, 2011 BRP/FDN Excavation 8/6/2011 DF-EH-D-0022 B 1/31/2012 Vol-1 9 MS 70-GG-CDC-009 June 27, 2011 Building Works Vol-1 10 MS 70-GG-CDC-010 August 17, 2011 Formworks Vol-1 11 MS 70-GG-CDC-011 August 17, 2011 Concrete Repair Vol-1 12 AS-DS-L-0113 MS 70-GG-CDC-011 October 23, 2011 Concrete Repair Deaerator Area Unit # 71 Wall 10/23/2011 Reply NCR no. 003, Attached MS no.70- GG-CDC-011 (Concrete Repair) No Photos Attached Vol-1 13 AS-DS-L-0116 MS 70-GG-CDC-011 October 25, 2011 Concrete Repair (Deaerator Wall) Deaerator Area Unit # 71 Wall 10/25/2011 Reply NCR no. 003, Attached MS no.70- GG-CDC-011 (Concrete Repair) No Photos Attached Vol-1 14 MS 70-GG-CDC-012 August 17, 2011 Mechanical Couplers Vol-1 15 AS-DF-T-0070 MS 70-GG-CDC-013 September 25, 2011 Concrete(Thin Section) 9/25/2011 Vol-1 16 AS-DF-T-0081 MS 70-GG-CDC-013 1 October 03, 2011 Concrete(Thin Section) 10/3/2011 Vol-1 17 AS-DF-T-0099 MS 70-GG-CDC-015 November 20, 2011 Excavation-Post Treatment Sedimentation Basin 11/20/2011 Vol-1 18 AS-DF-T-0096 MS 70-GG-CDC-016 November 15, 2011 (Erection of PS-Hollow Core Slabs) 11/15/2011 Vol-1 19 AS-DF-T-0097 MS 70-GG-CDC-017 November 15, 2011 (Erection of LLC Siporex Wall Panels) 11/15/2011 Vol-1 20 AS-DF-T-0109 MS 70-GG-CDC-018 November 26, 2011 Masonry Block Work-As Permanent Form Work 11/26/2011 Vol-1 21 AS-DF-T-0137 MS 70-GG-CDC-019 March 14, 2012 CMU-Block Masonry Works-Walls 3/14/2012 Vol-1 22 AS-DF-T-0149 MS 70-GG-CDC-020 April 16, 2012 Epoxy Paint on Exposed Concrete Surface 4/16/2012 Vol-1 23 AS-DF-T-0150 MS 70-GG-CDC-021 April 28, 2012 Plastering Works for Walls 4/28/2012 Vol-1 24 AS-DF-T-0166 MS 70-GG-CDC-022 May 20, 2012 Emulsion & Enamel Paint 5/20/2012 Vol-1 25 AS-DF-T-0178 MS 71-GG-CDC-023 June 03, 2012 Roof Waterproofing System 6/3/2012 Vol-1 26 AS-DF-T-0182 MS 71-GG-CDC-023 1 June 10, 2012 Roof Waterproofing System 6/10/2012 Vol-1 27 AS-DF-T-0194 MS 71-GG-CDC-024 July 22, 2012 Tiling Works for Floors & Walls 7/22/2012 Vol-1 RAS AL KHAIR DESALINATION PLANT PHASE 1 PACKAGE "D" METHOD OF STATEMENT REPORT DATE COVERED : AS OF JULY 26,2012 S.N. DOOSAN Name of Suppliers Place of Application/Location Date of Submit Description of Material Doosan Recd File Location ASC Transmittal no. Doosan Heavy Industries & Construction. Assad Said For Contracting Co.,Ltd. Page 32 of 75 ASSAD SAID Letter No. Submittal's MS Docu.Ref.No Rev Material Ref. No Reference No. Status ASC Recd Remarks 1 AS-DS-L-0032 MS 70-GG-CDC-001 June 08, 2011 Excavation Excavation Works for Evaporator Foundation 6/8/2011 DF-EH-D-0010/019 B 1/31/2012 Vol-1 2 AS-DS-L-0035 MS 70-GG-CDC-002 June 08, 2011 Blind Concrete Concreting Works (General) 6/8/2011 DF-EH-D-0011 B 1/31/2012 Vol-1 3 AS-DS-L-0034 MS 70-GG-CDC-003 June 08, 2011 Water Proofing Works Waterproofing Membrane & Protective Coatings 6/8/2011 DF-EH-D-0013/30 B 1/31/2012 Vol-1 4 AS-DS-T-0028 MS 70-GG-CDC-004 June 25, 2011 Concrete General A Vol-1 5 AS-DF-T-0032 MS 70-GG-CDC-005 June 25, 2011 Back Filling 6/8/2011 DF-EH-D-0016 B 1/31/2012 Vol-1 6 AS-DS-L-0036 MS 70-GG-CDC-006 June 08, 2011 Dewatering & Sheet Piling Works Dewatering & Sheet Piling Works 6/8/2011 DF-EH-D-0015 B 1/31/2012 Vol-1 7 MS 70-GG-CDC-007 June 25, 2011 Deep Excavation DF-EH-D-0014 B 1/31/2012 Vol-1 8 MS 70-GG-CDC-008 June 15, 2011 BRP/FDN Excavation 8/6/2011 DF-EH-D-0022 B 1/31/2012 Vol-1 9 MS 70-GG-CDC-009 June 27, 2011 Building Works Vol-1 10 MS 70-GG-CDC-010 August 17, 2011 Formworks Vol-1 11 MS 70-GG-CDC-011 August 17, 2011 Concrete Repair Vol-1 12 AS-DS-L-0113 MS 70-GG-CDC-011 October 23, 2011 Concrete Repair Deaerator Area Unit # 71 Wall 10/23/2011 Reply NCR no. 003, Attached MS no.70- GG-CDC-011 (Concrete Repair) No Photos Attached Vol-1 13 AS-DS-L-0116 MS 70-GG-CDC-011 October 25, 2011 Concrete Repair (Deaerator Wall) Deaerator Area Unit # 71 Wall 10/25/2011 Reply NCR no. 003, Attached MS no.70- GG-CDC-011 (Concrete Repair) No Photos Attached Vol-1 14 MS 70-GG-CDC-012 August 17, 2011 Mechanical Couplers Vol-1 15 AS-DF-T-0070 MS 70-GG-CDC-013 September 25, 2011 Concrete(Thin Section) 9/25/2011 Vol-1 16 AS-DF-T-0081 MS 70-GG-CDC-013 1 October 03, 2011 Concrete(Thin Section) 10/3/2011 Vol-1 17 AS-DF-T-0099 MS 70-GG-CDC-015 November 20, 2011 Excavation-Post Treatment Sedimentation Basin 11/20/2011 Vol-1 18 AS-DF-T-0096 MS 70-GG-CDC-016 November 15, 2011 (Erection of PS-Hollow Core Slabs) 11/15/2011 Vol-1 19 AS-DF-T-0097 MS 70-GG-CDC-017 November 15, 2011 (Erection of LLC Siporex Wall Panels) 11/15/2011 Vol-1 20 AS-DF-T-0109 MS 70-GG-CDC-018 November 26, 2011 Masonry Block Work-As Permanent Form Work 11/26/2011 Vol-1 21 AS-DF-T-0137 MS 70-GG-CDC-019 March 14, 2012 CMU-Block Masonry Works-Walls 3/14/2012 Vol-1 22 AS-DF-T-0149 MS 70-GG-CDC-020 April 16, 2012 Epoxy Paint on Exposed Concrete Surface 4/16/2012 Vol-1 23 AS-DF-T-0150 MS 70-GG-CDC-021 April 28, 2012 Plastering Works for Walls 4/28/2012 Vol-1 24 AS-DF-T-0166 MS 70-GG-CDC-022 May 20, 2012 Emulsion & Enamel Paint 5/20/2012 Vol-1 25 AS-DF-T-0178 MS 71-GG-CDC-023 June 03, 2012 Roof Waterproofing System 6/3/2012 Vol-1 26 AS-DF-T-0182 MS 71-GG-CDC-023 1 June 10, 2012 Roof Waterproofing System 6/10/2012 Vol-1 27 AS-DF-T-0194 MS 71-GG-CDC-024 July 22, 2012 Tiling Works for Floors & Walls 7/22/2012 Vol-1 RAS AL KHAIR DESALINATION PLANT PHASE 1 PACKAGE "D" METHOD OF STATEMENT REPORT DATE COVERED : AS OF JULY 26,2012 S.N. DOOSAN Name of Suppliers Place of Application/Location Date of Submit Description of Material Doosan Recd File Location ASC Transmittal no. Doosan Heavy Industries & Construction. Assad Said For Contracting Co.,Ltd. Page 33 of 75 ASSAD SAID Letter No. Submittal's MS Docu.Ref.No Rev Material Ref. No Reference No. Status ASC Recd Remarks 1 AS-DS-L-0032 MS 70-GG-CDC-001 June 08, 2011 Excavation Excavation Works for Evaporator Foundation 6/8/2011 DF-EH-D-0010/019 B 1/31/2012 Vol-1 2 AS-DS-L-0035 MS 70-GG-CDC-002 June 08, 2011 Blind Concrete Concreting Works (General) 6/8/2011 DF-EH-D-0011 B 1/31/2012 Vol-1 3 AS-DS-L-0034 MS 70-GG-CDC-003 June 08, 2011 Water Proofing Works Waterproofing Membrane & Protective Coatings 6/8/2011 DF-EH-D-0013/30 B 1/31/2012 Vol-1 4 AS-DS-T-0028 MS 70-GG-CDC-004 June 25, 2011 Concrete General A Vol-1 5 AS-DF-T-0032 MS 70-GG-CDC-005 June 25, 2011 Back Filling 6/8/2011 DF-EH-D-0016 B 1/31/2012 Vol-1 6 AS-DS-L-0036 MS 70-GG-CDC-006 June 08, 2011 Dewatering & Sheet Piling Works Dewatering & Sheet Piling Works 6/8/2011 DF-EH-D-0015 B 1/31/2012 Vol-1 7 MS 70-GG-CDC-007 June 25, 2011 Deep Excavation DF-EH-D-0014 B 1/31/2012 Vol-1 8 MS 70-GG-CDC-008 June 15, 2011 BRP/FDN Excavation 8/6/2011 DF-EH-D-0022 B 1/31/2012 Vol-1 9 MS 70-GG-CDC-009 June 27, 2011 Building Works Vol-1 10 MS 70-GG-CDC-010 August 17, 2011 Formworks Vol-1 11 MS 70-GG-CDC-011 August 17, 2011 Concrete Repair Vol-1 12 AS-DS-L-0113 MS 70-GG-CDC-011 October 23, 2011 Concrete Repair Deaerator Area Unit # 71 Wall 10/23/2011 Reply NCR no. 003, Attached MS no.70- GG-CDC-011 (Concrete Repair) No Photos Attached Vol-1 13 AS-DS-L-0116 MS 70-GG-CDC-011 October 25, 2011 Concrete Repair (Deaerator Wall) Deaerator Area Unit # 71 Wall 10/25/2011 Reply NCR no. 003, Attached MS no.70- GG-CDC-011 (Concrete Repair) No Photos Attached Vol-1 14 MS 70-GG-CDC-012 August 17, 2011 Mechanical Couplers Vol-1 15 AS-DF-T-0070 MS 70-GG-CDC-013 September 25, 2011 Concrete(Thin Section) 9/25/2011 Vol-1 16 AS-DF-T-0081 MS 70-GG-CDC-013 1 October 03, 2011 Concrete(Thin Section) 10/3/2011 Vol-1 17 AS-DF-T-0099 MS 70-GG-CDC-015 November 20, 2011 Excavation-Post Treatment Sedimentation Basin 11/20/2011 Vol-1 18 AS-DF-T-0096 MS 70-GG-CDC-016 November 15, 2011 (Erection of PS-Hollow Core Slabs) 11/15/2011 Vol-1 19 AS-DF-T-0097 MS 70-GG-CDC-017 November 15, 2011 (Erection of LLC Siporex Wall Panels) 11/15/2011 Vol-1 20 AS-DF-T-0109 MS 70-GG-CDC-018 November 26, 2011 Masonry Block Work-As Permanent Form Work 11/26/2011 Vol-1 21 AS-DF-T-0137 MS 70-GG-CDC-019 March 14, 2012 CMU-Block Masonry Works-Walls 3/14/2012 Vol-1 22 AS-DF-T-0149 MS 70-GG-CDC-020 April 16, 2012 Epoxy Paint on Exposed Concrete Surface 4/16/2012 Vol-1 23 AS-DF-T-0150 MS 70-GG-CDC-021 April 28, 2012 Plastering Works for Walls 4/28/2012 Vol-1 24 AS-DF-T-0166 MS 70-GG-CDC-022 May 20, 2012 Emulsion & Enamel Paint 5/20/2012 Vol-1 25 AS-DF-T-0178 MS 71-GG-CDC-023 June 03, 2012 Roof Waterproofing System 6/3/2012 Vol-1 26 AS-DF-T-0182 MS 71-GG-CDC-023 1 June 10, 2012 Roof Waterproofing System 6/10/2012 Vol-1 27 AS-DF-T-0194 MS 71-GG-CDC-024 July 22, 2012 Tiling Works for Floors & Walls 7/22/2012 Vol-1 RAS AL KHAIR DESALINATION PLANT PHASE 1 PACKAGE "D" METHOD OF STATEMENT REPORT DATE COVERED : AS OF JULY 26,2012 S.N. DOOSAN Name of Suppliers Place of Application/Location Date of Submit Description of Material Doosan Recd File Location ASC Transmittal no. Doosan Heavy Industries & Construction. Assad Said For Contracting Co.,Ltd. Page 34 of 75 ASSAD SAID Letter No. Submittal's MS Docu.Ref.No Rev Material Ref. No Reference No. Status ASC Recd Remarks 1 AS-DS-L-0032 MS 70-GG-CDC-001 June 08, 2011 Excavation Excavation Works for Evaporator Foundation 6/8/2011 DF-EH-D-0010/019 B 1/31/2012 Vol-1 2 AS-DS-L-0035 MS 70-GG-CDC-002 June 08, 2011 Blind Concrete Concreting Works (General) 6/8/2011 DF-EH-D-0011 B 1/31/2012 Vol-1 3 AS-DS-L-0034 MS 70-GG-CDC-003 June 08, 2011 Water Proofing Works Waterproofing Membrane & Protective Coatings 6/8/2011 DF-EH-D-0013/30 B 1/31/2012 Vol-1 4 AS-DS-T-0028 MS 70-GG-CDC-004 June 25, 2011 Concrete General A Vol-1 5 AS-DF-T-0032 MS 70-GG-CDC-005 June 25, 2011 Back Filling 6/8/2011 DF-EH-D-0016 B 1/31/2012 Vol-1 6 AS-DS-L-0036 MS 70-GG-CDC-006 June 08, 2011 Dewatering & Sheet Piling Works Dewatering & Sheet Piling Works 6/8/2011 DF-EH-D-0015 B 1/31/2012 Vol-1 7 MS 70-GG-CDC-007 June 25, 2011 Deep Excavation DF-EH-D-0014 B 1/31/2012 Vol-1 8 MS 70-GG-CDC-008 June 15, 2011 BRP/FDN Excavation 8/6/2011 DF-EH-D-0022 B 1/31/2012 Vol-1 9 MS 70-GG-CDC-009 June 27, 2011 Building Works Vol-1 10 MS 70-GG-CDC-010 August 17, 2011 Formworks Vol-1 11 MS 70-GG-CDC-011 August 17, 2011 Concrete Repair Vol-1 12 AS-DS-L-0113 MS 70-GG-CDC-011 October 23, 2011 Concrete Repair Deaerator Area Unit # 71 Wall 10/23/2011 Reply NCR no. 003, Attached MS no.70- GG-CDC-011 (Concrete Repair) No Photos Attached Vol-1 13 AS-DS-L-0116 MS 70-GG-CDC-011 October 25, 2011 Concrete Repair (Deaerator Wall) Deaerator Area Unit # 71 Wall 10/25/2011 Reply NCR no. 003, Attached MS no.70- GG-CDC-011 (Concrete Repair) No Photos Attached Vol-1 14 MS 70-GG-CDC-012 August 17, 2011 Mechanical Couplers Vol-1 15 AS-DF-T-0070 MS 70-GG-CDC-013 September 25, 2011 Concrete(Thin Section) 9/25/2011 Vol-1 16 AS-DF-T-0081 MS 70-GG-CDC-013 1 October 03, 2011 Concrete(Thin Section) 10/3/2011 Vol-1 17 AS-DF-T-0099 MS 70-GG-CDC-015 November 20, 2011 Excavation-Post Treatment Sedimentation Basin 11/20/2011 Vol-1 18 AS-DF-T-0096 MS 70-GG-CDC-016 November 15, 2011 (Erection of PS-Hollow Core Slabs) 11/15/2011 Vol-1 19 AS-DF-T-0097 MS 70-GG-CDC-017 November 15, 2011 (Erection of LLC Siporex Wall Panels) 11/15/2011 Vol-1 20 AS-DF-T-0109 MS 70-GG-CDC-018 November 26, 2011 Masonry Block Work-As Permanent Form Work 11/26/2011 Vol-1 21 AS-DF-T-0137 MS 70-GG-CDC-019 March 14, 2012 CMU-Block Masonry Works-Walls 3/14/2012 Vol-1 22 AS-DF-T-0149 MS 70-GG-CDC-020 April 16, 2012 Epoxy Paint on Exposed Concrete Surface 4/16/2012 Vol-1 23 AS-DF-T-0150 MS 70-GG-CDC-021 April 28, 2012 Plastering Works for Walls 4/28/2012 Vol-1 24 AS-DF-T-0166 MS 70-GG-CDC-022 May 20, 2012 Emulsion & Enamel Paint 5/20/2012 Vol-1 25 AS-DF-T-0178 MS 71-GG-CDC-023 June 03, 2012 Roof Waterproofing System 6/3/2012 Vol-1 26 AS-DF-T-0182 MS 71-GG-CDC-023 1 June 10, 2012 Roof Waterproofing System 6/10/2012 Vol-1 27 AS-DF-T-0194 MS 71-GG-CDC-024 July 22, 2012 Tiling Works for Floors & Walls 7/22/2012 Vol-1 RAS AL KHAIR DESALINATION PLANT PHASE 1 PACKAGE "D" METHOD OF STATEMENT REPORT DATE COVERED : AS OF JULY 26,2012 S.N. DOOSAN Name of Suppliers Place of Application/Location Date of Submit Description of Material Doosan Recd File Location ASC Transmittal no. Doosan Heavy Industries & Construction. Assad Said For Contracting Co.,Ltd. Page 35 of 75 ASSAD SAID Letter No. Submittal's MS Docu.Ref.No Rev Material Ref. No Reference No. Status ASC Recd Remarks 1 AS-DS-L-0032 MS 70-GG-CDC-001 June 08, 2011 Excavation Excavation Works for Evaporator Foundation 6/8/2011 DF-EH-D-0010/019 B 1/31/2012 Vol-1 2 AS-DS-L-0035 MS 70-GG-CDC-002 June 08, 2011 Blind Concrete Concreting Works (General) 6/8/2011 DF-EH-D-0011 B 1/31/2012 Vol-1 3 AS-DS-L-0034 MS 70-GG-CDC-003 June 08, 2011 Water Proofing Works Waterproofing Membrane & Protective Coatings 6/8/2011 DF-EH-D-0013/30 B 1/31/2012 Vol-1 4 AS-DS-T-0028 MS 70-GG-CDC-004 June 25, 2011 Concrete General A Vol-1 5 AS-DF-T-0032 MS 70-GG-CDC-005 June 25, 2011 Back Filling 6/8/2011 DF-EH-D-0016 B 1/31/2012 Vol-1 6 AS-DS-L-0036 MS 70-GG-CDC-006 June 08, 2011 Dewatering & Sheet Piling Works Dewatering & Sheet Piling Works 6/8/2011 DF-EH-D-0015 B 1/31/2012 Vol-1 7 MS 70-GG-CDC-007 June 25, 2011 Deep Excavation DF-EH-D-0014 B 1/31/2012 Vol-1 8 MS 70-GG-CDC-008 June 15, 2011 BRP/FDN Excavation 8/6/2011 DF-EH-D-0022 B 1/31/2012 Vol-1 9 MS 70-GG-CDC-009 June 27, 2011 Building Works Vol-1 10 MS 70-GG-CDC-010 August 17, 2011 Formworks Vol-1 11 MS 70-GG-CDC-011 August 17, 2011 Concrete Repair Vol-1 12 AS-DS-L-0113 MS 70-GG-CDC-011 October 23, 2011 Concrete Repair Deaerator Area Unit # 71 Wall 10/23/2011 Reply NCR no. 003, Attached MS no.70- GG-CDC-011 (Concrete Repair) No Photos Attached Vol-1 13 AS-DS-L-0116 MS 70-GG-CDC-011 October 25, 2011 Concrete Repair (Deaerator Wall) Deaerator Area Unit # 71 Wall 10/25/2011 Reply NCR no. 003, Attached MS no.70- GG-CDC-011 (Concrete Repair) No Photos Attached Vol-1 14 MS 70-GG-CDC-012 August 17, 2011 Mechanical Couplers Vol-1 15 AS-DF-T-0070 MS 70-GG-CDC-013 September 25, 2011 Concrete(Thin Section) 9/25/2011 Vol-1 16 AS-DF-T-0081 MS 70-GG-CDC-013 1 October 03, 2011 Concrete(Thin Section) 10/3/2011 Vol-1 17 AS-DF-T-0099 MS 70-GG-CDC-015 November 20, 2011 Excavation-Post Treatment Sedimentation Basin 11/20/2011 Vol-1 18 AS-DF-T-0096 MS 70-GG-CDC-016 November 15, 2011 (Erection of PS-Hollow Core Slabs) 11/15/2011 Vol-1 19 AS-DF-T-0097 MS 70-GG-CDC-017 November 15, 2011 (Erection of LLC Siporex Wall Panels) 11/15/2011 Vol-1 20 AS-DF-T-0109 MS 70-GG-CDC-018 November 26, 2011 Masonry Block Work-As Permanent Form Work 11/26/2011 Vol-1 21 AS-DF-T-0137 MS 70-GG-CDC-019 March 14, 2012 CMU-Block Masonry Works-Walls 3/14/2012 Vol-1 22 AS-DF-T-0149 MS 70-GG-CDC-020 April 16, 2012 Epoxy Paint on Exposed Concrete Surface 4/16/2012 Vol-1 23 AS-DF-T-0150 MS 70-GG-CDC-021 April 28, 2012 Plastering Works for Walls 4/28/2012 Vol-1 24 AS-DF-T-0166 MS 70-GG-CDC-022 May 20, 2012 Emulsion & Enamel Paint 5/20/2012 Vol-1 25 AS-DF-T-0178 MS 71-GG-CDC-023 June 03, 2012 Roof Waterproofing System 6/3/2012 Vol-1 26 AS-DF-T-0182 MS 71-GG-CDC-023 1 June 10, 2012 Roof Waterproofing System 6/10/2012 Vol-1 27 AS-DF-T-0194 MS 71-GG-CDC-024 July 22, 2012 Tiling Works for Floors & Walls 7/22/2012 Vol-1 RAS AL KHAIR DESALINATION PLANT PHASE 1 PACKAGE "D" METHOD OF STATEMENT REPORT DATE COVERED : AS OF JULY 26,2012 S.N. DOOSAN Name of Suppliers Place of Application/Location Date of Submit Description of Material Doosan Recd File Location ASC Transmittal no. Doosan Heavy Industries & Construction. Assad Said For Contracting Co.,Ltd. Page 36 of 75 ASSAD SAID Letter No. Submittal's MS Docu.Ref.No Rev Material Ref. No Reference No. Status ASC Recd Remarks 1 AS-DS-L-0032 MS 70-GG-CDC-001 June 08, 2011 Excavation Excavation Works for Evaporator Foundation 6/8/2011 DF-EH-D-0010/019 B 1/31/2012 Vol-1 2 AS-DS-L-0035 MS 70-GG-CDC-002 June 08, 2011 Blind Concrete Concreting Works (General) 6/8/2011 DF-EH-D-0011 B 1/31/2012 Vol-1 3 AS-DS-L-0034 MS 70-GG-CDC-003 June 08, 2011 Water Proofing Works Waterproofing Membrane & Protective Coatings 6/8/2011 DF-EH-D-0013/30 B 1/31/2012 Vol-1 4 AS-DS-T-0028 MS 70-GG-CDC-004 June 25, 2011 Concrete General A Vol-1 5 AS-DF-T-0032 MS 70-GG-CDC-005 June 25, 2011 Back Filling 6/8/2011 DF-EH-D-0016 B 1/31/2012 Vol-1 6 AS-DS-L-0036 MS 70-GG-CDC-006 June 08, 2011 Dewatering & Sheet Piling Works Dewatering & Sheet Piling Works 6/8/2011 DF-EH-D-0015 B 1/31/2012 Vol-1 7 MS 70-GG-CDC-007 June 25, 2011 Deep Excavation DF-EH-D-0014 B 1/31/2012 Vol-1 8 MS 70-GG-CDC-008 June 15, 2011 BRP/FDN Excavation 8/6/2011 DF-EH-D-0022 B 1/31/2012 Vol-1 9 MS 70-GG-CDC-009 June 27, 2011 Building Works Vol-1 10 MS 70-GG-CDC-010 August 17, 2011 Formworks Vol-1 11 MS 70-GG-CDC-011 August 17, 2011 Concrete Repair Vol-1 12 AS-DS-L-0113 MS 70-GG-CDC-011 October 23, 2011 Concrete Repair Deaerator Area Unit # 71 Wall 10/23/2011 Reply NCR no. 003, Attached MS no.70- GG-CDC-011 (Concrete Repair) No Photos Attached Vol-1 13 AS-DS-L-0116 MS 70-GG-CDC-011 October 25, 2011 Concrete Repair (Deaerator Wall) Deaerator Area Unit # 71 Wall 10/25/2011 Reply NCR no. 003, Attached MS no.70- GG-CDC-011 (Concrete Repair) No Photos Attached Vol-1 14 MS 70-GG-CDC-012 August 17, 2011 Mechanical Couplers Vol-1 15 AS-DF-T-0070 MS 70-GG-CDC-013 September 25, 2011 Concrete(Thin Section) 9/25/2011 Vol-1 16 AS-DF-T-0081 MS 70-GG-CDC-013 1 October 03, 2011 Concrete(Thin Section) 10/3/2011 Vol-1 17 AS-DF-T-0099 MS 70-GG-CDC-015 November 20, 2011 Excavation-Post Treatment Sedimentation Basin 11/20/2011 Vol-1 18 AS-DF-T-0096 MS 70-GG-CDC-016 November 15, 2011 (Erection of PS-Hollow Core Slabs) 11/15/2011 Vol-1 19 AS-DF-T-0097 MS 70-GG-CDC-017 November 15, 2011 (Erection of LLC Siporex Wall Panels) 11/15/2011 Vol-1 20 AS-DF-T-0109 MS 70-GG-CDC-018 November 26, 2011 Masonry Block Work-As Permanent Form Work 11/26/2011 Vol-1 21 AS-DF-T-0137 MS 70-GG-CDC-019 March 14, 2012 CMU-Block Masonry Works-Walls 3/14/2012 Vol-1 22 AS-DF-T-0149 MS 70-GG-CDC-020 April 16, 2012 Epoxy Paint on Exposed Concrete Surface 4/16/2012 Vol-1 23 AS-DF-T-0150 MS 70-GG-CDC-021 April 28, 2012 Plastering Works for Walls 4/28/2012 Vol-1 24 AS-DF-T-0166 MS 70-GG-CDC-022 May 20, 2012 Emulsion & Enamel Paint 5/20/2012 Vol-1 25 AS-DF-T-0178 MS 71-GG-CDC-023 June 03, 2012 Roof Waterproofing System 6/3/2012 Vol-1 26 AS-DF-T-0182 MS 71-GG-CDC-023 1 June 10, 2012 Roof Waterproofing System 6/10/2012 Vol-1 27 AS-DF-T-0194 MS 71-GG-CDC-024 July 22, 2012 Tiling Works for Floors & Walls 7/22/2012 Vol-1 RAS AL KHAIR DESALINATION PLANT PHASE 1 PACKAGE "D" METHOD OF STATEMENT REPORT DATE COVERED : AS OF JULY 26,2012 S.N. DOOSAN Name of Suppliers Place of Application/Location Date of Submit Description of Material Doosan Recd File Location ASC Transmittal no. Doosan Heavy Industries & Construction. Assad Said For Contracting Co.,Ltd. Page 37 of 75 ASSAD SAID Letter No. Submittal's MS Docu.Ref.No Rev Material Ref. No Reference No. Status ASC Recd Remarks 1 AS-DS-L-0032 MS 70-GG-CDC-001 June 08, 2011 Excavation Excavation Works for Evaporator Foundation 6/8/2011 DF-EH-D-0010/019 B 1/31/2012 Vol-1 2 AS-DS-L-0035 MS 70-GG-CDC-002 June 08, 2011 Blind Concrete Concreting Works (General) 6/8/2011 DF-EH-D-0011 B 1/31/2012 Vol-1 3 AS-DS-L-0034 MS 70-GG-CDC-003 June 08, 2011 Water Proofing Works Waterproofing Membrane & Protective Coatings 6/8/2011 DF-EH-D-0013/30 B 1/31/2012 Vol-1 4 AS-DS-T-0028 MS 70-GG-CDC-004 June 25, 2011 Concrete General A Vol-1 5 AS-DF-T-0032 MS 70-GG-CDC-005 June 25, 2011 Back Filling 6/8/2011 DF-EH-D-0016 B 1/31/2012 Vol-1 6 AS-DS-L-0036 MS 70-GG-CDC-006 June 08, 2011 Dewatering & Sheet Piling Works Dewatering & Sheet Piling Works 6/8/2011 DF-EH-D-0015 B 1/31/2012 Vol-1 7 MS 70-GG-CDC-007 June 25, 2011 Deep Excavation DF-EH-D-0014 B 1/31/2012 Vol-1 8 MS 70-GG-CDC-008 June 15, 2011 BRP/FDN Excavation 8/6/2011 DF-EH-D-0022 B 1/31/2012 Vol-1 9 MS 70-GG-CDC-009 June 27, 2011 Building Works Vol-1 10 MS 70-GG-CDC-010 August 17, 2011 Formworks Vol-1 11 MS 70-GG-CDC-011 August 17, 2011 Concrete Repair Vol-1 12 AS-DS-L-0113 MS 70-GG-CDC-011 October 23, 2011 Concrete Repair Deaerator Area Unit # 71 Wall 10/23/2011 Reply NCR no. 003, Attached MS no.70- GG-CDC-011 (Concrete Repair) No Photos Attached Vol-1 13 AS-DS-L-0116 MS 70-GG-CDC-011 October 25, 2011 Concrete Repair (Deaerator Wall) Deaerator Area Unit # 71 Wall 10/25/2011 Reply NCR no. 003, Attached MS no.70- GG-CDC-011 (Concrete Repair) No Photos Attached Vol-1 14 MS 70-GG-CDC-012 August 17, 2011 Mechanical Couplers Vol-1 15 AS-DF-T-0070 MS 70-GG-CDC-013 September 25, 2011 Concrete(Thin Section) 9/25/2011 Vol-1 16 AS-DF-T-0081 MS 70-GG-CDC-013 1 October 03, 2011 Concrete(Thin Section) 10/3/2011 Vol-1 17 AS-DF-T-0099 MS 70-GG-CDC-015 November 20, 2011 Excavation-Post Treatment Sedimentation Basin 11/20/2011 Vol-1 18 AS-DF-T-0096 MS 70-GG-CDC-016 November 15, 2011 (Erection of PS-Hollow Core Slabs) 11/15/2011 Vol-1 19 AS-DF-T-0097 MS 70-GG-CDC-017 November 15, 2011 (Erection of LLC Siporex Wall Panels) 11/15/2011 Vol-1 20 AS-DF-T-0109 MS 70-GG-CDC-018 November 26, 2011 Masonry Block Work-As Permanent Form Work 11/26/2011 Vol-1 21 AS-DF-T-0137 MS 70-GG-CDC-019 March 14, 2012 CMU-Block Masonry Works-Walls 3/14/2012 Vol-1 22 AS-DF-T-0149 MS 70-GG-CDC-020 April 16, 2012 Epoxy Paint on Exposed Concrete Surface 4/16/2012 Vol-1 23 AS-DF-T-0150 MS 70-GG-CDC-021 April 28, 2012 Plastering Works for Walls 4/28/2012 Vol-1 24 AS-DF-T-0166 MS 70-GG-CDC-022 May 20, 2012 Emulsion & Enamel Paint 5/20/2012 Vol-1 25 AS-DF-T-0178 MS 71-GG-CDC-023 June 03, 2012 Roof Waterproofing System 6/3/2012 Vol-1 26 AS-DF-T-0182 MS 71-GG-CDC-023 1 June 10, 2012 Roof Waterproofing System 6/10/2012 Vol-1 27 AS-DF-T-0194 MS 71-GG-CDC-024 July 22, 2012 Tiling Works for Floors & Walls 7/22/2012 Vol-1 RAS AL KHAIR DESALINATION PLANT PHASE 1 PACKAGE "D" METHOD OF STATEMENT REPORT DATE COVERED : AS OF JULY 26,2012 S.N. DOOSAN Name of Suppliers Place of Application/Location Date of Submit Description of Material Doosan Recd File Location ASC Transmittal no. Doosan Heavy Industries & Construction. Assad Said For Contracting Co.,Ltd. Page 38 of 75 ASSAD SAID Letter No. Submittal's MS Docu.Ref.No Rev Material Ref. No Reference No. Status ASC Recd Remarks 1 AS-DS-L-0032 MS 70-GG-CDC-001 June 08, 2011 Excavation Excavation Works for Evaporator Foundation 6/8/2011 DF-EH-D-0010/019 B 1/31/2012 Vol-1 2 AS-DS-L-0035 MS 70-GG-CDC-002 June 08, 2011 Blind Concrete Concreting Works (General) 6/8/2011 DF-EH-D-0011 B 1/31/2012 Vol-1 3 AS-DS-L-0034 MS 70-GG-CDC-003 June 08, 2011 Water Proofing Works Waterproofing Membrane & Protective Coatings 6/8/2011 DF-EH-D-0013/30 B 1/31/2012 Vol-1 4 AS-DS-T-0028 MS 70-GG-CDC-004 June 25, 2011 Concrete General A Vol-1 5 AS-DF-T-0032 MS 70-GG-CDC-005 June 25, 2011 Back Filling 6/8/2011 DF-EH-D-0016 B 1/31/2012 Vol-1 6 AS-DS-L-0036 MS 70-GG-CDC-006 June 08, 2011 Dewatering & Sheet Piling Works Dewatering & Sheet Piling Works 6/8/2011 DF-EH-D-0015 B 1/31/2012 Vol-1 7 MS 70-GG-CDC-007 June 25, 2011 Deep Excavation DF-EH-D-0014 B 1/31/2012 Vol-1 8 MS 70-GG-CDC-008 June 15, 2011 BRP/FDN Excavation 8/6/2011 DF-EH-D-0022 B 1/31/2012 Vol-1 9 MS 70-GG-CDC-009 June 27, 2011 Building Works Vol-1 10 MS 70-GG-CDC-010 August 17, 2011 Formworks Vol-1 11 MS 70-GG-CDC-011 August 17, 2011 Concrete Repair Vol-1 12 AS-DS-L-0113 MS 70-GG-CDC-011 October 23, 2011 Concrete Repair Deaerator Area Unit # 71 Wall 10/23/2011 Reply NCR no. 003, Attached MS no.70- GG-CDC-011 (Concrete Repair) No Photos Attached Vol-1 13 AS-DS-L-0116 MS 70-GG-CDC-011 October 25, 2011 Concrete Repair (Deaerator Wall) Deaerator Area Unit # 71 Wall 10/25/2011 Reply NCR no. 003, Attached MS no.70- GG-CDC-011 (Concrete Repair) No Photos Attached Vol-1 14 MS 70-GG-CDC-012 August 17, 2011 Mechanical Couplers Vol-1 15 AS-DF-T-0070 MS 70-GG-CDC-013 September 25, 2011 Concrete(Thin Section) 9/25/2011 Vol-1 16 AS-DF-T-0081 MS 70-GG-CDC-013 1 October 03, 2011 Concrete(Thin Section) 10/3/2011 Vol-1 17 AS-DF-T-0099 MS 70-GG-CDC-015 November 20, 2011 Excavation-Post Treatment Sedimentation Basin 11/20/2011 Vol-1 18 AS-DF-T-0096 MS 70-GG-CDC-016 November 15, 2011 (Erection of PS-Hollow Core Slabs) 11/15/2011 Vol-1 19 AS-DF-T-0097 MS 70-GG-CDC-017 November 15, 2011 (Erection of LLC Siporex Wall Panels) 11/15/2011 Vol-1 20 AS-DF-T-0109 MS 70-GG-CDC-018 November 26, 2011 Masonry Block Work-As Permanent Form Work 11/26/2011 Vol-1 21 AS-DF-T-0137 MS 70-GG-CDC-019 March 14, 2012 CMU-Block Masonry Works-Walls 3/14/2012 Vol-1 22 AS-DF-T-0149 MS 70-GG-CDC-020 April 16, 2012 Epoxy Paint on Exposed Concrete Surface 4/16/2012 Vol-1 23 AS-DF-T-0150 MS 70-GG-CDC-021 April 28, 2012 Plastering Works for Walls 4/28/2012 Vol-1 24 AS-DF-T-0166 MS 70-GG-CDC-022 May 20, 2012 Emulsion & Enamel Paint 5/20/2012 Vol-1 25 AS-DF-T-0178 MS 71-GG-CDC-023 June 03, 2012 Roof Waterproofing System 6/3/2012 Vol-1 26 AS-DF-T-0182 MS 71-GG-CDC-023 1 June 10, 2012 Roof Waterproofing System 6/10/2012 Vol-1 27 AS-DF-T-0194 MS 71-GG-CDC-024 July 22, 2012 Tiling Works for Floors & Walls 7/22/2012 Vol-1 RAS AL KHAIR DESALINATION PLANT PHASE 1 PACKAGE "D" METHOD OF STATEMENT REPORT DATE COVERED : AS OF JULY 26,2012 S.N. DOOSAN Name of Suppliers Place of Application/Location Date of Submit Description of Material Doosan Recd File Location ASC Transmittal no. Doosan Heavy Industries & Construction. Assad Said For Contracting Co.,Ltd. Page 39 of 75 ASSAD SAID Letter No. Submittal's MS Docu.Ref.No Rev Material Ref. No Reference No. Status ASC Recd Remarks 1 AS-DS-L-0032 MS 70-GG-CDC-001 June 08, 2011 Excavation Excavation Works for Evaporator Foundation 6/8/2011 DF-EH-D-0010/019 B 1/31/2012 Vol-1 2 AS-DS-L-0035 MS 70-GG-CDC-002 June 08, 2011 Blind Concrete Concreting Works (General) 6/8/2011 DF-EH-D-0011 B 1/31/2012 Vol-1 3 AS-DS-L-0034 MS 70-GG-CDC-003 June 08, 2011 Water Proofing Works Waterproofing Membrane & Protective Coatings 6/8/2011 DF-EH-D-0013/30 B 1/31/2012 Vol-1 4 AS-DS-T-0028 MS 70-GG-CDC-004 June 25, 2011 Concrete General A Vol-1 5 AS-DF-T-0032 MS 70-GG-CDC-005 June 25, 2011 Back Filling 6/8/2011 DF-EH-D-0016 B 1/31/2012 Vol-1 6 AS-DS-L-0036 MS 70-GG-CDC-006 June 08, 2011 Dewatering & Sheet Piling Works Dewatering & Sheet Piling Works 6/8/2011 DF-EH-D-0015 B 1/31/2012 Vol-1 7 MS 70-GG-CDC-007 June 25, 2011 Deep Excavation DF-EH-D-0014 B 1/31/2012 Vol-1 8 MS 70-GG-CDC-008 June 15, 2011 BRP/FDN Excavation 8/6/2011 DF-EH-D-0022 B 1/31/2012 Vol-1 9 MS 70-GG-CDC-009 June 27, 2011 Building Works Vol-1 10 MS 70-GG-CDC-010 August 17, 2011 Formworks Vol-1 11 MS 70-GG-CDC-011 August 17, 2011 Concrete Repair Vol-1 12 AS-DS-L-0113 MS 70-GG-CDC-011 October 23, 2011 Concrete Repair Deaerator Area Unit # 71 Wall 10/23/2011 Reply NCR no. 003, Attached MS no.70- GG-CDC-011 (Concrete Repair) No Photos Attached Vol-1 13 AS-DS-L-0116 MS 70-GG-CDC-011 October 25, 2011 Concrete Repair (Deaerator Wall) Deaerator Area Unit # 71 Wall 10/25/2011 Reply NCR no. 003, Attached MS no.70- GG-CDC-011 (Concrete Repair) No Photos Attached Vol-1 14 MS 70-GG-CDC-012 August 17, 2011 Mechanical Couplers Vol-1 15 AS-DF-T-0070 MS 70-GG-CDC-013 September 25, 2011 Concrete(Thin Section) 9/25/2011 Vol-1 16 AS-DF-T-0081 MS 70-GG-CDC-013 1 October 03, 2011 Concrete(Thin Section) 10/3/2011 Vol-1 17 AS-DF-T-0099 MS 70-GG-CDC-015 November 20, 2011 Excavation-Post Treatment Sedimentation Basin 11/20/2011 Vol-1 18 AS-DF-T-0096 MS 70-GG-CDC-016 November 15, 2011 (Erection of PS-Hollow Core Slabs) 11/15/2011 Vol-1 19 AS-DF-T-0097 MS 70-GG-CDC-017 November 15, 2011 (Erection of LLC Siporex Wall Panels) 11/15/2011 Vol-1 20 AS-DF-T-0109 MS 70-GG-CDC-018 November 26, 2011 Masonry Block Work-As Permanent Form Work 11/26/2011 Vol-1 21 AS-DF-T-0137 MS 70-GG-CDC-019 March 14, 2012 CMU-Block Masonry Works-Walls 3/14/2012 Vol-1 22 AS-DF-T-0149 MS 70-GG-CDC-020 April 16, 2012 Epoxy Paint on Exposed Concrete Surface 4/16/2012 Vol-1 23 AS-DF-T-0150 MS 70-GG-CDC-021 April 28, 2012 Plastering Works for Walls 4/28/2012 Vol-1 24 AS-DF-T-0166 MS 70-GG-CDC-022 May 20, 2012 Emulsion & Enamel Paint 5/20/2012 Vol-1 25 AS-DF-T-0178 MS 71-GG-CDC-023 June 03, 2012 Roof Waterproofing System 6/3/2012 Vol-1 26 AS-DF-T-0182 MS 71-GG-CDC-023 1 June 10, 2012 Roof Waterproofing System 6/10/2012 Vol-1 27 AS-DF-T-0194 MS 71-GG-CDC-024 July 22, 2012 Tiling Works for Floors & Walls 7/22/2012 Vol-1 RAS AL KHAIR DESALINATION PLANT PHASE 1 PACKAGE "D" METHOD OF STATEMENT REPORT DATE COVERED : AS OF JULY 26,2012 S.N. DOOSAN Name of Suppliers Place of Application/Location Date of Submit Description of Material Doosan Recd File Location ASC Transmittal no. Doosan Heavy Industries & Construction. Assad Said For Contracting Co.,Ltd. Page 40 of 75 ASSAD SAID Letter No. Submittal's MS Docu.Ref.No Rev Material Ref. No Reference No. Status ASC Recd Remarks 1 AS-DS-L-0032 MS 70-GG-CDC-001 June 08, 2011 Excavation Excavation Works for Evaporator Foundation 6/8/2011 DF-EH-D-0010/019 B 1/31/2012 Vol-1 2 AS-DS-L-0035 MS 70-GG-CDC-002 June 08, 2011 Blind Concrete Concreting Works (General) 6/8/2011 DF-EH-D-0011 B 1/31/2012 Vol-1 3 AS-DS-L-0034 MS 70-GG-CDC-003 June 08, 2011 Water Proofing Works Waterproofing Membrane & Protective Coatings 6/8/2011 DF-EH-D-0013/30 B 1/31/2012 Vol-1 4 AS-DS-T-0028 MS 70-GG-CDC-004 June 25, 2011 Concrete General A Vol-1 5 AS-DF-T-0032 MS 70-GG-CDC-005 June 25, 2011 Back Filling 6/8/2011 DF-EH-D-0016 B 1/31/2012 Vol-1 6 AS-DS-L-0036 MS 70-GG-CDC-006 June 08, 2011 Dewatering & Sheet Piling Works Dewatering & Sheet Piling Works 6/8/2011 DF-EH-D-0015 B 1/31/2012 Vol-1 7 MS 70-GG-CDC-007 June 25, 2011 Deep Excavation DF-EH-D-0014 B 1/31/2012 Vol-1 8 MS 70-GG-CDC-008 June 15, 2011 BRP/FDN Excavation 8/6/2011 DF-EH-D-0022 B 1/31/2012 Vol-1 9 MS 70-GG-CDC-009 June 27, 2011 Building Works Vol-1 10 MS 70-GG-CDC-010 August 17, 2011 Formworks Vol-1 11 MS 70-GG-CDC-011 August 17, 2011 Concrete Repair Vol-1 12 AS-DS-L-0113 MS 70-GG-CDC-011 October 23, 2011 Concrete Repair Deaerator Area Unit # 71 Wall 10/23/2011 Reply NCR no. 003, Attached MS no.70- GG-CDC-011 (Concrete Repair) No Photos Attached Vol-1 13 AS-DS-L-0116 MS 70-GG-CDC-011 October 25, 2011 Concrete Repair (Deaerator Wall) Deaerator Area Unit # 71 Wall 10/25/2011 Reply NCR no. 003, Attached MS no.70- GG-CDC-011 (Concrete Repair) No Photos Attached Vol-1 14 MS 70-GG-CDC-012 August 17, 2011 Mechanical Couplers Vol-1 15 AS-DF-T-0070 MS 70-GG-CDC-013 September 25, 2011 Concrete(Thin Section) 9/25/2011 Vol-1 16 AS-DF-T-0081 MS 70-GG-CDC-013 1 October 03, 2011 Concrete(Thin Section) 10/3/2011 Vol-1 17 AS-DF-T-0099 MS 70-GG-CDC-015 November 20, 2011 Excavation-Post Treatment Sedimentation Basin 11/20/2011 Vol-1 18 AS-DF-T-0096 MS 70-GG-CDC-016 November 15, 2011 (Erection of PS-Hollow Core Slabs) 11/15/2011 Vol-1 19 AS-DF-T-0097 MS 70-GG-CDC-017 November 15, 2011 (Erection of LLC Siporex Wall Panels) 11/15/2011 Vol-1 20 AS-DF-T-0109 MS 70-GG-CDC-018 November 26, 2011 Masonry Block Work-As Permanent Form Work 11/26/2011 Vol-1 21 AS-DF-T-0137 MS 70-GG-CDC-019 March 14, 2012 CMU-Block Masonry Works-Walls 3/14/2012 Vol-1 22 AS-DF-T-0149 MS 70-GG-CDC-020 April 16, 2012 Epoxy Paint on Exposed Concrete Surface 4/16/2012 Vol-1 23 AS-DF-T-0150 MS 70-GG-CDC-021 April 28, 2012 Plastering Works for Walls 4/28/2012 Vol-1 24 AS-DF-T-0166 MS 70-GG-CDC-022 May 20, 2012 Emulsion & Enamel Paint 5/20/2012 Vol-1 25 AS-DF-T-0178 MS 71-GG-CDC-023 June 03, 2012 Roof Waterproofing System 6/3/2012 Vol-1 26 AS-DF-T-0182 MS 71-GG-CDC-023 1 June 10, 2012 Roof Waterproofing System 6/10/2012 Vol-1 27 AS-DF-T-0194 MS 71-GG-CDC-024 July 22, 2012 Tiling Works for Floors & Walls 7/22/2012 Vol-1 RAS AL KHAIR DESALINATION PLANT PHASE 1 PACKAGE "D" METHOD OF STATEMENT REPORT DATE COVERED : AS OF JULY 26,2012 S.N. DOOSAN Name of Suppliers Place of Application/Location Date of Submit Description of Material Doosan Recd File Location ASC Transmittal no. Doosan Heavy Industries & Construction. Assad Said For Contracting Co.,Ltd. Page 41 of 75 ASSAD SAID Letter No. Submittal's MS Docu.Ref.No Rev Material Ref. No Reference No. Status ASC Recd Remarks 1 AS-DS-L-0032 MS 70-GG-CDC-001 June 08, 2011 Excavation Excavation Works for Evaporator Foundation 6/8/2011 DF-EH-D-0010/019 B 1/31/2012 Vol-1 2 AS-DS-L-0035 MS 70-GG-CDC-002 June 08, 2011 Blind Concrete Concreting Works (General) 6/8/2011 DF-EH-D-0011 B 1/31/2012 Vol-1 3 AS-DS-L-0034 MS 70-GG-CDC-003 June 08, 2011 Water Proofing Works Waterproofing Membrane & Protective Coatings 6/8/2011 DF-EH-D-0013/30 B 1/31/2012 Vol-1 4 AS-DS-T-0028 MS 70-GG-CDC-004 June 25, 2011 Concrete General A Vol-1 5 AS-DF-T-0032 MS 70-GG-CDC-005 June 25, 2011 Back Filling 6/8/2011 DF-EH-D-0016 B 1/31/2012 Vol-1 6 AS-DS-L-0036 MS 70-GG-CDC-006 June 08, 2011 Dewatering & Sheet Piling Works Dewatering & Sheet Piling Works 6/8/2011 DF-EH-D-0015 B 1/31/2012 Vol-1 7 MS 70-GG-CDC-007 June 25, 2011 Deep Excavation DF-EH-D-0014 B 1/31/2012 Vol-1 8 MS 70-GG-CDC-008 June 15, 2011 BRP/FDN Excavation 8/6/2011 DF-EH-D-0022 B 1/31/2012 Vol-1 9 MS 70-GG-CDC-009 June 27, 2011 Building Works Vol-1 10 MS 70-GG-CDC-010 August 17, 2011 Formworks Vol-1 11 MS 70-GG-CDC-011 August 17, 2011 Concrete Repair Vol-1 12 AS-DS-L-0113 MS 70-GG-CDC-011 October 23, 2011 Concrete Repair Deaerator Area Unit # 71 Wall 10/23/2011 Reply NCR no. 003, Attached MS no.70- GG-CDC-011 (Concrete Repair) No Photos Attached Vol-1 13 AS-DS-L-0116 MS 70-GG-CDC-011 October 25, 2011 Concrete Repair (Deaerator Wall) Deaerator Area Unit # 71 Wall 10/25/2011 Reply NCR no. 003, Attached MS no.70- GG-CDC-011 (Concrete Repair) No Photos Attached Vol-1 14 MS 70-GG-CDC-012 August 17, 2011 Mechanical Couplers Vol-1 15 AS-DF-T-0070 MS 70-GG-CDC-013 September 25, 2011 Concrete(Thin Section) 9/25/2011 Vol-1 16 AS-DF-T-0081 MS 70-GG-CDC-013 1 October 03, 2011 Concrete(Thin Section) 10/3/2011 Vol-1 17 AS-DF-T-0099 MS 70-GG-CDC-015 November 20, 2011 Excavation-Post Treatment Sedimentation Basin 11/20/2011 Vol-1 18 AS-DF-T-0096 MS 70-GG-CDC-016 November 15, 2011 (Erection of PS-Hollow Core Slabs) 11/15/2011 Vol-1 19 AS-DF-T-0097 MS 70-GG-CDC-017 November 15, 2011 (Erection of LLC Siporex Wall Panels) 11/15/2011 Vol-1 20 AS-DF-T-0109 MS 70-GG-CDC-018 November 26, 2011 Masonry Block Work-As Permanent Form Work 11/26/2011 Vol-1 21 AS-DF-T-0137 MS 70-GG-CDC-019 March 14, 2012 CMU-Block Masonry Works-Walls 3/14/2012 Vol-1 22 AS-DF-T-0149 MS 70-GG-CDC-020 April 16, 2012 Epoxy Paint on Exposed Concrete Surface 4/16/2012 Vol-1 23 AS-DF-T-0150 MS 70-GG-CDC-021 April 28, 2012 Plastering Works for Walls 4/28/2012 Vol-1 24 AS-DF-T-0166 MS 70-GG-CDC-022 May 20, 2012 Emulsion & Enamel Paint 5/20/2012 Vol-1 25 AS-DF-T-0178 MS 71-GG-CDC-023 June 03, 2012 Roof Waterproofing System 6/3/2012 Vol-1 26 AS-DF-T-0182 MS 71-GG-CDC-023 1 June 10, 2012 Roof Waterproofing System 6/10/2012 Vol-1 27 AS-DF-T-0194 MS 71-GG-CDC-024 July 22, 2012 Tiling Works for Floors & Walls 7/22/2012 Vol-1 RAS AL KHAIR DESALINATION PLANT PHASE 1 PACKAGE "D" METHOD OF STATEMENT REPORT DATE COVERED : AS OF JULY 26,2012 S.N. DOOSAN Name of Suppliers Place of Application/Location Date of Submit Description of Material Doosan Recd File Location ASC Transmittal no. Doosan Heavy Industries & Construction. Assad Said For Contracting Co.,Ltd. Page 42 of 75 ASSAD SAID Letter No. Submittal's MS Docu.Ref.No Rev Material Ref. No Reference No. Status ASC Recd Remarks 1 AS-DS-L-0032 MS 70-GG-CDC-001 June 08, 2011 Excavation Excavation Works for Evaporator Foundation 6/8/2011 DF-EH-D-0010/019 B 1/31/2012 Vol-1 2 AS-DS-L-0035 MS 70-GG-CDC-002 June 08, 2011 Blind Concrete Concreting Works (General) 6/8/2011 DF-EH-D-0011 B 1/31/2012 Vol-1 3 AS-DS-L-0034 MS 70-GG-CDC-003 June 08, 2011 Water Proofing Works Waterproofing Membrane & Protective Coatings 6/8/2011 DF-EH-D-0013/30 B 1/31/2012 Vol-1 4 AS-DS-T-0028 MS 70-GG-CDC-004 June 25, 2011 Concrete General A Vol-1 5 AS-DF-T-0032 MS 70-GG-CDC-005 June 25, 2011 Back Filling 6/8/2011 DF-EH-D-0016 B 1/31/2012 Vol-1 6 AS-DS-L-0036 MS 70-GG-CDC-006 June 08, 2011 Dewatering & Sheet Piling Works Dewatering & Sheet Piling Works 6/8/2011 DF-EH-D-0015 B 1/31/2012 Vol-1 7 MS 70-GG-CDC-007 June 25, 2011 Deep Excavation DF-EH-D-0014 B 1/31/2012 Vol-1 8 MS 70-GG-CDC-008 June 15, 2011 BRP/FDN Excavation 8/6/2011 DF-EH-D-0022 B 1/31/2012 Vol-1 9 MS 70-GG-CDC-009 June 27, 2011 Building Works Vol-1 10 MS 70-GG-CDC-010 August 17, 2011 Formworks Vol-1 11 MS 70-GG-CDC-011 August 17, 2011 Concrete Repair Vol-1 12 AS-DS-L-0113 MS 70-GG-CDC-011 October 23, 2011 Concrete Repair Deaerator Area Unit # 71 Wall 10/23/2011 Reply NCR no. 003, Attached MS no.70- GG-CDC-011 (Concrete Repair) No Photos Attached Vol-1 13 AS-DS-L-0116 MS 70-GG-CDC-011 October 25, 2011 Concrete Repair (Deaerator Wall) Deaerator Area Unit # 71 Wall 10/25/2011 Reply NCR no. 003, Attached MS no.70- GG-CDC-011 (Concrete Repair) No Photos Attached Vol-1 14 MS 70-GG-CDC-012 August 17, 2011 Mechanical Couplers Vol-1 15 AS-DF-T-0070 MS 70-GG-CDC-013 September 25, 2011 Concrete(Thin Section) 9/25/2011 Vol-1 16 AS-DF-T-0081 MS 70-GG-CDC-013 1 October 03, 2011 Concrete(Thin Section) 10/3/2011 Vol-1 17 AS-DF-T-0099 MS 70-GG-CDC-015 November 20, 2011 Excavation-Post Treatment Sedimentation Basin 11/20/2011 Vol-1 18 AS-DF-T-0096 MS 70-GG-CDC-016 November 15, 2011 (Erection of PS-Hollow Core Slabs) 11/15/2011 Vol-1 19 AS-DF-T-0097 MS 70-GG-CDC-017 November 15, 2011 (Erection of LLC Siporex Wall Panels) 11/15/2011 Vol-1 20 AS-DF-T-0109 MS 70-GG-CDC-018 November 26, 2011 Masonry Block Work-As Permanent Form Work 11/26/2011 Vol-1 21 AS-DF-T-0137 MS 70-GG-CDC-019 March 14, 2012 CMU-Block Masonry Works-Walls 3/14/2012 Vol-1 22 AS-DF-T-0149 MS 70-GG-CDC-020 April 16, 2012 Epoxy Paint on Exposed Concrete Surface 4/16/2012 Vol-1 23 AS-DF-T-0150 MS 70-GG-CDC-021 April 28, 2012 Plastering Works for Walls 4/28/2012 Vol-1 24 AS-DF-T-0166 MS 70-GG-CDC-022 May 20, 2012 Emulsion & Enamel Paint 5/20/2012 Vol-1 25 AS-DF-T-0178 MS 71-GG-CDC-023 June 03, 2012 Roof Waterproofing System 6/3/2012 Vol-1 26 AS-DF-T-0182 MS 71-GG-CDC-023 1 June 10, 2012 Roof Waterproofing System 6/10/2012 Vol-1 27 AS-DF-T-0194 MS 71-GG-CDC-024 July 22, 2012 Tiling Works for Floors & Walls 7/22/2012 Vol-1 RAS AL KHAIR DESALINATION PLANT PHASE 1 PACKAGE "D" METHOD OF STATEMENT REPORT DATE COVERED : AS OF JULY 26,2012 S.N. DOOSAN Name of Suppliers Place of Application/Location Date of Submit Description of Material Doosan Recd File Location ASC Transmittal no. Doosan Heavy Industries & Construction. Assad Said For Contracting Co.,Ltd. Page 43 of 75 ASSAD SAID Letter No. Submittal's MS Docu.Ref.No Rev Material Ref. No Reference No. Status ASC Recd Remarks 1 AS-DS-L-0032 MS 70-GG-CDC-001 June 08, 2011 Excavation Excavation Works for Evaporator Foundation 6/8/2011 DF-EH-D-0010/019 B 1/31/2012 Vol-1 2 AS-DS-L-0035 MS 70-GG-CDC-002 June 08, 2011 Blind Concrete Concreting Works (General) 6/8/2011 DF-EH-D-0011 B 1/31/2012 Vol-1 3 AS-DS-L-0034 MS 70-GG-CDC-003 June 08, 2011 Water Proofing Works Waterproofing Membrane & Protective Coatings 6/8/2011 DF-EH-D-0013/30 B 1/31/2012 Vol-1 4 AS-DS-T-0028 MS 70-GG-CDC-004 June 25, 2011 Concrete General A Vol-1 5 AS-DF-T-0032 MS 70-GG-CDC-005 June 25, 2011 Back Filling 6/8/2011 DF-EH-D-0016 B 1/31/2012 Vol-1 6 AS-DS-L-0036 MS 70-GG-CDC-006 June 08, 2011 Dewatering & Sheet Piling Works Dewatering & Sheet Piling Works 6/8/2011 DF-EH-D-0015 B 1/31/2012 Vol-1 7 MS 70-GG-CDC-007 June 25, 2011 Deep Excavation DF-EH-D-0014 B 1/31/2012 Vol-1 8 MS 70-GG-CDC-008 June 15, 2011 BRP/FDN Excavation 8/6/2011 DF-EH-D-0022 B 1/31/2012 Vol-1 9 MS 70-GG-CDC-009 June 27, 2011 Building Works Vol-1 10 MS 70-GG-CDC-010 August 17, 2011 Formworks Vol-1 11 MS 70-GG-CDC-011 August 17, 2011 Concrete Repair Vol-1 12 AS-DS-L-0113 MS 70-GG-CDC-011 October 23, 2011 Concrete Repair Deaerator Area Unit # 71 Wall 10/23/2011 Reply NCR no. 003, Attached MS no.70- GG-CDC-011 (Concrete Repair) No Photos Attached Vol-1 13 AS-DS-L-0116 MS 70-GG-CDC-011 October 25, 2011 Concrete Repair (Deaerator Wall) Deaerator Area Unit # 71 Wall 10/25/2011 Reply NCR no. 003, Attached MS no.70- GG-CDC-011 (Concrete Repair) No Photos Attached Vol-1 14 MS 70-GG-CDC-012 August 17, 2011 Mechanical Couplers Vol-1 15 AS-DF-T-0070 MS 70-GG-CDC-013 September 25, 2011 Concrete(Thin Section) 9/25/2011 Vol-1 16 AS-DF-T-0081 MS 70-GG-CDC-013 1 October 03, 2011 Concrete(Thin Section) 10/3/2011 Vol-1 17 AS-DF-T-0099 MS 70-GG-CDC-015 November 20, 2011 Excavation-Post Treatment Sedimentation Basin 11/20/2011 Vol-1 18 AS-DF-T-0096 MS 70-GG-CDC-016 November 15, 2011 (Erection of PS-Hollow Core Slabs) 11/15/2011 Vol-1 19 AS-DF-T-0097 MS 70-GG-CDC-017 November 15, 2011 (Erection of LLC Siporex Wall Panels) 11/15/2011 Vol-1 20 AS-DF-T-0109 MS 70-GG-CDC-018 November 26, 2011 Masonry Block Work-As Permanent Form Work 11/26/2011 Vol-1 21 AS-DF-T-0137 MS 70-GG-CDC-019 March 14, 2012 CMU-Block Masonry Works-Walls 3/14/2012 Vol-1 22 AS-DF-T-0149 MS 70-GG-CDC-020 April 16, 2012 Epoxy Paint on Exposed Concrete Surface 4/16/2012 Vol-1 23 AS-DF-T-0150 MS 70-GG-CDC-021 April 28, 2012 Plastering Works for Walls 4/28/2012 Vol-1 24 AS-DF-T-0166 MS 70-GG-CDC-022 May 20, 2012 Emulsion & Enamel Paint 5/20/2012 Vol-1 25 AS-DF-T-0178 MS 71-GG-CDC-023 June 03, 2012 Roof Waterproofing System 6/3/2012 Vol-1 26 AS-DF-T-0182 MS 71-GG-CDC-023 1 June 10, 2012 Roof Waterproofing System 6/10/2012 Vol-1 27 AS-DF-T-0194 MS 71-GG-CDC-024 July 22, 2012 Tiling Works for Floors & Walls 7/22/2012 Vol-1 RAS AL KHAIR DESALINATION PLANT PHASE 1 PACKAGE "D" METHOD OF STATEMENT REPORT DATE COVERED : AS OF JULY 26,2012 S.N. DOOSAN Name of Suppliers Place of Application/Location Date of Submit Description of Material Doosan Recd File Location ASC Transmittal no. Doosan Heavy Industries & Construction. Assad Said For Contracting Co.,Ltd. Page 44 of 75 ASSAD SAID Letter No. Submittal's MS Docu.Ref.No Rev Material Ref. No Reference No. Status ASC Recd Remarks 1 AS-DS-L-0032 MS 70-GG-CDC-001 June 08, 2011 Excavation Excavation Works for Evaporator Foundation 6/8/2011 DF-EH-D-0010/019 B 1/31/2012 Vol-1 2 AS-DS-L-0035 MS 70-GG-CDC-002 June 08, 2011 Blind Concrete Concreting Works (General) 6/8/2011 DF-EH-D-0011 B 1/31/2012 Vol-1 3 AS-DS-L-0034 MS 70-GG-CDC-003 June 08, 2011 Water Proofing Works Waterproofing Membrane & Protective Coatings 6/8/2011 DF-EH-D-0013/30 B 1/31/2012 Vol-1 4 AS-DS-T-0028 MS 70-GG-CDC-004 June 25, 2011 Concrete General A Vol-1 5 AS-DF-T-0032 MS 70-GG-CDC-005 June 25, 2011 Back Filling 6/8/2011 DF-EH-D-0016 B 1/31/2012 Vol-1 6 AS-DS-L-0036 MS 70-GG-CDC-006 June 08, 2011 Dewatering & Sheet Piling Works Dewatering & Sheet Piling Works 6/8/2011 DF-EH-D-0015 B 1/31/2012 Vol-1 7 MS 70-GG-CDC-007 June 25, 2011 Deep Excavation DF-EH-D-0014 B 1/31/2012 Vol-1 8 MS 70-GG-CDC-008 June 15, 2011 BRP/FDN Excavation 8/6/2011 DF-EH-D-0022 B 1/31/2012 Vol-1 9 MS 70-GG-CDC-009 June 27, 2011 Building Works Vol-1 10 MS 70-GG-CDC-010 August 17, 2011 Formworks Vol-1 11 MS 70-GG-CDC-011 August 17, 2011 Concrete Repair Vol-1 12 AS-DS-L-0113 MS 70-GG-CDC-011 October 23, 2011 Concrete Repair Deaerator Area Unit # 71 Wall 10/23/2011 Reply NCR no. 003, Attached MS no.70- GG-CDC-011 (Concrete Repair) No Photos Attached Vol-1 13 AS-DS-L-0116 MS 70-GG-CDC-011 October 25, 2011 Concrete Repair (Deaerator Wall) Deaerator Area Unit # 71 Wall 10/25/2011 Reply NCR no. 003, Attached MS no.70- GG-CDC-011 (Concrete Repair) No Photos Attached Vol-1 14 MS 70-GG-CDC-012 August 17, 2011 Mechanical Couplers Vol-1 15 AS-DF-T-0070 MS 70-GG-CDC-013 September 25, 2011 Concrete(Thin Section) 9/25/2011 Vol-1 16 AS-DF-T-0081 MS 70-GG-CDC-013 1 October 03, 2011 Concrete(Thin Section) 10/3/2011 Vol-1 17 AS-DF-T-0099 MS 70-GG-CDC-015 November 20, 2011 Excavation-Post Treatment Sedimentation Basin 11/20/2011 Vol-1 18 AS-DF-T-0096 MS 70-GG-CDC-016 November 15, 2011 (Erection of PS-Hollow Core Slabs) 11/15/2011 Vol-1 19 AS-DF-T-0097 MS 70-GG-CDC-017 November 15, 2011 (Erection of LLC Siporex Wall Panels) 11/15/2011 Vol-1 20 AS-DF-T-0109 MS 70-GG-CDC-018 November 26, 2011 Masonry Block Work-As Permanent Form Work 11/26/2011 Vol-1 21 AS-DF-T-0137 MS 70-GG-CDC-019 March 14, 2012 CMU-Block Masonry Works-Walls 3/14/2012 Vol-1 22 AS-DF-T-0149 MS 70-GG-CDC-020 April 16, 2012 Epoxy Paint on Exposed Concrete Surface 4/16/2012 Vol-1 23 AS-DF-T-0150 MS 70-GG-CDC-021 April 28, 2012 Plastering Works for Walls 4/28/2012 Vol-1 24 AS-DF-T-0166 MS 70-GG-CDC-022 May 20, 2012 Emulsion & Enamel Paint 5/20/2012 Vol-1 25 AS-DF-T-0178 MS 71-GG-CDC-023 June 03, 2012 Roof Waterproofing System 6/3/2012 Vol-1 26 AS-DF-T-0182 MS 71-GG-CDC-023 1 June 10, 2012 Roof Waterproofing System 6/10/2012 Vol-1 27 AS-DF-T-0194 MS 71-GG-CDC-024 July 22, 2012 Tiling Works for Floors & Walls 7/22/2012 Vol-1 RAS AL KHAIR DESALINATION PLANT PHASE 1 PACKAGE "D" METHOD OF STATEMENT REPORT DATE COVERED : AS OF JULY 26,2012 S.N. DOOSAN Name of Suppliers Place of Application/Location Date of Submit Description of Material Doosan Recd File Location ASC Transmittal no. Doosan Heavy Industries & Construction. Assad Said For Contracting Co.,Ltd. Page 45 of 75 ASSAD SAID Letter No. Submittal's MS Docu.Ref.No Rev Material Ref. No Reference No. Status ASC Recd Remarks 1 AS-DS-L-0032 MS 70-GG-CDC-001 June 08, 2011 Excavation Excavation Works for Evaporator Foundation 6/8/2011 DF-EH-D-0010/019 B 1/31/2012 Vol-1 2 AS-DS-L-0035 MS 70-GG-CDC-002 June 08, 2011 Blind Concrete Concreting Works (General) 6/8/2011 DF-EH-D-0011 B 1/31/2012 Vol-1 3 AS-DS-L-0034 MS 70-GG-CDC-003 June 08, 2011 Water Proofing Works Waterproofing Membrane & Protective Coatings 6/8/2011 DF-EH-D-0013/30 B 1/31/2012 Vol-1 4 AS-DS-T-0028 MS 70-GG-CDC-004 June 25, 2011 Concrete General A Vol-1 5 AS-DF-T-0032 MS 70-GG-CDC-005 June 25, 2011 Back Filling 6/8/2011 DF-EH-D-0016 B 1/31/2012 Vol-1 6 AS-DS-L-0036 MS 70-GG-CDC-006 June 08, 2011 Dewatering & Sheet Piling Works Dewatering & Sheet Piling Works 6/8/2011 DF-EH-D-0015 B 1/31/2012 Vol-1 7 MS 70-GG-CDC-007 June 25, 2011 Deep Excavation DF-EH-D-0014 B 1/31/2012 Vol-1 8 MS 70-GG-CDC-008 June 15, 2011 BRP/FDN Excavation 8/6/2011 DF-EH-D-0022 B 1/31/2012 Vol-1 9 MS 70-GG-CDC-009 June 27, 2011 Building Works Vol-1 10 MS 70-GG-CDC-010 August 17, 2011 Formworks Vol-1 11 MS 70-GG-CDC-011 August 17, 2011 Concrete Repair Vol-1 12 AS-DS-L-0113 MS 70-GG-CDC-011 October 23, 2011 Concrete Repair Deaerator Area Unit # 71 Wall 10/23/2011 Reply NCR no. 003, Attached MS no.70- GG-CDC-011 (Concrete Repair) No Photos Attached Vol-1 13 AS-DS-L-0116 MS 70-GG-CDC-011 October 25, 2011 Concrete Repair (Deaerator Wall) Deaerator Area Unit # 71 Wall 10/25/2011 Reply NCR no. 003, Attached MS no.70- GG-CDC-011 (Concrete Repair) No Photos Attached Vol-1 14 MS 70-GG-CDC-012 August 17, 2011 Mechanical Couplers Vol-1 15 AS-DF-T-0070 MS 70-GG-CDC-013 September 25, 2011 Concrete(Thin Section) 9/25/2011 Vol-1 16 AS-DF-T-0081 MS 70-GG-CDC-013 1 October 03, 2011 Concrete(Thin Section) 10/3/2011 Vol-1 17 AS-DF-T-0099 MS 70-GG-CDC-015 November 20, 2011 Excavation-Post Treatment Sedimentation Basin 11/20/2011 Vol-1 18 AS-DF-T-0096 MS 70-GG-CDC-016 November 15, 2011 (Erection of PS-Hollow Core Slabs) 11/15/2011 Vol-1 19 AS-DF-T-0097 MS 70-GG-CDC-017 November 15, 2011 (Erection of LLC Siporex Wall Panels) 11/15/2011 Vol-1 20 AS-DF-T-0109 MS 70-GG-CDC-018 November 26, 2011 Masonry Block Work-As Permanent Form Work 11/26/2011 Vol-1 21 AS-DF-T-0137 MS 70-GG-CDC-019 March 14, 2012 CMU-Block Masonry Works-Walls 3/14/2012 Vol-1 22 AS-DF-T-0149 MS 70-GG-CDC-020 April 16, 2012 Epoxy Paint on Exposed Concrete Surface 4/16/2012 Vol-1 23 AS-DF-T-0150 MS 70-GG-CDC-021 April 28, 2012 Plastering Works for Walls 4/28/2012 Vol-1 24 AS-DF-T-0166 MS 70-GG-CDC-022 May 20, 2012 Emulsion & Enamel Paint 5/20/2012 Vol-1 25 AS-DF-T-0178 MS 71-GG-CDC-023 June 03, 2012 Roof Waterproofing System 6/3/2012 Vol-1 26 AS-DF-T-0182 MS 71-GG-CDC-023 1 June 10, 2012 Roof Waterproofing System 6/10/2012 Vol-1 27 AS-DF-T-0194 MS 71-GG-CDC-024 July 22, 2012 Tiling Works for Floors & Walls 7/22/2012 Vol-1 RAS AL KHAIR DESALINATION PLANT PHASE 1 PACKAGE "D" METHOD OF STATEMENT REPORT DATE COVERED : AS OF JULY 26,2012 S.N. DOOSAN Name of Suppliers Place of Application/Location Date of Submit Description of Material Doosan Recd File Location ASC Transmittal no. Doosan Heavy Industries & Construction. Assad Said For Contracting Co.,Ltd. Page 46 of 75 Letter No. Material no. Submittal's Rev. Material Ref. No Reference No. Status ASC Recd Remarks 1 AS-DS-L-0004 DS-C-0001 MT 5/9/2011 Potable Water for Concrete Concrete & Reinforcement Assad Said Contracting co. Ltd Saudi 9/May/11 DF-EF-L-0001 A 9/May/11 2 AS-DS-L-0002 DS-C-0002 MT 4/27/2011 3-8 Coarse Aggregates of Concrete Concrete & Reinforcement Assad Said Contracting co. Ltd Saudi 27/Apr/11 DF-EF-L-0002 A 9/May/11 3 AS-DS-L-0001 DS-C-0003 MT 5/9/2011 Sand for Concrete Concrete & Reinforcement Assad Said Contracting co. Ltd Saudi 9/May/11 DF-EF-L-0003 A 9/May/11 4 AS-DS-L-0003 DS-C-0004 MT 5/9/2011 3-4 Coarse Aggregates of Concrete Concrete & Reinforcement Assad Said Contracting co. Ltd Saudi 9/May/11 DF-EF-L-0004 A 9/May/11 5 AS-DS-L-0010 MT 5/9/2011 Form Works System Concrete & Reinforcement Assad Said Contracting co. Ltd Saudi 9/May/11 DF-EF-L-0006 A 9/May/11 6 AS-DS-L-0012 5/8/2011 Formworks Accessories Saudi Alamar Trading & Industries Co. 8/May/11 7 AS-DF-T-0018 DS-C-0011 MT 5/9/2011 REBOOL- Chemical Mould Release Agent For All Formworks of The Project FOSAM Co. Ltd.P.O.11081 Jeddah 21453 9/May/11 DF-EH-L-0013 A 4/Oct/11 Vol-2 8 AS-DS-L-0014 MT x 5/9/2011 Water Proofing Membrane & Primer Waterproofing tanking system of underground structure &inverted roof Gulf Seal P.O.Box.231573 Riyadh 11321 KSA 28/May/11 Vol-2 9 AS-DF-T-0030 DF-EH-L-0017 DS-C-0020 MT x 6/8/2011 Alyaf A351- Geotextile 250 g/m2 Separation Layar Chipping Area & BRP Pit, DP & BBDP Pit ISAM KABBANI & Partner for Building & Const Material Co.P.O.6897 Damman KSA 8/Jun/11 DS-C-0020 DF-EH-L-0017 A 14/Sep/11 Vol-2 10 AS-DS-L-0023 MT 5/13/2011 CONPLAST RP264 - Retarding Water Reducing admixtures. CONPLAST SP 432 MS - High Performance Admixture for Microsilica Concrete. As Concrete Additives FOSAM Co. Ltd.P.O.11081 Jeddah 21453 11 AS-DF-T-0020 DS-C-0000 MT x 5/31/2011 1.Polyethylene Sheet (100 Microns to 300 Microns)2.Block Work Accessories 3. Filler Board & 4.Expanded Matal For all Underlean Concrete,Masonry Works, for Expansion Joint & Walls in Contact with Soil or Substructure & Plastering Works Mazen M.Al-Saeed Building Material Co.Ltd P.O.Box 79619,Al-Khobar 31952 31/May/11 DS-C-0014 DF-EF-L-0016 A 25/Sep/11 Vol-5 12 AS-DF-T-0068 AS-DS-L-82 DS-C-0016 MT 001 x 2 9/25/2011 Supercast PVC Waterstop Range (200mm wide for wall Thicking upto 300mm & PVC water 300mm wide for For Expansion & Construction Joint in all Structural Underground Concrete works & kicker where it is required Saudi BASF for Building Material co.Ltd. P.O.Box.1884 Al-Khobar-31952 KSA 25/Sep/11 DS-C-0043 DF-EH-L-0053 B 18/Oct/11 Vol-1 13 AS-DF-T-0069 AS-DS-L-83 DS-C-0009 MT 001 x 1 9/26/2011 Filler Board Bitu Impregnated 20mm think For Expansion & Construction Joint in all Structural Underground Concrete works ISAM KABBANI & Partner for Building & Const Material Co.P.O.6897 Damman KSA 26/Sep/11 DS-C-0044 DF-EH-L-0054 B 18/Oct/11 Vol-1 14 AS-DF-T-0074 AS-DS-L-89 DS-C-0019 MT X 2 10/1/2011 Masterflow 524L Non Shrink Cementitions Grout Anchor BOLT Rod,Column to Column, Column Basses, Rail Post to Slab & Heavy Equipment Machinary Bases Saudi BASF for Building Material co.Ltd. P.O.Box.1884 Al-Khobar-31952 KSA 1/Oct/11 DS-C-0058 DF-EH-L-0081 A 1/Feb/12 No Comment Vol-1 15 AS-DF-T-0072 AS-DS-L-0087 DS-C-0017 MT X 1 9/29/2011 Couplers /Splicing System Splicing of Reinforcement Bar Technical Factory of Steel Works Co.Ltd P.o Box.16464 Jeddah 21464 3/Oct/11 DS-C-0048 DF-EH-L-0060 C 1/Feb/12 Vol-1 16 AS-DF-T-0075 AS-DS-L-0090 DS-C-0020 MT x 10/1/2011 THIOFLEX 600 Gun Grade for Sealing Expansion & Contraction Joint For Sealing Expansion & Contraction Joint FOSAM Co. Ltd.P.O.11081 Jeddah 21453 1/Oct/11 DS-C-0046 B 18/Oct/11 Vol-1 17 AS-DF-T-0076 AS-DS-L-0091 DS-C-0021 MT x 10/1/2011 Bitumat Bituprotect (4mm) Bituminous Protection Board To be used as Protection Board for all substructure in the whole Project. BITUMAT Co.Ltd P.O BOX 7487 Dammam 31462 1/Oct/11 DS-C-0047 DF-EH-L-0058 A 18/Oct/11 Vol-1 18 AS-DF-T-0079 AS-DS-L-0094 DS-C-0009 MT 001 x 2 10/3/2011 Protection Board 20mm To be used as Protection Board for all substructure in the whole Project. ISAM KABBANI & Partner for Building & Const Material Co.P.O.6897 Damman KSA 3/Oct/11 DS-C-0049 DF-EH-L-0061 B 15/Nov/11 Vol-1 19 AS-DF-T-0009 MT 5/25/2011 Renderoc TG- Single Component Medium Weight Concrete & Masonry Reinstatement Mortar use in Hot Climates,Renderoc FC-Single Component polymer Modified Cementitious Fairing Coat & Nitobond AR-Acrylic Emulsion If Required for Concrete Repair in the Whole Project FOSAM Co. Ltd.P.O.11081 Jeddah 21453 25/May/11 DS-C-003 B 15/Nov/11 Vol-2 20 DS-C-0000 MT 5/28/2011 fine aggregate For All Under Lean Concrete ISAM KABBANI & Partner for Building & Const Material Co.P.O.6897 Damman KSA 28/May/11 DS-C-0010 DF-EH-L-0012 B 21 AS-DS-L-0020 DS-C-0000 MT 5/11/2011 STC- Specialist Trading Corporation for Polyethylene Film Assad Said Contracting co. Ltd Saudi 11/May/11 DS-C-0015 DF-EH-L-0015 A 12/May/11 22 AS-DF-T-0017 AS-DS-L-0024 DS-S-0000 MT 5/30/2011 Supercast PVC Waterstop Range Centrally & Externally Placed PVC Waterstop For All Underground Concrete, Concrete Expansion Joints and Kicker Where It Is Required FOSAM Co. Ltd.P.O.11081 Jeddah 21453 30/May/11 DS-C-0012 DF-EH-L-0014 B 1/Oct/11 Vol-2 23 AS-DS-L-0018 MT 5/9/2011 Polyethylene Sheet (100 Microns to 300 Microns) Which Will be Used Under the Building Concrete of Foundation For All Under Lean Concrete Mazen M.Al-Saeed Building Material Co.Ltd P.O.Box 79619,Al-Khobar 31952 9/May/11 DS-C-0014 DF-EH-L-0016 B 24 AS-DF-T0022 MT 6/1/2011 Microsilica to be Added to Ready Mix Concrete (for Batching Plant) Ready Mix Concrete for the Whole Project Specialist Trading Corp. P.O.Box 325027, Riyadh 11371 1/Jun/11 DS-C-0015 DF-EH-L-0018 B 14/Sep/11 Vol-2 No.of Sample File Location Sample Doosan Recd RAS AL KHAIR DESALINATION PLANT PHASE 1 PACKAGE "D" MATERIAL SUBMITTAL STATUS REPORT DATE COVERED : As of 25 August ,2012 S.N. DOOSAN Name of Suppliers Place of Application / Location ASSAD SAID ASC Transmittal no. Date of Submit Description of Material Doosan Heavy Industries & Construction. Assad Said For Contracting Co.,Ltd. Page 47 of 75 No.of Sample File Location Sample Doosan Recd RAS AL KHAIR DESALINATION PLANT PHASE 1 PACKAGE "D" MATERIAL SUBMITTAL STATUS REPORT DATE COVERED : As of 25 August ,2012 S.N. DOOSAN Name of Suppliers Place of Application / Location ASSAD SAID ASC Transmittal no. Date of Submit Description of Material Doosan Heavy Industries & Construction. Assad Said For Contracting Co.,Ltd. 25 AS-DF-T0006 AS-DS-L-0009 DS-C-0000 MT 5/8/2011 FBEC (Coated Reinforcing steel Bars) For All Reinforced Concrete in theWhole Project Al Faisal Steel Product Company P.Obox 2705, Dammam 31461 8/May/11 DS-C-0004 DF-EH-L-0006 A 14/Sep/11 Vol-2&3 26 AS-DF-T0019 DS-C-0000 MT 5/15/2011 Ordinary Portland Cement (Type-1) & Sulphate Resisting Portland Cement For All Concrete Reinforced Concrete, Mortar,Grout & Plaster Works Eastern Province Cement Co. P.O.Box.4536 Dammam 31412 15/May/11 DS-C-0013 DF-EH-L-0015/0084 A 3/Dec/11 Vol-2&3 27 AS-DF-T0015 DS-C-0009 MT 5/28/2011 Filler Board / Protection Board For Expansion Joint & Wall In Contact With Soils Or Substructure ISAM KABBANI & Partner for Building & Const Material Co.P.O.6897 Damman KSA 28/May/11 DS-C-0009 DF-EH-L-0011 C 4/Oct/11 Vol-4 28 AS-DF-T0021 DS-C-0000 MT 6/1/2011 Supercast PVC Waterstop Range Centrally & Externally Placed PVC Waterstop For All Underground Concrete, Concrete Expansion Joints and Kicker Where It Is Required Saudi BASF for Building Material co.Ltd. P.O.Box.1884 Al-Khobar-31952 KSA 1/Jun/11 DS-C-0016 DF-EH-L-0019 C 14/Sep/11 Vol-3 29 AS-DF-T0010 MT 5/25/2011 Protection Board For Expansion Joint & Wall In Contact With Soils Or Substructure Specialist Trading Corp. P.O.Box 325027, Riyadh 11371 25/May/11 DS-C-0002 DF-EH-L-0004 C 4/Oct/11 30 AS-DF-T-0033 AS-DS-L-0039 DS-C-000 MT x 6/22/2009 SC1 Crushed Stone To be used for GRP Pipe Backfinning Material Mohd.Nassir Al Hajry Sons P.o.Box.881 Al- Khobar 31952 22/Jun/09 DS-C-0022 DF-EH-L-0023 A 29/Nov/11 Vol-1 31 AS-DF-T-0034 AS-DS-L-0042 DS-C-000 MT x 6/30/2009 Resubmitted after change the date To be Used for Epoxy Coated Rebars Specialist Trading Corp. P.O.Box 325027, Riyadh 11371 30/Jun/11 DS-C-0022 DF-EH-L-0023 A 11/Oct/11 Vol-1 32 AS-DF-T-0035 AS-DS-L-0045 DS-C-0000 MT 7/13/2011 BITUSEAL 1000 & 1200 Self Adhesive Reinforced Membranes For Waterproofing Tanking System of Underground Structure BITUMAT Co.Ltd P.O BOX 7487 Dammam 31462 13/Jul/11 DS-C-0026 DF-EH-L-0030 C 9/Oct/11 Vol-1 33 AS-DF-T-0036 AS-DC-L-0045 DS-C-0000 MT 7/11/2011 Bitustick XL- Cross Laminated Self Adhesive Waterproofing Membrane For Waterproofing Tanking System of Underground Structure Henkel Polybit Industries Ltd P.O.Box.2230 Al-Khobar 31952 11/Jul/11 Vol-1 34 AS-DF-T-0039 AS-DS-L-0054 DS-C-0032 MT x 7/28/2011 Round Bar 20mm dia. With PVC Pipe 25mm dia. & Cap To be Used as Dowel Bar at Expansion Joint Approved Direct Line Trading P.O.Box.6729 Dhahran 31311 30/Jul/11 Vol-1 35 AS-DF-T-0040 AS-DS-L-0055 DS-C-0033 MT x 7/28/2011 Concure WB309 Water Based Concrete Curing Compound To be Used for As Curing Compound for All Concrete Structure FOSAM Co. Ltd.P.O.11081 Jeddah 21453 28/Jul/11 DS-C-0031 DF-EH-L-0035 B 11/Oct/11 Vol-1 36 AS-DS-L-0055 DS-C-0000 MT 7/30/2011 Concrete Mix Design for PS: Grade A- Type 1 Cement (50Mpa) For all Structural Concrete Works Assad Said Contracting co, Ltd Saudi 30/Jul/11 vol-4 37 AS-DF-T-0041 AS-DS-L-0056 DS-C-0034 MT x 7/28/2011 Concure A Multipurpose, Pliolite Resin, Curing Compound For Curing of All Concrete Structure FOSAM Co. Ltd.P.O.11081 Jeddah 21453 28/Jul/11 DS-C-0030 DF-EH-L-0034 A 11/Oct/11 Vol-1 38 AS-DS-L-0056 7/31/2011 SC1 Material Test Results 31/Jul/11 Attached Reports 39 AS-DS-L-0056A 001 8/1/2011 SC1 Material Test Results 3/Aug/11 Attached Reports 40 AS-DF-T-0045 AS-DS-L-0061 DS-C-0036 MT x 8/21/2011 Esscofoam 35- Thermal Insulation Board For Thermal Insulation Roof Gulf Insulating Material Manufacturing & Trading Co, P.O.Box.1306 Al-Farwaniah 80000 Kuwait 21/Aug/11 DS-C-0033 DF-EH-L-0038 C 11/Oct/11 Issued by Doosan Vol-1 41 AS-DF-T-0046 AS-DS-L-0062 DS-C-0027 MT x 8/21/2011 Rheofinish 202 Chemical Mould Release Agent For All Formworks of The Project Saudi BASF for Building Material co.Ltd. P.O.Box.1884 Al-Khobar-31952 KSA 21/Aug/11 DS-C-0034 DF-EH-L-0039 B 11/Oct/11 Vol-1 42 AS-DS-L-0067 DS-C-0037 MT 9/4/2011 Concrete (Class-C40) Spacer Block To Be Used for as Reinforcement Support for All Structural Concrete Assad Said Contracting co. Ltd Saudi 4/Sep/11 DS-C-0036 DF-EH-L-0041 A 11/Oct/11 43 AS-DF-T-0064 AS-DS-L-0074 DS-C-0000 MT x 9/14/2011 UPVC Pipe Dia. 100mm, 200mm,300mm,400mm,500mm& 600mm For Building Pipe Sleeves, Drainage & Sewage Pipe Line for Evaporator Remain Plant Area Fabco Plastic Factory Co. P.O box 150 Dammam 31411 14/Sep/11 DS-C-0039 DF-EH-L-0045 A 29/Nov/11 Vol-1 44 AS-DS-L-0077 9/17/2011 Select Fill Test Results 17/Sep/11 Attached Reports 45 AS-DS-L-0080 9/19/2011 Ordinary Fill Test Results 19/Sep/11 Attached Reports 46 AS-DF-T-0067 AS-DS-L-0081 DS-C-0028 MT x 9/19/2011 Chipping Gravel (25mm) Uniform Gauge To be Used for Backfilling of Evaporator Mohd.Nassir Al Hajry Sons P.o.Box.881 Al- Khobar 31952 19/Sep/11 DS-C-0042 DF-EH-L-0052 A 7/May/12 Vol-1 47 DF-EH-L-0032 DS-C-0028 MT x 7/17/2011 Bitumat Bituprotect - Indentation & Impact Resistant Board for Water proofing Membrane To be Used for Protection Board for all Substructure in the Whole project BITUMAT Co.Ltd P.O BOX 7487 Dammam 31462 20/Jul/11 DS-C-0028 DF-EH-L-0032 B 11/Oct/11 Vol-3 48 DF-EH-L-0033 DS-C-0029 MT x 7/19/2011 Bitumat Bitutherm- Extruded Polystyrene Thermal Insulation Boards For Termal Insulation for Roof BITUMAT Co.Ltd P.O BOX 7487 Dammam 31462 20/Jul/11 Vol-3 49 DF-EH-L-0034 DS-C-0030 MT x 7/19/2011 Polyflame-Torch Welded APP (Atactic Polypropylene) Modified Bitumen Membranes For Retaining Walls 150mm Above Ground Level & Roof Water Proofing System BITUMAT Co.Ltd P.O BOX 7487 Dammam 31462 20/Jul/11 DS-C-0029 DF-EH-L0033 C 11/Oct/11 Vol-5 50 AS-DF-T-0039 DF-EH-L-0035 DS-C-0031 MT x 7/20/2011 Masterflex 610-Water Swelling Waterbar for Joints For Construction Joints & Where it is Required Saudi BASF for Building Material co.Ltd. P.O.Box.1884 Al-Khobar-31952 KSA 20/Jul/11 DS-C-0018 DF-EH-L-0064 A 15/Nov/11 Vol-3 51 AS-DF-T-0080 AS-DS-L-0100 DS-C-000 MT 001 x 1 10/9/2011 Bituseal 1200 -Self Adhesive Reinforced Membrane For Waterproofing Tanking System of Underground Structure BITUMAT Co.Ltd P.O BOX 7487 Dammam 31462 9/Oct/11 DS-C-0050 DF-EF-L-0063 B 1/Feb/12 52 AS-DF-T-0071 AS-DS-L-0085 MT 10/10/2011 Chequered Plates/Steel Grating Pre-Qualification TEMCO Technical Works Industries Co.Ltd 53 AS-DF-T-0023 MT x 6/2/2011 Masterflex 700- Polysulphide Elastomeric Joint Sealant For Expansion Construction and Isolation Joint Saudi BASF for Building Material co.Ltd. P.O.Box.1884 Al-Khobar-31952 KSA 2/Jun/11 DS-C-0018 DF-EH-L-0021 C 11/Oct/11 Vol-3 54 AS-DF-T-0008 AS-DS-L-0012 DS-C-0000 MT 5/8/2011 PVC Chamfer, PVC Cone & PVC Pipe For formwork for entrie project Saudi Alamar Trading & Industries Co. P.O.Box.17, Dammam 31411 8/May/11 DS-C-0001 DF-EH-L-0003 B 11/Oct/11 Vol-2 Page 48 of 75 No.of Sample File Location Sample Doosan Recd RAS AL KHAIR DESALINATION PLANT PHASE 1 PACKAGE "D" MATERIAL SUBMITTAL STATUS REPORT DATE COVERED : As of 25 August ,2012 S.N. DOOSAN Name of Suppliers Place of Application / Location ASSAD SAID ASC Transmittal no. Date of Submit Description of Material Doosan Heavy Industries & Construction. Assad Said For Contracting Co.,Ltd. 55 MT sand for Concrete Concrete Works FESIL AS P.O.Box.1824 Lade 7440 Trondhelm Norway DS-C-0027 DF-EH-L-0031 B 11/Oct/11 56 MT Potable Water for Concrete Concrete Al-Bayader Group P.O.Box.11966 Al-Jubail 31961 DS-C-0038 DF-EH-L-0044 A 11/Oct/11 57 MT Aggergates for Concrete production Concrete Works Mohd.Nassir Al Hajry Sons P.o.Box.881 Al- Khobar 31952 DS-C-0032 DF-EH-L-0036 B 11/Oct/11 58 MT Bedding and Backfill Material for GRP Pipe Installation GRP Pipe Layingbi Mohd.Nassir Al Hajry Sons P.o.Box.881 Al- Khobar 31952 DF-EH-L-0040 B 11/Oct/11 59 AS-DF-T-0013 AS-DS-L-0016 DS-C-0030 MT 5/29/2011 1) Polyflame-APP Modified Bitumen Waterproofing Membrane with non- Woven Polyester re-Inforcement 2) Concrete Primer-Bituminious Primer For waterproofing Tanking System of Underground Structure & Invented roof BITUMAT Co.Ltd P.O BOX 7487 Dammam 31462 29/May/11 DS-C-0008 DF-EH-L-0010 B 11/Oct/11 Vol-3 60 AS-DF-T-0031 AS-DS-L-0031 DS-C-0020 MT x 5/23/2011 Concrete Mix Design for 20N/mm2 ( Grade/Class C20) @28 days on Cube & 40 N/mm2 (Grade/Class C40) @28 Days on Cube If Required for Concrete Repair in the Whole Project Saudi Readymix Conc31839 Al-Khobar 31952 23/May/11 DS-C-0019 DF-EH-L-0025 C 11/Oct/11 Vol-2 61 AS-DF-T-0032 AS-DS-L-0038 DS-C-0000 MT 6/13/2011 Concrete Mix Design for 20N/mm2 ( Grade/Class C20) @28 days on Cube & 40 N/mm2 (Grade/Class C40) @28 Days on Cube If Required for Concrete Repair in the Whole Project Assad Said Contracting co, Ltd Saudi 13/Jun/11 DS-C-0002 DF-EH-L-0022 B 11/Oct/11 Vol-2 62 AS-DF-T-0011 AS-DS-L-0014 DS-C-0000 MT x 5/28/2011 GS Plasto 4F Waterproofing Memebrane & GS Primer For Waterproofing Tanking System of Underground Structure and Inverted Roof Gulf Seal P.O.Box.231573 Riyadh 11321 KSA 28/May/11 DS-C-0006 DF-EH-L-0008 B 11/Oct/11 Vol-2 63 AS-DF-T-0016 5/29/2011 Polyethylene Sheet (100 Microns to 300 Microns) Which Will be Used Under the Building Concrete of Foundation For All Under Lean Concrete Specialist Trading Corp. P.O.Box 325027, Riyadh 11371 DS-C-0007 DF-EH-L-0009 A 11/Oct/11 64 Select Fill & Material Fill from +2.10m savd up to +2.10m savd up to +310m savd at ro Site Filling from +2.10m savd up to +310m savd to ro Mofarreh 4028 m. Al-Harbi Est. P.O.Box. 4028 Dmmama 31491 DS-C-0025 DF-EH-L-0029 A 11/Oct/11 65 AS-DF-T-0012 DS-C-0000 MT 5/28/2011 SIKA Bitumen 60- (Bitumen Emulsion Protective Coating) For All Concrete Exposed to Ground SIKA Saudi Arabia Co. Ltd. PH Floor Obaikan Blgd, Prince Sultan Street, P.O.Box.112356 Jeddah, KSA 28/May/11 vol-5 66 AS-DS-L-0098 10/6/2011 Test results of Excavated Natural Soil 6/Oct/11 Attached Reports 67 AS-DF-T-0081 AS-DS-L-0102 DS-C-0018 MT 001 10/11/2011 Masterflex 700- Polysulphide Elastomeric Joint Sealant For Expansion Construction and Isolation Joint Saudi BASF for Building Material co.Ltd. P.O.Box.1884 Al-Khobar-31952 KSA 11/Oct/11 DS-C-0018 DF-EH-L-0064 A 29/Nov/11 Vol-1 68 AS-DF-T-0082 AS-DS-L-0103 DS-C-0038 MT x 10/12/2011 SIKA Waterbar-Joint Sealing PVC Profile & Sika Waterbars SG For All Underground Concrete, Concrete Expansion Joints and Kicker Where It Is Required SIKA Saudi Arabia Co. Ltd. PH Floor Obaikan Blgd, Prince Sultan Street, P.O.Box.112356 Jeddah, KSA 12/Oct/11 DS-C-0056 DF-EH-0076 B 15/Nov/11 Vol-1 69 AS-DF-T-0083 AS-DS-L-0109 DS-C-0039 MT 10/24/2011 Security Fence SSD-1 & SSD-2 Category This Material to be Used for Inner & Outer Fencing in the Whole Project Saudi Chainlink Fence Mfg.Co.Ltd P.O.Box.2577 Dammam 31461 KSA 24/Oct/11 On Hold returned on 25-10- 11, After issueing the Dwg from Doosan than Submission Vol-6 70 AS-DF-T-0084 AS-DS-L-0110 DS-C-0040 MT x 2 10/24/2011 Latifia Geogrids Type B20 This Material to be Used as Road Base/Sub Base Reinforcement in the Whole Project Geosynthetics Technologies Co.Ltd P.O.Box.77067 Al-Khobar 31952 KSA 24/Oct/11 On Hold returned on 25-10- 11, After issueing the Dwg from Doosan than Submission Vol-6 71 AS-DF-T-0085 AS-DS-L-0105 10/15/2011 Steel Door,Fire Rated Steel Doors & Frame,Steel Gates,Folding Doors, Roller Shutter Doors Pre-Qualification Al-Kuhaimi Metal Industries Ltd, P.O.Box 545, Dammam 31421 KSA 15/Oct/11 72 AS-DF-T-0086 AS-DS-L-0111 DS-C-0041 MT x 10/23/2011 Sikafloor-161,Sikafloor-264 & Sikafloor- 359 SG This Material to be Used for Epoxy Coating for Outside Surface of Concrete and Wherever it is Required SIKA Saudi Arabia Co. Ltd. PH Floor Obaikan Blgd, Prince Sultan Street, P.O.Box.112356 Jeddah, KSA 23/Oct/11 DS-C-0052 DF-EH-L-0072 B 1/Feb/12 The color code shall be in accordance to SWCC color coding system. Approval is subject to final inspection and acceptance of sample to be prepared at site. Vol-6 73 AS-DF-T-0087 AS-DS-L-0112 DS-C-0042 MT 10/23/2011 Renderoc TG- Xtra This Material to be Used for Repair of Honeycombing,Voids Greater Than 10mm Deep, Vertical & Overhead Repair in Concrete and Wherever it is Required Fosam Co. Ltd.P.O.11081 Jeddah 21453 23/Oct/11 DS-C-0053 DF-EH-L-0069 B 15/Nov/11 Vol-6 74 AS-DF-T-0090 AS-DS-L-0114 DS-C-0043 MT x 10/27/2011 Chequered Plate (Thk 6mm&8mm)& Steel Gratings This Material to be Used for Manholes,Trenches,Metal Steps,Platforms,Walkways & Wherever it is Required Saudi Pan Gulf (Steel Division) P.O.Box 2473 Al-Khobar 31952 KSA 27/Oct/11 Resubmitted on 28-11-11 with Galvanizing Sample & Test Certificate Vol-6 75 AS-DF-T-0089 AS-DS-L-0117 DS-C-0044 MT X 10/25/2011 Renderoc HF- High Performance non- Shrink Cementitious Microconcrete This Material to be Used for Repair of Concrete Where Rebar are Exposed and Wherever it is Required for the Whole Project Fosam Co. Ltd.P.O.11081 Jeddah 21453 25/Oct/11 DS-C-0055 DF-EH-L-0073 A 15/Nov/11 Vol-6 76 AS-DS-L-0121 10/25/2011 Concrete Mix Design for Doosan Project: Grade A-Type 1 Cement (40Mpa) For all Structural Concrete Works Assad Said Contracting co, Ltd Saudi 25/Oct/11 Attached Trial Mixes & Field Test Report for 7 Days C40 Page 49 of 75 No.of Sample File Location Sample Doosan Recd RAS AL KHAIR DESALINATION PLANT PHASE 1 PACKAGE "D" MATERIAL SUBMITTAL STATUS REPORT DATE COVERED : As of 25 August ,2012 S.N. DOOSAN Name of Suppliers Place of Application / Location ASSAD SAID ASC Transmittal no. Date of Submit Description of Material Doosan Heavy Industries & Construction. Assad Said For Contracting Co.,Ltd. 77 AS-DF-T-0091 AS-DS-L-0122 DS-C-0045 MT 10/27/2011 Sikagrout-114 Cementitious,Shrinkage Compensated General Purpose Grout This Material to be Used for Grouting in Machine foundations, Base Plates, Concrete Anchors, Cavities, Gaps, Recesses and General Concrete repairs. SIKA Saudi Arabia Co. Ltd. PH Floor Obaikan Blgd, Prince Sultan Street, P.O.Box.112356 Jeddah, KSA 27/Oct/11 DS-C-0089 DF-EF-L-0137 B 16/Feb/12 Contractor to strictly follow the mix proportion as per the manufactureer recommendation Vol-6 78 AS-DF-T-0088 AS-DS-L-0120 DS-C-0046 MT x 10/27/2011 Embedded Plates, Plates (thk 9mm) & MS Pipes (Dia.38mm&42mm) This Material to be Used for Manholes,Trenches,Metal Steps,Platforms,Walkways & Wherever it is Required Saudi Pan Gulf (Steel Division) P.O.Box 2473 Al-Khobar 31952 KSA 27/Oct/11 Resubmitted on 28-11-11 with Galvanizing Sample & Test Certificate Vol-6 79 AS-DF-T-0092 AS-DS-L-0119 DS-C-0047 MT x 10/27/2011 Angle Bars & Steel Bars This Material to be Used in Trenches, Metal Steps, Ladder & wherever it is required Saudi Pan Gulf (Steel Division) P.O.Box 2473 Al-Khobar 31952 KSA 27/Oct/11 Resubmitted on 28-11-11 with Galvanizing Sample & Test Certificate Vol-6 80 AS-DF-T-0093 AS-DS-L-0128 DS-C-0048 MT 10/29/2011 Conbextra GP-General Purpose non- Shrink Cementitious Grout This Material is used Where it is Essential to Eliminate Shrinkage when Completely Filling the Void b/w a Base Plate and a Substrate. FOSAM Co. Ltd.P.O.11081 Jeddah 21453 29/Oct/11 DS-M-0001 DF-EH-L-0066 B 15/Nov/11 Vol-6 81 AS-DS-L-0125 10/30/2011 Concrete Mix Design for PS 1: Grade A- Type 1 Cement (40Mpa) For all Structural Concrete Works Assad Said Contracting co, Ltd Saudi 30/Oct/11 EF-DF-L-007&DH-EF- D-0060, A After Revising the Slump 82 AS-DF-T-0094 AS-DS-L-129 DS-C-0049 MT 10/31/2011 Renderco HS Xtra This Material is used for Vertical & Overhead repairs to restore covercrete, General Concrete & Masonry repairs, FOSAM Co. Ltd.P.O.11081 Jeddah 21453 31/Oct/11 DS-C-0057 DF-EH-L-0078 B 15/Nov/11 Vol-6 83 AS-DS-L-0135 11/16/2011 Concrete Mix Design for Doosan Project: Grade A-Type 1 Cement (40Mpa) For all Structural Concrete Works Assad Said Contracting co, Ltd Saudi 16/Nov/11 Attached Trial Mixes & Field Test Report for 28 Days C40 84 AS-DF-T-0098 AS-DS-L-0136 DS-C-0051 MT x 11/17/2011 Nitocote EPU Nitoflor EPU 100 For Epoxy Coating of Wall & Floor for Concrete Protection, Seawater Tanks, Channels & Intake,Reservoirs, Water Treatment Plants, Manhole & Pipe Linings, Secondary Containments, Lining for Sewage & Effluents Plants. FOSAM Co. Ltd.P.O.11081 Jeddah 21453 17/Nov/11 DS-C-0061 DH-EF-L-0088 B 1/Feb/12 The color code shall be in accordance to SWCC color coding system. Approval is subject to final inspection and acceptance of sample to be prepared at site. Vol-6 85 AS-DF-T-0100 AS-DS-L-0138 DS-C-0050 MT x 2 11/20/2011 Concrete Interlocking Pavers This Material Used for Roads & Areas to be Paved with Interlocking Concrete Blocks & Wherever it is required for the whole project Jubail Concrete Product Co.Ltd (Div. Al- Khinaini Co.Ltd) P.O.Box 30, Jubail 31951 KSA 20/Nov/11 Vol-6 86 AS-DF-T-0101 AS-DS-L-0139 DS-C-0051 MT x 1 11/20/2011 Kerb Stone Used for all the Road Works For Whole Project Jubail Concrete Product Co.Ltd (Div. Al- Khinaini Co.Ltd) P.O.Box 30, Jubail 31951 KSA 20/Nov/11 Vol-6 87 AS-DF-T-0102 AS-DS-L-0140 DS-C-0052 MT x 2 11/20/2011 Hollow Blocks Hollow Blocks is to be used for All Blocks Masonry Work in the Whole Project Jubail Concrete Product Co.Ltd (Div. Al- Khinaini Co.Ltd) P.O.Box 30, Jubail 31951 KSA 20/Nov/11 DS-C-0059 DH-EF-L-0085 C 1/Feb/12 Vol-6 88 AS-DF-T-0103 AS-DS-L-0141 DS-C-0053 MT x 2 11/20/2011 Hollow Blocks Hollow Blocks is to be used for All Blocks Masonry Work in the Whole Project Saudi Ready Mix Concrete Co. Ltd P.O.Box. 31839 Al-Khobar 31952 20/Nov/11 DS-C-0060 DH-EH-L-0087 B 1/Feb/12 Hollow masonry blocks to be used in partition or non -load bearing walls Vol-6 89 AS-DF-T-0104 AS-DS-L-0143 DS-C-0054 MT 11/21/2011 Fenomastic Emulsion Primer & Stucco Putty For Fully Cured Cement Plastered Walls, Ceiling, Concrete ,Gypsum Board Partitions, GRC Works etc Prior to Paint Application in the Building Wherever it is Reqquired for the Whole Project Jotun Saudi Co. Ltd P.O.Box 4906 Dammam 31412, KSA 21/Nov/11 DS-C-0063 DH-EF-L-0063 B 1/Feb/12 The primer used shall be compatible with the subsequent coating system Vol-6 90 AS-DF-T-0105 AS-DS-L-0144 DS-C-0055 MT 11/21/2011 Fenomastic Emulsion Matt & Fenomastic Emulsion Semigloss This Material is to be Used on Most Interior Surface, i.e Cement Plaster, Stucco Filler Gypsum Boards, Concrete, Asbestos Cement Sheeting & Rendered Block Works Jotun Saudi Co. Ltd P.O.Box 4906 Dammam 31412, KSA 21/Nov/11 DS-C-0062 DH-EF-L-0086 B 1/Feb/12 The color code shall be in accordance to SWCC color coding system and subject to approval of sample at site prior to application Vol-6 91 AS-DF-T-0106 AS-DS-L-0149 DS-C-0056 MT 11/24/2011 Nitoflor FC 110 & Nitoflor Lithurin As Liquid Hardener This Material is to be used as Liquid Hardener for Floor Finishing in S/G Building for Post Treament Plant, Seawater Intake S/G Building,RO Building & Wherever it is required FOSAM Co. Ltd.P.O.11081 Jeddah 21453 24/Nov/11 Vol-6 92 AS-DS-L-0151 11/24/2011 Concrete Mix Design for Doosan Project: Grade A-Type 1 Cement (20Mpa) For all Structural Concrete Works Assad Said Contracting co, Ltd Saudi 24/Nov/11 Attached Trial Mixes & Field Test Report for 28 Days C20 93 AS-DF-T-0107 AS-DS-L-0152 11/24/2011 Precast Hollow Core Slab Pre-Qualification Assad Said Contracting for Precast 24/Nov/11 With Soft copy 94 AS-DF-T-0108 AS-DS-L-0154 DS-C-0057 MT X 11/27/2011 Ceramic Tiles & Acid Resistant Ceramic Tiles (Floor & Walls) This Material to be Used for Tiling Work in Floors & Walls of Electrochlorination Building, S/G Bldg for MSF area, S/G Bldg for Post Treatment Plant, Seawater Intake S/G Bldg & Wherever it is Required Saudi Ceramics Co. Ltd P.O Box. 3893 Riyadh 11481 KSA 27/Nov/11 Vol 6 Page 50 of 75 No.of Sample File Location Sample Doosan Recd RAS AL KHAIR DESALINATION PLANT PHASE 1 PACKAGE "D" MATERIAL SUBMITTAL STATUS REPORT DATE COVERED : As of 25 August ,2012 S.N. DOOSAN Name of Suppliers Place of Application / Location ASSAD SAID ASC Transmittal no. Date of Submit Description of Material Doosan Heavy Industries & Construction. Assad Said For Contracting Co.,Ltd. 95 AS-DF-T-0110 AS-DS-L-0159 DS-C-0058 MT 12/1/2011 Heavy Duty Ductile Cast Iron & Medium & Heavy Duty Grey Cast Iron Manhole Cover & Frame This Material to be Used in Manholes, Pits & Wherever it is Applicable in the Whole Project Riyadh Foundry Co. P.O.Box 157474, Second Industrial Area, Riyadh KSA 1/Dec/11 DS-C-0068 DF-EF-L-0101 B 28/Feb/12 Provide protective bitumen paint details, Element size would be according to approved drawings, Inscription in Arabic & English to be written on the M.H cover top as drainage or storm water manhole as appropriate Vol-6 96 AS-DF-T-0111 AS-DS-L-0160 DS-C-0059 MT 12/1/2011 Cast Iron Heavy Duty Round Covers & Round Frame This Material to be Used in Manholes, Pits & Wherever it is Applicable in the Whole Project Saudi Cast P.O.Box.3505, Riyadh 11481, KSA 1/Dec/11 DS-C-0067 DF-EF-L-0100 B 28/Sep/12 Provide protective bitumen paint details, Element size would be according to approved drawings, Inscription in Arabic & English to be written on the M.H cover top as drainage or storm water manhole as appropriate Vol-6 97 AS-DF-T-0112 AS-DS-L-0161 DS-C-0060 MT 12/4/2011 NITOTILE 489- Epoxy Tile Adhesive and Grout This Material to be used as a Chemical Resistant Adhesive and Grout for bonding quarry and Ceramic Tiles to concrete or steel, also suitable as a multi-purpose adhesive for bedding and repairs & wherever it is required FOSAM Co. Ltd.P.O.11081 Jeddah 21453 4/Dec/11 DS-C-0069 DF-EF-L-0102 B 27/Jun/12 Vol-7 98 AS-DF-T-0113 AS-DS-L-0162 DS-C-0061 MT X 12/4/2011 NITOTILE XS - Polymer-Modified, One Component, High Performance, waterproof Tile Adhesive This Material to be used as an adhesive for the permanent fixing of Ceramic Wall and Floor Tiles including Porcelain and fully Vitrified Tiles, Ceramic Mosaics, Quarry Tiles, Dark Natural Stone, Terrazzo and Brick Silps & wherever required. FOSAM Co. Ltd.P.O.11081 Jeddah 21453 4/Dec/11 DS-C-0070 DF-EF-L-0103 B Vol-7 99 AS-DF-T-0114 AS-DS-L-0163 DS-C-0062 MT X 12/4/2011 NITOTILE GP- General Purpose Tile Adhesive This Material to be used as an adhesive for the permanent fixing of Ceramic Tiles & wherever it is required. FOSAM Co. Ltd.P.O.11081 Jeddah 21453 4/Dec/11 DS-C-0071 DF-EF-L-0104 B Vol-7 100 AS-DF-T-0115 AS-DS-L-0164 DS-C-0063 MT 12/4/2011 Roof Drain This material is to be used as roof drain. Sample will be provided as per your selection from the attached brochure which we marked. Saudi Cast P.O.Box.3505, Riyadh 11481, KSA 4/Dec/11 DS-C-0072 DF-EF-L-0105 B 1/Feb/12 Only Model 4020 Approved Vol-7 101 AS-DF-T-0116 AS-DS-L-0169 DS-C-0057 MT 001 x 12/13/2011 Ceramic Tiles (Floor & Walls) This Material to be Used for Tiling Work in Floors & Walls of Electrochlorination Building, S/G Bldg for MSF area, S/G Bldg for Post Treatment Plant, Seawater Intake S/G Bldg & wherever it is required Saudi Ceramics Co. Ltd P.O Box. 3893 Riyadh 11481 KSA 13/Dec/11 Vol-7 102 AS-DS-L-0170 12/13/2011 Test results of Batching Plant Aggregates (3/4", 3/8", 3/16" & Sand) & Water Assad Said Contracting co, Ltd Saudi 13/Dec/11 Test Results of BP for the Month of October 2011 Vol-7 103 AS-DF-T-0117 AS-DS-L-0172 12/13/2011 Al-Radayef Crusher (Select Fill, Basecourse, Subbase, Sand & Aggregates 1", 3/4", 3/8" & 3/16") Pre-Qualification Al-Radayef Trading & Contracting Co. P.O Box 30291 Al-Khobar 31952 KSA 13/Dec/11 104 AS-DF-T-0118 AS-DS-L-0174 DS-C-0064 MT X 12/19/2011 Angle Bars & Steel Bars This Material to be Used in Trenches, Metal Steps, Ladder & wherever it is required Al-Sharq Factory Steel Industries P.O.Box 40300, Riyadh 11499 19/Dec/11 Vol-7 105 AS-DF-T-0119 AS-DS-L-0175 DS-C-0065 MT X 12/19/2011 Chequered Plates This Material to be Used for Manholes,Trenches,Metal Steps,Platforms,Walkways & Wherever it is Required Al-Sharq Factory Steel Industries P.O.Box 40300, Riyadh 11499 19/Dec/11 Vol-7 106 AS-DF-T-0120 AS-DS-L-0176 DS-C-0066 MT X 12/19/2011 MS Plate & Tube This Material to be Used for Manholes,Trenches,Metal Steps,Platforms,Walkways & Wherever it is Required Al-Sharq Factory Steel Industries P.O.Box 40300, Riyadh 11499 19/Dec/11 DS-C-0082 DF-EF-L-0125 B 7/Apr/12 Vol-7 107 AS-DF-T-0121 AS-DS-L-0177 DS-C-0067 MT 1/22/2012 Anchor Bolts This material is to be used for foundation sample will be provided as per selection from the attached brochure Saudi Alamar Trading & Industries Co. 22/Jan/12 DS-C-0087 DF-EF-L-0133 C 16/Feb/12 Material Requested not suitable for the intended installed as per attached document Vol-7 108 AS-DF-T-122 AS-DS-L-0178 DS-C-0068 MT 12/19/2011 Lifting Socket & Lifting Loop This Material is to be used for Cable Trench, Precast Cover & wherever it is required Saudi Alamar Trading & Industries Co. 19/Dec/11 DS-C-0079 DF-EF-L-0121 B 28/Feb/12 The socket upper end to be plugged with plastic/PVC plug to prevent from rusting and sand filling Vol-7 Page 51 of 75 No.of Sample File Location Sample Doosan Recd RAS AL KHAIR DESALINATION PLANT PHASE 1 PACKAGE "D" MATERIAL SUBMITTAL STATUS REPORT DATE COVERED : As of 25 August ,2012 S.N. DOOSAN Name of Suppliers Place of Application / Location ASSAD SAID ASC Transmittal no. Date of Submit Description of Material Doosan Heavy Industries & Construction. Assad Said For Contracting Co.,Ltd. 109 AS-DF-T-0123 AS-DS-L-0180 DS-C-0069 MT 12/31/2011 Masterseal EPU 180- Two Component Solvent Free High Build Flexible Epoxy Poly-Urethane Resin Coating System This material to be used to provide Heavy-duty Protective, Waterproof, Flexible Coating, Lining of Tank, Pipe and Ducting, Coating Concrete, Asbestos Cement, Steel Pipes and Non- ferrous metals, wherever it is required Saudi BasF for Building Material co.Ltd. P.O.Box.1884 Al-Khobar-31952 KSA 31/Dec/11 DS-C-0078 DF-EF-L-0120 B 28/Feb/12 Subject to approved of Mock- up test at site, Specify the exact location to be used Vol-7 110 AS-DF-T-0124 AS-DS-L-0189 DS-C-0070 MT 1/1/2012 Precast Hollow Core Slab This Material is to be used as Wall Panel in Electro chlorination Building, Switchgear Building for MSF, SWI Switchgear Building, and Switchgear Building for Post Treatment Plant. Assad Said for Precast Factory 1/Jan/12 Vol-7 111 AS-DF-T-0125 AS-DS-L-0190 DS-C-0071 MT X 1 1/1/2012 Siporex Wall Panels This Material is to be used as Wall Panel in Electro chlorination Building, Switchgear Building for MSF, SWI Switchgear Building, and Switchgear Building for Post Treatment Plant. LCC- Siporex P.O.Box.6230, Riyadh 1142, KSA 1/Jan/12 DS-C-0083 DF-EF-L-0126 C 28/Feb/12 This is not a specified material Vol-7 112 AS-DF-T-0126 AS-DS-L-0200 DS-C-0072 MT 1 1/8/2012 MS Plate This Material to be Used for Manholes,Trenches,Metal Steps,Platforms,Walkways & Wherever it is Required Al-Sharq Factory Steel Industries P.O.Box 40300, Riyadh 11499 8/Jan/12 Vol-7 113 AS-DS-L-0198 1/8/2012 Test results of Batching Plant Aggregates (3/4", 3/8", 3/16" & Sand) & Water Assad Said Contracting co, Ltd Saudi 8/Jan/12 For the Month of December 2011 114 AS-DS-L-0179 12/22/2011 Test results of Batching Plant Aggregates (3/4", 3/8", 3/16" & Sand) & Water Assad Said Contracting co, Ltd Saudi 24/Dec/11 For the Month of November 2011 115 AS-DF-T-0127 AS-DS-L-0209 1/15/2012 Independent Testing Laboratories Geotechnical & Material Engineers Pre-Qualification Omar Jazzar Consulting Engineers 15/Jan/12 With Softcopy 116 AS-DS-L-0209 (A) 1 3/5/2012 Independent Testing Laboratories Geotechnical & Material Engineers Pre-Qualification & Company Questionnaire Omar Jazzar Consulting Engineers 5/Mar/12 Submitted with Company Questionnaire Vol-8 117 AS-DF-T-0128 AS-DS-L-0216 DS-C-0045 MT 1 x 1 1/22/2012 Sikagrout-114 Cementitious,Shrinkage Compensated General Purpose Grout This Material to be Used for Grouting in Machine foundations, Base Plates, Concrete Anchors, Cavities, Gaps, Recesses and General Concrete repairs. SIKA Saudi Arabia Co. Ltd. PH Floor Obaikan Blgd, Prince Sultan Street, P.O.Box.112356 Jeddah, KSA 22/Jan/12 Vol-7 118 AS-DF-T-0129 AS-DS-L-0217 DS-C-0073 MT 1/22/2012 Sikafloor- Curehard- 24 (Transparent Surface Hardener, Dust Proofer, Sealing & Curing Compound for Concrete This Material is to be used as Liquid Hardener for Floor Finishing in S/G Building for Post Treament Plant, Seawater Intake S/G Building,RO Building & Wherever it is required SIKA Saudi Arabia Co. Ltd. PH Floor Obaikan Blgd, Prince Sultan Street, P.O.Box.112356 Jeddah, KSA 22/Jan/12 DS-C-0088 DF-EF-L-0136 B 16/Feb/12 Subject to approved of sample panel to be provided at site Vol-7 119 AS-DF-T-0131 AS-DS-L-0219 DS-C-0075 MT X 1 1/28/2012 Sikaflex PRO-3 WF -1 Part high performance for flooring For Expansion Construction and Isolation Joint SIKA Saudi Arabia Co. Ltd. PH Floor Obaikan Blgd, Prince Sultan Street, P.O.Box.112356 Jeddah, KSA 28/Jan/12 DS-C-0090 DF-EF-L-0138 A 16/Feb/12 No Comment Vol-7 120 AS-DF-T-0130 AS-DS-L-0218 DS-C-0074 MT 2/6/2012 Anchor Bolts This material is to be used for foundation sample will be provided as per selection from the attached Ali Al-Dar Hardwares Est. P.O. Box 8554, Dammam 31492, KSA 6/Feb/12 DS-C-0092 DF-EF-L-0142 C 28/Feb/12 Size & type of Anchor Bolt to be highlighted on the attached brochure, Sample to Vol-7 121 AS-DF-T-0133 AS-DS-L-0229 DS-C-0077 MT X 2 2/6/2012 Block Works & Plastering Accessories This material is to be used for all blocks masonry in the whole project ISAM KABBANI & Partner for Building & Const Material Co.P.O.6897 Damman KSA 6/Feb/12 DS-C-0095 DF-EF-L-0147 A 28/Feb/12 Same material and supplier has already been approved for ASC, refer CRS attached Vol-7 122 AS-DF-T-0134 AS-DS-L-0254 DS-C-0078 MT X 3/5/2012 Suspended Metal Ceiling (Aluminum Panel Ceiling System) This material is to be used as Suspended Metal Ceiling in Toilets of All Buildings & Wherever it is required in the whole project Taliah Trading & Industrial Co. P.O Box. 41084 Riyadh-11521 5/Mar/12 DS-C-0099 DF-EF-L-0158 C 7/Apr/12 Vol-8 123 AS-DF-T-0135 AS-DS-L-0259 DS-C-0079 MT X 3/5/2012 Suspended Ceiling (Mineral Board Ceiling) This material is to be used as Suspended Mineral Board Ceiling in Corridor & Office of All Buildings & Wherever it is required in the whole project Taliah Trading & Industrial Co. P.O Box. 41084 Riyadh-11521 5/Mar/12 DS-C-0100 DF-EF-L-0160 C 7/Apr/12 Vol-8 124 AS-DF-T-0136 AS-DS-L-0271 DS-C-0080 MT X 3/21/2012 Lifting Socket & Lifting Loop This Material is to be used for Cable Trench, Precast Cover & wherever it is required AI-Monathem Industrial Tools Co. P.O.Box.118797, Jeddah KSA 21/Mar/12 DS-C-0104 DF-EF-L-0167 B 7/May/12 Sample provided on 10-4-12, Plastic caps to be provided over socket to prevent ingress of dust Vol-8 125 AS-DS-L-278 MT 1 X 3/24/2012 Anchor Bolts This material is to be used for foundation. Saudi Alamar Trading & Industries Co. 24/Mar/12 Returned from Doosan on 2-4- 12 Vol-8 126 AS-DF-T-0138 AS-DS-L-279 DS-C-0082 MT 4/1/2012 Sikagard-PW (Non Toxic High Chemical Resistance Epoxy Coating) This Material to be used for heavy protective coating for concrete, wood floors and metal structrure subjected to chemical attack & wherever it is required SIKA Saudi Arabia Co. Ltd. PH Floor Obaikan Blgd, Prince Sultan Street, P.O.Box.112356 Jeddah, KSA 1/Apr/12 DS-C-0106 DF-EF-L-0194 C 23/Jul/12 Contractor to specify the exact location where they intend to use this material Vol-8 127 AS-DF-T-0137 AS-DS-L-291 DS-C-0081 MT x 4/3/2012 Anchor Bolts This material is to be used in Columns Corbel for Crane Beams, Girders & Foundation. Saudi Alamar Trading & Industries Co. 3/Apr/12 DS-C-0087 DF-EF-L-0193 B 26/May/12 Resubmitted to Doosan on 3- 4-12 with Mill & Galvanizing Coating Certificate & Samples Vol-8 Page 52 of 75 No.of Sample File Location Sample Doosan Recd RAS AL KHAIR DESALINATION PLANT PHASE 1 PACKAGE "D" MATERIAL SUBMITTAL STATUS REPORT DATE COVERED : As of 25 August ,2012 S.N. DOOSAN Name of Suppliers Place of Application / Location ASSAD SAID ASC Transmittal no. Date of Submit Description of Material Doosan Heavy Industries & Construction. Assad Said For Contracting Co.,Ltd. 128 AS-DS-L-0284 3/27/2012 Test results of Batching Plant Aggregates (3/4", 3/8", 3/16" & Sand) & Water Assad Said Contracting co, Ltd Saudi 27/Mar/12 For the Month of January 2012 129 AS-DS-L-0292 4/4/2012 Test results of Batching Plant Aggregates (3/4", 3/8", 3/16" & Sand) & Water Assad Said Contracting co, Ltd Saudi 4/Apr/12 For the Month of February 2012 130 AS-DF-T-0140 AS-DS-L-293 DS-C-0084 MT X 1 4/5/2012 Blue Guard-Extruded Polystyrene Insulation Boards This Material is to be used for Cavity Wall of SWGR Building for Post Treament Plant, Seawater Intake SWGR Building, Gas Chlorination Building, Electro Chlorination Building SAPTEX- Insulation Products Factory 5/Apr/12 DS-C-0107 DF-EF-L-0195 A 17/May/12 Vol-8 131 AS-DF-T-0141 AS-DS-L-299 DS-C-0086 MT 4/8/2012 Vetonit Premium Fix & Ceramic Tile Fix This Material is to be used for Tiling Work Adhesive In Floors & Walls of SWGR Building for Post Treament Plant, Seawater Intake SWGR Building, Electro Chlorination Building & Wherever it is required Saudi Vetonit Co. Ltd. P.O.Box. 52235 Riyadh 11563 KSA 8/Apr/12 DS-C-0108 DF-EF-L-0200 B 17/May/12 Vol-8 132 AS-DF-T-0142 AS-DS-L-300 DS-C-0087 MT 4/8/2012 Vetonit Grout This Material is to be used for Tiling Works Grout In Floors & Walls of SWGR Building for Post Treament Plant, Seawater Intake SWGR Building, Electro Chlorination Building & Wherever it is required Saudi Vetonit Co. Ltd. P.O.Box. 52235 Riyadh 11563 KSA 8/Apr/12 DS-C-0109 DF-EF-L-0201 B 17/May/12 Vol-8 133 AS-DF-T-0143 AS-DS-L-302 DS-C-0088 MT 4/11/2012 Mastertile 30-Internal & External Tile Adhesive This Material is to be used for Tiling Work Adhesive In Floors & Walls of SWGR Building for Post Treament Plant, Seawater Intake SWGR Building, Electro Chlorination Building & Wherever it is required Saudi BASF for Building Material co.Ltd. P.O.Box.1884 Al-Khobar-31952 KSA 11/Apr/12 DS-C-0112 DF-EF-L0213 B 17/May/12 Vol-8 134 AS-DF-T-0144 AS-DS-L-303 DS-C-0089 MT 4/11/2012 Mastertile 530- Coloured Grout for Ceramic Tiles This Material is to be used for Tiling Works Grout In Floors & Walls of SWGR Building for Post Treament Plant, Seawater Intake SWGR Building, Electro Chlorination Building & Wherever it is required Saudi BASF for Building Material co.Ltd. P.O.Box.1884 Al-Khobar-31952 KSA 11/Apr/12 DS-C-0111 DF-EF-L-0212 B 17/May/12 Vol-8 135 AS-DF-T-0145 AS-DS-L-304 DS-C-0090 MT 4/11/2012 Mastertop 20- Concrete Hardening & Dustproofing Liquid This Material is to be used as Liquid Hardener for Floor Finishing in S/G Building for Post Treament Plant, Seawater Intake S/G Building & Wherever it is required Saudi BASF for Building Material co.Ltd. P.O.Box.1884 Al-Khobar-31952 KSA 11/Apr/12 DS-C-0110 DF-EF-L-0211 B 23/Jul/12 Hardening and dustproofing liquid shall be compatible with the successive hi-built epoxy coating Vol-8 136 AS-DS-L-326 MT X 4/30/2012 Roof Water Proofing System This material to be applied to all Bldgs such as Switchgear Buildings for MSF Area, Sea Water Intake Switchgear Building, Switchgear Building for Post Treatment, Electro Chlorination Building & Gas Chlorination Building. BITUMAT Co.Ltd P.O BOX 7487 Dammam 31462 30/Apr/12 Submitted Sample with attached Specfi & Drawings Vol-8 137 AS-DF-T-0151 AS-DS-L-0325 DS-C-0096 MT 5/3/2012 Hollow Metal Doors The doors to be installed in all Bldgs such as Switchgear Buildings for MSF Area, Sea Water Intake Switchgear Building, Switchgear Building for Post Treatment, Electro Chlorination Building & Gas Chlorination Building & Wherever it is required. Al-Manashy Doors Manufacturer Al- Khozama Dist/Exit 1 P.O.Box.71021 Al- Diriyah 11587 KSA 3/May/12 DS-C-0126 DF-EF-L-0250 C 23/Jul/12 No Sample Provided & Frame thickness should be 4mm thick vol-8 138 AS-DF-T-0150 AS-DS-L-0317 DS-C-0094 MT 5/3/2012 Paintco Alkali Resistant Primer 1507, Acrylux Enamel 6633 & Magna Spray Plaster Putty 20000 (Interior) For Fully Cured Cement Plastered Walls, Ceiling, Concrete ,Gypsum Board Partitions, GRC Works etc Prior to Paint Application in the Building Wherever it is Reqquired for the Whole Project Paintco Co. Ltd. P.O.Box 2549 Riyadh 11461 KSA 3/May/12 vol-8 139 AS-DF-T-0152 AS-DS-L-0329 DS-C-0098 MT 5/3/2012 Paintco Alkali Resistant Primer 1507, Acrylux Enamel 6633 & Magna Spray Plaster Putty 20000 (Exterior) For Fully Cured Cement Plastered Walls, Ceiling, Concrete ,Gypsum Board Partitions, GRC Works etc Prior to Paint Application in the Building Wherever it is Reqquired for the Whole Project Paintco Co. Ltd. P.O.Box 2549 Riyadh 11461 KSA 3/May/12 vol-8 140 AS-DF-T-0153 AS-DS-L-0327 DS-C-0097 MT 5/3/2012 Paintco Latex Primer Sealer 1201, Acrylic Emulsion Interior/ Exterior 2635 & Magna Wall Filler 10000 (Interior) This Material is to be Used on Most Interior Surface, i.e Cement Plaster, Stucco Filler Gypsum Boards, Concrete, Asbestos Cement Sheeting & Rendered Block Works Paintco Co. Ltd. P.O.Box 2549 Riyadh 11461 KSA 3/May/12 vol-8 Page 53 of 75 No.of Sample File Location Sample Doosan Recd RAS AL KHAIR DESALINATION PLANT PHASE 1 PACKAGE "D" MATERIAL SUBMITTAL STATUS REPORT DATE COVERED : As of 25 August ,2012 S.N. DOOSAN Name of Suppliers Place of Application / Location ASSAD SAID ASC Transmittal no. Date of Submit Description of Material Doosan Heavy Industries & Construction. Assad Said For Contracting Co.,Ltd. 141 AS-DF-T-0154 AS-DS-L-0330 DS-C-0098 MT 5/3/2012 Paintco Latex Primer Sealer 1201, Acrylic Emulsion Interior/ Exterior 2635 & Magna Spray Plaster Putty 20000 (Exterior) This Material is to be Used on Most Exterior Surface, i.e Cement Plaster, Stucco Filler Gypsum Boards, Concrete, Asbestos Cement Sheeting & Rendered Block Works Paintco Co. Ltd. P.O.Box 2549 Riyadh 11461 KSA 3/May/12 vol-8 142 AS-DF-T-0156 AS-DS-L-0332 DS-C-0099 MT 5/7/2012 Concrete Primer-Bituminous Roofing Primer & Polyflame-APP Modified Bitumen Waterproofing Membrane with Non-Woven Polyester Re- Inforcements This material to be used as Roof Water Proofing Membrane in all Bldgs such as Switchgear Buildings for MSF Area, Sea Water Intake Switchgear Building, Switchgear Building for Post Treatment, Electro Chlorination Building & Gas Chlorination Building. BITUMAT Co.Ltd P.O BOX 7487 Dammam 31462 7/May/12 vol-8 143 AS-DF-T-0157 AS-DS-L-0333 DS-C-0100 MT 5/7/2012 FIBERLON-APP Modified Bitumen Membranes with Non-Woven Polyester Re-Inforcement This material to be used for exposed to weather upstands for Roof Parapets and sides of HVAC Equipment Foundation Pads at Roof Waterproofing System at Roof in all Bldgs such as Switchgear Buildings for MSF Area, Sea Water Intake Switchgear Building, Switchgear Building for Post Treatment, Electro Chlorination Building & Gas Chlorination Building. BITUMAT Co.Ltd P.O BOX 7487 Dammam 31463 8/May/12 vol-8 144 AS-DF-T-0158 AS-DS-L-0334 DS-C-0101 MT 5/7/2012 BITUTEX-Non-woven Geotextiles This material to be used as Building Paper in Roof Waterproofing System in all Bldgs such as Switchgear Buildings for MSF Area, Sea Water Intake Switchgear Building, Switchgear Building for Post Treatment, Electro Chlorination Building & Gas Chlorination Building. BITUMAT Co.Ltd P.O BOX 7487 Dammam 31464 9/May/12 vol-8 145 AS-DF-T-0159 AS-DS-L-0335 DS-C-0102 MT 5/7/2012 BITUTHERM-Extruded Polystyrene Thermal Insulation Boards This material to be used as Rigid Thermal Insulation in Roof Waterproofing System in all Bldgs such as Switchgear Buildings for MSF Area, Sea Water Intake Switchgear Building, Switchgear Building for Post Treatment, Electro Chlorination Building & Gas Chlorination Building. BITUMAT Co.Ltd P.O BOX 7487 Dammam 31463 8/May/12 vol-8 146 AS-DF-T-0155 AS-DS-L-0331 5/8/2012 Handover of SWGR for MSF Area Unit # 71 & 72 Handover of SWGR for MSF Area Unit # 71 & 72, Basement Floor, Walls, Columns, Beams & Ceiling 8/May/12 147 AS-DF-T-0160 AS-DS-L-0339 DS-C-103 MT X 5/8/2012 Concrete Tiles (400x400x40) for Roof Waterproofing System This material to be used as Concrete Tiles in Roof Waterproofing System in all Bldgs such as Switchgear Buildings for MSF Area, Sea Water Intake Switchgear Building, Switchgear Building for Post Treatment, Electro Chlorination Building & Gas Chlorination Building. New Century Est. Branch, Near Dallah Driving School, Industrial Area, Dammam, KSA 8/May/12 DS-C-0125 DF-EF-L-0249 C 23/Jul/12 Sample to be provided vol-8 148 AS-DS-L-0340 5/9/2012 Test results of Batching Plant Aggregates (3/4", 3/8", 3/16" & Sand) Assad Said Contracting co, Ltd Saudi 9/May/12 Test Results of BP for the Month of March 2012 149 AS-DF-T-0161 AS-DS-L-0341 DS-C-104 MT 5/9/2012 Angle Bars This Material to be Used in Trenches, Metal Steps, Ladder & wherever it is required Al-Sharq Factory Steel Industries P.O.Box 40300, Riyadh 11499 9/May/12 DS-C-122 DF-EF-L-246 C 27/May/12 Attached Technical Datasheet & Test Certificate 150 AS-DF-T-0162 AS-DS-L-0342 DS-C-105 MT 5/9/2012 Steel Plates This Material to be Used for Manholes, Trenches, Metal Steps, Plateform & Walkways & wherever it is required Al-Sharq Factory Steel Industries P.O.Box 40300, Riyadh 11500 9/May/12 DS-C-124 DF-EF-L-248 C 27/May/12 Attached Technical Datasheet & Test Certificate 151 AS-DF-T-0163 AS-DS-L-0343 DS-C-106 MT 5/9/2012 Chequered Plates This Material to be Used for Manholes, Trenches, Metal Steps, Plateform & Walkways & wherever it is required Al-Sharq Factory Steel Industries P.O.Box 40300, Riyadh 11501 9/May/12 DS-C-123 DF-EF-L-247 C 27/May/12 Attached Technical Datasheet & Test Certificate 152 AS-DF-T-0164 AS-DS-L-0352 DS-C-0106 MT 5/16/2012 Hollow Metal Doors The doors to be installed in all Bldgs such as Switchgear Buildings for MSF Area, Sea Water Intake Switchgear Building, Switchgear Building for Post Treatment, Electro Chlorination Building & Gas Chlorination Building & Wherever it is required. Al-Kuhaimi Metal Industries Ltd, P.O.Box 545, Dammam 31421 KSA 16/May/12 DS-C-0128 DF-EF-L-0258 C 23/Jul/12 Sample need to be submitted & Door frame steel sheet thickness should be 4mm vol-8 Page 54 of 75 No.of Sample File Location Sample Doosan Recd RAS AL KHAIR DESALINATION PLANT PHASE 1 PACKAGE "D" MATERIAL SUBMITTAL STATUS REPORT DATE COVERED : As of 25 August ,2012 S.N. DOOSAN Name of Suppliers Place of Application / Location ASSAD SAID ASC Transmittal no. Date of Submit Description of Material Doosan Heavy Industries & Construction. Assad Said For Contracting Co.,Ltd. 153 AS-DS-L-0353 X 1 5/16/2012 Internal Painting System This Material to be used in all Bldgs Jotun Saudi Co. Ltd P.O.Box 4906 Dammam 31412, KSA 16/May/12 Submitted as a sample board vol-8 154 AS-DF-T-165 AS-DS-L-0353 DS-C-0107 MT 5/17/2012 Fenomastic Enamel Semigloss This material to be used for fully cured Cement Plastered Walls, Cielings, Concrete, Gypsum board Partitions, GRC works etc Prior to Paint application in the Buildings &wherever it is required for the whole Project Paintco Co. Ltd. P.O.Box 2549 Riyadh 11461 KSA 17/May/12 vol-8 155 AS-DF-T-0167 AS-DS-L-357 DS-C-109 MT X 1 5/21/2012 Back-Up-Rod This material is to be used inside Buildings at the peripheral gaps bet. Structural Elements Columns & Beams and block masonry & wherever it is required for the whole Project. Saudi Alamar Trading & Industries Co. P.O.Box.17, Dammam 31411 21/May/12 DS-C-0132 DF-EF-L-0264 A 23/Jul/12 No Comment vol-8 156 AS-DF-T-0168 AS-DS-L-358 DS-C-110 MT X 1 5/23/2012 Sarnafil Solar Reflective Roofing System With Method Statement This material to be used in Roof Waterproofing System in all Bldgs such as Switchgear Buildings for MSF Area, Sea Water Intake Switchgear Building, Switchgear Building for Post Treatment, Electro Chlorination Building & Gas Chlorination Building. SIKA Saudi Arabia Co. Ltd. PH Floor Obaikan Blgd, Prince Sultan Street, P.O.Box.112356 Jeddah, KSA 23/May/12 DS-C-0134 DF-EF-L-0266 C 23/Jul/12 Submitted system is not according to specs as per SWCC specs roofing system should be asphalt built up roofing vol-8 157 AS-DF-T-0169 AS-DS-L-361 DS-C-111 MT X 1 5/23/2012 FRP-Gratings & Angle Bars This materials to be used for Trenches Covers the following structures. - Electro Chlorination Bldg Trenches - Gas Chlorination Bldg Trenches - PTP Recharging System Trenches - Or wherever it is required for the whole Project World Quality Fiberglass Factory P.O.Box. 3137, Al-Khobar 31952 KSA 23/May/12 DS-C-0133 DF-EF-L-0265 C 23/Jul/12 This Material is not specified in the project speci. The reference given at MAR application is irrelevant to FRP-material vol-8 158 AS-DS-L-364 MT X 1 5/26/2012 Tiles Sample Board for Walls & Floors This material to be used for Toilets Area in all Bldgs such as Switchgear Buildings for MSF Area, Sea Water Intake Switchgear Building, Switchgear Building for Post Treatment, Electro Chlorination Building & Gas Chlorination Building. Saudi Ceramics Co. Ltd P.O Box. 3893 Riyadh 11481 KSA 26/May/12 Submitted as a sample board- Size (200x200mm) vol-8 159 AS-DF-T-0171 AS-DS-L-365 DS-C-0113 MT X 1 5/28/2012 Terrazzo Tiles (300x300x30) This material to be used as Terrazzo Tile in Control Pannel Room in Electro Chlorination Building New Century Est. Branch, Near Dallah Driving School, Industrial Area, Dammam, KSA 28/May/12 Attached Technical Datasheet & Test Result vol-9 160 AS-DS-L-366 MT X 1 5/28/2012 Roof Water Proofing System This material to be used as Roof Waterproofing System in all Bldgs such as Switchgear Buildings for MSF Area, Sea Water Intake Switchgear Building, Switchgear Building for Post Treatment, Electro Chlorination Building & Gas Chlorination Building. BITUMAT Co.Ltd P.O BOX 7487 Dammam 31463 28/May/12 MAD submitted in one Document vol-9 161 AS-DS-L-367 MT X 1 5/28/2012 Penguard FC (Saffron Yellow) This material to be used for Doors in all Bldgs such as Switchgear Buildings for MSF Area, Sea Water Intake Switchgear Building, Switchgear Building for Post Treatment, Electro Chlorination Building & Gas Chlorination Building. Jotun Saudi Co. Ltd P.O.Box 4906 Dammam 31412, KSA 28/May/12 Submitted as a sample board- RAL no.1017 Vol-9 162 AS-DS-L-368 MT X 1 5/28/2012 Fenomastic Semigloss & High Gloss (Enamel) For Internal Paint-Plastered Walls & Concrete Walls in all Bldgs. Jotun Saudi Co. Ltd P.O.Box 4906 Dammam 31412, KSA 28/May/12 Submitted as a sample board- RAL no.9002 Vol-9 163 AS-DS-L-370 MT X 1 5/28/2012 Oil Paint-(Black) For Skirting wherever applicable in all Bldgs. Jotun Saudi Co. Ltd P.O.Box 4906 Dammam 31412, KSA 28/May/12 Submitted as a sample board- RAL no.9011 vol-9 164 AS-DS-L-371 MT X 1 5/28/2012 Pilot II- (Oyster White) For Rain Water Down Pipes in all Bldg. Jotun Saudi Co. Ltd P.O.Box 4906 Dammam 31412, KSA 28/May/12 Submitted as a sample board- RAL no.1013 Vol-9 165 AS-DS-L-372 MT X 1 5/28/2012 Tiles Sample Board for Walls & Floors for Battery Rooms For Battery Rooms in all Bldgs. Saudi Ceramics Co. Ltd P.O Box. 3893 Riyadh 11481 KSA 28/May/12 Submitted as a sample board Vol-9 166 AS-DF-T-0172 AS-DS-L-373 DS-C-0114 MT 5/29/2012 Fenomastic Enamel High Gloss This material is to be used for Cement Plastered Walls, Concrete Walls & Exposed Concrete Ceilings in all Bldg. Jotun Saudi Co. Ltd P.O.Box 4906 Dammam 31412, KSA 29/May/12 DS-C-0136 DF-EF-L-0269 B 23/Jul/12 Contractor to use Fenomastic Enamel Semigloss Jotun Paint for Internal plastered & concrete walls with Jotun Code no. # 0567 as agreed in the MOM last 26-6-12 & High gloss not accepted Vol-9 Page 55 of 75 No.of Sample File Location Sample Doosan Recd RAS AL KHAIR DESALINATION PLANT PHASE 1 PACKAGE "D" MATERIAL SUBMITTAL STATUS REPORT DATE COVERED : As of 25 August ,2012 S.N. DOOSAN Name of Suppliers Place of Application / Location ASSAD SAID ASC Transmittal no. Date of Submit Description of Material Doosan Heavy Industries & Construction. Assad Said For Contracting Co.,Ltd. 167 AS-DS-L-374 X 1 5/29/2012 Tiles Sample Board for Walls & Floors This material to be used for Toilets Area in all Bldgs such as Switchgear Buildings for MSF Area, Sea Water Intake Switchgear Building, Switchgear Building for Post Treatment, Electro Chlorination Building & Gas Chlorination Building. Saudi Ceramics Co. Ltd P.O Box. 3893 Riyadh 11481 KSA 29/May/12 Submitted as a sample board- Option -2 (200x200mm) Vol-9 168 AS-DS-L-374 X 1 5/29/2012 Polyguard 85 MC (Light Blue) This material is to be used for steel structural in all bldg. Jotun Saudi Co. Ltd P.O.Box 4906 Dammam 31412, KSA 29/May/12 Submitted as a sample board- RAL no.5012 Vol-9 169 AS-DS-L-376 X 1 5/29/2012 Pilot II- with LC This Material is to be used for Hand Rail of Staircases in all bldg. Jotun Saudi Co. Ltd P.O.Box 4906 Dammam 31412, KSA 29/May/12 Submitted as a sample board- RAL no.1018 Vol-9 170 AS-DF-T-165 AS-DS-L-353 DS-C-0107 MT 5/17/2012 Fenomastic Enamel Semigloss This material to be used for fully cured Cement Plastered Walls, Cielings, Concrete, Gypsum board Partitions, GRC works etc Prior to Paint application in the Buildings &wherever it is required for the whole Project Jotun Saudi Co. Ltd P.O.Box 4906 Dammam 31412, KSA 17/May/12 DS-C-0127 DF-EF-L-0257 B 23/Jul/12 Material Approved as per DSC/Poyry/SWCC material review last 26-6-12, to be use interior plastered wall & concrete surfaces with jotun paint color code #0567 Vol-9 171 AS-DF-T-173 AS-DS-L-0377 DS-C-0115 MT X 2 6/2/2012 PRIMER- D41, ASAD- REINFORCED MEMBRANES (SELF ADHESIVE)-ASAD- 1.6G & MEMBRANE SHIELD-MS-30 (BITUMINOUS PROTECTION BOARDS) as an alternative and second option for all underground Concrete Structures of Waterproofing/Tanking System & wherever it is required for whole project. Awazel Co.Ltd. 2/Jun/12 Vol-9 172 AS-DF-T-0174 AS-DS-L-378 DS-C-0116 MT X 2 6/2/2012 NOISE SUPPRESSION PROFILE-EPDM. RUBBER & PIPE STRAP-TWO HOLE/ U- CLIP STAINLESS STEEL This materials is to be used for Clamping of 75mm dia. PVC pipe in BRP,BBDP & DP Pits & wherever it is required for whole project. Unitech for Building & Construction Material 2/Jun/12 Vol-9 173 AS-DF-T-0175 AS-DS-L-380 DS-C-0117 MT X 1 6/2/2012 Dual-Clip Anchor NST This materials is to be used for Clamping of 75mm dia. PVC pipe in BRP,BBDP & DP Pits & wherever it is required for whole project. AI-Monathem Industrial Tools Co. P.O.Box.118797, Jeddah KSA 2/Jun/12 Vol-9 174 AS-DS-L-387 X 6/3/2012 Nitocote EPU-for External Paint of All Bldg.-Concrete Surfaces Used for External Walls- in all Bldg. Fosam Co. Ltd.P.O.11081 Jeddah 21453 3/Jun/12 Submitted as a sample board- RAL no.1001 175 AS-DF-T-0176 AS-DS-L-381 DS-C-118 MT 6/4/2012 HDPE Pipe-Dia. 100mm,150mm&500mm This material is to be used for Drainage System & wherever it is required for whole project. Al-Jubail Sanitary Pipe Factory P.O.Box 10177, Al-Jubail, Al-Sinayah 31961 KSA 4/Jun/12 Vol-9 176 AS-DF-T-0177 AS-DS-L-382 DS-C-119 MT 6/4/2012 HDPE Pipe-Dia. 100mm,150mm&500mm This material is to be used for Drainage System & wherever it is required for whole project. New Product Industries Co. Ltd. P.O.Box 460, Jeddah 21411, KSA 4/Jun/12 Vol-9 177 AS-DS-L-390 MT X 3 6/4/2012 Hollow Metal Doors The doors to be installed in all Bldgs such as Switchgear Buildings for MSF Area, Sea Water Intake Switchgear Building, Switchgear Building for Post Treatment, Electro Chlorination Building & Gas Chlorination Building & Wherever it is required. Al-Manashy Doors Manufacturer Al- Khozama Dist/Exit 1 P.O.Box.71021 Al- Diriyah 11587 KSA 4/Jun/12 Submitted Sample Only 178 AS-DF-T-180 AS-DS-L-391 DS-C-0120 MT X 2 6/6/2012 Steel Rain Water Down Pipe This material is to be used for Rain Water Down Pipe in all Bldg. Modern Industries Est. Modinest, Jarir Street, Riyadh-KSA 6/Jun/12 Vol-9 179 AS-DF-T-0183 AS-DS-L-0397 DS-C-0122 MT X 1 6/11/2012 Roof Water Proofing System This material to be used in Roof Waterproofing System in all Bldgs such as Switchgear Buildings for MSF Area, Sea Water Intake Switchgear Building, Switchgear Building for Post Treatment, Electro Chlorination Building & Gas Chlorination Building. ISAM KABBANI & Partner for Building & Const Material Co.P.O.6897 Damman KSA 11/Jun/12 Vol-9 180 AS-DF-T-0185 AS-DS-L-0399 DS-C-0123 MT 6/11/2012 Aluminum Flashing This material to be used in Roof Waterproofing System in all Bldgs such as Switchgear Buildings for MSF Area, Sea Water Intake Switchgear Building, Switchgear Building for Post Treatment, Electro Chlorination Building & Gas Chlorination Building. ISAM KABBANI & Partner for Building & Const Material Co.P.O.6897 Damman KSA 11/Jun/12 Vol-9 181 AS-DF-T-0181 AS-DS-L-0393 DS-C-121 MT X 3 6/12/2012 Terrazzo Tiles (250x250x25mm) This material to be used as Terrazzo Tile in Control Pannel Room in Electro Chlorination Building New Century Est. Branch, Near Dallah Driving School, Industrial Area, Dammam, KSA 12/Jun/12 Vol-9 182 AS-DF-T-0186 AS-DS-L-0400 DS-C-0124 MT 6/13/2012 Penguard Primer, Penguard HB & Hardtop AS This material is to be used for Steel structure & wherever it is required in the whole project. Jotun Saudi Co. Ltd P.O.Box 4906 Dammam 31412, KSA 14/Jun/12 Vol-9 Page 56 of 75 No.of Sample File Location Sample Doosan Recd RAS AL KHAIR DESALINATION PLANT PHASE 1 PACKAGE "D" MATERIAL SUBMITTAL STATUS REPORT DATE COVERED : As of 25 August ,2012 S.N. DOOSAN Name of Suppliers Place of Application / Location ASSAD SAID ASC Transmittal no. Date of Submit Description of Material Doosan Heavy Industries & Construction. Assad Said For Contracting Co.,Ltd. 183 AS-DF-T-0187 AS-DS-L-0402 DS-C-0125 MT 6/17/2012 Roof Water Proofing System This material to be applied to all Bldgs such as Switchgear Buildings for MSF Area, Sea Water Intake Switchgear Building, Switchgear Building for Post Treatment, Electro Chlorination Building & Gas Chlorination Building. Refer to the attchedment 17/Jun/12 Attached: Appendix 1 & 2 Vol-9 184 AS-DS-L-0403 X 6/18/2012 Fenomastic Semigloss (Emulsion)- Sample Board This Material Used for Concrete Ceiling in all Bldgs. Jotun Saudi Co. Ltd P.O.Box 4906 Dammam 31412, KSA 18/Jun/12 RAL-9010,9918&1453 185 AS-DS-L-0404 X 6/18/2012 Fenomastic Semigloss (Emulsion)- Sample Board This Material Used for Exterior Plastered Walls in all Bldgs. Jotun Saudi Co. Ltd P.O.Box 4906 Dammam 31412, KSA 18/Jun/12 RAL-002,0118&1063 186 AS-DS-L-0407 X 6/20/2012 Fenomastic Semigloss (Enamel)-Sample Board This Material Used for Interior Walls- Plastered & Concrete Surfaces in all Bldgs. Jotun Saudi Co. Ltd P.O.Box 4906 Dammam 31412, KSA 20/Jun/12 Jotun # 0567, RAL no. # 7035 & 7047 Red Folder 187 AS-DF-T-0188 AS-DS-L-0413 DS-C-0126 MT 6/25/2012 Acid/Alkali Resistant Ceramic Tile for Floors & Walls (15X15) This material is to be used for Battery Room in SWGR bldgs for MSF area, SWGR Bldg for Post Treatment, SWGR Bldg for SWI, for Electrolyzer Room in Electro Chlorination Bldg & Flooring of Chemical Storage Bldg. Saudi Ceramics Co. Ltd P.O Box. 3893 Riyadh 11481 KSA 25/Jun/12 Vol-9 188 AS-DS-L-0416 X 1 6/26/2012 Sample Board for Nitocote EPU-Epoxy Paint for External Exposed Concrete Surfaces All Bldgs. This material is to be used for External Exposed Concrete Surfaces in all Bldgs. FOSAM Co. Ltd.P.O.11081 Jeddah 21453 26/Jun/12 RAL NO.-1013,1014&1015 189 AS-DS-L-0419 7/2/2012 Test results of Batching Plant Aggregates (3/4", 3/8", 3/16" & Sand) Assad Said Contracting co, Ltd Saudi 2/Jul/12 Test Results of BP for the Month of April 2012 190 AS-DS-L-0420 X 2 7/4/2012 Submission of Ceramic Tiles Sample This Material is to be in Battery, Offices Rooms & Toilet Saudi Ceramics Co. Ltd P.O Box. 3893 Riyadh 11481 KSA 4/Jul/12 Annex 1 191 AS-DS-L-0421 X 1 7/4/2012 Sample Board for Nitocote EPU-Epoxy Paint for Floor This material is to be used for Flooring in Electro Bldg. & Chemcal Storage Bldg. FOSAM Co. Ltd.P.O.11081 Jeddah 21453 4/Jul/12 RAL No # 7032 192 AS-DF-T-0189 AS-DS-L-0424 DS-C-0127 MT 7/5/2012 Nitocote EPU-Chemical/Acid Resistant Paint This material is to be used in place of Chemical & Acid Resistant Paint in all Bldgs. & all the exposed concrete in the whole project FOSAM Co. Ltd.P.O.11081 Jeddah 21453 5/Jul/12 Attached:Clarification for Nitocote EPU from Fosam 193 AS-DF-T-0193 AS-DS-L-0432 DS-C-0128 MT 7/11/2012 Hempadur 15553, Hempadur Mastic 45881 & Hempathane Topcoat 55210 This material is to be used for Steel structure & wherever it is required in the whole project. Hempel Paints Co. Ltd. P.O Box.6783,Jeddah 21415 11/Jul/12 Vol-9 194 AS-DS-L-0435 7/18/2012 Test results of Batching Plant Aggregates (3/4", 3/8", 3/16" & Sand) Assad Said Contracting co, Ltd Saudi 18/Jul/12 Test Results of BP for the Month of May 2012 195 AS-DF-T-195 AS-DS-L-438 DS-C-0129 MT X 7/22/2012 Aluminum Windows The Windows to be installed in all Bldgs such as Switchgear Buildings for MSF Area, Sea Water Intake Switchgear Building, Switchgear Building for Post Treatment, Electro Chlorination Building & Gas Chlorination Building. Future Aluminum Factory Riyadh, Industrial Area Ext 11 22/Jul/12 Vol-9 196 AS-DF-T-196 AS-DS-L-439 DS-C-0130 MT X 1 7/23/2012 Suspended Ceiling System- Ceramaguard TheMaterial is to be used as Suspended Ceiling in Corridor & Office in the Bldgs. such as Switchgear Buildings for MSF Area, Sea Water Intake Switchgear Building, Switchgear Building for Post Treatment, Electro Chlorination Building & Gas Chlorination Building. Technical Trading Factory Co.Ltd P.o Box.1915 Riyadh 11372 23/Jul/12 Vol-10 197 AS-DF-T-198 AS-DS-L-442 DS-C-0103 MT 1 X 1 7/23/2012 Concrete Tiles (400x400x40) for Roof Waterproofing System This material to be used as Concrete Tiles in Roof Waterproofing System in all Bldgs such as Switchgear Buildings for MSF Area, Sea Water Intake Switchgear Building, Switchgear Building for Post Treatment, Electro Chlorination Building & Gas Chlorination Building. New Century Est. Branch, Near Dallah Driving School, Industrial Area, Dammam, KSA 23/Jul/12 Vol-10 198 AS-DF-T-197 AS-DS-L-443 DS-C-0131 MT X 3 7/23/2012 Suspended Aluminum Ceiling-Nortile TheMaterial is to be used as Suspended Aluminum Ceiling in Toilets in the Bldgs. such as Switchgear Buildings for MSF Area, Sea Water Intake Switchgear Building, Switchgear Building for Post Treatment, Electro Chlorination Building & Gas Chlorination Building. Technical Trading Factory Co.Ltd P.o Box.1915 Riyadh 11372 23/Jul/12 Vol-10 199 AS-DF-T-199 AS-DS-L-0446 DS-C-0132 MT X 1 26/Jul/12 Aluminum Strip Ceiling System This material is to be used in Toilets in all Bldgs. except Gas Chlorination Bldg Building Material House est. for Trading P.O.Box.23628 Riyadh:11436 26/Jul/12 Vol-10 Page 57 of 75 No.of Sample File Location Sample Doosan Recd RAS AL KHAIR DESALINATION PLANT PHASE 1 PACKAGE "D" MATERIAL SUBMITTAL STATUS REPORT DATE COVERED : As of 25 August ,2012 S.N. DOOSAN Name of Suppliers Place of Application / Location ASSAD SAID ASC Transmittal no. Date of Submit Description of Material Doosan Heavy Industries & Construction. Assad Said For Contracting Co.,Ltd. 200 AS-DS-L-0445 28/Jul/12 Assad Said for Structural Steel Fabrication Procedure & Quality Manual Assad Said Contracting co. Ltd Saudi 28/Jul/12 201 AS-DF-T-200 AS-DS-L-0448 DS-C-0133 MT 1/Aug/12 Nitoseal PU40 This Material is to be used for sealing external & internal joints in concrete, blockwork, brickwork, perimeter sealing around doors and windows in the Bldgs. such as Switchgear Buildings for MSF Area, Sea Water Intake Switchgear Building, Switchgear Building for Post Treatment & Electro Chlorination Building. Fosam Co. Ltd.P.O.11081 Jeddah 21453 1/Aug/12 Vol-10 202 AS-DS-L-450 8/6/2012 Test results of Batching Plant Aggregates (3/4", 3/8", 3/16" & Sand) Assad Said Contracting co, Ltd Saudi 6/Aug/12 Test Results of BP for the Month of June 2012 Page 58 of 75 NO.S ( S a t )
2 7 - J u l 1 7 7 7 7 7 7 7 2 1 1 1 1 1 1 1 3 1 1 1 1 1 1 1 4 2 2 2 2 2 2 2 5 2 1 1 1 1 1 1 6 13 12 12 12 11 11 12 7 3 3 3 3 3 3 3 8 1 1 1 1 1 1 1 9 5 5 5 5 5 5 5 10 7 7 7 7 7 7 7 11 6 6 6 5 5 5 5 12 6 6 6 6 6 6 6 13 1 1 1 1 1 1 1 14 6 6 6 6 6 6 6 15 1 1 1 1 1 1 1 16 1 1 1 1 1 1 1 17 1 1 1 1 1 1 1 18 5 4 4 4 4 3 4 19 2 2 2 2 2 2 2 20 2 1 2 1 1 1 2 21 4 4 4 4 4 4 4 22 2 2 2 2 2 2 2 23 3 3 3 3 3 3 3 24 2 2 2 2 2 2 2 25 8 8 8 7 7 7 7 26 1 1 1 1 1 1 1 27 1 1 1 1 1 1 1 28 5 5 5 5 5 5 5 29 1 1 1 1 1 1 1 30 2 2 2 3 3 2 2 31 2 2 2 2 2 2 2 32 7 7 7 7 7 7 7 33 4 4 4 4 4 4 4 34 7 7 7 7 7 7 7 35 1 1 1 1 1 1 1 36 9 9 9 9 9 9 9 37 9 9 9 9 9 9 9 38 2 2 2 2 2 2 2 Tower Lights GENERAL ITEMS FOR SITE Batching Mixer Machine ( 3 cu. Meter ) Storage Water Tank ( Big ) Storage Water Tank ( Small ) Bench Saw Small Generator ( Site ) Dyna Trailer Highbeds Service Pick-up ( Double Cabin ) Service Pick-up ( Single Cabin ) Staff Mini Bus Labor Bus Ambulance Engineer's Service POWER GENERATION Big Generator ( Batching Plant ) Big Generator ( Camp & Workshop ) Concrete Pump Water Tanker Backhoe Loader ( JCB ) Dewatering Pump by Sub-Con LIFTING EQUIPTMENTS Mobile Crane ( 20 Tons ) Mobile Crane ( 75 Tons ) Mobile Crane ( 70 Tons ) Mobile Crane ( 25 Tons ) Potable Water Tanker Waste Water Tanker Concrete Mixer Trailer Dumptrucks BACKFILLING & EXCAVATION Excavator ( Normal Arm ) Excavator ( Long Arm ) Grader Roller ( 10 Tons ) Roller ( 3 tons ) + Hand Roller Plate Compactor and Jumper Compactor Skid Loader ( Bobcat ) Forklift Loaders Dumptrucks Week No. 74 RAS AL KHAIR DESALINATION PLANT PHASE 1 PACKAGE "D" WEEKLY EQUIPMENT UTILIZATION REPORT FOR CIVIL & BUILDING WORKS DATE COVERED : WEEK NO. 74 ( 21-26 JULY, 2012) TRADE/POSITION Doosan Heavy Industries & Construction. Assad Said For Contracting Co.,Ltd. Prepared By : ENGR. ARIES HERNANDEZ Office Engineer Verified by: ENGR. ROGER BETANIA Chief-Office-Engineer Approved by: ENGR . SHAIK SHAFIULLA Project Manager Page 61 of 75 NO.S Number of Units Mobilized ( S a t )
2 1 - J u l ( S u n )
2 2 - J u l ( M o n )
2 3 - J u l ( T u e )
2 4 - J u l ( W e d )
2 5 - J u l ( T h u )
2 6 - J u l ( F r i )
2 7 - J u l Week No. 74 RAS AL KHAIR DESALINATION PLANT PHASE 1 PACKAGE "D" WEEKLY EQUIPMENT UTILIZATION REPORT FOR CIVIL & BUILDING WORKS DATE COVERED : WEEK NO. 74 ( 21-26 JULY, 2012) TRADE/POSITION Doosan Heavy Industries & Construction. Assad Said For Contracting Co.,Ltd. 39 3 3 3 3 3 3 3 40 3 2 2 2 2 2 2 41 2 2 2 2 2 2 2 42 6 6 6 6 6 6 6 43 1 1 1 1 1 1 1 44 6 6 6 6 6 6 6 45 2 2 2 2 2 2 2 46 4 4 4 4 4 4 4 47 1 1 1 1 1 1 1 48 2 2 2 2 2 2 2 49 3 3 3 3 3 3 3 176 171 172 170 169 167 170 Under Repair / Not working; 5 3 5 6 8 5 TOTAL : Grout Mixer Air Compressor Block Cutting Machine Mechanical Trowel Diesel Water Pump Vibrators Bar Bending Machine Bar Cutting Machine Welding Machine Generator Welding Machine Mini Diesel Tanker Prepared By : ENGR. ARIES HERNANDEZ Office Engineer Verified by: ENGR. ROGER BETANIA Chief-Office-Engineer Approved by: ENGR . SHAIK SHAFIULLA Project Manager FRI 27 (Morning) FRI 27 (Night) SAT 28 (Morning) SAT 28 (Night) SUN 29 (Morning) SUN 29 (Night) MON 30 (Morning) MON 30 (Night) TUES 31 (Morning) TUES 31 (Night) WED 1 (Morning) WED 1 (Night) THU 2 (Morning) THU 2 (Night) CLEAR CLEAR CLEAR CLEAR CLEAR CLEAR CLEAR CLEAR CLEAR CLEAR CLEAR CLEAR CLEAR CLEAR ------ -------- ------ -------- ------ -------- ------ -------- ------ -------- ------ -------- ------ -------- ------ -------- ------ -------- ------ -------- ------ -------- ------ -------- ------ -------- ------ -------- 41 41 42 42 42 42 43 44 44 45 43 42 46 46 40 40 39 39 41 41 41 43 42 45 42 38 46 39 40 40 39 39 41 41 41 43 42 45 42 38 46 39 5550 5550 5450 5550 5600 5700 5850 5950 6000 6050 6100 6200 6150 6150 5:05 -------- 5:05 -------- 5:05 -------- 5:05 -------- 5:07 -------- 5:07 -------- 5:07 -------- ------ 18:39 ------ 18:39 ------ 18:38 ------ 18:37 ------ 18:37 ------ 18:37 ------ 18:36 WEATHER FORECAST SUMMARY : Most Dry , Warm ( Max 46 C on Thursday Morning , Min. 38 C on Wednesday Night, wind will be generally light ) Min. Temp ( C ) Wind Chill ( C ) Freezing Level ( m ) Sunset Sunrise Rain ( mm ) Snow ( cm ) Max. Temp ( C ) JULY AUGUST Wind ( km/h ) Summary CIVIL & BUILDING WORKS RAS AL KHAIR DESALINATION PLANT PHASE 1 PACKAGE "D" WEATHER FORECAST CONDITION Period Covered : WEEK NO. 74 ( 21-26 JULY, 2012 ) Doosan Heavy Industries & Construction. Assad Said For Contracting Co.,Ltd. WEEK NO. 74 ( JULY 21 2012 - JULY 26,2012 ) 5. PHOTOS RAS AL KHAIR DESALINATION PLANT PHASE 1 PACKAGE "D" CIVIL & BUILDING WORKS Doosan Heavy Industries & Construction. Assad Said For Contracting Co.,Ltd. Page 64 of 75 RAS AL KHAIR DESALINATION PLANT PHASE 1 PACKAGE "D" PHOTOS CIVIL WORKS DATE COVERED :WEEK NO. 74 ( 21-26 JULY,2012 ) Doosan Heavy Industries & Construction. Assad Said For Contracting Co.,Ltd. PIPE PROTECTION SLAB ( SOUTH WEST OF ELECTRO CHLORINATION BUILDING ) TRENCH # 1 DB 05 BETWEEN CP141 & CP142 DB 11-2 BETWEEN CP214 & CP215 CP 57 & CP58 CP 75 , CP76 & CP77 Page 65 of 75 CABLE ROUTE RAS AL KHAIR DESALINATION PLANT PHASE 1 PACKAGE "D" PHOTOS CIVIL WORKS DATE COVERED :WEEK NO. 74 ( 21-26 JULY,2012 ) Doosan Heavy Industries & Construction. Assad Said For Contracting Co.,Ltd. CP 05 CP 02 DB09-4 BET. CP60 & CP156 DB10-5 BET. CP 156 & CP178 CP 219 & CP221 CP 190 & CP191 CONCRETE PIT FOR STATIC MIXER CP 09 & CP10 Page 66 of 75 UNDERGOUND PIPES ( GRP ) 2. B3 columns - Rebar works BRINE HEATER FLATFORM FOUNDATION UNI# 76 1. Flatform F5, F6, F7, F8 & F9 - For bituminous paint DEAERATOR UNIT # 78 1. A1 BASE SLAB - Rebar works RAS AL KHAIR DESALINATION PLANT PHASE 1 PACKAGE "D" PHOTOS CIVIL WORKS DATE COVERED :WEEK NO. 74 ( 21-26 JULY,2012 ) Doosan Heavy Industries & Construction. Assad Said For Contracting Co.,Ltd. Evaporator unit 71 West side.
Ordinary soil, backfilling Evaporator unit 73 East side ,
surface preparation Evaporator unit 76-77 North side
SC1 backfilling around pipes Page 67 of 75 DEAERATOR UNIT # 77 1. Wall - formworks PUMP PIT D-1 STORM DRAINAGE - Base slab, casted - wall rebars DEAERATOR UNIT # 76 1. BRP 1 - formworks & alignmment RAS AL KHAIR DESALINATION PLANT PHASE 1 PACKAGE "D" PHOTOS CIVIL WORKS DATE COVERED :WEEK NO. 74 ( 21-26 JULY,2012 ) Doosan Heavy Industries & Construction. Assad Said For Contracting Co.,Ltd. Page 68 of 75 EVAPORATOR UNIT # 74 ( CABLE ROUTE ) 1. CP-85 - Surface preparation DEAERATOR UNIT # 75 - formworks EVAPORATOR UNIT # 74 ( MISCELLANEOUS FOUNDATION ) 1. F12-1, F12( 2 Nos. ), SF1, SF2, F3, BCP & BCSF - Lean concrete already casted EVAPORATOR UNIT # 73 ( MISCELLANEOUS FOUNDATION ) 1. F4 Foundation - waterproofingmembrane RAS AL KHAIR DESALINATION PLANT PHASE 1 PACKAGE "D" PHOTOS CIVIL WORKS DATE COVERED :WEEK NO. 74 ( 21-26 JULY,2012 ) Doosan Heavy Industries & Construction. Assad Said For Contracting Co.,Ltd. Page 69 of 75 - formworks - some are casted already - Waterproofing membrane & protection board , balance CABLE ROUTE ( NEAR EVAP. UNIT # 71 ) 1. DB-07 Between CP47 & CP48 2. DB-04 Between CP46 & CP 47 EVAPORATOR between UNIT # 71 & UNIT # 72 1. PIPE STEAM & AUX. FOUNDATION - surface preparation EVAPORATOR UNIT # 72 ( MISCELLANEOUS FOUNDATION ) 1. F4, F3 & F1 - Casted & surface preparation RAS AL KHAIR DESALINATION PLANT PHASE 1 PACKAGE "D" PHOTOS CIVIL WORKS DATE COVERED :WEEK NO. 74 ( 21-26 JULY,2012 ) Doosan Heavy Industries & Construction. Assad Said For Contracting Co.,Ltd. Page 70 of 75 2. Flash Tank Foundation - Curing EVAPORATOR UNIT # 72 1. CEP Foundation ( 2 nos. ) - Formworks EVAPORATOR UNIT # 71 ( MISCELLANEOUS FOUNDATION ) 1. F39 Foundation - surface preparation EVAPORATOR UNIT # 71 ( MISCELLANEOUS FOUNDATION ) 1.Pump Pit Cover - Rebar works - block-outs & form works RAS AL KHAIR DESALINATION PLANT PHASE 1 PACKAGE "D" PHOTOS CIVIL WORKS DATE COVERED :WEEK NO. 74 ( 21-26 JULY,2012 ) Doosan Heavy Industries & Construction. Assad Said For Contracting Co.,Ltd. Page 71 of 75 1. Pipe Rack Type 2 - F2 ( 4 Nos ) Pedestal, Casted 1. CP 52 , CP 53, & CP 54 EVAPORATOR UNIT # 71 ( CABLE PIT ) - Painting EVAPORATOR UNIT # 71 ( MISCELLANEOUS FOUNDATION ) EVAPORATOR UNIT # 71 ( MISCELLANEOUS FOUNDATION ) 1. Vehicle Area Foundation RAS AL KHAIR DESALINATION PLANT PHASE 1 PACKAGE "D" PHOTOS CIVIL WORKS DATE COVERED :WEEK NO. 74 ( 21-26 JULY,2012 ) Doosan Heavy Industries & Construction. Assad Said For Contracting Co.,Ltd. Page 72 of 75 1. Foundations ---- formworks ---- CHB installation & plastering inside building ---- Surface preparation in roof CHEMICAL STORAGE BUILDING ---- rebarworks ---- soil preparation for Lean concrete RAS AL KHAIR DESALINATION PLANT PHASE 1 PACKAGE "D" PHOTOS BUILDING WORKS DATE COVERED :WEEK NO. 74 ( 21-26 JULY,2012 ) ELECTRO-CHLORINATION BUILDING 1. Ground Floor ---- preparation for installation of Hollow Blocks ---- waterproofing membrane , preparation for screed 2. MF5 Outdoor Foundation SEAWATER INTAKE BUILDING Doosan Heavy Industries & Construction. Assad Said For Contracting Co.,Ltd. Page 73 of 75 1. Parapet 1. Roof Beam 1. Ground Floor ---- Kicker already casted ---- reinforcement of column fabricated / erection
RAS AL KHAIR DESALINATION PLANT PHASE 1 PACKAGE "D" PHOTOS BUILDING WORKS DATE COVERED :WEEK NO. 74 ( 21-26 JULY,2012 ) SWITCHEGEAR BUILDING FOR MSF 73-74 --- .Installation of forms , South side & west side --- Surface preparation Finished 2. Basement ( Ceiling, Wall & Floor ) SWITCHEGEAR BUILDING FOR MSF 75-76 ---- Installation of supports & plates, Bottom of Beam already started. ---- Fabrication of sidings for beam & slab SWITCHEGEAR BUILDING FOR MSF 77-78 Doosan Heavy Industries & Construction. Assad Said For Contracting Co.,Ltd. Page 74 of 75 1. Ground Beam 1. Parapet 1. Ceiling & Wall 2. Flooring ----- Surface preparation RAS AL KHAIR DESALINATION PLANT PHASE 1 PACKAGE "D" PHOTOS BUILDING WORKS DATE COVERED :WEEK NO. 74 ( 21-26 JULY,2012 ) GAS CHLORINATION BUILDING ----- South side Casted, East side Balance POST TREATMENT BUILDING ----- Installation of forms ,South side & west side POST TREATMENT BUILDING ( BASEMENT ) ----- Application of first coat Doosan Heavy Industries & Construction. Assad Said For Contracting Co.,Ltd. Page 75 of 75 1. Wall & Ceiling 1. Wall & Ceiling 2. Flooring 1. Wall & Ceiling 2. Flooring SWITCHEGEAR BUILDING FOR MSF 71-72 ( TRANSFORMER FOUNDATION ) ---- ready for screed ---- Preparation for final Coat SWITCHEGEAR BUILDING FOR MSF 71-72 ( OFFICE ROOM ) ---- Final Coat Finished ---- Tiles Installation Finished ---- Application of First Coat SWITCHEGEAR BUILDING FOR MSF 71-72 ( SWITCHGEAR ROOM - NORTH SIDE ) ---- Final Coat Finished ---- First Coat Finished RAS AL KHAIR DESALINATION PLANT PHASE 1 PACKAGE "D" PHOTOS DATE COVERED :WEEK NO. 74 ( 21-26 JULY,2012 ) SWITCHEGEAR BUILDING FOR MSF 71-72 ( SWITCHGEAR ROOM - SOUTH SIDE ) BUILDING WORKS Doosan Heavy Industries & Construction. Assad Said For Contracting Co.,Ltd.