FIJACIN DE PRECIOS DE NUDO

DE CORTO PLAZO
ABRIL DE 2014
SISTEMA INTERCONECTADO
DEL NORTE GRANDE
(SING)

INFORME TCNICO PRELIMINAR












MARZO DE 2014

SANTIAGO CHILE


Informe Tcnico Preliminar Abril 2014 COMISIN NACIONAL DE ENERGA
FONO (56-2) 2797 2612 - FAX (56-2) 2797 2600 CLASIFICADOR 14 - CORREO 21
E-MAIL: pnudo@cne.cl URL: http://www.cne.cl SANTIAGO - CHILE


1
NDICE

1.- INTRODUCCIN ..................................................................................................................... 2
2.- ANTECEDENTES GENERALES ............................................................................................ 2
2.1.- Ventas Mensuales de Energa ............................................................................................ 2
2.2.- Precios de Dlar Observado ............................................................................................... 3
2.3.- Precios de Combustibles ..................................................................................................... 4
3.- PREVISIN DE DEMANDA .................................................................................................... 6
4.- PROGRAMA DE OBRAS EN EL SING................................................................................... 7
5.- NIVEL DE PRECIOS ............................................................................................................... 8
6.- COSTOS VARIABLES DE OPERACIN................................................................................ 8
7.- COSTO DE RACIONAMIENTO ............................................................................................ 10
8.- TASA DE ACTUALIZACIN ................................................................................................. 10
9.- CLCULO DE LOS PRECIOS DE NUDO Y RESULTADOS OBTENIDOS ......................... 10
9.1.- Precio Bsico de la Energa .................................................................................................. 11
9.2.- Precio Bsico de la Potencia de Punta ................................................................................. 12
9.3.- Precios de Energa y Potencia Resto del SING .................................................................... 13
10.- FRMULAS DE INDEXACIN PARA LOS PRECIOS DE NUDO ....................................... 14
10.1.- Precio de la Potencia Punta .......................................................................................... 14
10.2.- Precio de la Energa ...................................................................................................... 15
11.- CARGOS POR ENERGA REACTIVA .................................................................................. 16
12.- CARGO NICO TRONCAL (CU) .......................................................................................... 17
13.- ANEXO N 1: PRECIOS DE COMBUSTIBLES .................................................................... 18
14.- ANEXO N 2: PRECIOS BSICOS DE ENERGA Y POTENCIA DE PUNTA ..................... 20
14.1.- Precio Bsico de Energa .............................................................................................. 20
14.2.- Precio Bsico de la Potencia de Punta ......................................................................... 22
15.- ANEXO N 3: CALIDAD DE SUMINISTRO ........................................................................... 23
15.1.- Simplificaciones Adoptadas .......................................................................................... 23
15.2.- Calidad de Suministro ................................................................................................... 23
16.- ANEXO N 4: BASES METODOLGICAS Y CONCEPTUALES DEL CLCULO
FACTORES DE PENALIZACIN ..................................................................................................... 26
16.1.- Introduccin ................................................................................................................... 26
16.2.- Modelo de Factores de Penalizacin ............................................................................ 26
16.3.- Resultados ..................................................................................................................... 28
17.- ANEXO N 5: PLAN DE OBRAS ........................................................................................... 29
17.1.- Introduccin ................................................................................................................... 29
17.2.- Metodologa ................................................................................................................... 29
17.3.- Proyectos de Generacin .............................................................................................. 30
17.4.- Obras de Transmisin ................................................................................................... 31
17.5.- Escenario de Demanda ................................................................................................. 32
17.6.- Precios de Combustibles ............................................................................................... 32
17.7.- Costos y Criterios de Localizacin de Centrales ........................................................... 32
17.8.- Resultados ..................................................................................................................... 33
18.- ANEXO N 6: ACTUALIZACIN VALOR COSTO DE FALLA DE LARGA DURACIN. ..... 34
18.1.- Introduccin ................................................................................................................... 34
18.2.- Costo de Racionamiento por Sectores SING ................................................................ 34
19.- ANEXO N 7: ALTERNATIVAS DE GENERACIN Y DE TRANSPORTE .......................... 35
20.- ANEXO N 10: OBLIGACIN ERNC. ................................................................................... 36

Informe Tcnico Preliminar Abril 2014 COMISIN NACIONAL DE ENERGA


FONO (56-2) 2797 2612 - FAX (56-2) 2797 2600 CLASIFICADOR 14 - CORREO 21
E-MAIL: pnudo@cne.cl URL: http://www.cne.cl SANTIAGO - CHILE


2
INFORME TCNICO PRELIMINAR
CLCULO DE PRECIOS DE NUDO DE CORTO PLAZO
EN EL SISTEMA INTERCONECTADO DEL NORTE GRANDE (SING)
PARA LA FIJACIN DE PRECIOS DE ABRIL DE 2014

1.- INTRODUCCIN

En el presente informe se explicitan las bases utilizadas y los resultados obtenidos
por la Comisin Nacional de Energa, en adelante la Comisin, en la determinacin
de los precios de nudo de corto plazo del Sistema Interconectado del Norte
Grande, en adelante SING, el cual tiene una potencia instalada igual o superior a
200 MW, efectundose en l distribucin de Servicio Pblico, sujeta a la regulacin
de precios a que se refieren los artculos 147, 155 y siguientes del DFL N4/06.

Debe tenerse presente que este sistema elctrico es abastecido bsicamente por
unidades termoelctricas, no existiendo embalses de regulacin interanual que
establezcan una ligazn entre los costos de produccin de un ao respecto de los
aos siguientes. No obstante lo anterior, y en virtud de que en la presente fijacin
se ha establecido el programa de obras de generacin necesario para los
prximos 10 aos, los costos marginales de energa se han calculado para un
perodo de 48 meses, de acuerdo al artculo 8 y siguientes del Decreto N86, que
Aprueba Reglamento para la Fijacin de Precios de Nudo, en adelante
Reglamento de Precio de Nudo.

Los valores de costos que deban estar expresados a las fechas correspondientes
para esta fijacin y las frmulas de indexacin resultantes de estos valores podrn
variar en el Informe Tcnico Definitivo, as como los resultados finales de Precios
de Nudo.


2.- ANTECEDENTES GENERALES

En relacin a la determinacin de insumos tales como Previsin de Demanda,
Costos de Combustibles, Programa de Obras, y resultados determinados en la
presente fijacin, la Comisin tuvo a la vista los siguientes antecedentes:


2.1.- Ventas Mensuales de Energa

De acuerdo a la informacin hecha llegar a esta Comisin por la Direccin de
Operacin y Peajes del Centro de Despacho Econmico de Carga del Sistema
Interconectado del Norte Grande, en adelante CDEC-SING, en sus Informes
Mensuales, las ventas de electricidad de este sistema han tenido la evolucin que
se muestra a continuacin:

Informe Tcnico Preliminar Abril 2014 COMISIN NACIONAL DE ENERGA
FONO (56-2) 2797 2612 - FAX (56-2) 2797 2600 CLASIFICADOR 14 - CORREO 21
E-MAIL: pnudo@cne.cl URL: http://www.cne.cl SANTIAGO - CHILE


3
GRFICO N 1: VENTAS MENSUALES DE ENERGA DEL SING, LTIMOS 24 MESES




2.2.- Precios de Dlar Observado

La Comisin utiliz como tipo de cambio, el promedio mensual del dlar observado
publicado por el Banco Central. La variacin del dlar observado promedio de
febrero de 2014, utilizado en el presente informe preliminar, respecto del dlar
observado promedio de septiembre de 2013, utilizado en la ltima fijacin de precio
de nudo, es de un 9,9%. En el siguiente grfico se muestra la evolucin del
promedio mensual para el dlar observado de los ltimos 24 meses.




















0,0%
0,5%
1,0%
1,5%
2,0%
2,5%
3,0%
3,5%
4,0%
4,5%
5,0%
0
200
400
600
800
1.000
1.200
1.400
1.600
G
W
h
[GWh] Tasa12meses
Informe Tcnico Preliminar Abril 2014 COMISIN NACIONAL DE ENERGA
FONO (56-2) 2797 2612 - FAX (56-2) 2797 2600 CLASIFICADOR 14 - CORREO 21
E-MAIL: pnudo@cne.cl URL: http://www.cne.cl SANTIAGO - CHILE


4
GRFICO N 2: EVOLUCIN DLAR OBSERVADO LTIMOS 24 MESES, $/US$





2.3.- Precios de Combustibles

Para la elaboracin del presente informe esta Comisin utiliz los precios de
combustibles para las distintas centrales trmicas del SING, contenidos en la
programacin semanal del CDEC-SING enviada el da 14 de febrero de 2014. La
informacin mencionada fue enviada a esta Comisin por la Direccin de Operacin
del CDEC-SING de acuerdo a lo establecido en el artculo N 19 del Reglamento de
Precio de Nudo. Los costos de combustibles y parmetros utilizados para las
centrales trmicas del SING se entregan en el punto 6 de este informe, resumidos
en el Cuadro N 4, en los formatos de modelacin utilizados por esta Comisin.


2.3.1 Referencia de Precios de Diesel

El precio del petrleo West Texas Intermediate (WTI) a nivel internacional, desde
abril de 2009, se ha mantenido por sobre los 50 US$/bbl. El siguiente grfico
entrega la evolucin del precio WTI desde marzo de 2006 a febrero de 2014. La
variacin experimentada entre febrero de 2014 y agosto de 2013 es de un -5,5%.






485,40
486,00
497,09
505,63
491,93
480,99
474,97
475,36
480,57
477,13
472,67
472,34
472,48
472,14
479,58
502,89
504,96
512,59
504,57
500,81
519,25
529,45
537,03
554,41
400,00
420,00
440,00
460,00
480,00
500,00
520,00
540,00
560,00
580,00
T
i
p
o

d
e

C
a
m
b
i
o

[
$
/
U
S
D
]
Informe Tcnico Preliminar Abril 2014 COMISIN NACIONAL DE ENERGA
FONO (56-2) 2797 2612 - FAX (56-2) 2797 2600 CLASIFICADOR 14 - CORREO 21
E-MAIL: pnudo@cne.cl URL: http://www.cne.cl SANTIAGO - CHILE


5
GRFICO N 3: EVOLUCIN PETRLEO WTI



2.3.2 Referencia de Precios del Carbn

Este insumo desde enero de 2010 se ha mantenido sobre 75 US$/Ton, tal como
se aprecia en el grfico siguiente, en el cual se muestran los precios para las
centrales a carbn relevantes del SING.

GRFICO N 4: EVOLUCIN PRECIO CARBN



0,0
10,0
20,0
30,0
40,0
50,0
60,0
70,0
80,0
90,0
100,0
110,0
120,0
130,0
140,0
150,0
U
S
$
/
b
b
l
PerfilCrudoWTI
0
10
20
30
40
50
60
70
80
90
100
110
120
130
140
150
160
170
180
190
200
210
PrecioCarbn(US$/Ton)
U12 NTO1 CTM1 CTTAR
Informe Tcnico Preliminar Abril 2014 COMISIN NACIONAL DE ENERGA
FONO (56-2) 2797 2612 - FAX (56-2) 2797 2600 CLASIFICADOR 14 - CORREO 21
E-MAIL: pnudo@cne.cl URL: http://www.cne.cl SANTIAGO - CHILE


6
3.- PREVISIN DE DEMANDA

En el Cuadro N 1 se presenta la previsin de demanda para el SING.

CUADRO N 1: PREVISIN DE DEMANDA

PROYECCIN DE VENTAS DE ENERGA
Ao Sistema [GWh] Tasa Sistema
2014 16.591 5,9%
2015 17.695 6,7%
2016 18.832 6,4%
2017 20.009 6,3%
2018 21.248 6,2%
2019 22.509 5,9%
2020 23.831 5,9%
2021 25.211 5,8%
2022 26.640 5,7%
2023 28.130 5,6%
2024 29.626 5,3%

Las bases y antecedentes que fundamentan la anterior previsin de demanda, se
encuentran contenidos en el informe ESTUDIO DE PREVISIN DE DEMANDAS
DE ENERGA Y POTENCIA 2013-2023 del Sistema Interconectado del Norte
Grande, fijacin de precios de Nudo octubre 2013
1
, de la Comisin Nacional de
Energa, conforme los artculos 14 y 15 del Reglamento de Precio de Nudo.

La desagregacin geogrfica de la demanda se efectu a partir de la informacin
contenida en las respuestas a las cartas CNE N 07, CNE N 08 y CNE N 09,
todas de fecha 09 de enero de 2014, por parte de las empresas generadoras y
distribuidoras del SING. Las bases de tiempo de las curvas de duracin se
entregan en CUADRO N2:

CUADRO N 2: CURVAS DE DURACIN MENSUAL DE DEMANDA

CURVAS DE DURACIN MENSUAL DE DEMANDA
Duracin Bloque (horas) Total
Mes Bloque 1 Bloque 2 Bloque 3 Bloque 4 Bloque 5
Abril 181 101 162 224 52 720
Mayo 163 121 158 279 23 744
J unio 60 139 139 335 47 720
J ulio 167 110 184 258 25 744
Agosto 163 113 220 221 27 744
Septiembre 41 191 163 275 50 720
Octubre 168 105 236 186 49 744
Noviembre 193 86 229 179 33 720
Diciembre 194 108 209 196 37 744
Enero 26 222 151 272 73 744
Febrero 176 93 223 160 20 672
Marzo 187 111 262 152 32 744


1
Modificada de acuerdo a la evolucin observada durante el presente ao.
Informe Tcnico Preliminar Abril 2014 COMISIN NACIONAL DE ENERGA
FONO (56-2) 2797 2612 - FAX (56-2) 2797 2600 CLASIFICADOR 14 - CORREO 21
E-MAIL: pnudo@cne.cl URL: http://www.cne.cl SANTIAGO - CHILE


7
4.- PROGRAMA DE OBRAS EN EL SING

El presente Programa de Obra de Generacin fue desarrollado tomando en
consideracin los antecedentes y criterios indicados en el Informe Tcnico Anual
Programa de Obras de Generacin y Transmisin en el Sistema Interconectado
Central (SIC) y en el Sistema Interconectado del Norte Grande (SING) vigente de
agosto de 2013, de acuerdo a lo establecido en el artculo 38 del Reglamento de
Precio de Nudo.

Sin perjuicio de lo anterior, esta Comisin actualiz el Programa de Obras
tomando en consideracin los antecedentes proporcionados por aquellas
empresas propietarias de instalaciones que tienen en construccin unidades
generadoras, para los cuales se hayan obtenido los respectivos permisos de
construccin de obras civiles o se haya dado orden de proceder para la fabricacin
y/o instalacin del correspondiente equipamiento elctrico o electromagntico, tal
como se menciona el artculo N 31 del Reglamento de Precio de Nudo.

Las fechas de puesta en operacin para las centrales elctricas en construccin
se establecen segn informacin entregada por sus propietarios.


CUADRO N 3: PROYECTOS DE GENERACIN EN CONSTRUCCIN Y RECOMENDADOS.

Central Estado
Potencia
Neta [MW]
Tecnologa Barra de conexin
Fecha
puesta en
servicio
Costo Unitario
de Inversin
[US$/kW]
Portada En Construccin 3 Diesel La Portada 110 abr-14 -
Arica Solar 1 En Construccin 18 Solar Fotovoltaica Parinacota 066 abr-14 -
La Huayca En Construccin 9 Solar Fotovoltaica Pozo Almonte 066 abr-14 -
Pozo Almonte 3 En Construccin 16 Solar Fotovoltaica Pozo Almonte 066 abr-14 -
Arica Solar 2 En Construccin 22 Solar Fotovoltaica Parinacota 066 may-14 -
La Huayca 2 En Construccin 21 Solar Fotovoltaica Pozo Almonte 066 may-14 -
Mara Elena En Construccin 71 Solar Fotovoltaica Crucero 220 sep-14 -
San Pedro 1 En Construccin 17 Solar Fotovoltaica Calama 110 sep-14 -
San Pedro 3 En Construccin 30 Solar Fotovoltaica Calama 110 sep-14 -
San Pedro 4 En Construccin 30 Solar Fotovoltaica Calama 110 sep-14 -
San Pedro 2 En Construccin 24 Solar Fotovoltaica Calama 110 nov-14 -
Calama Sur En Construccin 30 Solar Fotovoltaica Calama 110 nov-14 -
Quillagua I En Construccin 23 Solar Fotovoltaica Crucero 220 dic-14 -
Quillagua II En Construccin 27 Solar Fotovoltaica Crucero 220 dic-15 -
Cochrane 1 En Construccin 236 Carbn Encuentro 220 may-16 -
Cochrane 2 En Construccin 236 Carbn Encuentro 220 oct-16 -
Kelar En Construccin 517 Gas Natural Atacama 220 oct-16 -
Quillagua III En Construccin 50 Solar Fotovoltaica Crucero 220 dic-16 -
Solar SING I Recomendadas 150 Solar Fotovoltaica Pozo Almonte 220 ene-21 2.500
Elico SING I Recomendadas 50 Elica Laberinto 220 mar-21 2.300
Geotrmica Irruputunco Recomendadas 50 Geotrmica Collahuasi 220 jun-21 3.550
Elico SING II Recomendadas 200 Elica Lagunas 220 jun-22 2.300
Solar SING II Recomendadas 150 Solar Fotovoltaica Lagunas 220 may-23 2.500
Geotrmica Puchuldiza 01 Recomendadas 40 Geotrmica Cerro Colorado 110 oct-23 3.550

En el Anexo N 5 del presente informe se presentan las bases utilizadas para la
elaboracin del plan de obras presentado anteriormente.

Informe Tcnico Preliminar Abril 2014 COMISIN NACIONAL DE ENERGA
FONO (56-2) 2797 2612 - FAX (56-2) 2797 2600 CLASIFICADOR 14 - CORREO 21
E-MAIL: pnudo@cne.cl URL: http://www.cne.cl SANTIAGO - CHILE


8
5.- NIVEL DE PRECIOS

Todos los costos utilizados en los clculos del presente informe, corresponden a
los precios existentes a febrero de 2014, de acuerdo a lo establecido en el artculo
162, nmero siete, del DFL N 4/06.

La tasa de cambio utilizada corresponde al valor promedio del mes de febrero de
2014, del tipo de cambio observado del dlar EEUU, publicado por el Banco
Central (554,41 [$/US$]).

6.- COSTOS VARIABLES DE OPERACIN

Los costos variables de cada unidad, presentados en el cuadro N 3, se han
obtenido de acuerdo a lo establecido en el artculo 162 del DFL N 4/06, utilizando
los valores vigentes a febrero de 2014 para cada uno de ellos.

Para determinar los precios del carbn, de las mezclas carbn-petcoke, de los
combustibles lquidos y del gas natural, puesto en cada central, se consider el
valor informado por la Direccin de Operacin del CDEC-SING segn lo
establecido en el artculo N 19 del Reglamento de Precio de Nudo. En el Anexo
N1 se muestra un cuadro resumen de estos precios.




























Informe Tcnico Preliminar Abril 2014 COMISIN NACIONAL DE ENERGA
FONO (56-2) 2797 2612 - FAX (56-2) 2797 2600 CLASIFICADOR 14 - CORREO 21
E-MAIL: pnudo@cne.cl URL: http://www.cne.cl SANTIAGO - CHILE


9
CUADRO N 4: COSTOS VARIABLES DE OPERACIN
-



-
El precio de combustible utilizado en la modelacin considera la modulacin descrita en el Anexo N1 del
presente ITP, implementada en el archivo CenTerEtaCVar.csv de la base de datos de los archivos OSE 2000.
Potencia Puesta Tasadesalida Tipo Porcentaje Unidades Consumo Unidades Costo C.Var. C.Var.
Propietario Central Unidad Neta en forzada de de deConsumo Especfico Costode de noComb.
[MW] Servicio (%) Combustible Mezcla Especfico Combustible Combustible [US$/MWh] [US$/MWh]
EECSA CAVANCHA CAVA 2,6 1995 2,5% Hidro
ENERNUEVAS MINIHIDROALTOHOSPICIO(PMGD) MHAH 1,1 2010 2,5% Hidro
MINIHIDROELTORON2(PMGD) MHT2 1,1 2010 2,5% Hidro
ECL CHAPIQUIA CHAP 10,1 1967 2,5% Hidro
DIESELARICA GMAR 8,4 1973 4,2% Diesel [m3/MWh] 0,2948 [US$/m3] 834,94 9,20 255,36
M1AR 2,9 1953 2,8% Diesel [m3/MWh] 0,3016 [US$/m3] 834,94 9,20 261,06
M2AR 2,8 1965 10,8% Diesel [m3/MWh] 0,3007 [US$/m3] 834,94 9,20 260,27
DIESELIQUIQUE MIIQ 2,8 1964 2,1% Diesel [m3/MWh] 0,3015 [US$/m3] 825,43 9,90 258,79
SUIQ 4,1 1957 3,0% Diesel [m3/MWh] 0,3260 [US$/m3] 825,43 9,90 278,99
TGIQ 23,6 1978 4,0% Diesel [m3/MWh] 0,3807 [US$/m3] 825,43 1,70 315,94
MAIQ 5,6 1972 7,1% Diesel 24%76% [Ton/MWh] 0,2570 [US$/Ton] 743,12 7,90 198,88
MSIQ 5,9 1985 7,8% Diesel 23%77% [Ton/MWh] 0,2276 [US$/Ton] 740,04 4,70 173,13
TERMOELCTRICAMEJILLONES CTM1 154,9 1995 5,0% Carbn [ton/MWh] 0,4350 [US$/ton] 89,74 2,08 41,11
CTM2 164,0 1998 5,0% Carbn [ton/MWh] 0,4154 [US$/ton] 89,74 2,56 39,84
CTM3GNL 243,2 2000 2,3% GasNatural [MBtu/MWh] 7,1080 [US$/Mbtu] 7,95 4,65 61,18
CTM3d 243,2 2000 2,3% Diesel [m3/MWh] 0,2482 [US$/m3] 830,50 7,21 213,37
DIESELMANTOSBLANCOS MIMB 27,9 2000 7,0% Diesel [m3/MWh] 0,2368 [US$/m3] 994,62 9,00 244,53
TERMOELCTRICATOCOPILLA U12 79,6 1983 6,0% Carbn [ton/MWh] 0,5113 [US$/ton] 85,80 2,97 46,84
U13 79,8 1985 6,0% Carbn [ton/MWh] 0,4887 [US$/ton] 85,80 2,97 44,90
U14 127,7 1975 6,0% Carbn [ton/MWh] 0,4510 [US$/ton] 85,80 2,00 40,69
U15 124,1 1975 6,0% Carbn [ton/MWh] 0,4343 [US$/ton] 85,80 2,00 39,26
TG1 24,6 1970 2,0% Diesel [m3/MWh] 0,3980 [US$/m3] 832,02 0,99 332,13
TG2 24,8 1970 2,0% Diesel [m3/MWh] 0,3980 [US$/m3] 832,02 0,99 332,13
U10 36,0 1993 6,0% FuelOilNro.6 [ton/MWh] 0,2972 [US$/ton] 680,28 1,19 203,39
U11 36,0 2001 6,0% FuelOilNro.6 [ton/MWh] 0,2972 [US$/ton] 680,28 1,19 203,39
TG3GNL 37,2 1993 3,0% GasNatural [MBtu/MWh] 12,3781 [US$/Mbtu] 7,95 0,99 99,43
TG3d 37,2 1975 3,0% Diesel [m3/MWh] 0,3140 [US$/m3] 832,02 0,99 262,24
U16GNL 343,0 1990 3,0% GasNatural [MBtu/MWh] 6,7020 [US$/Mbtu] 7,95 6,37 59,67
U16d 343,0 1990 3,0% Diesel [m3/MWh] 0,1950 [US$/m3] 832,02 85,35 247,59
TAMAYA 100,0 2009 5,0% FuelOilNro.6 [ton/MWh] 0,2249 [US$/ton] 687,27 12,66 167,24
ANDINA CENTRALTRMICAANDINA CTA 152,6 2011 5,0% Carbn [ton/MWh] 0,3971 [US$/ton] 100,88 5,91 45,97
HORNITOS CENTRALTRMICAHORNITOS CTH 153,9 2011 5,0% Carbn [ton/MWh] 0,3863 [US$/ton] 109,29 5,74 47,96
NORGENER TERMOELCTRICANORGENER NTO1 127,4 1995 5,0% Carbn [ton/MWh] 0,4008 [US$/ton] 82,03 1,66 34,54
NTO2 131,9 1997 5,0% Carbn [ton/MWh] 0,3970 [US$/ton] 82,03 1,63 34,20
CELTA TERMOELCTRICATARAPAC CTTAR 148,5 1998 4,1% Carbn [ton/MWh] 0,4460 [US$/ton] 90,08 1,40 41,57
TGTAR 23,7 2000 1,5% Diesel [m3/MWh] 0,3929 [US$/m3] 820,82 0,41 322,94
ENAEX DIESELENAEX CUMMINS 0,7 1996 5,0% Diesel [m3/MWh] 0,3529 [US$/m3] 832,94 14,00 307,98
DEUTZ 2,0 1996 5,0% Diesel [m3/MWh] 0,3882 [US$/m3] 832,94 15,00 338,38
GASATACAMA ATACAMA CC1GNL 325,6 1999 2,3% GasNatural [MBtu/MWh] 7,5029 [US$/Mbtu] 12,82 4,39 100,61
CC1d 325,5 1999 2,3% Diesel [m3/MWh] 0,2152 [US$/m3] 859,49 7,83 192,79
CC2GNL 325,6 2002 2,3% GasNatural [MBtu/MWh] 7,5029 [US$/Mbtu] 12,82 4,39 100,61
CC2d 325,5 2002 0,5% Diesel [m3/MWh] 0,2152 [US$/m3] 859,49 7,83 192,79
AESGENER SALTA CCSALTA 223 2000 2,5% GasNatural [MBtu/MWh] 0,0000 [US$/Mbtu] 2,00 0,35 0,35
CCSALTA 109 2000 2,5% GasNatural [MBtu/MWh] 0,0000 [US$/Mbtu] 2,00 0,54 0,54
ANGAMOS ANGAMOS ANGAMOSI 244 2011 5,0% Carbn [ton/MWh] 0,4190 [US$/ton] 89,48 5,63 43,12
ANGAMOSII 244 2011 5,0% Carbn [ton/MWh] 0,4190 [US$/ton] 89,48 4,22 41,71
INACAL INACAL INACAL 6,6 2009 2,5% FuelOilNro.6 [ton/MWh] 0,2312 [US$/ton] 638,17 9,06 156,63
ENOR DIESELZOFRI ZOFRI_1 0,9 2006 2,5% Diesel [m3/MWh] 0,3376 [US$/m3] 854,37 5,00 293,47
ZOFRI_2 5,2 2006 2,5% Diesel [m3/MWh] 0,3376 [US$/m3] 854,37 2,00 290,47
ZOFRI_3 4,8 2009 2,5% Diesel [m3/MWh] 0,2647 [US$/m3] 854,37 23,03 249,19
Estandartes 1,6 2014 3,5% Diesel [m3/MWh] 0,3364 [US$/m3] 836,12 10,62 291,89
NORACID NORACID NORACID 17 2012 2,5% Calorresidual 0,0000 0,00 0,00 0,00
ONGROUP INGENOVA Ingenova 2,0 2013 7,3% Diesel [m3/MWh] 0,2276 [US$/m3] 740,04 4,70 173,13
ECL ELAGUILA Elguila 2,0 2013 70,0% Solar 1,0000 0,00 6,00 6,00
SOLARPACK POZOALMONTE PozoAlmonte2 7,5 2014 70,0% Solar 1,0000 0,00 6,00 6,00
ENEL VALLEDELOSVIENTOS ValledelosVientos 90,0 2014 70,0% Elica 1,0000 0,00 7,70 7,70
PLANDEOBRAS PLANDEOBRASENCONSTRUCCIN Portada 3,0 abr14 7,3% Diesel [Ton/MWh] 0,2276 [US$/Ton] 740,04 4,70 173,13
AricaSolar1 18,0 abr14 70,0% Solar 1,0000 0,00 6,00 6,00
LaHuayca 9,0 abr14 70,0% Solar 1,0000 0,00 6,00 6,00
QuillaguaI 23,0 dic14 70,0% Solar 1,0000 0,00 6,00 6,00
AricaSolar2 22,0 may14 70,0% Solar 1,0000 0,00 6,00 6,00
LaHuayca2 21,0 may14 70,0% Solar 1,0000 0,00 6,00 6,00
PozoAlmonte3 16,0 abr14 70,0% Solar 1,0000 0,00 6,00 6,00
MaraElena 71,0 sep14 70,0% Solar 1,0000 0,00 6,00 6,00
SanPedro1 17,0 sep14 70,0% Solar 1,0000 0,00 6,00 6,00
SanPedro3 30,0 sep14 70,0% Solar 1,0000 0,00 6,00 6,00
SanPedro4 30,0 sep14 70,0% Solar 1,0000 0,00 6,00 6,00
SanPedro2 24,0 nov14 70,0% Solar 1,0000 0,00 6,00 6,00
CalamaSur 30,0 nov14 70,0% Solar 1,0000 0,00 6,00 6,00
QuillaguaII 27,0 dic15 70,0% Solar 1,0000 0,00 6,00 6,00
Cochrane1 236,0 may16 5,0% Carbn [ton/MWh] 0,4250 [US$/ton] 94,19 6,00 46,03
Cochrane2 236,0 oct16 5,0% Carbn [ton/MWh] 0,4250 [US$/ton] 94,19 6,00 46,03
Kelar 517,0 oct16 3,0% GasNatural [MBtu/MWh] 7,2080 [[US$/Mbtu]] 12,70 3,20 94,77
QuillaguaIII 50,0 dic16 70,0% Solar 1,0000 0,00 6,00 6,00
PLANDEOBRASRECOMENDADAS SolarSINGI 150 ene21 70,0% Solar 1,0000 0,00 6,00 6,00
EOLICOSINGI 50 mar21 70,0% Elica 1,0000 0,00 7,70 7,70
GeotermicaIrruputunco 50 jun21 4,3% Geotrmica 1,0000 0,00 2,00 2,00
EOLICOSINGII 200 jun22 70,0% Elica 1,0000 0,00 7,70 7,70
SolarSINGII 150 may23 70,0% Solar 1,0000 0,00 6,00 6,00
GeotermicaPuchuldiza01 40 ene23 4,3% Geotrmica 1,0000 0,00 2,00 2,00
Informe Tcnico Preliminar Abril 2014 COMISIN NACIONAL DE ENERGA
FONO (56-2) 2797 2612 - FAX (56-2) 2797 2600 CLASIFICADOR 14 - CORREO 21
E-MAIL: pnudo@cne.cl URL: http://www.cne.cl SANTIAGO - CHILE


10
7.- COSTO DE RACIONAMIENTO

En base al Estudio Costo de Falla de Corta y Larga Duracin SIC, SING y SSMM
remitido a los CDEC con carta CNE N 324 de fecha 3 de agosto de 2012 para su
distribucin entre las empresas integrantes, los diferentes valores utilizados segn
los niveles de dficit de suministro y el valor nico representativo del costo de falla
de larga duracin estipulado en el artculo N 30 del Reglamento de Precio de
Nudo, son los siguientes:

CUADRO N 5: COSTO DE FALLA SEGN PROFUNDIDAD DE LA MISMA

Profundidad de Falla US$/MWh
0-5% 404,74
5-10% 451,27
10-20% 671,62
Sobre 20% 862,79


Estos valores se determinan conforme a lo sealado en el ANEXO N 6.

Valor nico representativo, denominado Costo de Racionamiento: 404,74
[US$/MWh]

Este valor nico representativo, se obtiene de calcular un precio de nudo de falla,
definido como la valoracin a costo marginal de falla, de la energa de falla
esperada para todas las barras del sistema, dentro del horizonte de clculo de
precio de nudo.

Este valor nico representa el costo por kilowatthora (224,39 $/kWh), en que
incurriran en promedio, los usuarios al no disponer de energa.

8.- TASA DE ACTUALIZACIN

Se utiliz la tasa de 10% que estipula el artculo N35 del Reglamento de Precio
de Nudo.


9.- CLCULO DE LOS PRECIOS DE NUDO Y RESULTADOS OBTENIDOS

Para determinar los costos marginales de energa se hizo un llenado de la curva
montona de carga utilizando el modelo multinodal OSE2000, el cual permite una
completa modelacin del sistema, en donde cada uno de los componentes se
representa con la profundidad requerida, manteniendo un nivel de detalle acorde
entre las diferentes partes de la modelacin.

Informe Tcnico Preliminar Abril 2014 COMISIN NACIONAL DE ENERGA
FONO (56-2) 2797 2612 - FAX (56-2) 2797 2600 CLASIFICADOR 14 - CORREO 21
E-MAIL: pnudo@cne.cl URL: http://www.cne.cl SANTIAGO - CHILE


11
Sin perjuicio de que los desarrollos de generacin previstos reconocen en sus
costos de inversin elementos de control y regulacin de frecuencia, mantener la
frecuencia del sistema dentro de los lmites establecidos por la reglamentacin
vigente requiere de una operacin coordinada de las unidades de generacin,
destinada a mantener un margen de reserva de potencia en el sistema. Para este
efecto se incorpor en la modelacin una reduccin de 8,5 % de la potencia de las
centrales generadoras del SING que no han sido limitadas por restricciones
operacionales.

De igual forma, las instalaciones previstas contemplan costos en elementos de
compensacin. Sin embargo, los costos implcitos en el plan de obras no permiten
a priori suponer que se pueda prescindir de una operacin coordinada, con objeto
de mantener los rangos de tensin en los lmites aceptados. As, la regulacin de
tensin es efectuada mediante el despacho de una unidad de generacin
destinada a mantener los perfiles de tensin en los rangos nominales. Para este
efecto se incorpor en la modelacin descrita anteriormente la operacin forzada
de una unidad de 4 MW ubicada en la ciudad de Arica considerando un costo de
combustible para esta unidad de 834,94 [US$/m3]. Se determin el costo con la
operacin forzada del sistema y adems se identific el costo de la operacin de la
unidad forzada, incorporndolo como un coeficiente de sobrecosto por el que se
ponder los costos marginales de energa obtenidos de la simulacin, lo que
permite recuperar la diferencia de costos de operacin en el mismo periodo de
clculo de precios de nudo. El perfil de costos marginales mostrados en el cuerpo
de este informe considera este efecto. Dicho coeficiente es:

Frv=1,0032

La utilizacin de este modelo permite la representacin detallada del sistema de
transmisin del SING, adems de la incorporacin de la totalidad de las unidades
generadoras existentes y futuras.


9.1.- Precio Bsico de la Energa

El Precio Bsico de la Energa se calcul en el Nudo Troncal Crucero 220 kV a
partir de la asociacin de consumos aguas abajo de esta barra. Para esto, se
consider los costos marginales esperados y energas mensuales tanto en esta
barra como en las barras de consumo asociadas a esta. En el ANEXO N 2 se
muestra el clculo del precio bsico de la energa.

De esta forma, considerando los primeros 48 meses de operacin del SING,
contados a partir del 1 de abril de 2014, el precio bsico se determina como:

Informe Tcnico Preliminar Abril 2014 COMISIN NACIONAL DE ENERGA
FONO (56-2) 2797 2612 - FAX (56-2) 2797 2600 CLASIFICADOR 14 - CORREO 21
E-MAIL: pnudo@cne.cl URL: http://www.cne.cl SANTIAGO - CHILE


12
Precio Bsico Energa
Nudo Referencia
=

=

=

+
+

48
1
) 1 (
,
48
1
) 1 (
, ,
) 1 (
) 1 (
i
i
i Nref
i
i
i Nref i Nref
r
E
r
E CMg


Donde:
N
ref
: Nudo Troncal definido como Subestacin Bsica de Energa para
el Precio de Nudo Bsico de la Energa, Crucero 220 kV.
CMg
Nref,i
: Costo Marginal Mensual en el mes i en la Subestacin Bsica de
Energa.
E
Nref,i
: Energa Mensual en el mes i asociada a la Subestacin Bsica de
Energa.
i : mes i-simo.
r : Tasa de descuento mensual, equivalente a 10% anual.


El Precio Bsico de la Energa es de 47,708 [$/kWh] para el Nudo Bsico de
referencia. En este clculo se ha considerado una operacin que recoge
exigencias de calidad de servicio establecidas en la normativa vigente, en lo
relativo a regulacin de frecuencia y tensin, cuyos aspectos generales se
describen en ANEXO N 3.

En el ANEXO N 4 se entrega la informacin necesaria para determinar los precios
de nudo en las barras troncales del sistema.


9.2.- Precio Bsico de la Potencia de Punta

El Precio Bsico de la Potencia de Punta se obtuvo a partir del costo de ampliar la
capacidad instalada mediante turbinas a diesel de tamao y caractersticas
adecuadas al SING. Conforme a lo establecido en el artculo 162, N 3 DFL
N4/2006, el precio bsico de la potencia de punta resulta igual a 4.805,18
[$/kW/mes] en el nudo Lagunas 220 kV, por ser el nudo del sistema de
Transmisin Troncal en donde se necesita incrementar la capacidad de generacin
para el horizonte de evaluacin pertinente, de acuerdo a los clculos que se
detallan en el ANEXO N 2.








Informe Tcnico Preliminar Abril 2014 COMISIN NACIONAL DE ENERGA
FONO (56-2) 2797 2612 - FAX (56-2) 2797 2600 CLASIFICADOR 14 - CORREO 21
E-MAIL: pnudo@cne.cl URL: http://www.cne.cl SANTIAGO - CHILE


13
9.3.- Precios de Energa y Potencia Resto del SING

9.3.1 Precios de Energa en el Resto del SING

Los precios de energa en los restantes nudos troncales del sistema de
transmisin se determinan aplicando la expresin sealada en el punto 9.1, los
cuales incorporan las exigencias de calidad de servicio correspondientes, que se
describen en el ANEXO N 3: CALIDAD DE SUMINISTRO.

Los Factores de Penalizacin de Energa resultan de referir los precios
determinados en el resto de las subestaciones principales del SING respecto del
nudo de referencia Crucero 220 kV. La determinacin de los precios mencionados
entre otros factores considera las prdidas marginales y saturaciones del sistema
de transmisin as como tambin los costos de operacin del sistema.


9.3.2 Precios de Potencia en el Resto del SING

Los precios de potencia en los restantes nudos o barras del SING se determinaron
aplicando Factores de Penalizacin al Precio Bsico de la Potencia sealado en el
punto 9.2.

Estos Factores se obtienen de referir al nudo de referencia, los precios para el
bloque de mayor demanda obtenidos de acuerdo a la expresin del punto 9.1, para
cada nudo troncal. Dichos factores de penalizacin incorporan las exigencias de
calidad de servicio correspondientes, que se describen en ANEXO N 3.

Finalmente, los factores de penalizacin y los precios bsicos, tanto de energa
como de potencia de punta, se presentan en el Cuadro N 6.

CUADRO N 6: FACTORES DE PENALIZACIN Y PRECIOS BSICOS*

NUDO
Factor de
Penalizacin
Factor de
Penalizacin
Precio Bsico
de la Energa
Precio Bsico mensual
de la Potencia de Punta
de la Energa de la Potencia (US$/MWh) ($/kWh) (US$/kW-mes) ($/kW-mes)
TARAPAC 1,0302 1,0027 88,6497 49,1490 8,6906 4.818,15
LAGUNAS 1,0323 1,0000 88,8304 49,2490 8,6672 4.805,18
CRUCERO 1,0000 0,9477 86,0510 47,7080 8,2139 4.553,87
ENCUENTRO
1,0123 0,9905 87,1094 48,2950 8,5849 4.759,53
ATACAMA 1,0116 0,9955 87,0492 48,2610 8,6282 4.783,56

*: Subestaciones troncales conforme al Artculo 14 transitorio del DFL N 4/06.




Informe Tcnico Preliminar Abril 2014 COMISIN NACIONAL DE ENERGA
FONO (56-2) 2797 2612 - FAX (56-2) 2797 2600 CLASIFICADOR 14 - CORREO 21
E-MAIL: pnudo@cne.cl URL: http://www.cne.cl SANTIAGO - CHILE


14
10.- FRMULAS DE INDEXACIN PARA LOS PRECIOS DE NUDO

10.1.- Precio de la Potencia Punta
5


| |
(

+
|
|
.
|

\
|
+ =
0 0 0 0
0
3 2 1 $
IPC
IPC
Coef
PPI
PPI
Coef
PPIturb
PPIturb
Coef
Dol
Dol
Pb mes kW Pb
i i i i


Potencia
Central
[MW]
Potencia
Central
[MW]
Pb
0

[$/kW/mes]
PPIturb
COEF 1
PPI
COEF 2
IPC
COEF 3
Lagunas 70 4.805,18 0,46625 0,10373 0,43002

En que:

Pb: Precio bsico de la potencia actualizado en $/kW/mes.

Pb
0
: Precio bsico de la potencia vigente segn la ltima fijacin
tarifaria en $/kW/mes.

Dol
i
: Dlar observado EEUU promedio publicado por el Banco Central
correspondiente al mes anterior a cual se aplique la indexacin.

Dol
0
: Dlar observado EEUU promedio correspondiente al mes de
febrero 2014 (554,41 [$/US$]), utilizado en la fijacin tarifaria
vigente publicado por el Banco Central.

PPIturb
i
: Producer Price Index Industry Data: Turbine & Turbine Generator
Set Unit Mfg publicados por el Bureau of Labor Statistics
(www.bls.gov, PCU333611333611) correspondiente al sexto mes
anterior al cual se aplique la indexacin.

PPIturb
0
: Producer Price Index Industry Data: Turbine & Turbine Generator
Set Unit Mfg publicados por el Bureau of Labor Statistics
(www.bls.gov, PCU333611333611) correspondiente al mes de
septiembre de 2013 (215,90).

5
La frmula de indexacin, as como la estructura y valores base del clculo del precio bsico de la
potencia, han sido determinados considerando el Estudio DETERMINACIN DE LOS COSTOS
DE INVERSIN Y COSTOS FIJ OS DE OPERACIN DE LA UNIDAD DE PUNTA, EN SISTEMAS
SIC, SING Y SSMM del 2012. Dicho estudio se enmarca dentro de lo estipulado en el Reglamento
de Precio de Nudo, especficamente en su artculo 49.

Informe Tcnico Preliminar Abril 2014 COMISIN NACIONAL DE ENERGA
FONO (56-2) 2797 2612 - FAX (56-2) 2797 2600 CLASIFICADOR 14 - CORREO 21
E-MAIL: pnudo@cne.cl URL: http://www.cne.cl SANTIAGO - CHILE


15
PPI
i
: Producer Price Index- Commodities publicados por el Bureau of
Labor Statistics (www.bls.gov, WPU00000000) correspondiente al
sexto mes anterior al cual se aplique la indexacin.

PPI
0
: Producer Price Index- Commoditie publicados por el Bureau of
Labor Statistics (www.bls.gov, WPU00000000) correspondiente al
mes de septiembre de 2013 (203,90).

IPC
i
: ndice de precio al consumidor publicados por el INE para el
segundo mes anterior al cual se aplique la indexacin.

IPC
0
: ndice de precio al consumidor publicado por el INE
correspondiente al mes de enero de 2014 (112,08). IPC
determinado, en conformidad a lo estipulado el Decreto Supremo
N 322 de 2009 del Ministerio de Economa Fomento y
Reconstruccin.


10.2.- Precio de la Energa

El precio de nudo de la energa ser indexado respecto de las variaciones que
experimente el precio medio de mercado de acuerdo a la siguiente expresin:

Precio Energa = Precio Base
(

O
i
PMM
PMM


Donde:

PMM
i
: Precio Medio de Mercado determinado con los precios medios de los
contratos informados por las empresas generadoras a la Comisin
correspondientes a la ventana de cuatro meses que finaliza el tercer
mes anterior a la fecha de publicacin de este precio.

PMM
0
: Precio Medio de Mercado determinado con los precios medios de los
contratos informados por las empresas generadoras a la Comisin
correspondientes a la ventana de cuatro meses que incluye los meses
de noviembre de 2013 a febrero de 2014.

A ms tardar el primer da hbil de cada mes, la Comisin publicar en su sitio de
dominio electrnico el valor del PMMi respectivo para efectos de la aplicacin de la
frmula anterior.

Los precios medios de los contratos de clientes libres sern indexados mediante el
ndice de Precios al Consumidor (IPC) al mes anterior al cual se realice la
aplicacin de la frmula de indexacin de la energa.
Informe Tcnico Preliminar Abril 2014 COMISIN NACIONAL DE ENERGA
FONO (56-2) 2797 2612 - FAX (56-2) 2797 2600 CLASIFICADOR 14 - CORREO 21
E-MAIL: pnudo@cne.cl URL: http://www.cne.cl SANTIAGO - CHILE


16
11.- CARGOS POR ENERGA REACTIVA

Los cargos por energa reactiva de la fijacin de abril de 2014 varan en un
2,08% respecto de la fijacin de octubre de 2013, cifra que corresponde a un
1,15% por la variacin del tipo de cambio entre septiembre de 2013 y febrero de
2014, y a un 0,92% por la variacin real del dlar en adquisicin de maquinaria
elctrica (IPM USA) en seis meses (entre los meses julio 2013 y diciembre 2013).

Los nuevos cargos para estos rangos se presentan en el Cuadro N 7 y se
aplicarn en cada uno de los puntos de compra de toda empresa distribuidora de
servicio pblico que est recibiendo energa elctrica de una empresa generadora
o de otra empresa distribuidora de servicio pblico horariamente de acuerdo al
siguiente procedimiento:

1. Medir y registrar energa activa, reactiva inductiva y reactiva capacitiva.
2. Calcular el cociente entre energa reactiva inductiva y energa activa.
3. Conforme al cociente anterior y de acuerdo al nivel de tensin del punto de
compra aplicar los cargos por energa reactiva inductiva presentados en el
cuadro N 7 para cada una de las horas del perodo comprendido entre las
08:00 y 24:00 hrs.
4. Se excepta la aplicacin de los siguientes cargos slo para aquellas horas
correspondientes a los das domingos o festivos.

El mecanismo de aplicacin de los cargos sealados en el Cuadro N 7 ser
detallado en el Decreto de Precios de Nudo respectivo.

La aplicacin de los cargos se deber realizar considerando el desglose del
cociente entre la energa reactiva inductiva y energa activa para cada uno de los
tramos indicados. As en caso de que dicho cociente exceda el rango exento de
pago comprendido entre 0% y 20% slo se deber aplicar el cargo al exceso por
sobre el 20%. Dicho exceso deber dividirse en cada uno de los rangos indicados
en el Cuadro N 7 pagando el valor del rango respectivo hasta alcanzar el valor
total del cociente.

En aquellos casos en que existan puntos de compra con mediciones que incluyan
inyecciones o consumos de energa activa o reactiva distintos a los reconocidos
por la empresa distribuidora consumidora la Direccin de Peajes del Centro de
Despacho Econmico de Carga (CDEC) respectivo deber realizar un balance
horario que permita identificar el consumo de energa activa y reactiva al cual se
deben aplicar los cargos presentados en el Cuadro N 7 segn corresponda.








Informe Tcnico Preliminar Abril 2014 COMISIN NACIONAL DE ENERGA
FONO (56-2) 2797 2612 - FAX (56-2) 2797 2600 CLASIFICADOR 14 - CORREO 21
E-MAIL: pnudo@cne.cl URL: http://www.cne.cl SANTIAGO - CHILE


17
CUADRO N 7: CARGOS POR ENERGA REACTIVA INDUCTIVA SEGN
NIVEL DE TENSIN DE PUNTO DE COMPRA

Cuociente
(%)
Cargo para tensin
superior a 100 kV
$/kVArh
Cargo para tensin
entre 100 kV y 30 kV
$/kVArh
Cargo para tensin
inferior a 30 kV
$/kVArh
Desde 0 y hasta 20 0,000 0,000 0,000
Sobre 20 y hasta 30 5,320 0,000 0,000
Sobre 30 y hasta 40 9,580 9,580 0,000
Sobre 40 y hasta 50 9, 580 9, 580 9, 580
Sobre 50 y hasta 80 12,767 12,767 12,767
Sobre 80 15,952 15,952 15,952


12.- CARGO NICO TRONCAL (CU)

De acuerdo al procedimiento Contabilidad de Recaudacin del Cargo nico
Troncal del SING, aprobado por Resolucin Exenta N188 de la Comisin
Nacional de Energa, el CDEC-SING en su carta N288/2014 del 5 de marzo de
2014, ha informado a esta Comisin el saldo total de Cargo nico Troncal
esperado a enero de 2013.

Total $
SALDO ACUMULADO CU2 46.270.472


En el Informe Tcnico Definitivo de abril 2014, se informar y determinar el cargo
traspasable a usuarios sometidos a regulacin de precios y Cargo nico para el
segmento de usuarios que se seala en el artculo 102, letra a), prrafo segundo
de la LGSE.


Informe Tcnico Preliminar Abril 2014 COMISIN NACIONAL DE ENERGA
FONO (56-2) 2797 2612 - FAX (56-2) 2797 2600 CLASIFICADOR 14 - CORREO 21
E-MAIL: pnudo@cne.cl URL: http://www.cne.cl SANTIAGO - CHILE


18
13.- ANEXO N 1: PRECIOS DE COMBUSTIBLES

Los precios del carbn y de las mezclas de carbn-petcoke de los combustibles
lquidos y del diesel en las distintas centrales se determinaron de acuerdo a los
valores informados por la Direccin de Operacin del CDEC-SING, segn lo
establecido en el artculo N 19 del Reglamento de Precio de Nudo.

CUADRO N 8: PRECIO DE COMBUSTIBLES EN CENTRALES.

Potencia Tipo Porcentaje Unidades Consumo Unidades Costo
Propietario Central Unidad Neta de de deConsumo Especfico Costode de
[MW] Combustible Mezcla Especfico Combustible Combustible
EECSA CAVANCHA CAVA 2,6 Hidro
ENERNUEVAS MINIHIDROALTOHOSPICIO(PMGD) MHAH 1,1 Hidro
MINIHIDROELTORON2(PMGD) MHT2 1,1 Hidro
ECL CHAPIQUIA CHAP 10,1 Hidro
DIESELARICA GMAR 8,4 Diesel [m3/MWh] 0,2948 [US$/m3] 834,94
M1AR 2,9 Diesel [m3/MWh] 0,3016 [US$/m3] 834,94
M2AR 2,8 Diesel [m3/MWh] 0,3007 [US$/m3] 834,94
DIESELIQUIQUE MIIQ 2,8 Diesel [m3/MWh] 0,3015 [US$/m3] 825,43
SUIQ 4,1 Diesel [m3/MWh] 0,3260 [US$/m3] 825,43
TGIQ 23,6 Diesel [m3/MWh] 0,3807 [US$/m3] 825,43
MAIQ 5,6 Diesel 24%76% [Ton/MWh] 0,2570 [US$/Ton] 743,12
MSIQ 5,9 Diesel 23%77% [Ton/MWh] 0,2276 [US$/Ton] 740,04
TERMOELCTRICAMEJILLONES CTM1 154,9 Carbn [ton/MWh] 0,4350 [US$/ton] 89,74
CTM2 164,0 Carbn [ton/MWh] 0,4154 [US$/ton] 89,74
CTM3GNL 243,2 GasNatural [MBtu/MWh] 7,1080 [US$/Mbtu] 7,95
CTM3d 243,2 Diesel [m3/MWh] 0,2482 [US$/m3] 830,50
DIESELMANTOSBLANCOS MIMB 27,9 Diesel [m3/MWh] 0,2368 [US$/m3] 994,62
TERMOELCTRICATOCOPILLA U12 79,6 Carbn [ton/MWh] 0,5113 [US$/ton] 85,80
U13 79,8 Carbn [ton/MWh] 0,4887 [US$/ton] 85,80
U14 127,7 Carbn [ton/MWh] 0,4510 [US$/ton] 85,80
U15 124,1 Carbn [ton/MWh] 0,4343 [US$/ton] 85,80
TG1 24,6 Diesel [m3/MWh] 0,3980 [US$/m3] 832,02
TG2 24,8 Diesel [m3/MWh] 0,3980 [US$/m3] 832,02
U10 36,0 FuelOilNro.6 [ton/MWh] 0,2972 [US$/ton] 680,28
U11 36,0 FuelOilNro.6 [ton/MWh] 0,2972 [US$/ton] 680,28
TG3GNL 37,2 GasNatural [MBtu/MWh] 12,3781 [US$/Mbtu] 7,95
TG3d 37,2 Diesel [m3/MWh] 0,3140 [US$/m3] 832,02
U16GNL 343,0 GasNatural [MBtu/MWh] 6,7020 [US$/Mbtu] 7,95
U16d 343,0 Diesel [m3/MWh] 0,1950 [US$/m3] 832,02
TAMAYA 100,0 FuelOilNro.6 [ton/MWh] 0,2249 [US$/ton] 687,27
ANDINA CENTRAL TRMICAANDINA CTA 152,6 Carbn [ton/MWh] 0,3971 [US$/ton] 100,88
HORNITOS CENTRALTRMICAHORNITOS CTH 153,9 Carbn [ton/MWh] 0,3863 [US$/ton] 109,29
NORGENER TERMOELCTRICANORGENER NTO1 127,4 Carbn [ton/MWh] 0,4008 [US$/ton] 82,03
NTO2 131,9 Carbn [ton/MWh] 0,3970 [US$/ton] 82,03
CELTA TERMOELCTRICATARAPAC CTTAR 148,5 Carbn [ton/MWh] 0,4460 [US$/ton] 90,08
TGTAR 23,7 Diesel [m3/MWh] 0,3929 [US$/m3] 820,82
ENAEX DIESELENAEX CUMMINS 0,7 Diesel [m3/MWh] 0,3529 [US$/m3] 832,94
DEUTZ 2,0 Diesel [m3/MWh] 0,3882 [US$/m3] 832,94
GASATACAMA ATACAMA CC1GNL 325,6 GasNatural [MBtu/MWh] 7,5029 [US$/Mbtu] 12,82
CC1d 325,5 Diesel [m3/MWh] 0,2152 [US$/m3] 859,49
CC2GNL 325,6 GasNatural [MBtu/MWh] 7,5029 [US$/Mbtu] 12,82
CC2d 325,5 Diesel [m3/MWh] 0,2152 [US$/m3] 859,49
AESGENER SALTA CCSALTA 223 GasNatural [MBtu/MWh] 0,0000 [US$/Mbtu] 2,00
CCSALTA 109 GasNatural [MBtu/MWh] 0,0000 [US$/Mbtu] 2,00
ANGAMOS ANGAMOS ANGAMOSI 244 Carbn [ton/MWh] 0,4190 [US$/ton] 89,48
ANGAMOSII 244 Carbn [ton/MWh] 0,4190 [US$/ton] 89,48
INACAL INACAL INACAL 6,6 FuelOilNro.6 [ton/MWh] 0,2312 [US$/ton] 638,17
ENOR DIESEL ZOFRI ZOFRI_1 0,9 Diesel [m3/MWh] 0,3376 [US$/m3] 854,37
ZOFRI_2 5,2 Diesel [m3/MWh] 0,3376 [US$/m3] 854,37
ZOFRI_3 4,8 Diesel [m3/MWh] 0,2647 [US$/m3] 854,37
Estandartes 1,6 Diesel [m3/MWh] 0,3364 [US$/m3] 836,12
NORACID NORACID NORACID 17 Calorresidual 0,0000 0,00
ONGROUP INGENOVA Ingenova 2,0 Diesel [m3/MWh] 0,2276 [US$/m3] 740,04
ECL ELAGUILA Elguila 2,0 Solar 1,0000 0,00
SOLARPACK POZOALMONTE PozoAlmonte2 7,5 Solar 1,0000 0,00
ENEL VALLEDELOSVIENTOS ValledelosVientos 90,0 Elica 1,0000 0,00
PLANDEOBRAS PLANDEOBRAS ENCONSTRUCCIN Portada 3,0 Diesel [Ton/MWh] 0,2276 [US$/Ton] 740,04
AricaSolar1 18,0 Solar 1,0000 0,00
LaHuayca 9,0 Solar 1,0000 0,00
QuillaguaI 23,0 Solar 1,0000 0,00
AricaSolar2 22,0 Solar 1,0000 0,00
LaHuayca2 21,0 Solar 1,0000 0,00
PozoAlmonte3 16,0 Solar 1,0000 0,00
MaraElena 71,0 Solar 1,0000 0,00
SanPedro1 17,0 Solar 1,0000 0,00
SanPedro3 30,0 Solar 1,0000 0,00
SanPedro4 30,0 Solar 1,0000 0,00
SanPedro2 24,0 Solar 1,0000 0,00
CalamaSur 30,0 Solar 1,0000 0,00
QuillaguaII 27,0 Solar 1,0000 0,00
Cochrane1 236,0 Carbn [ton/MWh] 0,4250 [US$/ton] 94,19
Cochrane2 236,0 Carbn [ton/MWh] 0,4250 [US$/ton] 94,19
Kelar 517,0 GasNatural [MBtu/MWh] 7,2080 [[US$/Mbtu]] 12,70
QuillaguaIII 50,0 Solar 1,0000 0,00
PLANDEOBRAS RECOMENDADAS SolarSINGI 150 Solar 1,0000 0,00
EOLICOSINGI 50 Elica 1,0000 0,00
GeotermicaIrruputunco 50 Geotrmica 1,0000 0,00
EOLICOSINGII 200 Elica 1,0000 0,00
SolarSINGII 150 Solar 1,0000 0,00
GeotermicaPuchuldiza01 40 Geotrmica 1,0000 0,00
Informe Tcnico Preliminar Abril 2014 COMISIN NACIONAL DE ENERGA
FONO (56-2) 2797 2612 - FAX (56-2) 2797 2600 CLASIFICADOR 14 - CORREO 21
E-MAIL: pnudo@cne.cl URL: http://www.cne.cl SANTIAGO - CHILE


19
Los precios contenidos en el cuadro anterior se modelaron para el horizonte de
estudio a travs de los factores obtenidos de las proyecciones del Cuadro N 9,
Cuadro N 10 y N 11.

Para aquellas centrales que utilizan como combustibles el carbn, la mezcla
carbn-petcoke y el GNL, los precios contenidos en el cuadro anterior se
modelaron hasta diciembre de 2017 a travs de los factores de modulacin
obtenidos de las proyecciones del Cuadro N 9 y Cuadro N 10 respectivamente. A
contar de enero de 2018 se utilizan los precios de la proyeccin elaborada por la
CNE. Para los combustibles diesel, fuel y mezcla diesel-fuel la modulacin de
precios se realiz a travs del coeficiente de modulacin del crudo WTI del Cuadro
N 11.
CUADRO N 9: PROYECCIN PRECIO DE CARBN TRMICO
6


Carbn Trmico
Ao
Precio
US$/Ton
Factor de
Modulacin
2014 94,19 1,0000
2015 95,61 1,0151
2016 96,90 1,0288
2017 99,10 1,0522
2018 100,78 1,0701
2019 101,43 1,0769
2020 101,95 1,0824
2021 102,34 1,0865
2022 102,85 1,0920
2023 103,37 1,0975
2024 104,28 1,1071

CUADRO N 10: PROYECCIN PRECIO DE GAS NATURAL LICUADO
7


GNL
Ao
Precio
[US$/MBtu]
Factor de
Modulacin
2014 12,70 1,0000
2015 12,48 0,9823
2016 12,00 0,9448
2017 11,80 0,9286
2018 10,68 0,8405
2019 10,51 0,8270
2020 10,16 0,7996
2021 10,51 0,8276

6
Estimacin CNE 2014-2024 en base a la proyeccin de precios de largo (EAO 2014: Early
Release) proporcionada por el portal web US Energy Information Administration de Estados Unidos
(www.eia.gov). Flete Supra Handymax promedio en dicho clculo y en el actual clculo
corresponde a 13,58 US$/ton. Precio de Paridad se considera en Ventanas.
7
Estimacin CNE en base a la proyeccin de precios de largo plazo (EAO 2014: Early Release)
proporcionada por el portal web US Energy Information Administration de Estados Unidos
(www.eia.gov). Precio Gas Natural entre 2014-2017 se calcula como el 12% Brent; 2018 en
adelante el precio del gas natural se calcula como 115% HH ms 4,5 US$/MBTU. En ambos casos
se considera un arancel de importacin de 6%.
Informe Tcnico Preliminar Abril 2014 COMISIN NACIONAL DE ENERGA
FONO (56-2) 2797 2612 - FAX (56-2) 2797 2600 CLASIFICADOR 14 - CORREO 21
E-MAIL: pnudo@cne.cl URL: http://www.cne.cl SANTIAGO - CHILE


20
GNL
Ao
Precio
[US$/MBtu]
Factor de
Modulacin
2022 10,71 0,8427
2023 10,87 0,8559
2024 11,07 0,8716

CUADRO N 11: PROYECCIN PRECIO DE CRUDO WTI
8


Crudo WTI
Ao
Diesel Paridad
[US$/bbl]
Factor de
Modulacin
2014 94,02 1,0000
2015 90,33 0,9608
2016 88,64 0,9813
2017 89,72 0,9932
2018 90,89 1,0062
2019 93,19 1,0316
2020 95,51 1,0158
2021 98,02 1,0425
2022 100,56 1,0695
2023 103,23 1,0979
2024 105,73 1,1245

Para las centrales recomendadas en el Plan de Obras se utiliz precios de
combustible de las centrales ms cercanas, incluyendo la modulacin
correspondiente.


14.- ANEXO N 2: PRECIOS BSICOS DE ENERGA Y POTENCIA DE
PUNTA

14.1.- Precio Bsico de Energa

Sobre la base de las caractersticas de las unidades y las curvas de carga del
sistema elctrico se calcularon los costos marginales para los diferentes aos
calendario de operacin analizados en el sistema elctrico en el nudo Crucero 220
kV.

Una vez obtenidos los costos marginales mensuales para cada ao calendario se
calcul el costo marginal promedio ponderado actualizado en el perodo de 48
meses a partir de abril de 2014 en el nudo Crucero 220 kV.

El cuadro siguiente muestra los costos marginales resultantes entre los meses de
abril de 2014 y marzo de 2018, y el valor del costo marginal actualizado.


8
Estimacin CNE 2014-2024 en base a la proyeccin de precios de largo plazo (EAO 2014: Early
Release) proporcionada por el portal web US Energy Information Administration de Estados Unidos
(www.eia.gov).
Informe Tcnico Preliminar Abril 2014 COMISIN NACIONAL DE ENERGA
FONO (56-2) 2797 2612 - FAX (56-2) 2797 2600 CLASIFICADOR 14 - CORREO 21
E-MAIL: pnudo@cne.cl URL: http://www.cne.cl SANTIAGO - CHILE


21
CUADRO N 12: COSTOS MARGINALES Y DEMANDA DE ENERGA NUDO CRUCERO 220 kV

Ao Mes
Costo Marginal
Equivalente
[US$/MWh]
Demanda
Asociada
[GWh]
Tasa
Descuento
2014 Abril 71,70 792,45 1,0000
2014 Mayo 64,05 828,46 0,9919
2014 J unio 62,99 799,98 0,9842
2014 J ulio 63,51 832,19 0,9763
2014 Agosto 63,95 825,03 0,9684
2014 Septiembre 67,43 805,30 0,9613
2014 Octubre 63,27 853,42 0,9536
2014 Noviembre 62,82 829,29 0,9462
2014 Diciembre 62,74 861,26 0,9385
2015 Enero 95,89 897,36 0,9312
2015 Febrero 97,90 826,95 0,9237
2015 Marzo 96,90 898,87 0,9162
2015 Abril 98,42 792,56 0,9091
2015 Mayo 97,79 836,73 0,9018
2015 J unio 96,20 803,77 0,8947
2015 J ulio 97,97 838,90 0,8875
2015 Agosto 98,13 830,49 0,8804
2015 Septiembre 97,62 811,33 0,8739
2015 Octubre 96,78 843,72 0,8669
2015 Noviembre 97,77 820,68 0,8601
2015 Diciembre 95,67 851,51 0,8532
2016 Enero 92,91 923,07 0,8465
2016 Febrero 95,31 825,68 0,8397
2016 Marzo 95,40 924,86 0,8330
2016 Abril 96,42 894,72 0,8265
2016 Mayo 93,06 937,38 0,8198
2016 J unio 92,25 899,61 0,8134
2016 J ulio 93,10 938,26 0,8068
2016 Agosto 93,27 929,64 0,8003
2016 Septiembre 92,55 795,46 0,7945
2016 Octubre 90,13 828,65 0,7881
2016 Noviembre 62,01 807,02 0,7819
2016 Diciembre 79,46 836,42 0,7756
2017 Enero 87,66 931,93 0,7696
2017 Febrero 88,93 833,32 0,7634
2017 Marzo 89,55 932,97 0,7572
2017 Abril 89,49 902,67 0,7513
2017 Mayo 89,50 949,43 0,7453
2017 J unio 89,51 907,69 0,7394
2017 J ulio 89,58 947,12 0,7335
2017 Agosto 89,55 936,84 0,7276
2017 Septiembre 90,35 912,66 0,7223
2017 Octubre 89,62 949,96 0,7164
2017 Noviembre 89,28 924,60 0,7109
2017 Diciembre 89,52 958,05 0,7051
2018 Enero 80,86 961,36 0,6996
2018 Febrero 81,67 859,65 0,6940
2018 Marzo 82,57 962,35 0,6884
Informe Tcnico Preliminar Abril 2014 COMISIN NACIONAL DE ENERGA
FONO (56-2) 2797 2612 - FAX (56-2) 2797 2600 CLASIFICADOR 14 - CORREO 21
E-MAIL: pnudo@cne.cl URL: http://www.cne.cl SANTIAGO - CHILE


22
Precio bsico de la energa en nudo Crucero 220 kV :

Precio Bsico Energa = 86,051 [US$/MWh] x 554,41 [$/US$] = 47,708 [$/kWh]


14.2.- Precio Bsico de la Potencia de Punta
9


El clculo del precio bsico de la potencia de punta en el nudo Lagunas 220 kV se
obtiene de acuerdo a la siguiente expresin:

| | ( ) { } ( ) FP MRT 1 C CF FRC C FRC C FRC C mes kW $ US Ppot
op LT LT SE SE TG TG
+ + + + =

Sus valores y clculo que se detallan a continuacin:

CUADRO N 13: CLCULO DEL PRECIO BSICO DE LA POTENCIA DE PUNTA

Precio Bsico de la Potencia, Lagunas 70 [MW]
C
TG
[US$/kW] 609,109 Costo unitario de inversin de la unidad generadora para este proyecto.
FRC
TG
[-] 0,008785
Factor de recuperacin de capital de la inversin de la unidad generadora,
corresponde a la mensualidad de la inversin sobre una vida til de 20
aos.
C
SE
[US$/kW] 73,284 Costo unitario de inversin de la subestacin elctrica de este proyecto.
FRC
SE
[-] 0,008459
Factor de recuperacin de capital de la inversin de la subestacin elctrica,
corresponde a la mensualidad de la inversin sobre una vida til de 30
aos.
C
LT
[US$/kW] 10,289
Costo unitario de inversin de la lnea de transmisin que conecta la
subestacin de este proyecto con la subestacin Lagunas.
FRC
LT
[-] 0,009366
Factor de recuperacin de capital de la inversin de la lnea de transmisin,
corresponde a la mensualidad de la inversin sobre una vida til de 20
aos.
CF[-] 1,048809 Costo financiero.
C
OP
[US$/kW] 1,359 Costo fijo de operacin y mantenimiento.
1 + MRT [-] 1,1176 Incremento por Margen de Reserva Terico definido por la Comisin.
FP [-] 1,00428 Factor de prdidas.
Pbpot [US$/kW/mes] 8,6672 Precio Bsico de la potencia.


Se ha adoptado un margen de 11,76% para todos los nudos en consistencia con lo
utilizado en la anterior fijacin correspondiente a una disponibilidad promedio de
89,48% de las unidades generadoras ms econmica para suministrar potencia

9
La frmula de indexacin, as como la estructura y valores base del clculo del precio bsico de la potencia,
han sido determinados considerando el Estudio DETERMINACIN DE LOS COSTOS DE INVERSIN Y
COSTOS FIJ OS DE OPERACIN DE LA UNIDAD DE PUNTA, EN SISTEMAS SIC, SING Y SSMM del 2012,
enviado a las empresas generadoras mediante carta CNE N237 de fecha 29 de junio de 2012. Dicho estudio
se enmarca dentro de lo estipulado en el Reglamento de Precio de Nudo, especficamente en su artculo 49.
Informe Tcnico Preliminar Abril 2014 COMISIN NACIONAL DE ENERGA
FONO (56-2) 2797 2612 - FAX (56-2) 2797 2600 CLASIFICADOR 14 - CORREO 21
E-MAIL: pnudo@cne.cl URL: http://www.cne.cl SANTIAGO - CHILE


23
adicional durante las horas de demanda mxima anual del sistema elctrico, esto
es, turbinas a gas Diesel.


Precio Bsico Potencia de Punta =8,6672 [US$/kW/mes] x 554,41 [$/US$]
= 4.805,18 [$/kW/mes]


15.- ANEXO N 3: CALIDAD DE SUMINISTRO

15.1.- Simplificaciones Adoptadas

Para la modelacin del sistema elctrico se han adoptado las siguientes
simplificaciones:

a) Modelacin uninodal del sistema elctrico para determinacin de
probabilidad de prdida de carga en generacin y costos de regulacin de
tensin y frecuencia.
b) Representacin multinodal del sistema elctrico para determinacin de
probabilidad de prdida de carga en transmisin.

15.2.- Calidad de Suministro

La calidad de suministro se ha considerado respecto de los parmetros
Indisponibilidad de Generacin, Indisponibilidad de Transmisin, Regulacin de
Frecuencia y Regulacin de Tensin.

a) Indisponibilidad de Generacin

Se determin la indisponibilidad de generacin asociada al plan de obras utilizado
en la presente fijacin.

La indisponibilidad del sistema de generacin es representada a travs del
desarrollo de un modelo esttico anual que considera la curva de duracin de la
demanda del sistema y las indisponibilidades caractersticas de las unidades
generadoras del sistema.

La modelacin utilizada reemplaza las unidades generadoras reales por unidades
ideales con disponibilidad igual a 100% obtenindose la curva de duracin de la
demanda equivalente a partir del proceso de convolucin entre la curva de
duracin de la demanda y las distribuciones de indisponibilidad de cada una de las
unidades del sistema.

Una vez obtenida la curva de duracin de la demanda equivalente y a partir de la
capacidad de oferta de potencia reconocida al sistema se obtiene la probabilidad
de prdida de carga (LOLP) como indicador que representa el nmero de horas
Informe Tcnico Preliminar Abril 2014 COMISIN NACIONAL DE ENERGA
FONO (56-2) 2797 2612 - FAX (56-2) 2797 2600 CLASIFICADOR 14 - CORREO 21
E-MAIL: pnudo@cne.cl URL: http://www.cne.cl SANTIAGO - CHILE


24
esperado en que el sistema de generacin no es capaz de absorber la demanda
de potencia del sistema durante las horas de punta.

Este valor corresponde al mismo determinado en la fijacin de octubre de 2013 y
alcanza el valor:

Indisponibilidad de Generacin SING = 3,4 [horas/ ao]


b) Indisponibilidad de Transmisin

La indisponibilidad de transmisin se trat mediante afectacin directa de los
factores de penalizacin considerando que los modelamientos que les dieron
origen no incorporaron factores de indisponibilidad.

Para ello se efectu una simulacin esttica de la operacin del sistema elctrico
para una condicin tpica de operacin en la hora de demanda mxima utilizando
el modelo multinodal PCP
10
.

Considerando una tasa de indisponibilidad de 0,00176 [horas/km] al ao se
simul la operacin del sistema para diferentes escenarios de indisponibilidad de
lneas. Se consider la salida sucesiva de 23 tramos redespachando el
abastecimiento en cada caso y observando los casos en que la demanda total del
sistema no fue abastecida.

A cada escenario de insuficiencia de demanda y a su distribucin de costos
marginales por barra se asign la probabilidad correspondiente determinando un
coeficiente promedio de sobrecosto por sobre el costo marginal promedio del caso
base sin salidas de lnea.

Como costo de falla se us el costo correspondiente declarado en el cuerpo de
este informe. Se acumularon las tasas de falla asociadas a cada escenario de
falla. Los resultados son los siguientes:

Indisponibilidad de Transmisin SING = 0,24 horas/ao

Factor de Sobrecosto por Indisponibilidad = 1,000085 p.u.

Este coeficiente destinado a afectar a los factores de penalizacin resulta ser bajo
pues el modelo utilizado reconoce que pocos eventos de salida de lneas
asociados a su vez a bajas probabilidades provocan insuficiencia en el
abastecimiento de la demanda.


10
El modelo PCP fue revisado y aprobada su utilizacin en el CDEC-SIC por la Comisin Nacional
de Energa con motivo de la divergencia surgida en Sesin N72.1/98.
Informe Tcnico Preliminar Abril 2014 COMISIN NACIONAL DE ENERGA
FONO (56-2) 2797 2612 - FAX (56-2) 2797 2600 CLASIFICADOR 14 - CORREO 21
E-MAIL: pnudo@cne.cl URL: http://www.cne.cl SANTIAGO - CHILE


25
Se afect los factores de penalizacin de potencia por dicho factor de sobrecosto.
Los factores de penalizacin de potencia presentados en el cuerpo de este Informe
Tcnico Preliminar incluyen este factor de sobrecosto.

Cabe sealar lo siguiente:

- Las metodologas para el tratamiento de los ndices de calidad de suministro
deben entenderse de exclusiva aplicacin en la presente fijacin de precios.

- Los parmetros definidos no pueden entenderse como una condicionante del
trabajo que el CDEC debe efectuar para cumplir con lo establecido en la letra
d) del Artculo 36 del Decreto Supremo N291 de 2007, del Ministerio de
Economa, Fomento y Reconstruccin.

Informe Tcnico Preliminar Abril 2014 COMISIN NACIONAL DE ENERGA
FONO (56-2) 2797 2612 - FAX (56-2) 2797 2600 CLASIFICADOR 14 - CORREO 21
E-MAIL: pnudo@cne.cl URL: http://www.cne.cl SANTIAGO - CHILE


26
16.- ANEXO N 4: BASES METODOLGICAS Y CONCEPTUALES DEL
CLCULO FACTORES DE PENALIZACIN

16.1.- Introduccin

Segn lo establecido en el DFL N 4/06 la Comisin Nacional de la Energa (CNE)
debe determinar semestralmente el Precio de Nudo de la Energa y la Potencia.
Asimismo la Comisin debe calcular los Factores de Penalizacin de Energa y
Potencia para los sistemas cuyo tamao sea igual o superior a 200 MW de
capacidad instalada los cuales deben ser utilizados para determinar los precios
regulados en cada una de las subestaciones de los respectivos sistemas elctricos
a partir de los precios bsicos de nudo de energa y potencia.

En virtud de lo anterior, y con motivo de la fijacin de precio de nudo
correspondiente a abril de 2014, la Comisin ha decidido actualizar los Factores de
Penalizacin vigentes en el Sistema Interconectado del Norte Grande (SING)
cuyas bases metodolgicas y conceptuales se entregan a continuacin.

16.2.- Modelo de Factores de Penalizacin

16.2.1 Bases Generales del Clculo de Factores de Penalizacin

Los factores de penalizacin reflejan la forma en que las prdidas marginales se
distribuyen en la red elctrica y por lo tanto son un ndice de costos asociado a la
generacin elctrica.

En la determinacin de los Factores de Penalizacin de Energa y de Potencia
para el SING se utiliz un Modelo Multinodal OSE2000 mediante una
representacin topolgica que se muestra en detalle ms adelante.

A partir de la previsin de demanda a que se refiere el cuerpo del presente informe
se model la demanda de carcter residencial e industrial en las diferentes barras
del sistema en base a factores de reparticin mensual y utilizando una curva de
duracin para cada tipo de demanda es decir curva residencial en aquellas barras
en las cuales existen consumos principalmente regulados (ciudades) y curva
industrial en todas aquellas barras en las cuales existen consumos de carcter
industrial.

Por otra parte el flujo en cada lnea se represent mediante una aproximacin de 5
tramos.

Los factores de penalizacin se determinaron a partir de la relacin de precios de
nudo por barra de acuerdo a la barra de referencia elegida para un perodo de 48
meses. En el caso particular de los factores de penalizacin de la potencia dichos
precios fueron determinados utilizando los resultados para el bloque de mayor
demanda en cada mes.
Informe Tcnico Preliminar Abril 2014 COMISIN NACIONAL DE ENERGA
FONO (56-2) 2797 2612 - FAX (56-2) 2797 2600 CLASIFICADOR 14 - CORREO 21
E-MAIL: pnudo@cne.cl URL: http://www.cne.cl SANTIAGO - CHILE


27
Los precios de combustibles, crecimiento, de las ventas y consideraciones
operacionales del SING utilizados, son las que se entregan en el cuerpo del
Informe Tcnico Preliminar.

Las barras utilizadas as como sus caractersticas se encuentran disponibles en las
bases que acompaan la publicacin del presente informe. La proyeccin de
ventas se muestra en los cuadros siguientes.

CUADRO N 14: VENTAS TOTALES.

PROYECCIN DE VENTAS DE ENERGA
Ao
Clientes
Libres
GWh
Tasa
Libres
Clientes
Regulados
GWh
Tasa
Regulados
Sistema
GWh
Tasa
Sistema
2014 14.792 6,0% 1.799 5,8% 16.591 5,9%
2015 15.809 6,9% 1.886 4,9% 17.695 6,7%
2016 16.862 6,7% 1.971 4,5% 18.832 6,4%
2017 17.955 6,5% 2.054 4,2% 20.009 6,3%
2018 19.112 6,4% 2.137 4,0% 21.248 6,2%
2019 20.290 6,2% 2.219 3,8% 22.509 5,9%
2020 21.532 6,1% 2.299 3,6% 23.831 5,9%
2021 22.832 6,0% 2.379 3,5% 25.211 5,8%
2022 24.180 5,9% 2.460 3,4% 26.640 5,7%
2023 25.592 5,8% 2.538 3,2% 28.130 5,6%
2024 27.011 5,5% 2.616 3,0% 29.626 5,3%


CUADRO N 15: VENTAS REGULADAS POR BARRA [MWh]
Consumo Clientes Regulados SING [MWh]
Barra 2014 2015 2016 2017 2018 2019 2020 2021 2022 2023 2024
Alto Hospicio 110 91.982 96.488 100.853 105.169 109.437 113.656 117.826 121.947 126.151 130.179 134.159
Antofagasta 013 42.105 44.173 46.177 48.159 50.118 52.055 53.970 55.862 57.791 59.641 61.468
Calama 110 263.652 276.604 289.154 301.563 313.832 325.961 337.949 349.798 361.881 373.463 384.905
Centro 110 320.137 335.864 351.102 366.169 381.067 395.794 410.351 424.738 439.410 453.473 467.366
Cerro Dragn 110 126.179 132.360 138.348 144.269 150.123 155.911 161.631 167.285 173.051 178.577 184.037
Chapiquia 066 1.738 1.839 1.934 2.027 2.119 2.210 2.300 2.389 2.480 2.567 2.653
Chinchorro 066 111.764 116.879 121.826 126.718 131.555 136.335 141.060 145.729 150.499 155.063 159.570
Dolores 110 1.053 1.104 1.154 1.202 1.251 1.298 1.346 1.392 1.440 1.485 1.530
El Tesoro 220 1.464 1.536 1.606 1.675 1.743 1.810 1.877 1.943 2.010 2.074 2.138
La Negra 110 64.305 67.464 70.524 73.551 76.543 79.502 82.426 85.316 88.263 91.087 93.878
La Portada 110 111.983 117.485 122.815 128.085 133.297 138.448 143.540 148.573 153.705 158.624 163.484
Lagunas 023 1.723 1.808 1.890 1.970 2.050 2.129 2.208 2.285 2.364 2.439 2.514
Mantos Blancos 220 3.001 3.149 3.292 3.433 3.572 3.711 3.847 3.982 4.119 4.251 4.382
Mejillones 110 21.889 22.964 24.006 25.036 26.055 27.061 28.057 29.040 30.044 31.005 31.955
O'higgins 220 - - - - - - - - - - -
Pacifico 110 122.468 128.467 134.279 140.026 145.709 151.326 156.878 162.365 167.962 173.326 178.625
Palafitos 110 103.087 108.137 113.029 117.867 122.650 127.378 132.051 136.670 141.381 145.896 150.357
Pozo Almonte 13.8 42.054 44.114 46.110 48.084 50.035 51.964 53.870 55.755 57.676 59.518 61.338
Pukara 066 146.097 152.782 159.250 165.645 171.967 178.216 184.392 190.496 196.731 202.696 208.589
Quiani 066 53.872 56.338 58.722 61.080 63.412 65.716 67.993 70.244 72.543 74.743 76.916
Sur 110 85.376 89.570 93.634 97.652 101.625 105.553 109.435 113.272 117.185 120.935 124.640
Tamarugal 066 26.827 28.141 29.414 30.673 31.918 33.148 34.364 35.566 36.792 37.967 39.128
Tarapac 220 9.891 10.375 10.845 11.309 11.768 12.221 12.670 13.113 13.565 13.998 14.426
Tocopilla 005 28.225 29.611 30.955 32.283 33.597 34.895 36.179 37.447 38.741 39.981 41.205
Uribe 110 18.009 18.893 19.751 20.598 21.436 22.265 23.084 23.893 24.718 25.509 26.291
Informe Tcnico Preliminar Abril 2014 COMISIN NACIONAL DE ENERGA
FONO (56-2) 2797 2612 - FAX (56-2) 2797 2600 CLASIFICADOR 14 - CORREO 21
E-MAIL: pnudo@cne.cl URL: http://www.cne.cl SANTIAGO - CHILE


28
CUADRO N 16: VENTAS LIBRES POR BARRA [MWh]

Consumo Clientes Libres SING [MWh]
Barra 2014 2015 2016 2017 2018 2019 2020 2021 2022 2023 2024
Alto Norte 110 333.510 340.041 347.571 360.779 372.812 379.377 383.170 387.726 394.525 398.839 409.163
Arica 110 8.720 29.087 31.672 32.462 33.212 33.462 33.554 33.525 33.775 33.806 34.681
Calama 110 10.731 10.806 11.045 11.465 11.847 12.056 12.176 12.321 12.537 12.674 13.002
Centro 110 24.977 25.400 26.220 27.486 28.684 29.478 30.067 30.726 31.574 32.236 33.397
Chacaya 220 1.079.558 1.294.823 1.334.442 1.396.643 1.455.237 1.493.225 1.561.643 1.732.710 1.987.829 2.361.195 2.737.995
Chapiquia 066 75 75 77 80 83 85 86 87 89 90 93
Chuquicamata 110 6.833 6.813 6.895 7.086 7.250 7.304 7.304 7.318 7.373 7.379 7.496
Chuquicamata 220 2.178.669 2.215.583 2.287.068 2.397.481 2.501.972 2.571.236 2.828.359 2.975.328 3.147.409 3.307.839 3.427.056
Collahuasi 220 1.397.404 1.442.579 1.519.075 1.608.979 1.684.522 1.735.841 1.822.633 1.917.342 1.950.967 1.972.301 2.023.351
Desalant 110 86.179 87.640 90.467 94.835 98.968 101.708 103.742 104.975 106.816 107.984 110.779
Dolores 110 5.999 5.328 4.731 4.182 4.279 4.311 4.311 4.319 4.351 4.355 4.424
El Abra 220 808.810 814.450 832.485 864.120 892.940 908.663 917.750 928.660 944.946 955.279 980.005
El Aguila 066 16.919 18.742 20.922 23.392 24.412 25.088 25.589 26.150 26.872 27.435 28.423
El Loa 220 222.597 223.040 226.850 234.305 240.921 243.949 245.169 246.856 249.941 251.424 256.654
El Negro 110 29.840 32.653 36.818 38.714 44.785 47.457 49.927 52.495 55.664 58.496 62.239
El Tesoro 220 303.390 303.993 309.186 319.347 328.364 332.492 334.154 336.453 340.658 342.679 349.808
Encuentro 220 1.144.376 1.708.956 2.235.984 2.574.596 2.902.011 3.460.616 3.907.153 4.221.902 4.567.425 4.877.791 5.133.064
Escondida 220 3.648.526 3.696.666 3.817.488 4.001.810 4.174.643 4.287.000 4.367.910 4.457.136 4.572.065 4.658.040 4.814.321
Gaby 220 395.096 397.851 406.661 422.114 436.193 443.873 448.312 453.641 461.597 466.645 478.723
La Cruz 220 30.444 36.423 37.230 38.644 39.933 40.636 41.043 41.531 42.259 42.721 43.827
La Negra 110 59.482 63.455 68.713 75.561 82.720 89.177 90.069 91.140 92.738 93.752 96.179
Lagunas 023 27.134 25.725 26.983 28.706 30.368 31.602 32.608 33.676 34.942 35.990 37.588
Lince 110 146.394 147.415 149.187 153.323 156.868 158.050 158.050 158.345 159.527 159.675 162.186
Lomas Bayas 220 300.920 301.518 306.669 316.747 325.691 329.785 331.434 333.714 337.885 339.889 346.960
Mantos Blancos 220 222.222 222.664 226.468 233.910 240.515 243.538 244.756 246.439 249.520 251.000 256.222
Mejillones 110 80.119 85.267 91.338 99.968 109.635 119.223 120.415 121.846 123.983 125.339 128.583
Minsal 023 273.541 288.327 299.380 296.980 313.934 321.079 332.344 337.726 355.678 371.454 392.985
Norgener 220 74.247 75.505 77.941 81.704 85.265 87.625 89.378 90.440 92.026 93.033 95.441
O'higgins 220 23.645 23.810 24.338 25.262 26.105 26.565 26.830 27.149 27.625 27.927 28.650
Pozo Almonte 066 305.517 308.186 315.545 328.072 339.551 346.059 350.037 354.704 361.422 365.860 375.811
Quebrada Blanca 220 91.195 104.910 174.730 224.551 307.479 454.413 607.544 758.770 917.319 1.147.711 1.247.363
Radomiro Tomic 220 842.817 857.267 890.911 985.346 1.145.233 1.213.009 1.273.660 1.339.842 1.417.333 1.489.578 1.588.653
Spence 220 25.749 25.928 26.502 27.509 28.427 28.927 29.217 29.564 30.082 30.411 31.199
Tamarugal 066 22.327 23.011 24.047 25.494 26.881 27.888 28.692 29.552 30.584 31.425 32.745
Tarapac 220 25.725 27.183 29.919 30.749 32.192 33.173 36.571 49.463 59.799 62.847 67.027
Tocopilla 005 2.905 2.896 2.931 3.013 3.082 3.105 3.105 3.111 3.134 3.137 3.187
Zaldvar 220 535.045 535.042 543.100 559.831 574.493 619.338 653.357 855.051 947.575 1.043.297 1.171.586


16.3.- Resultados

De este modo a partir de los precios de nudo por barra en la tabla siguiente se
presentan los correspondientes factores de:

CUADRO N 17: FACTORES DE PENALIZACIN

Factor de Factor de
NUDO Penalizacin Penalizacin

de la
Energa
de la
Potencia

Tarapac 220 1,0302 1,0027
Lagunas 220 1,0323 1,0000
Crucero 220 1,0000 0,9477
Encuentro 220 1,0123 0,9905
Atacama 220 1,0116 0,9955

Informe Tcnico Preliminar Abril 2014 COMISIN NACIONAL DE ENERGA
FONO (56-2) 2797 2612 - FAX (56-2) 2797 2600 CLASIFICADOR 14 - CORREO 21
E-MAIL: pnudo@cne.cl URL: http://www.cne.cl SANTIAGO - CHILE


29
17.- ANEXO N 5: PLAN DE OBRAS

17.1.- Introduccin

En Chile la legislacin vigente le entrega a la Comisin la responsabilidad de velar
por el desarrollo del sector elctrico. Para cumplir adecuadamente esta labor en
materias de generacin y de transmisin de electricidad, la Comisin debe analizar
peridicamente la evolucin de la demanda y de la oferta de electricidad.

A continuacin se entregan los antecedentes y bases utilizadas para determinar el
Programa de Obras correspondiente a la fijacin de precios de nudo de abril de
2014.

17.2.- Metodologa

La metodologa para obtener el programa de generacin y transmisin ptimo se
basa en determinar, para distintas alternativas de puesta en servicio de centrales
trmicas y lneas de transmisin, la suma de los costos presentes de inversin,
operacin (fija y variable) y falla.

Para establecer el costo presente de abastecimiento de cada alternativa se ha
incluido lo siguiente:

- Inversin en centrales y lneas de transmisin a la fecha de puesta en
servicio.
- Valor residual de las inversiones a fines del perodo considerado (incluyendo
los posibles aos de relleno), en base a una depreciacin lineal, y de
acuerdo a las siguientes vidas tiles de las instalaciones:
o Centrales de Ciclo Combinado: 24 aos.
o Centrales a Carbn: 24 aos.
o Proyectos de interconexin y lneas de transmisin: 30 aos.
- Costo fijo anual de reserva de transporte de gas de centrales de ciclo
combinado por un 90% de su demanda mxima, dependiendo de su fecha
de puesta en servicio y localizacin.
- Gasto fijo anual de operacin y mantenimiento.
- Gasto variable anual, representado por los costos total de operacin y falla
entregado por el modelo de optimizacin utilizado.

La determinacin de la alternativa de expansin ms conveniente surge de un
proceso iterativo de comparacin de las opciones de desarrollo y de minimizar la
siguiente funcin objetivo:

} {
a s
sidual C M CO Inv Min
/
Re var & + + =


Informe Tcnico Preliminar Abril 2014 COMISIN NACIONAL DE ENERGA
FONO (56-2) 2797 2612 - FAX (56-2) 2797 2600 CLASIFICADOR 14 - CORREO 21
E-MAIL: pnudo@cne.cl URL: http://www.cne.cl SANTIAGO - CHILE


30

Restricciones de demanda
Limitaciones del sistema de transmisin
Potencias mximas de centrales generadoras.

donde:

Inv : Valor actualizado de las todas las inversiones futuras a optimizar.
CO&M : Valor actualizado de todos los costos de operacin y mantenimiento
de las nuevas instalaciones. Los valores de CO&M anual previos a su
actualizacin se consideran al final de cada ao.
Cvar : Costo de operacin y falla futuro actualizado del sistema.
Residual :Valor actualizado del monto residual de todas las inversiones futuras.

En la obtencin de los planes de obra se consider una tasa de descuento igual al
10% para las centrales futuras y para la planta regasificadora de GNL.

17.3.- Proyectos de Generacin


17.3.1 Alternativas de Expansin del Parque Generador

Para determinar las alternativas de expansin y la localizacin indicativa de las
centrales de generacin en estudio, esta Comisin tuvo en vista los antecedentes
proporcionados por el Servicio de Evaluacin Ambiental (SEA), respecto de los
proyectos de generacin en estudio que poseen distintas empresas y que estn en
proceso de evaluacin del impacto ambiental por parte de dicha institucin.
Adems se solicit informacin a las empresas de generacin actualmente
operando y a aquellas de las cuales se tiene informacin relacionada con posibles
proyectos en estudio que estn llevando actualmente a cabo.

En cuanto a los tipos de tecnologa y en virtud a lo estipulado en la ley N 20.257,
que introduce modificaciones a la Ley General de Servicios Elctricos, respecto de
la generacin de electricidad con fuentes de energa renovables no
convencionales, se ha considerado tambin en el presente plan de obras, la
inclusin de centrales generadoras pertenecientes a este tipo de tecnologas.

A partir de lo anterior, esta Comisin conform un set de proyectos de generacin,
tcnica y econmicamente factibles de ser desarrollados en el horizonte 2014-
2024, incluyendo alternativas tecnolgicas que cubrieran diferentes fuentes
energticas. Las caractersticas y criterios generales aplicados en la eleccin de los
proyectos analizados fueron los siguientes:




Informe Tcnico Preliminar Abril 2014 COMISIN NACIONAL DE ENERGA
FONO (56-2) 2797 2612 - FAX (56-2) 2797 2600 CLASIFICADOR 14 - CORREO 21
E-MAIL: pnudo@cne.cl URL: http://www.cne.cl SANTIAGO - CHILE


31
17.3.1.1 Centrales a Gas Natural Licuado (GNL)

Para los ciclos abiertos y combinados existentes que utilizan gas natural se
consider un valor adicional de 0,12 US$/MBtu a los valores proyectados de GNL
por costos de regasificacin. Se considera una capacidad de 5,5 Mm3/da la cual
es ampliable a medida que la demanda lo requiera. En relacin al precio de este
combustible, se consider una proyeccin de acuerdo a lo indicado en el ANEXO
N1.

17.3.1.2 Centrales a Carbn

Otra de las opciones energticas analizadas tiene que ver con centrales que
utilizan carbn como insumo principal. A partir de los antecedentes disponibles por
esta Comisin, se conformaron proyectos tipo de distintas potencias, factibles de
ser localizados en la I y II regin del pas. Los costos de inversin de estos
proyectos incluyen el desarrollo de los puertos, necesarios para la descarga y
almacenamiento del carbn, y los costos de los equipos de mitigacin ambiental.

17.3.1.3 Centrales Elicas, Solares Fotovoltaicas y Geotrmicas

A partir de antecedentes disponibles por esta Comisin, se conformaron proyectos
elicos, solares fotovoltaicos y geotrmicos de diferentes potencias, factibles de
ser localizados en distintas regiones del pas.

Se han utilizado como factor de planta, un 30% para parques elicos y solares
fotovoltaicos y de 95% para centrales geotrmicas.

17.4.- Obras de Transmisin

En la elaboracin del presente estudio de expansin del SING se han considerado
las instalaciones de transmisin necesarias para el adecuado desarrollo del plan de
expansin de generacin.

En relacin a los proyectos de transmisin troncal, se consideraron los proyectos
sealados en el Decreto Exento N 82 del Ministerio de Energa, de fecha 29 de
febrero de 2012, el cual fija Plan de Expansin del Sistema de Transmisin Troncal
para los doce meses siguientes.

Asimismo, se consideraron en la presente fijacin, las obras incluidas en el Decreto
Exento N 310 del Ministerio de Energa, de fecha 29 de julio de 2013, que fija Plan
de Expansin del Sistema de Transmisin Troncal para los doce meses siguientes,
correspondiente al periodo 2012-2013.




Informe Tcnico Preliminar Abril 2014 COMISIN NACIONAL DE ENERGA
FONO (56-2) 2797 2612 - FAX (56-2) 2797 2600 CLASIFICADOR 14 - CORREO 21
E-MAIL: pnudo@cne.cl URL: http://www.cne.cl SANTIAGO - CHILE


32
CUADRO 18: PLAN DE OBRAS DE TRANSMISIN
Obras de Transmisin Tipo
Potencia
Neta
[MVA]
Fecha
Puesta En
Servicio
S/E Seccionadora Nueva Encuentro 220 kV. En construccin - oct-15
Ampliacin SE Lagunas 220 kV, Banco de condensadores de 60
MVAr y cambio TTCC paos J 1 y J 2.
En construccin - may-15
Ampliacin S/E Encuentro 220 kV, aumento de capacidad de
lnea 2x220 Crucero-Encuentro y cambio TTCC y trampa de onda
pao J 5 S/E Crucero.
En construccin 1.000 feb-16
Nueva Lnea 2x220 kV Encuentro - Lagunas, primer circuito. En construccin 290 abr-17
Tendido segundo circuito lnea 2x220 kV Encuentro - Lagunas (*) En construccin 290 abr-17
Nueva Subestacin Crucero Encuentro (*) En construccin - oct-17
Nueva Lnea 2x220 kV Tarapac - Lagunas, primer circuito. Recomendadas 254 ago-18
(*) Obra cuya construccin se encuentra en proceso de Publicacin de Decreto.

Adicionalmente se ha considerado en la simulacin de ambos sistemas una lnea
de interconexin de 1.500 MW entre el Sistema Interconectado Central (SIC) y el
Sistema Interconectado del Norte Grande (SING) a partir de enero de 2021, entre
las subestaciones Nueva Encuentro del SING y Nueva Cardones del SIC.

17.5.- Escenario de Demanda

El escenario de demanda considerado en los planes de expansin analizados,
corresponden a la proyeccin de demanda presentada en la seccin 2 del presente
informe.
17.6.- Precios de Combustibles

Para los distintos combustibles utilizados, se han considerado los criterios y precios
de combustibles sealados en el punto 6 del presente informe.

17.7.- Costos y Criterios de Localizacin de Centrales

Para determinar la localizacin indicativa de las centrales de generacin, esta
Comisin tuvo en vista los antecedentes indicados en el punto 17.3.1 del presente
Informe.

Los costos de inversin considerados para las instalaciones de generacin se
determinaron a partir del estudio de los valores informados por las empresas que
actualmente tienen instalaciones en construccin, as como tambin de la
informacin recabada relativa a los proyectos en estudio. Para proyectos de
centrales a carbn, los costos de inversin incluyen la realizacin de puertos
necesarios para la descarga y almacenamiento del carbn, y los costos de los
equipos de mitigacin ambiental. Por su parte, los costos de inversin de
proyectos hidroelctricos, de manera referencial, incluyen los costos de
transmisin y los costos asociados al cumplimiento de la normativa ambiental, as
como otros costos de mitigacin. Por ltimo, los proyectos solares fotovoltaicos,
Informe Tcnico Preliminar Abril 2014 COMISIN NACIONAL DE ENERGA
FONO (56-2) 2797 2612 - FAX (56-2) 2797 2600 CLASIFICADOR 14 - CORREO 21
E-MAIL: pnudo@cne.cl URL: http://www.cne.cl SANTIAGO - CHILE


33
geotrmicos, biomasa y parques elicos, los costos de inversin incluyen la
subestacin y la lnea de conexin el sistema.

CUADRO N 19: COSTOS DE INVERSIN DE CENTRALES DE GENERACCIN POR TIPO DE
TECNOLOGA.
Tecnologa
Costo Unitario
de Inversin
[US$/kW]
Carbn 2.500
GNL 1.000
Hidro Pasada 2.100
Hidro Embalse 2.100
Elico 2.300
Solar Fotovoltaico 2.500
Geotrmica 3.550
Biomasa 3.125

Para el Costo de Operacin, Mantencin y Administracin de las instalaciones de
generacin, se utiliz como valor fijo equivalente al 2% del Costo de Inversin de
cualquier tipo de Central de Generacin.

17.8.- Resultados

El Programa de Obras ptimo correspondiente a la fijacin de precios de nudo de
abril de 2014 es el que a continuacin se indica :

CUADRO N 20: PLAN DE OBRAS EXPANSIN EN GENERACIN

Central Estado
Potencia
Neta [MW]
Tecnologa Barra de conexin
Fecha
puesta en
servicio
Portada En Construccin 3 Diesel La Portada 110 abr-14
Arica Solar 1 En Construccin 18 Solar Fotovoltaica Parinacota 066 abr-14
La Huayca En Construccin 9 Solar Fotovoltaica Pozo Almonte 066 abr-14
Quillagua I En Construccin 23 Solar Fotovoltaica Crucero 220 dic-14
Arica Solar 2 En Construccin 22 Solar Fotovoltaica Parinacota 066 may-14
La Huayca 2 En Construccin 21 Solar Fotovoltaica Pozo Almonte 066 may-14
Pozo Almonte 3 En Construccin 16 Solar Fotovoltaica Pozo Almonte 066 abr-14
Mara Elena En Construccin 71 Solar Fotovoltaica Crucero 220 sep-14
San Pedro 1 En Construccin 17 Solar Fotovoltaica Calama 110 sep-14
San Pedro 3 En Construccin 30 Solar Fotovoltaica Calama 110 sep-14
San Pedro 4 En Construccin 30 Solar Fotovoltaica Calama 110 sep-14
San Pedro 2 En Construccin 24 Solar Fotovoltaica Calama 110 nov-14
Calama Sur En Construccin 30 Solar Fotovoltaica Calama 110 nov-14
Quillagua II En Construccin 27 Solar Fotovoltaica Crucero 220 dic-15
Cochrane 1 En Construccin 236 Carbn Encuentro 220 may-16
Cochrane 2 En Construccin 236 Carbn Encuentro 220 oct-16
Kelar En Construccin 517 Gas Natural Atacama 220 oct-16
Quillagua III En Construccin 50 Solar Fotovoltaica Crucero 220 dic-16
Solar SING I Recomendadas 150 Solar Fotovoltaica Pozo Almonte 220 ene-21
Elico SING I Recomendadas 50 Elica Laberinto 220 mar-21
Geotrmica Irruputunco Recomendadas 50 Geotrmica Collahuasi 220 jun-21
Elico SING II Recomendadas 200 Elica Lagunas 220 jun-22
Solar SING II Recomendadas 150 Solar Fotovoltaica Lagunas 220 may-23
Geotrmica Puchuldiza 01 Recomendadas 40 Geotrmica Cerro Colorado 110 oct-23
Informe Tcnico Preliminar Abril 2014 COMISIN NACIONAL DE ENERGA
FONO (56-2) 2797 2612 - FAX (56-2) 2797 2600 CLASIFICADOR 14 - CORREO 21
E-MAIL: pnudo@cne.cl URL: http://www.cne.cl SANTIAGO - CHILE


34
18.- ANEXO N 6: ACTUALIZACIN VALOR COSTO DE FALLA DE LARGA
DURACIN.

18.1.- Introduccin

En base al Estudio Costo de Falla de Corta y Larga Duracin SIC, SING y SSMM
remitido a los CDEC con carta CNE N 324 de fecha 3 de agosto de 2012 para su
distribucin entre las empresas integrantes, se presenta la actualizacin del Valor
de Costo de Falla de Larga Duracin, conforme a la estructura aplicable indicada
en el Anexo N6 del Informe Tcnico de Precio de Nudo de octubre de 2013.

Conforme a lo anterior, el costo de falla medio del SING est determinado para
restricciones de 5, 10, 20 y 30%, y perodos de 1, 2 y 10 meses respectivamente.
Adicionalmente se utiliz ponderadores para cuatro sectores econmicos: sector
residencial, sector comercial, sector minero y empresas varias. Por ltimo, para
cada una de las cuatro componentes sealadas se indica su frmula de
indexacin, para finalmente determinar el costo de falla en el SING.

18.2.- Costo de Racionamiento por Sectores SING

Para la determinacin del valor actualizado del costo de racionamiento, se
procede a tomar las cuatro componentes que corresponden al sector Residencial,
Comercial y Minera y Empresas Varias y se multiplica cada costo de
racionamiento por su indexador correspondiente. Con ello se obtienen los costos
de racionamiento para cada sector, para todas las profundidades y duraciones de
racionamiento incluidas en el estudio.

A continuacin se muestran los Indexadores de los cuatro sectores econmicos
mencionados anteriormente.

CUADRO N 21: INDEXADORES PARA EL SING.

SECTOR MINERO (IM)
Profundidad 1 mes 2 meses 10 meses
5% 0,98 0,98 0,98
10% 0,95 0,95 0,94
20% 0,88 0,90 0,92
30% 0,86 0,88 0,91
EMPRESAS VARIAS (IV)
Profundidad 1 mes 2 meses 10 meses
5% 0,97 0,97 0,97
10% 0,95 0,95 0,95
20% 0,94 0,94 0,94
30% 0,92 0,93 0,94
SECTOR RESIDENCIAL (IB)
Informe Tcnico Preliminar Abril 2014 COMISIN NACIONAL DE ENERGA
FONO (56-2) 2797 2612 - FAX (56-2) 2797 2600 CLASIFICADOR 14 - CORREO 21
E-MAIL: pnudo@cne.cl URL: http://www.cne.cl SANTIAGO - CHILE


35
Profundidad 1 mes 2 meses 10 meses
5% 0,88 0,88 0,88
10% 0,88 0,88 0,88
20% 0,88 0,88 0,88
30% 0,88 0,88 0,88
SECTOR COMERCIAL (IC)
Profundidad 1 mes 2 meses 10 meses
5% 0,84 0,84 0,84
10% 0,84 0,84 0,84
20% 0,84 0,84 0,84
30% 0,84 0,84 0,84

El Costo de Racionamiento del Sistema se obtiene sumando los Costos indexados
de cada sector multiplicados por su importancia relativa. El Costo de
Racionamiento promedio indexado del Sistema se obtiene aplicando las
probabilidades de ocurrencia de cada escenario.



19.- ANEXO N 7: ALTERNATIVAS DE GENERACIN Y DE TRANSPORTE

Las alternativas de expansin se presentan en el Cuadro N 21. Asimismo, se
indica la fecha ms pronta de puesta en servicio de cada uno de los proyectos
considerados.

CUADRO N22: ALTERNATIVAS DE GENERACIN Y DE TRANSPORTE (CON GASTOS
FINANCIEROS)



En el proceso de optimizacin se consider aquellas alternativas de generacin
tcnica y econmicamente factibles de ser desarrolladas en el horizonte de
planificacin a utilizar. Similar criterio se aplic para las instalaciones de
transmisin.





PROYECTO CARACTERSTICAS
FECHA
PUESTA
SERVICIO
ZONA TENSIN/TIPO
Tarapaca 220->Lagunas 220 III 366 MVA ene-17 SING 220 kV
Nueva Mejillones 500->Nueva Encuentro 500 II 1500 MVA feb-20 SING 500 kV
Nueva Mejillones 220->Nueva Mejillones 500 I 750 MVA feb-20 SING
Cndores I 50 MW abr-15 SING Diesel
Cndores II 50 MW abr-15 SING Diesel
Mejillones I GNL 300 MW ago-19 SING GNL
LNEAS DE TRANSMISIN
CENTRALES DE GENERACIN
Informe Tcnico Preliminar Abril 2014 COMISIN NACIONAL DE ENERGA
FONO (56-2) 2797 2612 - FAX (56-2) 2797 2600 CLASIFICADOR 14 - CORREO 21
E-MAIL: pnudo@cne.cl URL: http://www.cne.cl SANTIAGO - CHILE


36
20.- ANEXO N 10: OBLIGACIN ERNC.

En virtud de la obligacin establecida en el artculo 150 bis del DFL N4 de 2006
del Ministerio de Minera, se han calculado los porcentajes de energa anual que
deben ser inyectados por medios de generacin renovables, de acuerdo a los
criterios sealados en el artculo 1 transitorio de la ley 20.257, modificado por el
artculo 2 de la ley 20.698, esto es:

- No hay obligacin para los retiros de energa cuyos contratos con su
suministrador fueron suscritos con anterioridad al 31 de agosto de 2007.

- Para los contratos celebrados con posterioridad al 31 agosto de 2007 y con
anterioridad al 1 de julio de 2013, la obligacin aludida ser del 5% para los
aos 2010 a 2014, aumentndose en el 0,5% anual a partir del ao 2015.
Este aumento progresivo se aplicar de tal manera que los retiros afectos a
la obligacin al ao 2015 debern cumplir con el 5,5%, los del ao 2016 con
el 6% y as sucesivamente hasta alcanzar el ao 2024 el 10%,

- Para los contratos firmados con posterioridad al 1 de julio de 2013, la
obligacin aludida ser del 5% al ao 2013, con incrementos del 1% a partir
del ao 2014 hasta llegar al 12% el ao 2020, e incrementos del 1,5% a
partir del ao 2021 hasta llegar al 18% el ao 2024, y un incremento del 2%
al ao 2025 para llegar al 20% el ao 2025.

En vista de estos criterios, de la proyeccin de demanda, y de los antecedentes
con la informacin referente a la fecha de suscripcin de los contratos entre
clientes y suministradores, se detalla en el Cuadro N36 el porcentaje estimado
de inyeccin ERNC en relacin a la energa total inyectada necesaria para cumplir
con la obligacin ya mencionada. Cabe sealar que se incorporaron dentro del
plan de obras recomendado instalaciones necesarias para el cumplimiento de
dicha obligacin.

CUADRO N 23: ESTIMACIN OBLIGACIN DE INYECCIN ERNC.

2014 2015 2016 2017 2018 2019 2020 2021 2022 2023
SING 2,9% 3,3% 4,2% 5,0% 5,9% 6,7% 7,9% 9,1% 9,8% 10,6%
SIC 3,5% 4,1% 4,9% 5,4% 6,1% 6,9% 8,6% 10,2% 12,1% 14,1%
SING+SIC 3,4% 3,9% 4,7% 5,3% 6,1% 6,9% 8,4% 9,9% 11,5% 13,1%