S.N.

PENDING WORKS STATUS


7.1 CONTROL ROOM
7.2 TOILET WORKS
1. WASH BASIN Not Complete
2. EXHAUST FAN Not Complete
3. WATER CLOSET Not Complete
4. DOORS ( D3, 800 X 2.100 ) Not Complete
7.2 PANTRY ROOM WORKS
1. EXHAUST FAN Not Complete
2. KITCHEN SINK Not Complete
3. DOORS ( D3, 800 X 2.100 ) Not Complete
7.3 BATTERY ROOM
1. DOOR ( D2 , SIZE 1200 X 2100 ) Not Complete
2. FALSE CEILING Not Complete
7.4 FLOORING WORKS
1. EPOXY PAINT completed
7.5 PLUMBING WORKS
1. INSPECTION CHAMBER Not Complete
2. PVC PIPE Not Complete
7.6 FENCING WORKS
1. CHAIN LINK FENCE UNDER CONTROL
ROOM WITH PEDESTRIAN GATE Not Complete
7.7 External wall Sand lime Bricks Not Complete (RECTIFY )
7.8 GYPSUM WORKS
GYPSUM WALL RECTIFY
10 MOTOR CONTROL CENTER ( MCC )
10.1 BATTERY ROOM
1. TILES Not Complete
2. EXHAUST FAN Not Complete
3. WASH BASIN Not Complete
4. LOUVRE WINDOW Not Complete
10.2 FLOORING WORKS
1. THRESHOLD FOR DOORS Not Complete
2. EPOXY PAINT Not Complete
10.3 FENCING WORKS
1. CHAIN LINK FENCE UNDER CONTROL
ROOM WITH PEDESTRIAN GATE Not Complete
TV BUILDING PENDING WORKS
QUANTITY REMARKS
I nos.
1 nos.
1 nos.
2 nos.
1 nos.
1 nos.
1 nos.
1 nos.
8.64 M
1 nos. concrete
LUMPSUM
PERIMETER LENGTH 44.28 WITH
2 NOS. OF GATE
22.437 M
2.5 M
45 M Anti Acid Tiles
1 NOS
1 NOS
1 NOS
Same quantity of Doors / Lintel
beam
( area=232 m )
perimeter length 76.852 m with 2
nos. of gate
TV BUILDING PENDING WORKS
Sl.No.
KOC
Punch
Sl. No.
Punch Description Rectification Action
64 Entry gates are still pending.
65
Control room toilet / bath room
works and soak-pit for sewage
disposal is pending
66
Platform grating to be
completed near TV compressor
area.
67
Platform and ladder to be
provided for PA receiver and
N2 receiver. Platform grating
to be completed for IA
receiver.
68
Egg barrel sump : Ladder and
grating or railing is pending
69
Platform ladders : Foot rests to
be provided.
70
Access road need to be
properly leveled and marked
71
Support at the base for all
stairs and crossovers are not
completed
72
foundation for seal pot is
missing
73
piping trench cover is missing
in GEG area
74
Pits for corrosion coupon and
probes are not provided
Manpower Quantity
Mr.Rasul
Carpenter 1 , mason 1,
labour 2.
3 Main gate and
2 pedestrian
gate/Concrete k-
350 apprx. 4 m3
Mr.Rasul _ _
Mr.Rasul _ _
Mr.Rasul _ _
Mr.Rasul _ _
Mr.Rasul
Mason 1 , Carpenter 1,
Steel Fixer
4 meter cubic
Mr.Rasul
Heavy Duty driver,
labours 2
lumpsum for
gatch
Mr.Rasul _ _
Mr.Rasul _ _
Mr.Rasul _ _
Mr.Rasul _ _
Responsible person (s)
Duration Remarks
1 week
_
see attach excel
sheet/ check with
new
subcontructor
_
To be provided by
mechanical /
fabshop
_
To be provided by
mechanical /
fabshop
_
To be provided by
mechanical /
fabshop
5 days
4 days
_
repeat point from
69 above
_ Done
_
To be provided by
mechanical /
fabshop
_
Drawing for
corrosion coupon
is not available