BIM Use in Construction

Presentation to ASM
March 10 2010 March 10, 2010
Christopher Fogg
Virtual Engineer
BIM Use In Construction
Agenda | About Bond| Services | Preconstruction| Construction| Expectations
AGENDA
Goals and Objectives j
Preconstruction Services
Construction Analysis & Planning
Schedule Simulations
Construction Services
Interference Detection / Avoidance
Red Line Comments Red Line Comments
Layout Dimensioning
Visualization
Progress Simulations Progress Simulations
Facility Access Management
BIM Use In Construction
Agenda | About Bond| Services | Preconstruction| Construction| Expectations
FACTS & FIGURES
103years old 103 years old
Total staff: 300+
Bonding capacity:
Si l j t $500 Milli
Roger Williams University
Residence Hall
Single project: $500 Million
Total program: $1 Billion
Project size ranging from $100,000 to
$250Million Perkins +Will $250 Million
Markets
Institutional
Health Care Health Care
Corporate
Energy
Heavy Civil
Massachusetts Institute of Technology
Media Lab
Maki Associates with Leers Weinzapfel
Heavy Civil
BIM Use In Construction
Agenda | About Bond| Services | Preconstruction| Construction| Expectations
Building, Civil &Utility Construction
SERVICES
Building, Civil & Utility Construction
Preconstruction
Construction Management
General Contracting General Contracting
Facilities Asset Management
Self Performing Civil & Utility Capabilities
BIM Use In Construction
Agenda | About Bond| Services | Preconstruction| Construction| Expectations
VALUE ADDED SERVICES
BuildingInformation Modeling Building Information Modeling
LEED Consulting
Budget & Logistics Planning
Grant Funding Assistance Grant Funding Assistance
Feasibility Studies
Cost Modeling
24 7Emergency Services 24-7 Emergency Services
O&M Ready
BIM Use In Construction
Agenda | About Bond| Services | Preconstruction| Construction| Expectations
Estimating
QUALITY
TECHNOLOGY
Scheduling
Interference Detection
Coordination
Building Information Modeling (BIM) is not a piece
of software. It is a belief in collaboration for the
greater good of the project through the open
sharingof informationsupportedby software
Logistics
sharing of information supported by software.
Christopher Fogg
Virtual Engineer
BIM Use In Construction
Agenda | About Bond| Services | Preconstruction| Construction| Expectations
CONSTRUCTION ANALYSIS & PLANNING
Logistics
Existing Conditions
Mobilization
Truck Routes
Excavation
Foundations
Steel Erection
Exterior Envelope
MEP Equipment / Systems
Interior Finishes
Site Improvements
BIM Use In Construction
Agenda | About Bond| Services | Preconstruction| Construction| Expectations
CONSTRUCTION ANALYSIS & PLANNING
BIM Use In Construction
Agenda | About Bond| Services | Preconstruction| Construction| Expectations
CONSTRUCTION ANALYSIS & PLANNING
Phasing
Step 3
Remove Temporary Footing
Remove TemporarySteel
Add Permanent Infill Steel
Step 1
Add Temporary Footing
Add Temporary Steel
Step 2
Cut Existing Column
Add Permanent Footing
Add Permanent Steel
BIM Use In Construction
Agenda | About Bond| Services | Preconstruction| Construction| Expectations
CONSTRUCTION ANALYSIS & PLANNING
Animations of critical elements
BIM Use In Construction
Agenda | About Bond| Services | Preconstruction| Construction| Expectations
SCHEDULE SIMULATION
Transform the standard bar chart schedule into a visual tool
BIM Use In Construction
Agenda | About Bond| Services | Preconstruction| Construction| Expectations
INTERFERENCE DETECTION / AVOIDANCE
Coordinationof the MEP systems with: Coordination of the MEP systems with:
Building Architecture
Structural Slabs and Walls
BelowGrade Mechanical Systems Below Grade Mechanical Systems
Structural Steel
Overhead Mechanical Systems
BIM Use In Construction
Agenda | About Bond| Services | Preconstruction| Construction| Expectations
INTERFERENCE DETECTION / AVOIDANCE
Steel fabrication / penetrations Steel fabrication / penetrations
BIM Use In Construction
Agenda | About Bond| Services | Preconstruction| Construction| Expectations
RED LINE COMMENTS
BIM Use In Construction
Agenda | About Bond| Services | Preconstruction| Construction| Expectations
LAYOUT DIMENSIONING
Complex openings
Slab edges
Walls
Superstructure
Everything can be dimensioned in 3D
BIM Use In Construction
Agenda | About Bond| Services | Preconstruction| Construction| Expectations
LAYOUT DIMENSIONING
Unlimitedviews / sections Unlimitedviews / sections
BIM Use In Construction
Agenda | About Bond| Services | Preconstruction| Construction| Expectations
VISUALIZATION
2D Traditional Subcontractors Submitted Coordination Drawing
BIM Use In Construction
Agenda | About Bond| Services | Preconstruction| Construction| Expectations
VISUALIZATION
Traditional engineers comments
BIM Use In Construction
Agenda | About Bond| Services | Preconstruction| Construction| Expectations
VISUALIZATION
Modeled view for increased accuracy and efficiency
BIM Use In Construction
Agenda | About Bond| Services | Preconstruction| Construction| Expectations
PROGRESS SIMULATIONS
Track Progress Track Progress
Identify Deficiencies
BIM Use In Construction
Agenda | About Bond| Services | Preconstruction| Construction| Expectations
FACILITY ASSET MANAGEMENT
Maintenance / Service Zones Of Influence Maintenance / Service Zones Of Influence
BIM Use In Construction
Agenda | About Bond| Services | Preconstruction| Construction| Expectations
FACILITY ASSET MANAGEMENT
Access zones in ceilings Access zones in ceilings
BIM Use In Construction
Agenda | About Bond| Services | Preconstruction| Construction| Expectations
EXPECTATIONS
What does BOND expect from our subcontractors?
Keep an open mind
Participate in coordination meetings
Share your experience and expertise
Subcontractor Benefits:
Better understanding of
the project
Greater productivity
Reduced change orders
BIM Use In Construction
ASM Presentation
03-10-10
Ch i t h F Christopher Fogg
Virtual Engineer
cfogg@bondbrothers.com
Thank you. y