1 Construction Of ONE KANNAL HOUSE

1.1 Initiation
1.1.1 Plot Possession
1.1.2 Designing & Planning
1.1.3 Lay-out Plan
1.1.4 Site Clearance
1.1.5 Inauguration
1.1.6 Procurements
1.1.6.1 Procure Cement for Store
1.1.6.2 Procure Bricks for Store
1.1.6.3 Procure Sand Ravi
1.1.6.4 Procure BrickBat
1.2 Ground Mobilization
1.2.1 Store Construction
1.2.2 Request water connection
1.2.3 Request Tele connection
1.2.4 Request Temp Electric connection
1.2.5 Site clearing and grubing
1.2.6 Site grading & marking
1.3 Construction upto DPC
1.3.1 Procurements
1.3.1.1 Procure Ghassu
1.3.1.2 Procure Cement
1.3.1.3 Procure Bricks
1.3.1.4 Procure Sand Ravi
1.3.1.5 Procure Termite Proofing
1.3.2 Excavation
1.3.3 Termite Proofing
1.3.4 Lean Laying
1.3.5 Brick Work upto DPC
1.3.6 DPC
1.3.7 DPC MS
1.3.8 Ghassu Filling in Foundation
1.4 Construction upto Ground Floor Roof
1.4.1 Procurements
1.4.1.1 Procure Cement
1.4.1.2 Procure Steel and Steel Fixer
1.4.1.3 Procure Bricks
1.4.1.4 Procure Sand Ravi
1.4.1.5 Procure Sand Chenab
1.4.1.6 Procure Crush
1.4.1.7 Procure Elec Pipe Conduit
1.4.1.8 Water Supply / gas Pipes (PPRC+GI)
1.4.2 Brickwork upto Lintel Level
1.4.3 RCC of Lintels at Doors and Windows
1.4.4 Brickwork upto Ceiling
1.4.5 Shuttering at GF Roof
1.4.6 Steel Fixing at GF Roof
1.4.7 Concrete Pouring for Roof at GF
1.4.8 Curing Time for Roof
1.4.9 Electrical Pipe conduit
1.4.10 Internal Plumbing of GF
1.4.11 Internal Wall Plastering GF
1.4.12 GF Chowghats
1.4.13 GF Floor PCC
1.5 Construction upto First Floor Roof
1.5.1 Procurements
1.5.1.1 Procure Cement
1.5.1.2 Procure Steel and Steel Fixer
1.5.1.3 Procure Bricks
1.5.1.4 Procure Sand Ravi
1.5.1.5 Procure Sand Chenab
1.5.1.6 Procure Crush
1.5.1.7 Procure Elec Pipe Conduit
1.5.1.8 Water Supply / gas Pipes (PPRC+GI)
1.5.2 Brickwork upto Lintel Level
1.5.3 RCC of Lintels at Doors and Windows
1.5.4 Brickwork upto Ceiling
1.5.5 Shuttering at FF Roof
1.5.6 Steel Fixing at FF Roof
1.5.7 Concrete Pouring for Roof at FF
1.5.8 Curing Time for Roof
1.5.9 Electrical Pipe conduit
1.5.10 Internal Plumbing of FF
1.5.11 Internal Wall Plastering FF
1.5.12 FF Chowghats
1.5.13 FF Floor PCC
1.6 Procurement Assignments
1.6.1 Assign Marble
1.6.2 Assign Granite for Podium + Stairs
1.6.3 Assign Tiles Floor / Kitchen
1.6.4 Assign Tiles Bath
1.6.5 Assign Lamination Floo
1.6.6 Assign Ash Wood for Door
1.6.7 Assign Ash Wood for chowghat
1.6.8 Assign Lamination for Wardrobe
1.6.9 Assign Wood for Door
1.6.10 Assign Wood for Main Doo
1.6.11 Assign Door's and Wardrobe's Handles, hinges, catcher and Lock
1.6.12 Assign for Lamination TV / LCD
1.6.13 Misc Works
1.6.13.1 Parapet Wall
1.6.13.2 Water Tank on the roof
1.6.13.3 Water Proofing Treatment at Roof
1.6.13.4 Boundry Wall & Gate Pillars
1.6.13.5 External Plaster Building Walls
1.6.13.6 External Plaster Bdry Wall , Gate (I /O)
1.6.13.7 Under Ground Water Tank
1.6.13.8 Sewer Works outside
1.6.13.9 Plumbing Outside
1.6.13.10PCC in galleries & Porch
1.6.13.11Finish Works in Plaster
1.7 Tile Works
1.7.1 GF Bath Tiles Wall
1.7.2 FF Bath Tiles Wall
1.8 Bath
1.9 Bath Tiles
1.10 Bath Sanitar
1.11 Bath Accessories
1.12 Bath Vanitie
1.13 Bath Tubs & Cabins
1.14 Bath Glass partition
1.15 Bath Falce Ceiling
1.16 Bath Looking Mirro
1.17 Kitchen
1.18 Kitche
1.19 Kitchen Accessorie
1.20 Kitchen Floor Tile
1.21 Kitchen Wall Tiles
1.22 Hood + Koria
1.23 Fridge + Freezer
1.24 Electric
1.25 Fans Roo
1.26 Fans Bracket
1.27 Fans Exhaust
1.28 Tube light
1.29 Picture Lights
1.30 Swithe
1.31 Bulbs / Energy Saver
1.32 Shanglie
1.33 Accessorries
1.34 LCD + Home Theater
1.35 Flooring
1.36 Floor Tile
1.37 Floor Marble
1.38 Stair Granit
1.39 Floor Granit
1.40 Floor Mossai
1.41 Lamination Woo
1.42 Aluminum
1.43 Aluminium Material
1.44 Aluminium Glas
1.45 Stair Railin
1.46 Terrace Railin
1.47 Wood Wor
1.48 Door Wood Main
1.49 Doors Wood
1.50 Wardrobe
1.51 Door Hardwar
1.52 Wardrobe Hardwar
1.53 Glass on wardrobes
1.54 Decoration
1.55 False Ceilin
1.56 Grinding & Polis
1.57 Internal Paint
1.58 Ext Graphy
1.59 Wall Paper
1.60 Out-Skirts
1.61 Main + Wicket Gate
1.62 Gate Light
1.63 Ramp Const
1.64 Porch Decoration
1.65 Bndry wall
1.66 Manhole covers
1.67 Horticulture
1.68 Gras
1.69 Plants
1.70 Water-fall
1.71 Misc Expdr
1.72 Monthly Elec Bil
1.73 Pay Chowkida
1.74 Site Expdr
1.75 Final Preparations
1.76 Elec Connectio
1.77 Gas Connection
1.78 Sewage Connectio
1.79 As Built Dwg
1.80 Final Handing Over
1.81 Refreshments
1.82 Labour
1.83 Excavation
1.84 Electricia
1.85 Plumbe
1.86 Brick Bat Compaction
1.87 Civil Works La
1.88 Steel Fixe
1.89 Nishes wor
1.90 Bath Labou
1.91 Aluminium Labour