You are on page 1of 1

Activity ID Activity Name Original

Duration
Planned
Start
Planned
Finish
Mobilization Plan for Earthworks PDO North Oman - Qarnalam Mobilization Plan for Earthworks PDO North Oman - Qarnalam 173d 15-Dec-14 05-Jun-15
Mobilization of Contract Key & Core Personnel Mobilization of Contract Key & Core Personnel 18d 15-Dec-14 01-Jan-15
A1000 Notification for Key & Core Personnel 1d 15-Dec-14 15-Dec-14
A1010 HSE Tr aining for All Personnel 14d 16-Dec-14 29-Dec-14
A1020 Mobilization of HSE Trained Per sonnel 14d 19-Dec-14 01-Jan-15
A1030 PDO Assessment for Key & Core Personnel (If Required) 7d 26-Dec-14 01-Jan-15
PDO Approval for Industrial & Residential Facilities PDO Approval for Industrial & Residential Facilities 23d 02-Jan-15 24-Jan-15
A1040 Internal Inspection for Existing Industrial & Residential Facilities 4d 02-Jan-15 05-Jan-15
A1050 Renting / Leasing the Industrial & Residential Facilities 2d 06-Jan-15 07-Jan-15
A1060 Renovation of the Rented Leased Facilities 7d 08-Jan-15 14-Jan-15
A1070 Arranging Water, Electricity & Waste Management from PDO 7d 15-Jan-15 21-Jan-15
A1080 PDO Inspection for the Renovated Facilities 2d 22-Jan-15 23-Jan-15
A1090 PDO Approval for the Inspected Facilities 1d 24-Jan-15 24-Jan-15
Contract HSE & Quality Plans Contract HSE & Quality Plans 8d 02-Jan-15 09-Jan-15
A1100 Submission of Contract HSE Plan 1d 02-Jan-15 02-Jan-15
A1110 Submission of Contract Quality Plan 1d 02-Jan-15 02-Jan-15
A1120 PDO Review of Submitted Plans 6d 03-Jan-15 08-Jan-15
A1130 Getting PDO Approval for the Reviewed Plans 1d 09-Jan-15 09-Jan-15
Mobilization of Vehicle, Plant & Equipments Mobilization of Vehicle, Plant & Equipments 133d 16-Dec-14 27-Apr-15
A1140 Procurement/ Hiring of Vehicle, Plant & Equipments 120d 16-Dec-14 14-Apr-15
A1150 Fixing PDO Specifications 120d 16-Dec-14 14-Apr-15
A1160 Internal Inspection for the Vehicle, Plant & Equipments 120d 21-Dec-14 19-Apr-15
A1170 Mobilization of Inspected EVPs 120d 23-Dec-14 21-Apr-15
A1180 PDO Inspection for the Vehicle, Plants & Equipments 120d 27-Dec-14 25-Apr-15
A1290 Getting PDO Approval for Inspected EVSs 120d 29-Dec-14 27-Apr-15
A1300 Dispatch to Site Locations 120d 29-Dec-14 27-Apr-15
Mobilization of Construction Crews Mobilization of Construction Crews 172d 16-Dec-14 05-Jun-15
Assigning Construction Crews Assigning Construction Crews 120d 16-Dec-14 14-Apr-15
A1190 HSE Tr aining for t he Constr uction Crews 120d 16-Dec-14 14-Apr-15
A1200 Recruting / Hiring PDO Approved Permit Holders & Applicants 15d 31-Dec-14 14-Jan-15
A1210 Assigning Crews for Individual Location / Activities 120d 16-Dec-14 14-Apr-15
Dispatching Construction Crews Dispatching Construction Crews 162d 26-Dec-14 05-Jun-15
A1230 Earth Work Crews for Qarnalam Field 7d 26-Dec-14 01-Jan-15
A1240 Structure Work Crews for Qarnalam Field 7d 02-Jan-15 08-Jan-15
A1250 Earth Work Crews for Musallam Field 7d 04-Feb-15 10-Feb-15
A1260 Structure Work Crews for Musallam Field 7d 11-Feb-15 17-Feb-15
A1270 Road Work Crew for the Contract 7d 30-May-15 05-Jun-15
A1280 Civil Crew for Concrete Precast Yard 7d 15-Jan-15 21-Jan-15
Engineering & Construction Engineering & Construction 7d 26-Dec-14 02-Jan-15
A1310 Start of Engineering Activities 0d 26-Dec-14
A1320 Start of Construction Activities 0d 02-Jan-15
1 2 3 4 5 6 7
8
Month
05-Jun-15, Mobilization Plan for Earthworks PDO North Oman - Qarnalam
01-Jan-15, Mobilization of Contract Key & Core Personnel
Notification for Key & Core Personnel
HSE Tr aining for All Personnel
Mobilization of HSE Trained Per sonnel
PDO Assessment for Key & Core Personnel (If Required)
24-Jan-15, PDO Approval for Industrial & Residential Facilities
Internal Inspection for Existing Industrial & Residential Facilities
Renting / Leasing the Industrial & Residential Facilities
Renovation of the Rented Leased Facilities
Arranging Water, Electricity & Waste Management from PDO
PDO Inspection for the Renovated Facilities
PDO Approval for the Inspected Facilities
09-Jan-15, Contract HSE & Quality Plans
Submission of Contract HSE Plan
Submission of Contract Quality Plan
PDO Review of Submitted Plans
Getting PDO Approval for the Reviewed Plans
27-Apr-15, Mobilization of Vehicle, Plant & Equipments
Procurement/ Hiring of Vehicle, Plant & Equipments
Fixing PDO Specifications
Internal Inspection for the Vehicle, Plant & Equipments
Mobilization of Inspected EVPs
PDO Inspection for the Vehicle, Plants & Equipments
Getting PDO Approval for Inspected EVSs
Dispatch to Site Locations
05-Jun-15, Mobilization of Construction Crews
14-Apr-15, Assigning Construction Crews
HSE Tr aining for t he Constr uction Crews
Recruting / Hiring PDO Approved Permit Holders & Applicants
Assigning Crews for Individual Location / Activities
05-Jun-15, Dispatching Construction Crews
Earth Work Crews for Qarnalam Field
Structure Work Crews for Qarnalam Field
Earth Work Crews for Musallam Field
Structure Work Crews for Musallam Field
Road Work Crew for the Contract
Civil Crew for Concrete Precast Yard
02-Jan-15, Engineering & Construction
Start of Engineering Activities, 26-Dec-14
Start of Construction Activities, 02-Jan-15

MARMUL CONTRACTING & TRADING COMPANY LLC.

Mobilization Plan for Earthworks PDO North Oman -


Qarnalam
Client: Petroleum Developement Oman
24-May-14
Actual Level of Effort
Actual Work
Remaining Work
Critical Remaining Work
Milestone
summary
Page 1 of 1 TASK filter: All Activities