1. Content...1 2. Overview...2 3. SMS 2 2.1 Working & Charging..3 2.2 Data Sheet Of Heat4 2.3 Observations SMS 2..6 4. SMS 3 4.1 Data Sheet Of Heat...7 4.2 Observations SMS 310
OVERVIEW :
JSPL has two SMSs in working i.e. SMS-2 & SMS-3. SMS feeds on hot metal coming from the blast furnace. Hot metal is transferred through Torpedo of capacity 350T. Hot metal from torpedo is poured in the ladle of 100T and transferred to EAF (Electric Arc Furnace) by hot metal car. In EAF, majorly percentage of carbon, silicon, phosphorous is controlled. It is then transferred to LRF ( Ladle Refining Furnace ) for chemistry control i.e. controlling composition of other elements in hot metal, then according to requirement hot metal is transferred to VD ( Vaccume Degaser ) and R-H Degaser ( only for rails). After attaining required temperature for casting, hot metal ladle is send for casting to slab caster and combi caster.
SMS-2 :
After pouring hot metal in ladle from torpedo, it is weighed and then sent to EAF. Charging materials of EAF are hot metal from Blast Furnace, Scrap (if taken on requirement ), DRI, Lime Stone, Dolomite and Carbon ( as CPC ). Working and Charging sequence of EAF :- 1. After tapping of heat and slag from previous heat, scrap is added at first to hot heal left in the furnace. Adding scrap at first gets more time for melting of solid scrap pieces till starting of arcing. Scrap charging is done from top and slowly, otherwise causes damage to refractory lining.
2. After that hot metal is poured in vessel of EAF. Generally it is done through launder car and hot metal is poured through slag door but to minimize pouring time sometimes done from top. It harms the refractory lining and requires regular coating of refractory lining.
3. When pouring is done through launder car and nearly 20-30T of hot metal is poured, then arcing is started immediately to reduce tap to tap time. In this case immediately after scrap charging DRI is charged as it acts as cushion for electrodes during arcing and protects from damage.
4. Charging of limestone, dolomite and DRI is done continuously during process and is not done all at a time because it reduces the dissolving and melting of charge takes longer time, hence increases tap to tap time.
5. Oxygen lancing is started after 3-4 min of power on. Before that lances were in burning + lancing mode to additional heat for scrap melting.
6. Carbon jet is used to produce foamy slag. It is started as per requirement. If slag removal is continuous and foamy, carbon jet is not used.
7. After 25-30min of power on, temperature tip and sampling tip is used to read temperature and take samples of heat.
8. Celox tips are also used to get instantaneous reading of carbon%, temperature and oxygen ppm ( parts per million ).
9. After attaining required temperature, C% and P% heat is tapped in ladle which is already Argon gas purged. During heat tapping, ferroalloy addition, Al and carbon addition is done. Nearly 70% of addition is done here to save processing time in LRF.
DATA SHEET OF 2 HEATS FROM EAF OF SMS-2 :- Heat No. 2207865 MS Scrap 3.0T Pig Iron 4.0T HBI (Hot Briquetted Iron) 3.0T Skull 5.0T Hot Metal 67T Sponge Iron (Lumps) 34T Sponge Iron (fines) 25T Oxygen consumption 5492Nm 3 Electrical Energy Consumption 40383Kwh CPC ( Calcined Petroleum Coke) 971kg Lime 5.2T Dolomite 4.3T Temperature tips 4 Sample tips 2 Celox 2 Lime Stone Chips 2.2T Arcing Duration 38min Tap to Tap time 57min
Heat No. 2207866 MS Scrap 3.0T Pig Iron 4.0T BF Skull 3.0T Skull 5.0T Hot Metal 66T Sponge Iron (Lumps) 34T Sponge Iron (fines) 15T Oxygen consumption 4892Nm 3 Electrical Energy Consumption 43614Kwh CPC ( Calcined Petroleum Coke) 1257kg Lime 5.6T Dolomite 4.9T Temperature tips 4 Sample tips 2 Celox 2 Lime Stone Chips 2.1T Arcing Duration 40min Tap to Tap time 54min
OBSERVATIONS SMS 2 :-
1. In furnace where top pouring is done, after regular heats refractory material is coated on upper shell to protect it from splashes of hot metal during pouring.
2. Arcing is started with long arc i.e. metal pouring and scrap melting is in process for very short durations, then move to short arc, so as to provide more energy to produce heat.
3. As process moves towards completion, power is not lowered as in theory to use more of chemical energy produced and lower the electrical power use. As by doing this tap to tap time comes down.
4. As addition of DRI, limestone and dolomite is continous process but all quantity is added in first 25min after power on time.
5. Life of EBT is measured by the tapping time. Normal tapping time is 4min. if taping time is less then 4min than this decrease in time shows increase in diameter of EBT due to erosion caused by tapping of metal.
6. Electrode consumption is about 1.6kg/ton of hot metal.
7. Oxygen Lancing is readily done in these three modes. (i)Lower mode 800Nm 3
(ii)Pilot mode 1500Nm 3
(iii)Lancing mode 1800Nm 3
After percentage of carbon and phosphorus is achieved, hot metal is tapped in ladle during which around 70% of ferroalloy addition is done. After tapping, ladle is taken to the LRF for chemistry control.
SMS-3 : SMS 3 consists of one EAF of 100T , two LRF (one in working other in erection ), one Vacuum Degasser and one Combi Caster. Working of EAF in SMS 3 is same as in SMS 2, difference is in design of EAF which increases its efficiency i.e. more efficient than EAF of SMS 2. Here EAF doesnt have Virtual Lance Burning unit which removes oil consumption. Only Oxygen Lancing and carbon jet is used for making heat. DATA SHEET OF 2 HEATS FROM EAF OF SMS-3 :-
Heat No. 4208401 MS Scrap 24T BF Skull 17T Hot Metal 48T Sponge Iron 33T Sponge Iron (fines) 6T EBT Filling 150kg Oxygen Consumption 2825Nm 3
Power Consumption 45698kwh CPC Consumption 694kg Lime 4T Dolomite 4T Temperature Tips 4 Sampler Tips 1 Celox 0 Arcing Duration 39min Tap to Tap time 56min Tap Temperature 1620 0 C Composition (%) : C 0.197 Si 0.2244 Mn 1.35 S 0.0234 Al 0.0517 Cr -0.175 V 0.0018 Mo 0.0842 Nb 0.0008 Ti 0.0024 B 0.0005 Ca 0.0003 Ni 0.0098 Sn 0.0022 As 0.0008 Zr 0.0002 Sb 0.0004 Pb 0.0003 Co 0.0038 Fe 97.8366 P 0.0156 Cu 0.0099 N 0.0081 W 0.0008
Heat No. 4208427 MS Scrap 23T HBI 3T Hot Metal 50T Sponge Iron 49T Sponge Iron (fines) 5T EBT Filling 150kg Oxygen Consumption 2925Nm 3
Power Consumption 43774kwh CPC Consumption 460kg Lime 4T Dolomite 4T Temperature Tips 4 Sampler Tips 1 Celox 1 Arcing Duration 38.50min Tap to Tap time 55min Tap Temperature 1620 0 C Composition (%) : C 0.045 Si 0.0967 Mn 0.25 S 0.026 Al 0.013 Cr -0.0083 V 0.0005 Mo 0.001 Nb 0.0003 Ti 0.0008 B 0.0003 Ca 0.0002 Ni 0.0078 Sn 0.0012 As 0.0009 Zr 0.0003 Sb 0.0004 Pb 0.0002 Co 0.003 Fe 99.5199 P 0.0127 Cu 0.0049 N 0.0059 W 0.0007
OBSERVATIONS SMS 3 :-
1. In foamy slag practice, electrode arcing is submerged, hence its electrical power efficiency is increased. Heat loss is also minimized as it acts as a blanket.
2. Sample tips are always used above 1550 o C because below this temperature sample consists of blowholes and sparking at blowholes gives variable C% and non-uniform results.
3. If slag temperature is not constant & low throughout process, then phosphorus gets reverted. Therefore DRI should be uniformly & evenly charged during entire process.
4. Great Melting Practice Synchronization between temperature required & required C%. (a) If carbon % is achieved earlier to temperature, then O 2 ppm increases in hot metal and effects refractory lining. (b) If temperature is achieved earlier to C%, then time loss occurs as lances are on & arcing is powered off.
5. For low N 2 heat, energy should be provided by O 2 lancing & not by arcing, as arcing ionizes air and increases N 2 dissolving in heat.
6. For V.D. heat quantity of hot metal in ladle should be low because during vacuum degassing when vacuum is applied for degassing effective volume of hot metal increases as gases try to escape through surface of hot metal by making it foamy.
7. In scrap bucket preparation large and course forms & carbon and lime are placed at bottom where as fine scrap at top or upper part of bucket.
8. If slag volume is less in hot metal during arcing then splashing of hot metal & loss of energy takes place. This happens readily in case of new bottom shell, as effective working volume is less & therefore most of slag gets drained during tapping. The remedy for this is to keep the hot metal quantity less for some heats, later size of heat can be increased.