Professional Documents
Culture Documents
Site
Standards & Guidelines
for
Consultants & Contractors
Foreword
Table of Contents
PRELIMINARIES
LIFTING OPERATIONS
CONSTRUCTION OPERATIONS
WORKING AT HEIGHT
SPECIAL PROCESSES
Municipalities & Agricultural Department
H&S Construction Codes of Practice
PART TWO
Foreword
In an industry such as ours with its diversity of activities, personal injury and health risks are,
unfortunately, an ever present hazard.
To successfully combat these hazards it is important that all of us contribute to the health and safety of
ourselves and others in all our work activities.
This H&S Construction Codes of Practice (Part Two) is intended to provide a base at which the
highest level of safety can be achieved on all our construction projects. It provides not only for the
physical working environment, but for appropriate consultation and discussion between the
department, consultants and contractors on accident prevention and occupational Health & Safety
matters;
Although the standards and guidelines contained in this manual have been developed from the best
and most appropriate international health and safety standards, they are not intended to replace any
present, or future Ministerial Orders applicable to health and safety of persons at work, nor any
specific health and safety requirements incorporated in contract specifications, all of which should be
fully adhered to at all times.
All concerned should note that as these manuals are controlled documents and as such, various forms
and checklists contained in them are sample formats only and should not be removed. A master file of
all the forms checklists and drawings are held with ADM Health and Safety Unit, copies of which are
readily available on request by quoting the Document No. located in the footers.
Both manuals will be regularly reviewed by ADM’s H&S Committee, and any amendments or additions
made by that committee, will be circulated to all concerned.
I look forward to the full co-operation of all concerned in, over a period of time, adopting the standards
and guidelines laid down in this manual, and to work together to achieve an improved safety record for
this very important industry.
Signed:
FOREWORD
(i) Foreword
TABLE OF CONTENTS
(ii) Table of Contents
(iv) Municipalities & Agricultural Dept. Abu Dhabi Municipality H&S Contact Details +
Emergency Contacts
PRELIMINARIES
1.0 ENVIRONMENTAL PROTECTION
2.0 WORKING IN HIGH TEMPERATURES AND REMOTE LOCATIONS
3.0 NOISE AT WORK
4.0 OCCUPATIONAL HEALTH
5.0 SUBSTANCES HAZARDOUS TO HEALTH
6.0 OVERHEAD AND UNDERGROUND SERVICES
7.0 ELECTRICITY AT WORK
8.0 MANUAL HANDLING & LIFTING
9.0 HIGHLY FLAMMABLE LIQUIDS & LIQUEFIED PETROLEUM GASES
10.0 SAFETY SIGNAGE
11.0 PERMIT TO WORK
12.0 PERSONAL PROTECTIVE EQUIPMENT (P.P.E)
LIFTING OPERATIONS
19.0 CRANES AND HOISTS
20.0 LIFTING GEAR
CONSTRUCTION OPERATIONS
21.0 CONFINED SPACES
22.0 ROAD WORKS - BRIDGES
23.0 EXCAVATIONS - COFFERDAMS
24.0 TUNELLING - SHAFT SINKING
25.0 FALSEWORK
26.0 PILING
27.0 WELDING
28.0 WORKING OVER OR ADJACENT TO WATER
WORKING AT HEIGHT
29.0 SCAFFOLDING – LADDERS – CRADLES – SAFETY NETS
30.0 ERECTION OF STRUCTURES
31.0 DEMOLITION
32.0 SAFE WORKING ON ROOFS
33.0 REFURBISHMENT
34.0 MAINTENANCE
SPECIAL PROCESSES
35.0 High Pressure Water Jetting
Lasers
Site Investigation
Watercraft & Dredging
Diving
Health & Safety Plan Format used by the Consultant to identify the main H&S risks
during the design stage of a contract
Lifting Appliances A grab, winch, pulley block, gin wheel, hoist, crane,
excavator, dragline.
Lifting Gear A chain, sling, rope sling, webbing sling or similar gear and a
ring, link, hook, shackle, swivel or eyebolt.
SWL Safe Working Load.
ASLI Automatic Safe Load Indicator.
Scaffold Any temporarily provided structure on or from which persons
perform work in connection with operations or works to which
this manual applies.
Site Any place where building operations or works of engineering
construction, or both such operations of such works are
being carried on, and any temporary storage or workshop
area associated with the works.
Sloping Roof A roof with a pitch of more than 10 degrees.
ENVIRONMENTAL PROTECTION
DEFINITION 1
INTRODUCTION
MAIN APPLICABLE U.A.E. LEGISLATION
MAIN APPLICABLE BEST PRACTICE AND TECHNICAL GUIDELINES
EXECUTIVE REGULATIONS AND LOCAL ORDERS
1.1 GENERAL 2
1.2 ENVIRONMENTAL ASSESSMENT –
IDENTIFYING POTENTIAL IMPACTS ON THE ENVIRONMENT 3
SECTION 1
Municipalities & Agricultural Department
Health & Safety at Work
PART TWO
SECTION 1
ENVIRONMENTAL PROTECTION
DEFINITION
The key issues that must be taken into consideration when undertaking any work which may, to any
extent, impact the environment.
INTRODUCTION
During construction certain development projects pose a significant risk to the environment. This risk
must be addressed through the consideration of Environmental Protection which involves
environmental assessment, management and monitoring to ensure that the effects of development
are not significantly detrimental. All personnel are responsible for considering the environmental
implications of their activities. This should be overseen by the consultant, or a specialist
environmental consultant where appropriate. Construction practices that fail to control pollution can
cause damage to the terrestrial environment, upset ecological systems and wildlife communities, and
result in the contamination of land and groundwater.
The issue of environmental protection during the contract period should be discussed with the
consultant prior to the site hand-over. Where deemed appropriate the consultant should seek
guidance from an approved specialist environmental consultant. Stiff penalties can be brought to bear
upon individual persons and companies whose actions result in damage, be it temporary or
permanent, direct or indirect, to the environment.
Ministerial Order No.32 (1982) regarding protection of employers against occupational hazards
Local orders on discharge and disposal of wastes (Environmental Protection Section - Food and
Environmental Control Centre - Abu Dhabi Municipality)
1.1 GENERAL
• all contracts, whether new or existing, must comply with the Federal law and enforcing
regulations on environmental protection and also any local orders currently in place.
• it is recommended that all contracts, whether new or existing, comply with best practice
and technical guidance.
• in accordance with best practice recommendations, the contractor must have in place/be in
the process of developing an integrated Health, Safety Environmental Management
System in order to minimise risks.
• the contractor should make himself aware of any risks to the environment which may occur
within or outside the agreed site area as a result of his activities.
• the contractor should seek advice from an approved specialist environmental consultant as
to what measures should be taken to prevent or reduce to an acceptable level (as agreed
by the local authorities) the impact on the environment of activities taking place under the
contract in question.
• the contractor should have procedures in place to enable the monitoring of all discharges
into the environment, be they liquid, solid or gaseous and ensure adherence to permissible
threshold emission levels. Scrutiny of data arising from environmental monitoring may be
undertaken by the relevant authorities.
If necessary the contractor should seek advice from an approved specialist environmental
consultant.
The contractor should be aware that potential sources of pollution could include, but may not be
limited to, the following:-
• disposal of solid wastes arising from construction activities, be they on or off site.
• discharge of waste waters, sewage or ground waters to land, sewer, surface water drain,
the marine environment or any other location.
• the disturbance of species or habitat either within or in the immediate vicinity of the site.
In order to ensure that the contractor minimises all potential environmental impacts, and has
best working practices to minimise risks the consultant must also ensure that the contractor has
an appropriate Health, Safety Environmental Management System (HSEMS) in place. The
HSEMS aims to establish quality systems to consistently high health, safety and environmental
outcomes for the project as a whole.
For projects which are deemed to be environmentally sensitive, as defined by the regulatory
authority, the contractor will be required to develop a Construction Environmental Management
Plan (CEMP).
The CEMP is required to contain all aspects of a projects environmental management, and
should be prepared by the main contractor before work commences. This aims to implement
mitigation measures that may be required as defined by any previous environmental
assessments conducted by the Municipality. The CEMP should contain best practice sources
documents which can be used to address significant environmental impacts. These are generic
and should be applied to the site conditions via the environmental control plan.
The CEMP should be developed in accordance with ERWDA Techncial Guidance and should
include details of:
article 2
To combat pollution of all forms and to prevent any immediate or long-run damage or effects
due to economic, agricultural, industrial or reconstruction development plans and programs
aimed at improving quality of life and to secure co-ordination between the Authority and the
parties involved in the environment protection, conservation of its diversity and natural
balance and to spread environmental awareness and anti-pollution principles.
articles 49-55
The contractor should make himself fully aware of the Executive Regulations which relate to
the above articles.
article 49
Machinery, engines or vehicles generating combustion beyond the limits specified by the
Executive Regulations shall not be used.
article 52
In carrying out drilling, construction, demolition, or transportation of whatsoever results
therefrom, including garbage or sands, all parties and individuals shall take the necessary
precautions in the course of practising such activities, as well as the precautions, needed for
their safe storage and transportation to prevent their scattering, in the manner to be shown in
the Executive Regulations.
article 54
• in carrying out production or service activities or otherwise, especially in operating
machinery, equipment, horns, loudspeakers all parties and individuals shall not exceed
the permissible limits for noise.
• the Executive Regulations shall show the tolerable limits for the maximum volume of
sound and the time limit to exposure thereto.
The contractor should make himself aware of the penalties which may applied for non-
compliance with this Law which could include:-
• death penalty,
• imprisonment
article 71
Any person, whose act or negligence causes damage to the environment or a third party,
due to violation of the provisions of this law or the regulations or decisions issued in
implementation thereof, shall be held responsible for all costs required for the handling or
elimination of such damage. He shall be bound as well to pay any consequent indemnity.
article 77
Whosoever pollutes drinking or ground waters, shall be punished with imprisonment for a
period of not less than one year and a fine not less than five thousand Dirhams and not more
than one hundred thousand Dirhams.
POLICE 999
ELECTRICITY 4464677
WATER 991
ETISALAT 8005500
ADNOC 6023177
ENVIRONMENTAL PROTECTION
DEFINITION 1
INTRODUCTION
MAIN APPLICABLE U.A.E. LEGISLATION
MAIN APPLICABLE BEST PRACTICE AND TECHNICAL GUIDELINES
EXECUTIVE REGULATIONS AND LOCAL ORDERS
1.1 GENERAL 2
1.2 ENVIRONMENTAL ASSESSMENT –
IDENTIFYING POTENTIAL IMPACTS ON THE ENVIRONMENT 3
SECTION 1
Municipalities & Agricultural Department
Health & Safety at Work
PART TWO
SECTION 1
ENVIRONMENTAL PROTECTION
DEFINITION
The key issues that must be taken into consideration when undertaking any work which may, to any
extent, impact the environment.
INTRODUCTION
During construction certain development projects pose a significant risk to the environment. This risk
must be addressed through the consideration of Environmental Protection which involves
environmental assessment, management and monitoring to ensure that the effects of development
are not significantly detrimental. All personnel are responsible for considering the environmental
implications of their activities. This should be overseen by the consultant, or a specialist
environmental consultant where appropriate. Construction practices that fail to control pollution can
cause damage to the terrestrial environment, upset ecological systems and wildlife communities, and
result in the contamination of land and groundwater.
The issue of environmental protection during the contract period should be discussed with the
consultant prior to the site hand-over. Where deemed appropriate the consultant should seek
guidance from an approved specialist environmental consultant. Stiff penalties can be brought to bear
upon individual persons and companies whose actions result in damage, be it temporary or
permanent, direct or indirect, to the environment.
Ministerial Order No.32 (1982) regarding protection of employers against occupational hazards
Local orders on discharge and disposal of wastes (Environmental Protection Section - Food and
Environmental Control Centre - Abu Dhabi Municipality)
1.1 GENERAL
• all contracts, whether new or existing, must comply with the Federal law and enforcing
regulations on environmental protection and also any local orders currently in place.
• it is recommended that all contracts, whether new or existing, comply with best practice
and technical guidance.
• in accordance with best practice recommendations, the contractor must have in place/be in
the process of developing an integrated Health, Safety Environmental Management
System in order to minimise risks.
• the contractor should make himself aware of any risks to the environment which may occur
within or outside the agreed site area as a result of his activities.
• the contractor should seek advice from an approved specialist environmental consultant as
to what measures should be taken to prevent or reduce to an acceptable level (as agreed
by the local authorities) the impact on the environment of activities taking place under the
contract in question.
• the contractor should have procedures in place to enable the monitoring of all discharges
into the environment, be they liquid, solid or gaseous and ensure adherence to permissible
threshold emission levels. Scrutiny of data arising from environmental monitoring may be
undertaken by the relevant authorities.
If necessary the contractor should seek advice from an approved specialist environmental
consultant.
The contractor should be aware that potential sources of pollution could include, but may not be
limited to, the following:-
• disposal of solid wastes arising from construction activities, be they on or off site.
• discharge of waste waters, sewage or ground waters to land, sewer, surface water drain,
the marine environment or any other location.
• the disturbance of species or habitat either within or in the immediate vicinity of the site.
In order to ensure that the contractor minimises all potential environmental impacts, and has
best working practices to minimise risks the consultant must also ensure that the contractor has
an appropriate Health, Safety Environmental Management System (HSEMS) in place. The
HSEMS aims to establish quality systems to consistently high health, safety and environmental
outcomes for the project as a whole.
For projects which are deemed to be environmentally sensitive, as defined by the regulatory
authority, the contractor will be required to develop a Construction Environmental Management
Plan (CEMP).
The CEMP is required to contain all aspects of a projects environmental management, and
should be prepared by the main contractor before work commences. This aims to implement
mitigation measures that may be required as defined by any previous environmental
assessments conducted by the Municipality. The CEMP should contain best practice sources
documents which can be used to address significant environmental impacts. These are generic
and should be applied to the site conditions via the environmental control plan.
The CEMP should be developed in accordance with ERWDA Techncial Guidance and should
include details of:
article 2
To combat pollution of all forms and to prevent any immediate or long-run damage or effects
due to economic, agricultural, industrial or reconstruction development plans and programs
aimed at improving quality of life and to secure co-ordination between the Authority and the
parties involved in the environment protection, conservation of its diversity and natural
balance and to spread environmental awareness and anti-pollution principles.
articles 49-55
The contractor should make himself fully aware of the Executive Regulations which relate to
the above articles.
article 49
Machinery, engines or vehicles generating combustion beyond the limits specified by the
Executive Regulations shall not be used.
article 52
In carrying out drilling, construction, demolition, or transportation of whatsoever results
therefrom, including garbage or sands, all parties and individuals shall take the necessary
precautions in the course of practising such activities, as well as the precautions, needed for
their safe storage and transportation to prevent their scattering, in the manner to be shown in
the Executive Regulations.
article 54
• in carrying out production or service activities or otherwise, especially in operating
machinery, equipment, horns, loudspeakers all parties and individuals shall not exceed
the permissible limits for noise.
• the Executive Regulations shall show the tolerable limits for the maximum volume of
sound and the time limit to exposure thereto.
The contractor should make himself aware of the penalties which may applied for non-
compliance with this Law which could include:-
• death penalty,
• imprisonment
article 71
Any person, whose act or negligence causes damage to the environment or a third party,
due to violation of the provisions of this law or the regulations or decisions issued in
implementation thereof, shall be held responsible for all costs required for the handling or
elimination of such damage. He shall be bound as well to pay any consequent indemnity.
article 77
Whosoever pollutes drinking or ground waters, shall be punished with imprisonment for a
period of not less than one year and a fine not less than five thousand Dirhams and not more
than one hundred thousand Dirhams.
DEFINITION 1
INTRODUCTION
MAIN APPLICABLE U.A.E. LEGISLATION
SECTION 2
Municipalities & Agricultural Department
H&S Construction Codes of Practice
PART TWO
SECTION 2
INTRODUCTION
Driving and working in remote areas such as the Deserts of the UAE, and working on sites where the
temperature exceeds 75° F, requires planning and preparation to assure the safety of the men and
resources involved in the activity.
Complacency while working in the desert, and not appreciating the effects of excessive heat on sites
can lead to serious problems.
It is the management’s responsibility to ensure that the appropriate resources and training are in place
before sending his workforce into remote areas, and working in high temperatures.
DEFINITIONS
remote locations
A remote work site e.g. (working in the desert), that requires all resources brought in to complete the
activity safely.
high temperature
When temperature on any site in any location, exceeds 210 Celcius (750Farenheit)
• battery.
• tool kit, jack and jack handle. • block of wood for the jack.
2.2 WEATHER
2.2.1 dust storm
• slow down immediately and get off the highway
• shake out all clothes and shoes before reaching into them.
• never go barefoot.
• apply ice, using a layer of cloth between it and the skin (no longer than 10 minutes at a
time).
If you have not had a Tetanus booster in the past 10 years, you should get one within 72 hours
following the sting.
2.3.6 snakes
Snakes are best avoided by never putting
your hands or feet where you can’t see.
The two main effects are called heat exhaustion and heat stroke. They are quite different and
must be recognised since the treatment of the two conditions differs.
Heat exhaustion can be compared to a faulty radiator and heat stroke can be compared to a
breakdown of the thermostat.
look for
treatment
• replace fluids, large quantities of water or isotonic saline (1/4 teaspoon of salt in 1 litre
of water.
• if the patient is vomiting give water as above and seek medical treatment immediately,
as intravenous fluid replacement may be required.
look for
• a sudden dramatic rise in body temperature above 40 o c.
• the cessation of sweating.
• the patient will feel very hot and dry.
• there may be disorientation, struggling or convulsions or unconsciousness.
treatment
• immediate cooling of the body is essential to prevent death.
• remove patient to a cool environment.
• wrap in wet sheets and/or sponge down with cold water. Immerse in cold water bath if
possible until temperature is down to 39oc, at which time cooling should be stopped to
avoid shock.
• seek medical attention as soon as possible.
• avoid exposure to the sun in the heat of the day, if possible arrange work during the
cooler hours.
• while working outside prepare shade over the task area if possible.
• if stranded in the desert, take steps to maintain good fluid intake until rescued. Prepare
shade and stay with your vehicle. Reduce exercise.
• move workers to activities in shaded areas in shifts to prevent a build up of body heat.
Alternate heavy and light work activities.
• prepare shade for the cab of equipment so as not to hinder the operator’s field of vision.
• equipment and operators in remote areas of the site should be checked every 3 hours
min.
• gloves to prevent damage to hands when handling tools or equipment that has been
sitting in the sun.
NOISE AT WORK
INTRODUCTION 1
MAIN APPLICABLE U.A.E. LEGISLATION
SECTION 3
Municipalities & Agricultural Department
H&S Construction Codes of Practice
PART TWO
SECTION 3
NOISE
INTRODUCTION
Safety in the building industry has a high priority, however, health hazards are often less understood.
Many causes of occupational ill-health, including noise, are recognised by industry but can be difficult
to manage because there is often a long latency period before the disease or effect develops and
susceptibility varies.
Strategies for controlling occupational health risks are on the whole led by legislation and are seen as
requiring time and resources to develop and as not producing immediate direct cost benefits, for
example audiometry
noise can:
• be a nuisance, resulting in disturbance and loss of enjoyment of life, loss of sleep and
fatigue
• it can distract attention and concentration, mask audible warning signals or interfere with
work, thereby being a factor in workplace accidents; and
• result in hearing impairment.
The danger levels for noise are identified as being, 85dBA and 90dBA. At 85dBA which is
known as the first action level, employees will probably have to shout to be heard at a
distance of 2m away from the person they are talking to, and must be provided with hearing
protection at their request.
At the second action level which is 90dBA or above, employees will probably have to shout
to be heard at a distance of 1 m away from the person they are talking to. The exposure of
employees to noise must be reduced as far as reasonably practicable, without the use of
hearing protection. If it cannot be reduced below this level then hearing protection must be
provided and reasonable steps taken to ensure that it is used; employees have a duty to use
hearing protection in such circumstances.
There are two types of hearing loss associated with damage to the receptive hairs,
temporary and permanent threshold shift.
Temporary threshold shift is a temporary dullness in hearing after exposure to loud noises.
Hearing will subsequently recover, the time taken depends on factors such as loudness and
duration of the noise. If hearing does not fully recover after 48 hours, the level of hearing
loss that remains can be considered permanent.
noise induced or occupational deafness, which results when the sufferer has been
regularly exposed to noise over a long period of time. Normally, hearing loss will be similar in
both ears and increase with continued exposure to the noise.
acoustic trauma, occurring with exposure to a very high sound level over a short period of
time, in some cases resulting in perforation of the eardrum. Once permanent damage has
occurred to the inner ear, it is irreversible.
• noise meters vary considerably depending on type, size and cost, but even the
inexpensive range will give a reasonable indication of sound levels being produced. Most
instruments can be switched to 'slow' response which dampens the oscillation of the
reading needle to allow easier reading.
3.3.2 surveys
• noise surveys should only be carried out by a person who has received adequate training
in noise measurement techniques.
• if conversation would be difficult in the nearest building (with windows closed) noise
levels are probably excessive.
• a reasonably steady sound level is where the level fluctuates through a total of less than
8dB(A) on a slow response scale.
• these are minimum requirements and everything possible should be done to improve on
them and reduce exposure to noise.
• municipality requirements.
• hours of working.
• disturbance of nearby residents (if this is likely, the situation and measures to be taken to
reduce noise should be explained to persons likely to be affected).
Note: Failure to plan the control of noise may lead to delay and increased cost later.
• placing site buildings, stores, etc between noise source and noise sensitive areas.
• screening source with a barrier, wall, acoustic screen, spoil heap or locating source
behind partly completed buildings.
• the effectiveness of a noise barrier will depend on its dimensions, its position relative to
the source and the listener, and the material used for the barrier.
• care must be taken to ensure barriers do not, by reflecting sound, transfer the nuisance
from one sensitive area to another.
90 8 hours
93 4 hours
96 2 hours
99 1 hour
102 30 minutes
105 15 minutes
108 7 1/2 minutes
111 3 3/4 minutes
Notes:
• this is the noise level at the ear and not at the source
• the table above is based on the logramithic calculation where an increase of 3 dB (A) is
regarded as doubling the noise level or halving the exposure time.
Notes:
• sound levels are for guidance only and are taken at source.
• information should be sought from plant hire company regarding machines on site.
• noise level emitted from the machines will be affected by the competence of the operator
and the quality of maintenance.
OCCUPATIONAL HEALTH
INTRODUCTION 1
MAIN APPLICABLE U.A.E. LEGISLATION
SECTION 4
Municipalities & Agricultural Department
H&S Construction Codes of Practice
PART TWO
SECTION 4
OCCUPATIONAL HEALTH
INTRODUCTION
Occupational health anticipates and prevents health problems which are caused by the work which
people do. In some circumstances the work may aggravate pre-existing medical condition and
stopping this is also the role of occupational health.
Health hazards often reveal their effects on the human body only after the passage of time; many have
cumulative effects, and in some cases the way this happens is not fully understood.
Because the effects are often not immediately apparent, it can be difficult to understand and persuade
others that there is a need for caution and control.
• quantification of the extend of the hazard - usually by measuring physical/chemical factors and
their duration, and relating them to known or required standards.
• control of exposure to the hazard through design, engineering, working systems, the use of
personal protective equipment and biological monitoring.
• monitoring change in the hazard by means of audits or other measurement techniques, including
periodic re-evaluation of work conditions and systems.
The Medical - Care which the Employer is Obliged to Provide to his Workers.
• physical — air pressure, heat, dampness, noise, radiant energy, electric shock
Substances may cause health hazards from a single exposure, even for a short time (acute
effect) or after prolonged or repeated exposure (chronic effect). The substance may affect
the body at the point of contact, when it is known as a local agent, or at some other point,
when it is described as a systemic agent.
Absorption is said to occur only when a material has gained access to the bloodstream and
may consequently be carried to all parts of the body.
generally have delayed effects and are often due to unrecognised conditions which are
therefore permitted to persist.
Inhalation - the most important route of entry, which can allow direct attacks against lung
tissue which bypass other defences such as those of the liver. The lungs are very efficient in
transferring substances into the body from the outside environment, and this is the way
inside for 90 per cent of industrial poisons.
Scrotal cancer - produced by rubbing contact with workers’ clothing impregnated with a
carcinogen such as mineral oil, in close contact with the scrotum. This can be prevented by
substitution of the original substance, by use of splash guards, and by provision of clean
clothing and washing facilities for soiled work clothing.
Pneumoconiosis - resulting from exposure to dust which deposits on the lung, such as
metal dust and man-made mineral fibre. Other examples of these fibroses of the lungs are
silicosis due to the inhalation of free silica, and asbestosis from exposure to asbestos fibres.
Humidifier fever — giving influenza-like symptoms and resulting from contaminated
humidifying systems.
Cause cancer and birth defects - by encouraging cells to undergo fundamental changes by
altering the genetic material within the cell. Substances which can do this are carcinogens,
Examples are asbestos, mineral oil, hardwood dusts and arsenic. Teratogens cause birth
defects by altering genetic material in cells in the reproductive organs, and cause abnormal
development of the embryo. Examples are organic mercury and lead compounds. Mutagens
trigger changes affecting future generations.
Cause asphyxiation - by excluding oxygen or by direct toxic action. Carbon monoxide does
this by competing successfully with oxygen for transport in the red cells in the blood.
Cause central nervous system disorders - by acting on brain tissue or other organs, as in
the case of alcohol eventually causing blindness.
Cause damage to specific organs - such as kidneys and liver. An example is vinyl chloride
monomer (VCM).
Is hereby decided:
Article (1)
The obligation of an employer for the medical treatment of workers shall be in accordance
with the medical care standards set forth in the provisions of this decision and within the
limits of available treatment in the State.
Article (2)
An employer whose the number of employees in his establishment in not more than fifty in
one place or within an area the radius of which is twenty kilometres, shall provide at the work
place in his establishment with first aid kits.
Article (3)
An employer whose the number of his workers in one place or within an area the radius of
which is twenty kilometres, is exceeding fifty workers and less than two hundred, and in
addition to his obligation to provide first aid kits, must employ; nurse holding a nursing
certificate recognised by the Ministry o Health who shall be entrusted with rendering first aid
treatment The employer shall also appoint a doctor to treat workers at the place prepared by
him for that purpose and shall give then medicines required, all free of charge.
And if treatment requires a specialist doctor, the establishment doctor shall recommend in
writing for the treatment of the worker by a specialist provided that in such case. Treatment
expenses shall equally be shared by both the employer and the worker.
Article (4)
An employer whose employees are two hundred workers or more in one place or within an
area the radius of which is twenty kilometers shall provide the treatment facilities stipulated in
Article (2) and (3) of this decision in addition to his obligation to provide all other treatment
facilities in cases the treatment of which require specialist doctors, or undergo surgical
operations or otherwise, as well as necessary medicines, all of which are at the expense of
the employer.
Article (5)
The doctor of an establishment which the number of its’ workers is two hundreds or more
must treat any disease in the normal way and dispense necessary medicines.
He shall refer the worker to a specialist doctor or to the hospital in cases which require so. In
such case the worker may not ask that his treatment shall he by a specialist doctor, or
undergoes a surgical operation or be treated at a hospital except upon the decision of the
establishment doctor or on the basis of a certificate issued by specialist and approved by the
medical administration or the concerned medical zone within which jurisdiction the
establishment is situated.
The worker may not ask for treatment by specialist doctors other than those determined by
the employer, nor in hospital not been agreed.
Article (6)
The place assigned for the workers clinic and for their treatment shall be as near as possible
from the work place and shall have adequate ventilation, lighting and healthily conditions;
and it shall be equipped with necessary equipments and devices.
Article (7)
The expenses of transportation of workers to the clinic shall be paid by the employer and at
the times specified for treatment or medical check-up.
However, the worker shall not be entitled to such expenses unless he complies with the
instructions of the employer as to the times specified for treatment or medical examination at
the clinic except in emergencies or urgent cases.
The employer may designate means of transportation for transporting patients and injured
workers, and in such a case the worker may not refuse such transportation means if they are
suitable and shall not be entitled to transportation expenses if he refuses to use the
transportation means without justifiable reason.
Article (8)
If there is a fund in the establishment or a scheme providing medical services in which the
worker is contributing which gives the right to receive medical treatment for himself and the
members of his family, the employer shall reduce the subscription fees of the worker in such
fund or scheme to an amount equal to the expenses of his treatment which the employer
bears, pursuant to the provisions of this decision. be pu
shall t
Article (9)
An employer who employs fifty workers or more must display at the main gates used by
workers to enter to the workplace, the following information:
Inspectors of the labour inspection division at the Ministry may instruct to display all the
foregoing information or some of them, as the case may be, at another place or suitable
places whenever they deem it necessary.
Article (10)
Any employer who is employing workers from out of the country must be sure of their
physical fitness, through a certified medical certificate proving that which must be
authenticated by the official concerned authorities.
In all cases, the employer must be sure of the physical fitness of the worker employed by
him before he joins work after subjecting him to medical examination; the result of which
must be included in a written report approved by the competent authority at the Ministry.
Article (11)
Any employer must prepare for every worker employed by him a medical file including the
following:
• The result of medical examination of the worker at the time he joined work.
• The result of medical check-up, and the prescribed treatment whenever the worker
reports for medical check-up and any date thereof.
• The Results of medical analysis, or treatment and X-ray, if any.
• Result of medical examination to know whether the worker is suffering from chest or
dermatological disease.
• The period for which the worker was absent because of illness provided that every (4)
days of absence due to illness or accidents shall be shown separately.
Such files shall be confidential, and shall not be seen except by the treating doctor, or the
employer or who represents him.
Article (12)
An employer who employs fifty workers or more must send a list of two copies every three
months to the concerned labour department showing the number of workers who received
medical treatment at the expense of the employer, the nature ol their diseases and the days
of absence because of illness.
Article (13)
Compliance with the provisions of this decision shall not prejudice nor nullify any other
regulations related to medical treatment in the establishment if such regulations achieve
better medical care than those set forth herein.
Article (14)
This decision shall be published in the official gazette and shall come into force from the date
of its publication.
SUBSTANCES
HAZARDOUS TO HEALTH
INTRODUCTION 1
DEFINITION & CLASSIFICATION
MAIN APPLICABLE U.A.E. LEGISLATION
SECTION 5
Municipalities & Agricultural Department
H&S Construction Codes of Practice
PART TWO
SECTION 5
SUBSTANCES
HAZARDOUS TO HEALTH
INTRODUCTION
Hazardous substances are considered to be chemical materials and products which are used every
day for a variety of purposes, many of which are dangerous if not handled correctly, majority are toxic,
corrosive, flammable, oxidising or irritants and all pose a risk to workers, the public, and the
environment.
There are four routes by which chemical substances may enter the body and cause harm, inhalation,
ingestion, penetration and skin absorption, but the one by which building site workers are more at risk
is that of inhalation, and this section, in the main, gives priority to this.
The material may lodge in the mouth, nose or throat or be comprised of small enough
particles to penetrate the deep lung. It may be cleared from the respiratory tract by the
body’s natural mechanisms or may lodge in the lungs, or it may be absorbed by the body
and transported in the blood to other organs.
Solvent vapours, welding fumes, asbestos, legionella and silica are all inhalation toxins or
hazards.
DUST
FUMES
• ventilation at source
WELDING & CUTTING Metal fume fever: Flu-like illness. • respiratory protection
• personal hygiene
FUMES
• no eating, drinking or smoking on the job
• establishing and instructing employees on safe systems of use and handling of chemical
products.
• ensuring clear and correct labelling - especially when products are decanted from their
original containers, prohibition of drinking and smoking in areas when chemicals are
used, or on sites where general contamination may be present.
• actively promoting programmes of health education, with particular regard to the need for,
and value of good personal hygiene,
Construction workers are vulnerable when breaking new ground and particularly when
working on sites previously used for agriculture. Large, dirty, lacerated wounds are very
susceptible, but infection can result from minor pricks or puncture wounds, e.g. treading on a
nail.
Signs shown below are an example of hazardous substance control safety signs
commonly used to identify hazards and mark areas to protect employees.
SUBSTANCES
HAZARDOUS TO HEALTH
INTRODUCTION 1
DEFINITION & CLASSIFICATION
MAIN APPLICABLE U.A.E. LEGISLATION
SECTION 5
Municipalities & Agricultural Department
H&S Construction Codes of Practice
PART TWO
SECTION 5
SUBSTANCES
HAZARDOUS TO HEALTH
INTRODUCTION
Hazardous substances are considered to be chemical materials and products which are used every
day for a variety of purposes, many of which are dangerous if not handled correctly, majority are toxic,
corrosive, flammable, oxidising or irritants and all pose a risk to workers, the public, and the
environment.
There are four routes by which chemical substances may enter the body and cause harm, inhalation,
ingestion, penetration and skin absorption, but the one by which building site workers are more at risk
is that of inhalation, and this section, in the main, gives priority to this.
The material may lodge in the mouth, nose or throat or be comprised of small enough
particles to penetrate the deep lung. It may be cleared from the respiratory tract by the
body’s natural mechanisms or may lodge in the lungs, or it may be absorbed by the body
and transported in the blood to other organs.
Solvent vapours, welding fumes, asbestos, legionella and silica are all inhalation toxins or
hazards.
DUST
FUMES
• ventilation at source
WELDING & CUTTING Metal fume fever: Flu-like illness. • respiratory protection
• personal hygiene
FUMES
• no eating, drinking or smoking on the job
• establishing and instructing employees on safe systems of use and handling of chemical
products.
• ensuring clear and correct labelling - especially when products are decanted from their
original containers, prohibition of drinking and smoking in areas when chemicals are
used, or on sites where general contamination may be present.
• actively promoting programmes of health education, with particular regard to the need for,
and value of good personal hygiene,
Construction workers are vulnerable when breaking new ground and particularly when
working on sites previously used for agriculture. Large, dirty, lacerated wounds are very
susceptible, but infection can result from minor pricks or puncture wounds, e.g. treading on a
nail.
Signs shown below are an example of hazardous substance control safety signs
commonly used to identify hazards and mark areas to protect employees.
INTRODUCTION 1
MAIN APPLICABLE U.A.E. LEGISLATION
SECTION 6
Municipalities & Agricultural Department
H&S Construction Codes of Practice
PART TWO
SECTION 6
INTRODUCTION
Live overhead lines have been responsible for a number of serious and fatal accidents on construction
sites when contact with the lines has been made by workmen or machines. The voltages may lie in
the range between 240 and 400,000 volts, and they all have lethal potential.
Underground services are, to a great extent, out of sight and out of mind until the time comes for
someone to dig a hole or start excavating. Accidental contacts with buried services such as electricity
cables and gas pipes may lead to serious injury or fatality.
The damage and injury can be avoided if the proper procedures outlined in this section are followed.
There are many other types of buried services, often confined to specific locations, which
are not likely to be the subject of public knowledge at all, they include services associated
with:
• pneumatics,
• highway authorities,
• street lighting,
• military authorities.
Work in the vicinity of oil & gas transmission pipelines, often requires special measures to be
taken and the oil & gas company will supply detailed procedures on request.
Most injuries are caused to persons using pneumatic drills of jackhammers, ruptured gas
pipes can cause a leak, a fire, or an explosion.
The cost of damage can be considerable. The new generation of fibre optic
telecommunication cables are very expensive - and an apparently simple break may mean
the replacement of two kilometre length, at a cost measured in thousands of dirhams.
Indirect costs, in some cases resulting from loss of production and disruption of business
activities, will be borne by all affected, including those whose negligence caused the
incident.
• any service said to exist, should be clearly marked on the site plans.
• when looking at plans, it should be borne in mind that reference points may have been
moved, surfaces may have been re-graded, services moved without authority or consent,
and that not all service connections or private services are shown.
• plans must be interpreted with care; a pencil on a map may cover a width equivalent to a
metre on the ground.
• where appropriate the route, when established, should be identified with paint, tape or
markers - not steel spikes, which might penetrate a cable or pipe.
• a line on a plan does not mean a pipe or cable is located exactly in the position marked. It
only indicates that it is roughly in that location.
• the exact position will only be known when the buried service is found, as in many cases,
there is no indication above the ground that a buried service exists. They may be found
almost anywhere and at any depth from immediately beneath the surface of the
pavement, or tarmac, to 1.5 metres or more.
• indications that buried services do exist include the presence of lamp posts, illuminated
traffic signs, telephone boxes, concrete or steel manhole covers, hydrant and valve pit
covers, etc.
• small concrete indicator posts, usually on the verge, or plaques on walls have this
specific function. Indicator posts belonging to water authorities often give the size of the
pipe and its distance from the post.
• the absence of posts or covers, must not be taken as evidence that there are no buried
services. Access covers can be a substantial distance apart.
• cables or pipes may be laid loose in the ground, run in earthenware, concrete, metal,
asbestos or plastic ducts, or be buried in cement-bound sand, loose sand, fine backfill or
material dissimilar from the surrounding ground.
• plastic marker tape, tracer wire, boards, tiles or slabs may have been laid above the
service to indicate that there is something below. These may, however, have been
removed or damaged in the past; they are also liable to be laterally displaced by ground
water or movement and thus no longer indicate the true location of the service.
Note: The absence of a tape should not be taken as evidence that there are no pipes or
cables at the location; it may simply mean that no marker tape was used.
The following points should be considered prior to, and during digging operations:
• where two holes are dug at intervals, it should not be assumed that the service runs in a
straight line between them.
• mechanical excavators and power tools should not be used within 0.5 metres of the
indicated line of a service, unless prior agreement on a safe system of work has been
reached with the service owner.
• power tools may be used to break paved surfaces, but great care must be taken to avoid
over-penetration, since a service may have been laid at an unusually shallow depth,
especially in the vicinity of buildings or other services.
• power tools must never be used directly over the indicated line of a cable unless it has
been made dead or steps have been taken to prevent damage.
• excavations must be adequately supported, especially it more than 1.2 metres deep, or
dug in poor ground, at a location exposed to traffic vibration or near a building, or
embankment, etc.
• assume presence of service when digging, even though nothing is shown on plans.
• detectors must be used, and close watch kept for signs or tapes, etc., indicating a buried
service.
• although there are recommended minimum depths for all services, they may be closer to
the surface than normal, especially in the vicinity of works, structures, or other services.
• markers such as plastic tape, tiles, slabs or battens may have been displaced, and not
indicate the exact location of the buried service.
• some electric cables, gas pipes and water pipes look alike. Ensure proper identification
before working on them.
• careful use of spades and shovels enables services, which could easily be damaged by a
fork or a pickaxe forced into the ground, to be safely uncovered.
• over-penetration of the ground or surface with hand-held power tools is a common cause
of accidents.
• if an excavator or digger is being used near any service, extra care must be taken in case
the service is damaged or broken.
• when possible, no one should be near the excavator or digger while it is digging.
• if the service is embedded in concrete or paving material, the utility or owner should de-
energise it or otherwise make it safe, or approve a safe system of work before it is broken
out.
• closed, capped, sealed, loose or pot ended services should always be assumed to be live
or charged, not dead or abandoned, until proven otherwise.
• follow the guidelines and advice issued by the electricity, gas, water and
telecommunication authorities.
• services across a trench or along a trench above the bottom should be supported by
slings or props, to avoid unnecessary stresses. In cases of doubt, advice should be
sought from utilities or the owner.
• cables and services must never be used as jacking or anchorage points, or as footholds
or climbing points.
• if a service pipe or cable needs to be moved to allow work to progress, the owner should
be consulted and advice sought.
• Inform Etisalat
• inform owner.
6.5 BACKFILLING
• surplus concrete, hard core, rock, rubble, flint, etc., must never be tipped onto a service
while backfilling a trench or hole, since it may result in damage.
• selected backfill material should be adequately settled and compacted, care being taken
to avoid mechanical shocks to the service pipe or cable.
• when gas service pipes have been exposed, advice on backfill should be sought from the
gas companies.
On sites the electricity supply will generally be obtained either from Electricity Department or
from site generators.
Overhead lines belonging to A.D.W.E.A. are subject to the requirements of their rules. High
voltage overhead lines are not normally insulated and comprise bare conductors mounted
on insulators on steel or wooden towers or poles.
Low and medium voltage lines may be insulated or uninsulated but, in either case, care is
necessary if hazards and accidents are to be avoided.
Fig.5 - Showing the Minimum clearance required on both Low, Medium and High
Voltage Overhead Electricity Lines.
• where a roadway or passage is required under a line the crossing should be at right
angles to the line and be restricted to the smallest possible working width for the type of
plant using the roadway.
• such crossings should be restricted to the smallest possible number and should be
fenced to give a clear indication of the roadway, and goalposts should be erected on both
sides of the overhead line to act both as gateways and height limits.
• the height and position of such goalposts will depend upon the voltage of the overhead
line and A.D.W.E.A. will advice on these points. (see Fig.6) below.
Advance
Warning Sign
Between 3 – 6m
Fig.6 - Showing various safe heights required for traffic to safely pass under Overhead Power Lines.
Note: If any work takes place after dark, notices and cross bar should be
illuminated.
• A.D.W.E.A. will advise on safe working clearances and all plant, equipment or hand tools
to be used must be of such construction or be so restricted that these safe working limits
cannot be exceeded. In extreme cases it is usually possible for the Department to make
the line dead for certain periods of time so that work can proceed.
ELECTRICITY AT WORK
INTRODUCTION 1
MAIN APPLICABLE U.A.E. LEGISLATION
INTERNATIONAL STANDARDS
7.1 DUTIES 2
7.2 SUPPLIES 2
7.3 OPERATION AND MAINTENANCE 5
7.4 PLUGS, SOCKET-OUTLETS, COUPLERS 6
7.5 EQUIPMENT EARTHING (PROTECTIVE CONDUCTORS) RCD 7
7.6 SYSTEM VOLTAGE 8
7.7 CABLES 9
7.8 PLANT AND TOOLS 10
7.9 LIGHTING 11
SECTION 7
Municipalities & Agricultural Department
H&S Construction Codes of Practice
PART TWO
SECTION 7
ELECTRICITY AT WORK
INTRODUCTION
The use of electrical energy to assist in the construction process is extensive. The misuse or
malfunction of electrical equipment could have harmful effects on people and plant, but electricity is
perfectly safe if treated with respect.
This section is aimed to assist site managers, safety advisors and people in similar positions to satisfy
themselves that necessary steps are taken to ensure that electrical installations are safe.
INTERNATIONAL STANDARDS
BS 7671 : Requirements for electrical installations
(Formerly the IEE Wiring Regulations Sixteenth Edition)
BS 4343 : Industrial plugs, socket outlets and couplers for AC and DC supplies.
BS 4363 : Specification for distribution units for electricity supplies for construction and building
sites.
BS 7375 : Code of Practice for distribution of electricity on construction and building sites
7.1 DUTIES
7.1.1 consultants
The consultant engineering company shall ensure that:-
• the necessary and appropriate approvals are given for a selected electrical contractor or
sub contractor.
• the fixed and temporary ‘Electrical Distribution System’ and utilisation of ‘Electrical
Energy’ required for the construction phase of the contract complies and is operated
within the requirements of this section.
7.1.2 contractor
The Contractor shall ensure that:-
• both the fixed and temporary ‘Electrical Distribution System’ is designed with due
consideration of its purpose, external influences, compatibility of equipment and
maintainability of equipment used.
• they appoint, in accordance with ADWEA regulations, a ‘Competent Person’ who shall be
responsible for the installation, its use and modification during the construction phase of
the contract. The name of the designated person shall be prominently and permanently
displayed close to the main switch or circuit breaker controlling the installation.
7.2 SUPPLIES
7.2.1 incoming supplies
In making an assessment of the incoming supply requirements due consideration shall be
given to the size and locations of electrical loads and the manner in which they vary with
time during the project.
Ample allowance should be made in respect of welfare facilities. It should be noted that in
practice the air conditioning plant, heaters, drying room heaters, water heaters and canteen
cooking equipment, tend to be in continuous use. The use of thermostats, time or light
sensitive switches should be considered.
On large sites, allowance has to be made for the use of large items of equipment, e.g. tower
cranes. Where the load is sizeable or where there are special problems, such as remote
locations or large site areas, early and detailed planning of the site electrical system will be
necessary.
For large and complex installations, design and circuit drawings should be prepared,
showing the type and location of equipment.
When this estimated load is known, a decision as to how the supply is to be obtained may
be made. The options being from the Public Utility or where such a supply cannot be
obtained or where perhaps such a supply would be uneconomical, the only alternative is to
generate the electricity locally on site.
Site Incoming
Unit
Portable
Tools
oooo
oooooo
Accommodation
Outlet panel Outlet Units
fitted with Tower Crane
30mA- ELCB,s
Outlet
oooo Units
Tower
Flood
oo Extension Compressor Lighting
o Outlet Units
Festoon Lighting
Wiring problems can arise because runs require re-routing or extension. Site conditions
themselves are scarcely conducive to planning a safe distribution system and the long
flexible cables for portable tools and lighting only make the overall situation the more
hazardous. Control gear may need to be portable thus its siting should be carefully planned.
Note: No work must be carried out on any live cable, or so near as to cause danger, unless
it is not practicable to make the cable dead and all necessary precautions are taken to
ensure safety.
• fixed installations must be inspected and tested at least at three monthly intervals, routine
maintenance being carried out in accordance with equipment manufacturers’
recommendations.
• moveable and portable/transportable electrical equipment (as defined in BS 7671) should
be inspected, tested and maintained on a routine basis, depending on the use and
application of the particular item.
• records of training, permits-to-work, inspection, testing and maintenance should be kept
throughout the working life of an electrical system. In addition, records of circuit
diagrams, cable runs, loading diagrams and other relevant information should be retained
and kept up to date.
Plugs and sockets are available in a variety of designs providing varying degrees of
protection against damage and weather. The two types most commonly used on construc-
tion sites are the “splashproof” and the better “waterproof” designs. (see Figs. 2,3,4 & 5)
220/240V
110/130V
Fig.4 - Plugs fitted with central Fig.5 - Angled panel sockets which allow for
water tight cable gland and easier insertion and extraction when
strain relief clamp for used on vertical surfaces.
mechanical support
On all building sites where temporary electricity supplies are required voltage operated earth
leakage circuit breakers shall be installed and shall be arranged to have the operating coil
connected between the consumers earthing terminal and the main earth electrode with
insulated connecting leads.
Additional residual current earth leakage circuit breakers should be fitted on the advice of
the duty holder. In particular, BS 7671 requires the fitting of residual current device
protection for socket outlets used to supply portable equipment outdoors. However, it is
emphasised that such devices, in themselves, do not provide complete protection against
shock.
All extraneous metalwork and exposed conductive parts should be bonded together and
connected to the system’s main earth terminal. Circuit protective conductors must be
installed to provide the return path from each outlet of an installation to the main earthing
terminal.
Reduced voltage provides increased protection against shock, but its effectiveness depends
upon the transformer being correctly earthed and this must not be overlooked.
Figs. 6,7,& 8 showing typical examples of RCD protected sockets and adaptors:
Fig.6 - RCD protected outlet Fig.7 - Metal Clad RCD Fig.8 - 13 amp RCD Adaptors
plug. Sockets.
110 V 3-phase
• using a double-wound transformer with the neutral point of its star-connected secondary
winding earthed so that the nominal voltage to earth is approximately 65 V.
110V 1-phase
• using a double-wound transformer with the centre tap of the secondary winding earthed
so that the nominal voltage to earth is 55 V.
110 V 3-phase
• using portable generator set properly or 1-phase earthed in accordance with BS 7375.
7.7 CABLES
For all site offices, workshops, huts, drying rooms and similar premises which are regarded
as permanent type installations, BS 7671 must be adhered to. For general site work
additional precautions are necessary.
Other than supplies for welding purposes, cables carrying a voltage to earth in excess of
65V should have continuous metal armour or sheath which has been effectively earthed.
Where. trailing cables are concerned, this earthing should be in addition to the normal cable
protective conductor.
In view of the rough conditions on site, all cables should be sheathed overall.
PCP (polychloroprene)
combines the advantages of TRS and PVC, i.e. resists wear and abrasion; withstands
solvents, oil, etc.
Cables buried directly in the ground shall be of a type incorporating an armour or metal
sheath or both or be of the PVC insulated concentric type. Such cables shall be marked by
cable covers or a suitable marking tape and be buried at a sufficient depth to avoid their
being damaged by any disturbance of the ground. Cable routes should be marked on the
plans kept in the site electrical register.
Low and medium voltage cables often have to be suspended and some type of bold marking
or “goal post” arrangement of non-conductive material should be erected to indicate their
presence. Where these cables need to cross open areas, or where spans of 3m or more are
involved, a catenary wire on poles or other supports will provide a convenient means of
suspension. Minimum height should be 6m above ground.
Joints in cables should be avoided wherever possible. Where unavoidable, they should be
enclosed in purpose-built housings.
fixed plant
(415 V: 3-phase), e.g. tower cranes, large hoists, continuous batch mixers, etc. Siting should
be carefully planned so that they can remain in one position throughout the job and so that
supply cables, of sufficient capacity, can be routed clear of construction work and be
protected against traffic movement.
movable plant
With load in excess of the 110 V: 3-phase system capacity, e.g. compressors (415 V: 3-
phase). The earth conductor in the heavy trailing supply cable must remain unimpaired if the
plant is to be used safely. If it is broken, current cannot flow to earth if a fault occurs, and it is
therefore strongly recommended that earth monitoring and/or a residual current operated
circuit breaker is provided.
supply leads
to these tools are likely to be lengthy; every effort should be made to protect them from
damage. Tools should be disconnected before any adjustments are made or attachments
changed.
portable tools
for use on high frequencies (in excess of 50 Hz) need a supply from a special generator and
manufacturer’s instructions should be consulted before any connections are made.
certified (kite-marked)
double-insulated or all-insulated tools may be used without earthing (i.e. with two core
cables), but they should still be used only if power supply unit is either protected by Earth
Leakage Breakers, or the portable tool itself is fitted with a 13amp. RCD plug.
Where tools have to be used away from the supply plant, an OU (outlet unit) or EOU
(extension outlet unit) should be used.
Visual checks should be carried out daily by users and formal inspections should be carried
out by competent persons at regular intervals.
• bare wires are not visible, • the cable covering is gripped where it enters
the plug or equipment,
• the cable covering is not damaged,
• the outer casing of the equipment is not
• the plug is in good condition,
damaged or loose
• there are no taped or other non-
• there are no signs of overheating on the plug,
standard joints in the cable,
Residual Current Devices (RCD’s) should be checked to ensure they are working correctly
(the test button should be pressed daily).
Testing, by a competent person can detect faults such as loss of earth continuity,
deterioration of the insulation and internal or external contamination by dust, water, etc.
Note: The practice of connecting portable tools or any other type of electrical apparatus by
inserting bare wires into a distribution board or socket, is strictly forbidden.
7.9 LIGHTING
As well as supplementing poor daylight and enabling work to continue after dark, site lighting
is always necessary if in those areas are devoid of natural light, e.g. shafts and enclosed
stairways. Apart from permitting men to see what they are doing, adequate lighting helps to
minimise physical hazards; it facilitates the delivery and movement of material after dark; it is
an effective deterrent to intruders, pilferers and vandals. In short it safeguards men,
equipment and materials and makes for efficient, economic production.
Site lighting must be sufficient, well planned, of the right type and in the right place for it to
be properly effective. Lighting ought not to introduce the risk of electric shock.
The level of illumination required to provide conditions in which work can be carried out
without undue risk or fatigue should not be less than the figures shown below. The figures
quoted take into account the effect of dust and dirt, depreciation, low contrast areas, etc.
The term interior lighting covers those parts of structures which may not have cladding
during erection, but which will become interiors when the work is finished.
Luminaires of the area lighting type should be mounted on poles, towers, or static crane
towers. Moving supports, e.g travelling cranes, are quite unsuitable since they cause lamps
to cast dangerously deceptive moving shadows.
If luminaires are spaced too widely, illumination becomes patchy, confusing and ineffective.
Luminaires of the non-symmetrical type should be spaced at not more than three times the
mounting height. Other area luminaires should be spaced at not more than 1.5 times the
mounting height.
Floodlight beams are usually classified according to their spread - wide, medium or narrow -
and it should be noted that performance changes radically with size and type of lamp. A
flood that gives a medium spread with a GLS lamp can give a wide spread with an MBF
lamp.
Narrow beam floodlights are only used on sites with large open group areas and they are
usually mounted in clusters on temporary towers at least 30m high.
With narrow beam luminaires there is always a hazard from glare because the beams are
intense. To minimise glare, they should be mounted as high as possible and the beams
should be directed downwards on the work.
significant points:
• the area illuminated decreases and the level of illumination increases as the floodlight is
brought closer to the work on the basis of the “inverse square rule”;
• to increase or decrease the level of illumination, floodlights should be moved closer to, or
further from the work — or their power should be changed;
• beam floodlights are often used to raise the light level at the point of work. (Sufficient light
should reach the workpoint from at least two directions to avoid creating shadow
hazards).
Figs. 9 & 10 show typical examples of Beam Flood Lighting lamps available.
• luminaires are of the well glass or bulkhead type: when fitted with red lamps or red or
orange glasses, these types are widely used to delineate danger areas -hales,
excavations, obstructions, etc.
• If practicable, 11OV supply should be used for regular site work, e.g. on scaffolding and
other temporary structures, because both fittings and cables are prone to damage. A
230V supply should only be used where luminaires and cables are properly fixed, well
protected and supply protected with Earth Leakage Breakers.
• sufficient light for access purposes on a scaffold platform 1 -1 .5 m wide can be obtained
from walkway luminaires using 60 watt Filament amps or two B waif fluorescent tubes,
set 2.5m - 3m above the walkway and not more than 6 m apart.
Tungsten Filament lamps provide the most convenient forms of local lighting, but these
lamps, being relatively small sources of light, tend to produce hard shadows. Therefore, they
should be used with diffusers, or strung in a row so that each bulb in turn softens the
shadows created by the bulb on either side of it.
All lamps required for this type of work should be in waterproof lampholders and be
protected by guards or shades. Local lighting at the work point should supplement the
general Lighting scheme.
Luminaires should always be placed so that no person is required to work in their own
shadow and so that the local light for one person is not a source of glare for the next.
Great care should be taken that local light reaches the work from the same general direction
as light will come from window or permanent fitment when the job is finished. By doing so,
blemishes that would show up badly in the final lighting can be avoided.
Pendant luminaires should be supported so that the supply cable is not required to bear any
weight. Festoon lighting is an exception but, in this connection, only the type which uses
moulded-on lampholders is to be recommended.
Preparation
is the operation part of a routine. If so, could it be more effectively planned and executed?
Preparation
is the operation part of a routine. If so, could it be more effectively planned and executed?
INTRODUCTION 1
DEFINITION
MAIN APPLICABLE U.A.E LEGISLATION
SECTION 9
Municipalities & Agricultural Department
H&S Construction Codes of Practice
PART TWO
SECTION 9
INTRODUCTION
Both highly flammable liquids (HFL) and liquefied petroleum gas (LPG) are widely used in building site
processes and operations. The principle hazard associated with both is fire, and it is essential that
precautions are taken to limit the risk involved.
Broadly speaking in dealing with both substances safety may be divided into three aspects:
• Storage
• Handling/transport
• Use
DEFINITION
Highly Flammable Liquid means any liquid, liquid solution, emulsion or suspension which when tested:
Liquefied Petroleum Gas means commercial butane, commercial propane or any mixture thereof.
9.1.1 storage
On building sites, highly flammable liquids are not normally stored in fixed tanks. The following
details relate to the facilities necessary for safe storage of adhesives, paint, solvents etc. in
drums and cylinders up to 225 litres (50 gals’) capacity.
in open air
inside buildings
• a separate building should normally be provided and used solely for the storage of highly
flammable liquids where security and protection from weather is required. Such a building
need not be constructed of a fire resisting material.
• It should be located in a safe position, i.e. the distance between the outside wall of the store
and any adjacent buildings or boundary fence should not be less than 4m. Should space be
insufficient to isolate the store in this way, wall/partitioning must constructed with a fire
resisting material.
additional points
• adequate ventilation of the store should be achieved by louvers or grilles. Care should be
taken not to obstruct these vents by stacked drums.
• a sill,no greater than 150mm should be provided at each door opening to prevent the outflow
of spilled flammable liquid.
• store should be marked ‘Highly Flammable’, or flammability specified, e.g. ‘Flash point below
32oC’, in clear bold letters.
• naked flames, smoking or means of ignition should be prohibited in the area. Lighting
should be of the approved flameproof type.
• portable fire extinguishers of the dry powder or vaporising liquids (BCF) type should be sited
at strategic positions adjacent to the store as necessary.
• where the quantity of highly flammable liquid to be stored is not more than 50 litres (10 gals)
it may be stored in the workplace, in a suitable cupboard or bin of fire resisting structure.
9.1.2 fire
For small fires involving highly flammable liquids Foam (AFFF) portable fire extinguishers are
preferable. Dry powder should only be used in the absence of Foam - especially if the liquid is
flowing; when the liquid is contained (as in a drip tray) CO2 extinguishers also suitable, but is
best used in covered areas preferably by trained personnel.
You should note that the efficiency of the external use of CO2 is severely restricted because it
gets quickly dispersed with the wind.
Note: Water must never be used to extinguish fire involving flammable liquids.
• decanting of HFL should be carried out either in the open air or in a separate room of fire
resisting construction. Containers should be checked for leaks, sealed or contents
transferred as necessary. Small ready-to-use containers should be marked ‘Highly
Flammable’ and capped. A number of companies supply special drums, containers, taps
and drip trays, especially designed for HFL, incorporating spring loaded caps and spouts
etc. (see Fig.3) funnels should be used to minimise spillage and trays to contain any
unavoidable spillage.
• filling of small containers from larger drums should
not be carried out in the store but in a well-
ventilated place, preferably in the open air. Small
containers should be marked ‘Highly Flammable’
and fitted with an effective cap. Where applicable,
cans should be fitted with pouring nozzle with
spring-loaded closure cap.
• in general, where work involves the use of HFL inside a room or confined space, the power
supply should be cut off. Any space-heating appliance provided must either be sited remote
from any flammable vapour source or be incapable of causing ignition.
• naked flames, welding, heating torches, cigarettes, etc. should be prohibited in an area
when HFL vapour is present.
• metal bins with lids should be provided for off cuts, waste material and cleaning rags
contaminated with HFL, and should be emptied frequently.
• HFL or toxic solvents should never be used to wash hands, floors or surfaces. Use
detergent degreaser cleaner.
• if brushes and scrapers require soaking, use suitable container with lid.
• identify adhesive, its flash point and manufacturers recommendations for use and safety.
• open doors and windows; provide mechanical exhaust ventilation where necessary.
• when fixing floor coverings with highly flammable adhesives, treat only small areas at a time
and work towards door from further point.
• avoid introducing sources of ignition into work areas, e.g. cigarettes, hand tools, combustion
engines, heating equipment producing naked flames. Electrical equipment and fittings
should be of suitable flameproof design, or be isolated by removal of fuses.
• provide warning notices at entrances to the area and, where necessary, barriers to prevent
unauthorised access.
Note: Where petroleum-based adhesives are in use and doubts exist as to the concentration
of flammable or explosive vapours, sampling equipment should be employed.
• leakage, especially of liquid, may release large volumes of highly flammable gases. One
cubic metre of liquid propane equals roughly 250 cubic metres of propane gas.
• a small, proportions of gas in air (for propane, between 2% and 10%) can give rise to an
explosive mixture. If present in a confined space and ignited, it will cause an explosion.
• because LPG vapour will sink and flow, any vapour/air mixture arising from leakage may be
ignited some distance from the point of leakage and the resulting flame travel back to the
point of leakage.
• leakage may be noticed by smell or the cooling effect on the air at the point of leakage
causing condensation. Leaks should not be traced using a lighted match or naked flame.
Use soapy water.
• in contact with skin, the liquid will cause severe frost burns.
KGs Distance in
metres
50-300 1
300-1000 2
1000-4000 4
• cylinders should be protected from direct sunlight by a roof of light, fire resistant material.
• two exits should be formed (not adjacent to each other) with doors opening outwards and
not self locking.
• signs should be displayed indicating the presence of LPG and prohibiting smoking and
naked flames.
• the storage area should be kept free of weeds and grass. Sodium chlorate should not be
used for this purpose. Access/egress must be kept clear.
• LPG cylinders may be stored with other cylinders of flammable gases but should be
separated from oxygen, toxic or corrosive gases by a distance of 3m.
• stocks should be grouped by the 1000kg and groups separated by 1.5m gangways.
• LPG cylinders should not be stored within 3m of flammable liquids or combustible materials.
• cylinders must not be dropped during handling or brought into violent contact with other
cylinders, or adjacent objects.
• where lighting is necessary, it should be mounted at least 4m above ground level and at
least 2m above the topmost cylinder of the stack.
9.2.3 transportation
When loaded on vehicles for transportation, cylinders, (whether full or empty), must be stood
upright and secured. Vehicles should have fire extinguishers (CO2 - dry powder) readily
available, should carry first aid packs, and display appropriate warning notices.
It is difficult to cover all aspects of the use and application of LPG; following list of points should
not be regarded as exhaustive.
• before and after use, valve protection caps and plastic thread caps/plugs should be fitted to
minimise damage.
• cylinders should be kept upright and care should be taken during handling.
• full and empty cylinders should remain separated. Valves should be left in closed position
when not in use.
• never place cylinders below ground level, since any leakage of gas will not disperse.
• the gas cylinder should always be positioned at least 3m away from the boiler or cauldron.
• full cylinders, not connected, should be kept at least 6m away from appliance. Full cylinders
awaiting use should be kept out of direct sunlight.
• supply hoses should be checked for crushing, damage to metal braiding and impregnation
by bitumen. Unserviceable hoses should be replaced.
• if frost forms on outside of cylinder, flow rate is excessive. Avoid by using two or more
cylinders and a manifold or, if possible, a smaller burner.
• a suitable high-pressure hose should be used and inspected frequently for wear.
site huttage
• cylinders and regulators should be fixed outside the building and the supply taken in at low
pressure via rigid pipe (copper or iron), with a flexible connection to the appliance.
• appliances designed for use outside and requiring high ventilation should not be used within
huts.
• ventilation for convector heaters and cookers should be both permanent and adequate.
• weekly inspections should be carried out if soot forms or smell occurs, the reasons should
be determined.
fire
Instructions for dealing with LPG in the event of fire may vary with given situations. However, in
an emergency, it is of paramount importance to avoid endangering human life.
• summon the Fire Services (civil defence department). Acquaint Fire Officer with location of
all cylinders.
• if it can be done safely, turn off all valves to cut fuel supply and remove cylinders from the
danger area. Where this is not practicable, cool by copious spraying of water.
• if cylinders are equipped with automatic relief valves and fire exposure is severe, it must be
remembered ignited gas jets from these valves can extend a considerable distance.
• if cylinders are exposed to severe fire conditions and engulfed in flame, no attempt should
be made to fight fire. In such conditions summon Civil Defence and evacuate the area.
• where flame from a leaking gas bottle is extinguished, but gas or vapour continues to
escape, there is danger of an explosive re-ignition.
fire extinguishers
• sufficient numbers of adequate size dry powder fire extinguishers should be available.
Foam extinguishers are only suitable for small internal LPG fires.
• extinguishers should be provided for all operations and locations involving LPG, ranging
from the use of hand tools to site huttage and bulk storage.
access clear
mesh fence
roof cover
separation distance 4m
c) storage in building
used exclusively for HFL
sill at doorway
well ventilated
separation distance 4m
Workplace
50 litres (10 gals) or less in fire resistant, marked bin/cupboard
Decanting
in open air or fire resistant building
funnels/trays used
Spraying
identify materials: observe precautions in use and storage
protective equipment/clothing
Flammable adhesives
identify type of adhesive and check precautions for safe usage
Storage
fixed/movable tanks - obtain specialist advice
separation distance 4m
compacted/paved base
mesh fence
access clear
Transportation
cylinders upright and secured
first aid
warning notices
inspect equipment weekly, hoses, clips etc. Test for leaks - use soapy water.
Bitumen Boilers
cylinder - 3m from boiler (not in use - 6m)
protect from direct sunlight
Hand tools
lash cylinders upright
Huttage
cylinders outside building
SAFETY SIGNAGE
INTRODUCTION 1
MAIN APPLICABLE U.A.E. LEGISLATION
10.1 PROHIBITION 2
10.2 MANDATORY 3
10.3 WARNING 4
10.4 SAFE CONDITION 5
10.5 FIRE EQUIPMENT 6
10.6 HAZARDOUS SUBSTANCE CONTROL 7
10.7 DETERMINING SIGN SIZES 8
10.8 STANCHION SIGNS 8
10.9 SAFETY NOTICE BOARDS 9
SECTION 10
Municipalities & Agricultural Department
H&S Construction Codes of Practice
PART TWO
SECTION 10
SAFETY SIGNAGE
INTRODUCTION
Safety Signs should be used to inform, advise, instruct, warn of danger and improve safety in the
workplace. Signs incorporate certain colours which have specific meanings as follows:
- You Must Not - -You Must Do - - Caution - - The Safe Way - - To indicate -
INTERNATIONAL STANDARDS
BS 5378: Part 1:1980
10.1 PROHIBITION
• background colour should be white
• the symbol shall be black and placed centrally on the background and shall not obliterate
the crossbar
• red shall cover at least 35% of the area of the safety sign
10.2 MANDATORY
• background colour shall be blue
• the symbol or text shall be white and placed centrally on the background
• blue shall cover at least 50% of the area of the safety sign
10.3 WARNING
• background colour shall be yellow
• triangular band shall be black
• the symbol or text shall be black and placed centrally on the background
• yellow shall cover at least 50% of the area of the safety sign
symbol signs
450
400
200
100
Clips are supplied for retaining signs into the frame, this allows interchangeable messages
to suit the necessary requirements
• be set up in prominent locations on the site that are clearly visible to the Contractors
employees and anyone entering the works
• contain all relevant emergency and contact numbers required for the contract
• be safely supported and suitably placed to withstand bad weather conditions e.g. strong
winds
The Contractor’s staff and labour force shall be made fully aware of the safety signs and the
emergency contact information, prior to commencing duties on site.
A Actions/Conditions Yes No N/A B Safety Eq. & Protective Clothing Yes No N/A
Depressurised/ Drained Reqd.
Goggles/Face Visors/Hard Hats
Steamed/Water Flushed PVC Gloves/Safety Boots
Ventilated Properly Respirators
Isolated Mech. & Tagged Escape Sets/Full BA Sets
Isolated Electrically & Tagged Safety Belts/Safety Harnesses & Safety
Combustible Mats Cleared Lines
Three in One Gas Monitor
Lighting is Sufficient Man Riding Winch
Continuous Monitoring Reqd Portable Fire Appliances
Area clean & Safe Overalls - Chemical/Ordinary
C Other Safety/Protective Equipment or Actions Required:
I Certify That I have Inspected the Site, and Subject to all the Safety Requirements detailed in this Permit being fully
implemented, I Confirm that it is Safe for Hot/Cold Work to Start.
Name: Position: Signature: Date:
D Toxic/Hazardous Mats. To Safe Limit Test N/A Time Date Name Signature
be tested Result
Combustibles/Methane Gas L.E.L. 5%
Oxygen Above 19%
Hydrogen Sulphide 10 PPM.
Chlorine 1 PPM.
Carbon Monoxide 50 PPM.
Special Instructions:
Note: A new Permit Must be Issued For Any Change In Conditions: IMPORTANT: This Permit Does Not Allow
“SMOKING” At Any Time
AUTHORISATION:
Signature of issuing authorised person Time: Date
RECEIPT:
P I have read this form and understand the special precautions to be taken prior to and during entry.
A Signed: (person in charge of the work) Time: Date:
R
T
CLEARANCE:
4 Work in the above enclosed space has been completed (or stopped) and all the men under my charge withdrawn.
Signed: (person in charge of the work) Time: Date:
CANCELLATION:
All copies of this permit are hereby cancelled.
Signed: (person in charge of the work) Time: Date:
Project:
Authorisation is given to the Contractor/Person as indicated below , to carry out the following task/s and shall adhere
to the precautions as listed to ensure the work is carried out safely.
Description of work:
Plant/Equipment/System:
Precautions necessary:
1.
2.
3.
Location of:-
I acknowledge receipt of this permit and I am satisfied that the precautions taken are adequate and I accept
responsibility for undertaking the work specified above in a safe manner. I declare that neither myself nor those
persons within my control will attempt any task other than as specified above.
I certify that the work specified above has been completed/stopped*, and that the safety measures have/have not*
been removed.
I certify that the above safety measures have been removed and the plant/equipment* is safe to operate and is hereby
returned to normal service. This permit is hereby cancelled and his completed form is filed for record purposes.
MECHANICAL/CIVIL CHECK
Underground Pipelines/Drains etc. Yes No If present – specify exact location and Precautions
………………………………………………………………………………………………………………………....…………..
Name Position Signature Date
Underground Running Telephone Cables etc.: Yes No - If present – specify exact location and Precautions
…………………………………………………………………………………………………………………………………........
Name Position Signature Date
Safety Eequipment: (tick box) Road Signs Barriers Flashing Lights Traffic Lights
I have personally checked the site and conditions and permission is granted for work to commence under all the above
mentioned precautions.
Name Position Signature Date
I confirm that I fully understand and will implement all the safety requirements detailed in this permit, and that all
those under my control will be fully informed and instructed in its implementation.
Name Position Signature Date
“E” - COMPLETION: Work is stopped/completed. Site Inspected and made safe. Work permit cancelled.
PERMIT TO WORK
INTRODUCTION
MAIN APPLICABLE U.A.E. LEGISLATION
SECTION 11
Municipalities & Agricultural Department
H&S Construction Codes of Practice
PART TWO
PERMIT TO WORK
INTRODUCTION
For work involved in areas defined as confined spaces or when isolation of either Electrical,
Mechanical or High Pressure Systems etc. is required, the most satisfactory way of ensuring a safe
system of work is by observing a permit to work system.
The permit to work is an operational document prepared by a responsible person who is familiar with
the work procedures, the hazards and all necessary precautions and who has carried out a thorough
assessment of the situation.
The permit gives a written authority that the area concerned is safe to enter and the work to start, and
lays down the time when it must stop. It sets out the correct sequence of work, the precise way in
which the work is to be done, the responsibilities of all persons involved, and the safety checks made
and all the precautions taken. The permit to work is not issued until the responsible person has put his
signature to this record, signifying that every step in the sequence of safety checks has been taken.
• limitation of time
• clearance of isolation
• cancellation of permit
The term Permit to Work refers to the pro-forma or certificate which forms a part of an overall
safe working system.
• effective instructions and training to all personnel in the issue and use of permits.
The permit is therefore a written document that gives authorisation to certain people to carry
out specific work within certain time constraints and which sets out the main precautions
needed to complete the work safely and without risk to health and safety of all those who are
involved.
Note: The mere issue of a Permit to Work does not simply give permission to carry out
dangerous work or, In itself, make a job safe.
The purpose of a Permit to Work system is to ensure that proper consideration is given to
the risk of particular work and that these are assessed and controlled before work starts.
11.2.3 objectives
The primary objectives of the procedure are to ensure proper authorisation of designated
work which may be of certain types and type within certain designated areas (other than
normal production).
11.2.4 understanding
Management and Supervision must ensure that persons involved in such work fully
understand the exact:-
• precautions to be taken
• limitations as to the extend of the work and time during which the work may be carried
out
A system of control must be provided and provisions made for a record showing that the
nature of the work and the necessary precautions have been checked by the appropriate
persons.
Line management should also provide a formal hand - back procedure to ensure that the
part of the plant, installation or equipment affected by the work is in a safe condition before
normal work is resumed.
• inspection • dismantling
• alteration • modification
• construction • cleaning
11.3 Attachments
Attachments A, B, C & D are samples of typical formats that can be used when a Permit to
Work is required.
INTRODUCTION 1
MAIN APPLICABLE U.A.E. LEGISLATION
12.1 DUTIES 2
12.2 SUITABILITY 2
12.3 HEAD PROTECTION 3
12.4 EYE PROTECTION 5
12.5 HEARING PROTECTION 7
12.6 FOOT PROTECTION 9
12.7 HAND PROTECTION 10
12.8 BODY PROTECTION 11
12.9 RESPIRATORY PROTECTIVE EQUIPMENT (RPE) 12
12.10 SAFETY HARNESSES AND BELTS 16
12.11 ENERGY ABSORBING DEVICES 17
SECTION 12
Municipalities & Agricultural Department
H&S Construction Codes of Practice
PART TWO
SECTION 12
INTRODUCTION
Where a risk cannot be controlled adequately by other means, employers have a duty to provide
suitable PPE.
The use of personal protection in the form of clothing or equipment should be considered as a last
resort in the minimisation of accidents. All too often there is insufficient effort to reduce or eliminate a
hazard, and too much reliance on personal protection to prevent the hazard giving rise to personal
injury.
When engineering control measures are not possible to be provided for total elimination of hazards,
the use of personal protective equipment is required.
There is considerable requirement within the Construction Industry for the use of personal protection,
even as a last resort, in view of the fact that, even on the safest of sites, hazards are not totally
eliminated.
In this section, required safety standards and advice is given on the following items:
Head Protection
Eye Protection
Hearing Protection
Foot Protection
Hand Protection
Body Protection
Respiratory Protective Equipment (RPE)
Safety Harness and Belts
Energy Absorbing Devices
12.1 DUTIES
12.1.1 employers
• assess hazards and risks prior to work to ensure proper selection and adequate provision
of personal protective equipment.
• equip all visitors with a minimum of hard hats and safety boots.
• erect signage to inform of PPE requirements when entering a site area and near site
hazards (see signage section)
12.1.2 employees
• be trained before using any PPE
• report any defects or loss, and where appropriate, return PPE to storage after use.
12.2 SUITABILITY
12.2.1 recognised marking
• All PPE shall either have a BS kite mark or CE mark (both being recognised marks
for PPE tested and approved to International Standards).
• the wearer should also inspect it before use to ensure that it is clean and not defective.
12.2.3 checks
To be suitable, PPE must:
• be selected to take account of factors such as length of time it needs to be worn and the
need to see and hear.
• be compatible with other PPE which may need to be worn (e.g. safety helmets and
hearing protection).
• allow wearer to be selective and have a degree of choice, where appropriate, before final
selection is made.
12.3.4 accessories
When determining the type of helmet to be supplied, consideration should be given to other
protective equipment which may be needed to be worn. Equipment, which can be mounted
on safety helmets, includes:
chin straps
used for work that might cause the helmet to fall off e.g. steel
fixing, where much of the work is done whilst bending over.
ear defenders
face shields
lamp brackets
• suitable face and eye protection must be worn by employees to protect face/eyes against
any flying particles / splash of chemical / hot solutions.
• impact resistant safety glasses with side shields / safety goggles/full face shield suitable
for grinding, buffing, chipping operations shall be provided and used.
• welding masks with appropriate filter glasses must be used when performing welding
operations and be to BS 1542.
• in addition, eye wash fountain shall be readily available at the site. In remote locations,
eye wash bottles may be substituted.
face shields
Type/Hazard Marking
Note: Glass lens supplied for use in impact and/or molten metal eye protectors in
combination with plastic lenses, must be additionally marked with the word “outer”.
The maximum levels to which persons may be exposed are expressed as a function of
intensity and time, e.g. 90 decibels [db (A)] for a period of 8 hours, or its equivalent This
value is quoted as the ‘equivalent continuos sound level’ or 90dB(A) Leq (8hr). The noise
levels in any particular working environment should be determined by measurement with
meters but, as a rough guide, if it is necessary to shout over a distance of 1 metre or less in
order to he heard, then the noise level may be excessive.
12.5.1 required safety standards
• persons working in areas with excessive noise above 90 dB(A), shall wear ear muffs/ear
plugs.
• high noise level areas should be identified and appropriate warning notices should be
exhibited to warn employees.
ear plugs
These are effective in relatively low noise level areas and many different types are now
available e.g:
• foam ear plugs which are compressed in order to fit into the
ear and expand to maximise protection.
ear muffs
The level of protection (amount of noise reduction) offered by hearing protectors, known as
the attenuation, will be dependent on the frequency of the sound source. Each manufacturer
of ear protection will have available an attenuation chart or graph showing the level of
attenuation at a range of different frequencies. Also quoted will be a standard deviation and
this figure should he deducted from the attenuation value to determine the assumed
protection. This is only if the equipment is properly fitted and adequately maintained.
Hearing protection, particularly ear muffs, should be selected so that it is compatible with
other items of protective clothing which may have to be worn.
• standard safety boots with metal toe caps must be worn by all personnel on site and in
places where foot injury could occur.
• prevent injury by the penetration of nails and similar sharp objects. Steel midsoles are
standard only on some boots and shoes and is preferred for building construction sites.
12.6.3 selection
The selection of foot protection will depend primarily on the assessed risk. In general, safety
boots rather than shoes are recommended for site work as they provide support for the
ankle on uneven or soft ground. Where there is a risk of injury from penetration or crushing,
protective steel toecaps and midsoles will be required.
comfort
• the weight factor particularly with boots having safety features such as steel toe caps and
midsoles can he important with respect to foot comfort.
• steel toe caps, designed to protect toes from falling objects may bruise and chafe the
toes across the foot joint after prolonged wear. It is important to choose the correct size
of footwear allowing for the type of socks to be worn.
12.7.2 selection
The first consideration in the selection of industrial protective gloves must be to identify the
hazard to be overcome and the handling requirements.
The handling of small components will require that the glove must be highly flexible and give
good dexterity to the worker.
grip
where grip is important, gloves made of a base material such as knitted
nylon or cloth with a latex coating, are suitable
chemical resistance
heat resistance
this will be required by welders, burners and other such as those working
on live heating systems. Leather gauntlets will be appropriate for these
trades
water resistance
• a PVC apron must be worn against splash from any chemical or corrosive substances,
• a leather apron is required to be worn by welders and others where there is potential
hazard of hot metal/sparks.
• full PVC suit to cover full body is required for persons entering tanks/vessels/sumps/pits
to protect against any chemical/corrosive substance.
usually In the form of PVC either one or two piece suits, and often in company livery. PVC
clothing is particularly prone to condensation on the inside and the incorporation of vents will
help alleviate the problem. Clothing manufactured from a breathable fabric (Gortex) is
available, but is quite expensive.
overalls
leather aprons
used by welders and burners to provide protection against sparks and molten metal which
might otherwise ignite their clothing
trousers
incorporating ballistic nylon or similar material, are available to give round leg protection to
chain saw operators.
The overall choice of equipment is wide. As the wrong choice could seriously affect the
health of the wearer, or lead to asphyxiation, expert advice is essential combined with
training and information being given to the wearer. In addition, cleaning and maintenance
facilities for the equipment must be provided to ensure continued effective protection.
• when there is potential for the presence of toxic gas/vapor or oxygen deficient
atmosphere, the self-contained breathing apparatus (SCBA) should be used.
• persons trained /certified on the usage of self contained breathing apparatus shall be
engaged and the work should be done under direct supervision. The basic tests to
ensure proper fitting of face masks must be done before each operation.
• proper selection and use of RPE should be ensured by taking into consideration
hazardous operation, contaminant, time, protection from the particular equipment,
limitations, state of health of individual.
• when working with asbestos, staff shall be provided with respiratory equipment approved
for use with asbestos which does not allow penetration by, or retain dust and which
should be a close fit with head cover.
• when engaged in grit blasting, the use of air supplied hood is essential If blasting in direct
contact with the dust / grit.
12.9.2 types
Inhaled air is drawn through a medium that is designed to remove most of the contaminant.
It is imperative that the correct medium is used for the particular contaminant and, where
dust and fibres are concerned the actual size range of the particles is an important
consideration. Filters are used to collect dust and fibres whereas, for gases and vapours, a
chemical absorbent is used usually contained within a replaceable cartridge.
disposable respirators
manufactured from filtering material and are usually termed
filtering facepeices or facemask. The facepiece is at a
negative pressure.
full-facepeice respirator
are made from rubber or flexible plastic, but designed to cover the nose, mouth and eyes.
The filter median is contained in a cartridge or canister directly coupled to the facepiece or
connected via a flexible tube with the appropriate filter fitted, it is suitable for either dust
gas or vapour and the facepiece is at a negative pressure.
consists of a full facepiece, with insulation and exhalation valves connected by a non
kinking hose to fresh air. The hose is normally less than 25mm in diameter and should not
exceed 9m in length unless breathing air is assisted by means of a hand or mechanical
power to maintain a positive pressure in the facepiece.
compressed air-line
12.9.4 selection
RPE should be selected so that the wearer does not breathe level of contaminants above
the relevant occupational exposure limits. A wide range of equipment is available, which
have various limitations in respect of efficiency and wearability. Proper selection is essential
if wearers are to receive adequate protection.
Heat stress call also be a factor when working in hot and humid atmospheres, or when
clothing is sealed as in asbestos stripping. The cooling effect of the supplied air in power-
assisted equipment and the low breathing resistance, make it more acceptable than non-
powered equipment.
Freedom of movement must also be considered. With compressed air line, breathing
apparatus movement is restricted by the air line, which must not become entangled or
kinked. Self-contained breathing apparatus does not have this limitation, but is bulky and
heavy; power assisted respirators are lighter.
• after the harness straps have been properly tensioned and adjusted, the inlet should be
lightly closed and the wearer should inhale gently. The face piece should collapse
slightly. Excessive leakage is indicated if the face piece does not collapse, in which case
the equipment should be readjusted and the test repeated. If excessive leakage is still
indicated, it is unlikely that the equipment will be suitable to the wearer. Alternative
equipment should then be made available for test.
In the case of power assisted respirators fitted with face masks, loss of air flow will be
indicated by increased breathing resistance.
12.9.7 training
Training in the use and application of RPE is essential for all types of equipment. Only
persons who are thoroughly familiar with the equipment and know the procedure to adopt in
an emergency should wear RPE.
• safety belts shall be examined periodically. Defective and worn out safety belts must
never be used.
• rescue safety belts with harness / life line must be worn when an employee is working in
a confined space.
• when using ladders, a fall arrest device connected to body harness must be used.
are used in situations where short duration work is necessary in areas where provision or
fall prevention measures would be impracticable. Belts and harnesses should be fitted with
a line of the appropriate length to prevent access to the danger area.
rescue harness
a rescue harness is used for protecting or rescuing workmen entering dangerous enclosed
places It must be capable of reasonable adjustment, be easy to fit in an emergency, and
be used in such a way that the fall is limited to 600mm.
The distance of fall should be as small as is possible, and to that end, the harness lanyard
should be fixed to the structure, or fixing point, as high as practicable above the working
position.
12.11.2 selection
The selection of energy absorbing devices is as important as the proper selection of your
body belt or full-body harness.
• one of the most important aspects of selecting energy absorbing devices is fully
planning the operation before it is put into use. Probably the most overlooked
component is planning for suitable anchorage points.
• lanyards should be kept as short as possible to reduce the possibility of serious injury
and should not exceed 2 metres.
• ensure that forces incurred during a fall would be less than 1,800 lbs.
• ensure the anchorage point and device will take the dynamic loads generated in a fall.
• energy - absorbing device selected should match the particular work situation, and any
possible free fall distance should be kept to a minimum.
• consideration should be given to the particular work environment and conditions. For
example, the presence of acids, dirt, moisture, oil, grease, etc., and their
effect on the device, should be evaluated. Hot or cold environments may
also have an adverse effect on the system. Wire rope should not be used
where an electrical hazard is anticipated.
12.11.3 use
• choose the correct type of anchorage point or restraint system.
• check for dangerous obstacles which a person could hit or swing into.
12.11.4 inspection
• check the equipment prior to use for damage (If in doubt seek expert advice
or replace it)
Note: If a harness and lanyard has been subjected to a fall, they should be disposed of and
replaced. The human eye cannot evaluate the stresses that have been put on the
equipment and next time they may not work. A suitably qualified person should
inspect energy absorbing devices, anchorages and systems annually or following a
fall.
12.11.5.1 training
• ensure you have received comprehensive instructions from the supplier as to
the devices proper use and application.
• train personnel in the correct use of equipment and the procedures that
should be followed.
• put in place emergency procedures and have means available to promptly rescue an
employee should a fall occur, since the suspended employee may not
be able to reach a work level independently.
SITE TRANSPORT
INTRODUCTION 1
MAIN APPLICABLE U.A.E. LEGISLATION
13.1 TRAINING 2
13.2 VEHICLE SAFETY CHECKS 2
13.3 SELECTION OF DRIVERS/OPERATORS 2
13.4 GENERAL SAFETY RULES 3
SECTION 13
Municipalities & Agricultural Department
H&S Codes of Practice Manual
PART TWO
SECTION 13
SITE TRANSPORT
INTRODUCTION
Transport accidents continue to contribute to the overall toll of injury and consequent personal misery.
About one quarter of all fatal industrial accidents involving transport occur in construction. Common
sense therefore suggests the need for clear rules and systems of work to ensure the safe use of
vehicles in the construction environment.
13.1 TRAINING
The provision of adequate training and instruction is a legal requirement as well as being
essential to good general safety management. This is particularly so in regard to the safe
use of mechanically propelled vehicles.
∗ fuel
∗ water
∗ oil
∗ batteries – for secure placing, cleanness, corrosion, and correct electrolyte level
before use and charging.
• any defects, damage or other condition considered by the driver as being likely to make
the operation of the vehicle unsafe should be reported immediately.
Persons selected to drive site vehicles should be physically fit with normal eyesight and
hearing. They should be mature, reliable and have the capacity to carry out the work in a
responsible manner.
INTRODUCTION 1
MAIN APPLICABLE U.A.E. LEGISLATION
SECTION 14
Municipalities & Agricultural Department
H&S Construction Codes of Practice
PART TWO
SECTION 14
INTRODUCTION
Mechanical plant and equipment in use in the Construction Industry are available in a wide and ever
increasing variety. The categorisation of such plant and equipment can be produced as follows:
∗ earthmoving Plant
This section covers hazards common to the above categories in addition to those hazards specifically
associated with the safe control of individual items of mobile plant and equipment.
• attainment of the legal age (as per Applicable UAE Legislation Section above) and to be
eligible of driving and operating such equipment.
• achievement of training on the correct operation of the specific plant or equipment, the
limitations of its use, and the hazards which exist if, it is not used properly.
• full awareness of usage instructions for the plant and equipment that will be operated by
them.
• ability to maintain stability of the mobile type plant they use and its load at all times.
• awareness that mobile plants should be parked on firm, level ground, with the engine
turned-off, brakes on, and any load lowered to the ground.
employers responsibilities
• ensuring that their drivers, operators and banksmen have the minimum of the
qualifications and achievements mentioned above.
• establishing a procedure to ensure that only drivers and operators, holding Certificates of
Authorization issued by the appropriate authority, use their equipment.
14.1.2 maintenance
It is only after proper maintenance that mechanical plant or equipment will remain safe to
operate. In this regard, the measures to be undertaken by the person, or department
assigned by the user to do the maintenance of the plants or equipment, are as follows:
• maintaining during repair and maintenance activities a safe system of work whereby
permit to work system, like lock-off systems, are established to ensure that no part of the
equipment can accidentally go into motion while work on it is in process.
• ensuring that measures like the propping of raised attachments (e.g. bodies, cabs, etc.)
are applied to prevent the occurrence of accidents as a result of accidental lowering.
• clear visibility of mobile plant drivers should be secured at all times. The following
measures must be secured:
∗ restricting speed limits, applying one-way traffic system within the site, in addition to
the spraying of water can help prevent dust from impairing visibility.
∗ keeping all persons not performing any activity related to the work under execution,
well outside the work boundary of working plant and equipment.
• drivers should never remain on a vehicle being loaded unless falling objects protective
structures/ cabins are used.
• drivers should always use the safe means of access to the cab (like ladders, steps, stairs
etc.) that should always be provided.
• all mobile plant should be properly equipped with lights, side and rear view mirrors.
• only trained persons having the proper tools are to mount or dismount, inflate or deflate
tyres which should be carried out following the manufacturers’ recommended
procedures, especially if the tyre is ballasted.
• persons should be trained to distinguish between the different required precautions with
the different designs and sizes of tyres.
• the jack should never be relied upon on its own to support a machine during the changing
of a tyre; sound and substantial timber must be used as a support for the jack.
• when earthmoving plant are driven on the highway, tooth guards should always be fitted
to excavator bucket teeth.
∗ the plant operator should supervise the loading/unloading of the plant under the
directions of the transporter driver to ensure that such activities are done at low
speed and safely.
∗ the vehicle should be designed to carry loads exceeding the anticipated maximum
floor load to be carried.
∗ the carried plant should be securely fixed so that there is no possibility of potential
moving, toppling, or falling off the vehicle during transport. Brakes are to be also
engaged.
∗ the carried plant should also be loaded in such a way as to keep its center of gravity
as low as possible, and as close as possible to the centerline of the vehicle in order
to increase its stability.
∗ the availability of sufficient area to prevent the striking of the machine with
obstructions, is to be checked.
∗ the transporter on which the plant is loaded should be parked on a firm and level
ground and never on a ramp with an unsafe angle.
• Special care to be made in soft fill areas since there is possibility of sinking of the lower track deeper than
the upper one.
• During travel, the bowl should be kept high enough to prevent any collision with low objects and ground, and
low enough to prevent any instability occurrence on turns.
• No person should be present in the work area of the excavator. When necessary, the person may access
this zone only after informing the operator by signs or radio.
• The machine should be positioned so that the wheels or tracks are at 90ºto the workface to allow for rapid
withdrawal when necessary.
• The bucket should not be extended too far in the downhill direction so as to prevent unstable conditions.
In addition to those applicable to excavator (item c above), the following is applicable to backhoe:-
• Backhoe attachment must be set in the travel position when the front shovel is used.
• The shovel should be lowered to ground whenever the backhoe is operated in poor soils conditions which
could cause stabilisers to sink.
• Correctness of Trenching depths is to be verified immediately before start, especially when working in multi-
service areas.
• Operator should not rely on the clutch slip mechanism which could stop the operation when a boulder is
encountered. He should manually disengage the digging mechanism before attempt of removal of boulders.
• Operators must check the rear before and during reversing the machine as for the majority of the time, this
equipment is operated in reverse direction.
High-speed equipment
designed to work on
slopes.
• When working on slopes, special precautions are to be made in presence of wet soil conditions.
• Flags are to be fixed to the blade in addition to lights whenever the grader machine is working on a road
used by other equipment.
The following guidance applies, in general terms, to the use of both Rough Terrain Fork Lifts
and Telescopic Materials Handlers. The expression "Fork Lifts" will be used in this chapter to
cover both types of machine.
The efficiency and safety in use of fork lifts depends mainly on the competence of those who
control, maintain and operate the equipment.
Operators must.
• Before anyone is permitted to operate a machine for the first time, he must be given off-
the-job basic training by a competent instructor and, at the end of the training, pass a test
on the skills and knowledge required for safe operation in all aspects of fork lift operation.
• A record must be kept which includes the details of basic training given and the nature of
the test. The employee will need a copy of the record, as evidence of training, on change
of employment.
• Employers should not allow personnel to operate fork lifts without written authorisation,
relating to specified types of fork lift.
• Banksmen should be 18 years of age or over and medically fit, with good eyesight,
hearing and reflexes. They should be familiar with any communication systems or signals
used in association with the machine's operation and have been sufficiently trained in the
workings of the fork lift to be able to direct the driver as necessary.
Safety in fork lift operation demands that machine stability is maintained at all times. Fork
lifts should, therefore, be carefully selected for the work they are required to do. For
construction sites, only those types designed for site work should be used.
The rated capacity of a machine will be quoted by the manufacturer; but careful checks
should be made to ensure that the capacity is appropriate for the work to be done. For
example, safe loads will be lower if the mast is tilted forward or the boom of a telescopic
materials handler is extended. Stated capacities apply in a static condition and may be far in
excess of those which are safe when the machine is moving. Limits of safe operation will
depend on site conditions and, as far as possible, machines should be operated only on
designated routes.
Even with the right machine for the job and satisfactory site conditions, the safe operation of
fork lifts on site still depends on the machine being properly operated. The establishment of
safe systems of work (in written form where appropriate) and incorporated in operator
training programmes is all important.
When stabilisers are fitted to a machine, they should be used in accordance with
manufacturers' instructions.
When operating fork lifts, drivers must be aware of the effect on the machine's stability of
induced forces. These are the forces which act upon a machine or on its load due to a
change in speed or direction; for instance, when starting, stopping, turning or rolling. The
greater the speed of the machine, the greater these induced forces. Accelerating,
decelerating and braking must be done progressively and smoothly, never hard or jerkily.
Turning must be done carefully, giving due consideration to the weight and placing of the
load and the condition of the ground.
Accident experience has indicated certain points which need particular attention:
• The weight of timber and other porous material should be re-estimated if it is wet.
• If the machine has a mast, loads should be lifted with the mast vertical or slightly tilted
back.
• Travelling on slopes, or in poor ground conditions, may be critical and the machine
manufacturer's recommendations should be followed. The danger of skidding and
overturning is particularly serious on two wheel drive machines where braking can cause
weight transfer away from the brake axle when negotiating a slope.
• There are reversing hazards with fork lifts, as with other transport. Audible warning
alarms are a useful aid, but their effectiveness can be limited by general background
noise and by operators relying on them, instead of carrying out a visual check before
reversing. The need for a banksman should always be considered.
Whenever the load impairs the operator's vision, a banksman should be used to guide the
operator.
With articulated fork lifts, a lift should not be made unless the front and back wheels are in
the same straight line.
Unit loads should not be broken down unless the overall weight would overload the machine.
stacking of materials
Stacking areas should be clearly designated and built on firm level ground with good
drainage. There should be adequate clearance between the stack and any wall, because
walls have been known to collapse as a result of the horizontal pressure exerted by the
weight of stacked material.
• Relation of its height to the narrowest base dimension (height should not exceed three
times the narrowest base width).
• The avoidance of any projecting items which, if accidentally struck, could cause
the collapse of the stack.
On sites operating fork lifts, all personnel must be fully instructed in the safe systems of work
laid down for their protection, and must observe them at all times. Some of the points which
should be covered by safe systems of work are:
• Everyone not directly involved in fork lift operations should keep well clear of the
machine.
3. never stand between the load and any exposed floor edge, or between the load and
a fixed object
4. wear conspicuous clothing; reflective jackets should be worn during poor visibility
attachments
safety devices
Each rough terrain fork lift should have a device incorporated in its hydraulic system which
will not allow the machine to lift weights greater than its rated load. The machine should also
have a device which will prevent a specified load being lifted beyond a given height.
The provision of a simple levelling indicator is strongly recommended, with the danger
zones, where it is not permitted to raise the load, clearly marked. Such indicators, if not
fitted as original equipment, can be fitted by the user; but only after consultation with the
manufacturer of the fork lift.
Every telescopic materials handler should be fitted with an Automatic Safe Load Indicator
which gives a continuous read out of forward stability and sounds an audible alarm when
the load exceeds 95% of the Safe Working Load. Other safety devices which should be
fitted to these machines are:
• a levelling indicator
• check valves which will hold the load in the event of hydraulic pressure loss
• an indicator lamp which will show when stabilisers are on firm ground
working platforms
Due to height limitations and the necessity to have an absolutely level surface, the use of
working platforms on fork lifts will be very rare on site.
maintenance
Fork lifts should be maintained in efficient state, efficient working order and in good repair.
• check that any defects previously reported to the supervisor have received
attention
• check brakes
• check the mirrors and test the horn (it is recommended that these items are fitted)
• check working of lift mechanism; check chains for lubrication and for foreign
material caught in links
Any defects revealed by these checks should be reported by the driver to his supervisor.
Machines should not be used until defects which affect their safety have been rectified.
• Ensure that before the start of work that the excavator is in proper working order and capable
of carrying the load of the attachments.
• Only involved persons are to remain close of the breaker and these persons should wear
safety helmets and eye protection.
• Driver/operator must be fully trained in all operational and safety aspects of the plant.
INTRODUCTION 1
MAIN APPLICABLE U.A.E. LEGISLATION
15.1 DUTIES 2
15.2 SELECTION 2
15.3 SITING 3
15.4 USE 3
15.5 MAINTENANCE 3
15.6 SAFETY STANDARDS FOR SPECIFIC TYPE OF
PLANT & EQUIPMENT 4
15.6.1 compressors/air receivers & pneumatic tools 4
15.6.2 cement and concrete mixers 5
15.6.3 bar bending and cropping machines 6
15.6.4 burning and welding equipment 6
15.6.5 brick/block saws 6
15.6.6 woodworking machinery 7
15.6.7 winches 7
15.6.8 tirfors 8
15.6.9 hoists 9
15.6.10 drilling rigs 9
15.6.11 piling equipment 10
15.6.12 cement silos 10
15.6.13 batching plants/transmixers 11
SECTION 15
Municipalities & Agricultural Department
H&S Construction Codes of Practice
PART TWO
SECTION 15
INTRODUCTION
This section identifies the general principles of selecting, siting, maintaining and using static plant and equipment
commonly found on Building Sites in Abu Dhabi.
Ministerial Order No. (32) Year 1982 – Article (1), (6), (7) (9), (10) (15),
15.1 DUTIES
15.1.1 employers
Have a legal duty to ensure the proper selection and maintenance of mechanical plant and
equipment, and to provide the required information, instruction and training to their operators
in their safe use
15.1.2 operators
should have been trained not only in the correct operation of the plant and equipment, but
also in the limitations of its use, and the hazards which exist if it is not used properly. It is
recommended that all plant operators hold relevant Certificates of Training Achievement
15.1.3 manufacturers
Have a duty to provide information on any hazards associated with their products and advice
on their safe use. Users should ensure they are in possession of this information, and make
certain that the operators are instructed accordingly.
15.2 SELECTION
The proper selection of static plant and equipment is of paramount importance to reducing
risks in the workplace. The exact requirements for each specific item of plant or equipment
should be determined by risk assessment.
• location of use and any limitations, eg noise, weight, vibration, fumes, fire risk, etc. that
exist, or will exist.
• method in which the plant or equipment will be safely transported to site, safely offloaded
and positioned.
• if appropriate, whether electric or combustion engine options are more suitable for the
workplace?
• what type of ground conditions are required to support the plant or equipment?
• if appropriate, whether solid tyres are a safer option than pneumatic tyres, or vice-versa?
• whether the item of plant or equipment can be safely removed from its location after
construction works have progressed?
• will any lifting operations be required to position the plant or equipment? If so, are lifting
eyes available?
15.3 SITING
As previously mentioned, specific items of plant and equipment should be selected with
exact siting (location and suitability) requirements in mind.
In some cases, the area where the plant or equipment is to be sited will need to be
prepared. For instance, ground compaction, level firm surfaces, extract systems, exclusion
zones, sound barriers, etc, may be needed. A risk assessment should be used to determine
the safe method of siting the plant or equipment, taking into account all the hazards from
when it enters the site gate to its final position(s).
15.4 USE
Before any item of plant or equipment is put into operation, it should be assessed to ensure
that it is in accordance with the selection specification, and safe for use.
• all operatives should be trained and/or experienced and competent to safely operate the
plant or equipment.
• all specific safety control measures determined by risk assessment should be in place
before the plant or equipment is used.
15.5 MAINTENANCE
Any item of plant or equipment will remain safe to operate only if it is properly maintained in
good condition. A programme of regular preventative maintenance should be established to
ensure that all plant and equipment is systematically inspected, serviced, maintained and
repaired as necessary. Responsibility for taking this action should be clearly identified.
A safe system of work must be maintained during all maintenance and repair operations
and, where necessary, a permit to work system (e.g. a lock-off system) should be
established to ensure that no part of the machinery is accidentally set into motion whilst
work on it is being carried out. (see Pt 2 section 11) - Permit to Work.
While personnel are carrying out inspections, maintenance or repair tasks, machinery
should be isolated and inspection covers, etc should be securely propped to ensure the
safety of the inspector.
The appropriate manufacturer’s repair and servicing instructions should be made available
to all persons responsible for carrying out the work.
• air supply to all tools is switched off when tools are left unattended or changed.
• sufficient room will be required around the mixer for easy/local access for materials.
• provision should be made to facilitate the delivery of materials to the mixer workplace
without the need to move the mixer, equipment, or materials.
• workplace should be maintained to provide a safe work environment for the attendant
and those people delivering materials and collecting cement or concrete.
• should be positioned to allow sufficient ventilation for diesel/petrol fumes to exhaust away
from the operation. If area is not sufficiently ventilated, a change of location should be
considered, but if this is not reasonably practicable, an exhaust extract system will be
required.
• all pulley wheels, belts and gears must be guarded as per the manufactures’ standards.
• on diesel/petrol engine mixers, the exhaust should be suitably shielded to prevent burns.
• unless otherwise stated by the manufacturer, the cover lid over the engine/motor should
be closed whilst the mixer is operational.
• should never be stopped when materials remain inside. Restarting the mixer when it is
loaded poses increased risks to safety.
• should not be loaded beyond its designed limits. If it will not do what is required of it with
reasonable ease, then it is probably not the correct machine for the job.
• care should be taken when operating the wheel. A tight grip is required when unloading
the mixer to prevent the wheel spinning, which can result in arm and hand injuries.
• mixer and workplace should be inspected daily to ensure continued safe working. Any
faults or damage should be repaired.
• many diesel engine mixers generate potentially harmful noise levels, especially for mixer
attendants working in the noise for many hours at a time. Risk assessment will determine
what ear defenders are required (if any) and who is required to wear them.
• proper procedure for starting diesel engines with a starting handle should be followed to
prevent thumb/hand injuries.
• attendants should wear suitable gloves whilst handling the mixer (but not for starting it).
gloves used should also be suitable for handling cement, lime and sand.
• stored, and adequately protected from the weather when not in use.
• fitted with a diamond tipped, steel blade to achieve a constant depth of cut throughout its
long life.
Because of the inherent dangers in using this type of saw, it is paramount that the
following precautions are taken:-
• saw should always be positioned on a firm, level and flat surface to ensure stability.
• cutting operations should be within a barriered off safety zone to prevent others being at
risk from the saw, and provide the operative (who cannot hear other work operations),
with protection from others.
• area surrounding the saw should be kept in a tidy condition to prevent trip hazards whilst
carrying bricks and blocks.
• ear defenders should be worn, especially with diesel/ petrol driven saws.
• hands should be kept a safe distance away from the revolving blade during the cutting
operation.
15.6.7 winches
Checks should be carried out on all winches to ensure that:
15.6.8 tirfors
The following precautions are necessary in the use of a tirfor machine:
• only the specially designed wire rope supplied by the manufacturer should be used.
• it should be remembered that, when using a tirfor machine for pulling purposes, the
necessary pulling effort is not equal to the load being moved. If the operation of the tirfor
is too much for one man, then the work should be stopped and the number of blocks
increased (within the rated capacity of the machine). (see Fig.5)
15.6.9 hoists
(see Pt 2 section 19) – Cranes and Hoists.
The proposed site should be investigated prior to any drilling operations, and particular
attention given to such hazards as overhead power lines, underground services, toxic fills,
mine cavities, cellars, derelict buildings etc., which could affect the safe installation and
operation of the drilling rig, and the safety of personnel. (see Pt 2 section 6) – Overhead
and Underground Services.
Permission must be sought from, and notification given to, the various interested bodies and
organisations, such as ADWEA, A.D.N.O.C, S.P.D. before site access or drilling operations
commence.
The working area immediately around the drilling rig should be kept tidy at all times, and any
working platforms, (e.g. on the vehicle-mounted rig) should be uncluttered and free of
grease and oil spillage. Rods, casings etc., should be stored in a safe manner; i.e., pegged
to prevent collapse and spreading
In particular:
• process of connecting and disconnecting rods and casings should be carried out in a
manner which avoids the possibility of injury to personnel.
• manual lifting of heavy equipment, rods and casings, should be carried out in the
recommended manner.
• loose attire such as scarves, ties and sleeves, and the wearing of wrist watches and
jewellery such as finger rings can lead to serious injury, and should not be allowed.
• when rotary percussive drilling is taking place, ear defenders should be worn.
• in the presence of rock dust, or similar hazards, suitable protection should be taken
against inhalation, ingestion, or damage to the eyes.
• wearing of safety footwear at all times is strongly recommended. (see Pt 2 section 12)
PPE
• entry into silo should be under a permit to work system as this is classed as a confined
space. (see Pt 2 section 11) – Permit to Work.
PORTABLE TOOLS
INTRODUCTION 1
MAIN APPLICABLE U.A.E. LEGISLATION
INTERNATIONAL STANDARDS
16.1 ELECTRIC TOOLS - GENERAL REQUIREMENTS 2
16.2 PORTABLE ELECTRIC SAWS 3
16.3 PORTABLE ELECTRIC DRILLS 3
16.4 PORTABLE ELECTRIC GRINDERS & CUTTING BLADES 3
16.5 CARTRIDGE OPERATED TOOLS 4
16.6 COMPRESSED - AIR TOOLS 5
16.7 HAND TOOLS - GENERAL PRECAUTIONS 7
SECTION 16
Municipalities & Agricultural Department
H&S Construction Codes of Practice
PART TWO
SECTION 16
PORTABLE TOOLS
INTRODUCTION
The majority of power driven hand tool accidents are caused by improper handling and poor
maintenance of the equipment, both of these can be overcome by good supervision and proper
training of the tool operators.
This section will introduce the legal requirements, and applicable standards that should be adopted
when using ‘Power Tools’ on the Departments Building/Construction sites.
INTERNATIONAL STANDARDS
OSHA 2207, Part 1926, Subpart I, section 1926.300 – 1926.305
condition of tools
All power tools and similar equipment, whether furnished by the employer or employee, shall
be maintained in a safe condition.
guarding
When power tools are designed to accommodate guards, they shall be equipped with such
guards when in use.
power source
Portable electric tools, when used in normal industrial conditions working off 220/240v power
source, should be in good condition, properly maintained and power supply to the tool fitted
with an approved earth leakage detector. (refer to site electrical requirements section in this
manual section 9) Electricity at Work.
Employees using power tools and are exposed to the hazard of falling, flying, abrasive, and
splashing objects, or exposed to harmful dusts, fumes, mists, vapours, or gases shall be
provided with the particular personal protective equipment necessary to protect them from
the hazard. (see Pt 2 section 12) PPE.
housekeeping
Good housekeeping is essential for good workmanship and safety. All tools shall be neatly
and correctly stowed when not in use. Work areas must be maintained in a clean and orderly
fashion.
maintenance
All tools shall be cleaned and inspected regularly, and those which are worn or damaged,
should be replaced or repaired immediately.
operators
Only authorised and competent persons shall be permitted to operate power tools.
• all portable saws are equipped with a fixed guard over the upper half of the blade and a
moveable guard which automatically covers the lower half of the blade. Both these guards
must be kept in place; blocking of the lower guard to prevent closure is prohibited.
(see Fig.1)
• saw blades shall be regularly checked, kept in good condition and stored suitably.
• blades used must be those recommended for the material being cut.
• operators shall be trained in the use of the tool; selection of the bit for the material to be
drilled, use of ‘starter’ marks, clamping of work piece and elimination of loose clothing on
the operator.
• appropriate personal protective equipment for the task and material being drilled.
• no person shall operate an abrasive wheel grinder unless he is trained and found to be
competent to mount and operate an abrasive wheel or cutting blade and perform the task
safely.
• grinding wheels maximum permissible speed should be higher or the same as the grinder
motor.
• the wheel must be inspected and dressed regularly. Appropriate eye shields and
respirators must be worn during the dressing operation.
• tool rests shall be used and adjusted properly. The rest should not be adjusted when the
grinder is in motion.
• cutting-off wheels should only be used on machines designed specially for their use –
never use an un-reinforced cutting-off wheel on a portable grinder machine.
• all guards designed for use with a grinder must be used and never removed.
• so far as it is practicable, the work area shall be maintained in good and even condition,
shall be kept clear of loose material and prevented from becoming slippery.
• approved cautionary notices displaying the hazards associated with grinding wheels shall
be posted at the work area where grinding or cutting is being carried out.
• the side of the wheel shall not be used to perform work under any circumstances.
• appropriate approved personal protective equipment shall be used by the operator and
helpers.
• grinding or cutting operations shall be isolated from other activities and personnel by the
use screens or any other approved means.
• the operator must undergo a specific test to check for colour blindness.
• all guards designed for use with a cartridge operated shall be used at all times – there
are no exceptions.
• tools and cartridges must always remain in the possession of the person to whom they
are issued. When not in use, they must be locked up in a safe and controlled place. They
must never be left unattended at any location for even the shortest of times.
• used and spare cartridges must be returned to the stores as soon as possible, and must
tally with cartridges signed out.
• the tool shall be examined when taken from the store, before use, and upon return to the
store for defects (by persons competent to carry out those examinations).
• any problems with the tool or cartridges shall be reported to the store keeper immediately
and a record kept for the life of the project.
• the tool must be dismantled and examined for defects (by a competent person duly
appointed and authorised to undertake this duty) every seven days and taken out of
service if any defects are found.
• the tool must always be operated from a firm and stable position. A scaffold is preferable,
but if use of a ladder is unavoidable, the operator must use effective fall-arrest equipment.
Mobile scaffolds must be securely tied to a stable structure.
• full face screen, safety helmet, ear protectors and suitable gloves shall be worn by the
tool operator and by any other worker who might be endangered by flying pins, particles
of materials, sparks, or the noise of firing.
Patent Head to
• cartridges must always be kept in the prevent over
penetration.
makers package and never be carried
loose or in a pocket.
• the manufacturers safe operating pressure for Fig.4 - Showing a pneumatically driven
hoses and appurtenances shall not be exceeded. Nailer/Stapler fitted with safety
device at the muzzle to prevent
• the use of hoses for hoisting or lowering tools shall tool from ejecting Nails/ Staples.
not be permitted.
• all tools will be stored in storage racks or bins and will be cleaned and oiled to prevent
corrosion.
• cutting edges will be protected during storage, and transporting to work area.
• all damaged or worn tools will be promptly and soundly repaired to original condition. If
tools cannot be repaired on the job, they will be replaced and the damaged tool taken
from site and repaired or destroyed.
• mushroomed chisels and cracked or broken chisel handles shall be repaired or replaced.
• appropriate personal protective equipment shall be used when performing work with tools.
Since errors in formwork erection are not always remediable, checking for the correctness of formwork
erection should be scheduled far enough ahead of erection time for the permanent structure. Items to
be checked for the correctness of formwork erection are the following:
General
adequate anchorage, levelling and correct positioning of sole plates and grillages are achieved.
base plates and grillages should be located to the centre of underlying sole plates.
vertical alignment should be plumbed within deviation in accordance with specified tolerance.
spacing for these members is to be executed in conformance with drawings and standard
details.
all members, couplers, fittings, wedges of the formwork and others are installed properly,
secured, tightened and at correct positions. If these precautions are not taken into account,
loose and non-nailed wedges may fall-out in presence of any vibration arising from activities
such as concrete placing and consolidation.
base and head jacks are not over extended unless detailed with adequate special bracing (see
figs. 4 & 5)
all bracings and lacings are coupled as close to node points and never more than 150mm away.
all bracings and lacings are connected to correct members e.g. diagonals to lacings to allow
right angle structural couplers to be used.
no storage should be placed on formwork since it is not designed to carry additional heavy
loads for other purposes.
formwork should be designed to allow safe lifting and handling from points designed for this
purpose.
persons not involved in the construction process, dismantling or inspection of formwork should
be denied access.
loose materials and plant should be fixed against any movement including lateral movement
induced by high winds.
whenever it is possible that workers can fall from slab formwork by more than 2metres, suitable
edge guards shall be installed.
whenever workers are erecting formwork elements higher than 2 metres over previously erected
slabs, guarded work platforms with access ways should be provided. These access ways
should be also guarded and wide enough to allow for workers to carry materials (see section 2 -
Scaffolding & Working Platforms)
proprietary formwork systems should be erected and used in accordance with manufacturers’
instructions.
removal of projecting nails and sticking elements (in the case of concrete) as work proceeds.
before removal of safety guardrails making part of the formwork, replacement safety guardrails
are to be installed and connected to the edges of concrete.
after removal, formwork should be supported safely during repair, oiling and other maintenance
works needed before reuse.
steel fixers should work at safe places or shops provided on site. Persons not involved in steel
shop work should be denied access.
during the cutting of reinforcement, protective gloves and eye protection must be worn by
persons performing work.
only recommended types of blades should be fitted to disc cutters to prevent any accident
arising from the breaking of a blade.
torches shall not be used in cutting steel of types adversely affected by heat.
the short end of the cut bar should not be left to fly off and endanger life of persons.
proper walkways should be installed over the fixed steel cages to secure the safety of persons
crossing over to access their destination.
ABRASIVE WHEELS
INTRODUCTION 1
DEFINITION
MAIN APPLICABLE U.A.E. LEGISLATION
17.1 DUTIES OF OPERATORS 2
17.2 TRAINING AND APPOINTMENT OF PERSONS TO MOUNT WHEELS 2
17.3 SELECTION OF WHEELS 2
17.4 ABRASIVE WHEEL CHARACTERISTICS AND MARKINGS 2
17.5 MOUNTING OF WHEELS 4
17.6 CUTTING OFF WHEELS 5
17.7 PEDESTAL/BENCH MOUNTED GRINDERS 5
17.8 GUARDS 5
17.9 CONTROLS 6
17.10 GENERAL SAFETY REQUIREMENTS 6
17.11 SUMMARY OF MOUNTING PRECAUTIONS 7
SECTION 17
Municipalities & Agricultural Department
H&S Construction Codes of Practice
PART TWO
SECTION 17
ABRASIVE WHEELS
INTRODUCTION
Abrasive wheels are commonly used in the workshop environment, and are potentially dangerous
because of their high speed of rotation, with the resultant possibility of break – up under centrifugal
stress.
For these reasons it is paramount that all personnel who use Abrasive Wheels follow the rules set out
in this section, in especially the wearing of suitable and approved eye protection.
• a mounted wheel or point and a wheel or disc having in either case separate segments of abrasive
material.
• a wheel, or disc made in either case of metal, wood, cloth, felt, rubber or paper and having any
surface consisting wholly or partly of abrasive material.
• a wheel, disc or saw to any surface any of which is attached a rim or segments consisting in either
case of diamond abrasive particles, which is, or is intended to be, power driven and is for use in
any grinding or cutting operations;
Ministerial Order No. (32) Year 1982 – Article (7), (10), (11) & (12)
• no employed person using an abrasive wheel shall wilfully misuse or remove any guard,
or wilfully misuse any protection flanges , other appliance provided, or any rest for a work
piece.
• every employee shall make full and proper use of guards, protection flanges and any
other safety devices fitted, and if he discovers any defect in the same, shall report such
defect to the manager, or other appropriate person.
• all entries must specify the class or description of the abrasive wheels which the
appointed person may mount, and the person appointed must be provided with a copy of
the entry or certificate.
• the employer may revoke an appointment at any time by a signed and dated entry in a
Register.
The best policy in selecting grinding plant is to consult manufacturers of machines and
abrasive wheels, and not to experiment without competent advice.
• abrasive means the abrasive used in the wheel construction. Aluminium Oxide is
expressed as A, Silicon Carbide as C.
• grain size means the size of abrasive grains used as cutting particles. The grains are
classified according to the sieve through which they have passed. The range is
expressed by numbers (coarse 8 to very fine 600).
• wheel grade is generally considered as the tenacity with which the bonding materials
hold the abrasive grains in a wheel. Wheels are graded as ‘soft’ or ‘hard’ according to
this degree of tenacity. The Grade scale is expressed in letters from A (soft) to Z (hard).
• structure means the relationship of abrasive grain to bonding material, and the
relationship of both to the spaces or voids that separate them. The void or spaces in the
structure assist in rapidly removing ‘chips’ from the wheel face, thus eliminating or
choking of the abrasive surface.
• bond type means the bonding material used in the wheel construction, and is
described by letters V (vitrified) B (resinoid) etc.
SEQUENCE Prefix ABRASIVE GRAIN SIZE GRADE Structure BOND TYPE Suffix
W A 46 K 5 V 17
Manufacturer’s
Abrasive Type Symbol DENSE TO OPEN Manufacturer’s
(Use Optional) 1 9 Wheel Type
2 10 Symbol
3 11 (Use Optional)
4 12
5 13
Aluminium Oxide - A 6 14
Silicon Carbide - C 7 15
8 ETC
VERY
Examples of marks
COARSE MEDIUM FINE FINE
8 30 80
1. cutting-off wheel
220 intended for cutting
10 36 100 240
12 46 120 metal might be A 30 T B.
280
14 54 150 320 2. cutting-off wheel
16 60 180 400 intended for cutting
20 500
24
brick might be C 30 T B.
600
3. a general purpose wheel
for use on metal and
mounted on a portable
GRADE SOFT MEDIUM HARD
grinding machine might
SCALE ABCDEFGH IJKLMNOPQRST UVWXYZ be A 163 R 5 B.
• before mounting the wheel, check that the speed of the spindle does not exceed the
maximum permissible speed marked on the wheel.
• it must be remembered that centrifugal force (the ultimate cause of wheel bursts)
increase, not directly with speed, but as the square of the speed. The speed at which the
grinding wheel revolves is, therefore, extremely important.
• It cannot be too strongly impressed that doubling the number of revolutions per
minute of a wheel, increases four fold its tendency to burst. The peripheral speed
is generally used for describing permissible wheel.
flanges
• every abrasive wheel must be mounted between suitable flanges, which should be not
less than one third the diameter of the wheel. The flanges should be recessed on the side
next to the wheel, to ensure that clamping pressure is not exerted near the hole.
• flanges should be of mild steel or other material of equal or greater strength and rigidity.
Ordinary cast iron is not suitable.
washers
Washers or blotters, as they are sometimes called, should be made of compressible material
not more than 1/16th of an inch thick. They should be used between the wheel and the
flanges whenever the clamping surfaces are flat, but not otherwise, as in the instance of
taper sided or dovetailed abrasive wheels.
• before running the wheel make sure the guard is in proper adjustment.
• if the machine is fitted with a work rest, adjust this as close as possible to the surface of
the wheel, rotate the wheel by hand to make sure it is clear all the way round.
unacceptable practices
The following unacceptable practices increase the liability of the wheel to fracture because
they result in excessive stress concentrated near the hole:
• paper washers not used between the wheel and the flanges.
• one flange omitted and the nut tightened directly against the wheel.
• the use of an ordinary steel washer as a substitute for a properly recessed flange.
• use of unequal flanges is liable to cause distortion and breakage of a cutting-off wheel.
(see Fig.1)
17.8 GUARDS
• guards shall be securely attached to the body of the machine.
• guards for straight grinding machines shall be Fig. 4 - Front enclosed Guard for
Straight Sided Wheels
provided with a front curtain, which shall be securely
fastened to the body of the machine.
• for cup wheels, the back face and periphery shall be enclosed, and the guard shall be
adjusted to compensate for the wear of the wheel.
• for depressed centre grinding wheels, the wheel shall
have a maximum angular exposure of 180° and the
guard shall be located as to be between the operator
and the wheel during use. (see Fig.5)
17.9 CONTROLS
• machines in which abrasive wheels are used must be provided with efficient devices for
starting and cutting off power, and the controls of such devices must be readily and
conveniently operated by the person using the machine.
• while the wheel is in motion, they must be properly secured and adjusted so as to be as
close as practicable to the exposed part of the abrasive wheel.
• before mounting, all wheels should again be closely inspected and ‘rung’ to make sure
that they have not been mishandled in transit or storage.
• wheel mounting should be carried out only by competent and authorised persons.
• the bush, if any, should not project beyond the side of the wheel.
• care should be taken to ensure that all wheels, washers and flanges are free from foreign
matter. Any burrs should be taken off flanges.
• washers of compressible materials not over 1/16th of an inch, should be fitted between
the wheel and its flanges where the surfaces are flat.
• wrinkles in washers should be avoided. Washers are not recommended for taper and
dovetail wheels.
• when tightening nuts, care should be taken to tighten them only just enough to hold the
wheel firmly. Excessive clamping pressure is liable to damage the wheel.
• the nuts should be tightened by hand pressure on a spanner and never by a hammer and
chisel or similar means.
• when the flanges are clamped by a series of bolts, care should be taken to screw up
each bolt uniformly. All the bolts should first be run up with the fingers and then tightened
in pattern formation afterwards.
WOODWORKING MACHINERY
INTRODUCTION 1
MAIN APPLICABLE UAE LEGISLATION
SECTION 18
Municipalities & Agricultural Department
H&S Construction Codes of Practice
PART TWO
SECTION 18
WOODWORKING MACHINERY
INTRODUCTION
Many accidents on different types of woodworking machinery are reported in the Building Industry.
Woodworking machine cutters can inflict very serious injuries and it is essential that all the precautions
for guarding them are strictly observed.
Neglect or ignorance of the safety rules governing the use of such machinery creates the conditions in
which accidents occur.
Everyone who operates woodworking machinery must understand and comply with the safety
requirements outlined in this section.
• they must report to responsible persons any defects in machinery, guards, devices or
appliances, and any damage or defects in the surface or ground around the machine.
• floors to be level, in good condition, free of loose material, (which includes chips, shaving
and saw dust) and not slippery.
• adequate natural or artificial lighting must be provided for the work being done on each
machine.
• where persons are likely to be exposed continuously for eight hours to a sound level of
90dB(A) or more, ear protectors must be made available and used, and all reasonable
measures taken to reduce noise levels. see section 24 – Noise at Work.
18.1.4 maintenance
• saw blades must not be cleaned while in motion.
18.1.5 controls
• every machine must be fitted with start and stop Fig.1 - Showing an emergency
controls which can be quickly and easily controlled stop fitted at knee height
to a fixed circular saw.
by the operator. (see Fig.1)
• must be guarded to the greatest practicable extent, having due regard to the work being
done.
• no adjustment may be made to any guard while cutters are in motion, unless safe means
(i.e. mechanical adjusters) are provided.
• allowance can be made for the development of alternative safeguards for cutters
providing these are effective.
Exhaust outlet
Extension
Table
Saw
Guard
Exaust
Outlet Emergency
Stop
Cross – Cut
Fence
Push Stick
• in the case of a parallel plate saw blade, the knife must Fig.3 - Showing position of
Riving Knife
be thicker (usually about 10%) than the plate of the saw
blade.
• where the diameter of the saw blade is less than 600mm, the top of the knife should not
be more than 25mm below the top of the blade. knife must extend at least 225mm above
the table.
• in the case of saw benches with more than one spindle speed, the blade must not be less
than 60% of the diameter of the largest blade the machine is designed to use at fastest
spindle speed.
• a notice must be displayed on the machine specifying the smallest diameter saw blade to
be used in compliance with the above provisions.
limitations on use
• no circular saw may be used for cutting any rebate, tenon, moulding or groove unless the
cutter above the table is effectively guarded.
• the saw blade teeth must project right through the upper surface of the timber at all times
in any ripping operation.
• circular saw must not be used for cross-cutting logs unless the material is firmly held by a
gripping device secured to a travelling table.
push sticks
be available for use on every hand-fed circular saw, and used to:
• assistants employed to ‘take-off’ cut material may only stand at the delivery end of
machine.
• where this operation must be performed, the delivery end of the machine table must
extend (over its whole width) at least 1200mm from the up-running part of saw blade.
• It must never be tied back or rendered inoperative Fig.6 - Example of a Hand Held Electrically
during sawing. operated Circular saw complete
with spring return guard.
• guard operates freely before using the machine.
operators should:-
• secure saw firmly, e.g. put a foot on the rear handle base plate and a hand on the front
handle.
18.5 TRAINING
No person should be employed on a woodworking machine, unless he has been trained and
instructed in its operation. Training should include:
• instruction on all machines the person is likely to operate and the types of work to be
undertaken on completion of training.
• instruction on the provisions in the law on Woodworking machines and the methods of
using guards, devices and appliances required by the law must be included.
General
Operatives
keep a list of authorised operatives.
operatives fully aware of requirements of woodworking machinery law and procedures for
testing new employees.
adequate training given on types of machine used and kinds of work done.
provided with all necessary equipment – including goggles, ear protectors, face masks and
other protective equipment where required.
floors to be level, in good repair, free of loose material and not slippery.
noise levels reduced as far as practicable – ear protection available where required.
fire extinguishers of correct type immediately available, and personnel trained in use.
Circular Saw
Riving knife
secure, sound condition, easily adjustable.
Fence
correctly adjusted and secured.
Top guard
sound; easily adjustable.
Feeding work
gripping device in use for cross-cutting logs.
Saw blade
in good condition – sharp, no cracks; not less than smallest diameter permitted.
Bottom guard
blade guarded below table (open frame machines).
Taking off
delivery table to extend 1200mm from up- running part of saw blade.
Prior to use
machine and plug compatible with supply.
blade securely fitted to rotate in the correct direction (teeth upwards at front end of saw towards
shoe plate).
saw adjusted to correct depth and angle before use, with teeth projecting just through underside
of the material.
During use
material being cut adequately supported.
use fence or straight edge as a guide; ensure clamps do not impede movements of saw.
INTRODUCTION
MAIN APPLICABLE U.A.E. LEGISLATION 1
SECTION19
Municipalities & Agricultural Department
H&S Construction Codes of Practice
PART TWO
SECTION 19
INTRODUCTION
Cranes and Hoists are used extensively on most building site, and although they each have their
different role, they are both primarily used to lift/transport men and material safely from ground level to
various levels and areas on a building site.
This section of the manual gives not only the safety standards required to select, erect, operate and
maintain this type of equipment, but also gives advice and guidance on how to achieve this, it is
therefore imperative that all contractors follow the standards and guidance outlines in this section
result of which will ensure the safe lifting of both men and materials at all times.
The person so appointed should be given adequate training and possess the relevant
experience to carry out the following duties:
• plan such operations and select the most suitable lifting appliances, gear and equipment.
• ensure that adequate inspection and maintenance procedures are in effect for the
selected plant and equipment
• must be at least 18 years of age and should be sufficiently mature to undertake the duties
involved.
• be medically fit for the purpose, with particular emphasis on eyesight, hearing and re-
flexes, and have a head for heights. (Periodic medical examinations are advised).
• trained in the general principles of crane operation and specifically in the type of machine
he is required to operate.
• trained sufficiently in the mechanics of his machine to be able to carry out routine
maintenance if required by his employer and to identify and report defects.
• trained in the hand-signalling system (approved signalling system is shown at the end
of this section)
Signallers should be readily identifiable to all concerned in lifting operations, (e.g. by wearing
a helmet in a distinguishing colour, or a high visibility jacket).
• be medically fit for the purpose with particular emphasis on eyesight, hearing, and
reflexes.
• be capable of selecting lifting gear suitable for the loads to be lifted, and to identify
defects.
• have a sensible knowledge of the safe working loads at the various radii of the crane.
• be capable of directing the safe movement of the crane and its load to maintain the safety
of all personnel.
Planning should consider a wide range of factors including the selection of lifting appliances
and gear.
Initially the appointed person will have to select the type of crane most suited for the work in
hand. Each type of crane has certain features which usually dictate the most suitable for a
particular application.
Mobile cranes are most suitable where the job duration is short and good mobility is required
around the site or between sites. Very few mobile cranes have pick and carry duties;
therefore they normally must be set up on their outrigger base at each lifting location.
crawler cranes
gradients:
Sufficient clear space for the length of the jib involved should always be provided as with
other cranes nearby, overlapping of jibs can create a special problem. Jibs and counter jibs
might touch and it is essential, therefore, to have a height differential.
Consideration should also be given to the proximity of other structures, buildings, houses,
(including the possible violation of their air space), Public access areas like highways should
always be checked with the owners or appropriate local Utility.
Note: There is now a new Ministry of Labour directive that in future, Tower Cranes will be
required to be sited so that neither the boom nor the jib part of the crane will overhang
onto main streets or any other buildings.
erection precautions:
The erection of a tower crane requires personnel with a good head for heights, specially
trained, and experienced in the particular type to be assembled working under the control of
a trained and competent supervisor.
Insistence must be placed upon the use of safety harness and the wearing of safety helmets
should be enforced where appropriate.
• company carrying out the erection is approved and licensed by the Municipality.
• that foundations for a static crane, the track for a travelling crane, or the supports for a
climbing crane, meet the detailed requirements of the manufacturer, or engineer.
• crane selection in erecting a tower crane should be adequate for any lift involved,
therefore the weight of each component (and its centre of gravity) determined, and
sufficient margin allowed for error.
• local weather and wind speed forecasts should be obtained from the Meteorological
Office and erection should only take place if the wind speed is within the limit quoted in
the manufacturer’s instructions for erection.
• concrete structures used for anchorage should be allowed to harden long enough to
acquire sufficient strength to take the loads imposed on the ties of climbing cranes. (see
Fig.6)
• rail mounted cranes should be operated in a fixed position or tied in. Secure stops
should be fitted to the rails in close contact with the bogies to eliminate all longitudinal
movement.
• at each stage of erection, the correct amount of ballast and counter-weight must be
properly positioned. On many cranes, the counter-weight is set in place on the counter-jib
before the main jib is erected.
• weight for ballast and counter-weight, as supplied by the manufacturer, should be marked
with their weight and secured in position to prevent accidental displacement and damage.
• ballast charts, showing the amount, distribution and unit weights of ballast used, must be
fitted to the crane base. Charts must be sited on the crane where they can readily be
seen at all stages of construction work.
• safe means of access must be provided to the cab and throughout the structure for the
purpose of inspection and maintenance. Access to the cab will be achieved using a
permanent steel ladder fitted with safety hoops and provided with rest platforms at 9m
vertical intervals.
• jib inspection may be afforded by the provision of an expanded metal walkway inside the
jib with life lines fitted to permit the fixing of safety harnesses, or by the use of an
inspection cage suspended from the jib or fitted to the saddle.
• wind speed indicators, visible in, or from the driver’s cabin, and at the base of the crane
should be fitted, and If the wind velocity registered is near the manufacturer’s safe
working limit, the crane should be placed out of service.
• automatic audible alarm must be fitted to sound when rail mounted cranes travel.
• warning lights should always be fitted where the top of the crane exceeds 150m above
local ground level and may be required where the obstruction exceeds 90m.
base
• should be calculated from the maker’s given loading figure on any one bogie under the
worst conditions and the known bearing capacity of the ground.
track
• must be laid to an accuracy of 6mm in gauge and the maximum slope either along or
across the track should not exceed 1 in 200 metres, unless recommended by the
manufacturer. Curved track can be used for most crane rails, but special precautions are
required to prevent distortion - steel tie rods must be fitted to stop tendency to spread;
curved fish plates should be used. A watch should be kept for any tendency of wheel
flanges to climb the rails
• where laid on a concrete base, the concrete should be level and strong enough to
stand the loading. Thin hardwood, grout or dry pack should be used between rails and
concrete to prevent the holding bolts from becoming loose as the rails bed down.
• should be straight or true to curve, slightly but not excessively worn, and be free from
holes burnt in the web, and holes in rails should always be drilled (burning makes the
rails too brittle). Rails should preferably be bolted to timbers and bolts kept tight. (Dogs
or spikes are not recommended.)
• must be perfectly level on curves, radii of curves will be specified by the crane
manufacturer and track layouts should be set and thoroughly checked by competent
engineers.
• area between must be kept clear of all materials and other obstructions, effective steel
wheel stops should be clamped at the end of the rail tracks with sand boxes, or
alternative method of retardation fitted in front.
• earthing must be effective and provide electrical continuity between individual rails. Fish
plates are not enough to give electrical continuity. The resistance between rail and earth
should never exceed 1 ohm.
• deflection of rail track under full load should never exceed 3mm.
• Where practical, outriggers can be extended and the feet kept just clear of the ground for
added safety, but care must be taken to ensure that the outriggers do not foul the ground
or any obstacle.
• lifting must be done with the stick/dipper in the outward reach mode only.
• if to be used as a crane without any restriction and with a variable SWL greater than one
ton, be fitted with an automatic safe load indicator and be subject an annual test and
thorough examination, or,
• loads carried on scaffold cranes should be such that they cannot protrude into the
scaffold structure and become dislodged and, to that end, any protruding scaffold
member in the line of operation should be cut off.
Note: The safe working load specified by the manufacturer may not be achieved due to the
unsuitability of many scaffolds to which these cranes are attached. In order to positively
determine their capacity in any given situation, it is strongly recommended that they are
tested in situ so that any deficiency in the scaffold may be rectified. Alternatively, the crane
may be derated.
On soft ground it will be necessary to pack solid material (timber, digger mats, hard core)
beneath crawlers and/or outriggers to allow for settling under load. Bearing plates or grillage
may be necessary to distribute the loads. (see Fig11)
For lorry mounted and mobile cranes, if there is any doubt about the suitability of the ground,
the following procedure must he adopted:
• test by lifting the load approximately 150mm off the ground and holding for a period over
one outrigger at maximum possible safe radius to see if the outrigger sinks.
• if an outrigger sinks, lower the load, increase the area of packing under the outrigger and
re-test as above.
The work area should be delineated and, where appropriate, process plant etc. which may
create risk should be isolated, also road closure may be necessary.
Care should he taken to ensure that, prior to erection of any large crane, air traffic control
authorities, both civil and military are consulted
There must be available all the necessary parts and equipment to enable work to be carried
out safely. Substitution of parts with those of inferior quality or even incorrect components,
can lead to structural failure, often with disastrous consequences.
• have access to the manufacturer’s instruction book appropriate to the particular crane.
Special care should be taken when unfolding swing-around fly jibs or lattice extensions.
Always ensure pins are in position before releasing the latch mechanisms. Careful control
during the swing around operation is important. Manufacturer’s instructions should be
followed, particular note being taken of the use of control ropes.
19.4.5 ropes
It is essential that the correct number
of hoist-rope falls are reeved for a
given duty in accordance with the
crane.
The ends of hoist and other ropes should be
properly secured. Where pear wedges are
fitted, they must be of the correct size and Fig.12 - Tail rope folded back on itself and
the tail of the rope should extend sufficiently secured with a bulldog grip.
Note: “U” part of bulldog clip should
through the wedge for it to be folded back on always be attached to the dead end of
itself and secured with a bulldog grip. (see rope.
Fig.12)
The following points should also be Fig.13 - Small length of rope attached to dead
end and secured by a Bulldog Clip.
observed:
• when transferring wire rope from reel to drum, every precaution should be taken to avoid
twists and kinks.
• when reeving hook blocks on cranes capable of height extension, special care should he
taken to provide sufficient length of hoist rope to accommodate the height in use at the
time, and still leave the statutory two full turns on the drum when the hook is in its lowest
working position. In addition, the rope must be secured to the drum.
• ropes should lay correctly on all winding drums. Uneven winding causes gaps in the
layers, which produce undue wear and tear.
• wherever ropes need to be renewed or replaced, the replacement must be of correct size
and construction.
Earthing electrodes, capable of dealing with all contingencies, including electric storms,
should be provided for tower and derrick cranes; where cranes are rail mounted, it will be
sufficient to earth the track.
Operational controls on the crane not required for use during the actual erection procedure,
should be isolated where possible.
• warn all other personnel to keep away from the crane and not to touch any part of it or
the load.
• if the machine is not mobile, remain in the cab until ADWEA Officials can make the area
safe.
• if, due to fire, or any other reasons the crane must be vacated by the operator, he should
jump clear as far from the crane structure as he is able, avoiding touching both crane and
ground simultaneously.
On truck mounted cranes controlled from the truck cab, there will be an indicator on both
sides of the jib. (see Fig.14)
Where the term SWL is used in the following paragraphs, this refers to the maximum safe
working load of the crane as sited. The automatic safe load indicator (ASLI) is a safety
device provided to warn when the crane is being overloaded and at risk of overturning.
All cranes over one ton capacity are required to have such a device fitted and in proper
working order. They must be inspected each week and a record kept. The indicators are
required to give visual warning to the crane driver of an approach to SWL, and an audible
warning to those in the vicinity of the crane of an overload state. The percentage of SWL or
overload at which these devices operate will vary according to setting and requirements but,
correctly set, the driver receives his visual warning at between 90% and 97.5% SWL and the
site receives audible warning at 102.5% to 110% SWL., therefore, when the bell or hooter is
heard, the crane is overloaded and at risk.
Some types of ASLI incorporate a cut-out which prevents further movement of the load to
danger, after the audible warning has been given.
Any defects must be reported in accordance with the company procedures. For a lift that
may require a long period of time to complete, continuous working may be essential and
therefore relief supervisors, crane operators and key personnel should be available and the
following strictly observed.
• any signalling or communication system should be well practiced. (If radios are used,
they should have been previously checked and back up sets should be available).
• crane must not be operated in winds of a speed greater than those specified.
• loads must be carefully handled to avoid snatching, and slewed and travelled so as to
remain suspended vertically. They must not be pulled or dragged and must not be carried
over any person’s head.
• care should be taken to allow for the increase in radius when the load is first raised. This
can arise from flexing of the jib, stretching of ropes and compression of hydraulics. It is
particularly important that persons do not stand between the load and any fixed object.
• cranes must never be overloaded and drivers must react immediately to the warnings of
the safe load indicator by either lowering the load, or by reducing the radius of operation.
Loads must never be left suspended from the crane hook when the crane is
unattended.
The crane should be put through all motions by the driver and any defects reported
immediately. All brakes and clutches should be checked for correct operation.
Before any repairs. adjustments or inspections are carried out, a proper system of granting
permission to work, including isolation of the machine should be properly implemented.
In addition to normal mechanical maintenance, the following points are worth regular
attention:
• an independent inspection should be carried out to ensure that no slowly developing fault
has become accepted, and that no-unauthorised modifications have been carried out and
that safety devices have not been tampered with by an operator for his own convenience.
• contractors name boards and similar wind resisting items should not be fitted without
reference to the manufacturer’s instructions.
• bolted joints should he inspected for tightness; suspect parts should he replaced to guard
against failure.
• where only part of the working rope is in regular use, the unused length should be run off
the drum at regular intervals to see that it remains undamaged.
• rail tracks, particularly curved sections, should be checked for level, soundness of
construction and maintenance of correct gauge.
• always ensure that the rope is the correct length for the crane as rigged. A minimum of
two full turns must be remaining on any winch, as the rope termination is not designed to
take line pull directly as reverse winding could occur.
• all ropes should be regularly lubricated according to manufacturers’ instructions.
• where ropes are running over plastic sheaves, it is possible that fatigue fractures of
internal wires may be present even though external wear is slight. Additional tests, other
than visual examination of the outer wires, may be necessary on these ropes.
Note: When a crane has been erected in a corrosive atmosphere e.g. sea air, near chemical
works etc., rope anchorages should receive special attention and may need to be cut
off and re-made periodically, to guard against the effects of hidden corrosion.
19.8 HOISTS
Hoists can be categorised as follows:
Goods hoists — used for lifting goods only and must not be used for transporting
passengers.
Passenger hoists — suitable for lifting persons and goods.
19.8.1 erection
• passenger and/or goods hoists should, as a minimum, be provided on any building
project which has four or more storeys and be extended, as the building progresses, to
the topmost floor.
• hoists should only be operated by fully trained and qualified personnel, be thoroughly
examined by a competent person after erection and before being put into service to
ensure that they have been properly erected and are safe to operate.
• the erection, extension and dismantling of hoists is a specialised job and should only be
carried out by competent erectors under the charge of a competent supervisor who will
have planned the work in detail, examined the site and assessed the correct method of
tying-in before work commences. If scaffolders carry out this work they must be suitably
trained and experienced.
19.8.2 base
A good base is essential. The hoist winch and other devices must be correctly positioned
and anchored to the base to ensure stability and to enable the load on the tower to be
carried. The base units of some passenger carrying hoists weigh several tonnes and
adequate lifting facilities should be available for installation purposes.
19.8.3 ties
It is essential that the freestanding height of the hoist mast is never exceeded, and that it is
tied to the building strictly in accordance with manufacturer’s instructions.
It is essential that, when tied to a building or scaffold (which itself must be adequately tied to
the structure), the mast is maintained vertical, so that no undue stress becomes imposed on
the tower; with consequent misalignment and interference with the platform.
19.8.5 platforms
• hoist platforms should be sound and maintained in good condition. Broken or missing
boards can easily cause a load to tip, or a man to fall when loading.
• gaps between the platform or cage and the landing, and between an open platform and
the hoistway, must be sufficiently small to prevent persons falling down the hoistway
when loading or unloading.
• platform must carry a notice stating the safe working load. On a goods hoist a notice
prohibiting passengers must also be displayed.
No’s. Denote:-
1. Over run device
1 2. 2m high landing
4 gate
3. Hoist enclosure
2
4. Hoist mast tied
into building.
5. Hoist arrestor
4
device.
8 6. Hoist operated
2 from one
position only
giving operator
5 unobstructed
4 view.
7. Dead man
handle.
6 3
7 8. S.W.L. marked
2
on hoist
platform.
Fig. 16. - Showing sketch of a cantilever Goods Hoist .
(Wire mesh surround to the hoistway has been ommitted allowing detail
to be shown).
• an over-run device must be fitted just above the highest platform position required, or
near the top of the mast.
• on all types of hoist, the top over-run device must be correctly set in accordance with the
manufacturer’s instructions, to ensure that there is no danger of headgear being struck by
platform or cage.
• bottom over-run devices must also, where fitted, be properly set. In the case of rack and
pinion hoists, there may be a danger of the platform or cage climbing off the top of the
mast, particularly during erection and dismantling.
• hoists must be fitted with an arrestor device to support the platform or cage, fully loaded,
in the event of failure of the hoist rope or driving gear.
All passenger hoists may be used to carry goods up to the rated SWL. The usual procedure
is for the driver to travel with the goods, and his weight, calculated as a fraction of the
permitted number of persons, should be deducted from the payload (e.g. SWL 1 tonne or 12
men; therefore 1 man = 1/12 tonne; therefore payload = 11/1 2 tonne). When passengers
are carried, the driver is included in the permitted number of passengers.
Enclosures must be at least 2m high at the base and at landing stages, and should be of a
mesh size as laid down in BS 4465.
The gates must be fitted with mechanical or electrical locking devices, so that the gates
cannot be opened except when the cage is at the landing stage and so that the hoist cannot
be operated unless that gate is closed and the lock is in the shut position. ( Where this is
not practicable, it is allowable for the gate to be locked from inside the landing platform
provided the hoist operator is the only one issued with the key).
Cage gates must be mechanically and/or electrically interlocked. Access and egress gates
at working platform level must also be interlocked.
No’s Denote:-
1. Over run
1 device
4 2. 2m high
landing gate
9
3. Hoist
2 enclosure
4. Hoist mast tied
into building.
8 4
5. Hoist arrestor
device.
6 9 6. Hoist
operated from
7 9 one position.
7. Dead man
10 handle.
4
5 8. Cage interlock
on Gates.
9 9. Landing gates
interlock.
2 1
10.S.W.L. on
hoist.
3
Fig. 17 Showing sketch of a Passenger Hoist with
all the safety devices fitted.
Hoists may only be operated from one position. This normally is from inside the cage. If, for
any reason, the cage stops between landing stages, it should be isolated electrically from
outside to prevent any possibilily of further movement. There is a mechanical device that
keeps the gates locked in such circumstances.
Passengers should remain in the cage until a competent person instructs them on the
correct method of egress, which may be through a roof trapdoor which is kept locked, except
when properly needed. A notice bearing instruction to this effect, or with any variations
peculiar to that specific model of hoist, should be prominently displayed in the cage
The SWL figure and the permitted number of passengers must be marked on the cage.
Drivers have particular responsibility to see that the hoist does not become overloaded.
The distance from the underside of the cage, when at its lowest position, to the ground, is
carefully calculated by the makers to prevent damage to the cage and its occupants if the
cage over-runs the bottom landing level. It is essential that the ground space beneath the
cage is kept completely clear in case such emergency arises, despite any trip mechanisms
incorporated by the manufacturer.
The operation of mechanical safety gear from inside the cage should be expressly forbidden
except in an emergency. For checking purposes, the safety gear should occasionally be
fired with the manual lever, if fitted, to ensure that it is working properly.
• barriers must be erected and maintained at the loading area to prevent unauthorised
access.
• the load should be in full view of the driver throughout its travel.
19.8.12 maintenance
Systematic maintenance should be carried out at the manufacturer’s recommended intervals
by persons competent for the purpose.
Regular maintenance of both electrical and mechanical systems, should be carried out by
competent electricians and mechanics, to keep hoists in goad working order.
Hoist electrical work should only be carried out by an electrician trained in the control
systems involved. Drivers should not be permitted to attempt electrical maintenance, but
they can help to avoid breakdowns by observing chafing in the supply cables, or unusual
noise or performance.
rack and pinion hoists
The lubrication of the rack is a job normally carried out by the driver during maintenance but,
in order to have safe access, he must have assistance with the operation of the hoist. The
manufacturer’s recommendations should be followed regarding correct lubricant and
method.
swivel hoists
There are additional dangers with the operation of this type of hoist, because the cage must
be swung towards the landing levels for loading/unloading. Either:
• someone may try to open the gate(s) and lean into the hoistway to swing the cage into
position; or
• the cage may swing away from the landing level if it has not been locked into position.
These problems can be overcame by fitting hoist gates split into upper and lower gates and
by checking to make sure that the cage is locked into position at that level, before opening
the lower gate.
A single gate at least 910mm high may be fitted instead of the larger split gate, providing that
no-one can be struck by any moving part of the hoist or falling materials should they lean
into the hoistway.
All ties should be kept clear of the hoist rope and power cables and, as far as possible, out
of the way of all building operations, so that there is no temptation for anyone to remove
them. Proper planning can remove the risk of occurrences such as this, and other forms of
dangerous interference. Such planning must be backed by adequate site discipline and
enforcement of all instructions so that alterations may be made only by authorised
personnel.
Clench and
Unclench
Fingers to
Operation Start Stop Emergency signal winch Lower Slew In Direction
Hoist Lower Slowly Indicated
(Follow my Instructions) Stop the load
Jib Up
Jib
Down
Derricking Jib Extend Retract Jib Travel to Me Travel in Direction Indicated OPERATION CEASE
Travel From (Or cease to follow my instructions)
Signal with one Hand -Other on Head Jib Me
NOTE: Signaller should stand in a secure position where he can see the load and can be clearly seen by
the Crane Driver. If at all possible he should face the driver. Each Signal should be precise.
Name and address of the site to which the method statement relates.
Indication of whether the operation will be undertaken as a “contract lift” or as a “crane hire”.
Name and address of the company arranging for the contract lift/hiring the crane.
Name of the person appointed to have overall control of the lifting operation.
Name of the appointed safety adviser and arrangements for monitoring the work.
Confirmation of training standards for crane driver and slinger/signaller and methods of
communication.
Name and address of the site to which the method statement relates.
Names of the supervisor / foreman and appointed safety adviser and arrangements for
monitoring the work.
Details of the mobile crane to be used (see mobile crane method statement checklist) including
copies of relevant certification.
Height(s) of lift(s).
Arrangements for notification to police and highways authority where necessary e.g. for
temporary road closure.
Note
This checklist is intended to aid the production and approval of method statements. It is not an
exhaustive list of every possible issue that may need to be addressed for any given task.
— Confirmation that members of the erection/dismantling team will wear full safety harness at all
times whilst aloft.
— Confirmation that harnesses will be secured as necessary e.g. when bolting up, sledging,
slinging, etc.
— Details of how the crane testing will be carried out. (in accordance with BS71 21: Part 2 1991)
LIFTING GEAR
INTRODUCTION 1
DEFINITION
MAIN APPLICABLE U.A.E. LEGISLATION
SECTION 20
Municipalities & Agricultural Department
H&S Construction Codes of Practice
PART TWO
SECTION 20
LIFTING GEAR
INTRODUCTION
Lifting must, by its very nature, be regarded as a hazardous operation. The severe usage to which
lifting gear is often subjected, together with the serious consequences to life and property which may
result from any failure, make it important that maximum attention is paid to the correct use and
maintenance of such gear. This can best be achieved by :-
• regular, careful inspection and maintenance during the life of the gear.
It is unfortunate that, whereas considerable importance is generally attached to the selection and
training of crane drivers, comparatively little attention is paid to banks men / slingers who are an
equally important part of any lifting operation. Management should accept that the duty of banks men /
slingers is not one that can be undertaken by untrained persons.
DEFINITION
Any loose equipment used for lifting with a lifting appliance, e.g. rope or chain slings, webbing slings,
hooks, eyes, shackles, eyebolts etc. (does not apply to ropes used for haulage on the level or
lashings).
Fig.1
1 Single Leg Sling - normally used on loads with a single point of attachment with the sling in a vertical plane.
2 Two Legged Sling - Used when two lifting points are required. The angle between the legs of the sling should not exceed 90o
3 Three Legged Sling - This type of sling not to be used when the angle between any leg and a line vertically below centre
master ring exceeds 450
4 Four Legged Sling - Angle between legs on a four legged sling is measured between diagonally opposite legs and
should not exceed 45o
(1) 2
Fig. (2) (3) (4)
1. Two single leg slings used in a Basket Hitch. NOTE: Total load that may be lifted – provided that no
included angle exceeds 900 – is 2.1x that marked on the sling.
2. Choke Hitch Double Wrapped. NOTE: Total load that may be lifted is that marked on the sling.
3. Basket Hitch.
NOTE 1: Total load that may be lifted when the included angle does nor exceed 900 is 1.4 x that marked
on the sling.
NOTE 2: A Basket Hitch should only be used when the sling is passed through part of the load – and
the load is balanced on the sling.
4. Simple Choke Hitch. NOTE: Total load that may be lifted is that marked on the sling.
• hooks, rings, welded or mechanical coupling links and other attachments when used
with alloy steel chains shall have a rated capacity at least equal to that of chain.
• job or shop hooks and links or make shift fasteners, formed from bolts, rods etc. or other
such attachments, shall not be used.
• rated capacity (working load limit) for alloy steel chain slings (single/multileg) shall not
exceed the values given by the manufacturer.
• whenever wear at any point of any chain link exceeds 10 per cent reduction in diameter,
the chain shall not be used,
20.5.2 wire rope slings
• the safe working load recommended by the manufacturer for
various sizes and classifications of wire ropes shall be
followed.
• wire ropes shall not be secured by knots.
Fig. 9
• each wire rope used in hoisting, lowering or in pulling loads
shall consist of one continuous piece without knot or splice.
• spliced fibre rope slings shall not be used unless they have been spliced as per the
manufacturer’s recommendation,
• natural and synthetic fibre rope slings shall be immediately removed from service if any of
the following conditions are present:-
distortion of hardware in the sling. broken or cut fibres.
abnornal wear. variations in the size or roundness of
strands.
powdered fibre between strands.
discolouration or rotting.
Stitching shall be the only method used to attach end fittings to webbing and to form eyes.
The thread shall be in an eyes pattern and contain a sufficient number of stitches to develop
the full breaking strength of the sling.
environmental conditions
When synthetic web slings are used the following precautions shall be taken:
• nylon web slings shall not be used where fumes, vapours, sprays, mists or liquid of
acids or phenolics are present.
• polyester and polypropylene web slings shall not be used where fumes, vapours, sprays,
mists or liquids of caustics are present.
synthetic web slings shall be immediately removed from service if any of the following
conditions are present:-
• acid or caustic burns
• broken or worn stitches
• melting or charring of any part of the sling surfaces
• distortion of fittings.
snags, punctures, ~ tears or cuts
Table 1. above shows the working load limit when using 1 webbing sling - Double ply at varying angles and sling
configuration.
20.5.5 hooks
Every hook used for raising or lowering or as
means of suspension shall either:
• be of such shape as to reduce, as far as
possible. the risk of such displacement.
(see Fig.6) for types of hooks normally
used on building construction work.
or;
• be provided with an efficient device to
prevent the displacement of the sling or Fig. 6 - “C” Type Hook – Fig. 7 -
load from the hook (see Fig 7) sometimes referred Eye Hook with
to as the “Liverpool Safety Catch
“C” Hook
20.5.7 eyebolts
• is of good construction, sound material, adequate strength, suitable quality and free from
patent defects.
• is inspected prior to use on each shift and as necessary during its use to ensure that it is
safe. Defective equipment shall be removed from service.
• it is clearly marked with its safe working load and identification number.
• all unused legs of the sling are hooked back to the eye to prevent the hook swinging
where it may strike personnel or get caught up.
• It is free from makeshift devices. i.e. must not be shortened with knots or bolts.
20.7.2 hooks
• are of sufficient size to permit the load to be taken on the bed and not the tip.
• is placed over the centre of gravity of the load to avoid the load swinging.
20.7.4 slinger
• ensures that the slings do not pass directly over sharp edges such that they may be
damaged.
• always wear a safety helmet, safety boots and gloves, and wear high visibility clothing so
that they are easily identifiable.
20.7.5 load
• is checked to ensure that it is “free” and not trapped in any way and lifted slightly then
checked for stability and angle.
• adequate steps have been taken through the use of suitable packing or otherwise to
prevent the edges of the load from coming into contact with the lifting gear where it is
likely to result in damage.
• hands and fingers not be placed between the sling and its load while the sling is being
tightened around the load.
Note: Only Competent persons approved by Ministry of Labour and Social Affairs to test
lifting appliances are authorised to test and certify all types of lifting gear.
CONFINED SPACES
INTRODUCTION 1
MAIN APPLICABLE U.A.E. LEGISLATION
21.1 PLANNING 2
21.2 SAFE SYSTEMS OF WORK 2
21.3 PERSONNEL SELECTION 2
21.4 TRAINING 3
21.5 TOXIC AND FLAMMABLE ATMOSPHERES 5
21.6 ATMOSPHERE MONITORING 5
21.7 PERMIT TO WORK 7
21.8 WORKING PRECAUTIONS 7
21.9 RESCUE 8
21.10 BREATHING APPARATUS 9
21.11 PERSONNEL 11
21.12 SEWERS 12
21.13 BACTERIAL INFECTION & HYGIENE 12
21.14 DETERIORATING ATMOSPHERE 13
21.15 SUBSTANCES WHICH MAY BE ENCOUNTERED 13
IN A CONFINED SPACE
SECTION 21
Municipalities & Agricultural Department
H&S Construction Codes of Practice
PART TWO
SECTION 21
CONFINED SPACES
INTRODUCTION
For the purpose of safety the term ‘confined spaces” covers a great variety of workplaces which have
limited access and inadequate ventilation. They are therefore potentially dangerous places in which to
work because they may trap hazardous concentrations of toxic or flammable gases or vapours.
Confined spaces are also liable to become deficient in oxygen due to the build-up of a gas or vapour
which is not itself toxic but which displaces the breathable air.
Very often, the dangerous atmosphere is a result of the work being done for instance welding,
painting, flame cutting and the use of adhesives and solvents.
At some time or another almost any place on a construction site may become a confined space. Some
are quite obviously confined spaces e.g. tanks, ducts, bore-holes, silos, manholes, furnaces,
pipelines, sewers and underground chambers. But serious accidents have occurred in the past in
such places as rooms which were ultimately to become occupied rooms and which were therefore not
regarded as confined spaces when construction work was going on in them.
Everyday operations of the construction industry often involve work in excavations, holes and so on
which may not be recognised as confined spaces, but which nevertheless may present a danger of
toxic, flammable or oxygen-deficient atmospheres.
If there is any doubt whether or not a particular workplace presents the problems of a confined space,
atmospheric testing must be carried out to determine what are the hazards, if any.
• whether it is practicable to substitute safer materials than those which are producing the dangerous
atmosphere
• whether alternative methods of work could be adopted which would not give rise to hazards.
21.1 PLANNING
The special conditions of confined space working make it vital that the work should be
planned in detail and risk assessments made in order to determine appropriate health and
safety measures and emergency arrangements. (see Pt 2 section 19)- Risk Assessments -
Part One Manual
These measures should be incorporated in a safe system of work and included in the health
and safety plan which the principal contractor will have developed.
The following measures are priorities: Fig.1 - Photo showing entry into a sewer
manhole using winch, tripod, safety
• test atmosphere prior to entry. harness etc. and following the
correct safe system of work
• continuous monitoring at the workplace.
• maintain contact between operative and attendant in free air who is trained to carry out
emergency procedures.
Heavy manual tasks, with the necessity for rescue training and the possible added burden of
working in breathing apparatus may make the job too demanding for older men. Men of 55
and over who are already employed on work in confined spaces should be medically
examined annually and additionally after any illness.
no one with any of the following disabilities should work in confined spaces:
21.4 TRAINING
Work in confined spaces must only be undertaken by employees who have been properly
trained for the job.
It is the employer’s duty to provide such information, instruction, training and supervision as
is necessary to ensure, so far as is reasonably practicable, the health and safety at work of
his employees.
• persons who will be expected to enter • persons appointed to form a rescue team.
confined spaces to work in them
The precise form of the training and instruction must depend on the individual operations,
but in addition to any specialised training for particular tasks, general training for work in
confined spaces should include:
• restrictions on size imposed by existing manholes or access shafts should be taken into
account when developing safe systems of work.
• training in the procedures for rescue, including the correct use and maintenance of
rescue equipment and resuscitation equipment.
instruction :-
Note: Instruction in the use and maintenance of equipment can often be given by the
Manufacturer.
They must also learn the correct procedure for summoning medical aid or the emergency
services and the use and maintenance of any recovery winches and/or other methods of
recovery.
It is important that employees should learn to recognise situations requiring the use of
respiratory protective equipment and be able identify the appropriate atmosphere testing
equipment.
Refresher courses should be given as necessary on a regular basis. It is important that a full
and up to date record should be kept of the type of training given to each individual. (see
Fig.2)
• earlier process (e.g. degreasing, in which case a residue of trichlorethylene solvent in the
tank could emit fumes when the sludge is cleaned off).
• previous contents where confined spaces such as tanks have previously contained
flammable, explosive or toxic materials and where the work being done could create
vapour from the remains of the previous contents.
An atmosphere which is not fit to breathe may exist at the bottom of a hole from stagnant
water or from the subsoil itself e.g. the passage of water through chalk for instance, can
release carbon dioxide.
Oxygen in more than its normal proportions in the air also greatly increases the
combustibility of all other materials. A fire in an oxygen-enriched atmosphere develops with
great speed and ferocity and may be particularly difficult to extinguish.
The atmosphere can accidentally become too rich in oxygen as a result of work which
releases extra oxygen into the air, for instance oxy-propane cutting.
Note: It is dangerous to purge with oxygen instead of air, and in no circumstances should
oxygen be introduced into a confined space to “sweeten” the air or to provide
ventilation. A leak of liquid oxygen or oxygen gas must be treated as a serious matter.
All electrical tools and lighting must be of the flameproof or intrinsically safe type. The
British/American Approvals Service for Electrical Equipment in Flammable Atmospheres
defines ‘intrinsically safe’’ as ‘‘Systems comprising apparatus and interconnecting wiring in
which any spark or thermal effect in any part of the system for use in the hazardous area, is
incapable, under prescribed conditions, of causing ignition of a given gas or vapour.
(BASEEFA Certification Standard SEA 3012). Intrinsically safe is also defined in BS 1259.
21.9 RESCUE
The procedure for rescue in an emergency should be set out clearly in the permit-to-work,
with specific jobs allocated to specific persons.
Training should ensure that if a rescue becomes necessary, all persons concerned are
thoroughly familiar with the routine procedures through frequent practice drills.
The communication system must not rely on any method (for instance, blowing whistles)
which becomes impossible when breathing apparatus is being worn. Signals by means of
rope can also be unreliable since if the rope snags communication is lost.
At the same time, a danger alert must not rely on a signal given by the worker inside the
confined space, since if he is overcome suddenly he will be in no condition to give the alarm
and he may be working alone.
If space allows, a minimum of two men should enter a confined space when working out of
sight of the external observer. Communication must be of a fail-safe type. That is to say, if
the worker inside the confined space does NOT take the right action, the alarm is given. For
instance, if a periodic pre-arranged signal is NOT received at the end of the normal interval,
it could result in serious injury, or even death.
The essentials for rescuing someone from a confined space are that:
• the outside observer must have means of knowing immediately that a man is gassed or
has met with an accident.
• the rescue team, alerted by the observer, must get the casualty out into free air speedily.
• the casualty must be given first aid quickly, either at the work location or immediately he
is brought out into free air and the appropriate medical attention as soon thereafter as
possible.
rescue equipment
Rescue equipment should include breathing apparatus, resuscitation apparatus and oxygen.
It should also include:
Where, however, the casualty has collapsed and the cause is not known, then rescuers
must wear breathing apparatus.
This applies even if, when the person entered the confined space, it was certified as safe to
enter. The reason for the collapse could be an overall deterioration in the atmosphere since
entry was made, or a deterioration in the particular area where the casualty has been
overcome.
Apart from the paramount necessity of rescuing a worker who has been overcome, if gas is
suspected the emergency procedure must provide for the immediate evacuation of any other
person who may be within the confined space. A system of "audible" evacuate alarms
operated by the observer outside should always be installed if persons have to work out of
the sight of the observer at some distance from the openings.
If fire has broken out, or flammable gas is suspected, a pre-arranged procedure must
provide for the immediate summoning of the Civil Defense.
Emergency plans should be discussed with the local emergency services including fire,
police and ambulance so that the best use can be made of their expertise and facilities. If it
is practicable, there is great advantage in having an emergency practice with all the services
participating.
Where access to a confined space is too small for a man to enter wearing self-contained
breathing apparatus with cylinders. or where it is not possible to site a compressor unit
nearby, a mobile breathing apparatus unit (hose reel and trolley set) is useful.
All breathing apparatus must be thoroughly examined at least once every month by a
competent person authorised by certificate to carry out such examinations, and inspected,
tested and certified at intervals not exceeding six months.
21.11 PERSONNEL
People who will or may have to use breathing apparatus must be fit and not suffering from
any chronic or acute respiratory ailment. And they must he properly trained in the use of the
equipment.
instruction on :-
• the equipment, its mode of operation • how to deal with malfunctions and
and its limitations. failures of equipment during use.
• the care and cleaning of apparatus. • the use of breathing apparatus in
• how to don the equipment, adjust the emergency situations.
face-piece and supply valves where • the functions and limitations of escape
necessary, and to test for leaks around breathing apparatus.
the face-piece (beards and facial hair • the hazards which necessitate the use
may prevent an air tight seal). of breathing apparatus.
21.12 SEWERS
Additional to the precautions for confined spaces,
work in sewers necessitates safeguards against:
drowning and/or being swept away, 200mm of
water in a fast flowing sewer is difficult to stand
against and 600mm of water is a danger.
Conditions in a sewer can change very quickly,
and workers should be able to recognise
indications of danger such as: (see Fig.9)
• Chains or bars should be fixed downstream of the working place before work starts.
• Wherever necessary for safety, running lines should be fixed for men to clip on to them.
A kind of infective jaundice, Weil’s disease or Leptospirosis is usually a mild illness if treated
in the early stages, but it can be a serious illness if it remains unrecognised and therefore
the patient is not given the appropriate treatment. It starts with flu-like symptoms, and to
safeguard against a wrong diagnosis, men who will be working in sewers should be provided
with a card to present to their doctor which informs him of the mans occupation.
The disease is not conveyed from person to person, so that a man’s family is not at risk, and
an attack confers a certain amount of immunity.
It is strongly recommended that anyone whose job brings him into possible contact with
sewage, should be inoculated against tetanus, poliomyelitis and hepatitis "A & B" and to
have the immunity maintained the whole time he is at work. Other precautions against all
these infections consist of good personal hygiene.
All workers should wear appropriate protective clothing (which is thoroughly cleaned after
each work period) and avoid exposing the skin, as infection can enter through abrasions.
Lanolin - based barrier cream should be used before work, and after work the hands, face
and forearms washed with hot water and soap. The nails should be scrubbed, but not the
skin, as this can roughen the skin surface and increase the risk of infection, and even the
smallest scratch should be washed and covered with antiseptic dressing, and every
accident, however trivial, reported to the person in charge of the work.
Eating, drinking and smoking must not be allowed until the personal hygiene rules have
been observed. Routine hygiene is easier to observe if mobile vans contain toilets, proper
hot water washing facilities and first aid on the site.
The characteristic smell of rotten eggs indicates low concentrations of H2S, but at
concentrations high enough to be dangerous the gas paralyses the sense of smell, so the
absence of detectable smell is no guarantee of safety. H2S is an acute irritant to the eyes
and the respiratory passages massive inhalations can produce death by asphyxia.
Symptoms of exposure can be eye irritation, sickness, dizziness, choking and lack of
muscular control.
Note: Any time that workers experience symptoms such as eye irritation or any feeling of
illness, it should be taken to indicate a potentially dangerous situation and
precautionary measures instituted immediately.
INTRODUCTION 1
MAIN APPLICABLE U.A.E. LEGISLATION
22.1 PLANNING 2
22.2 PERSONS AT RISK 3
22.3 RISKS AND HAZARDS 4
22.4 SAFETY PRECAUTIONS 6
22.5 TRAFFIC DIVERSIONS 10
22.6 TABLE 1 - positioning of signs and cones 15
22.7 FIGURE 1 - traffic diversion diagram 16
22.8 BRIDGE CONSTRUCTION 16
SECTION 22
Municipalities & Agricultural Department
H&S Construction Codes of Practice
PART TWO
SECTION 22
INTRODUCTION
This section is intended to cover safety aspects on all roadworks, as applied to both new highway
construction works and the reconstruction or resurfacing of existing highways
The term "Roadworks" includes the use of road surfacing materials containing cement, such as concrete and
mortars, and those containing bitumen, pitch or tar, such as hot rolled asphalt, cold asphalt, bituminous-
macadam and tar macadam, etc., and also the use of bitumens and tars in cold or hot liquid and spray
form. Various ancillary works and materials are also covered, including the use of waterbound macadam
and epoxy resins, the burning off and planning of existing bituminous road surfaces, the use of fuels such
as diesel oil, petrol and liquefied petroleum gas, as well as the many other maintenance activities such as
patching, surface dressing, drainage works and trench reinstatements, etc., carried out on our highways
every day.
The term "Bituminous Material" used in this section refers to any material containing bitumen, tar or pitch
as a binder and can also be considered to apply to bitumen or tar used in liquid form.
22.1 PLANNING
Road works can be a hazardous operation, both to contractors and to users of the public
highway. It is therefore essential to assess the various risks and to establish systems of
work which are both safe to contractors and the public.
22.1.1 generally
• it is essential to ensure road works wherever applicable are included in the pre tender
health and safety plan.
• associated safe systems of work and site rules should be included in the construction
health and safety plan which the main contractor must ensure is sufficiently developed
before the work is carried out.
• consider that pedestrian access and properties requiring vehicular access should at all
times be maintained.
• where work is planned which involves breaking up or opening any street or any
sewer drain or tunnel under it, this should be specified on the Notice of Intent and
approval must be given by all relevant authorities before commencing works.
• visitors must be given sufficient instruction on relevant hazards before entering the
works area and be accompanied at all times by a trained person.
• thorough planning is essential to ensure that adequate space and sufficient time is
available to enable the work to be carried out safely and efficiently.
• where possible, well signed lead-in and lead-out coned off lanes should be provided
for site transport.
• where possible, a clear traffic lane should be provided between the limits of the
"working space" and the live traffic, for use by the emergency services.
• where a clear lane cannot be provided, the site access lane will need to be used by
emergency services and, in the event of an accident blocking the running lanes, the
police may require the site access lane to be used by general traffic.
• where a site access lane cannot be provided, it will be necessary for an access
through the works area to be available for use in an emergency.
• works personnel may need to get from one side of a traffic lane to the other.
• traffic lanes must never be crossed on foot and safe procedures must be introduced, such
as the provision of temporary bridges, or an approved route for authorised vehicles.
• the overheating of bitumen or tar, the misuse of fuels or the use of fuels in defective plant, can
create a serious fire risk. Heaters or burners used for heating existing road surfaces can,
if not properly operated and controlled, damage or set fire to adjacent property.
• skin contact with LPG can give cold burns, and cement, when wet, in the form of
concrete or mortar can cause serious burns.
• a further possible hazard from prolonged and constant contact with these same materials is
the contraction of dermatitis.
• the traffic accident type where a pedestrian operative is run over by plant or a vehicle.
Provision of a banksman should help to combat this type of hazard.
• the machinery/operative type of accident where injury is caused by the operation of the
plant or vehicle or the machinery in the plant or vehicle. For example, where an operative is
injured by unguarded machinery in a paving machine.
• a further danger can be caused by the inadvertent entry into the eye of other foreign
matter such as bitumen, oil, cement or other dusts.
• the use of epoxy resins adds a further hazard. If the curing agent gets into the eye,
permanent damage is likely.
22.3.6 falls
• operatives falling over any object or falling into excavations etc. account for many
accidents on roadworks sites. Falls from moving vehicles or plant are a further hazard.
• the reduction of noise at source and the provision and use of hearing protection can
remove this hazard. However, it must be appreciated that, if hearing protection is worn
when working close to fast moving traffic, the risk of a traffic accident is increased.
• the location and identification of all underground and overhead mains and cables
must be established before works on site commence. (see Pt 2 Section 6)
• the use of correct lifting techniques and assuming correct postures will assist in
eliminating this most common of all hazards. (see Pt 2 section 8).
• fumes and smoke from hot bituminous materials are always present when these
materials are being used and they can cause discomfort and nausea to some operatives.
Careful assessment and monitoring of any dust, fume or smoke conditions is essential.
• personal hygiene is an absolutely essential step in combating the risk of dermatitis and
cancer.
• clean overalls are of little use if worn over clothing which is itself impregnated with
cement, oil or tar etc. Therefore, operatives' clothing should be kept reasonably clean
and free from cement, bituminous materials and dirt (see below)
safety helmets
• conspicuously coloured to make the wearer more visible to vehicle and plant operators.
All site personnel must wear a safety helmet at all times.
• essential to ensure that operatives are easily visible to all vehicle and plant drivers and
to passing traffic. Must be worn on dual carriageways with a speed limit of 80km/h or
above.
general covering/clothing
• cover exposed parts of the body in order to prevent contamination of the skin with
bituminous materials or concrete or cement.
• therefore, it is essential that all overalls, gloves etc. are regularly cleaned to remove
any contamination. Dry cleaning is probably the only effective method. In bad cases
of saturation with bituminous material or cement, the only remedy is disposal and
replacement.
gloves
• able to protect the wearer against heat, oil, tars, bitumens and concrete etc.
eye protection
• noise from various sources can often be reduced by the provision of baffles or screens.
Noise from internal combustion engines can be reduced by the provision of silencers
or replacement of defective ones.
• normally with roadworks the site is of an open nature and problems of fumes, smoke
and dusts are the exception rather than the rule.
• the problem may arise especially in confined sites such as a narrow road between tall
buildings or in tunnels or underpasses.
• dusts can generally be controlled by damping down but it may be necessary to provide
forced ventilation, e.g. air movers, and masks or breathing apparatus of a suitable type
for operatives.
• Particular attention must be paid to electricity cables, both underground and overhead
and also to gas mains. In addition, it is advisable to verify the location of any given main
before commencing other excavation works in the locality.
• it is essential that all users obtain such information and are familiar with and follow the
recommendations. A copy should always be kept with the particular machine.
• plant manufacturers must provide all necessary guards and safety devices for their
plant and if not, the plant must not be operated until a suitable protective guard has
been fitted.
• it is strongly recommended that all mobile plant and vehicles be painted a conspicuous
colour (e.g. bright golden yellow) and be equipped with rotating amber flashing
beacons.
• the operators of all plant and machinery must be properly trained and competent in the
use of the particular machine which they operate.
• it is the duty of all plant owners and operators to ensure that all safety devices such
as guards, brakes, hand-rails, warning lights and flashers etc. are always operating
satisfactorily or are reported immediately they become defective. The continued
use of plant or machines with defective safety devices must be prohibited.
• the misuse, overloading or the unauthorised riding on any plant or vehicle is forbidden
22.4.6 fuels
• the fuels generally used on roadworks sites are diesel oil or gas oil, liquefied petroleum
gas and, more rarely, petrol.
• guard rails should be at least 910mm above ground level and there should be toe boards
or another rail, approximately 150mm above the ground.
The following are examples of temporary barriers used to both protect the public and warn
vehicles.
• all vehicles and plant drivers and other occupants should vacate their vehicle by
the kerb side.
• all vehicles and plant should be equipped with two high intensity rear fog lamps that
are automatically switched on when reversing, plus an automatic audible reversing
alarm to warn operatives of the danger from a reversing vehicle. In addition, it is
highly desirable to have all reversing manoeuvres directed by a banksman located
towards the rear of the vehicle but within sight of the driver.
working at night
working at weekends
• works carried out at night should always be floodlit, taking care not to dazzle or
blind oncoming traffic.
• when works are being carried out on a highway open to traffic, two-way working
of traffic flows should be maintained whenever possible. The minimum widths
recommended are 2.75m for one-way working and 5.5m for two-way working.
• steps should be taken to maintain both site safety and security outside working
hours in order to reduce the risk of accidents to the public, particularly to
inquisitive children. All vehicles and plant should be immobilised when not in use.
• it is essential and mandatory for the protection of operatives and the general public that
adequate signs are displayed giving highway users advance warning of road works.
• the sizes and positioning of signs and cones are dependant on the type of the road and
the relevant speed limits. For example, high speed roads require more and larger signs
displayed further in advance of the works, than minor or slower speed roads.
• if it is necessary to hold down signs, cones etc. because of wind problems, only
sandbags should be used. Hard heavy objects should not be used as, if hit by a moving
vehicle, they could become lethal missiles to the danger of persons or other vehicles
nearby.
• warning signs should be set so that their lower edge is at least 300mm clear of the
ground. This prevents any wording at the bottom of the sign from becoming too
dirty, or obscured.
• signs must be clearly visible to approaching drivers by both day and night, and in all
weather conditions.
• if there is not adequate lighting available to sufficiently illuminate the sign at night, then
reflective signs must be used.
• there must be sufficient working space to ensure that the movement and operation of
plant (e.g. swinging of jibs and excavator arms) is clear of passing traffic and is not
encroaching into the safety zone, or adjacent footway.
• a safety zone, delineated by cones and lamps should be provided to protect operatives
from the traffic and to protect traffic from the road works.
• plant must not be allowed to encroach on to the safety zone, nor must operatives be
allowed to enter it other than to maintain the cones or safety signs.
a lead-in taper of cones (T), which will vary with the speed limit and width of the
works. (see Table 1)
a sideways clearance between the working space and moving traffic, which
must be at least 0.5 metres on roads with speeds up to 80 km/h and at least 1.2
metres on roads with speeds of 80 km/h and over.
a traffic barrier, facing oncoming traffic, positioned within the coned-off area
to show the width of the works site. (This barrier may not be necessary if a
conspicuous vehicle is present).
N.B For roads with a speed limit of 80 km/h or more, an additional traffic barrier is required at
the end of the lead-in taper.
• the width of such buffer zones is preferably a full lane width of 3.65 metres, but should
be at least 1 metre. A full lane width has the added advantage of providing a separate
unused lane for access and emergency vehicles if breakdown or accident occurs.
• barriers should be used to delineate buffer zones. The ideal types in this case are
traffic cones, cats eye bollards or simple red and white coloured plastic pendant
markers, all of which are relatively harmless if hit by a vehicle.
traffic barriers
• traffic barriers should be constructed and should be continuous concrete traffic barriers,
used to indicate the road works and segregate the traffic from the works.
• their design should not cause a further hazard, if hit by a moving vehicle and they
should be of a conspicuous colour (e.g red or yellow stripes) and kept clean.
22.5.6 signage
advance signs
• Road Works Ahead’ signs shall be placed in advance of the road works and shall be the
first signs to be seen by the driver, as indicated in Table 1 (D).
ahead signs
• ‘Road Narrows Ahead’ signs shall be placed midway between the ‘Road Works Ahead'
signs and the beginning of the taper of traffic cones.
• ‘Keep Right’ or ‘Keep Left’ signs shall be placed at the beginning and end of the lead in
taper of cones.
• On roads with speed limits of 80km/h or more, all “ahead” signs should have the distance
to the works in meters printed on them as shown in Figure 1.
22.5.7 cones
• A line of traffic cones shall be positioned at a taper and should guide traffic past the
works, at a distance ahead of the works as indicated in Table 1 & Figure 1 (T).
• The maximum spacing distance of cones in longitudinal lengths of coning shall be no
more than 9 meters, but no less than 2 cones shall be used in any length between
tapers.
• Generally lead in tapers used with traffic control, and all exit tapers, shall be about 45° to
the kerb line with cones spaced 1.2 m apart and more specifically as below:
1 in 20 4 metres
1 in 30 6 metres
22.5.8 lamps
• road danger lamps must be provided for use at night, in poor daytime visibility and in bad
weather
• road danger lamps must not be higher than 1.2 metres above the road
steady lamps
22.5.9 pedestrians
• works on footways must leave at least 1.5m unobstructed width for temporary pedestrian
ways and should never be less than 1 m wide. Where this is not obtainable, an
alternative safe route for pedestrians must be provided.
• rigid barriers must be used to mark any temporary footway and to protect
pedestrians from traffic, excavations, plant and materials. Road danger lamps must
be placed at the ends of the barriers at night. Hand rails should be between 1.0
and 1.2m above ground level.
• if the temporary footway is in the carriageway, signing will be necessary for both
pedestrians and drivers. The provision of kerb ramps or raised footways may also be
necessary to help blind, elderly or disabled persons, or for those with prams or
wheelchairs.
(Note 1) (Note 2)
1 2 3 4 5 6 7
All-purpose dual Length of taper (T) in metres 25 50 75 100 125 150 175
110
carriageway to 60 750 450 Min. No. of cones 4 7 10 13 15 18 21
road, restricted to 275
40km/h or less Min. No. of lamps at night 3 6 9 12 14 17 20
All-purpose dual Length of taper (T) in metres 32 64 96 128 160 192 224
725
carriageway 105 1200 750
to Min. No. of cones 5 9 12 16 19 23 26
road, with speed limit 1600
80km/h or more Min. No. of lamps at night 4 8 11 15 18 22 25
Note 1: Minimum and normal maximum distance of the first sign (D) is given to allow a
range wherein the sign can be placed in a convenient position, bearing in mind
available space and visibility for drivers.
Note 2 : It may be appropriate to use the next larger size of cone in lead-in tapers (i.e.
750mm cones) in tapers where 450mm cones are indicated and 1 meter high
cones where 750mm cones are shown.
• this section raises relevant detailing issues and, in particular, those related to access
during bridge construction, operation and maintenance.
carried out in high-risk areas, such as adjacent to high-speed traffic, the requirement
for such activity should be minimised.
• when working close to high-speed traffic, all relevant safety standards Roadworks as
explained in this chapter should be adhered to and in particular there should be a
safety zone for protection of the workforce in addition to the necessary working space.
• for motorways, this safety zone is a minimum of 12 m wide, so for bridge structures
with narrow verges the nearside lane will need to be closed when maintenance activity
takes place within the verge.
• other published guidance on health and safety issues in Bridge Construction should
be consulted as necessary. Further information can be obtained from:
CIRIA Report 166, CDM Regulations - work sector guidance for designers which
has sections on bridge construction and bridge maintenance.
• badly detailed and congested reinforcement can also create construction difficulties.
• where ground conditions are unsuitable to support necessary falsework, consideration
should be given to supporting the falsework off the permanent works foundations.
• permanent formwork offers the advantage of protecting the areas beneath the bridge
deck against falling items, and avoids the need to send operatives below the deck to
remove temporary works.
22.8.3 access
general
• access into box girders should be arranged from the abutments or, where the boxes
are discontinuous, through the soffit. Care must be taken to provide safe access to
locations in the soffit. Size of openings, ease of entry and rescue requirements
including anchor points also need to be considered. Heavy skews may create
particular difficulties, and special measures are needed for arch, cable-stayed and
suspension bridges.
internal access
• the size of openings at entry and between the cells of a structure should be decided
as part of the designer's consideration of hazards and risks.
• any minimum required by any applicable authority should be taken into account. It is
recommended that absolute minima of 460 mm x 410 mm or, if circular, 460 mm
diameter, should be provided unless there are other adequate means of egress.
• access size should allow necessary equipment (eg ventilation or stressing equipment
and/or a loaded stretcher) to be handled safely.
• the spacing of the access points influences this assessment. Platforms should be
provided at access and egress points along with appropriate lifting points.
• designers should avoid details that present hazards or create access problems. Box
girder structures present particular difficulties, as internal inspection is required. The
interior of a box girder must be recognised as a confined space. Associated
requirements include:
trained personnel
risk assessments
emergency procedures
controlled entry
air monitoring.
frequency of inspections
methods of internal protection
frequency of subsequent maintenance.
22.8.4 lighting and walkways
• The frequency of inspections and maintenance visits makes installation of permanent
lighting essential in large box girder bridges.
• they improve both safety and efficiency, thereby justifying the investment. The
infrequency of visits to the interiors of small bridges makes a permanent lighting
installation unnecessary, although the provision of intrinsically safe power-points
protected from misuse is appropriate.
• as part of their risk assessment, designers should minimise the hazards of slipping
on wet surfaces and of infection from the build-up of fungi in box girders by making
allowance for water to be dispersed.
• water ingress into smaller hollow sections should be considered even when no entry
is envisaged. Problems from deadweight effects have been known to occur.
22.8.6 security
• improved access to all parts of bridges makes security more difficult. The security
risks at each location of a new bridge should be assessed and appropriate measures
taken.
• secure doors/gates to the access routes may be necessary in some locations and
surveillance systems may need to be installed for full security.
• public access to girders over roads and railways etc should be prevented. For
example, permanent access ladders should stop out of reach from the ground, or
locked fold-down ladders should be provided.
for operatives
Have you planned how you will sign and guard the works?
When traffic control changes are made at night or weekends, have the warning signs been
changed?
Are traffic control arrangements reviewed and changed to reduce delays as works change?
Are the works adequately signed, guarded and lit for the overnight period?
Have you cleared away any spoil, etc. which may have spread onto the surrounding road or
footway?
EXCAVATIONS
INTRODUCTION 1
MAIN APPLICABLE U.A.E. LEGISLATION
23.1 HAZARDS 2
23.2 GROUND CONDITIONS 3
23.3 CHOICE OF SUPPORT METHODS 5
23.4 SUPPORT SYSTEMS 6
23.5 MAIN SAFETY REQUIREMENTS 10
23.6 MAINTENANCE 13
23.7 INSPECTION AND EXAMINATION 14
23.8 COFFERDAMS & CAISSONS 14
23.9 COFFERDAMS & CAISSONS - SAFETY PRECAUTIONS 17
SECTION 23
Municipalities & Agricultural Department
H&S Construction Codes of Practice
PART TWO
SECTION 23
EXCAVATIONS
INTRODUCTION
Almost all construction work involves some form of excavation for foundations, drains, sewers, etc.
These can be very deep and very dangerous. Every year, many people are killed, some actually
buried alive, in collapsed tunnels and trenches; many others are injured and there are several
reportable accidents during excavation and tunnelling operations. A relatively small collapse might
involve a cubic meter of soil, but a cubic meter of soil weighs over a ton. A man at the bottom of a
trench buried under this volume of material would be unable to breathe due to the pressure on his
chest and would quickly suffocate and die.
Deep excavations look dangerous - so precautions are usually taken. But most deaths occur in
excavations less than 2.5 meters deep. In fact, most accidents occur in ground conditions with no
visible defects; the trench sides seem clean and self-supporting. Despite appearances however, the
removal of material causes pressure relief - and introduces the conditions which lead to failure.
Rainwater or hot dry weather increase the chances of such failure.
Neither the shallowness of an excavation or the appearance of the ground should be automatically
taken as indications of safety. The evidence suggests that far too often they are.
It is impossible to forecast the behaviour of earth as its condition can change in a very short period of
time, and for this reason several factors, e.g. nature of soil, weather condition, size & method of
excavation and proximity of other structure, etc. need to be considered in the design and planning of
excavation work.
Considering all the above factors, Contractors should adopt the most appropriate method of
stabilising the sides of an excavation, example, battering, poling, sheeting, etc. for the safety of their
personnel.
23.1 HAZARDS
Excavation can result in serious injury, fatality or property damage due to the following
causes:
• collapse of earthwork due to lack • persons not being provided with, or not using
of, inadequate, or weak shoring. proper tools for the job.
• persons falling into excavations • vehicles or plant too close to the edge, causing
due to lack of barriers or the edge to collapse.
inadequate fencing.
• workers in the excavation being struck by soil
• asphyxiation from exhaust gases or materials falling into the excavation.
that have collected in the bottom of
the excavation. • falls through unsafe means of access into, or
out of the excavation.
• soil from excavations not being
thrown clear of the sides that then • workers being struck by excavating machinery,
become overloaded and collapse. e.g. excavator bucket.
• failure to maintain shoring, • vehicles being driven into the excavation due
particularly after rain and sand to driving errors, inadequate barriers, or the
storm. absence of stop blocks.
• water seepage.
Note: No soil whatever its structure, can be relied upon to support its own weight, and if a
trench or excavation cannot be made safe by slopping or battering the sides, some
form of support will be required.
When examining bore holes or trial pit information, particular importance should be paid to
the location of any water table. If the water table is going to be exposed by the excavation,
careful consideration will need to be given as to how it may affect the stability of the
excavation sides. Ground water can greatly affect the stability of any soil and, in particular,
non-cohesive materials. Water can also enter an excavation as surface run-off.
If the ground is suitable, one of several ground dewatering techniques may be used. Such
methods involve either shallow well pumping or well-pointing. In either case, the pumping out
of water has the effect of lowering the ground water table to a level below that to which the
excavation is to be taken. (see Fig.1)
Where a water bearing strata overlays an impervious one and the depth of this impervious
strata is not too great, the use of sheet piling may be more effective and economical. The
piling, being substantially watertight, cuts off the water from the excavated area, thus
enabling the excavation to proceed in the dry. (see Fig.2)
1
excavation
2 2
2
Fig. 2
3
Well point New de-Watering
Original water 1. Permable strata. 2. Water. 3 Impermeable strata
Table
table
Fig.1 - Shallow well pointing Fig.2 - Use of sheet piles to “cut off” excavation from
water-logged ground.
.
Table 1
Safe temporary slopes
Ground Conditions
(degrees from the horizontal)
Dry Site Wet Site
BOULDERS
35/45 30/40
COBBLES
35/40 30/35
GRAVEL
30/40 10/30
SAND
30/35 10/30
SILT
20/40 5/20
SOFT CLAY
20/30 10/20
FIRM CLAY
30/40 20/25
In some soils the vertical excavation sides may stand unsupported for a short period. With
experienced and competent operatives this time may be used to erect the support system.
Excavation is dug to level over a short length and the support system installed without delay,
preferably from outside the trench. If the operatives need to enter the excavation during the
erection of the full support system, a protective cage or other interim support must be used.
The interim support must be quick and easy to erect to minimise risk
• skeletal system of struts and walings giving immediate protection and forming part of the
final system of support.
The interim support is only intended to allow safe access for installation of the full support
system which should follow without delay. All other activities e.g. boning in, bottoming up etc.
should be done after the full support system is installed.
The exposed face of the excavation does not necessarily reflect the total ground condition.
An adjacent service trench or old well may contain weak saturated fill which could initiate a
failure. Where there are buried services adjacent to, or crossing the excavation, sides should
not usually be left unsupported, even for a short period.
In unstable ground the sheeting can be pre driven and the waling frames installed as
excavation progresses, or the sheeting can be driven progressively as excavation continues.
Both trench sheeting and proprietary boxes and slide rail systems can be adapted to this
method.
Beware that the excavated face at the end of the excavation does not collapse
inwards particularly under the action of the trenching machine straddling the trench.
The ‘free-standing’ time may be only a few minutes, if so. it is essential to install support as
the excavation progresses.
For larger excavations, a survey of the soil prior to excavation by a trained and experienced
person will usually provide sufficient information for suitable methods of excavation and
support to be determined, and decided by a specialist engineer.
battered sides
This is definitely the safest method as accidents from the collapse of properly designed and
executed battered systems are rare. (see Fig. 4)
Almost all soils can be excavated to a safe batter, provided that sufficient space is available
and a safe angle of repose known and adhered to. (See Table 1 on page 4)
Slope Beware:
Surface water can affect stability of
slopes and benches, endangering
the trench.
Intercept surface water to prevent it
entering trench. For some soils it
will be necessary to protect slopes
and horizontal surfaces adjacent to
trench.
trench. Where more than one box is required due to the depth, the boxesshould either
remain connected if lowered into a pre-dug trench or be connected/disconnected at
ground level by progressive excavation/backfilling. Install sufficient boxes so that the
full depth of the excavation is supported before people enter the excavation. If the
excavation is overdug, backfill needs to be placed between the excavation side and
the box to prevent both the risk of people falling into the gap and of rotation of the box
following ground movement. If required, trench sheets should be positioned at the
open ends to prevent material falling inwards. Some configurations of box may be
unstable when standing upright on the surface and should be either laid flat or 'dug in.
Only one face of the excavation is involved. Earth pressure from the excavated face is
resisted by transferring the load through the support material via wailings to either raking
shores or ground anchors. In the raking shore approach, an adequate foundation is needed
to transfer the loads involved to the excavated ground. (see Figs. 11 & 12)
• in ground conditions which are sufficiently stable to provide the necessary resistance to
balance the overturning forces, or
• where the effect of superimposed loads and their stability is not critical.
All cantilevers will deflect to a degree. Such deflection will create risk to adjoining installations
and structures, roads etc. and their use in these circumstances should be avoided.
(see Figs. 13 & 14)
Earth
Resisting
Overturning pressure
Earth pressure movement
movement
Anchor
block
Penetration to provide
end fixing
Fig.13 - Free cantilever support
Fig.14 - Propped cantilever
support
• ladders must be securely fixed and properly maintained, and should permit quick and
easy escape in case of flooding or falls of materials.
Note: Using the walings and struts for access and egress purposes must be prohibited.
• ladders should be positioned within the excavation at a height:base ratio not flatter than
4:1 and secured by tying at the upper end to prevent slipping. The upper end of the
ladder should project at least 1 m above ground level to ensure sufficient hand hold.
Ladders should be positioned where they will not be damaged by plant or from materials-
handling operations.
• barriers should
Poling boards
also serve to keep extended to act as
materials, plant toe-boards
and equipment
Exposed services supported
away from the
edges of an
excavation.
• where excavation work is carried out on the roads, Traffic Police approval are necessary
and appropriate barricades and warning notices shall be erected.
23.5.5 ventilation
• excavations must be kept clear of suffocating, toxic or explosive gases.
• there may be natural gases like hydrogen sulphide, methane and methane and sulphur
dioxide, or exhaust gases from nearby plant, or leaks from nearby pipes or installations.
• these can seep through the soil and can accumulate at the bottom of an excavation,
below ground level.
• leakage of propane and butane from LPG cylinders is potentially very dangerous; the
gases will sink to the lowest point and form an explosive concentration.
• the most common method of ventilation is to blow clean air into the excavation in
sufficient volume to dissipate any gas accumulation.
23.6 MAINTENANCE
All excavation work requires careful watching, especially when they are first opened and
sides are unsupported , even when support work has been installed, constant vigilance is
essential.
Small movements of earth, resulting in movements in the timbering of no more than 6-12
mm are usually the only sign of the progressive weakening in cohesive soils which can
cause collapse. Such small movements can easily pass unnoticed but they are signs that
something is wrong.
Movements can be detected from slight distortion in timbering, bowing of poling boards and
walings, or signs of local crushing.
• raking or angle, struts should all be regularly examined for signs of having been
dislodged.
• safety helmets and safety boots should be worn at all ties since earth and other material
can slide down or fall.
• excavations must be thoroughly examined weekly (every seven days) and after
substantial collapse or damage.
The chief factors influencing the type of construction used are ground conditions and the
depth to which the work is to be carried.
Where the work can be safely carried out in free air, cofferdams or open caissons may be
used.
For deep cofferdams it may be preferable not to lower the water below a certain level, the
last stages of excavation, concreting and if necessary strutting being carried out through
water.
23.8.3 cofferdams
introduction
The purpose of a cofferdam is to exclude soil and water from an area in which it is required
to carry out construction to a depth below the surface. Total exclusion of water is often not
necessary and in some instances is not possible, but the effects of water ingress must be
taken into account.
There are two principal approaches to cofferdam design. Single skin structures are most
common, but for very large or deep excavations and marine works, double wall or cellular
cofferdams may be preferred.
The design of a cofferdam is carried out in the same manner as a retaining wall and
consequently, the same rules apply.
• for water cofferdams, the strength of the current, wave action and scour before, during
and after construction
• availability of materials
• methods of constructing and dismantling the cofferdam
• time available for construction of the cofferdam
• noise, vibration, fumes and fire risk
• accessibility especially for cofferdams in water
Certain of the types are suitable for both land and water cofferdams, while others are
applicable to one or the other only. The extent of the working area will further limit the
choice. When the depth is great, the soil and water level conditions will be particularly
significant.
For extreme depths, depending on the soil conditions, it may be necessary to resort to
monolith or caisson construction.
A caisson in free air or an open caisson may be employed where it is necessary to establish
the foundation at a considerable depth below surface water or ground level, e.g. to depths
which may in exceptional cases exceed 45 m. Excavation will usually be done by grabbing.
Caissons are not commonly employed if the ground contains a large proportion of very stiff
clay, owing to the great weight of the structure required to overcome skin friction in such
ground, but skin friction may be reduced by lubrication with water or clay grouts. Open
caissons are difficult to pass through rock or ground containing large boulders.
Caissons may be used for a wide variety of ground conditions. These include the following:
a) in water-bearing ground where it is required to inspect the soil at foundation level, and
where alternative means of dewatering are impracticable;
b) where the caisson is to be sunk through water-bearing strata containing rock either as
beds or as large boulders;
Reinforced concrete caissons (monoliths) may be preferable to steel caissons during sinking
because of their greater weight.
Steel caissons usually present fewer problems during their construction than reinforced
concrete caissons.
e.g. unexpected ground conditions that may require a change in construction technique, or
unusual smells which may indicate the presence of noxious or dangerous gases.
The need for protective helmets is particularly important for those in piling gangs and
persons engaged in working in excavations or in areas with confined headroom.
safety footwear
Should be reinforced by steel not only in the toes but also in the soles, to prevent injury by
sharp objects concealed under the spoil.
safety harnesses
ear defenders
Noise levels during certain operations can be injurious to hearing and so require the wearing
of ear protectors.
23.9.4 ladders
Ladders should be of substantial construction and secured to prevent slipping. They should
not rise more than 9 m without intermediate platforms (see Pt 2 section 29)-Scaffolding
23.9.5 electricity
Supply of electric power for lighting and hand tools should be at a voltage not exceeding 65
V to earth.
Where higher voltages are required for supply to machinery, the supply cable should either
be armoured or enclosed in continuous metal conduit, (see Pt 2 section 7) for electrical
installations
23.9.6 fire
Particular attention should be paid to fire hazard on working platforms. Drip trays should be
provided for oildrums and under machinery; fire extinguishers have to be provided and kept
in working order.
water which enters the excavation it is often desirable to install a drainage system which can
channel water to a sump from which the water can be pumped away.
As the hydraulic gradient adjacent to the corner of a cofferdam is at its largest, it is advisable
to place any sumps at excavation level as far as possible from any corner and wall.
It should not be forgotten that pumps are able to remove soil as well as water and a suction
hose laid in the bottom of a cofferdam can disturb the base of the excavation with
subsequent movement of the wall if the hose is badly located. Consideration should be given
to forming a sump using a perforated drum into which the hose can be fixed to limit damage.
23.9.11 tide work, work over or adjacent to water (also see Pt 2 section 28.0)
• Taking into account the circumstances, in some cases, especially in flowing water,
lifebelts with lines attached should be provided and be readily available at positions
where they are likely to be needed.
• Buoyed lines will be desirable at a suitable distance from the work to give anyone who
falls in an adequate chance of securing a handhold while awaiting rescue
• Particular attention is drawn to the need for adequate floodlighting at night at least
within the limits of the buoyed lines.
• In fast flowing waters or tidal waters a safety boat, boatmen and lifebelts at conspicuous
positions should be provided.
• All men working over water should be required to wear a buoyant life-jacket.
23.9.12 concrete, steel and steel sheet piling (also see Pt 2 section 26) -Piling
The safety precautions necessary in handling steel piles and interlocking steel sheet piling
are also applicable to precast concrete piles.
The pile topman who guides the pile into the interlock of a pile should be provided with a
fenced platform which can often be built onto the temporary timber trestle used for pitching
the piles in panels or provided with a safety harness attached to permanent static line. If a
man-riding skip used for access is suspended from a crane, then the hoisting mechanism of
the crane has to be provided with automatic braking facilities.
Only skilled and experienced men with adequate and safe equipment should be required to
carry out the potentially hazardous operation of interlocking steel sheet piles.
The extraction of steel sheet piles should be carried out with an extractor of adequate size,
so that the performance is not mainly dependent on the pull of the crane and there is no
danger of overloading or overturning the crane.
storage areas provided for spoil, trench supports materials, plant and permanent work
materials
imported backfill and materials ordered (compactors, compressors, generators, lighting, traffic
lights and signs etc.)
special plant ordered (dewatering equipment, pumps etc.) special plant ordered (dewatering
equipment, pumps etc.)
Is the sketch for the foremen or ganger complete, clear and unambigous?
If there is a detailed drawing for the Temporary Works Co - Ordinator and does it show
everything?
have the temporary works quantities been taken off for the site engineer?
are the design assumptions shown on drawings and calculation sheets correct?
INTRODUCTION 1
MAIN APPLICABLE U.A.E. LEGISLATION
SECTION 24
Municipalities & Agricultural Department
H&S Construction Codes of Practice
PART TWO
SECTION 24
INTRODUCTION
This section makes recommendations for and gives guidance on Health & Safety practices in shaft
sinking and tunnelling.
The standards and guidelines also include health & safety recommendations that are particularly
relevant to the type of shaft sinking and tunnelling that is carried in the Emirate of Abu Dhabi.
24.1.1 workers
All persons employed should have a high standard of physical fitness. It is desirable that
all persons working underground and all plant operators and banksmen be not less than
18 years old.
24.1.2 training
All employees involved in underground construction must be trained to recognise and
respond to hazards associated with this type of work. Training should be tailored to the
specific requirements of the jobsite and include any unique issues or requirements.
24.2.1 communication
above ground person
• Any time an employee is working underground, the employer must maintain at least one
designated person on duty above ground.
audible signals
• Audible signals by bell, whistle, or other device can be used for routine operations
such as hoisting and lowering in a shaft. Signals should be distinctive and sufficiently
loud to avoid confusion with any incidental or accidental noises.
emergency: continuous
visual signals
lone working
To help control access, all unused openings must be tightly covered, bulk headed,
barricaded, or fenced off, and posted with warning signs that read, "Keep Out" or similar.
It is essential that persons trained in first aid and capable of responding rapidly to any
incident be available on each shift during working hours.
emergency response
All personnel should be told that, in the event of serious injury, a casualty should be
moved only by a trained first-aider, unless there is the immediate risk of further injury.
Sufficient first aid boxes should be provided, designed to protect the contents as far as
possible from damp and dirt. They should be clearly identified and be readily accessible
to working areas and should be in the charge of designated first-aiders on each shift.
stretchers
Stretchers (and blankets) suitable for the confined space of a tunnel should be provided
and maintained. They should be readily accessible for use in working areas in an
emergency, and should be protected against dirt and damp. In particular, where access
to a tunnel is by a shaft, stretchers should, where practicable, be stored at tunnel level.
Appropriate means of transporting an injured person to the surface should be provided.
Lifting arrangements in shafts should take this into account.
24.2.6 evacuation
Good communications are essential between the working areas and the surface. A clear
plan of action should be formulated for the rapid transfer of any injured persons from
working areas and to ensure that ambulances can reach shaft tops or other access
points quickly. Clear instructions should be given to all persons on the procedures to be
adopted for evacuating tunnels in an emergency.
standards
• working in the tunnel have a portable hand lamp or cap lamp unless natural light or an
emergency lighting system provides adequate illumination.
• be provided with an escape type breathing apparatus and approved gas monitor if the
area they are working in areas which may present a gas or smoke hazard.
• If 25 or more employees work underground at any one time, the employer must provide a
fully equipped and trained rescue team together with appropriate vehicle to transport an
injured person to the nearest hospital.
• If a shaft is used as the means of egress, the employer must arrange for a readily
available lifting capability unless the regular lifting means will function in the event of a
power failure.
• Open flames and fires are prohibited in underground construction areas except as
permitted for welding, cutting, or other hot work operations.
• Smoking is prohibited at all times and notices to this effect should be prominently
displayed.
• Fire extinguishers or equivalent extinguishing means must be available at the head and
work areas.
• All underground structures and those within 30 m of an opening to the underground must
be constructed of materials with a fire resistance rating of at least one hour. Also, non
flammable or combustible material may not be stored above ground within 30 m of any
access point to an underground operation.
• Petrol may not be underground at any time for any purpose and internal combustion
engines (except diesel-powered engines on mobile equipment) are prohibited
underground.
• Oil, grease, and diesel fuel stored underground must be kept in tightly sealed containers
in fire-resistant areas away from passage ways.
hot works
• Acetylene and liquefied petroleum gas may be used underground for welding, cutting,
and other hot work if all requirements/standards pertaining to such activities are met.
(see Pt 2 section 27 )-welding
• Only enough fuel gas and oxygen cylinders for welding, cutting, or hot work during a 24-
hour period are allowed underground.
• Non combustible barriers must be installed below such activities if they are performed in
or over a shaft or rise.
• A surface level tank holding diesel fuel to be pumped to an underground storage site
must have a maximum capacity no greater than the amount of fuel required to supply
underground equipment for 24 hours.
• The transfer pipe must remain empty at all times except when transferring diesel fuel.
• All hoisting operations in the shaft must be suspended during refueling operations if
the supply piping in the shaft is not protected from potential damage.
24.3 NOISE
24.3.1 general
The effects of noise are intensified in tunnels because the confined space increases the
reverberant sound field that can be developed by noisy plant and equipment, tools or
processes. This is especially problematic if persons have to work close to, or use, noisy
tools, e.g. pneumatic picks producing a sound pressure level of 110dB(A) to 115dB(A).
• Since there is insufficient space to reduce the level of noise emission by confinement
and/or containment retrospectively, all machines and tools should be selected on the
basis of risk assessment to be designed to eliminate or reduce the noise at
source with minimum operator exposure.
Pt 2 section 3 gives guidance on how noise arising from worksites affects site personnel
and others. It contains information on noise emission from tools, plant and equipment
that could be useful at the planning stage in reducing noise and recommendations for the
control of noise.
24.4 VENTILATION
24.4.1 general
• polluted air must be removed from tunnel continually.
• if natural ventilation does not provide the necessary air quality through sufficient air
volume and air flow, the employer must provide mechanical ventilation to ensure that
each employee working underground has at least 200 cubic feet (5.7m3) of fresh air per
minute.
• the inlet to the ventilation system must be positioned away from petrol and diesel
engines, hazardous materials and dust fumes.
• the outlet from ventilation system should be positioned such that it would free to
disperse any harmful substances away from the work area.
24.4.2 cooling
• the volume of fresh air required for cooling purposes should be examined carefully
to ensure a sufficient flow of air to keep the working temperature within acceptable
limits.
24.4.3 selection
• The methods of ventilation adopted should be in accordance with the hazards
presented by each tunnelling situation. Factors that should be considered include:
• In a tunnel advancing as a single face, fresh air supply to face workers is likely to be
the primary consideration; but where there are many areas of work the requirements
for the supply of fresh air and ventilation will vary.
• Where dust is a major problem, the system should be designed to control dust and
should incorporate filters to clean the dusty air before readmission to the general body
of airflow.
• The effect of heat added to the air from installed machinery, and the increase in
humidity, can be reduced by using forcing systems having high local air velocities and
by carefully controlling the amount of water used for dust suppression.
a) a forced supply of fresh air, exhaust being through the tunnel and access ways
b) extraction of polluted air from the tunnels, fresh air being drawn into the tunnel due to
the reduction in pressure caused by the exhaust ventilation
d) air movers to assist locally and to eliminate stagnant pockets. If air movers are used
locally, care should be taken to ensure that these will not cause recirculation.
24.4.6 earthing
The movement of dust and gases through a ventilation system can cause a dangerous
build-up of static electricity. All ducts, fan bodies, casings and support structures should
be properly bonded to each other and to an adequate earth. Air movers and venturi
devices should also be earthed.
methane
Where an extraction ventilation system is in use and there is a risk of methane being
encountered, the design and construction of the system should take into account the
hazard of methane passing through fans and fan motors. The methane concentration in
the ducts should be continuously monitored.
is shut down. Explosion protection of the extraction system in many cases involves
the use of bifurcated fans with non-incendive impeller rings.
dust
• To prevent dust particles migrating back against the main body of airflow, the air
velocity in any section of tunnel should be not less than 0.5 m/s. Ventilation
calculations should use this as a minimum value. The efficiency of the ventilation
system should be tested periodically and any deterioration in performance should
be remedied.
24.5 DUST
24.5.1 general
Dust generated from tunneling works should be suppressed at source as far as is
practicable. Its spread should be controlled by methods such as water spraying, water
infusion and extraction ventilation.
The exposure of persons to various kinds of mineral dust can produce a variety of lung
conditions. Among the more serious conditions is pneumoconiosis.
Respirable dust that has become airborne cannot be controlled by water sprays. However,
these can be used whilst handling spoil to suppress dust by preventing it from becoming
airborne.
In dusty conditions, extraction ventilation and possibly filtration is essential. Dusty air is
likely to be very erosive, and fans and ducts should be designed accordingly and be
properly maintained.
when drilling rock or concrete, dust control measures such as wet drilling, vacuum collectors,
and water mix spray systems must be used to maintain dust levels within limits set for gases,
vapors, fumes, dusts, and mists.
• A risk assessment should be carried out to help determine whether or not fixed electric
lighting is required and, in the exceptional case where it is not, hand lamps or cap lamps
should be provided.
• Where colour recognition is an important factor, the type of light source should be
carefully considered. For example, sodium lighting can present problems in colour
discrimination.
Lighting levels can be measured with a lightmeter and should be as high as is practicable, taking
into account the work to be undertaken in the area. The table below sets out the recommended
mean lighting levels.
The presence of dust or mist in the atmosphere can also have a very significant effect on lighting
levels and should be a consideration to meet the values in the above table.
• hand lamps or cap lamps – if used it is essential that management procedures be put
in place and facilities provided for their proper storage, charging, distribution, use, and
maintenance.
• Emergency lighting should be installed along the tunnels intervals of not more than
50 m to allow safe egress from the tunnel, and should be installed at the following
locations:
escape routes
emergency exits
∗ 21.00% Oxygen
∗ pollutant levels should not exceed their occupational exposure limits and should
be reduced as low as reasonably practicable.
In the vicinity of any shaft, special precautions should be taken to prepare a suitable base
for siting a crane to minimize settlement and to spread crane loads as widely as possible,
and also to avoid excessive lateral thrust from the ground against the shaft lining. A
reinforced concrete raft, or beams, spanning any sensitive area should be designed
and provided if the ground resistance is locally inadequate.
With mobile cranes that are not restricted to predetermined locations, particular care
should be taken to check that loadings imposed upon the ground are kept within safe
limits, i.e. that they are no greater than the bearing capacity of the ground.
24.8.2 clearances
Where adequate personnel clearance around a crane (500 mm) cannot be provided,
access to areas of restricted clearance should be prohibited while the crane is
operating.
The limit switch should only be used when operational controls malfunction. Hoist controls
must be arranged so the operator can reach all controls and the emergency power cutoff
without reaching beyond his normal operating position.
• Employees may not ride on top of any cage, skip, or bucket unless inspecting or
maintaining the system and wearing a safety belt or harness.
• Personnel and materials must be hoisted separately (except small tools and supplies
secured in a non hazardous manner).
24.9 SHAFTS
24.9.1 shaft sinking
general
The shaft sinking operation is likely to have an impact on the general public, and can
affect adjacent structures. Particular care should be taken in designing and locating
shafts to minimize disturbance outside the site. Both safety and environmental factors
should be considered.
• If grabs are to be used, personnel should be either protected within the shaft, or
removed from the shaft before grabbing commences.
• The number of persons in the shaft bottom area should be kept to a minimum whilst
operations are in progress
• In small diameter shafts, particular care should be taken due to the limited scope
for refuge, and persons should be alerted to any loads being sent down.
• All skips used in shafts should have positive fixings so that they cannot tip while
being hoisted. Other potential hazards, such as material falling off the top due to
overfilling, or loose material becoming stuck to the bottom, should be assessed and
minimized.
• Larger shafts are often excavated by a 360° hydraulic excavator working within the
shaft. Measures should be taken to minimize the risk of persons being struck or
trapped by moving plant.
• When handling loads with a crane or hoist, precautions should be taken to ensure
that:
• the load or skip does not swing or twist causing it to strike the lining of the shaft or
other structure;
• the load or skip does not catch a ledge, either in lowering or in hoisting, causing it to
tip over and spill out its contents (whether persons or materials);
• the rope does not become slack when the load is resting on the bottom or on a stage
and catch in some part of the shaft structure, with resultant damage when
tightened.
• All plant regularly transferred down the shaft should be designed for hoisting and be
tested and certificated for such work.
• As a standard procedure in lifting, the load should be lifted a short distance then
stopped, steadied and inspected before hoisting continues.
permanently disused
When a shaft is to be decked over on completion of its use, the decking used should be
specifically designed for that purpose and should be installed for its intended use. If a
void is left, it should be ventilated. Traceable records should be kept of all disused shafts
or access tunnels giving details of the shaft or tunnel, and the method of capping or filling.
temporarily disused
tunnel eye
A shaft through which any opening is to be formed should be designed to facilitate the
safe construction and use of that opening.
When a tunnel eye is to be provided near the shaft bottom through which the tunnel or
heading is to be formed, the shaft structure should be supported as for a tunnel
opening.
The actual operation of breaking out should be carried out with the utmost care
because the ground is inevitably disturbed by the sinking of the shaft, and it is probable
that water has followed down the side of the shaft however carefully grouting has been
done. Immediate close support of all ground is therefore often essential.
In bad ground, it can be advisable to fix the first setting of a heading, or build the first
ring of iron or concrete, within the shaft. Alternatively, a small heading can be driven out
of the shaft, from which a break-up for the full size access tunnel is constructed at a safe
distance in undisturbed ground, the heading or tunnel being subsequently enlarged back
to the shaft.
The layout and detail at the top of the shaft should be designed to prevent the accidental
fall of persons, plant, spoil or material into the shaft.
The area immediately around each shaft should be level, clear of obstructions and
properly drained; it should generally provide a safe working area, and should be
adequately lit.
Stacking and storage of materials should be arranged at a distance from the shaft top
so that excessive ground pressures are not imposed on the shaft.
The shaft should be guarded using, for example, additional segmental rings or
substantial steelwork and/or solid bariers and mesh, which should reach a height of at
least 1.2 m above adjacent ground level.
Surface water should be excluded from the shaft by the provision of barriers and by
drainage and pumping if necessary. Special precautions should be taken against
inundation.
Mobile plant poses a particular hazard. Either it should be physically prevented from
working near a shaft, or barriers should be erected that are robust enough to prevent the
equipment from falling into the shaft.
personnel access
Personnel access in shafts should be by fixed access equipment such as a mast climbing
hoist or man-riding crane where it is reasonably practicable to provide such equipment
In all cases where the normal means of access is by mechanical means (hoist or crane),
there should be a secondary means of egress to cover plant breakdown.
Fixed access should be provided in every shaft as early as possible, and in any case on
completion, except where an alternative route provides safe pedestrian access to the
base of the shaft.
Fixed access includes stairways, ladderways or vertical ladders with protective hoops.
Stairways should be used whenever possible as the preferred option, as these allow
persons to carry hand tools and similar equipment.
Every ladder should be securely fixed at its base and at the upper landing. It should
extend at least 1.1m above the upper landing unless other adequate handhold is
provided.
Vertical ladders fixed to shaft walls should be made of steel (rather than light alloy or
timber). Vertical ladders should have protective hoops and straps fixed above a height of
2.5 m from a landing.
The foothold at every rung on all ladders should be unobstructed. Landings should be at
intervals not exceeding 9 m. They should be solidly constructed with hand rails, guard
rails and toe boards. Openings for ladders should be as small as is practicable and sited
clear of the foot of the upper ladder. Every landing should be adequately lit.
Stair bays and ladder bays in shafts should be protected by substantial barriers against
swinging loads being handled in the shaft.
All means of access including hoists should be inspected weekly, and maintenance
carried out where necessary.
general
• For tunnels under construction, the internal size for man-entry should be not less
than 1.2 m high by 0.9 m wide, in order to facilitate rescue. Tunnels smaller than
this should be constructed by methods that do not involve man-entry.
• The risk of collapse or excessive settlement is greater with small timbered headings
than with other forms of tunnel construction. Only the highest standards of
workmanship in initial timbering and subsequent back filling should be used.
• Any temporary support should be capable of lasting for as long as the heading
remains open and be capable of securing the surrounding ground against
settlement and collapse.
• In small tunnels, persons cannot walk upright and can pass one another only with difficulty.
It is normal practice for a single person to excavate the face, although a second should
always be present.
• Arrangements should be defined for the rescue and escape of the face workers in the event
of accident, injury, illness, collapse of the tunnel face, immobilization of a locomotive,
derailment or fire etc.
ventilation
• Ventilation can be a particularly difficult problem. There will be little or no natural circulation, and
shallow tunnels through variable ground will frequently pass through or near ground with
organic content or with other contamination that could pollute the tunnel atmosphere. Where
contamination could occur, a forced ventilation system should be used to limit the ingress of
contaminants, and a supply of fresh air to the face is therefore essential. Low-volume, high-
pressure ventilation systems may be appropriate owing to the lack of space.
pipe jacking
• the high thrusts necessary to propel the pipe forward should be resisted by a properly
designed and constructed abutment or thrust wall at the working pit.
• hydraulic rams and any load-spreading rings, spacing blocks or packers should be carefully
secured, with all loaded surfaces precisely aligned perpendicular to the thrust.
• as far as possible, persons should be protected from and withdrawn from the vicinity of
highly stressed equipment during thrusting.
• when jacking pipes into firm or stiff clays, the techniques adopted should take into account
any displacement of the soil caused by entry of the pipes, and possible heave of the ground
surface.
• jacking pipes are installed via a working shaft and joined using hydraulic jacks. It is essential
that all persons seek shelter or protection within the part-completed pipeline or elsewhere
whilst pipes are lowered.
Subsidence areas must be similarly guarded by shoring, filling in, or placing barricades and
warning signs to prevent entry.
Adjacent areas must be scaled or secured to prevent loose soil, rock, or fractured
materials from endangering portal, subsidence, and access areas.
A competent person must determine how often rock bolts need to be tested to ensure that
they meet the necessary torque, taking into consideration ground conditions, distance from
vibration sources, and the specific bolt system in use. Only torque wrenches should be
used when torsion-dependent bolts are used for ground support.
The bottoms of any support sets installed must have sufficient anchorage to prevent
ground pressures from dislodging the support base.
Lateral bracing (including collar bracing, tie rods, or spreaders) must be provided between
immediately adjacent sets to increase stability.
Any dislodged or damaged ground supports that create a hazardous condition must be
promptly repaired or replaced. The new supports must be installed before removing the
damaged supports. Some type of support, such as a shield, must be used to maintain a
safe travel way for employees working in dead-end areas ahead of any support
replacement operations.
not change as a result of exposure. Where the potential for shear exists, where the shaft
passes through earth into solid rock in either direction, or where the shaft ends in solid
rock, the casing or bracing must extend at least 5 feet (1.53 m) into the solid rock.'
The casing or bracing must also extend 42 (± 3) inches above ground level unless a
standard railing is installed, the adjacent ground slopes away from the shaft collar, and
barriers exist to prevent mobile equipment operating near the shaft from jumping over the
bracing. If these conditions are met, the casing or bracing may be reduced to 12 inches
above ground.
FALSEWORK
DEFINITION 1
INTRODUCTION
MAIN APPLICABLE U.A.E. LEGISLATION
SECTION 25
Municipalities & Agricultural Department
HSE Construction Codes of Practice
PART TWO
SECTION 25
FALSEWORK
INTRODUCTION
Since collapses of falsework cause loss of life and serious injuries, the objective of this section is to
ensure that all persons involved with are well informed of safe procedures and of proper application of
these in order to set the risk of failures to minimum.
The check list at the end of this section also includes guidance on related matters in concrete
construction: falsework, steel fixing and concrete operations.
DEFINITION
Falsework is defined as any temporary structure used to support a permanent structure during its
erection and until it becomes self – supporting.
This definition also applies not only to in-situ concrete construction, but also precast concrete
structures, structural steel, steel erection, and even such items as brick arches, etc. indeed, any
construction method where the permanent structure may have a period of instability, requiring support
is the erection process.
• people falling during steel fixing and erection of • being struck by a concrete skip
falsework • silica dust from scrabbling
• collapse of falsework operations
• materials falling whilst striking falsework • arm and back strain for steel
• manual handling of shutters reinforcing bars etc fixers
• cement burns from wet concrete
Falsework covers a wide range of temporary support methods and BS 5975 recognises that,
in simpler and more commonplace situations, e.g. support of floors and beams involving light
loadings and low height support (within the range of standard props) etc., standard solutions
can most likely be used instead of individual design,
Standard solutions are given in section 8 of BS 5975. However, unless the job falls within the
limitations of the particular standard solution, further design will be required.
With standard solution designs, the set of information released would include the following:
• design brief
• concept of the scheme
• design drawings and specifications
All the above phases and responsibilities have to be co-ordinated, distributed, and overall
checked by the Falsework Co-ordinator whose responsibilities and duties are defined
below:
Falsework Co-ordinator
• co-ordinate all falsework activities;
• ensure that the various responsibilities have been allocated and accepted;
• ensure that a design brief has been established with full consultation, is adequate,
and is in accordance with the actual situation on site;
a) concept
b) structural adequacy
• where appropriate, ensure that the design is made available to other interested
parties, e.g. the structural designer;
• register or record the drawings, calculations and other documents relevant to the final
design;
• ensure that those responsible for on-site supervision receive full details of the
design, including any limitations associated with it;
• ensure that checks are made at appropriate stages covering the more critical
factors
• ensure that any agreed changes, or corrections of faults, are correctly carried out on
site;
• after final check, issue formal permission to load if this check proves satisfactory;
• when it has been confirmed that the permanent structure has attained adequate strength,
issue formal permission to dismantle the falsework.
Of particular note in the above list of duties is the concept of issuing a formal permit to
load before any concreting takes place - followed, at the appropriate time, by a permit
to dismantle.
The design brief should be prepared in both cases of standard and individual solution
design and all design parameters should be precisely determined and stated clearly in the
design brief.
The basic items to be considered at this stage, but not limited to, are the following:
Not only the weight of the permanent structure, but also other factors are to be included in
the calculation of loads to be applied to falsework
Factors to be accounted for are as follows:
• weight of permanent structure: (this should be based on actual unit weight of materials
used in permanent structure).
• weights for all the attachments and bolts should be included in weight calculation of
steelwork.
loading sequence
To prevent the build-up of stresses in individual members of the support structure, and to
eliminate the possibility of moment reversal and uplift on supports, designer of falsework
must be aware of:
• sequence of pouring
Additional loads arising from plant and method of erection are imposed on the
falsework, most common causes being:-
• limited concrete heaps in addition to impact, weights of labour and plant involved in
spreading, compacting and levelling concrete : 150kg/m2
Any modification of the loading programme after designing falsework should only be carried
out after consultation with of falsework designer. It is the responsibility of the site team to
notify the designer of any changes.
• to ensure proper performance, all persons in charge for erecting, inspection and checking
activities should receive copies of the following:
There should be no start in the erection of falsework unless all necessary materials and
equipment are already made available on site, otherwise, assurances that materials and
equipment delivery to site are to be made whenever their incorporation in the structure is
required. Whether new, second hand or fabricated equipment and materials are to be
incorporated into the erection, they should be checked for their compliance with the design.
timber
• type, grade, and size in accordance with the drawings and specifications.
• no presence of (defects, shakes, splits, winds, loose or large knots, and crushed or
damaged areas) is allowed.
fabricated equipment
• no substitution for critical items (like high tensile pins in props) is allowed. These items
should be provided as new.
25.5.3 foundations
It is of great importance that foundations of falsework be properly erected and thoroughly
checked.
Foundations are the basis on which the integrity of the structure as a whole depends,
therefore you should ensure that:-
• no modifications were made to the latest loading programme followed in the final
falsework design.
Equally, foundations require protection from the effects of weather so that the ground
conditions as excavated are not altered (see Figs.1 & 2). Failure in this respect may result
in collapse or, at best, settlement.
Ponded Water
Flowing water:
Water penetration or
Wash Out Zone Absorption
cohesive soils
Provide surface blinding to prevent ponding of water which alters appreciably the
characteristics of cohesive soil.
cohesionless soils
• provide cut-off drains and surface blinding to prevent the wash-out of non-cohesive soils
due to flowing water, especially in storm conditions.
• when it is recommended by the designer that full bedding of the sole plates be
performed, execution should be undertaken as such:
∗ use grout or dry pack to fully anchor steel members into foundations.
These are critical points in the structure and both those who design falsework and those who
erect it, must be aware of good practice. (See Check List at end of section).
Diagonal as
close as
possible to
node
Connecting tube on
25.7 LACING AND BRACING every row of
Secondary Timber
standards
Ensure that:
the following items are to be checked for proper installation of end bearers
• full contact is achieved between end bearers and its underlying ground or plates.
• proper restraint is made to ensure the stability of end bearers in their position.
Main Timber
“a”
Fig.8 - above showing the correct method of using Jack Head Bracing
• the lifting system must be arranged in a way to avoid collision and consequential
breaking of pre cast elements.
• lateral supports should be provided before releasing pre cast elements from the sling,
especially in the case of beams with a width to depth ratio exceeding 1 - 3.
• hand-lines should be fixed to these panels to make handling more convenient and safer,
especially in presence of high wind.
• fixing of the panels is made by studs, bolts, or welding to prevent lateral movement,
excessive deflection and displacements arising from wind action.
• panels can be affected by heat, therefore, heat generating sources should not be brought
close to these panels.
• during the cutting of panels, dust masks and eye protection should be worn.
Note: Anchoring of decking panels and use of clamps or weights whenever required is a must to
prevent uplift forces from moving the panels.
Since errors in falsework erection are not always remediable, checking for the correctness of
falsework erection should be scheduled far enough ahead of erection time for the permanent
structure. Items to be checked for the correctness of falsework erection are the following:
General
adequate anchorage, levelling and correct positioning of sole plates and grillages are achieved.
base plates and grillages should be located to the centre of underlying sole plates.
vertical alignment should be plumbed within deviation in accordance with specified tolerance.
spacing for these members is to be executed in conformance with drawings and standard
details.
all members, couplers, fittings, wedges of the falsework and others are installed properly,
secured, tightened and at correct positions. If these precautions are not taken into account,
loose and non-nailed wedges may fall-out in presence of any vibration arising from activities
such as concrete placing and consolidation.
base and head jacks are not over extended unless detailed with adequate special bracing (see
figs. 4 & 5)
all bracings and lacings are coupled as close to node points and never more than 150mm away.
all bracings and lacings are connected to correct members e.g. diagonals to lacings to allow
right angle structural couplers to be used.
no storage should be placed on falsework since it is not designed to carry additional heavy
loads for other purposes.
falsework should be designed to allow safe lifting and handling from points designed for this
purpose.
persons not involved in the construction process, dismantling or inspection of falsework should
be denied access.
loose materials and plant should be fixed against any movement including lateral movement
induced by high winds.
whenever it is possible that workers can fall from slab falsework by more than 2metres, suitable
edge guards shall be installed.
whenever workers are erecting falsework elements higher than 2 metres over previously
erected slabs, guarded work platforms with access ways should be provided. These access
ways should be also guarded and wide enough to allow for workers to carry materials (see Pt 2
section 29 - Scaffolding & Working Platforms)
proprietary falsework systems should be erected and used in accordance with manufacturers’
instructions.
removal of projecting nails and sticking elements (in the case of concrete) as work proceeds.
before removal of safety guardrails making part of the falsework, replacement safety guardrails
are to be installed and connected to the edges of concrete.
after removal, falsework should be supported safely during repair, oiling and other maintenance
works needed before reuse.
steel fixers should work at safe places or shops provided on site. Persons not involved in steel
shop work should be denied access.
during the cutting of reinforcement, protective gloves and eye protection must be worn by
persons performing work.
only recommended types of blades should be fitted to disc cutters to prevent any accident
arising from the breaking of a blade.
torches shall not be used in cutting steel of types adversely affected by heat.
the short end of the cut bar should not be left to fly off and endanger life of persons.
proper walkways should be installed over the fixed steel cages to secure the safety of persons
crossing over to access their destination.
INTRODUCTION 1
MAIN APPLICABLE U.A.E. LEGISLATION
PILING
INTRODUCTION.
Piling operations can give rise to different hazards dependent upon the type of piling being
undertaken. Certain hazards are, however, generally common on all types of piling, and this section
gives both the general precautions to be taken and the special precautions relating to the different
types of piling.
• if a rig with a SWL of more than one ton is used for general lifting operations, such as the
loading and transport of materials on site, it must be fitted with an “automatic safe load
indicator” ASLI.
• a firm level base of adequate bearing value must be provided, or crane mats used.
• piling machine operators must be at least 18 years of age, trained, competent, medically
fit and authorised by site management to operate the machine.
• cranes which have been employed on piling duties should be subjected to a thorough
examination before being returned to general lifting operations
• when piling from a pontoon or adjacent to water, personnel should wear life lackets.
Rescue equipment (e.g. a safety boat and Iifebuoys with lifelines attached) must be kept
ready for immediate use and enough men must know how to use it. (see Pt 2 section 28)
-Working over or Adjacent to Water.
• piles should not be stacked too high or in a cantilever position. Spacers and chocks
should be used where necessary. Tubular piles should not be stacked more than four
high and should be properly chocked.
• when lifting piles or piling hammers, hand lines should be used to control the load. It is
important that due consideration is given to wind speed during these operations.
Piles can either be held in position during driving using a special leader arrangement
attached to the crane or piling plant or, alternatively, a gate system may be used as
described below.
A single gate system is made up of a simple frame of either timber or steel gates supported
by blocks a suitable distance above ground level. A shallow guide trench is normally dug to
assist with the location of the sheet piles.
Sheet Piles pitched – not driven
Toeboard Guardrails Sheet piles pitched
and part driven
Walkway top
gates with Hanger Brackets
gap covered
Bottom Gate
Bolts
Anchor Block with lifting eye
Kelly Block cast into block
Fig.2 - TWO GATE SYSTEM – Showing piling, the use of hanger brackets and the provision of a safety walkway
“Gate support system” See Fig.2 shown above is a two gate system, made up from timber
H-frames, set in concrete Kelly Blocks. These H-frames are then spanned by RSJ’s (gates).
If the gates are over 2m high, or over any potentially dangerous area, they must not be used
as working platforms unless fitted with toe boards which rise at least 150mm, and main
guardrails at least 910mm above the walkway. Additionally, intermediate guardrails, or other
rigid barriers must be fitted so that there is not an unprotected gap of more than 470mm in
height in the means of protection against a fall (as in the illustrated in Fig.2).
Where such protection cannot be provided, access to slinging points must be gained by
ladder and NOT by means of the gates.
• permanent ladder access must be secure and extend above the gates sufficiently to
provide a safe handhold. (A distance of 1 .05m is recommended).
• when constructing Kelly Blocks, reinforcement should be placed in the concrete base.
Vertical RSJ’s should have a good “key”. Vertical timber should not be cast into the block
but should be wedged and bolted.
• where doubt exists over the stability of Kelly Blocks, guy lines should be used.
• remote release shackles (see Pt 2 section 30)- Erection of Structures , should be used
where possible and the sheet pile must not be lifted vertically without first checking that
the pin is properly engaged through the sheet. The length of the operating rope must be
less than the length of the pile, and the rope should be secured around the pile to prevent
snagging or being caught in the wind and becoming inaccessible.
• if piles are too heavy for a remote release shackle and work cannot safely be carried out
from a ladder, a lifting cage should be provided to gain access for unscrewing the
shackle. (see Fig.1)
• if a special lifting eye is to be welded to the pile for angled pitching, the weld should have
a factor of safety of at least 2.
• long sheet piles should be pitched with a pile threader following the manufacturer’s
guidance for use. Where this is not possible, a pile pitching cage should be used. The
cage should hang from an adjacent pile with the operatives wearing safety harnesses
hooked to the adjacent pile before the crane hook is removed from the cage.
• when sheet piles are being pitched, it is essential to take particular care to ensure the
stability of the first few piles, but especially the first pile. This may be achieved by fixing
the pile to the gate at two points so that it cannot move within the plane of the gate. This
action will also ensure that the pile is stable if an effective toe-in is not achieved due to
hard/stony ground conditions.
• when feeding sheet piles through top and bottom gates, use wood blocks or a bent bar.
Never use a straight pinch bar, as fingers can easily be trapped.
When working off ladders during pitching piles operation, the following additional precautions
is required:-
clutching
• ladder must be placed in the valley of a previously placed pile; the ladder must be footed
and, when at the top of the ladder and both hands are required For clutching, a safety
harness must be worn and secured to the pile using a girder grip. (see Pt 2 section 29) -
Scaffolding/Working Platforms.
wedging
• ladder must be placed against the RSJ and footed; wedges should be pre-positioned on
the RSJ a 41b lump hammer should be used as this can be swung with one hand. If two
hands are required, a safety harness must be worn, with the lanyard wrapped around the
RSJ or connected to a girder grip.
• work method must not be changed without the approval of the senior site representative
or the contractor responsible for the piling operation.
• if windy conditions make the handling of the sheet piles difficult, work must stop until the
responsible person has been consulted and a safe method of continuing the work has
been devised.
26.3.4 hammers
• hammers, and in particular all clamping bolts, should be inspected daily.
• should the piston of a hammer jam, the trip-lever should be pulled to the open position
before removing the hammer from the pile.
• damaged high pressure airlines or high voltage cables, feeding the hammer, can present
a serious hazard to persons working in the vicinity of the operation. Therefore it is
important to keep supply lines/cables under constant observation to avoid damage by
trapping or from sharp objects.
• all hose couplings should be properly manufactured and matched. The joining of rubber
pipes to brass spigots should be by clamp and not hose clips.
• attachment of a hoist rope should always be done using a properly matched anchor and
pear; the dead end of the rope should be secured using a bulldog clip or other approved
means.
• persons are not permitted to enter any borehole less than 750 mm in diameter.
• where it is necessary for any person to enter a borehole, special precautions must be
taken. It must be ensured that no toxic or flammable substance/gas is present in the
borehole and that the air is fit to breathe. Where necessary, a proper ventilation system or
suitable breathing apparatus must be provided. No person should remain in the hole for
more than one hour at a time.
accessing pile shaft
Descent by any person into any pile shaft, or bore hole, from here on referred to as a shaft,
should only be carried out in compliance with the following conditions:-
(see Fig.4)
• it is preferable for mechanical means to be provided and used for inspection and
sampling the sides of the shafts, instead of having to send a person down to carry out the
work.
• banks man must be in attendance at all times when any person is lowered into a bore
hole. He should be in such a position that he can observe the man in the borehole, and If
necessary, should wear a safety harness and line.
• operatives engaged in this work should be trained and competent in rescue from deep
bore holes.
• emergency rescue drills supervised by a competent person should be carried out at the
start of operations and at regular intervals thereafter. A set of printed rescue drill
instructions should be issued and displayed at each site.
• all rescue equipment should be tested regularly to ensure that it is in good working order
and capable of reaching to the maximum depth of the borehole.
• if the secondary rope is used as a crane (i.e. to lift Fig.5 - Type of Piling Auger
commonly used on
casings into place) then there must be an approved
Building/Construction Sites.
automatic safe load indicator fitted to the system.
• when ropes are subject to heavy wear, they must be frequently inspected and changed as
necessary.
26.3.9 tripods
(see Fig.6)
• no tripod should be used unless the rig is tested and the legs marked. The numbers on
the items must coincide with the numbers on the test and examination records
Note: knots must not be tied in any rope used for lifting.
• when a rope/chain block is being used to extract the casings, the capacity of the block
must not exceed the capacity of the rig.
• under no circumstances must there be less than 2 full turns of the rope on the winch
drum at any time
SAFETY CHECKLIST - PILING OPERATIONS
Piling method statements should normally include the following so far as is relevant in the
circumstances:
Name and address of the site to which the method statement relates.
Names of the supervisor/foreman and appointed safety adviser and arrangements for
monitoring the work.
Descriptions of the work to be carried out including the number, type and size of piles and the
method of placing.
Hours of work.
Nature of the soil including details of any contamination present and the precautions to be
taken.
Details of the methods of locating and avoiding any existing underground services, whether or
not their presence if known.
Assessment of any work at height and arrangements for the provision of a safe place of work
and safe access/ egress.
Details of plant and equipment to be used together with confirmation that all necessary records
will be provided on site.
Details of auger cleaning device used and auger or drill guarding provided.
Confirmation that man access will not be permitted to under reamed pile shafts.
Note
This checklist is intended to aid the production and approval of method statements. It is not an
exhaustive list of every possible issue that may need to be addressed for any given task.
WELDING
INTRODUCTION 1
MAIN APPLICABLE U.A.E. LEGISLATION
SECTION 27
Municipalities & Agricultural Department
H&S Construction Codes of Practice
PART TWO
SECTION 27
WELDING
INTRODUCTION
Welding has been defined as the fusion of two pieces of metal, rendered plastic or liquid by heat or
by pressure, or by both.
There are many different welding processes, but the two most commonly used in the construction
industry are gas welding and electric arc welding.
In gas welding metal fusion is achieved by the use of very high temperature flames, produced by a
mixture of gases at a torch or blowpipe. The gases involved are oxygen and a fuel gas, such as
acetylene or liquefied petroleum gas (LPG).
In electric arc welding, the arc is struck between an electrode and the workpieces. The temperature
attained by the welding arc is approximately 4000 degrees celcius. At this temperature, the work
pieces are melted and fused together.
Ministerial Order No. (32) Year 1982 - Articles (5)d & Articles 7 - 9
Valve connections are not therefore interchangeable, and every effort should be made to
preserve the original colour to avoid confusion.
Acetylene is lighter than air, has a wide flammable range and will form an explosive
mixture with air or oxygen.
LPG is heavier than air and may therefore collect in low lying areas.
• cylinders should be shielded from direct sunlight, or other heat, to avoid the build up of
excess internal pressure which might lead to gas leakage or, in extreme cases, bursting
of the cylinder.
• may be stacked horizontally, maximum four high, and wedged to prevent rolling.
• gas cylinders should preferably be kept on a hard standing in a safe place in the open
air. Where this is not reasonably practicable, flammable gases should be kept in a
storeroom, constructed of non-combustible material, and has adequate high and low
level ventilation.
• gas cylinders must be treated with care and not subjected to shocks or falls.
• when they are transported in a vehicle around a site, they should be secured to prevent
injury in the event of any sudden vehicle movement, and when being unloaded from a
vehicle, they should not be dropped to the ground.
• acetylene cylinders must always he transported and used in the vertical position. If they
have been left in the horizontal position, they must be stood upright for approximately
10 minutes to settle out before use.(see Fig.1)
• the adjusting screw of the regulator must always be released before the cylinder valve
is opened, and the cylinder valve must be opened gradually. If it is opened suddenly,
the abrupt compression of the gas will generate excessive heat which might be enough
to ignite the valve seat material or damage the gauge.
• periodic checks should be made to ensure that no gas is leaking from the regulator
when the pressure regulating screw is set at zero. A leak will cause a build-up of
pressure in the hose to the torch when the blowpipe valve is shut. Checks for gas
leakage from any part of the equipment should only be made with water containing
detergent. Bubbles in the detergent indicate the presence of a leak. (see Fig. 2)
27.4.2 hoses
hoses should be:-
• kept for one type of gas only, and colour coded for identification - red for acetylene or
other fuel gases (except LPG), orange for LPG and blue for oxygen.
• inspected daily before use to see that they are free from cuts, scratches, cracks, burnt
or worn patches.
• be effectively clipped or crimped to the equipment and protected at all times from sharp
edges, falling metal, passing traffic and sparks from the welding operation.
27.4.4 blowpipes
If the nozzle of a blowpipe becomes damaged or blocked, then a build up of pressure can
cause a reverse flow of gas and a flashback may occur. It is advisable, therefore, that
blowpipes should be dismantled and cleaned at regular intervals.
• on no account should oil, grease or other substances such as soap be allowed to come
into contact with an oxygen regulator valve or fittings, as these substances are
explosive in the presence of high pressure oxygen. Any leaking oxygen fittings should
not be tightened before closing the cylinder valve and venting the oxygen to
atmospheric pressure.
• it is dangerous to allow the flame to come into contact with the cylinders, or a lighted
torch to be hung on a regulator or its guard. It is equally dangerous to rest blowpipes on
empty oil drums or similar containers even after the flame has been extinguished. It has
been estimated that only half a fluid ounce of flammable material may he required to
give sufficient vapour to form an explosive mixture in a 40 gallon drum. Such a small
volume of liquid would be present as only a thin film inside the drum.
• fatal and other serious accidents are caused by oxygen enrichment of the atmosphere,
due to leaks from equipment or the deliberate "sweetening" of the atmosphere with
oxygen. In such circumstances, the area must be purged with fresh air until the oxygen
level is below 25 percent. All clothing should be well ventilated in the open air to prevent
the risk of spontaneous combustion. At the same time, all sources of ignition in the area
must be eliminated.
Joints between cable sections should be made with properly constructed insulated cable
couplings adequately shrouded, so that live metal is not exposed if the parts of the
connector are separated.
The welding return should be firmly connected to the metal on which welding is taking
place, by means of a well constructed clamp.
Where possible, flammable materials should he kept out of any area where welding is
taking place. Where such a course of action is not practicable, fire resisting sheets should
be used to protect the surroundings from the flame and from spatter. At least one fire
extinguisher should always be immediately available in the area of any welding operation.
27.8.2 burns
Skin burns may result from metal spatter or from
touching hot workpieces. The hands, arms, legs,
and feet are particularly vulnerable, so should be
protected by gloves or gauntlets.(see Fig.5) and
spats and jackets made from chrome leather. The
use of leather safety footwear is also
recommended.
Prolonged exposure to the heat from welding may Fig.5 - Example of Welders Leather Gloves.
lead to reddening of the skin of the face. In the
case of gas welding, discomfort may be avoided by
the use of a hand shield.
Every welding process produces gas and fumes which may result in respiratory disease as
the hot metal vapour from the weld pool will produce fumes when the vapour is rapidly
cooled and oxidised by the surrounding air. Fumes consist mainly of a cloud of line
particles, predominantly iron oxide.
In addition to fumes, harmful gases may also be generated during gas welding, the
principal toxic gases produced being carbon monoxide and nitrous fumes which is only
formed in large enough amounts to be dangerous when combustion is incomplete.
Arc welding produces ozone, a gas which irritates the respiratory system. Nitrous fumes
are also produced, but to a smaller extent than during gas welding.
It cannot be assumed that natural ventilation will produce acceptably low gas and fume
concentrations in the welder’s breathing zone. If a number of welding operations are being
carried out in the same area, or the work is being carried out in a confined space, then the
risk is obviously increased.
The fumes from galvanised metals, lead coated or other toxic metals may affect not only
the respiratory system, but also the rest of the body, particularly where the work which
produces the fumes is carried on for any length of time in poorly ventilated conditions.
The provision of an exhaust ventilation system for this type of work is essential and, in
addition, the use of respirators may be required.
Air sampling must be carried out to confirm the adequacy of the precautions.
INTRODUCTION 1
MAIN APPLICABLE U.A.E. LEGISLATION
SECTION 28
Municipalities & Agricultural Department
H&S Construction Codes of Practice
PART TWO
SECTION 28
INTRODUCTION
Any workplace over, on, or near water, presents a danger that persons might slip, fall or be swept off
their feet by a rapid rise of tide, strong current, or swell from passing water traffic. Whether or not a
person is injured by a fall, there is an immediate risk of drowning and/or being carried away by the
current.
Considerable effort must be made, firstly to prevent persons from tripping, falling or being swept into
the water and secondly, if the worst does happen, to ensure that they are rescued in the shortest time
possible before they can come to any further harm.
• at all edges from which a person might fall into the water, secure barriers or fences are
required.
• warning notices must be erected at all edges and boundaries near water and set so that
they are easily seen by operatives approaching the danger point.
• where platforms or gangways are erected above tidal water, decking boards should be
secured so that they cannot become dislodged by rising water or high winds.
• barges, pontoons etc. used as working platforms, must be properly constructed and
sufficiently stable to avoid tipping.
For further information and guidance on scaffolds and working platforms –
(see Pt 2 section 29) Scaffolds and Working Platforms.
28.2 LADDERS
• must be sound and of sufficient length and strength.
• where ladders are permanently fitted to plant over water, they should be fitted with safety
hoops.
For further information and guidance on ladders – (see Pt 2 section 29) - Scaffolding,
Working Platforms, Ladders and Safety Nets.
• manufacturers should be consulted on what type of net best suits the kind of work to be
carried out and the prevailing conditions.
For further information and guidance on safety nets – (see Pt 2 section 29) - Scaffolding
and Working Platforms.
• materials awaiting use should be stacked compactly and, particularly on pontoons, not
piled too high.
• oily or greasy surfaces should be gritted or treated with industrial salt or sand.
• drip trays should be sand filled and set beneath all machinery to prevent the development
of oily, slippery surfaces and, especially on pontoons to minimise fire hazards.
28.5 ILLUMINATION
• essential for night work, especially in shafts, dark corners and stairways.
• should have an even spread of light to avoid deceptive shadows and glare.
• Navigation lights may be needed on working places afloat or sighted close to the shore.
NUMBER OF EMPLOYEES
1-5 6-10 11-50 51-100 101-500
TRIANGULAR BANDAGES 1 2 4 6 8
SAFETY PINS 6 6 12 12 12
• all passenger carrying crafts, prior to use, must be registered with the above
establishments.
• are only allowed to operate within a stipulated number of passengers according to size.
• provided with the appropriate life - saving and fire fighting appliances as specified by the
regulatory department e.g.
• life lines should be long enough for the state of the tide,
height of working place above water, or for the person
being carried downstream by a current.
• all rescue boats should carry three oars or paddles to cater for losing one overboard.
• rawlocks should be removable and on retaining lines so that they can hang from the side
without being lost.
• should be fitted with grab lines and carry at least one approved lifebuoy.
• two way communication between boat and shore is always advisable.
• if night work is to take place, a powerful spotlight should be fitted.
• should be manned continuously and on patrol whilst work is in progress by experienced
boatmen trained in basic first aid.
• if possible, there should be two persons to a boat so that one is free to to attend to the
person in the water.
• the number of persons at work is periodically checked to ensure that no one is missing
• operatives work in pairs so that there is always one to raise the alarm.
• each person is trained in what to do in the event of an emergency.
rescue procedure should consist of
• a set routine to for getting persons to hospital whether for check-up through immersion in
water, or for treatment as the result of an injury.
INTRODUCTION 1
MAIN APPLICABLE U.A.E. LEGISLATION
SECTION 29
Municipalities & Agricultural Department
H&S Construction Codes of Practice
PART TWO
SECTION 29
INTRODUCTION
Since work on many construction sites is required to be done at heights which cannot be reached from
the ground, means must be provided to prevent persons from falling from their place of work and
injuring themselves; precautions must also be taken to prevent falls of tools and materials.
In most case it will be practicable to provide a safe working platform supported by some form of
scaffold or, failing this, by using a suspended scaffold or mobile work platform.
Where it is not practicable to provide a working platform, or where provisions of such a platform would
be unreasonable because of the nature or short duration of the work, personal suspension equipment
must be provided and used. As a last resort, where none of these measures are practicable or
reasonable in the circumstances, injury from falls must be prevented by the provision and use of
safety nets or safety harnesses.
This section is therefore designed to give standards, and where applicable, guidance on the provision
and use of the above.
It covers the standard types of scaffold structures and ladder access, together with standards and
guidance on mobile work platforms and use of safety nets.
• that the materials used in its construction are sound, and that the standards as laid down
in this manual are in adhered to.
• a competent person shall inspect all materials for any scaffold on each occasion before
being taken into use. Contractors shall appoint such competent persons and shall
arrange for their training as necessary.
• when tubes are supplied with a protective coating, care should be taken to protect the
coating so that the tubes do not deteriorate excessively.
• unprotected steel should not be used where the atmosphere is particularly corrosive.
Tubes which appear to be excessively corroded should be examined by a specialist
before they are used.
• split or damaged sections of tube should be cut out and discarded, all cuts being at
right angles to the tube axis.
• couplers and fittings should be examined before use. Moving parts should be free
from wear or damage and be well lubricated. Particular attention should be paid to
threads.
• scaffold boards should be inspected after each job and any showing signs of abuse,
decay or excessive warping should be discarded. End hoops, or bands, should be
replaced or re-fixed as necessary.
• where boards have split ends which do not exceed the limits specified in BS 2482,
nail plates may be used. No other repairs should be carried out and boards should not
be painted or treated in any way which could conceal defects.
• boards should be cleaned on return from site, then stacked flat, and raised from the
ground on cross battens.
• damaged boards are hazardous and therefore all forms of abuse must be avoided. Do not
use them as a base on which to stack materials, or as ramps at kerbs, or as temporary
roadways. Scaffold boards should not be used as makeshift crawling boards or for
shuttering or propping up door frames.
• boards or other components should never be dropped or thrown down from a height. The
impact resulting from this form of abuse may result in unseen but potentially lethal
damage.
29.5 DISMANTLING
Normal procedure is to dismantle in the reverse order of erection - last up, first down, at
least in the case of more complicated scaffolds, get the same team that put it up to take it
down
• all dismantling activities should be carried out progressively, reversing the erection
process. Therefore scaffolders should work along the elevation removing the
guardrail(s) and then lowering the boards from that section to the lift below. Scaffolders
MUST NOT remove the guardrail(s) from the whole elevation before lowering the
boards.
• it may be necessary to insert additional ties and in any case no ties or braces should be
removed in advance of general dismantling.
• checks should be carried out as to the stability of the structure, and platforms should be
cleared of all materials and debris before dismantling begins.
• once a scaffold is partly dismantled, all possible access to the dismantled sections
should be barred and a warning sign prominently displayed.
• all materials must be lowered carefully; surplus boards and fittings must be removed
from the platforms as the work progresses and, particularly, at the end of each day.
• tube fittings should be stacked at ground level unless the first lift has been specially
designed to support the extra loading.
• the public must be protected at all times. If necessary, barriers should be erected round
the area where scaffolding is being dismantled.
• sufficient material shall be provided for, and shall be used in the construction of scaffolds.
• scaffold construction should take into consideration the type of work, load, height, and
also weather conditions.
• timber used for scaffold shall be of suitable quality, be in good condition and have the
bark completely stripped off.
• timber used for scaffolds, trestles, ladders and folding stepladders shall not be so painted
or treated that defects cannot be easily seen.
• metal parts used for scaffolds shall be of good quality, be in good condition and free from
corrosion or other patent defect likely to affect their strength.
• all material and parts of scaffolds shall, when not in use, be kept in good condition and
kept apart from any materials or parts unsuitable for scaffolds.
• every scaffold shall be properly maintained/kept clean and every part shall be kept so
fixed, secured, or placed in position as to prevent, so far as is reasonably practicable,
accidental displacement.
• In normal use, transoms should be spaced so that the spans of scaffold boards should
not be greater than:
• transoms must be firmly fixed to ledgers or standards and be so spaced according to the
expected load and thickness of the boards to be used on the platform. (see Fig.3)
Fig.3 -
LEDGERS: TRANSOMS:
Centres not to exceed 2.0 m, Maximum spacing 1.5 m.
but base lift may be a maximum of 2.7 m
• stairs must be kept free from all obstructions - materials and rubbish, and if they become
slippery, should be cleaned or sanded as quickly as possible
• fixed with a ladder clamp to the ledger or transom near the top to prevent slipping both
sideways and outwards
Fig. 5.
No.1 GIN WHEEL – To be secured on load bearing couplers S.W.L. Clearly marked. load not to exceed 50 KGS.
No.2 GUARD RAIL – Minimum height of 910mm on all structures over 2.00m high and secured on inside of standards.
A second lower guard rail or higher toe board should be provided to limit gap to 470mm.
No.3 TOE BOARDS - Min. height 150mm fixed on all structures.
No.4 BOARDING - To be close boarded and end butted throughout.
No.5 TRANSOMS – Maximun spacing 1.5m.
No.6 TARPAULINS – To be fixed only to structures designed for their use.
No.7 STANDARDS. – Centres dependent upon duty use.
No 8 LEDGERS – Centres not to exceed 2m, but base lift may be up to 2.7m max.
No.9 TIES – Hook, Lip, physical reveal etc. to be considered individually, and B.S. requirements observed.
No.10 LEDGER JOINTS – Not more than 1/3 into a bay and be staggered throughout i.e. adjacent bays or lifts.
No.11 STANDARD JOINTS – Must not occur at same height.
No.12 STANDARD/LEDGERS – Fixed with right angle couplers.
No.13 BRACING – Ledger, Zig Zag, Dog Leg, always secured on load bearing couplers at alternate pairs of
standards. Face, Façade, Longitudinal, Wind, 45o Angle over full structure height at 30m centres
secured with load bearing couplers and joined end with sleeves.
No.14 BASEPLATES – Generally below standards, and 150mm x 150mm size.
No.15 SOLE PLATES – Use in prescribed circumstances and no smaller than 1,000cm2 beneath one standard.
Viewed from
inside
Fig. 6 - Showing the requirement for reveal ties – through ties – fixing of eyebolts and position of base plates in
order to ensure stability of scaffold.
• strong enough for the intended work and not be less than Fig.7
200mm wide if 50mm thick or less, and not less than 150mm
wide if more than 50mm thick.
• 600mm wide (3 boards) when used for persons only and not for materials.
• 800mm wide (4 boards) when used for persons and for the deposit of materials, though
there must be a 430mm passage left for persons clear of materials. This passage must
be increased to 600mm if barrows are to be used.
• 1.05m wide (5 boards) if used to carry a trestle or any other higher platform, and 1.30m
wide (6 boards) if used by masons.
Note: 430mm wide (2 boards) platforms are, however permitted on ladders scaffolds, folding
trestles scaffolds in the vicinity of a roof and suspended scaffolds, when work is light
and of short duration.
• toe boards must rise at least 150mm above the working platform.
• guard rails must not be less than 910mm, nor more than 1.15mm above the working
platform.
• if guard rails and toe boards are removed to permit passage of men and materials, they
must be replaced as soon as possible afterwards.910mm, nor more than 1.15mm above
the working platform.
Towers may be made from normal tubes or fittings, but are frequently constructed from
proprietary components.
29.11.1 foundation
• erected and used on firm ground.
• mobile towers must be used only on hard, level surfaces and fitted with wheels or castors
which should not be less than 125 mm in diameter.
• castors or wheels should be locked into the base of standards and be fitted with brakes
which cannot accidentally be released.
29.11.2 stability
Manufacturers recommendations will specify either the maximum height to which a tower
should be erected, or the maximum height to least base ratio for free standing towers. In
each case, the height of a tower is that to platform level.
For all towers, recommendations for maximum height to least base ratio are normally:-
Towers should be positioned to make the effective least base dimension as large as
possible.
• protected from tipping or sliding by being properly supported by the use of cleats or other
proprietary fittings.
• any trap door or hatch on the platform should be closed when the platform is in use.
29.11.5 access
Access should be provided either by:-
• vertical ladders attached internally to the
narrow side.
• internal inclined ladders, or inclined stairway,
• ladder sections, integral with frame members
should be climbed from the inside as illustrated
in Fig.10.
• rungs should be no more than
300mm apart and the stiles not
more than 480mm apart
• climbing using the horizontal of
end frames should not be
permitted
• the maximum recommended free-
Fig. 10 - Prefabricated tower fitted with an internal
standing height for mobile towers
ladder, fully boarded working platform
is 9.6m, and for static towers, 12m. complete with guard rails and toe boards,
fitted with outriggers to assist stability and
lockable wheels.
29.11.6 precautions during use
• ladder or trestle must never be placed on the top platform to extend the height of the
tower as this will cause instability.
• mobile towers should have their casters turned outwards to provide maximum base
dimension and brakes locked “on” when tower is in use.
• mobile towers should be moved only by pulling or pushing at the base.
• working platform should be clear of persons and materials before towers are moved.
The following types of ties are commonly used, depending on anticipated loading and the
nature of the facade.
through tie
Ledger
A tie assembly through a window or Bracing
other opening in wall. Safe working
capacity 6.25 KN. (see Fig.11)
Secured Packing
The assembly of a reveal tube with wedges or screwed fitting and timber pads, fixed
between opposing faces of an opening in a wall, together with a tie tube. Safe working
capacity (where relying solely on friction) 3.5KN inwards and outwards. Where the reveal
tube is tight behind a load- bearing feature, and there is a butt tube, the safe working
capacity is 6.5KN outwards. (see Fig.12)
Ledger
Bracing
Therefore:
1) the building itself should be examined to ensure that it is sound enough to take the
stresses involved in anchoring the scaffold and that all ledges and window sills, etc.
are strong enough to bear the load from the rakers,
Only steel tubes and fittings should be used and these must be specially checked before
use.
29.13.1 structure
• in the very simplest form of truss-out scaffold,
horizontal tubes (needles, protruding through
windows or similar openings), are anchored
within the building to vertical tubes securely
strutted between the ceiling and floor and
bearing hard against the inside wall.
• these simple truss-outs are only intended for very light work and should certainly not be
loaded with materials.
29.15.1 base
• The floor of the building has to carry the full load of the scaffold and the total weight
involved should be distributed as widely as possible.
• Floors must be examined before the scaffold is begun and if there is any doubt as to
whether they are capable of bearing the weight, they should be shored.
29.15.2 standards
• Standards on baseplates should be set
vertically in rows at not more than 2.50m
centre to centre in each direction.
29.15.3 ledgers
• Ledgers, strengthening and keeping the standards in each row equidistant, should be
fixed horizontally to the standards with right angle couplers.
• The first lift should not be more than 2.50m high; subsequent lifts should be at 2m
intervals.
• Joints in ledgers should be staggered (i.e. joints in adjacent ledgers should not occur in
the same bay) and should preferably be made with sleeve couplers. Joints should be
positioned at not more than one third of the distance between two standards.
29.15.4 transoms
• On all lifts except the top, transoms should be set horizontally and fixed to standards
with right angle couplers.
• At working platform level, transoms spaced at not more than 1.50m intervals (assuming
38mm thick boards are used) should be fixed to ledgers with right angle or putlog
couplers. In each bay one transom should not be more than 300mm from the standard.
Intermediate transoms may be removed if not supporting boards, but those next to
standards should be left in place and fixed with right angle couplers.
• Where transoms need to be doubled to allow boards to butt, they should be spaced so
that no board overhangs by more than four times its thickness or by less than 50mm.
• In larger Birdcage Scaffolds transoms may frequently need to have joints in them. Joints
should preferably be made with sleeve couplers and all joints should be staggered.
29.15.5 bracing
• A single lift birdcage is not automatically stable because of its small height. It needs
bracing just as much as a multi lift scaffold. This is normally catered for by the use of
diagonal bracing and, where the birdcage is subject to wind forces, bracing should be
provided with one brace for every six verticals in each line, with the corner panels of
each section being tied in both directions. Bottom connections of the brace must be
attached to the bottoms of the standards by swivels or to a foot tie with right angle
couplers. Foot ties should be provided at a minimum of alternative bays in each
direction.
• For multi-lift birdcages the bracing may take the form of a diagonal tube from top to
bottom, or short tubes between lifts in a zig-zag, or all of one slope in every sixth bay.
29.15.6 tying
• Where the birdcage scaffold is within or against an existing structure, it is often more
satisfactory to use the structure to afford stability. The most satisfactory detail is to
extend the transoms or ledgers to butt the walls, or push/pull fixings may be used. No
vertical should be more than 6 tubes away from a restraint point and at least one should
be provided for every 40m2 of vertical face.
• A mixture of bracing and tying may be used but both directions must be taken into
account for stability.
• The working lift should be tied and butted to the main structure at approximately every
8m.
• Other platforms may be erected at any lift in the side bays and all requirements are
similar to any normal working platform.
• Toeboards and guardrails should be fitted on the inside of standards to prevent outward
movement.
• Toeboards must rise at least 150mm and the main guardrail must be at least 910mm
above the working platform.
• There must not be an unprotected gap of more than 470mm in height in the means of
protection against a person's fall. An intermediate guardrail or other form of effective
barrier (eg brickguard frames) must therefore also be fitted. Where materials need to be
stored above toeboard height, additional boards, brickguards or similar mesh must be
fitted to prevent the fall of such material.
• The stiles should be lashed or clamped to a ledger or transom near the top to prevent
slipping both sideways and outwards.
• Ladders should be set at a working angle of 75° to the horizontal, i.e. one metre out for
every four metres of height and extend sufficiently above platform level to provide
adequate handhold at the stepping-off point. A distance of 1.05m (5 rungs) is
recommended.
• Ladders required to rise more than 9m of vertical height should have an intermediate
landing place provided -properly protected with guardrails, etc. as described above.
Toeboards are not required unless the landing place is used for the storage of
materials.
• Ledgers for the first lift may be fixed at a maximum height of 2.50m and thereafter at 2m
vertical intervals.
• Bracing Single lift - diagonal bracing to every sixth bay in each direction.
• multi-lift- either diagonal bracing from top to bottom or zig-zag bracing in every sixth bay
in each direction.
• tying by transoms or ledgers abutting surrounding structure; the use of push/pull fixings,
or with box ties around columns.
• centres to be at a maximum of 8m. There should be at least one tie for each 40m2 of
vertical surface area.
• all ropes, winches, blocks and tackle must be strong enough and correctly rigged.
• maintained in good condition and platforms prevented from swaying whilst in use.
• steel wire rope must be used for the suspension of all platforms other than lightweight
cradles.
• lightweight cradles may be suspended by fibre ropes and pulley blocks which should not
be more than 3.20m apart. (only ropes recommended by manufacturers should be used).
29.16.1 outriggers
• be long enough and strong enough.
29.16.2 counterweights
• be bolted or securely attached to the outriggers.
29.16.3 platforms
• hung clear of the building or face of the structure.
• be close boarded.
• be at least 600mm wide on all other types if used only for workmen, or be at least 800mm
wide if used for workmen and materials.
29.16.4 runways
• strong enough and in good condition
29.16.6 winches
• must have at least two full turns of rope on the drum when platform is in its lowest
position
29.17.1 suspension
• only tested wire ropes, chains or scaffold tubes may be used
• tested wire ropes should be secured to the overhead supports and to the ledgers of the
working platform as close as possible to junctions with transoms by two full round turns,
and the end held with three bulldog grips or woven or tested eye and shackle.
• platform should be close boarded and evenly set with each board adequately secured
• angle couplers and a check coupler used at each end of the hanger.
2 round
turns of
wire and 3
bulldog
grips
29.18.1 general
Suspended access equipment is most
frequently used for painting, glazing,
scaling, cleaning and light repair
work on tall buildings or structures
above busy streets. (see Fig.17)
• a temporary or permanent roof rig to which the suspension ropes and cradle are
attached.
• those which are structurally attached to the roof or top part of the building (usually
permanently installed).
• all equipment is thoroughly examined by a competent person after installation and /or
rigging and before being put into service.
• Particular attention is paid to the safety of those installing or rigging the equipment to
ensure that they are provided with appropriate means of fall prevention or fall arrest.
29.18.3 stability
All equipment relies on some form of roof rig to support the suspended platform. The
cantilevered portion of the roof rig consists of outriggers, which may be metal joists, timber
poles, scaffold tube framework, etc.
The following are the main points to consider when assessing the stability of any suspended
access equipment:
• roof rig should be designed by a competent engineer who should ensure that that the
supporting structure is able to withstand the imposed loading.
• when traversing tracks are used they should be set as nearly horizontal as possible.
• where counterweights are used as the means of holding down the inboard end of an
outrigger they should be marked with their weight and firmly attached to the outrigger.
(Bags of sand, cement etc. are not appropriate counterweights).
• all outriggers must be strong enough to carry the weight of the suspended platform and
its load, with the appropriate safety factor.
decking
Decking of the platform, which must be at least 600mm wide, should have a sound, slip
resistant surface and should be fixed so that it cannot be accidentally displaced. Except to
the extend necessary for drainage, the decking should be close – boarded, or plated.
Where it is not practical to fit a safety rope, each operative should be provided with a
suitable safety harness and lanyard of appropriate length which should be attached to an
independent safety line secured to a safe anchorage of the building.
The power point should be accessible at all times, and, when work is in progress, there
should be a notice clearly displayed to warn that power must not be switched off.
• looped and secured at roof level to prevent any risk of them being pulled out of their
sockets.
• cables and connections should not be allowed to lie in gutters where water can collect.
• pendant cables must be robust and of adequate length to allow for planned movement of
the platform.
Provisions must be made for winching operatives to safety in the event of a power failure.
All control units should be so marked that there is no confusion as to the purpose of various
controls.
29.18.7 operation
Suspended access equipment must be operated strictly in accordance with manufacturers
recommendations. It is recommended that the equipment is checked daily.
Main requirements:
• working platforms should be raised and lowered with care so thaat they remain as near
horizontal as possible.
• mobile roof rigs should not be moved whilst operatives are on the platform.
• when work is being carried out from the platform , or it is left in place between periods of
work, it should be tied to each end of the building to prevent undue movement.
• when left in position unattended, care should be taken to ensure that unauthorised
persons cannot easily reach trailing ends of suspension or safety ropes. Similarly, all
electrical gear should be out of reach and effectively isolated
• suspended access equipment should only be used for the purpose for which it was
intended. It should never be used for transferring persons from place to place.
• platform and equipment should be regularly washed down (taking care to prevent
wetting any electrical equipment).
• Precautions for the protection of the public, such as the provision of ground level bariers,
must always be considered in the use of suspended access equipment
• may be used only where the work is such short duration as to make all other forms of
suspended platforms not reasonably practicable.
• all ropes should be thoroughly examined before use for sign of wear.
• in use, fall rope should always be maintained under, or around the cleat to act as a break.
T O
Securely fixed to
support of adequate
strength.
Hook either
moused or fitted
Single sheave with safety catch
pulley blocks.
C
Chair to
Tying off point B.S. 2830
for handline.
Smaller mesh 12mm-19mm, intended to protect those below from falling objects. (see
Fig.20)
• When erecting nets in the vicinity of electricity lines or overhead power cables, the
appropriate authority should be consulted before work is commenced.
• nets can be outrigged on scaffolding provided that the scaffold structure is securely tied
into a building or similar.
• a safe exit from the net must be provided for anyone who falls into it.
• date of manufacture.
• maximum distance below the working height at which the net is designed for use.
• type of net
∗ mesh
∗ border cord
∗ under test
• height of drop withstood and deflection at centre when proof net tested.
29.20.6 storage
• wet nets should be dried naturally.
• nets should not be stored in a wet state (risk of rot with natural fibre nets)
• storage cupboards to be well ventilated (nets hung if possible)
• nets should be turned periodically to allow air circulation.
Note: Safety nets are intended to save lives and prevent injury; they are not
receptacles to catch unwanted items.
There is a number of differing types of MEWP. They can be classified according to:
Most have hydraulic stabilisers and are stationary when in use. Some small platforms can
operate off locked-out suspension systems allowing low speed travel with the work platform
elevated.
trailers
Designed to be towed on the highway. Usually come with low capacity range. Most have
manually deployed stabilisers of the screw jack type and are stationary when in use.
self propelled
Generally vertical lift only. May be fitted with outriggers, depending on size and height to
which lift extends.
Gives direct straight line approach to the point of work but has a limited ability to clear
obstructions between the vehicle and the point of work.
Fig.26 - combined
1. If outriggers are fitted, check they can be fully extended in the working area.
3. Check the ground is firm and will support loadings. Use adequate packing if necessary
under outriggers. Avoid basements, cellars, sewers, drains, manholes, old trenches,
joints in concrete, and cracks.
4. Only trained persons should be allowed to operate a MEWP. Operators should have
received training for the relevant class of machine and, in addition, should receive
familiarisation training for the particular make and model to be operated. Such
familiarisation training is typically provided by plant hire companies when a MEWP is
delivered to site. It does not constitute adequate training in itself.
5. Safety harnesses should be worn at all times by personnel working from the platform.
Harnesses must be attached to purpose-designed anchorage points (if provided) or
other suitable anchorage points as indicated in the manufacturers' instructions. Note that
the top guard-rail of the working platform may not be suitable as an anchorage point.
6. The safe working load must be clearly marked at the base of the machine and on the
working platform. The load specified must not be exceeded. Care needs to be taken to
reduce the build up of debris and material on the platform. Telescopic and articulating
machines are normally designed to carry operators and tools only. Scissor lifts may have
the capability to carry some materials. Manufacturers' instructions must be followed.
7. Persons should not leave the working platform whilst in an elevated position, nor
should materials be transferred.
8. Step ladders or hop-ups must never be used on the working platform to gain extra reach
or height.
9. MEWPs must only be used within the manufacturers recommended wind speeds. This
may necessitate a wind speed indicator being available.
10.If MEWPs are self-propelled, the operator must walk the intended route to identify any
hazards before commencing the operation. Travelling on inclines must only be carried out
within the limits specified by the manufacturer. Most MEWPs have very low gradient
tolerance and are fitted with tilt alarms to warn when the limits are exceeded.
11.MEWPs are fitted with emergency (auxiliary) lowering controls and an emergency stop
switch. Before using a MEWP the operator(s) and another responsible person on site
(who is not working on the platform) must know how to use the emergency controls.
12.On completion of the work, the MEWP should be parked in a designated area. It should
never be left in a raised position. The MEWP should have the engine/ motor switched off
and the key removed.
2. Check fuel, water and oil levels and that batteries are fully charged. Ensure batteries are
secure, clean, free from corrosion and electrolyte level is adequate
3. Check the machine starts and that the emergency stop button (engine cut-out) works.
4. Check that tyres are free from significant damage and are inflated to the correct pressure.
Check that wheel nuts are in place and properly tightened.
6. Check that the hydraulic system is free from leaks and that cables are in good condition.
7. Check that pins and retainers are in position and in good condition.
8. Check that signs identifying the controls, SWL, crush points, etc are in place and
readable.
9. Check that all powered movements for telescoping, raising, lowering and slewing are in
good working order.
10.Check that emergency lowering controls are fully functional. Always refer to
manufacturer's handbook.
1. Check that the platform structure is in good condition, clean and free from grease and
dirt, and that cage door locks are fully functional.
2. Check that decals identifying the controls, SWL, harness anchor points, maximum wind
speeds, etc are in place and readable.
3. Check that all powered movements for telescoping, raising, lowering and slewing are in
good working order.
6. Check that the steering controls function correctly in forward and reverse.
7. Test brakes to ensure that they are working efficiently in forward and reverse.
8. For machines designed to travel while the platform is raised, check that the "drive speed
is restricted when the platform is in the raised position.
NB When carrying out these checks operators must not work under a raised boom or
platform unless movement has been prevented by means of suitable locking devices.
ERECTION OF STRUCTURES
INTRODUCTION 1
MAIN APPLICABLE U.A.E. LEGISLATION
SECTION 30
Municipalities & Agricultural Department
H&S Construction Codes of Practice
PART TWO
SECTION 30
ERECTION OF STRUCTURES
INTRODUCTION
The erection of structures can be both difficult and dangerous. Many fatal or serious accidents occur
during the erection process, the principal cause being falls from heights, either from working positions
or whilst gaining access to them. Other accidents occur because of structural instability during
erection and whilst handling, lifting and transporting materials.
This section of the manual, therefore, is designed to give guidance on the correct method of erecting
structures by establishing safe erection procedures and implementing them through effective
management control.
For example, instead of assuming that construction work will be carried out insitu at height, it
would be better if the work was designed to be prefabricated in a factory, cast or assembled
with much greater safety on the ground at the site, and subsequently hoisted into position.
If the work can incorporate safety provisions such as edge protection or access provision, so
much the better. In this way the designer can eliminate some of the risks to health and safety
through the design and perhaps, also contribute positively to the quality of the completed
structure.
It is important to realise that the general term “design” can refer to all stages, from concept
through to main structural design and detailing. This is relevant to design for both permanent
and temporary works.
Planning for safe erection should commence at the initial design stage with designers taking
into account the need for, and the practicality of, safe methods of working during erection.
The extent of detail in a method statement will depend upon the size and/or complexity of
the work. Before work commences on site, outline proposals produced at tender stage
should be developed into a method statement.
• erection monitored to ensure that the planned sequence of operations is not deviated
from in any way.
• special requirements relating to the safe erection of the structure should be highlighted
at the pre-contract stage, (e.g. the need for temporary bracing/guying or the use of
mobile access platforms).
• site conditions
• ground conditions
Checklists for the production and checking of method statements relating to steel
erection, pre-cast concrete and timber frame erection are provided at the end of this
section.
This is particularly helpful for single storey work, when fixing sag bars. Good vehicular
access on to the hard standing ground should also be provided, and ground loadings and
vehicle turning circles must also be taken into account.
A sound foundation is necessary for each column and should be capable of accepting both a
vertical load and also the additional horizontal thrust which is developed as soon as
temporary props have been removed.
Pre-cast frame columns are usually inserted into sockets cast into the foundation blocks and
consequently are required to be held temporarily in place after alignment. Wedges and
props are used for this purpose until the column has been made secure by grouting. Other
types of pre-cast columns incorporate a steel base plate, similar to the base of a
prefabricated steel column.
• access to erection areas, with regard to adverse ground conditions likely to contaminate
the erector’s footwear and increase the risk when aloft.
• restricted access to, and on, the site due to road alignment which may limit the size and
weight of structural members and plant, including cranes.
• restricted space for erection, maneuvering, storage and, if required, for on-site pre-
assembly manufacture of fabrication, low ground bearing capacity which may be due, for
instance, to made-up ground, or existing underground services or structures.
• proximity and condition of other buildings, roads, railways etc., which may affect the
planned method of erection and craneage.
• area of the site affected by erection operations should be designed as a restricted area.
• toxic gases, chemicals, fluids or dust emitting from processes on or near the site.
• all fabricated units should have a distinctive mark identical to the erection drawings, in
order to ensure that structures are correctly assembled.
cranes
Detailed guidance on types of cranes most commonly used in construction processes and
on the safety requirements applicable are given in (see Pt 2 section 19). – Cranes & Hoists
manual handling
Care should be taken when manually handling components. Erectors should be trained in
the principles of manual handling, (see Pt 2 section 8) – Manual Handling.
• will normally be slung by the use of chain or flat slings in a conventional manner.
• in the case of concrete units, it is not safe to attach slings to projecting reinforcing steel.
One of a number of types of proprietary lifting devices cast into the concrete, should be
used.
• it is essential that the manufacturer’s instructions regarding installation and loading are
followed
• pre-cast units may have to remain attached to the crane until they are secured by
temporary props. In such cases, proprietary remote control devices, which can be
operated by the crane driver or the fixing contractor’s supervisor when the unit is safely
secured, may be valuable.
slinging
sling release
slinging materials
• on ground which is capable of withstanding loads imposed by the stored materials and
plant used in the area (investigation should include a check for the presence of
underground services in order to prevent damage from imposed loads),
• arranged so that clear access and lines of sight are provided and maintained between
stacks of components.
• provided with artificial lighting and weather protection, where appropriate, to aid handling.
stacking
Matters which should be taken into account when stacking or de stacking components
include:
• adequate supply of timbers, battens and wedges, which should be of suitable size and
strength.
• components used to aid erection should be stacked on suitable timber battens and
packing pieces.
• not brought into contact with the ground, thereby preventing mud deposits which could
present a slipping hazard,
• when fastenings may be incomplete, for example, in course of lining up and adjustment
of level,
• when the stage of completion of permanent work (for example brickwork, concrete, etc)
on which the stability depends is inadequate, or when the permanent work has not
developed adequate strength.
• when the structure or parts of it may be subject to construction loads for example - due
to impact, stacking of parts, and lifting or freeing of components which may have
become inadvertently wedged in position.
anchor points:
• should be such that they are able to resist any force likely to be imposed upon them.
• any movement of an anchor should be reported immediately and prompt remedial action
taken.
• steel cables for anchorage purposes should not enter the ground unless suitably
protected.
• fastening of guy lines to anchorages in the ground should be carried out using chains or
steel bars or sections.
• screw type anchors should be used in accordance with the manufacturer’s instructions.
Various means of temporary access may be used in the erection of structures, and type of
equipment to be used must be carefully considered in the preparation of the method
statement.
platforms
they may be used in an inclined position for general access to heights, but they require a
firm base and must always be securely fixed; means of fixing, e.g. lanyards, should be
permanently attached to ladders.
ladders
in concrete structures, ladder fixings may be incorporated into the columns. Ladders may
also be used vertically for access up columns; they should be fixed to columns prior to
erection and must be capable of safe removal after erection. All ladders must be provided
with safe landing places no more than 9m apart
General guidance on the safe use of ladders is given in (see Pt 2 section 19). – Scaffolding
and Working Platforms.
holes in floors
where any hole is left in a floor through which a person may fall, it must be provided with
guardrails and toe boards or; alternatively, it must be covered over. Such covers must be
strong enough for the purpose and either be secured in position or marked to indicate its
purpose.
30.5.3 scaffolds
tower
used for making low level connection where the cost of powered plant would be prohibitive.
Further details on tower scaffolds can be found in (see Pt 2 Section 29).- Scaffolding
independent scaffolds
may be used in timber frame or panel construction, or for the construction of ladder access
towers.
Further details on independent scaffolds and safety requirements can be found in (see Pt 2
Section 29). - Scaffolding.
purpose-built platforms
Where the above requirements are not met, access of short duration only may be
permitted by the following means:-
beam straddling
where straddling is not possible, the practice of side walking the beam, with both hands on
the top flange and both feet on the same side of the bottom flange, is permitted provided
that:-
Further details the use and safe installation of safety nets can be found in (see Pt 2 Section
29) –Scaffolding (Safety Nets).
safety harnesses
This can be achieved, for example, by the use of a taut steel wire rope set to run along the
beam. It should be stressed that any anchorage must be capable of withstanding the
likely impact loads. Where movement along a beam is necessary, then a fixing for a safety
harness may be achieved by the provision of additional holes at specific points on the steel
and the use of a proprietary device such as a girder grip. (see Fig.8)
General
name(s) and address(es) of the contractors involved.
name and address of the site to which the method statement relates.
names of the supervisor / foreman and appointed safely adviser and arrangements for
monitoring the work.
provision and maintenance of a safe place of work and means of acces/egress including:
provision and maintenance of a safe place of work and means of access/egress including:
name and address of the site to which the method statement relates.
names of the supervisor/foreman and appointed safety adviser and arrangements for
monitoring the work.
DEMOLITION
INTRODUCTION 1
MAIN APPLICABLE U.A.E. LEGISLATION
31.1 TENDERING 2
31.2 DEMOLITION SURVEY 2
31.3 PREFERRED WORK METHOD 3
31.4 PRE-CONTRACT ACTIVITY AND PRECAUTIONS 3
31.5 SEQUENCE OF DEMOLITION 5
31.6 DEMOLITION HAZARDS 6
31.7 DEMOLITION TECHNIQUES 8
31.8 SAFETY PRECAUTIONS FOR SPECIAL STRUCTURES 13
31.9 TRAINING AND COMPETENCE 14
SECTION 31
Municipalities & Agricultural Department
H&S Construction Codes of Practice
PART TWO
SECTION 31
DEMOLITION
INTRODUCTION
Demolition can not only be one of the most dramatic operations in the building/construction industry, it
can also, by its very nature, be one of the most dangerous.
Demolition work varies very widely from the controlled collapse of large structures from using
explosives, mechanical plant and even down to hand demolition of walls.
Demolition operations must only be carried out under the immediate supervision of a foreman with
personal experience of the work, or, by men who have the necessary experience and training on what
safe methods to adopt.
31.1 TENDERING
31.1.1 provision of information
The client has duties to provide information, where necessary, after making reasonable
enquiries, which will enable them to ensure the preparation of the initial health and safety
plan. This information could include details of the construction of buildings, plant in the
structure and known hazards such as any contamination of the structure, plant, or land by
current or previous use.
The health and safety plan should include sufficient information on which demolition
contractors may base their tenders.
• condition of structural members and the • health hazards, such as lead dust or
contribution of floors, roofs, walls, etc. paint, residues from previous
processes, or contaminated land etc.
• suitable access for the proposed method of
demolition and vehicle access for the
removal of waste.
• deliberate controlled collapse, which minimises work at heights and limits exposure to
such danger.
• when work cannot be safely carried out from part of the building or structure, working
platforms should be provided.
Where it is not practicable to provide such platforms, safety nets or safety harnesses should
be used. Guidance on the provision of working platforms and safety nets is given in Pt 2
Section 29, and safely harnesses in Pt 2 Section 12.
31.4.2 notifications
Demolition Contractor may be required to notify utilities such as ADWEA, SPD, ADGAS. etc.
to request for the following information:
• drains and sewers to be sealed to prevent vermin gaining access to the site.(detailed
plans where possible).
• arrangements for the isolation or diversion of overhead or underground services,
Outside working hours, debris at ground level should be cleared, excavations should be
fenced, vehicles and plant effectively immobilised and electricity and gas supplies isolated
or enclosed and locked.
The assistance of a competent analyst may be required to identify residues, carry out air
monitoring and assess whether pockets of contamination remain. Any residual flammable
material must be rendered safe by, for example, cleaning, purging or the application of an
inert gas.
Where it is necessary to enter plant for cleaning or assessment purposes, the use of
breathing apparatus may be required, and a strict permit-to-work system should be
employed. (see Pt 2 section 11)
The fittings for any electric lighting used in such circumstances must be suitable for use in an
explosive atmosphere and conform to BS 5345: Electrical apparatus for use in potentially
explosive atmospheres.
In the case of mechanical demolition, the design of steel framed, reinforced concrete and, in
particular, pre-stressed concrete buildings or structures, may also determine the overall
sequence; the design will certainly determine the extent of any pre-weakening that can be
done prior to a deliberate collapse.
• a radius of 6m, or half the drop height (whichever is the greater), should be used to
determine the restricted area to be kept clear
• a space of 6m minimum width from the face of the building to be demolished should be
allowed for the operation of cranes, grabs, balling machines, pusher arms and similar
equipment.
• If wire rope pulling is used, a distance of three quarters of the exposed length of pull rope
should be allowed an either side of the rope, and also behind the winch or pulling vehicle.
• when tall structures are being felled, a distance of not less than twice the total height
should be allowed along the proposed line of fall to cater for parts coming free in flight, or
bouncing and rolling on impact.
• on slender structures, a 20 degree arc either side of the line of fall should be clear of
obstructions, and an area of radius not less than twice the total height should be cleared
of persons before the actual felling.
In demolition, it may not be practicable to control these hazards by means such as exhaust
ventilation and emphasis should therefore be placed on the following:-
• segregation of workers,
• ensuring that airborne hazards do not escape from the site to affect members of the
public.
lead
Lead as a toxic dust or fume arises from cutting and burning steelwork covered with lead
based paint and the handling of old petrol tanks from filling stations.
The cutting of steelwork often has to be carried out within the confines of a building, where
the dust and fume has little chance to disperse and there is risk of a very rapid absorption of
lead, Under these circumstances, exposure should be assessed.
Where information on lead-in-air concentrations from a particular type of work is lacking, air
monitoring should be carried out. Assessment should be made when exposure is likely to be
at a maximum level. Monitoring may not be necessary for work where there is a clear need
for the wearing of respiratory protective equipment but, if other persons are working, or likely
to be in the vicinity, air monitoring may still be needed to ensure that such persons are not
exposed to risk..
Where persons are likely to be exposed to concentrations above the lead-in-air standard,
suitable approved respiratory protective equipment must be provided and used.
Arrangements should be made for such equipment to be cleaned and stored at the end of
each shift, and to be regularly maintained.
asbestos
Asbestos dust will be generated whenever demolition involves work on asbestos in sprayed
coatings, thermal and acoustic insulation materials, fire resistant walls and partitions,
asbestos cement sheets, or flooring materials.
Asbestos insulation or coating should be removed by specialist contractors only, and,
where possible, before any other demolition work is started.
Clients should ensure that contractors have relevant experience and knowledge of the
necessary precautions when dealing with Asbestos.
PCB’s
PCBs (Polychlorinated Biphenyls) are toxic substances which were used as dielectric filler
fluids in electrical transformers and capacitors and are still used in some refrigeration and
heating equipment.
Drainage of PCB fluid must be carried out in an open or well ventilated area and full
protective clothing including respirator and chemical eye protection, must be worn.
Note: Waste PCB fluid must not be disposed of by pouring into drains, on to land, or by
burning other than in a licensed incinerator.
Entry to and work in confined spaces should be controlled by pre-planned “permit” systems
and backed up by a rescue procedure.
For further information on entry into Confined Spaces, (see Pt 2 section 21).
31.6.3 noise
Demolition plant, such as compressors and concrete breakers, frequently create noise
“levels” in excess of 100dB(A). Jobs likely to expose workers to an 8-hour noise dose above
90 dB(A) should be identified and arrangements made to ensure that ear muffs or plugs are
provided and worn.
Machines, were appropriate, should be marked with a prominent notice to warn that
operators should wear ear protection.
Ear protection must be suitable for the circumstances, supervision and training in its care
and use must be provided and there must be adequate facilities for its maintenance and
storage. Further guidance on Noise is given in Pt 2 section 3.
31.6.4 vibration
Pneumatic drills and breakers are among many hand held tools likely to give rise to vibration
white finger, particularly in cold weather. Keeping warm with waterproof and wind resistant
clothes and gloves, and restricting the time which individual workers operate such tools, can
reduce the risk of serious disability.
Plant and tools should be selected, as far as possible, to minimise the harmful effects of
vibration or jolting motions.
• piecemeal demolition, using hand held tools, or machines, to reduce the height of the
building or structure gradually, or
• deliberate controlled collapse, demolition being completed at ground level.
Work on roofing sheets should be carried out from a FIG.2 - Example of a type of Rubbish
Chute commonly used in both
working platform, or crawling boards spanning the demolition and building
purlins. In many cases, demolition of asbestos operations.
cement sheeting may be achieved more effectively
by properly controlled machine methods, with a fan
of sprayed water onto the sheeting to control dust
emmission.
work on roofs.
A safe place of work must always be provided for hand demolition; the top of an unprotected
wall is not a safe place of work. Where scaffolding provides a working platform, it should
normally be dismantled progressively as the building is demolished, so that scaffold tubes
do not project mare than 3m above the work. Scaffold towers should not project above the
work more than one lift.
When scaffolding is tied to a building, additional ties may need to be provided at a lower
level before the upper ties are removed as the demolition proceeds. The working platform
should never be more than 6m above the highest row of ties. For further guidance on roof
work see Pt 2 section 32, and for use of scaffolding and mobile towers see Pt 2 section
29.
In all work on roofs, such as the recovery of second-hand tiles and slates, edge protection
must be provided where possible, or safety harnesses used.
Each main structural member, including roof trusses, should be supported by crane or
temporary props whilst the ends are unbolted or cut. Care should be taken due to the
possible springing of members when load restraining connections are removed. Structural
members and trusses should be carefully lowered to ground level.
Suitable working platforms, e.g. man-riding skips, must be provided for the cutting and
disconnecting of members at height. Existing structural steelwork is not normally suitable for
use as a working platform. Properly anchored safety harnesses should be used where
necessary.
Timber joists spanning the beams of steel framed buildings may be severed by chain saw.
Where material is allowed to drop to a lower level, the area below should be sealed to
prevent anyone entering.
31.7.2 piecemeal demolition by machine
Roof structures supported on wall plates should normally be demolished to wall plate level by
hand. Where the building to be demolished is attached to another structure, the two
properties should be separated by a minimum of 1m, using hand methods, before machine
demolition begins.
Only the machine operator and a trained banks man should be allowed within the restricted
area of 6m from the part of the building being demolished. The cabs of all machines should
be strong enough to protect the operator against the fall of debris; in particular the
windscreen and any roof light should be of shatterproof material and guarded by a grille of
steel bars or substantial steel mesh.
balling
• minimum effective weight of ball should be selected; a weight of one ton or less is often
adequate, and In order to reduce shock loading, ball may be suspended from a rubber
tyre shackled to the end of the hoist rope; in this case, a restraining chain must also be
fitted to ensure the ball cannot become detached in the event of tyre failure.
Where a crane is to be returned from demolition balling duties to lifting duties, it should first
be subjected to a thorough examination which should include:
• detailed inspection of the parts of the crane which may have been subject to damage or
deterioration during the balling operations.
Note: machines with fly jibs or telescopic booms should not be used.
impact hammers
Impact hammers may have a track or wheeled mounted chasis with an articulated boom
which can be vibrated by hydraulic or pneumatic power and is fitted and used to walls or
columns in courses not greater than 600mm in depth. Steel reinforcement should be cut
separately as necessary.
shears
Prior to a deliberate controlled collapse, after loads such as furnishings, plant and machinery
have been removed, it may be possible to weaken some structural elements and remove
those which have become redundant. This pre weakening must be carefully planned and
take into account the ability of the remaining elements to resist wind or impact loads until the
intended deliberate collapse. The indiscriminate cutting of steel members until the structure
collapses (“Cut and run”), is highly dangerous.
Steel structural elements are normally pre weakened by cutting, wholly or partially, through
the section, with a gas torch or thermic lance. For small sections, a cutting disc may be used.
A variety of different types of cut may be used to suit the planned method of collapse.
removing selected internal walls and floors where they join external walls.
Reinforced concrete walls may be similarly pre weakened by breaking out the concrete along
the outline of the required opening and cutting away the exposed steel. Selected concrete
columns may be removed completely, or weakened by exposing some of the reinforcing
bars,
Ropes should be attached to the structure before pre weakening is carried out; mobile work
platforms, or other suitable equipment, may be needed to gain access, and be in good
condition and not less than 38mm circumference
When used with winches of sufficient rope capacity and tractive effort, an adequate steel cab
or cage should protect the winch or vehicle operator which should be at a minimum distance
from the building of one and a half times its height, or twice the height where parts of the tap
of the structure may separate.
Note: Brick or masonry buildings over 21m high should not be demolished by rope pulling.
prestressed concrete
A pre stressed concrete component has pre compression applied by steel wire, cables or
threaded bars tensioned to counteract the tensile forces induced by the working load.
chimneys
When a chimney is demolished by hand, debris may be dropped down the inside and
cleared at intervals through a narrow opening cut at ground level. Where practicable, a
working platform complying with the requirements in Pt 2 section 29 must be provided and
used.
Name and address of the site to which the method statement relates.
Names of the supervisor/foreman and appointed safety adviser and details for monitoring the
work.
Details of any scaffolding required including name of scaffolding firm, details of Municipality
Licenses required.
How safe access/egress and a safe place of work will be provided for each operation.
Note
This checklist is intended to aid the production and approval of method statements. It is not an
exhaustive list of every possible issue that may need to be addressed for any given task.
INTRODUCTION 1
MAIN APPLICABLE U.A.E. LEGISLATION
SECTION 32
Municipalities & Agricultural Department
H&S Construction Codes of Practice
PART TWO
SECTION 32
INTRODUCTION
Working on a roof can be dangerous. Falls account for more deaths and serious injuries in
construction than anything else. Nearly half of them are from or through roofs and frequently involve
fragile materials. Any fall from a roof inevitably involves serious injuries.
The risks are substantial however long or short the work. Many have been killed who only meant to be
on the roof for a few minutes ‘to have a quick look’.
The information in this section is aimed at people who actually carry out roof work or are directly
responsible for managing or supervising it, and sets out key safeguards
falls occur:
• from the edges of roofs
• through gaps or holes in roofs
• through fragile roof materials and roof lights
In addition, many people have been seriously injured by material falling or thrown from roofs.
Accidents occur not only to those building roofs, but also to people maintaining, cleaning, demolishing
and inspecting them.
Any work on a roof is high risk. High safety standards are essential however long or short term the
work is. The nature of the precautions needed may vary from one job to another, but not providing any
safeguards is simply unacceptable.
Max. Gap
Max 910mm. 910mm.
To raise the
Scaffold line of the
Board roof slope
with a min.
height of
150mm.
Guard rails toe boards and covers may be removed to allow access for men and materials,
but must be replaced as soon as possible. This does not apply to demolition work unless
it is left unattended.
If there is no parapet or similar barrier against falling, edge protection must be provided. This
may take the form of standard guard rails and toe board or, providing nobody will approach
the edge of a barrier, set back from the edge.,
Where work on the leading edge is actually in progress, guard rails may be removed or left
off, subject to the requirements that:
Work on a sloping roof with a pitch of more than 30 degrees or between 10 degrees and 30
degrees if slippery, should:
• be done using crawling ladders or boards which must be securely fixed to prevent
slipping.
• employ either a suitable catch barrier or platform erected at the eaves, or a two board
430mm wide working platform with guard rails.
Note: this applies to any work on a sloping roof including access and egress to other work
places.
Ridge Iron.
Hip Iron.
Fig.5 - Showing roof ladder fitted with wheels–to Fig.6 - Showing ridge and hip irons which should be
facilitate the ladder being placed in of sufficient size so that when in position,
position over roof ridge. they are clear of the ridge and tiles.
• properly supported
• securely fixed to the sloping part of the roof over the ridge. Ridge hooks must not bear
on ridge tiles or capping tiles.
If the spacing of the battens is greater than 400mm and persons could fall through, roof
ladders or crawling boards must be used.
Substantial - looking roof cladding can be dangerously corroded. Surface coatings or dirt
may conceal the fragile nature of the material, giving an appearance of solidity to glass,
plastic, etc.
When working on or passing across fragile roofing materials, crawling boards must be used
so that the workman's weight is on the board, never on the fragile roof sheeting, various
plastic materials are particularly brittle and shatter without warning. At least two crawling
boards should be used, one to support the workman while the other is moved to a new
position.
The practice of trying to 'walk the line of the bolts' is dangerous and akin to walking a tight
rope. Where walkways are not provided, a safe system of work such as that described
above must be employed.
Work involving the handling of sheeting and cladding requires extra care in windy conditions,
when a sheet may act like a 'sail' - causing the person holding it to lose balance.
32.3.1 walkways
Valleys, parapets, gutters or channels etc. where access is
required, must be provided with suitable guardrails or the
fragile material should be suitably covered to prevent any
possibility of anyone falling through,
(A general check list for working on roofs, also for producing a method statement for
working on fragile roofs can be found at the end of this section)
Further details re types of harnesses and belts available can be found in (see Pt 2
Section 12) - PPE, and details regarding safe anchoring points etc. can be found in (see Pt
2 Section 30). –Erection of Structures.
Further details re the safe use of ladders, mobile and independent scaffolds can be found in
(see Pt 2 section 29). – Scaffolds and Working Platforms.
It may also be necessary to lay sheeting or boarding to prevent material falling through gaps
in the working platform, or between working platform and the building.
Means of protecting fragile materials which persons work near or pass close to.
Arrangements for protection against falls from the edge of the roof and other workplaces.
Do the roof battens provide safe hand and foot holds? If not, are crawling ladders or boards
provided and used?
Are suitable barriers, guard rails or covers, etc provided where people pass or work near fragile
material such as glass. Plastic and roof lights?
Are people excluded from the area below the roof work? If this is not possible, have additional
precautions been taken to stop debris falling onto them?
Details of any hazardous substances and arrangements for safe working and disposal of waste.
Note:
This checklist is intended to aid the production, and approval of method statements. It is not
an exhaustive list of every possible issue that may need to be addressed for any given task.
REFURBISHMENT
INTRODUCTION 1
MAIN APPLICABLE U.A.E. LEGISLATION
33.1 PLANNING 2
33.2 PRE TENDER HEALTH AND SAFETY PLAN 2
33.3 STORAGE 3
33.4 WELFARE FACILITIES 3
33.5 ACCESS 3
33.6 SCAFFOLDING AND ROFWORK 4
33.7 TEMPORARY WORKS 4
33.8 WORKING IN PARTIALLY OCCUPIED BUILDINGS
AND ADJACENT TO THE GENERAL PUBLIC 5
33.9 SERVICES 6
33.10 LIFTS 6
33.11 RUBBISH CHUTES 6
SECTION 33
Municipalities & Agricultural Department
H&S Construction Codes of Practice
PART TWO
SECTION 33
REFURBISHMENT
INTRODUCTION.
The refurbishment of buildings can be complex whatever the age of the building. In older buildings, all
or part of the building, may be the subject of strict control under Planning Legislation.
Very detailed preparation and planning will be necessary where extensive shoring-up operations are
to be carried out and professional advice from a structural engineer or a surveyor should be obtained
before any structural members are removed.
Temporary supports will invariably be required, or loads transferred to other areas to avoid an
unplanned collapse.
Buildings being refurbished may be located between, or form part of a complex of other buildings
which must not be disturbed. This creates additional problems relating to the space available and the
possibility of nuisance to occupiers. Every effort must be made to establish good working relationships
with existing occupiers and neighbours.
Many more contemporary buildings are now reaching a stage where major refurbishment is
contemplated. This is particularly relevant in the case of commercial buildings where work patterns
have changed and the provision of extensive services is seen as a particular need. Many of these
buildings were speculatively built and little, if any, detailed record of their construction exists. Great
care is therefore needed in planning the work. There are often hidden dangers in their construction
that need to be thoroughly investigated at an early stage.
33.1 PLANNING
The primary rule in planning the refurbishment of old buildings is that the fabric of the
building cannot be assumed to be sound. In addition to the likely differences from modern
construction, it must be realised that maintenance work and previous refurbishment may
have been carried out over the years.
Assumptions should not be made regarding the load bearing elements of the structure and
in particular supporting members e.g. joists, since these may have been replaced in a
completely different format to the original structure. Planning will invariably be much more
complex than is the case with a new construction.
Work should not start until an in depth survey has been carried out to determine the real
extent of deterioration and other hidden hazards which may not be known at the tender
stage. The building fabric may have been covered by plaster, panelling, floor coverings etc.
The need for further demolition and remedial work due to damp, dry rot, presence of
asbestos, etc. may only become apparent as work progresses. The health and safety plan
will therefore need to be reviewed and updated at each stage of the work after close
consultation between the principal contractor, designers and other contractors. The planning
supervisor must be advised of these changes.
Each aspect of the refurbishment work needs to be carefully planned and detailed method
statements produced where appropriate. It is particularly important that any demolition
should be covered by a method statement which takes into account the integrity of the
remainder of the building, any temporary works required and a checking or monitoring
system for the falsework before demolition takes place.
The health and safety plan should also co-ordinate all aspects of the work in order to
achieve a correct sequence of operations. Plant and equipment must be positioned in its
correct place, especially since space may be limited and access may not be ideal.
33.3 STORAGE
Storage facilities are usually very restricted. However; adequate and proper facilities must be
provided for the storage of items such as highly flammable liquids and LPG which are a
potential fire hazard Preplanning of the storage areas, together with the provision of
appropriate Floor loading notices, is necessary at the start of the contract. Where necessary,
materials should be stored off site and only the minimum quantities called in as required.
Adequate and suitable fire fighting equipment must be provided and supervisors must be
made aware of the dangers of carelessly stored materials or overloaded floors, resulting
from the accumulation of debris or temporary loads.
33.5 ACCESS
In many situations, there is only limited access to the site, particularly in congested town and
city areas. It is essential, at tendering stage, to investigate the means of access required
during the contract and the provisions to be made for the unloading of materials, plant and
equipment and the removal of rubbish.
In particular the safety of the public, occupiers, and any adjacent occupiers needs to be
considered, also allowance must be made for any fans, hoardings, safety netting or gantries
required.
Safe access from floor to floor is paramount during the course of the works. If the building
has only a single staircase access to upper floors and this is to be replaced or repositioned,
then consideration needs to be given to its provision or repositioning as a first priority.
A ladder access tower should be erected as a temporary measure only. If this cannot be
achieved then a temporary external scaffold staircase should be provided particularly where
the existing staircase is suspect as to strength.
Consideration should also be given to the provision of a passenger/goods hoist where there
are more than three floor levels.
On contracts where major roof works are required, it may be necessary to install a
temporary roof, with or without side sheeting. This decision has to be made at an early
stage, preferably prior to tendering and the scaffold designed to take the roof loads, wind
loads etc. Specialist advice should be sought for all but the simplest of structures.
Further, there are difficulties in tying the scaffold into a possibly unsound structure.
Moveable ties (through reveal, or box ties) rely on the strength of the structure for their
security. Where non-movable ties (e.g. drilled anchors) are to be used in unreliable material,
it is essential that tests are carried out as recommended by the anchor manufacturer.
In order to ensure a sound tie, it may be necessary to connect the front and rear elevations
of scaffold right through the building. Further guidance on ties and scaffolding in general, is
given in (see Pt 2 section 29). – Scaffolding.
Unlike formwork in most building contracts, the major problem with refurbishing is where to
transmit a load to an adequate support. It is absolutely vital that the foundation aspects are
dealt with as a priority item and completed prior to alterations to the main structure.
It is also essential for each situation to be carefully assessed and all formwork designed by a
competent person. Any underpinning and foundation works must be conducted under the
supervision of an experienced structural engineer; as the imposed loads can be quite
deceptive in older buildings. A temporary works co-ordinator may be essential in this type of
work.
For further information on formwork – (see Pt 2 section 25). – Falsework.
Consideration should be given to fitting residual current earth leakage circuit breakers on
services which may be damaged by contractors’ activity.
Wherever possible, temporary fire stopping should be provided as work proceeds, and at the
end of each day's work. Care should be taken that occupants are not put at risk during such
work.
33.8.4 noise
there can also be major problems with noise levels and vibration which affect not only the
workers, but also other persons and their employees during office or opening hours,
depending on the use of the buildings, and the hours being worked. In such cases, planning
needs to be directed towards noise-reduced compressors and other machinery, in order to
33.9 SERVICES
In all refurbishment contracts, especially where buildings have been left empty, all services
must be checked carefully, particularly electricity and gas since any persons temporarily
occupying these premises may have illegally reconnected services, often in a dangerous
manner. Where any suspect installation is found, the appropriate authorities must be
contacted to eliminate any faults.
It is often a wise precaution to have temporary supplies provided but, before this is done, all
existing services should be identified. Where existing services are to remain live, their
positions must be located and clearly marked.
On a larger type of refurbishing contract, the installation of a temporary supply is very similar
to that on any building contract. The only difference is that, in refurbishing as the structure
already exists, most of the temporary supply is required to be put in at the beginning. The
lighting must be of the right type and in the right place (e.g. stairs must be well lit) and
waterproof lampholders provided if moisture is present inside the building, or if rain can
penetrate. Tungsten filament lamps should always be protected by guards or shades.
For further information electricity – (see Pt 2 section 7) – Electricity at Work.
33.10 LIFTS
Refurbishment in large buildings sometimes necessitates use of passenger lifts for transfer
of building materials. Copies of thorough examination certificates should be obtained; it may
be necessary to increase the frequency of inspection and examinations to take account of
heavy usage.
Chutes may be attached directly to a building, or to a scaffold and often have branched
connections at different working levels. Sections are raised and lowered by means of a
winch, rope or crane and most designs rely on gear such as U-bolts, eyebolts, chains and
shackles, etc. for suspension and the attachment of one section to another.
MAINTENANCE
INTRODUCTION 1
MAIN APPLICABLE U.A.E. LEGISLATION
SECTION 34
Municipalities & Agricultural Department
H&S Construction Codes of Practice
PART TWO
SECTION 34
MAINTENANCE
INTRODUCTION
Maintenance work is dangerous. Around 40% of all fatal accidents on building operations occur during
maintenance; yet the seriousness of the problem is too often underestimated by management, safety
advisers and operatives because the jobs are usually relatively simple, and of short duration.
Many of these accidents could be prevented by the properly planned implementation of well
understood precautions, so there is clearly considerable scope for reducing their number - but this will
only happen if there is a drastic change in industry’s approach to maintenance work.
Preparing guidance on maintenance safety is difficult because so many different trades are involved,
all with their own distinctive hazards, while at the same time, the individual trades encounter some
common problems when engaged in maintenance work.
Detailed guidance on the risks and precautions in individual sectors will be found in other sections of
the manual. This section highlights the factors which create special risks during maintenance, looks
briefly at the accident background and draws together the most important lessons from other sections
of the manual and from other sources.
• the short duration of much of the work, which can encourage the use of the least time-
consuming and least safe means of access,
• its repetitive nature, which breeds complacency about the risks and contempt for safety
procedures and precautions,
• the difficulties in supervising and monitoring small mobile groups working away from their
base,
• the deterioration in the structure, or the disguising of its fragile nature after years of use,
• the building often remains in use, creating problems for the maintenance workers, and
risks to the occupants.
34.2 PLANNING
In view of the high level of risk likely to be involved in maintenance, it is essential for the
work to be properly planned. Planning should include:
• ensuring that all relevant information on the building and on activities within it is provided
by the occupier or client,
• carrying out a preliminary survey to identify the type of structure, the range of
maintenance work required and the hazards likely to be encountered,
• preparing safe systems of work to eliminate or reduce the risks from identified hazards,
• where work is to be carried out in occupied premises, ensuring adequate arrangements
for the health and safety of occupiers,
• ensuring that employees are adequately instructed, trained and supervised.
Identified hazards should be included in the pre-tender health and safety plan which the
consultant must ensure is prepared. Relevant safety precautions and procedures should be
included in the construction phase health and safety plan which the main contractor must
ensure has been sufficiently developed before the work is carried out.
In addition, work may be carried out close to machinery which is continuing to be operated. It
is therefore essential that, prior to detailed planning of working procedures, a thorough
survey of the building and its contents is implemented by persons whose experience and
training will enable them to identify such circumstances which may give rise to risks during
the maintenance.
Note should also be taken of any safety rules imposed by the occupier, with which
maintenance workers must comply.
• fragile roofs including any gutters which may be required to be used either as a working
place or as a means of access. Asbestos-cement roofs for instance, should always be
treated as fragile and materials such as corrugated metal decking should be examined
for deterioration due to prolonged exposure to the elements or corrosion from processes
within the building..
• floor joists and roof trusses which may be required to support scaffolds, falsework, plant
and materials or any other load hitherto not imposed on those members.
• walls which may be required to accept scaffold ties or fixings for safety nets or
harnesses. Where the strength of the wall is in doubt, then further investigation may be
required by a Structural Engineer.
Note:
Maintenance work may involve the use of permanent equipment which has not been used
for many years, and any such permanent metal access ladders, gantries, safety harness
anchorages, etc., should be thoroughly inspected and where necessary, tested before any
assumption is made that they may be used in the maintenance operation.
Where there is any risk of damage to any of the services arising from the maintenance
operation, every attempt must be made to isolate them prior to the commencement of the
work.
Any such isolation procedures must be controlled by a formal “Permit to Work” system
incorporating the use of “lock off” devices with the key in the possession of the person
carrying out the maintenance. If it is necessary to maintain the services, then isolation may
still be achieved by diverting the supply away from the area where the work is to be carried
out. (see Pt 2 section 11) – Permit to Work.
34.6 MACHINERY
When persons are required to work in elevated positions then they may be in close proximity
to dangerous parts of moving machines which would otherwise be safe by position. In such
cases, the machines must be locked off with the maintenance operator holding the key, and
the activity controlled by a “Permit to Work” system.
Where it is necessary to keep any such machine working, then the maintenance should be
re-scheduled to a time when it is possible to close the machine down or, alternatively,
protective screens must be erected to prevent the risk of contact with the dangerous parts.
Erection of such screening would take place with the machine locked off under a “Permit to
Work” system. Particular attention should be given to the situation where persons are
required to work on or near the wheel track of an overhead travelling crane, or any other
position where he can be struck by a part of that crane.
The crane should either be locked off or have stops fitted to the rail to ensure that the crane
does not approach within 6.0m of that person.
34.7.2 lead
Particular attention should be paid to steelwork which has been coated with lead based
paint. If such steel is to be burned, wire brushed, ground, etc., then samples of paint must be
taken to establish the lead content. Control measures or personal protection will be required
in accordance with (See Pt 2 section 5) – Substances Hazardous to Health.
Serious consideration must therefore be given to the adverse effects which maintenance
work may have on persons not employed, particularly where domestic premises and public
places to which children, the elderly and the blind or otherwise handicapped persons have
access. For example:
34.8.1 public highways
Where it is necessary to obstruct any public highway, including footpaths, for the purpose of
depositing material, erecting scaffolds, etc., then the requirements of Abu Dhabi Municipality
Traffic Section.
34.9 STORAGE
Before bringing plant and materials to the site of maintenance operations, careful
consideration must be given to storage facility.
Care must be taken to establish areas which do not give rise to obstructed access either to
the occupiers of the building or to persons engaged in maintenance work. It should be noted
that the storage of traditional building materials such as timber, due to its flammability, or
hazardous chemicals, due to their interaction with processes carried out within the building
or arising out of the proximity of the storage areas with fire escape routes, may give rise to
risks to safety and health. In order to minimise such risks, it is important that close liaison
exists between persons carrying out the maintenance work and the persons in control of
processes within the building.
This is often due to the short duration of a particular operation and the fact that no suitable
form of access or working place exists
The high accident frequencies highlight the need for a serious commitment to the provision,
inspection and maintenance of places of work together with the routes used to gain access
to them.
It may be possible to use permanent accesses and gantries etc. within a building, but they
must be checked for their suitability for the passage of persons and material. Where any
such facility has not been used for some time they should be checked for deterioration,
paying particular attention to the integrity of decking and any handrails and their points of
attachment to the structure.
lighting
many accesses and working places used in maintenance operations will be in areas not
served by the permanent lighting within the building and will have to be provided with
temporary lighting as described in (see Pt 2 section 7) – Electricity at Work.
ladders
these are the most commonly used means of access to an elevated working place. Ladders
are also widely used as working places but this should be allowed only after careful
consideration that it is safe to do so. This will depend on the type and duration of the work
and on the security of the ladder.
full guidance on the safe use of ladders is given in (see Pt 2 section 29) -Scaffolding, but
the following criteria are particularly relevant to maintenance work:
• ladders must be inspected prior to their use, and those with missing or damaged rungs or
• ladders must be set at a working angle of approximately 75°, i.e. 4 units vertical to I
horizontal (unless fixed to the side of a scaffold tower; when they will be fixed vertically).
• ladder stiles should normally rest on a firm level base. If it is intended to rest the ladder
on an uneven base or stairway, etc. then a levelling device must be fixed to the lower end
of the stile or stiles to ensure that the ladder is supported evenly. Bricks, blocks of wood,
etc. must not be used to pack up stiles an uneven ground.
• where possible, ladders must be secured near the upper resting point by both stiles. In
certain cases, the use of spreader arms attached to the top of the ladder may satisfy this
requirement, but it must first be established that the ladder; so fitted, cannot slip in the
circumstances in which it is used..
• ladders must be placed so that there is a clear space behind each rung to permit the
secure placing of a person’s feet.
• suitable access to a working place must be provided at the stepping off point. Persons
must not be required to climb aver or through guardrails and toe boards. Gaps in
toeboards and guardrails must, however; be kept as small as possible.
Intermediate guardrails, or other forms of barriers (e.g. brickguards), must also be fitted so
that there is not an unprotected gap of mare than 470mm in height. This standard of edge
protection must, where practicable, always be provided where persons could fall more than
2m.
34.12PLANT
34.12.1 power operated platforms
It is important to recognise the limitations as well as the
advantages of such equipment. Normally, they should be
used only to elevate persons. tools and materials into a
position where they can carry out the maintenance work
from the platform.
34.12.2 fork lift trucks (also see Pt 2 section 14) – Mobile Plant & Equipment
the provision of a platform on the forks of a fork lift truck is common in maintenance
operations. In such cases the following safeguards are necessary:
• the capacity of the machine should be established from the manufacturer and this must
be marked on the truck together with its weight. The platform must not be overloaded.
• only trained competent persons may operate the platform on the fork lift truck.
• preferably, the controls for lifting and lowering should be fitted an the platform.
• fork lift truck must not be travelled whilst a person is an the platform unless the truck has
been specifically designed to allow only small positioning movements at creep speed.
• when a platform is fitted, the fork lift truck should not be used for the transfer of persons
or material from one level to another.
34.13 SCAFFOLDS
The requirements in relation to scaffolds, including slung and suspended scaffolds are
covered in (see Pt 2 section 29). Particular attention must be given to the condition of any
roof or rail used to support cradles.
The use of scaffolds in maintenance work is often hindered by lack of space and by the
difficulty experienced in tying them. These difficulties mainly arise when the building eleva-
tions to be scaffolded do not contain any openings through which to tie, particularly in metal
or clad buildings.
This difficulty in tying locations will promote the use of drilled-in anchorage but care must be
taken to ensure that the material into which they are drilled will permit the necessary pull out
values.
Where the structure material is questionable then either of the following tests must be
carried out:-
• proof load of 1.25 times the design load should be applied to at least 1 in 20 anchors.
(minimum 1 anchor)
If the scaffold is used in places to which the public have access then care must be taken to
remove access ladders at the end of the working day. This is particularly important for the
protection of children.
• chutes should be fully enclosed and have no internal projections which are likely to
retain material discharged into them. The openings at the top of the chutes should be
large enough to adequately to receive the material being put into them. If there is any
risk of spillage then additional protection (possibly mesh) should be fixed around the
opening.
• the discharge end of the chute should also be designed to prevent material bouncing out
of the skip or other receptacle. This is often achieved by wrapping a tarpaulin around the
bottom of the chute and the top of the skip or alternatively by fixing mesh screens to the
side of the skip.
• it is essential, particularly when the maintenance is carried out by a contractor with little
or no knowledge of hazards arising out of the processes or plant in the building, that
close liaison exists between the maintenance supervisors, and the persons in control. It
may be necessary that certain medical precautions be taken if the process demands e.g.
work near lead or radiation where initial or periodic medical examinations may be
necessary.
• consideration should be given not only to the processes currently carried out in the
building, but also to those which have been discontinued and may have given rise to
toxic dusts which are still found in pipe ducts etc. Where such a possibility exists, dust
samples should be analysed and all necessary precautions taken.
34.17 ROOFS
Work on roofs is the biggest single cause of fatal accidents in maintenance work, either from
falls from the edge or the even greater cause of falls through fragile roof material.
For further information on working on both Flat and Sloping Roofs (see Pt 2 section 32) –
Safe Working on Roofs.
• the maintenance work may involve the use of eye protection which incorporates Grade 1
impact capabilities, or indeed chemical protection, when all that is held in the Company
stares are general purpose safety glasses.
• ear defenders, generally supplied, may not have sufficient attenuation to protect persons
working adjacent to considerable noise source for long periods, and it would be unlikely
that respirators held in the stores would be suitable to combat specific toxic hazards such
as asbestos or those found when entering confined spaces.
• the person in charge of the maintenance operation must evaluate the hazards associated
with that operation. If the hazards still exist after statutory compliance and carrying out
such measures as are reasonably practicable, but can be further reduced by the use of
protective clothing and equipment, then such clothing and equipment, being suitable for
the operative and for the operation, must be provided, used and maintained.
• in addition, the person using it must be trained in its use and maintenance and given
adequate facility for its storage.
For further information on PPE (see Pt 2 section 12) - PPE.
• the significant death toll amongst those involved in maintenance work will not be
reduced whilst persons walk directly an fragile roofs, work on platforms and other
working places without guardrails and toeboards or without appropriate safety nets or
harnesses, or work from unsecured ladders, makeshift platforms and fail to observe the
many necessary precautions appertaining to maintenance operations.
The use of skilled operatives, who have been trained to recognise hazards associated with
maintenance work and to overcome those hazards, together with adequate supervision and
close liaison with the persons in control of processes carried out in the premises, will go
some considerable way to improve the standards of accident prevention in this hazardous
occupation.
SPECIALIST PROCESSES
SECTION 35
Municipalities & Agricultural Department
H&S Construction Codes of Practice
PART TWO
SECTION 35
SPECIALIST PROCESSES
INTRODUCTION
The term “high pressure water jetting'' covers all jetting including the use of additives and
abrasives at pressure above 140 bars. Pressures currently used can exceed 2500 bar.
This is a high risk operation that requires a high level of supervision and control.
Only adequately trained and competent persons should operate and supervise high
pressure water jetting equipment. The operation is normally carried out by a team and
they should therefore be trained as a team and not as individuals.
35.1.1 hazards
The main hazards involved in working with high pressure water jetting equipment include:
• use of electricily
• combination of a wet environment and the use of electricity
• pressure injection iniuries
• being struck by material dislodged during operations
35.1.2 precautions
Where possible, the work piece to be jetted should be removed to an isolated area. If this is
impracticable, area limits should be defined with barriers and notices restricting access.
When carrying out the operation with chemical additives, extra precautions may be
necessary, due to the presence of the chemical see Pt 2 section 5 - Substances Hazardous
to Health.
Rigid or semi-rigid lances having nozzles fitted to them with any combination of forward,
backward or 90 degree angle jets shall be used. These must be fitted with a safety shut-off
device or dead mans handle device, which should be checked before use to ensure it is in
good working order.
High pressure water jetting should not be used to clean asbestos cement sheets.
• the pump unit lubricant and coolant • where the equipment is electrically
levels are up to the mark, operated, all junction boxes, switches
and cables are watertight and free from
• filters on pump units and suction pick-
defects,
up are clear,
• spark arresters on internal combustion
• all hoses and connections are in good
driven equipment are functioning
condition and correctly made,
correctly,
• the foot control and guard are
• a serviceable fire extinguisher, (C02), is
functioning properly,
readily available.
• all guns/lances, together with jets and
All the above should be recorded in a maintenance! inspection, log or register, and any
adjustments to the equipment must not be attempted when it is under pressure.
• eye protection
• ear defenders
• safety helmets
• waterproof clothing
35.1.5 accidents
Anyone injured while carrying out water jetting
operations can sustain injuries greater than is
possibly visible on the surface.
Fig.1 – showing an operator using a
Medical. advice should be sought immediately portable High pressure Jetting
following any injury however minor, and lance to clean concrete, and
wearing the appropriate PPE.
information should be provided on the nature of the
operation and details of any chemicals involved.
SECTION 35
SPECIALIST PROCESSES
35.2 LASERS
INTRODUCTION
For many years, laser equipment has been finding increasing application in the surveying
and construction industry, offering as it does a means for rapid and accurate alignment and
the facility for precise distance measurement.
As with other civil engineering plant, it is common for firms to hire laser survey equipment
which may then be used by operators who may have received scant training and information
on its safe use. Such equipment will frequently be used on open construction sites with
ready public access.
Most laser instruments have a variety of optical attachments to allow wide changes in the
direction of the beam and its power intensity, which may present significant alterations in the
potential hazard to persons in the vicinity.
It is essential, therefore, that all those involved in the use of lasers, particularly in out-of-
doors situations, where invariably long exposed beam paths are present, are made aware of
the hazards which may exist and the control procedures that are necessary to secure the
safety of everyone, including members of the public.
Ministerial Order No. (32) Year 1982 - Article (1), (6), (9), (15) & (22).
35.2.1 hazards
Because of the wide ranges possible in wavelength, energy content and pulse length of a
laser beam, the hazards associated with lasers vary widely. It is therefore considered
impracticable to regard lasers as a single group to which common standards can apply.
Three aspects of laser application may influence the total hazard evaluation and thereby
influence the application of control measures:
• the laser or laser system’s capability of injuring personnel, which may include burns to
the skin or severe damage to the eyes,
• the personnel who operate the laser and the personnel who may be exposed.
Fig.1 denotes the approved type of Safety Signs required when Laser Operations are in
progress.
Fig.1
35.2.2 classification
One practical means of evaluation and control of laser radiation hazards is for the
manufacturer to classify laser products according to their relative hazard potential, following
rules set out in British (and international) Standards and then to specify appropriate controls
for each class. The use of such a classification will, in most cases, preclude on the part of
the end user of the laser product, any requirement for radiometric measurements. BS EN
60825 groups laser products into five classes based on accessible emission levels (AELs),
i.e. the measured level of radiation to which human access is possible. To conform with BS
EN 60825, the manufacturer is required to label the laser product with the classification
number and to provide certain engineering controls, warning signals etc. Corresponding
details on control precautions necessary for the “user” to implement in respect of each class
are also specified in the standard.
35.2.3 precautions
In line with the laser product classification philosophy, the recommendations for laser safety
vary with the class of laser product in use and may be broadly summarised as follows:
Class 1
These products are safe under all viewing conditions but are not practicable for many
construction applications.
Class 2
The laser beam should, where reasonably practicable, be terminated at the end of its useful
path.
The laser should not be aimed at vehicles or personnel, particularly at head height.
Class 3A
While it is preferred that Class 2 laser products be used wherever possible, there are times
when, for example, due to high ambient light levels, more power may be required than is
available from Class 2 laser products. In such cases, 3A laser products may be used but
their use requires additional precautions, e.g.:
• person competent to supervise the safe use of lasers should be appointed wherever
lasers above Class 2 are in use.
• suitable and adequately trained personnel should be assigned to install, adjust and
operate the laser equipment.
• areas where such lasers are used should be treated as controlled areas, be posted with
standard laser warning signs, and access restricted to personnel who have been advised
as to the precautions they should take.
• precautions should be taken to ensure that the laser beam is not intentionally directed at
specularly reflecting surfaces such as mirrors, lenses etc.
• similarly, care must be taken to ensure that such reflecting surfaces are not accidentally
introduced into the beam path.
Class 3B and 4
Such lasers are hazardous, particularly as the beam may be invisible to the eye. They
require extreme caution and careful evaluation prior to their use.
Engineering controls such as physical barriers, interlocks limiting beam traverse and
elevation etc., should be used whenever practicable to augment the administrative controls,
and the need for eye protection must be assessed. (see Pt 2 section 12) - PPE.
SECTION 35
SPECIALIST PROCESSES
Until the advent of high land prices, investigation was usually confined to natural, or green
field sites. On such sites, if fill material was encountered, it was considered only for its
geotechnical properties. Many investigations are now carried out on contaminated and
derelict sites; such work involves chemists and environmental specialists, to sample and test
for contaminated materials to ensure control or elimination of hazards in the development
and future use of the land.
This section deals only with the safety and health aspects of personnel undertaking site
investigations of land,
desk study
The desk study comprises the inspection of available geological records, Ordnance Survey
data, local archive and authority maps, memoirs and records, aerial photographs and
consultation with public utility authorities.
It is essential to carry out a desk study in order to establish the past usage of a site and thus
to advise contractors of the possible presence of harmful and toxic materials, or
subterranean hazards.
walkover survey
A walkover inspection of a site can provide very useful information with regard to the
planning of the subsequent investigation.
Great care must be taken to avoid falling into unrecorded cavities, such as old mine shafts or
uncapped underground tanks which may have been used as liquor or tar wells at disused
gas works or chemical sites.
The possible instability of staircases and suspended floors must also be considered when
entering derelict structures and basements.
Shafts and manholes must not be entered without taking account of the potential risks from
atmospheric contamination by the ingress of such gases as hydrogen suiphide, methane or
carbon dioxide. Advice on safe systems of work for entry into confined spaces is given in Pt
2 section 21 -Safe Working in Confined Spaces.
inspection pits
dug to a maximum depth of 1.2m, for the purpose of locating underground services.
• Sampling and testing may need to take place in the side of the excavation, in which case
the support system will need to be designed to allow sections to be exposed, whilst
retaining the stability of the excavation.
Guidance on systems of support is given in Pt 2 section 23- Excavations
• Observation pits or trenches should be checked for gas ingress, or oxygen deficiency,
using a suitable atmosphere testing device, and may need to be treated as confined
spaces, requiring special precautions before entry is permitted. Guidance on appropriate
precautions is given in section 21 - Working in Confined Spaces.
buried services
Prior to any excavation it is essential to obtain all possible relevant information on buried
services from all the appropriate authorities, also from land or building owners.
The position of any services in or near the proposed work should then be pinpointed as
accurately as possible by means of a locating device. Power tools or mechanical excavators
should not be used until the position of services has been confirmed. Further guidance is
given in Pt 2 section 6 – Overhead and Underground Services.
open trenches
• spoil from the pit or trench should not be placed adjacent to the walls of the excavation,
as this causes additional ground stresses and hazards to persons who enter even
shallow trenches.
• in unstable ground, a continuous check must be made for the presence of tension cracks,
which may indicate the imminent collapse of a trial pit or trench.
35.3.2 boreholes
The general safety and health precautions to be adopted by personnel operating and
supervising the construction of boreholes are similar to those discussed in the paragraphs
dealing with the excavation of trial pits. In addition, attention must be given to the stability
and operation of the drilling rig, deep services and tunnels, overhead power cables and
noise.
It is essential that the boring or drilling rig is set up in a stable manner. This is of particular
importance when working on sloping ground.
The precautions already outlined for avoiding underground services apply equally to bore
holes. However, due to the greater depth of penetration, consideration must be given to the
possible presence of deep sewers, gas mains and cable tunnels.
The noise from drilling and boring rigs should be assessed and, where possible, reduced.
Where persons are likely to be exposed to 90 dBA, or above, over a working day, hearing
protection must be provided and worn.
Further guidance on noise is given in Pt 2 section 3 – Noise at Work.
Persons must not enter a borehole of less than 760mm diameter. Suitable equipment must
be used for lowering a person into the hole and a Type E safety harness must be worn. A
rescue procedure must be prepared and persons trained in its operation.
Further guidance is given in Pt 2 section 21 – Safe Working in Confined Spaces.
Where tests require the use of grillages to support dead weight kentledge or anchored
reaction cables, it is essential to establish that the ground below the grillage is able to safely
support the imposed loading. Care must be taken not to work or walk in the line of anchored
cables.
All test equipment must be checked and calibrated before use to ensure that the correct
pressure or loading is applied to the test plate or pile.
The lifting appliance and lifting gear used to place load test materials must be suitable for the
purpose and have current test and examination certificates. The ground bearing capacity of
the surrounding area must also be considered before putting a lifting appliance to work.
Further guidance on lifting appliances and lifting gear is given in Pt 2 section 19 - Cranes
and Hoists and section 20- Lifting Gear.
protective clothing
Suitable protective overalls, gloves, safety helmets, and protective footwear must be
provided. All items should be selected to provide the degree of personal protection that
ensures adequate protection for the worst case of contamination. Hand protection is
essential when handling samples.
washing facilities
The provision of washing facilities is essential for use prior to eating, smoking or attending to
bodily functions.
bacterial infection
Persons engaged in handling samples should be encouraged to keep up to date with anti
tetanus injections and be provided with information regarding Ieptospirosis (Weil’s Disease),
first aid
First aid provisions should be made depending on the size of workforce but, as a minimum,
there should be a travel pack with each vehicle
emergency procedures
Fencing of site operations, securely covering excavations, isolating all plant and equipment
and ensuring secure storage of materials are essential minimum procedures to be adopted.
If the excavated spoil is contaminated, the hazard should be clearly indicated on notices.
SECTION 35
SPECIALIST PROCESSES
Inspection, training, certification and various operating activities are discussed in detail.
To construct all watercraft and perform all watercraft operation in accordance with the
standards and local requirements laid down by the Abu Dhabi Coast Guard and Marine
Department.
Inspect, certify, license, and number all watercraft and equipment according to standards
and local requirements laid down by the Abu Dhabi Coast Guard and Marine Department.
capacity plates
Plainly marked on all watercraft with the maximum occupancy and carrying capacity allowed
on board for safe passage. Do not exceed this maximum occupancy or carrying capacity.
loading
make sure that each boat has enough room, freeboard, and stability to safely carry the
maximum cargo and passenger under various weather and water conditions.
flame arrestors
Equip gasoline engines, except for outboards types, with an approved backfire flame
arrestor. Make sure the arrestor is attached to the air intake with a flame – tight connection.
It must be kept clean and in serviceable condition.
fire extinguishers
For watercraft less than 65 feet in length, a minimum two x 10lb Dry Powder extinguishers
should be provided. Watercraft 65 feet or larger must carry sufficient fire extinguishers to
meet Abu Dhabi Coast Guard and Marine Department’s requirements.
ventilation
Watercraft with permanently installed gasoline engines must have powered ventilation
systems to remove gasoline vapours from the vessel.
fuel
Fuel must be stored in approved containers suitable for marine use. Fuel lines must be
equipped with a valve to cut off fuel flow. In addition, if the watercraft will not be in use for a
period of 8 hrs or longer, then the valve must be closed.
navigation lights
Watercraft must be able to display navigation lights required by the Abu Dhabi Coast Guard
and Marine Department. Display navigation lights between sunset and sunrise and any other
time visibility is reduced (fog, haze, rain etc).
Reclamation employees and others who operate a Reclamation – owned watercraft must
first be certified or licensed to operate the watercraft in accordance with the Abu Dhabi
Coast Guard and Marine Department.
float plans
If the operator expects watercraft to activities to take longer than 4 hrs from time of departure
until time of return, a float plan must be prepared. The float plan must include the following
information:
• personnel on board
• activity to be performed
• means of communication.
personnel floatation devices (PFD)
Equip watercraft with one approved PFD for each occupant, and one approved throw line
type onboard the watercraft. Wear a PFD whenever you are onboard or working around
bodies of water where drowning hazard exist. For further information on PFD see Pt 2
section 28 - Working over or adjacent to Water.
safety equipment
Equip all watercraft with adequate safety equipment to meet the Abu Dhabi Coast Guard and
Marine Department’s requirements and any hazards that may be encountered during normal
operations.
swimming
No one should swim from the watercraft or any floating equipment unless you are a certified
diver whose duties require such swimming.
A qualified person must inspect dredges and related equipment before they are entered into
service, and at least yearly thereafter to make sure they are in a safe operating condition.
Before performing repair or maintenance work on the pump, suction or discharge lines below
the water line, or within the hull, in addition to the normal process of securing hoisting
machinery, you must raise the ladder (or drag arm) above the water line and positively
secure it. Set blank or block plates in suction or discharge lines as appropriate.
pipeline marking
Dredge pipelines that float or are supported on trestles must display lights at night and when
visibility is restricted.
safety plans
Prepare a comprehensive safety plan for each dredging operation that may pose hazards to
navigation or to the public.
• where a pipeline crosses a navigation channel or other area subject to boat traffic,
submerged pipeline must rest on the channel bottom. The top pipeline and any anchor
securing the pipe must be no higher than the maximum draft of traffic expected in the
area where pipe is placed.
• when buoyant or semi buoyant pipeline is used, the dredge operator must make sure the
pipeline remains fully submerged and on the bottom. When raising the pipeline, warn
boat traffic of the pipeline hazard. Adequately mark the entire length of the pipeline.
• remove all anchors and related materials when removing the submerged pipe.
floating pipeline
Floating pipeline is any pipeline not anchored on the channel bottom. Clearly mark floating
pipeline, including rubber discharge hoses. Do not allow pipelines to fluctuate between the
water surface and the channel bottom or to lie partially submerged.
If floating pipelines are used as accessways, equip them with a walkway and handrail on
one side. Personnel using the walkway must wear an approved (PFD)
dredge design
Design dredges so that failure or rupture of any of the dredge pump components (including
dredge pipe) will not cause dredge to sink.
dredge pumps
Any dredge with a dredge pump below the water line must have a bilge alarm or
automatically shutdown in the event of a pump leak.
fall protection
Provide guard rails, bulwarks, or taut cable guard lines for deck openings, elevated surfaces,
or other locations where a person may slip or fall from them.
• provide anti slip surfaces on all working decks, stair treads, vessel ladders, and other
walking or working surfaces that may become wet during operation.
• where the distance between the vessel and docks or landing exceeds 18 inches
horizontal, or 12 inches vertical, provide gangways. Gangways must be at least 22 inches
wide, with standard railings and able to support 250 pounds (with a safety factor of 4-1) at
its midpoint.
SECTION 35
SPECIALIST PROCESSES
35.5 DIVING
INTRODUCTION
In the absence of any specific U.A.E. Safety Regulations covering Diving Operations, ADM
have decided to use, as their standard, the current United Kingdom’s Diving At Work
Regulations 1997 as a guideline, and have based the following procedure on the above
Regulations and expect, as far as is reasonably practicable, all diving operation carried out
on any of their Projects to meet the following standards.
The standards apply to diving operations from the time a diver commences his preparations
for diving until he has left the water, and is no longer subject to raised pressure and it may
reasonably be anticipated that he will not need therapeutic recompression.
Diving supervisors, all members of the diving team, and any person concerned with the
recompression or decompression of a diver are deemed to be engaged in a diving operation.
There are a number of people whose actions can affect the safety of the diving project, even
though they are not part of the diving team. These people include the client for whom the
diving project is being carried out. Others include vessel operators and the owners of the site
where the diving project is taking place.
Although their responsibilities vary, they all have a duty to co-operate with the diving
contractor and supervisor. This is to ensure that standards are complied with, and that their
actions do not affect the safety of the dive team.
The client who commissions the work has responsibilities which include:
• ensuring that they appoint a diving contractor who is competent to undertake the duties;
• identifying known hazards to the diving contractor, such as underwater obstructions and
contaminated water;
The diving contractor is normally the person who employs the divers for a diving project. A
diving project is the term used for the overall diving job (whether it lasts two hours or two
months). Depending on the size of the diving project, it can be made up of a number of
diving operations. A diving operation is the portion of the diving project which can be safely
supervised by one person. A supervisor must be appointed for each diving operation.
The diving contractor is the person who plans and conducts a diving project. No diving work
may go ahead without a diving contractor being appointed.
The diving contractor has the main responsibility to ensure a safe diving project. The diving
contractor should ensure that the diving project is planned, conducted and managed in a
safe way.
• ensuring that there are suitable and sufficient divers who are competent in both diving
and the actual work to be undertaken, such as in the use of tools;
• ensuring that the place from which the diving is to be carried out is suitable and safe;
• providing sufficient and suitable plant and equipment, and ensuring that it is correctly
certified and maintained;
• ensuring that adequate arrangements exist for first aid and medical treatment;
the supervisor
The supervisor should be qualified as a diver, and be competent in the techniques being
used in the diving project.
Supervisors are responsible for the safety of the diving operation that they are supervising,
and should be on site and in direct control of the diving operation.
• checking that divers are competent to dive and can carry out the work underwater;
• ensuring that everyone in the diving operation is aware of the diving project plan, and
that the plan is kept up to date;
• ensuring that there is adequate communication with the divers in the water;
• checking the site on the day of the dive, and when conditions change, confirming that
the risk assessment is still current;
• checking that the diving equipment provided is appropriate and adequate for the project.
the divers
• complying with the directions of the supervisor and the dive plan;
• maintaining a daily record of their dives which they should keep for at least two years.
There are three standards of competence. These are the main techniques used for
commercial diving:
• Surface Supplied
• SCUBA
• Closed Bell
If divers hold an Surface Supplied for onshore surface supplied diving, and want to work
offshore using surface supply, they will need to be assessed against a 'top up' standard.
Only divers with a Surface Supplied Top Up are eligible to be assessed for a Closed Bell
certificate. Before assessment, they must have gained at least one year's diving experience
at that level.
If a person fails to reach the required competence, a diver assessment organisation will
refuse to award the qualification.
35.5.5 medicals
Divers must hold a certificate of medical fitness to dive issued by an approved medical
examiner of divers.
The medical examiner considers the diver's ability to meet the physical requirements of
diving work and the physiological consequences of work under pressure. If passed fit, they
are given a certificate of medical fitness to dive, which they must show to prospective
employers.
It is the responsibility of both the diving contractor and the supervisor to ensure that divers
are medically fit and hold the relevant certificates.
Divers must see an approved medical examiner at intervals, not exceeding 12 months, for
an assessment of their fitness to work underwater for the next 12 months. They may decide
to take the medical up to one month before the expiry date. This certificate is valid for 12
months from the original expiry date, and not from the date the medical was taken.
The cost of the medical varies, depending on any further tests that a medical examiner may
have to carry out.
As part of diver training and assessment, divers are taught diving physiology (which includes
the function of the nervous and musculoskeletal systems), and diving medicine (which
includes decompression illness and ear problems).
First Aid training should provide the immediate initial treatment to reduce the effects of the
common injuries or illnesses suffered at work, for example bleeding, fractures, shock, burns
and respiratory arrest.
When considering who should be in a dive team, the diving contractor will include people
who can offer these skills.
As divers may forget their first-aid skills over time (hopefully they will not need to use them),
they may decide that carrying out refresher first-aid training will improve their employment
opportunities.
Refresher training should be done before the diver's current certificate expires. If undertaken
up to three months before the expiry date, the new certificate will be valid from the original
expiry date and not the date the refresher course was completed.
It may also be necessary to train divers in other first-aid procedures such as the emergency
administration of pure oxygen to an injured diver.
• do all divers have valid certificates of training for the type of diving to be executed?
• are all diving personnel in possession of an in date Diver First Aid Certificate?
• are there Diving Rules on site for the work being executed?
• does each diver have a copy of the relevant parts of the Rules?
• are there valid Certificates on site for this plant and equipment? Are they attached or
contained in a register kept for the purpose?
• is the correct first aid and medical equipment, medication, etc. available?
• has a method statement been produced detailing the diving work to be executed, means
of notifying other persons (including Port Authorities) that diving is being undertaken and
for raising the alarm in the event of an emergency.
• the date
• the name or other designation and the location of the offshore installation, work site, craft
or harbour from which the diving operation was carried on
• the time he left the surface, his bottom time and the time he reached the surface on each
occasion
• where the dive includes time spent in a compression chamber, details of any time spent
outside the chamber at a different pressure
• any work done by him on each occasion and the equipment (including tools) used by him
in that work
Consideration of:
• tidal information including local tide tables and indications of speed of current to be
expected
• underwater hazards of the diving site, including any culverts, penstocks, sluice valves or
areas where differences in hydrostatic pressure may endanger the diver
• availability and qualifications of the person and the effect on a diver of changes of air
pressure if he flies after diving
• the activities of any person who will be diving in connection with the diving operation
whether or not he is a diver for the purposes of these regulations.
preparations
Consultation with persons having any control over or information related to the safety of any
diving operation; and in particular persons having control of lifting appliances or having
control of information about shipping movements.
• allocation of personnel
• diving tables for use in decompression procedures for both single and repetitive diving
and in therapeutic decompression procedures; and for inland waters the need to take
account of the effect on pressure of the altitudes at which the diving takes place
• time for which divers are to remain in vicinity of the surface compression chamber
• maintenance of logbooks.
emergency procedures
• emergency signaling
• therapeutic recompression and decompression and the availability of chambers for that
purpose
• calling assistance from emergency services including advance liaison with those services
where appropriate
• precautions in the event of evacuation of the installation, work site, vessel, hovercraft or
floating structure