ID Task Name Duration InfoX % Complete Start Finish
Page 2
ID Task Name Duration InfoX % Complete Start Finish
95 Provide Marketing Attributes Data Template 0 days 0% Wed 11/4/09 Wed 11/4/09
96 Receive Marketing Attributes Data File from Shari (Initial Set) 2 days 0% Fri 11/6/09 Mon 11/9/09
97 Load Marketing Attributes Data in DEV 2 days 0% Wed 11/11/09 Mon 11/16/09
98 Provide Data Validation Report to Shari for Marketing Attributes 2 hrs 0% Tue 11/17/09 Tue 11/17/09
99 Receive Marketing Attributes Data File from Shari 2 days 0% Tue 11/17/09 Fri 11/20/09
100 Load Marketing Attributes Data in QA Client 1 day 0% Tue 11/24/09 Thu 11/26/09
101 Provide Data Validation Report to Shari for Marketing Attributes 2 hrs 0% Tue 12/1/09 Tue 12/1/09
102 Sales Order Data Conversion 7.5 days 0% Wed 11/4/09 Fri 11/13/09
103 Provide Sales Order Data Template 0 days 0% Wed 11/4/09 Wed 11/4/09
104 Receive Sales Order Data File from Shari 2 days 0% Wed 11/4/09 Thu 11/5/09
105 Load Sales Order Data in DEV 2 days 0% Fri 11/6/09 Mon 11/9/09
106 Provide Data Validation Report to Shari for Sales Orders 2 hrs 0% Tue 11/10/09 Tue 11/10/09
107 Receive Sales Order Data File from Shari 2 days 0% Tue 11/10/09 Thu 11/12/09
108 Load Sales Order Data in QA Client 1 day 0% Thu 11/12/09 Fri 11/13/09
109 Provide Data Validation Report to Shari for Sales Orders 2 hrs 0% Fri 11/13/09 Fri 11/13/09
110 Testing 18 days 71% Mon 10/26/09 Wed 11/18/09
111 Marketing 18 days 60% Mon 10/26/09 Wed 11/18/09
112 Campaign Management Test Script 1 day 100% Mon 10/26/09 Tue 10/27/09
113 Lead Management Test Script 1 day 100% Tue 10/27/09 Wed 10/28/09
114 IC Marketing Test Script 1 day 100% Wed 10/28/09 Thu 10/29/09
115 Campaign Automation Test Script 2 days 0% Tue 11/17/09 Wed 11/18/09
116 Sales 2 days 100% Thu 10/29/09 Mon 11/2/09
117 Account & Contact Management Test Script 1 day 100% Thu 10/29/09 Fri 10/30/09
118 IC Sales Test Script 1 day 100% Fri 10/30/09 Mon 11/2/09
119 Milestone: End of Build Phase 0 days 0% Wed 12/2/09 Wed 12/2/09
120 Test 5 days 0% Wed 12/2/09 Wed 12/9/09
121 Phase Startup 1 min 0% Wed 12/2/09 Wed 12/2/09
122 Integration Testing 3 days 0% Wed 12/2/09 Mon 12/7/09
123 Execute Conversion Test Scripts in QA 2 days 0% Thu 12/3/09 Mon 12/7/09
124 Execute Configuration Test Scripts in QA 1 day 0% Wed 12/2/09 Thu 12/3/09
125 Meeting: Product Walk thru 1 day 0% Thu 12/3/09 Fri 12/4/09
126 User Acceptance Testing 3 days 0% Fri 12/4/09 Wed 12/9/09
127 Customer Executes UAT 3 days 0% Fri 12/4/09 Wed 12/9/09
128 Testing 0 days 0% Wed 12/9/09 Wed 12/9/09
129 Milestone: End of Test Phase 0 days 0% Wed 12/9/09 Wed 12/9/09
130 Milestone: End of Realization 0 days 0% Wed 12/9/09 Wed 12/9/09
131 Final Preparation & Go-live 3 days 0% Wed 12/9/09 Mon 12/14/09
132 Phase Start-Up 1 min 0% Wed 12/9/09 Wed 12/9/09
133 Deploy 3 days 0% Wed 12/9/09 Mon 12/14/09
Page 3
ID Task Name Duration InfoX % Complete Start Finish
134 Load final data to production 1 day 0% Wed 12/9/09 Thu 12/10/09
135 Check Production System 1 day 0% Thu 12/10/09 Fri 12/11/09
136 Product Walk thru with the Client 1 day 0% Fri 12/11/09 Mon 12/14/09
137 Release & Support 2.5 days 0% Mon 12/7/09 Wed 12/9/09
138 Phase Startup 1 min 0% Mon 12/7/09 Mon 12/7/09
139 Production Support 2.5 days 0% Mon 12/7/09 Wed 12/9/09
140 Monitor Transactions Accuracy 1 day 0% Mon 12/7/09 Tue 12/8/09
141 Handover to Support Organization 1 day 0% Tue 12/8/09 Wed 12/9/09
142 Meeting: Help Desk Certification 4 hrs 0% Wed 12/9/09 Wed 12/9/09
143 Project Closing 2 days 0% Mon 12/7/09 Wed 12/9/09
144 Close Open Issues 1 day 0% Mon 12/7/09 Tue 12/8/09
145 Confirm Live Environment 1 day 0% Tue 12/8/09 Wed 12/9/09
146 Create & Staff Help Desk 2 hrs 0% Wed 12/9/09 Wed 12/9/09
147 Architecture 37.25 days 45% Tue 10/27/09 Thu 12/17/09
148 Create DEV Environment 5 days 100% Tue 10/27/09 Mon 11/2/09
149 Create ICON VPN Access for DEV team 1 day 100% Tue 11/3/09 Tue 11/3/09
150 Create ICON DEV Team Users 2 hrs 0% Wed 11/4/09 Wed 11/4/09
151 Validate CRM DEV Environment 1 day 100% Wed 11/4/09 Wed 11/4/09
152 Create QA Environment (Client in DEV Box) 4 days 100% Mon 11/2/09 Thu 11/5/09
153 Create Production System 5 days 0% Fri 11/6/09 Thu 11/12/09
154 Migrate Transports into QA 1 day 0% Wed 12/2/09 Thu 12/3/09
155 Migrate Final Transports into Production 1 day 0% Wed 12/9/09 Thu 12/10/09
156 Create Bobj Environment (Hosted) 5 days 0% Thu 12/10/09 Thu 12/17/09
157 Verify Production System Administration 2 hrs 0% Thu 12/10/09 Thu 12/10/09
158 Conduct System Test 4 hrs 0% Thu 12/10/09 Fri 12/11/09
159 Conduct Going Live Check 2 hrs 0% Fri 12/11/09 Fri 12/11/09
160 Training 40.25 days 18% Wed 10/21/09 Wed 12/16/09
161 Plan Trainer Training 2 hrs 100% Wed 10/21/09 Wed 10/21/09
162 Plan End User Training 2 hrs 0% Wed 10/21/09 Wed 10/21/09
163 Meeting: Training Plan Review Meeting 1 hr 100% Wed 10/21/09 Wed 10/21/09
164 Conduct Trainer Training 3 days 100% Tue 11/3/09 Thu 11/5/09
165 Customer Self Training 5 days 0% Fri 11/6/09 Thu 11/12/09
166 Customer Refines & Finalize End User Training Materials 5 days 0% Fri 11/13/09 Tue 11/24/09
167 Customer Key Users Conduct End User Training 5 days 0% Wed 12/9/09 Wed 12/16/09
168 ICON DEV Team Tasks 17 days 0% Fri 11/6/09 Mon 11/30/09
169 Create ICON DEV Team Users 2 hrs 0% Fri 11/6/09 Fri 11/6/09
170 Create Documentation for Loading Data 15 days 0% Mon 11/9/09 Fri 11/27/09
171 Mentor Customer on Load Programs 1 day 0% Mon 11/30/09 Mon 11/30/09