PROJET DE CONSTRUCTION D'UN IMMEUBLE ( SOUS SOL R + 2 )
DEVIS QUANTITATIF ET ESTIMATIF
SIS A LOGPOM VILLE DE DOUALA
SOUS SOL
Superficie
REZ DE CHAUSSEE
Superficie
ETAGE 1
Superficie
ETAGE 2
Superficie
SIS A
N DESIGNATION DES MATERIAUX UNITE QUANTITE PRIX UNITAIREPRIX TOTAL
1 ens 1 50,000 50,000
2 Tonne 4.5 92,000 414,000
3 camion 1.5 80,000 120,000
4 camion 0.5 35,000 17,500
5 Barre 55 2,350 129,250
6 Barre 35 1,100 38,500
7 Rouleau 10 1,500 15,000
8 paquet 5 3,500 17,500
9 nombre 40 1,600 64,000
10 nombre 6 2,000 12,000
11 nombre 5 3,500 17,500
12 nombre 10 300 3,000
13 Nombre 500 -
14 sac 25 1,100 27,500
15 ENS 1 25,000 25,000
16 camion 2 30,000 60,000
17 ENS 1 10,000 10,000
18 nombre 1 1,500 1,500
19 litre 10 1,500 15,000
20 m3 23.8 1,500 35,700
1,072,950
II ELEVATION ET CREPISSAGE
21 Tonne 10 92,000 920,000
22 camion 2 80,000 160,000
23 camion 1 35,000 35,000
24 Barre 87 2,350 204,450
25 Barre 150 1,100 165,000
26 Rouleau 15 1,500 22,500
27 paquet 8 3,500 28,000
28 nombre 50 1,600 80,000
29 nombre 15 3,500 52,500
30 nombre 6 1,800 10,800
31 Nombre 5 8,000 40,000
32 nombre 20 300 6,000
33 Nombre 1869 -
34 sac 63 1,100 69,300
35 ENS 1 25,000 25,000
36 ENS 1 10,000 10,000
37 Litre 10 1,500 15,000
1,843,550 TOTAL
CHARPENTE ET COUVERTURE
TOTAL DES FONDATIONS
Lattes 4/8 de 5ml implantation
Planches de 20 de 5 ML ayoux
PLanches de 30 de 5 ML ayoux
Taquet 3 x3 .5 ml ayoux
PARPAING 20x20x 40
FER HA 8 importes
Remblai de terre 20 tonnes
Usinage de bois de coffrage
Pinceau de _80
PLanches de 30 de 5 ML ayoux
Huile de coffrage
Fouille pour semelle et longrine
Fils d attache doux recuit 2.5 KG
Pointes de 90. 80. 60 de 5kg
FRAIS de moulage de parpaing
Transport materiaux
Usinage de bois de coffrage
Huiles de coffrage vrac 40
PLanches de 30 de 5 ML ayoux
Planches de15 de 5 ML ayoux
Taquet 3 x 3 .5 ml ayoux
PARPAING 15 x20x 40
PROJET DE CONSTRUCTION DE LA CASE FAMILIAL
Ciment C P J 35 Cim,encam
SableTranchant Mougo de 20 Tonnes
Tout venant riche 6 tonnes
Installation de chantier et implantation
Ciment C P J 35 Cim,encam
SableTranchant de moungo de 20 T
Tout venant riche 6 tonnes
FER HA 8 importes
FER rond lisse de 6
Pointes de 90. 80. 60 de 5kg
Lattes 4/8 de 5ml
DEVIS QUANTITATIF ET ESTIMATIF POUR LA REALISATION DU GROS UVRE
FER rond lisse de 6
Fils d attache doux recuit 2.5 KG
FRAIS de moulage de parpaing
Transport materiaux
38 Nombre 0 3,500 -
39 Nombre 65 2,800 182,000
40 Nombre 80 2,000 160,000
41 Nombre 15 6,000 90,000
42 litres 40 1,200 48,000
43 Nombre 2 1,500 3,000
44 Paquet 20 3,200 64,000
46 Nombre 1700 260 442,000
47 Nombre 17 4,800 81,600
48 m2 250 600 150,000
49 feuille 40 6,500 260,000
50 ENS 1 70,000 70,000
1,550,600
4,467,100
Faitiere crantee de 2 ML
Toles de couverture prelaquee de 7/10e
Toles planes strillees 5 /10e
Tansport materiaux
TOTAL
TOTAL CHARPENTE ET COUVERTURE
Bastig 4/12 en atui ou bilinga de 5ML
Chevron 5 /8 Atui ou bilingqa de 5ml
Lattes 4/8 de 5ml atui ou similaire
Planches 3/30 de 5ML ayoux
Brosse a chaux
Pointes de 60/ 80/ 90
Tire fond complet de 80
Xylamon pour traitement bois
SIS A BAMENA VILLE
N DESIGNATION DES MATERIAUX UNITE QUANTITE PRIX UNITAIREPRIX TOTAL
1 Raidisseurs en contre plaqu de 16mm feuilles 16 14000 224000
2 Usinage des raidisseurs ens 1 36000 36000
3 feuilles 30 3800 114000
4 Paquet 4 3800 15200
5 Paquet 2 3800 7600
6 Paquet 1 3800 3800
6 Rouleau 5 1500 7500
7 nombre 44 0 0
8 nombre 22 0 0
9 nombre 12 0 0
10 nombre 80 0 0
11 sac 0 0 0
12 Rouleau 0 0 0
13 litre 0 0 0
14 Fils d attache doux recuit 2.5 KG Rouleau 0 0 0
408100
15 0
16 25,000
433,100
Arrete le present devis debourse sec au montant de vingt trois millions cent soixante six
mille neuf cent quatre vingt francs CFA
Fil d'attaches
Rouleau de fillassee de 15 KG
Sac de pltre
Bande de 2,7cm x 2,7cm x 5ml
Huile d'arrachide
COMMANDE DE MATERIAUX POUR REALISATION CHENEAU M DJONOU
COMMANDE POUR 54 ML DE CHAINEAUX
Bande de 5cm x 2,7cm x 5ml
Bande de 7,7cm x 2,7cm x 5ml
Bande de 12cm x 2,7cm x 5ml
TRANSPORT DOUALA BAMENA
MAIN D'UVRE STAFFEUR
PARTIES EN COURBES
TOTAL
contre plaqu de 4mm
Pointe de 60
Pointe de 80
Pointe de 30
PRIX TOTAL MAIN MATERIAUX
SIS A MAKEPE
EN MACONNERIE
I FONDATIONS
N DESIGNATION DES MATERIAUX UNITE QUANTITE PRIX UNITAIREPRIX TOTAL
1 Installation de chantier et implantation ens 1 5000 5000
2 Ciment C P J 35 Cim,encam Tonne 2.5 92000 230000
3 Sable moyen propre de 20 Tonnes camion 2 80000 160000
4 SableTranchant de moungo de 20 T camion 3 75000 225000
5 Tout venant riche 6 tonnes camion 1 35000 35000
6 Calibre concasse15 /25 20 Tonnes camion 0 360,000 0
7 FER HA 12 importes Barre 0 6000 0
8 FER HA 10 importes Barre 0 3500 0
9 FER HA 8 importes Barre 40 2350 94000
10 FER rond lisse de 6 Barre 40 1100 44000
11 Fils d attache doux recuit 2.5 KG Rouleau 10 1500 15000
12 Pointes de 90. 80. 60 de 5kg paquet 3 3500 10500
13 Lattes 4/8 de 5ml implantation nombre 5 1600 8000
14 Planches de 20 de 5 ML ayoux nombre 4 2000 8000
15 PLanches de 30 de 5 ML ayoux nombre 0 3500 0
16 PLanches de 30 de 5 ML ayoux 40 par 4 de 5ML Nombre 0 8000 0
17 Taquet 3 ? 3 .5 ml ayoux nombre 5 300 1500
18 PARPAING 20x20x 40 Nombre 600 0
19 FRAIS de moulage de parpaing sac 20 1000 20000
20 Vibrations fondations ens 0 100000 0
21 Transport materiaux ENS 1 40000 40000
22 Remblai de terre 20 tonnes camion 1 0 0
23 Usinage de bois de coffrage ENS 1 30000 30000
24 Pinceau de _80 nombre 0 1500 0
25 Huile de coffrage litre 0 1500 0
26 Fouille pour semelle et longrine m3 30 1500 45000
TOTAL DES FONDATIONS 971000
II ELEVATION R D C
27 Ciment C P J 35 Cim,encam Tonne 5 92,000 460000
28 Sable moyen propre de 20 Tonnes camion 2 80,000 160000
29 SableTranchant Mougo de 20 Tonnes camion 2 75,000 150000
30 Calibre concasse7 /15 20 Tonnes camion 0 360000 0
31 Fer H A 12 Importe barre 0 6000 0
32 FER HA 10 importes barre 0 3500 0
33 FER HA 8 importes Barre 40 2350 94000
PROJET DE CONSTRUCTION DE LA RESIDENCE DE M
DEVIS QUANTITATIF ET ESTIMATIF POUR LA REALISATION DU GROS UVRE
34 FER rond lisse de 6 Barre 55 1100 60500
35 Fils d attache doux recuit 2.5 KG Rouleau 10 1500 15000
36 Pointes de 90. 80. 60 de 5kg paquet 4 3500 14000
37 Lattes 4/8 de 5ml implantation nombre 25 1600 40000
38 Planches de 20 de 5 ML ayoux nombre 0 2200 0
39 PLanches de 30 de 5 ML ayoux nombre 0 3500 0
40 Planches de15 de 5 ML ayoux nombre 5 1800 9000
41 PLanches de 30 de 5 ML ayoux 40 par 4 de 5ML Nombre 5 8000 40000
42 Taquet 3 ? 3 .5 ml ayoux nombre 10 300 3000
43 PARPAING 15 20 40 Nombre 1800 0
44 Socles circulares pour appuis poteaux nombre 0 6000 0
45 Amortissement ou locations coffres ENS 0 250000 0
46 Vibrations du R D C ENS 0 60000 0
47 FRAIS de moulage de parpaing sac 60 1000 60000
48 Transport materiaux ENS 1 25000 25000
49 Usinage de bois de coffrage ENS 1 25000 25000
50 Huiles de coffrage vrac 40 Litre 0 1500 0
51 Contres plaque de 4mm feuille 0 3000 0
52 Pointes de 30 de 5kg paquet 0 4800 0
TOTAL R D C 1155500
CHARPENTE ET COUVERTURE
102 Bastig 4/12 en atui ou bilinga de 5ML Nombre 0 3500 0
103 Chevron 5 /8 Atui ou bilingqa de 5ml Nombre 0 2800 0
104 Lattes 4/8 de 5ml atui ou similaire Nombre 100 2000 200000
105 Planches 3/30 de 5ML ayoux Nombre 0 6000 0
106 Xylamon pour traitement bois litres 20 1200 24000
107 Brosse a chaux Nombre 0 1500 0
108 Pointes de 60/ 80/ 90 Paquet 15 3200 48000
109 Pointes de 30sans tete Paquet 0 4800 0
110 Tire fond complet de 80 Nombre 600 260 156000
111 Toles prelaquees bordeaux de 5 Ml feuille 24 7000 168000
112 Noues en V de 2 ML Nombre 0 3300 0
113 Faitiere crantee de 2 ML Nombre 0 4800 0
114 Toles couvre jintjoint T 1 de 2ml Nombre 0 3200 0
115 Toles de couverture prelaquee de 7/10e m2 0 6300 0
116 Toles planes strillees 5 /10e feuille 0 6500 0
117 Element de lucarne prefabriquee Nombre 0 25000 0
118 Tansport materiaux ENS 1 200000 200000
TOTAL CHARPENTE ET COUVERTURE 796,000
TOTAL 2,922,500
Arrete le present devis debourse sec au montant de