KEGIATAN : PEMBANGUNAN RKB SDN KECAMATAN NUNUKAN TENGAH

PEKERJAAN : PEMBANGUNAN RKB SDN 010 PERSEMAIAN


LOKASI : KECAMATAN NUNUKAN
TAHUN ANGGARAN : 2014
No VOLUME SAT. HARGA SATUAN JUMLAH HARGA
1 3 4 5 6
I PEKERJAAN PENDAHULUAN
1 Pembersihan lokasi 360.00 M2 9,300.00 3,348,000.00
2 Papan Nama Kegiatan 1.00 Ls 400,000.00 400,000.00
3 Administrasi dan Dokumentasi 1.00 Ls 542,000.00 542,000.00
4 Pasang bouwplank 98.00 M1 53,097.06 5,203,511.88
JUMLAH 9,493,511.88
II PEKERJAAN STUKTUR
II.A PEKERJAAN TANAH / PASIR
1 Galian tanah pondasi bt. Gunung 99.00 M3 44,550.00 4,410,450.00
2 Galian tanah foot plat 53.42 M3 44,550.00 2,379,861.00
3 Urugan tanah kembali + pemadatan 38.11 M3 12,312.00 469,148.76
4 Urugan Tanah Bawah lantai 78.54 M3 123,420.00 9,693,406.80
5 Urugan pasir bawah lantai 11.90 M3 197,820.00 2,354,058.00
6 Urugan pasir bawah pondasi 0.55 M3 197,820.00 108,801.00
7 Urugan pasir bawah foot plat 4.27 M3 197,820.00 844,691.40
JUMLAH 20,260,416.96
II.B PEKERJAAN PONDASI
1 Pancang beton 20/20-8 m 1632.00 M' 387,090.00 631,730,880.00
2 Pondasi Batu Gunung 1 : 4 90.20 M3 789,220.00 71,187,644.00
3 Pasangan Aanstamping 41.00 M3 467,061.00 19,149,501.00
JUMLAH 722,068,025.00
II.C PEKERJAAN BETON BERTULANG
Lantai 1
1 Cor foorplat (F1) 120 x 120 cm tebal 35 cm 14.11 M3 3,112,632.54 43,925,470.34
2 Cor foorplat (F2) 100 x 100 cm tebal 30 cm 5.60 M3 2,973,049.00 16,649,074.42
3 Cor pedestal 30/40 (K1) 6.72 M3 8,312,332.80 55,858,876.44
4 Cor pedestal 25/25 (K2) 2.00 M3 10,275,931.38 20,551,862.77
5 Cor sloof 20/40 (S) 15.20 M3 6,457,369.55 98,152,017.13
6 Cor sloof 15/20 (S1) 0.45 M3 5,491,716.89 2,471,272.60
7 Cor kolom 30/40 (K1) 13.68 M3 8,312,332.80 113,712,712.75
8 Cor kolom 25/25 (K2) 4.00 M3 10,275,931.38 41,103,725.54
9 Cor Kolom praktis 13/13 (Kp) M3 9,532,776.32 -
10 Cor plat Lantai M3 5,772,267.03 -
11 Cor Balok 30/70 (B1) M3 6,236,884.08 -
12 Cor Balok 20/40 (B2) M3 8,376,367.74 -
13 Cor Balok 13/25 (Balok latai) M3 11,075,350.27 -
14 Cor tangga beton M3 8,548,137.00 -
15 Cor Plat Kanopi tbl 7 cm M3 7,685,087.40 -
SUBJUMLAH 392,425,011.98
Lantai 2
1 Cor kolom 30/40 (K1) M3 8,312,332.80 -
2 Cor kolom 25/25 (K2) M3 10,275,931.38 -
3 Cor kolom 10/30 (K4) M3 12,128,318.65 -
4 Cor Kolom praktis 13/13 (Kp) M3 9,532,776.32 -
5 Cor plat atap dak tbl 12 cm M3 5,772,267.03 -
6 Cor Balok 20/40 (R1) M3 8,376,367.74 -
7 Cor Balok 20/30 (R2) M3 9,328,326.64 -
8 Cor Balok 13/25 (Balok latai) M3 11,075,350.27 -
SUBJUMLAH -
JUMLAH 392,425,011.98
RENCANA ANGGARAN BIAYA ( RAB )
URAIAN PEKERJAAN
2
No VOLUME SAT. HARGA SATUAN JUMLAH HARGA
1 3 4 5 6
URAIAN PEKERJAAN
2
II.D PEKERJAAN BETON TAK BERTULANG
1 Cor lantai kerja foor plat 2.82 M3 905,952.00 2,551,160.83
2 Cor bawah lantai M3 905,952.00 -
JUMLAH 2,551,160.83
III PEKERJAAN ARSITEKTUR
III.A PEKERJAAN PASANGAN / PLESTERAN
Lantai 1
1 Pasangan batu bata tebal 1/2 bata 1 : 2 M2 157,455.00 -
2 Pasangan batu bata tebal 1/2 bata 1 : 4 M2 147,180.00 -
3 Plesteran 1 : 2 + acian M2 38,625.00 -
4 Plesteran 1 : 4 + acian M2 33,825.00 -
5 Plesteran Struktur beton + acian M2 33,825.00 -
6 Saluran Air M1 94,473.00 -
SUB JUMLAH -
Lantai 2
1 Pasangan batu bata tebal 1/2 bata 1 : 2 M2 157,455.00 -
2 Pasangan batu bata tebal 1/2 bata 1 : 4 M2 147,180.00 -
3 Plesteran 1 : 2 + acian M2 38,625.00 -
4 Plesteran 1 : 4 + acian M2 33,825.00 -
5 Plesteran Struktur beton + acian M2 33,825.00 -
SUB JUMLAH -
JUMLAH -
III.B PEKERJAAN PENTUP LANTAI DAN DINDING
Lantai 1
1 Pasang lantai keramik uk. 40 x 40 polish (untuk kelas) M2 171,610.00 -
2 Pasang lantai keramik uk. 40 x 40 unpolish (untuk teras) M2 171,610.00 -
3 Pasang lantai keramik uk. 40 x 40 unpolish ( tangga) M2 171,610.00 -
4 Pasang lantai keramik 20 x 20 untuk km/wc (unpolish) M2 159,110.00 -
5 Pasang dinding keramik 20 x 25 untuk km/wc (polish) M2 145,915.00 -
6 Pasang List Keramik 7 x 20 untuk KM/WC (polish) M1 12,110.70 -
SUB JUMLAH -
Lantai 2
1 Pasang lantai keramik uk. 40 x 40 polish (untuk kelas) M2 171,610.00 -
2 Pasang lantai keramik uk. 40 x 40 unpolish (untuk teras) M2 171,610.00 -
SUB JUMLAH -
JUMLAH -
III.C PEKERJAAN KUSEN
Lantai 1
1 Kusen Aluminium M1 107,726.33 -
2 Daun pintu panel 80 x 210 cm (PJ) + finishing Bh 1,166,088.00 -
3 Daun pintu panel 40 x 210 cm (PJ) + finishing Bh 583,044.00 -
4 Daun pintu PVC 70 x 210 cm (P2) Bh 971,740.00 -
5 Daun Jendala 35 x 70 cm Bh 96,998.48 -
6 Daun Jendala 55 x 70 cm Bh 152,426.18 -
7 Daun Jendela 70 x 120 cm Bh 332,566.22 -
8 Daun Jendela 35 x 120 cm Bh 166,283.11 -
9 Kaca Bening 5 mm M2 132,600.00 -
10 Kaca Es 5 mm M2 275,000.00 -
SUB JUMLAH -
Lantai 2
1 Kusen Aluminium M1 107,726.33 -
2 Daun pintu panel 80 x 210 cm (PJ) + finishing Bh 1,166,088.00 -
3 Daun pintu panel 40 x 210 cm (PJ) + finishing Bh 583,044.00 -
4 Daun pintu panel 80 x 210 cm (P1) + finishing Bh 971,740.00 -
5 Daun Jendala 35 x 70 cm Bh 96,998.48 -
6 Daun Jendala 55 x 70 cm Bh 152,426.18 -
7 Daun Jendela 70 x 120 cm Bh 332,566.22 -
8 Daun Jendela 35 x 120 cm Bh 166,283.11 -
9 Kaca Bening M2 132,600.00 -
SUB JUMLAH -
JUMLAH -
No VOLUME SAT. HARGA SATUAN JUMLAH HARGA
1 3 4 5 6
URAIAN PEKERJAAN
2
III.D PEKERJAAN KUNCI DAN PENGGANTUNG
Lantai 1
1 Pasang Engsel 4" Bh 17,500.00 -
2 Pasang Engsel 3" Bh 11,700.00 -
3 Pasang Kunci Tanam setara execlusive Unit 306,000.00 -
4 Pasang Tubular + knob (Pintu WC) Set 75,000.00 -
5 Pasang Hak Angin Bh 17,500.00 -
6 Pasang Handle Jendela Bh 14,600.00 -
7 Pasang Grendel Jendela Bh 35,700.00 -
8 Pasang Ekspangolet Bh 75,000.00 -
SUB JUMLAH -
Lantai 2
1 Pasang Engsel 4" Bh 17,500.00 -
2 Pasang Engsel 3" Bh 11,700.00 -
3 Pasang Kunci Tanam setara execlusive Psg 306,000.00 -
4 Pasang Hak Angin Bh 17,500.00 -
5 Pasang Handle Jendela Bh 14,600.00 -
6 Pasang Grendel Jendela Bh 35,700.00 -
7 Pasang Ekspangolet Bh 75,000.00 -
SUB JUMLAH -
JUMLAH -
III.E PEKERJAAN ATAP
1 Rangka Atap Baja Ringan M2 275,000.00 -
2 Atap Metal Sheet M2 99,700.00 -
3 Pas.bubungan atap M1 67,982.87 -
3 Listplank baja ringan M1 52,650.00 -
4 Pas.kuda-kuda batu bata M2 147,180.00 -
JUMLAH -
III.F PEKERJAAN PLAFOND
Lantai 1
1 Pasang rangka metal furing M2 105,770.00 -
2 Pasang plafond gypsumboard M2 49,857.80 -
3 List plafond gypsum + Finishing M1 43,558.00 -
SUB JUMLAH -
Lantai 2
4 Pasang rangka Metal M2 105,770.00 -
5 Pasang plafond gypsumboard M3 49,857.80 -
6 List plafond gypsum + Finishing M1 43,558.00 -
SUB JUMLAH -
JUMLAH -
III.G PEKERJAAN SANITASI
1 Kran air Bh 25,000.00 -
2 Floor Drain stainless Bh 50,000.00 -
3 Bak mandi Fiber Bh 50,000.00 -
4 Kloset Jongkok Bh 1,050,000.00 -
5 Wastafel + aksesoris Set 2,050,000.00 -
6 Biological Filter Septictank Unit 7,500,000.00 -
JUMLAH -
III.H PEKERJAAN CAT-CATAN
Lantai 1
1 Cat dinding interior M2 39,715.50 -
2 Cat dinding eksterior M2 44,225.50 -
3 Cat Struktur beton M2 44,225.50 -
4 Cat plafond M2 39,715.50 -
5 Waterproffing KM/WC (2 Lapis) M2 50,849.70 -
SUB JUMLAH -
No VOLUME SAT. HARGA SATUAN JUMLAH HARGA
1 3 4 5 6
URAIAN PEKERJAAN
2
Lantai 2
1 Cat dinding interior M2 39,715.50 -
2 Cat dinding eksterior M2 44,225.50 -
3 Cat Struktur beton M2 44,225.50 -
4 Cat plafond M2 39,715.50 -
5 Waterproofing atap dak (2 Lapis) M2 50,849.70 -
SUB JUMLAH -
JUMLAH -
III.I PEKERJAAN LAIN-LAIN
1 Railing Tangga Besi hollow M1 750,000.00 -
2 Teralis besi hollow Bh 1,500,000.00 -
3 Batu tempel acak M2 282,485.00 -
4 Sansite Besi Hollow M2 1,500,000.00 -
JUMLAH -
IV PEKERJAAN MEKANIKAL ELEKTRIKAL
IV.A PEKERJAAN INSTALASI LISTRIK
Lantai 1
1 Instalasi Penerangan Ttk 125,000.00 -
2 Instalasi stop kontak Ttk 125,000.00 -
3 Lampu Box Tanam -ALM (MIRROR LOUVRE) . 2x20Watt. Bh 350,000.00 -
4 Lampu Sl 18 watt + fitting Bh 50,000.00 -
5 Saklar Tunggal Bh 24,000.00 -
6 Saklar Double Bh 33,000.00 -
7 Stop Kontak Bh 26,000.00 -
8 Pemasangan Box 3 MCB Unit 525,000.00 -
SUB JUMLAH -
Lantai 2
1 Instalasi Penerangan Ttk 125,000.00 -
2 Instalasi stop kontak Ttk 125,000.00 -
3 Lampu Box Tanam -ALM (MIRROR LOUVRE) . 2x18Watt. Bh 350,000.00 -
4 Lampu Downlight PLCE 24 watt Bh 50,000.00 -
5 Saklar Tunggal Bh 24,000.00 -
6 Saklar Double Bh 33,000.00 -
7 Stop Kontak Bh 26,000.00 -
SUB JUMLAH -
JUMLAH -
IV.B PEKERJAAN INSTALASI PIPA
1 Pipa PVC-AW 4" M1 127,921.70 -
2 Pipa PVC-AW 2,5" M1 51,216.70 -
3 Pipa PVC-AW 1/2" M1 10,932.35 -
JUMLAH -