DMCI GLOBAL, LTD

Palm Jumeirah Monorail


DMCI GLOBAL, LTD
Palm Jumeirah Monorail
DMCI GLOBAL, LTD
Aerial View of
Palm Jumeirah
DMCI GLOBAL, LTD
Aerial View of
Atlantis Station
(Atlantis Hotel in the
background)
DMCI GLOBAL, LTD
Aerial View of
Atlantis Station
(Atlantis Aquaventure water
park at left)
DMCI GLOBAL, LTD
Atlantis Station
DMCI GLOBAL, LTD
Atlantis Station
DMCI GLOBAL, LTD
Atlantis Switch
Bridge
DMCI GLOBAL, LTD
Village Center
Station
DMCI GLOBAL, LTD
Village Center Station
DMCI GLOBAL, LTD
Trump Tower
Station
DMCI GLOBAL, LTD
Trump Tower Station
DMCI GLOBAL, LTD
Rebar Fabrication
DMCI GLOBAL, LTD
Inner Form Fabrication
DMCI GLOBAL, LTD
Soffit Form Setting
DMCI GLOBAL, LTD
End Form Setting
DMCI GLOBAL, LTD
Rebar Assembly
DMCI GLOBAL, LTD
Rebar Assembly
DMCI GLOBAL, LTD
Inner Form and Sheath
Installation
inner form
sheath
DMCI GLOBAL, LTD
Side Form Preparation before
inserting rebar cage
DMCI GLOBAL, LTD
Side Form Setting
DMCI GLOBAL, LTD
Concrete Placing
DMCI GLOBAL, LTD
Concrete Placing
DMCI GLOBAL, LTD
Curing
DMCI GLOBAL, LTD
Stressing
DMCI GLOBAL, LTD
Lifting to Stock Area
DMCI GLOBAL, LTD
Retouching
DMCI GLOBAL, LTD
Stocking Area
DMCI GLOBAL, LTD
CHALLENGES
Placing of
Stitching Concrete
DMCI GLOBAL, LTD
DMCI GLOBAL, LTD
Palm Jumeirah Monorail
Guideway Beam
Production & Stitching
Precasting of 428 beams
each beam is 28m long x 1m wide x 2m high and weighs 80 tons
Joining of beams to columns at site
beams are stitched to other beams and columns by concrete
Contract Amount: AED 11.3 Million

DMCI GLOBAL, LTD
Palm Jumeirah Monorail
Atlantis Station
3 floors
2100 sq m
Contract Amount (Structural): AED 3.6 Million
Contract Amount (Finishing): AED 11.0 Million

DMCI GLOBAL, LTD
Palm Jumeirah Monorail
Village Center Station
5 floors
2200 sq m
Contract Amount (Structural): AED 3.9 Million
Contract Amount (Finishing): AED 7.9 Million

DMCI GLOBAL, LTD
Palm Jumeirah Monorail
Trump Tower Station
3 floors
1700 sq m
Contract Amount (Structural): AED 2.6 Million
Contract Amount (Finishing): AED 9.5 Million

DMCI GLOBAL, LTD
Project Features
Monorail Guideway Beams
32 cu m concrete per beam (typical)
80 tons beam weight (typical)
2 beams per day average production
Hollow section
Pre-stressed, post-tensioned
Vertically & horizontally curved and canted beams
Curved soffit

Monorail Stations
Structural:
Concrete: 5900 cu m
Rebar: 1160 tons
Finishes:
(1) Custom glass and aluminum external envelope
(2) Spray tile finish to exterior concrete surfaces
(3) Granite interior walls and floors
(4) Perforated aluminum ceiling finish
Benefits Derived :
Profit realized
Retention of human resource
Capability enhancement through this
experience the company was able to win
two more projects in the Philippines.