You are on page 1of 1

SUPER SHOPPING MARKET INC.

SM HYPERMARKET GENSAN
December 15, 2013
I. PERMITS
1. Building Permit ZUMYRPHIL Awaiting for structural plan
II. BUILDING EXTERIOR
1. SITE DEVELOPMENT
1.1 Concreting works H.P FRANCISCO 01/20/14
1.2 Mortar open-lined canal H.P FRANCISCO 12/27/13
2. FAADE
2.1 Stractural Framing ZUMYRPHIL
Pending at right side entrance. No manpower
deploy
2.2 ACP Installation No Contractor Quotation for approval
2.3 Logo DLI Awaiting completion Faade
3. ROOF
3.1 Rectification of gutter ZUMYRPHIL 12/17/13
3.2 Sealant at main entrance ZUMYRPHIL 12/16/13
3.3 Roofing for sidewalk canopy ZUMYRPHIL 12/20/13
4. STP
4.1 Civil works HYDROGURAD 01/08/14
4.2 Electro-mechanical works HYDROGURAD 02/08/14
4.3 Blower room HYDROGURAD 02/08/14
5. RDU
5.1 Roll up door NEW ERA 12/16/13
5.2 Trench drain cover No Contractor For quotation
5.3. Office ACU DELTA COOL 12/22/13
5.4 Electrical works ENA 12/21/13
6. ARCADE
6.1 Tile Layout WTA For Issuance 12/16/13
6.2 Installation of arcade tiles ICC Awating for tile layout. Additional work for ICC
6.3 Ramp stainless steel railing installation ZUMYRPHIL No manpower deploy
6.4 Ceiling installation
7. LEASABLE
7.1 Wiring of feederline ENA 12/17/13
7.2 Installation of pull box ENA 12/18/13
7.3 Installation of sprinkle heads ICC 12/18/13
7.4 Exhaust and Fresh air DELTA COOL 12/28/13
7.5 Dropwall using GI ZUMYRPHIL No manpower deploy
8. OTHERS
8.1 Plumbing works ICC 12/23/13
8.2 MRF ZUMYRPHIL No manpower deploy
8.3 Relocation of downspout at clerestory ZUMYRPHIL 12/20/13
8.4 Canopy for left side entrance and utility rooms ZUMYRPHIL No manpower deploy
8.5 Dropwall for leasable space using GI ZUMYRPHIL No manpower deploy
III. BUILDING INTERIOR
1. WAREHOUSE
1.1 Electrical works ENA
a. Emergency Lights
- Roughing-in ENA 12/17/13
- Wiring ENA 12/19/13
1.2 Fire Protection Awating delivery of fittings
2. ADMIN OFFICE
2.1 Employee's Toilet
a. Painting works ICC 12/20/13
b. Installation of toilet fixtures ICC 12/17/13
c. Installation of phenolic partitions G.S GO BROS 12/16/13
d. Installation of lighting fixture ENA 12/16/13
e. Installation of facial mirror SALES DISPLAY 12/20/13
2.2 Mechanical works DELTA COOL 12/22/13
2.3 Installation of switches ENA 12/19/13
3. SELLING AREA
3.1 Installation of vinyl tiles ICC 12/15/13
3.2 Painting works
a. Perimeter color termination ICC Awaiting for final color
b. Hangers ICC changed color from white to gray 12/17/13
3.3 Installation of food gondola DEVEX 12/18/13
3.4 Refrigeration works KING RICHARD 12/20/13
3.5 Installation of grid ceiling ENA 12/19/13
3.6 Glass and glazing works SALES DISPLAY 12/20/13
3.7 Mechanical works
a. Big Ass Fan installation DELTA COOL 12/18/13
b. Diffuser installation/ tapping DELTA COOL 12/19/13
c. Ducting at main and side entrance DELTA COOL
e. ECB Installation DELTA COOL 12/17/13
f. Flushing/ leak test DELTA COOL 12/19/13
g. Drain line piping DELTA COOL 12/23/13
h. Installation of Control Switch DELTA COOL 12/28/13
i. Vacuum/ Charging DELTA COOL depends on the availability of power supply
j. Tapping and testing DELTA COOL depends on the availability of power supply
k. Installation of jet nozzle to spiral ducting DELTA COOL 12/28/13
3.8 Electrical Works
a. Dropping to gondola ENA erio 12/22/13
b. Wirings of Feederline (selling) ENA 12/17/13
c. Wirings for checkout counters ENA 12/17/13
d. Feederline (foodstall,forex and BPS) ENA
- Roughing-in ENA 12/18/13
- Wiring ENA 12/19/13
e. Feederline (AC) ENA Pending at Front Area 12/20/13
f. Installation of Lighting fixture ENA Lack of supply T5 (For ordering)
3.9 Fire protection
a. Installation of sprinkler heads ICC 12/18/13
b. Fire Hose Cabinets ICC
3.10 Installation of Ceramic Tiles @ Seafood Area ICC 12/16/13
3.11 Application of Epoxy Rough Finish @ seafood area ICC 12/20/13
3.12 Application of Epoxy Paint finish @ meat prep area ICC 12/20/13
3.13 Customer Toilet
a. Wall Plastering ICC Pending
b. Painting works ICC Pending
c. Installation of ceramic tiles ICC 12/15/13
d. Installation of toilet fixtures ICC 12/18/13
e. Installation of phenolic partitions G.S GO BROS 12/17/13
f. Installation of lighting fixture ENA 12/16/13
g. Installation of facial mirror SALES DISPLAY 12/20/13
3.14 Installation Checkout counter AandF Awaiting for mobilization of supplier
4. PUMP ROOM
4.1 Electrical works ICC Awaiting delivery of materials
4.2 Testing and Commissioning ICC
5. ELECTRICAL AND GENSET ROOM
5.1 Termination of Grounding ENA 12/18/13
5.2 Wiring ENA
- ATS to Genset ENA 12/16/13
5.2 Additional Equipment Panel
Awaiting for delivery. Additional due to
upgrading of some equipmentt
ITEM WORK SCOPE COMPLETION DATE ATTENTION REMARKS

You might also like