Activity ID Activity Name Original

Duration
Early Start Early Finish
100-409-01 - Interior fit out &MEPworksfor Sacoor Kids @Yas Mall - R1 100-409-01 - Interior fit out &MEPworksfor Sacoor Kids @Yas Mall - R1
137 06-Jun-14 20-Oct-14
General General
2 06-Jun-14 08-Jun-14
A1000 Work order confirmation 1 06-Jun-14 06-Jun-14
A1010 Kick off meeting 1 07-Jun-14 07-Jun-14
A1540 Receipt of client documents & drawings 0 08-Jun-14
Pre-construction Pre-construction
78 08-Jun-14 24-Aug-14
Shop drawing approval Shop drawing approval 26 08-Jun-14 07-Jul-14
A1020 Shop drawing preparation 25 08-Jun-14 06-Jul-14
A1030 Shop drawing submission 15 19-Jun-14 06-Jul-14
A1040 Shop drawing approval 12 24-Jun-14 07-Jul-14
Sample approval Sample approval 14 08-Jun-14 23-Jun-14
A1050 Preparation of samples 10 08-Jun-14 18-Jun-14
A1060 Submission of samples 1 19-Jun-14 19-Jun-14
A1070 Approval of samples 3 21-Jun-14 23-Jun-14
Authority approvals Authority approvals 46 22-Jun-14 06-Aug-14
A2390 Submission of drawings to mall 8 22-Jun-14 30-Jun-14
A2430 Safety induction 1 28-Jun-14 28-Jun-14
A2400 Receipt of mall approval 4 01-Jul-14 05-Jul-14
A2450 Submission of docs to ADCD 2 06-Jul-14 07-Jul-14
A2460 ADCD approval 10 08-Jul-14 21-Jul-14
A2410 Apply for temporary power 7 20-Jul-14 27-Jul-14
A2470 Submission of docs to ADDC 2 22-Jul-14 23-Jul-14
A2490 Submission of docs to ADM 2 22-Jul-14 23-Jul-14
A2480 ADDC approval 10 24-Jul-14 06-Aug-14
A2500 ADM approval 10 24-Jul-14 06-Aug-14
A2420 Receipt of temp power connection 2 28-Jul-14 29-Jul-14
Procurement & Production Procurement & Production 56 21-Jun-14 24-Aug-14
A1110 Procurement of materials 28 21-Jun-14 22-Jul-14
A1580 Receipt of client supplied Fabric/Leather 0 08-Jul-14
A1120 Joinery production 35 08-Jul-14 17-Aug-14
A1130 Delivery of materials to site 18 04-Aug-14 24-Aug-14
Construction Construction
83 30-Jul-14 20-Oct-14
Key milestiones Key milestiones 74 30-Jul-14 11-Oct-14
A2150 Site access 0 30-Jul-14
A2170 Receipt of temporary power 0 30-Jul-14
A2140 Receipt of authority approval 0 06-Aug-14
A2160 Substantial completion before authority approval 0 11-Oct-14
General General 2 30-Jul-14 31-Jul-14
A1140 Access to site 0 30-Jul-14
A1150 Site mobilization 2 30-Jul-14 31-Jul-14
Civil works Civil works 47 02-Aug-14 24-Sep-14
01 08 15 22 29 06 13 20 27 03 10 17 24 31 07 14 21 28 05 12 19
June July August September October
2014
06-Jun-14 06-Jun-14
07-Jun-14 07-Jun-14
08-Jun-14 06-Jul-14
19-Jun-14 06-Jul-14
24-Jun-14 07-Jul-14
08-Jun-14 18-Jun-14
19-Jun-14 19-Jun-14
21-Jun-14 23-Jun-14
22-Jun-14 30-Jun-14
28-Jun-14 28-Jun-14
01-Jul-14 05-Jul-14
06-Jul-14 07-Jul-14
08-Jul-14 21-Jul-14
20-Jul-14 27-Jul-14
22-Jul-14 23-Jul-14
22-Jul-14 23-Jul-14
24-Jul-14 06-Aug-14
24-Jul-14 06-Aug-14
28-Jul-14 29-Jul-14
21-Jun-14 22-Jul-14
08-Jul-14 17-Aug-14
04-Aug-14 24-Aug-14
30-Jul-14 31-Jul-14
Project Start: 06-Jun-14
Date: 21-Jul-14
Actual Work
Remaining Work
Critical Remaining Work
100-409-01 - Interior fit out MEP works for
Sacoor Kids @ Yas Mall - R1
Page 1 of 3
Date Revision Checked Approved
Activity ID Activity Name Original
Duration
Early Start Early Finish
A1240 Screed laying & drying 4 02-Aug-14 05-Aug-14
A1250 Laying of self leveling 3 22-Sep-14 24-Sep-14
MEP works MEP works 25 06-Aug-14 03-Sep-14
Electrical Electrical 23 06-Aug-14 01-Sep-14
P4LP102 Wiring for Lighting and Power 14 06-Aug-14 21-Aug-14
P4LP101 Installation of Cable Trays & Trunking 13 07-Aug-14 21-Aug-14
P4LP103 Power Cables Installation 9 14-Aug-14 24-Aug-14
P4LC100 Wiring for Fire Alarm 14 16-Aug-14 31-Aug-14
P4LC101 Wiring for Emergency lights 9 18-Aug-14 27-Aug-14
P4LP105 Cable Ter minations 6 20-Aug-14 26-Aug-14
P4LP106 Wiring Accessories Installation 9 23-Aug-14 01-Sep-14
P4LP114 DATA cables installation 5 23-Aug-14 27-Aug-14
P4LP104 DB Installation 7 25-Aug-14 01-Sep-14
HVAC works HVAC works 24 07-Aug-14 03-Sep-14
A1950 Installation of main ducts incl insulation 13 07-Aug-14 21-Aug-14
A1960 Installation of branch ducts incl insulation 14 11-Aug-14 26-Aug-14
A1970 Installation of dampers 7 27-Aug-14 03-Sep-14
Fire fighting Fire fighting 16 11-Aug-14 28-Aug-14
A2090 Installation of main fire fighting pipes 12 11-Aug-14 24-Aug-14
A2100 Installation of branch fire fighting pipes 8 17-Aug-14 25-Aug-14
A2110 Sprinkler pipe dropping 7 21-Aug-14 28-Aug-14
A2120 Pressure test 4 24-Aug-14 27-Aug-14
Ceiling finishes Ceiling finishes 24 17-Aug-14 13-Sep-14
A1180 Framework for gypsum suspended ceiling 9 17-Aug-14 26-Aug-14
A1190 Clearance for ceiling closure 1 28-Aug-14 28-Aug-14
A1200 Gypsum boarding,taping & jointing(Store area) 7 30-Aug-14 06-Sep-14
A1210 Installation of slatted ceiling panel 4 02-Sep-14 06-Sep-14
A1610 Installation of white painted wood cornices in ceiling 5 02-Sep-14 07-Sep-14
A1230 Grid ceiling in BOH area(including frameworks) 6 07-Sep-14 13-Sep-14
Wall finishes Wall finishes 13 07-Sep-14 21-Sep-14
A1170 Installation of gypsum wall lining to BOH area 3 07-Sep-14 09-Sep-14
A1300 Installation of white painted pine wood planking at fitting room walls 3 09-Sep-14 11-Sep-14
A1160 Installation of plasterboard walls 6 10-Sep-14 16-Sep-14
A1330 Painting 1& 2nd coat for ceiling & walls 5 10-Sep-14 15-Sep-14
A1340 Final paint for ceiling & wall 3 10-Sep-14 13-Sep-14
A1320 Primer & stucco works 4 17-Sep-14 21-Sep-14
A1360 Installation of shelves 2 18-Sep-14 20-Sep-14
Floor finishes Floor finishes 21 03-Sep-14 27-Sep-14
A1270 Installation of walnut wood floor(store area) 6 03-Sep-14 09-Sep-14
A1260 Installation of white painted pine wood floor(shop windows & back counter) 3 06-Sep-14 08-Sep-14
A1290 Installation of ceramic tile flooring at stock room 3 10-Sep-14 13-Sep-14
A1280 Installation of walnut wood floor at fitting room 2 13-Sep-14 14-Sep-14
01 08 15 22 29 06 13 20 27 03 10 17 24 31 07 14 21 28 05 12 19
June July August September October
2014
02-Aug-14 05-Aug-14
22-Sep-14 24-Sep-14
06-Aug-14 21-Aug-14
07-Aug-14 21-Aug-14
14-Aug-14 24-Aug-14
16-Aug-14 31-Aug-14
18-Aug-14 27-Aug-14
20-Aug-14 26-Aug-14
23-Aug-14 01-Sep-14
23-Aug-14 27-Aug-14
25-Aug-14 01-Sep-14
07-Aug-14 21-Aug-14
11-Aug-14 26-Aug-14
27-Aug-14 03-Sep-14
11-Aug-14 24-Aug-14
17-Aug-14 25-Aug-14
21-Aug-14 28-Aug-14
24-Aug-14 27-Aug-14
17-Aug-14 26-Aug-14
28-Aug-14 28-Aug-14
30-Aug-14 06-Sep-14
02-Sep-14 06-Sep-14
02-Sep-14 07-Sep-14
07-Sep-14 13-Sep-14
07-Sep-14 09-Sep-14
09-Sep-14 11-Sep-14
10-Sep-14 16-Sep-14
10-Sep-14 15-Sep-14
10-Sep-14 13-Sep-14
17-Sep-14 21-Sep-14
18-Sep-14 20-Sep-14
03-Sep-14 09-Sep-14
06-Sep-14 08-Sep-14
10-Sep-14 13-Sep-14
13-Sep-14 14-Sep-14
Project Start: 06-Jun-14
Date: 21-Jul-14
Actual Work
Remaining Work
Critical Remaining Work
100-409-01 - Interior fit out MEP works for
Sacoor Kids @ Yas Mall - R1
Page 2 of 3
Date Revision Checked Approved
Activity ID Activity Name Original
Duration
Early Start Early Finish
A1220 Installation of walnut wood floor at shop entrance 2 25-Sep-14 27-Sep-14
MEP final fix MEP final fix 6 18-Sep-14 24-Sep-14
A1980 Grills & diffusers installaiton 6 18-Sep-14 24-Sep-14
A2130 Sprinkler installation 6 18-Sep-14 24-Sep-14
P4LP107 Light Fittings Installation 6 18-Sep-14 24-Sep-14
P4LC106 Fire Alarm Devices Installation 6 18-Sep-14 24-Sep-14
P4LC108 CCTV Devices Installation 6 18-Sep-14 24-Sep-14
Joinery works Joinery works 20 22-Sep-14 14-Oct-14
A1350 Installation of structure in MDF boxing with meranti framing at shop front 2 22-Sep-14 23-Sep-14
A1400 Shop frontside wall covering in thick pine wood planks 3 22-Sep-14 24-Sep-14
A1380 Installation of entrance door 4 28-Sep-14 01-Oct-14
A1460 Installation of back counter,BOH, fitting room doors and ironmongeries 7 28-Sep-14 05-Oct-14
A1370 Installation of shop window 4 06-Oct-14 09-Oct-14
A1410 Installation of cabinets 3 06-Oct-14 08-Oct-14
A1420 Installation of badges structure 5 06-Oct-14 11-Oct-14
A1440 Installation of counters 5 06-Oct-14 11-Oct-14
A1390 Installation of signage 2 12-Oct-14 13-Oct-14
A1450 Installation of tables,bench,mini bar & charriot 3 12-Oct-14 14-Oct-14
Snagging & Handover Snagging & Handover 26 25-Sep-14 20-Oct-14
A1730 ADDC inspection (can be varied) 8 25-Sep-14 04-Oct-14
A1670 Getting permanent power supply 3 05-Oct-14 07-Oct-14
A1600 Fire alarm testing & commissioning & panel programming 3 06-Oct-14 08-Oct-14
A1680 Electrical testing & commissioning 3 07-Oct-14 09-Oct-14
A1690 A/C air balancing & commissioning 3 08-Oct-14 11-Oct-14
A1740 ADCD inspection 3 12-Oct-14 14-Oct-14
A1760 Snagging works 5 12-Oct-14 16-Oct-14
A1750 ADM inspection 2 15-Oct-14 16-Oct-14
A1700 Mall final inspection & approval 2 16-Oct-14 19-Oct-14
A1710 Final inspection by client 1 19-Oct-14 20-Oct-14
A1720 Client possession 0 20-Oct-14
01 08 15 22 29 06 13 20 27 03 10 17 24 31 07 14 21 28 05 12 19
June July August September October
2014
25-Sep-14 27-Sep-14
18-Sep-14 24-Sep-14
18-Sep-14 24-Sep-14
18-Sep-14 24-Sep-14
18-Sep-14 24-Sep-14
18-Sep-14 24-Sep-14
22-Sep-14 23-Sep-14
22-Sep-14 24-Sep-14
28-Sep-14 01-Oct-14
28-Sep-14 05-Oct-14
06-Oct-14 09-Oct-14
06-Oct-14 08-Oct-14
06-Oct-14 11-Oct-14
06-Oct-14 11-Oct-14
12-Oct-14 13-Oct-14
12-Oct-14 14-Oct-14
25-Sep-14 04-Oct-14
05-Oct-14 07-Oct-14
06-Oct-14 08-Oct-14
07-Oct-14 09-Oct-14
08-Oct-14 11-Oct-14
12-Oct-14 14-Oct-14
12-Oct-14 16-Oct-14
15-Oct-14 16-Oct-14
16-Oct-14 19-Oct-14
19-Oct-14 20-Oct-14
Project Start: 06-Jun-14
Date: 21-Jul-14
Actual Work
Remaining Work
Critical Remaining Work
100-409-01 - Interior fit out MEP works for
Sacoor Kids @ Yas Mall - R1
Page 3 of 3