You are on page 1of 59

PREPARED FOR:

October 2012
Version 2.0 - FINAL
COST PLANNING AND REPORTING STANDARDS


Definitions & Standard Pro-forma












Release notes
This release represents the public issue of the Cost Planning Standards and Reporting Standards.
Health Infrastructure endorsed the current release for industry use commencing 2nd October 2012.

What is new?
This is the first issue of this document in its current format. This Document supersedes any previous Cost
Planning or Cost Management documents issued by NSW Health.

Contacts
Anthony Manning
Health Infrastructure
02 9978 5402
Anthony.Manning@hinfra.health.nsw.gov.au

Acknowledgements
Health Infrastructure acknowledges the following contributors to the development of this Document:
NSW Health;
HI Expert Reference Group;
Rider Levett Bucknall;
All reviewers of the draft versions; and,
All past authors, contributors and reviewers to previous releases.

Foreword
This document is intended for the use on healthcare facility projects valued at $10 million and above.

First published
Version 2.0 FINAL Issued 9
th
October 2012

Access
The Standards can be accessed electronically at the following web site address:
http://www.hinfra.health.nsw.gov.au/__documents/publications-and-resources/cost-planning-and-reporting-
standards_ver-2.0_final_20121009.pdf

Cost Planning and Reporting Standards

CONTENTS

1. INTRODUCTION AND INSTRUCTIONS FOR USE................................................................ 1
1.1 Description ......................................................................................................................... 1
1.2 Objective of this Document ................................................................................................. 1
1.3 Document Structure ........................................................................................................... 1
1.4 Application ......................................................................................................................... 2
1.5 Relationship to other documents and guidelines ................................................................. 2
1.6 Review and revision ........................................................................................................... 3
1.7 Definitions .......................................................................................................................... 3
1.8 Acronyms ........................................................................................................................... 4
2.0 COST PLANS ........................................................................................................................ 6
2.1 Introduction ........................................................................................................................ 6
2.2 Cost Plans Required .......................................................................................................... 6
2.3 Probability (P) Rating ......................................................................................................... 6
2.4 General .............................................................................................................................. 6
2.5 Cost Plan Layout ................................................................................................................ 7
2.6 Travel and Engineering Allowance ...................................................................................... 7
2.7 On-Costs ............................................................................................................................ 8
2.8 Contingencies .................................................................................................................... 9
2.9 Fees................................................................................................................................. 10
2.10 FF&E ............................................................................................................................... 11
2.11 ICT ................................................................................................................................... 13
2.12 Escalation ........................................................................................................................ 15
2.13 Cashflow .......................................................................................................................... 15
3.0 FINANCIAL REPORTS ........................................................................................................ 17
3.1 HI Portal ........................................................................................................................... 17
3.2 Monthly Financial Report .................................................................................................. 17

APPENDICES
APPENDIX A FORMAT FOR STANDARD COST PLAN REPORT
APPENDIX B PRO-FORMA FOR STANDARD COST PLAN REPORT
APPENDIX C PRO-FORMA FOR STANDARD COST PLAN SUMMARIES
CP1 COST PLAN SUMMARY
CP4 ELEMENTAL SUMMARY
CP5 TRADE SUMMARY
CP6 PLANNING UNIT COST PLAN DETAILS
APPENDIX D PRO-FORMA FOR PRELIMINARIES (INDICATIVE)
APPENDIX E CONTINGENCIES
APPENDIX F PROFORMA FOR STANDARD CASHFLOW
APPENDIX G PROFORMA FOR VARIATION REGISTER
APPENDIX H FORMAT FOR (MONTHLY) FINANCIAL REPORTING
APPENDIX I PROFORMA FOR STANDARD (MONTHLY) FINANCIAL REPORTING
Cost Planning and Reporting Standards
Version 1.0, June 2012 Page 1
1. INTRODUCTION AND INSTRUCTIONS FOR USE
1.1 Description
This document provides standard information for Cost Managers to prepare cost
information and documentation in the planning, design and implementation of new and
refurbished healthcare facilities in NSW over $10million in value (principally). Information in
this document is referred to throughout the text as: Cost Planning and Reporting
Standards; this Document; or these Standards.
The purpose of these Standards is to ensure consistency in respect of the cost deliverables
of the Project and a framework for the uniform preparation and presentation of cost advice
by the Cost Manager to Health Infrastructure (HI).
1.2 Objective of this Document
The main objectives of these Standards are:
To provide general guidance to Project team members in the design and
implementation of health care facilities in NSW for HI;
To provide a single source reference document to define the requirements for cost
planning and cost reporting;
To ensure consistency in the presentation of the cost deliverables of a Project;
To facilitate cost comparison between projects;
To facilitate cost benchmarking of projects;
To convey HI policy;
To identify inclusions within key cost components; and,
To standardise reporting formats.
1.3 Document Structure
This Document is divided into numbered Sections. The Sections are as follows:
1. Introduction and Instructions for Use;
2. Cost Plans;
3. Financial Reports; and,
4. Appendices.
Introduction and Instructions for Use
This Section (1).
Cost Plans
Section (2) provides Standards on the format, structure and definitions of items for
inclusion in Cost Plans deliverable during HI Projects.
Financial Reports
Section (3) provides Standards for Financial Reporting deliverable during HI Projects.
Cost Planning and Reporting Standards
Version 1.0, June 2012 Page 2
Appendices
The Appendices to this Document include standard structures for reporting, pro-formas
and the like for Cost Plans and Financial Reporting.
1.4 Application
This Document is applicable to the entire Project Team to comprehend, support and apply
to all HI Projects.
Without limiting the professional processes of the Cost Manager, the User of this Document
is tasked with complying with the pro-forma documentation and structures for deliverables
and submissions to HI.
The application of these Standards is to ensure consistent information is presented to HI
during Projects and for later reference by others for benchmarking and general reference.
With the exception of Contingencies where allowances (percentages or otherwise) are
included within these Standards, the Cost Manager must undertake their own investigations
as well as any necessary benchmarking to validate the allowance as provided. In the
application of these Standards, where the allowances are significantly varied by the Cost
Manager, justification is required to be given in writing within the Project Reporting.
In all HI Projects, the Cost Manager must have a considered understanding of the intent of
these Standards together with advice and progressive thinking on how this intent can be
best presented to articulate the cost goals, and reporting of the Project.
1.5 Relationship to other documents and guidelines
This Document must be read in conjunction with other existing guidance and in accordance
with AIQS and RICS best practice.
All HI Projects must be delivered in accordance with the requirements of all relevant Codes
and Regulations.
1.5.1 Related Documents from HI
This Document forms part of a series of HI documents developed for use in design
and delivery of healthcare facilities in NSW.
To fully comprehend these Standards, Users must make themselves familiar with
the documents in this Section (1.5), as well as the relevant parts of any specific
reference documents noted in individual sections within these Standards.
The following HI documents (listed in order of relative importance) are associated
with this Document, including but not limited to:
a) Part F of the capital consultants Request For Tender documents: this
forms the Consultants scope of services and deliverables in the
administrative aspect of the consultants engagement with HI;
b) TS 11: Engineering Services Design Guidelines;
c) Health Infrastructure Portal Project Directors Manual; and,
d) FF&E Strategy HI Strategy and Documentation.
1.5.2 Other Related Documents
Other documents (listed in order of relative importance) relevant to this Document
and to be referred to by the User; include, but are not limited to:
Cost Planning and Reporting Standards
Version 1.0, June 2012 Page 3
a) Australian Health Facilities Guidelines (all parts);
b) Australian Health Facilities Guidelines, Part F - Project Implementation
680 Furniture, Fittings and Equipment; and,
c) Australian Cost Management Manual (ACMM).
The provisions or requirements of other documents and/ or guidelines will need to
be assessed against the deliverables required by this Document.
1.5.3 Reference to Other Documents
Where references are made in these Standards they are to the latest version of
referenced guides, codes and standards applicable. The user of this Document
must verify the latest guidance material available at the time work is to be carried
out.
The minimum requirements must be those listed in legislation, mandatory and
relevant standards and accepted good practice guides relevant to healthcare
facilities.
1.6 Review and revision
A process of review and revision has been developed for these Standards. HI and industry
comment will be sought and responded to in future versions of these Standards.
1.6.1 Consultant/User Feedback
Users of this Document are invited to provide feedback on any aspect of the
Standards that may be considered of benefit to HI in order to facilitate continuous
improvement in the design and operation of NSW healthcare facilities.
1.7 Definitions
Definitions that are specific to words or phrases used in this Document are listed in the
following table.
Item Definition
Business Case A budget established as part of the Business Case process developed in
accordance with NSW Treasury Guidelines.
Net Construction Cost The cost of the building consisting of the substructure, superstructure,
external fabric and finishes, internal fabric, internal finishes, fixed fittings
and all services within and under the building, the external works and
services within the boundaries of the site and connection to Authorities
services at the perimeter of the site, Project specific costs within the
boundaries of the site; unless otherwise stated.
Gateway Review A series of structured reviews that are held at key decision points (gates)
in the procurement process. NSW Treasury retains the responsibility for
Gateway Review(s).
Greenstar A comprehensive, national, voluntary environmental rating system that
evaluates the environmental design and construction of buildings. The
system has been developed by the Green Building Council of Australia.
Gross Construction
Cost
The Net Construction Cost plus preliminaries, overheads and profit,
staging and locality allowance
Project risk register The document prepared by the Project Manager (with input from the
Project Team) and issued to HI on a monthly (or other agreed) basis.
Cost Planning and Reporting Standards
Version 1.0, June 2012 Page 4
Project Team The consultant Project Team for the Project including; Project Manager.
Quantity Surveyor, Architect, Engineers and all Other Consultants.
HI Project Director The Health Infrastructure Project Director for the Project.
Access Layer Comprises the structured cabling system, hardware, WAP points and
supporting active equipment which enable access to the Access Layer.
1.8 Acronyms
Acronyms that may be used in this Document are listed in the following table.
Acronym Definition
ACMM Australian Cost Management Manual
AHFG[s] Australian Health Facility Guideline[s]
AS Australian Standard
AS/ NZS Australian and New Zealand Standard
BC Building Cost
CC Construction Cost
EA Economic Appraisal
ERG Expert Reference Group
ESC Executive Steering Committee
ESD Environmentally Sustainable Development
ETC End Total Cost
FF&E Furniture Fixtures & Equipment
FIS Financial Impact Statement
GCC Gross Construction Cost
HFBS Health Facility Briefing System
HFG Health Facility Guidelines
HI Health Infrastructure (also means the HI Project Director)
HPU Hospital Planning Unit
ICT Information & Communications Technology (ICT)
LHD Local Health District
NCC Net Construction Cost
NETC Net End Total Cost
PDC Project Development Committee
PDP Project Definition Plan
SOA Schedule of Accommodation
SPP Service Procurement Plan
TPC Total Project Cost
TS11 Technical Standards 11 Engineering Services Design Guidelines
VM Value Management
VMS Value Management Study
Cost Planning and Reporting Standards
Version 1.0, June 2012 Page 5


Cost Planning and Reporting Standards
Version 1.0, June 2012 Page 6
2. COST PLANS
2.1 Introduction
The Cost Manager is to ensure that Cost Plans are:
Holistic;
Based upon all documentation available at the time the Cost Plan is produced;
Incorporating all possible investigations;
Inclusive of individual Project characteristics and site specific features; and,
Established in conjunction with anticipated procurement methodologies and
programme; and,
Compliant with the Reporting Requirements of the Consultants contract.
Inclusive of all applicable allowances and imposts including any applicable
allowance for the carbon pricing mechanism
2.2 Cost Plans Required
The Cost Manager is required to prepare Cost Plans as indicated in the following table.
Cost Plan HI Project Delivery Part HI Project Delivery Phase
Cost Plan A (P50) Part 1 Master Planning Phase 1 - Planning
Cost Plan B (P60) Part 2 Feasibility Development Phase 1 - Planning
Cost Plan C (P70) See below See below
Cost Plan C1 Part 3 - Schematic Development Phase 1 - Planning
Cost Plan C2 Part 4 - Design Development Phase 2 - Implementation
Cost Plan D (P80) Part 5 - Contract Documentation Phase 2 - Implementation
Cost Plans are generally to be prepared in accordance with the Australian Cost
Management Manual (ACMM).
2.3 Probability (P) Rating
Each Cost Plan has a Probability rating. This relates to the level of certainty that the Cost
Plan provides. For example, P70 represents a Cost Plan that has a 70% chance of being
delivered within Budget. As the Project Stages progress, the Probability level will increase.
The benefit of this rating is that the Cost Plan represents a realistic expectation of the level
of certainty based on the information available.
The P level P70, for example, does not represent that the Budget is likely to be exceeded
by 70%, but that there is a 30% chance of the Budget being exceeded. The Contingency
sums still need to accurately reflect the level of risk for the Project at each Stage. The
probability level includes the Project Contingency allocated to each design Stage.
2.4 General
It is intended that each Cost Plan establishes the End Total Cost (ETC) with allowances
assessed and modified on an individual Project basis.
Once the Business Case has been established, the allowances for ESD initiatives,
Contingencies, LHD Fees and HI Management must be maintained, as a maximum, at their
Cost Planning and Reporting Standards
Version 1.0, June 2012 Page 7
Business Case level in subsequent Cost Plans; notwithstanding that the GCC may
increase. The rationale for this is that the works are to be designed to the Business Case
Budget and therefore the Business Case Allowances for these items will not be exceeded.
Notwithstanding this position, the allowances will be subject to detailed reviews as cost
plans are developed and can only be amended upon agreement with the HI Project
Director.
Cost Plans and Cost Reports must report costs exclusive of GST.
2.5 Cost Plan Layout
The Cost Plan must include commentary on all of the items identified in the standard
Contents list as included in Appendix A. It must also be based on the Pro-forma as supplied
in Appendix B.
The Cost Plan must also include the appropriate Cost Plan Pro-Forma(s) provided for
reference in Appendix C.
The applicable pro-formas to be presented with each different type of Cost Plan are as
identified in the following table.
Cost Plan
Pro-forma CP1
required
Pro-forma CP4
required
Pro-forma CP5
required
Pro-forma CP6
required
Cost Plan A required ~ ~ required
Cost Plan B required required
~
required
Cost Plan C1 required required
~
required
Cost Plan C2 required required
~
required
Cost Plan D required required required required
2.6 Travel and Engineering Allowance
Generally the schedule(s) of accommodation (SOA) provided to the Cost Manager include
both the HPU areas together with an allowance for intra-departmental circulation. They
generally exclude inter-departmental travel and engineering allowances.
The SOA provided must be interrogated to identify if any travel and engineering allowances
have been included.
Allowances for travel and engineering must be measured from the drawings. Where no
drawn information is available, allowances for travel and engineering must generally be as
advised in the AHFG, Part C, Clause 705.25.00.
These allowances above must be verified by benchmarking against similar projects and by
reference to the Project Design Team.
Note that central energy buildings, hospital streets, link corridors, bridges and the like must
be included as Project Specifics and not deemed part of travel and engineering.

Cost Planning and Reporting Standards
Version 1.0, June 2012 Page 8
2.7 On-Costs
2.7.1 ESD Initiatives
The HPU cost/m
2
rates must include best practice and minimum 4-Star Greenstar in
respect of the capital works that make up a HPU. ESD allowances are intended for
initiatives above 4-Star Greenstar and beyond best practice, to improve
sustainability, or meet Government policy initiatives such as energy efficiency and
water resource management.
For ESD Initiatives the following allowances must be made:
4% of Construction Cost (CC) where Total Project Cost (TPC) is less than
$100m; or,
2.5% of Construction Cost (CC) where Total Project Cost (TPC) is greater
than $100m.
Once design information is available it is anticipated that the ESD Initiatives costs
will be built up and replace the percentage allowance(s).
2.7.2 Preliminaries
Preliminaries allowance must take account of:
The proposed programme;
The manner (methodology) in which the works will be undertaken; and,
The specifics of the site.
Where Preliminaries allowances are based on percentages, the percentages must
be benchmarked from similar projects executed under similar conditions and take
account of market forces.
A Preliminaries Cost Plan must be developed no later than Cost Plan C1 and
updated for later Cost Plans. An indicative format is provided in Appendix D,
Preliminaries Pro-Forma (Indicative).
2.7.3 Margin
Margin allowance must take account of the Contractors profit and offsite overheads
as well as any contractual risk to be borne.
2.7.4. Staging Costs
Staging Costs include the cost of:
Temporary/ staged decanting of the NSW Healths operations;
Temporary works necessary as a consequence of the need to maintain an
existing healthcare facility during the works and maintain the NSW Healths
operations;
Works and costs consequential on a programmed staging of the works; and,
Costs associated with temporary services resulting from engineering
services shutdown to accommodate Project works (e.g. providing gas
bottles, temporary generators, bottled water etc.)
Cost Planning and Reporting Standards
Version 1.0, June 2012 Page 9
2.7.5 Locality Allowances
The locality allowance is added to take account of factors affecting labour and
material costs and/or the loss of competition that can occur in remote areas. There
is published cost data and indices comparing different localities to a base. Whilst
these may be used as a reference it is incumbent on the Cost Manager to apply
Locality Allowances derived from their own investigations of the anticipated
marketplace, resources available in the locality and other factors that will have a
bearing on the cost of the work.
The Locality Allowance must be identified separately in Cost Plans A and B. The
locality allowances may be built into the rates used or applied as a separate
allowance in Cost Plans C and D.
The Locality Allowance must be either built into the rates or shown separately as
appropriate, but must not be in both.
2.8 Contingencies
HI has prepared guideline Contingency allowances for each Phase of a Project. Refer to
Appendix E.
Whilst guideline Contingencies have been prepared, it is imperative that the Cost Manager
develop Project-specific Contingencies based upon the risk registers developed by the
Consultant Team.
From and including Cost Plan C the adequacy of the contingency must be reviewed by
undertaking a costing and probability analysis of the Project Risk Register. The Cost
Manager, in conjunction with the Project Manager, is to continuously review and update the
Register to reflect the changing risk profile.
2.8.1 Project Contingency
This is intended for risks that can be owned and managed by the project, based on
the information available to them at the appropriate stages. The Cost Manager
must make sufficient provision for risks as identified within the three categories
Design, Construction and Town planning:
Design development contingency % of gross construction cost required
whilst developing design issues;
Town planning contingency % of gross construction cost, required whilst
Town planning issues are resolved; and,
Construction contingency % of gross construction cost, an allowance to fund
client risks during construction.
2.8.2 Client Contingency
This is intended to capture risks outside of the Project that the Project Team can
have little or no influence over. Items such as scope definition, changes in HPU
guidelines, changes in legislation, best practice and Government policy and the
impact of Government reprioritisation.
Risks must generally transfer from the Client Contingency to the Project
Contingency, during development of the Project and then either be realised or
mitigated.
The percentages indicated in the summary table are taken as normal percentages,
in all cases this percentage will be reviewed by the Projects Executive Steering
Cost Planning and Reporting Standards
Version 1.0, June 2012 Page 10
Committee (ESC) in conjunction with the Project Team to establish the
appropriateness of the allowance compared to the known and unknown risks of the
Project. As such the allowance will be increased and decreased depending upon
the level of risk assessed in the Project.
At all stages the Cost Plan produced by the Cost Manager will include both the
Project Contingency and the Client Contingency. It is important that the two are
kept separate to allow the management of the contingency sums. Where
percentages are applied to both Project and Client contingencies are calculated on
the Gross Construction Cost (GCC) identified by the Cost Manager.
2.8.3 Allocation of Contingency
The allocation of project and client contingency is the sole domain of the Projects
Executive Steering Committee (ESC).
Any request for the ESC to allocate contingency must be based on a formal
submission from the HI Project Director and endorsed by the Projects Planning and
Development Committee (PDC) or Project Control Group (PCG).
2.9 Fees
2.9.1 Consultant Fees
Consultant Fees must include for:
Professional design documentation and supervisory fees;
Fees for consultants inputting advice into the Project; and,
Costs associated with investigations of the site.
The Consultant Fees are also inclusive of fees associated with the Economic
Appraisal of the Project together with Gateway facilitation costs.
Consultant Fees must be benchmarked and based upon the Cost Managers
experience but must be based on actual commissions as soon as available.
2.9.2 Authority Fees and Charges
The Cost Manager must make an assessment of the scheduled costs of external
agencies assessing and certifying building/construction approvals.
Authority Fees and Charges that may be applicable to a project include:
Project Application Fee;
Planning Reform Fee;
Administration Fee
Advertising Fee;
Headworks Charges;
Long Service Levy (may be included in building works contract at Cost Plan
D); and,
Authorities contributions and charges.
Cost Planning and Reporting Standards
Version 1.0, June 2012 Page 11
2.9.3 LHD Fee
For the LHD fee, Cost Plans A and B is to include an allowance of:
1.5% of Gross Construction Cost (GCC) for all LHD costs inclusive of final
decanting or as otherwise advised by HI.
Cost Plans C and D must include allowances calculated by the LHD within the
1.5% allowance.
The LHD Fee is to cover the costs of project support by the LHD relating to the
capital work including, but not limited to:
Input into the FIS;
Change management;
Communications strategy;
FF&E procurement; and,
Operational commissioning of the healthcare facility.
2.9.4 HI Management Fee
HI Management Fee is to be as follows:
2% of Net End Total Cost (NETC) or as otherwise advised by HI.
2.10 FF&E
Furniture, Fixtures and Equipment (FF&E) includes the following:
Furniture:
o Loose or movable, generally functional, items that equip a room (e.g. tables,
chairs and workstations);
Fixtures:
o May also be referred to as fittings;
o Fixed items that are attached to the building (walls, floors and/or ceiling);
and,
o May or may not require services (water, gas, electricity) connections;
Equipment:
o Clinical equipment (e.g. defibrillator, ventilator, diathermy machine);
o Non-clinical equipment, which has a specific therapeutic or diagnostic
purpose (e.g. wheelchairs, IV poles, mechanical lifts); and,
o Major Medical Equipment, which is high-cost clinical diagnostic and
treatment electromedical items that may require specialist services (water,
electricity, gas, data networking and/or airconditioning) to be operational
before commissioning (e.g. linear accelerator, MRI, dental chair, x-ray
machine).
FF&E is separated into three (3) groups of items:
Group 1, Supplied and installed by the Contractor:
o This includes everything that can be warranted and fully installed by the
Contractor.
Cost Planning and Reporting Standards
Version 1.0, June 2012 Page 12
Group 2, Supplied by the Client and installed by the Contractor:
o This may include items that the Client has on supplier contract or items for
transfer.
Group 3, Supplied and installed by the Client:
o This will include items that are specific to the Project, but are under full
procurement and delivery control of the Client.
2.10.1 FF&E for Cost Plans A and B
For Cost Plan A and B, the FF&E estimate is to be established by reference to
AHFG rates/m
2
for each HPU (or department rates), as well as benchmarking from
other Projects.
High cost transfer equipment should be identified at this stage (diathermy,
echocardiograph and the like).
Major medical equipment must be identified and costed separately.
2.10.2 FF&E for Cost Plans C and D
For Cost Plan C onwards, an FF&E Cost Report must be prepared as per the HI
template available on the HI Portal.
FF&E incurs two (2) separate costs:
Cost for procurement; and,
Cost for transfer;
The FF&E Cost Report template is designed to reflect this cost breakdown, so all
Cost Reporting is to be completed in the format specified in the Budget Template,
which has predefined formulas embedded into it.
2.10.3 Types of Equipment
The Budget Template is divided into the two types of equipment (new and
transfer). Each type is further defined to show costs for Major Medical (any item
that requires a final installation or shop drawing) and Minor Medical items. The Cost
Manager is to note the following:
Costs for New Group 1 Major Medical items should be reflected line item by
line item;
Costs for New Group 2, 3 items should be reflected line item by line item;
Costs for Transfer Major Medical items should be reflected line item by line
item;
Costs for Transfer Group 2, 3 items should be reflected line item by line item
and should include costs for Decontamination, Decommissioning, Tagging,
Wrapping and Packing, and actual Transfer / relocation costs.
2.10.4 Groups (1, 2 or 3)
Regarding Groups, the Budget Template is designed for the HI Project Directors to
monitor costs incurred by the LHD (Group 2 procurement and Group 3 procurement
and installation). The Budget Template does not show costs for Group 1 items, as
these will be reflected in the construction costs.
Cost Planning and Reporting Standards
Version 1.0, June 2012 Page 13
2.10.5 Resource Costs
The FF&E Cost Report template is specifically designed to ensure any costs
associated with resources are both accounted for and transparent. If the costs are
accounted for under Professional Fees or in other parts of the Budget, it must be
specifically stated where each Resource Cost is being taken into account.
2.11 ICT
Information and Communications Technology (ICT) includes the following:
ICT Infrastructure, which may include:
o Structured Cabling Systems;
o Wide Area (WAN) and Local Area Networks (LAN);
o Wireless Networks (WLAN), including support for Automatic Guided Vehicles
(AGV);
o Networking devices which facilitate the LANs and WLANs, including
switches, routers, racks and servers to enable the access layer;
o Communications, including Public Address and Messaging Systems, two
way radio and paging systems, voice over WLAN, Digitally Enhanced
Cordless Telecommunication (DECT), Unified Communications (including
legacy PABX and fixed voice);
o ICT accommodation, for example, Communications Rooms, Ducts and
Risers.
ICT Functional Systems, which may include:
o Clinical Information and Services, Point of Care Systems, and Patient
Records Systems;
o Building Management Control Systems (BMCS), Programmable Logic
Controllers (PLC) and Supervisory Control And Data Acquisition (SCADA);
o Logistics, Supply Chain Management, Stock and Instrument Control;
o Patient Entertainment, Comfort, Audio Visual, TV systems;
o Education, Research and Training; Hospital Administration, Asset
Management and Human Resources; and,
o Security, Staff Assist, Nurse Call, Porter, Duress and Orderly Systems, Real
Time Location and Way Finding Services.
Most of the ICT functional systems are included in the building contract except for the
software of:
Patient Entertainment systems;
Administration systems; and,
Asset management systems.
ICT is to be a separate line item in all cost plans and cost reports.
ICT is separated into three (3) Groups of items:
Group 1, Supplied and installed by the Contractor:
o This includes everything that can be warranted and fully installed by the
Contractor.
Group 2, Supplied by the Client and installed by the Contractor:
Cost Planning and Reporting Standards
Version 1.0, June 2012 Page 14
o This may include items that the Client has on supplier contract or items for
transfer.
Group 3, Supplied and installed by the Client:
o This will include items that are specific to the Project, but are under full
procurement and delivery control of the Client.
The Project will fund ICT infrastructure associated with the Access Layer, as well
as ICT equipment which directly supports clinical functions (including Nurse Call,
Security, Duress, Major Medical ICT, clinical video conferencing, master clocks,
master aerial systems and imaging.
2.11.1 ICT for Cost Plans A and B
For Cost Plan A and B, the ICT estimate is to be established by reference to AHFG
rates/m
2
for each HPU (or department rates), as well as benchmarking from other
Projects.
High cost transfer equipment should be identified at this stage.
2.11.2 ICT for Cost Plans C and D
For Cost Plan C onwards, an ICT Cost Report must be prepared as per the HI
template available on the HI Portal.
ICT incurs two (2) separate costs:
Cost for procurement; and,
Cost for transfer;
The ICT Cost Report template is designed to reflect this cost breakdown, so all Cost
Reporting is to be completed in the format specified in the Budget Template, which
has predefined formulas embedded into it.
2.11.3 Types of Equipment
The Budget Template is divided into the two types of equipment (new and
transfer). The Cost Manager is to note the following:
Costs for New Group 1 ICT should be reflected line item by line item;
Costs for New Group 2, 3 items should be reflected line item by line item;
Costs for Transfer Major ICT should be reflected line item by line item;
Costs for Transfer Group 2, 3 items should be reflected line item by line item
and should include costs for Decontamination, Decommissioning, Tagging,
Wrapping and Packing, and actual Transfer / relocation costs.
2.11.4 Groups (1, 2 or 3)
Regarding Groups, the Budget Template is designed for the HI Project Directors to
monitor costs incurred by the LHD (Group 2 procurement and Group 3 procurement
and installation). The Budget Template does not show costs for Group 1 items, as
these will be reflected in the construction costs.
Cost Planning and Reporting Standards
Version 1.0, June 2012 Page 15
2.11.5 Resource Costs
The ICT Cost Report template is specifically designed to ensure any costs
associated with resources are both accounted for and transparent. If the costs are
accounted for under Professional Fees or in other parts of the Budget, it must be
specifically stated where each Resource Cost is being taken into account.
2.12 Escalation
The Base Date(s) prevailing for the rates included in the Cost Plan must be clearly
identified. It is important that Escalation from the Base Date to Construction
Commencement and Escalation during the construction period are separately identified.
Whilst published cost data and indices may be used as a reference, it is incumbent on the
Cost Manager to apply escalation factors derived from their own investigation of the
anticipated marketplace and Project specifics. Escalation must be accounted for on the sum
total of the estimated Total Project Cost (TPC) prevailing at the Base Date.
Following completion of the Cost Plan (C2), Escalation is to be distributed within the
elemental and/or trade analysis.
2.13 Cashflow
2.13.1 Generally
Cashflows must reflect when expenditure is anticipated to be accrued and not when
paid, e.g. for the value of work done (vowd) during June, the cost is recorded
against June, not July, which is when the payment certification and payment is likely
to occur.
It is anticipated that the Cashflow is a compilation of the cash flowing of individual
cost centres and individual Construction contracts.
In the Cashflow, Project and Client Contingencies must be shown separately and
consideration must be given to when they are likely to be expended rather than
being cash flowed over the life of the project..
Cashflows must reflect NSW Government financial years that commence on 1 July
annually.
In the Cashflow, FF&E must reflect anticipated expenditure in accordance with the
programme and any deposits and early payments. Generally it is expended 30% in
the period 6-3 months prior to Project Completion and 70% in the final 3 months
prior to Project Completion. The Cashflow for professional fees shall reflect the
different rate of expenditure during the planning and delivery phases as well as pre-
and post-construction.
The Cashflows are to be updated monthly to reflect Actual Expenditure as incurred.
2.13.2
During the Business case phase, prior to Cost Plan C, the Cashflow must be
presented as included in Appendix F.
The Cashflow Pro-forma has been developed to serve competing interests. During
the Business Case the financial modellers require the Cashflow exclusive of
Escalation. HI for their purposes requires Annual Cashflows prepared that are both
inclusive and exclusive of Contingency.

Cost Planning and Reporting Standards
Version 1.0, June 2012 Page 16
2.13.3
For Cost Plan C and onwards the Cashflow must reflect the project programme
prepared by the Project Manager as updated from time to time and not based upon
standard Cashflow formulae. The programme must identify anticipated delivery
dates of major items of plant and equipment as well as cost significant items. The
Cashflow must reflect the expenditure of these items as lump sums rather than
being cash flowed over the life of the project.
Cashflows for LHD fees should be obtained from the LHD and for HI fees from HI.
The Cash flow is to reflect the anticipated ETC exclusive of contingency allowances
where it is deemed, by the Project Director in consultation with the Project team, that
the contingency allowance will not be required.
2.13.4
During construction the construction Cashflow is to be based upon the Contractors
cash flow. Prior to adoption, the Cashflow is to be vetted by the Cost Manager and
adjusted by the Contractor, if required, and agreed. An activity based Cashflow shall
be obtained from the Contractor prior to the first progress payment claim, and
preferably at tender time, to assist the vetting. The Contractor is to update the cash
flow at the time of each progress claim.
2.13.5
From PDP onwards the Cashflow shall be monitored in monthly reports by reference
to the PDP approved Cashflow, or other milestone Cashflow s instructed by HI, and
is to be presented as included in Appendix F. Any significant deviations must be
brought to the attention of the Project Director and Project Manager so that
corrective action can be investigated.
Additionally, the Cashflow is to be prepared in the HI Portal Format as included in
Appendix F.

Cost Planning and Reporting Standards
Version 1.0, June 2012 Page 17
3. FINANCIAL REPORTS
The process of Financial Reporting to HI is via the HI internet Portal as well as by way of a
Monthly Financial Report.
3.1 HI Portal
The Cost Manager is to refer to the HI Portal Manual.
Responsibility for inputting data in the HI Portal Financial Reporting is as indicated in the
following table.
Input Responsibility
Budget HI Project Director
Commitments Project Manager (approved by HI Project Director)
Forecast commitments Cost Manager
Payments Project Manager (approved by HI Project Director)
Cashflow Cost Manager
Commentary HI Project Director and Project Manager
3.2 Monthly Financial Report
The Cost Manager is to prepare a Monthly Financial Report and in addition is required to
upload information into the HI Portal as a Financial Report.
3.2.1 Purpose
The purpose of the Monthly Financial Report is to convey the financial status of the
Project by providing information on Project budget status, funding sources,
cashflow, financial risks and be a base data source for PDC, PCG and ESC
governance groups.
The HI Portal Financial Report must form an appendix to the Monthly Financial
Report.
3.2.2 Layout
The Monthly Financial Report must include commentary on all of the items identified
in Appendix H. It must be presented in the format as supplied in Appendix I.

Cost Planning and Reporting Standards
Version 1.0, June 2012 Appendices Cover Page



APPENDICES

Cost Planning and Reporting Standards




APPENDIX A

STANDARD COST PLAN REPORT
FORMAT


Cost Planning and Reporting Standards

FORMAT FOR STANDARD COST PLAN REPORT
Each Cost Plan Report must include the following standard headings (as indicated by
numbered, bold text) and content as described in dot-points below:
1.0 Executive Summary
Inclusive of an estimate budget comparison
2.0 Basis of Cost Plan
Summary of the information used as the basis for the specific Cost Plan.
2.1 Introduction
A concise note on the status of the project.
2.2 Scope of Project
A concise description of the project including location, building type,
number of storeys, service level and service objectives, major
departments, bed numbers, theatre numbers, etc.
2.3 Outline of Cost Plan
An outline of the level of cost plan, design stage, method of preparation,
methodology of pricing, etc.
2.4 Specific Inclusions
A schedule of items and allowances included in the Cost Plan. E.g. Mining
subsidence allowance, radiation shielding to imaging theatres, Contractors
design fees, shell space etc.
2.5 Specific Exclusions
Exclusions other than GST must be avoided. Items such as fit outs by
tenants are to be recorded as work by others outside the Project Scope.
2.6 Drawings & Information Used
A schedule of all drawings, specifications, reports and the like used in the
preparation of the cost plan.
2.7 Area Measurement
A schedule of gross floor areas (GFA) on a departmental basis;
A schedule of Travel and Engineering areas;
A schedule of unenclosed covered areas (UCA);
A summary of all building areas; and,
Where areas can be measured there must be a reconciliation of measured
areas to the SOA.
2.8 Procurement and Market Assumptions
An outline of the proposed procurement method, anticipated market
conditions and any other factors likely to affect the pricing of the Project.
Cost Planning and Reporting Standards

2.9 Escalation
Confirmation of the base date of the cost plan and the assumption used for
calculating escalation.
2.10 Locality Index
Confirmation of the locality factor used and basis of applying factor.
2.11 Exchange Rate
Exchange rate applicable for overseas procured items including FF&E.
2.12 Asset Acquisition & Asset Realisation
Details of land purchases included in estimate and any asset realisations
relied upon.
2.13 Risks and Contingencies
Details of specific risks having a bearing on the estimate;
Contingency allowances included in estimate; and,
Value Management workshops undertaken.
2.14 ESD and Sustainability Initiatives
A schedule of items and allowances
2.15 Staging Costs
A schedule of assumptions and allowances.
2.16 Benchmarking
Details of other projects upon which benchmarking has been undertaken
and details of major inputs; e.g. Building cost/HPU/bed, Building cost/unit
(e.g. theatre/bunker), FF&E cost/m
2
FF&E cost/unit (e.g. theatre/bunker),
Fees etc..
2.17 Fees
Details of fee allowances.
2.18 FF&E
Details of FF&E allowances; and,
Summary of FF&E cost report.
2.19 ICT
Details of ICT allowances; and,
Summary of ICT cost report.
2.20 Budget Reconciliation
Full reconciliation of cost plan against budget and previous cost plan.
Reconciliation of each cost plan to be maintained progressively so that all
cost plan adjustments are progressively visible.
2.21 Life Cycle Cost
Cost Planning and Reporting Standards

Refer to separate HI document Life Cycle Costing Guidelines.
3.0 Cost Plans
Cost Plans are to be included as applicable and to the pro-forma as supplied in Appendix C
of this Document (Cost Planning and Reporting Standards).
3.1 Cost Plan Summaries
Include for Cost Plan summaries as required for the particular Cost Plan
stage.
3.2 Cost Plan
Include the detailed cost plan.


Cost Planning and Reporting Standards




APPENDIX B

PRO-FORMA FOR STANDARD
COST PLAN

Cost Planning and Reporting Standards


COVER PAGE:








COST PLAN REPORT
NUMBER [Ref]


for


[PROJECT PHASE/ PART]

[PROJECT NAME]

[PROJECT LOCATION]



[Date]




Prepared by
[insert logo or name of company]







Prepared for:


Cost Planning and Reporting Standards


INSIDE COVER PAGE:





CONTENTS
1. Executive Summary
2. Outline of Cost Plan
2.01 Introduction
2.02 Scope of Project
2.03 Basis of Cost Plan
2.04 Specific Inclusions
2.05 Specific Exclusions
2.06 Drawings & Information Used
2.07 Area Measurement
2.08 Procurement & Market Assumptions
2.09 Escalation
2.10 Locality Index
2.11 Exchange Rate
2.12 Asset Acquisition & Asset Realisation
2.13 Risks & Contingencies
2.14 ESD & Sustainability Initiatives
2.15 Staging Costs
2.16 Benchmarking
2.17 Fees
2.18 FF&E
2.19 ICT
2.20 Budget Reconciliation
2.21 Life Cycle Costs
3. Cost Plans
3.01 Cost Plan Summaries
3.02 Cost Plan

Appendices
[List Appendices]
PROJECT CONSULTANTS
HI Project Director: [insert name]
Project Manager: [insert name and company]
Cost Manager: [insert name and company]
Architect: [insert name and company]
Structural & Civil Engineer: [insert name and company]
MEP Services Engineer: [insert name and company]
Landscape Architect: [insert name and company]
[Insert others or delete as appropriate]

QUALITY SYSTEM STATUS
Revision No: ____ [insert] Issue Date: _________[insert]
Controlled Doc No: ______[insert] Checked By: _________[insert]
Distribution: _______________________________________________[insert]
Header
Footer
Cost Planning and Reporting Standards


PAGES:






1 INTRODUCTION
This Report has been prepared by _____________________________ [insert company name].
The Report is based on information provided by _________________________________ [insert]
and includes all works completed up to the end of _________ [date] and forecast final cost of the
Project to completion.

[INSERT OTHER TEXT AS APPROPRIATE]



[INSERT REMAINDER HEADINGS AND BODY TEXT AS PER CONTENTS LIST]


Header
Footer
Cost Planning and Reporting Standards


APPENDICES SECTION COVER PAGE:











APPENDICES




Header
Footer
Cost Planning and Reporting Standards

OTHER APPENDIX COVER PAGE:












APPENDIX [letter]
[NAME OF APPENDIX]

[INSERT DOCUMENTS ON FOLLOWING PAGES]




Header
Footer
Cost Planning and Reporting Standards





APPENDIX C

PRO-FORMA FOR STANDARD COST PLAN
SUMMARIES
Cost Planning and Reporting Standards
12518 6.0 rlbrpts 6.9 nswhealthcpguidelines

CP1 COST PLAN SUMMARY
Job Ref.
NPWC /
Cost Plan
Single / Multiple
Building Project
Building Type Code Project / Building Job Ref.
Location
Date BPI
Current
Client
Tender
Locality Index
Physical Cost / Other Factors
Full Area
m
2

Area
%
Cost
Weight
%
Current
Building Cost
$
Cost/m
2

$
Cost
Fully Enclosed Cov. Area

100
FECA
Rate/Cost

Unenclosed Cov. Area


UCA
Rate/Cost

Gross Floor Area (GFA)

Building Rate / Cost

Departmental Area Total

Current $ Tenders $
Travel & Eng Area Total

Net Construction Cost

Area Efficiency

Gross Construction Cost

No. of Storeys *

Total Project Cost

Building Height *

End Total Cost

Floor / Floor Height *

Type of Contract:

Wall / Floor Area Ratio *

Time for Completion
POP Ratio *
Special Factors:
Facility Scope
- Bed numbers
- Bed numbers/m2
Level of facility
Locational factors
Proportion of new build/refurbishment
Extent of refurbishment
Allowances for significant abnormals




FF&E (% of Construction
Cost)



Shape / Description:
Drawing References:







* Not included in Multiple Building Project Summary
No. GCC/No. TEC/No
Internal Car Spaces
Cost Planning and Reporting Standards

CP4 ELEMENTAL SUMMARY
Job Ref.
PROJECT:
G.F.A. : m2 BUILDING:
Code Element
%
BC
Cost / m2
$
Cost
$
1 SB Substructure
2 CL Columns
3 UF Upper Floors
4 SC Staircases
5 RF Roof
6 EW External Walls
7 WW Windows
8 ED External Doors
9 NW Internal Walls
10 NS Internal Screens and Borrowed Lights
11 ND Internal Doors
12 WF Wall Finishes
13 FF Floor Finishes
14 CF Ceiling Finishes
15 FT Fitment
16 SE Special Equipment
17 SF Sanitary Fixtures
18 PD Sanitary Plumbing
19 WS Water Supply
20 GS Gas Service
21 SH Space Heating
22 VE Ventilation
23 EC Evaporative Cooling
24 AC Air-conditioning
25 FP Fire Protections
26 LP Electric Light and Power
27 CM Communications
28 TS Transportation Systems
29 SS Special Services
00 PR Proportion of Preliminaries

BUILDING COST (BC) 100

30 CE Centralised Energy Systems
31 AR Alterations and Renovations
32 XP Site Preparation
33 XR Roads, Footpaths and Paved Areas
34 XN Boundary Walls, Fencing and Gates
35 XB Outbuildings and Covered Ways
36 XL Landscaping and Improvements
37 XK External Stormwater Drainage
38 XD External Sewer Drainage
39 XW External Water Supply
40 XG External Gas
41 XF External Fire Protections
42 XE External Electric Light and Power
43 XC External Communications
44 XS External Special Services
45 XX External Alterations and Renovations
00 PR Proportion of Preliminaries
46 YY

CONSTRUCTION COST - CURRENT / TENDER DATE

Cost Planning and Reporting Standards

CP5 TRADE SUMMARY
Job Ref.
PROJECT:
G.F.A. : m2 BUILDING:
No Trade
%
BC
Cost / m2
$
Cost
$
1 General Items
2 Preliminaries
3 Demolition
4 Groundworks
4.1 Excavation
4.2 Filing and hardcore
4.3 Paper and plastic membranes
4.4 Underpinning
4.5 Rock stabilisation
5 Piling
5.1 Driven piling
5.2 Cast in-situ piling
6 Concrete
6.1 In-situ concrete
6.2 Formwork
6.3 Permanent metal formwork system
6.4 Reinforcement
6.5 Prestressing
6.6 Slip formed construction
6.7 Precast concrete
6.8 Tanking
7 Masonry
8 Stonework
8.1 Natural stonework
8.2 Artificial stone, terracotta and similar work
9 Structural steel
10 Metalwork
11 Woodwork
12 Glazing
13 Hardware
14 Access floors
15 Partitions
16 Roofing
17 Suspended ceilings
18 Windows
19 Doors
20 Finishes
20.1 In-situ applied finishes
20.2 Metal lathing
20.3 Plasterboard, fibrous plaster, plaster acoustic tiles and similar
20.4 Tile, slab, block or sheet finishes, pavings and carpets
20.5 Division strips and inserts
21 Painting
22 Fitments
23 Hydraulics
24 Drainage
25 Electrical Installations
26 Mechanical Installations
27 Exterior Elements
27.1 Landscaping
27.2 Roadworks
CONSTRUCTION COST CURRENT / TENDER DATE
Cost Planning and Reporting Standards

CP6 PLANNING UNIT COST PLAN DETAILS
Job Ref.
COST PLAN SUMMARY PROJECT:
Date of
Estimate :


BUILDING:

OPTION:

Base Date of
Estimate for
escalation :

PLANNING UNIT Briefed Measured


H.P.U. Area
m2
H.P.U. Area
m2
Cost
$
Cost
$/m2

1.00 General Acute
1.01 Medical m2
1.02 Surgical m2
1.03 Paediatrics m2
1.04 Mental Health m2

Sub total - - $ -

2.00 Sub Acute
2.01 Mental Health m2
2.02 Drug & Alcohol/Detox Unit m2
2.03 Assessment and Rehabilitation m2
2.04 Rehabilitation and Day Hospital m2
2.05 Palliative Care m2
2.06 Abulatory Care m2

Sub total - - $ -

3.00 Obstetrics
3.01 Birthing/Delivery Unit m2
3.02 Maternity m2
3.03 Gynaecology m2
3.04 Neonatal m2

Sub total - - $ -

4.00 Procedures
4.01 Emergency m2
4.02 Medical Imaging m2
4.03 Day Procedures m2
4.04 Intensive Care m2
4.05 Operating Suite m2
4.06 Mortuary/Post Mortem m2

Sub total - - $ -

5.00 Non Inpatient
5.01 Outpatients and Allied Health m2
5.02 Dental m2
5.03 Blood Bank m2
5.04 Pathology m2
5.05 Sexual Assault m2
5.06 Pharmacy m2
5.07 Imaging m2
5.08 Oncology m2
5.09 MRI / PET / Cyclotron ect. m2

Sub total - - $ -

6.00 Corporate Services
6.01 Linen m2
6.02 CSSD m2
6.03 Engineering Services m2
6.04 Stores m2
6.05 Domestic Services m2
6.05 Security m2
6.07 Biomedical m2
6.08 Food Services m2
6.09 Cafeteria (Staff/Pubic) m2
6.10 IT Services m2
6.11 Medical Records m2

Sub total - - $ -
Cost Planning and Reporting Standards



COST PLAN SUMMARY

PLANNING UNIT

Briefed Measured


H.P.U.
Area
m2
H.P.U.
Area
m2
Cost
$
Cost
$/m2

7.00 Administration
7.01 Child Care m2
7.02 Main Entry/Reception m2
7.03 Admissions and Discharge m2
7.04 Nursing Admin m2
7.05 Conference, Education and Library m2
7.06 Research m2
7.07 Staff Accommodation m2
7.08 Tenants m2
7.09 Area Executive m2

Sub total - - $ -

8.00 Community Health
8.01 Mental Health m2
8.02 Child Health m2
8.03 Dental m2
8.04 Community Health m2

Sub total - - $ -

9.00 Alterations to existing Structures
(Sub divide alterations)


10.00 Travel and Engineering
10.01 Inter Unit Space m2
10.02 Plant Rooms and Ducts m2
(sub divide T&E for alterations) m2

Sub total - - $ -

BUILDING COST (BC) - - $ -

11.00 Site Specifics e.g.
External Works item
External Services item
Stormwater Detention item
Temporary Works item
Earthquake Provisions item
Heritage Provisions item

12.00 Project Specifics e.g.
Central Energy and Plant item
Lifts No
PABX etc item
Car Park m2
Courtyard m2

NET CONSTRUCTION COST (NCC) - - $ -

13.00 Allowances, overheads and Margins
Main Contractor's Preliminaries item
Main Contractor's Overheads and Profit item
Staging Costs item
Locality Allowance item


GROSS CONSTRUCTION COST (GCC) - - $ -

Cost Planning and Reporting Standards

COST PLAN SUMMARY

PLANNING UNIT

Briefed Measured


H.P.U.
Area
m2
H.P.U.
Area
m2
Cost
$
Cost
$/m2


18.00 Special Provisions
Escalation item
Prolongation and Delay Costs item
Contributions item
Other item

19.00 Contingencies
Design Contingency % of GCC item
Planning Contingency % of GCC item
Construction Contingency % of GCC Item
Client Contingency % of GCC item

NET END TOTAL COST (NETC) Sub total - - $ -

HI MANAGEMENT COSTS
% of Project
End Cost

END TOTAL COST (ETC)
Notes :
All costs must exclude GST



14.00 Fees
Consultant Fees % of GCC item
Authority Fees and Charges % of GCC item
Area Health Division Costs % of GCC item

15.00 FF&E

Furniture, Equipment, Artworks
(Sub divide FF&E into categories) % of GCC item

16.00 ICT

Infrastructure and Systems
(Sub divide ICT into categories) % of GCC item
17.00 Land Acquisition & Property Settlement
Land Purchase item
Property Settlements item




TOTAL PROJECT COST (BASE COST) - - $ -

Cost Planning and Reporting Standards




APPENDIX D

PRELIMINARIES PRO FORMA
(INDICATIVE)
Cost Planning and Reporting Standards




APPENDIX E

CONTINGENCIES






Contingency Requirements
1 2 3 4 5 6 7 8
Nr HI Contract Stage (Completion) Cost Stage Procurement
responsibility
Project Contingency
(% costs)
Client Contingency
(% costs)
Total Contingency
(% costs)
Treasury
Guidance (%)
0 CSP
HI Benchmarking Tool
Includes Project Cont
C Only
A
l
l

H
I

Design 5
25% 40% 33 100% DD&C Const 5
D&C Planning* 5
1
Master Planning

Health Facility Briefing System
Cost Plan A
Includes Project Cont
C Only Design 5
15% 30% 33 100% DD&C Const 5
D&C Planning* 5
2
Feasibility - Concept Design (Business
Case)

Cost Estimate P50*
Cost Plan B
Includes Project Cont
C Only Design 5
10% 25% 18 - 33% DD&C Const 5
D&C Planning* 5
3 Schematic Design (PDP)
Cost Plan P70*
Cost Plan C1
Includes Project Cont
D&C Pre Tender Estimate
C Only Design 2.5
10% 20% 11 - 18% DD&C Const 5
D&C Planning* 2.5
D & C Procurement Point
5 Design Development
Updated Cost Plan P80*
Cost Plan C2
Includes Project Cont
DD&C Pre Tender Estimate
C Only HI Design 2.5
7.5% 15% 11 18% DD&C HI Const 5
D&C Con Planning* 0
DD & C Procurement Point
6 Construction Documentation
Revised Cost Plan P90*
Cost Plan D
Includes Project Cont Construct Only Pre Tender
Estimate
C Only HI Design 2.5
5% 12.5% 5 - 11% DD&C Con Const 5
D&C Con Planning* 0
Construct Only Procurement Point
7 Start of Construction Contract
C Only HI Design 2.5
2.5% 10% n/a DD&C Con Const 5
D&C Con Planning* 0
8 Project Commissioning Final Account
C Only HI Design 0
0% 2.5% n/a DD&C Con Const 2.5
D&C Con Planning* 0






Contingency Requirements
Accompanying Notes

Column 1 provides a stage number for each design stage during the process

Column 2 Identifies the HI Contract Stage Terminology

Column 3 Identifies the Cost stages aligned to the design stages

HI Benchmarking Tool

The HI Benchmarking tool is being designed to provide a high level budget, the tool utilises historic data and
considers a limited number of parameters;
Facility scope (bed numbers / m2)
Level of facility
Locational factors
Proportion of New Build / Refurbishment
Extent of Refurbishment (if any)
Allowances for significant abnormals

At present this is not undertaken in a formally recorded process, the intention is to develop a tool to allow
AHSs to provide high level budget information in line with HI.

Health Facility Briefing System

The HFBS system (subject to some development) will have the ability to generate a budget estimate which
is more sophisticated than the benchmarking tool. One of the issues raised in the initial consultation stage
related to the QSs continuity of involvement in the overall process, and that the limited extent of the
historic data that they hold on which they base their budgets. The HFBS system holds a significant amount
of historic information, both in terms of actual achieved costs and on Australia wide projects, it therefore
provides a much more extensive basis for budgeting.

Cost Plan A D have already been defined within Health

Probability (P) Each cost plan has a probability rating this relates to the level of certainty that cost plan
provides P 70 represents a cost plan that has a 70% chance of being delivered within budget, as the stages
progress the Probability level increases. The benefit of this is that the cost plan represents a realistic
expectation of the level of certainty based on the information available. The P level P50 for example does
not represent that the budget is likely to be exceeded by 50%, but that there is a 50% chance of the budget
being exceeded, the contingency sums still need to accurately reflect the level of risk for the project at each
stage. The probability level includes the project contingency allocated to each design stage.

Escalation Escalation should be accounted for on the sum total of the base cost, project contingency and
client contingency. Costs should be expressed at a base point in time (we have currently standardised
projects currently to 30/07/08) and as a total escalated in accordance with the proposed delivery program.
This allows for delivery timescales to be flexed and a revised escalation calculation assessed from the base
point, it also allows us to raise awareness of the impact of time on the costs of the project.

Column 4 - Procurement related Responsibility

The Framework as detailed needs to be applied to a number of different procurement options, the broad
philosophy is that regardless of the chosen procurement route the total design work needs to be
completed, the difference is in the party that is responsible for the design activity. The summary table
considers the following procurement criteria;

Construct Only (full design)
Design & Construct (D&C)
Design Development & Construct (DD&C)

The key difference between D&C and DD&C relates to the extent to the design that the contractor
is expected to undertake. D&C requires a greater extent of contractor design than a DD&C.

At this stage PPP and Construction Management have not been fully considered.

Column 5 & 6 - Contingency

Contingency has been divided into two separate elements, with two separate owners to recognise the
ownership of risk in a project. No adjustment or allocation of contingency shall occur without HI Director
approval.

Project Contingency

This is intended for risks that can be owned and managed by the project, based on the information available
to them at the appropriate stages. The QS should make sufficient provision for risks as identified within the
three categories Design, Construction and Town Planning.

Client Contingency

This is intended to capture risks outside of the project that the project team can have little or no influence
over. Items such as scope definition, changes in legislation, best practice and government policy, and the
impact of government reprioritisation.

Risk should generally transfer from the Client contingency to the project contingency, during development
of the project, and then either be realised or mitigated, for example the summary table shows project
contingency static at 15% for the initial phases, as SPP and PDP relate more to scope definition which is
provided for within the client contingency that falls during these stages from 20% to 5%, as the project is
developed and defined.

The percentages indicated in the summary table are taken as normal percentages, in all cases this
percentage will be reviewed by the PDPL or PDPR in conjunction with the project team to establish the
appropriateness of the allowance compared to the known and unknown risks of the project. As such the
allowance will be increased and decreased depending upon the level of risk assessed in the project.

At all stages the cost plan produced by the QS will include the project contingency, but exclude the client
contingency, it is important that the two are kept separate to allow the management of the contingency
sums. Both contingencies are based on the base costs identified by the QS rather than a client contingency
on base cost and project contingency.

Column 7 Total Allocated Contingency

This column identifies the total normal risk allocation for the project a combination of the project and
client contingencies.







Contingency Requirements
Column 8 - Treasury Guidance on Contingency

Treasury have provided guidance (within the Draft Capital Project Estimating (for construction) version no.1
dated 20
th
December 2006 Budget estimating & contingencies, pages 13 - 19), which has been considered
as part of developing this analysis. This guidance identifies what Treasury considers to be appropriate risk
allocations during a projects development. It is noted that any risk allocation that is significantly above or
below the range identified would have to be substantiated.

The risk percentages noted by Treasury represent a proportion of the total project costs, so an allocation of
50% for risk, actually represents 100% of base cost. Percentages in column 10 have been amended from the
report to reflect risk as a % of base costs.
Cost Planning and Reporting Standards





APPENDIX F

PRO-FORMA FOR STANDARD
CASHFLOW
Cost Planning and Reporting Standards





APPENDIX G

PRO-FORMA FOR VARIATION
REGISTER
Cost Planning and Reporting Standards






APPENDIX H
FORMAT FOR FINANCIAL (MONTHLY)
REPORTING

Cost Planning and Reporting Standards


FORMAT FOR FINANCIAL (MONTHLY) REPORTING

Each Cost Plan Report must include the following standard headings (as indicated by
numbered, bold text) and content as described in dot-points below:
Refer to Appendix I for Pro-forma for Financial (Monthly) Report.
1.0 Financial Report Structure
Each Financial Report must include the following:
Introduction;
Project Summary;
Variation Report;
Cashflow Report; and,
Appendices, incorporating detailed:
Cost Report;
Cashflow Report; and,
Sundry Reports as appropriate.
Introduction
The introduction of the Financial Report is to include fundamental information on:
Company responsible for preparing the Financial Report;
Period for which the Report is valid; and,
Information provided and on which the Report is based.
Project Summary
The Project Summary of the Financial Report is to include the following cost data abstracted
from the HI Portal Financial Report:
Forecast Final Cost.
The Project Summary must also include the following supplementary sections:
Risk Position, detailing
Original contingency amount;
Variations;
Remaining contingency;
Statement of adequacy of contingency to complete the project; and,
Statement of committed and uncommitted costs.
Budget Position, detailing:
Initial Budget;
Budget Transfers;
Cost Planning and Reporting Standards


Funded Scope Changes;
Current Budget; and,
Variance of Current Budget against Forecast Final Cost.
Explanatory Notes, detailing any:
Specific exclusions;
Specific inclusions;
Threats to the project; and,
Monthly movements in cost or contract status.
Variation Report
The Variation Report is to be linked to the detailed variation register included in the Appendices
and to include the following:
Value/number of approved variations;
Value/number of unapproved submitted variations;
Value/number of un-submitted variation; and,
Value of proposed variations.
Cashflow Report
The Cashflow Report is to be linked to the detailed cashflow included in the Appendices and to
include the following:
Approved project cashflow;
Indicative cashflow for current financial year;
Monthly update of forecast to actual; and,
Monthly movements/changes.
Appendices
The Appendices are to include detailed Monthly Reports in accordance with the Standard Pro-
forma for:
Cost Plan information;
Variations Register (refer to Appendix G of this Document, Cost Planning and Reporting
Standards for pro-forma);
Cashflow Report (refer to Appendix F of this Document, Cost Planning and Reporting
Standards for pro-forma); and
Other Reports, Correspondence, information etc., as appropriate.


Cost Planning and Reporting Standards






APPENDIX I
PRO-FORMA FOR STANDARD
FINANCIAL (MONTHLY) REPORT
Cost Planning and Reporting Standards


COVER PAGE:








FINANCIAL REPORT
NUMBER [Ref]


for


[PROJECT NAME]

[PROJECT LOCATION]



[Date]




Prepared by
[insert logo or name of company]








Prepared for:


Cost Planning and Reporting Standards


INSIDE COVER PAGE:






CONTENTS

1. Introduction
2. Project Summary
2.1 Forecast Final Cost
2.2 Risk Position
2.3 Budget Position
3. Variation Report
4. Cashflow Report

Appendices
[List Appendices]
APPENDIX A - COST PLAN INFORMATION
APPENDIX B - VARIATION REGISTER
APPENDIX C - CASHFLOW REPORT
[INSERT OTHERS AS REQUIRED]

Header
Footer
PROJECT CONSULTANTS
HI Project Director: [insert name]
Project Manager: [insert name and company]
Cost Manager: [insert name and company]
Architect: [insert name and company]
Structural & Civil Engineer: [insert name and company]
MEP Services Engineer: [insert name and company]
Landscape Architect: [insert name and company]
[Insert others or delete as appropriate]

QUALITY SYSTEM STATUS
Revision No: ____ [insert] Issue Date: _________[insert]
Controlled Doc No: ______[insert] Checked By: _________[insert]
Distribution: _______________________________________________[insert]
Cost Planning and Reporting Standards


PAGE 1:






1 INTRODUCTION
This Report has been prepared by _____________________________ [insert company name].
The Report is based on information provided by _________________________________ [insert]
and includes all works completed up to the end of _________ [date] and forecast final cost of the
Project to completion.


Header
Footer
Cost Planning and Reporting Standards


PAGE 2:




2 PROJECT SUMMARY
2.1 Forecast Final Cost
1. Authority Fees $ XX
2. Network and NSW HI costs $ XX
3. Professional fees $ XX
4. Land $ XX
5. Early works and decanting $ XX
6. Construction $ XX
7. Major equipment and FF&E $ XX
8. ICT $ XX
9. Escalation $ XX
10. Commissioning and relocation $ XX
11. Other $ XX
12. Contingency $ XX
Forecast Total Project End Cost $ XX
2.2 Risk Position
1. Budget design contingency $ XX
2. Budget planning contingency $ XX
3. Budget construction contingency $ XX
4. Budget executive contingency $ XX
Total budget contingency $ XX
5. Approved variations (X no) $ XX
6. Unapproved submitted variation (X no) $ XX
7. Unapproved variations (X no) $ XX
8. Proposed variations $ XX
Total proposed and actual variations $ XX
9. Remaining contingency $ XX
10. Committed costs $ XX
11. Uncommitted cost $ XX
12. Percent committed % XX
2.3 Budget Position
1. Initial Budget $ XX
2. Budget Transfers $ XX
3. Funded Scope Changes $ XX
4. Current Budget $ XX
Variance Current Budget vs. Forecast Final Cost $ XX


Header
Footer
Cost Planning and Reporting Standards


PAGE 3:





2.4 Explanatory Notes
[Insert text]

3 VARIATION REPORT
[Insert text]

4 CASHFLOW
[Insert text]


Header
Footer
Cost Planning and Reporting Standards


APPENDICES SECTION COVER PAGE:











APPENDICES




Header
Footer
Cost Planning and Reporting Standards


APPENDIX A COVER PAGE:











APPENDIX A
COST PLAN INFORMATION
[USING PRO-FORMA AS APPLICABLE]


[INSERT DOCUMENTS ON FOLLOWING PAGES]




Header
Footer
Cost Planning and Reporting Standards


APPENDIX B COVER PAGE:











APPENDIX B
VARIATION REGISTER

[INSERT DOCUMENTS ON FOLLOWING PAGES]




Header
Footer
Cost Planning and Reporting Standards


APPENDIX C COVER PAGE:











APPENDIX C
CASH FLOW REPORT
[USING PRO-FORMA AS APPLICABLE]

[INSERT DOCUMENTS ON FOLLOWING PAGES]




Header
Footer
Cost Planning and Reporting Standards


OTHER APPENDIX COVER PAGE:











APPENDIX [letter]
[NAME OF APPENDIX]

[INSERT DOCUMENTS ON FOLLOWING PAGES]




Header
Footer

You might also like