abalt solutions limited - 2005 INTRODUCTION TO HYDROCARBON EXPLOITATION Abalt Solutions Introduction to Hydrocarbon Exploitation 2005 Abalt Solutions Limited. All rights reserved Development Phase Well Costing Abalt Solutions D r i l l i n g T e c h n o l o g y - W e l l C o s t i n g 2005 Abalt Solutions Limited. All rights reserved Well Economics Maximizing revenue by: Increase in probability of finding hydrocarbons. Controlling costs of Drilling and Production. Planning and Design of wells to produce at optimum flow rates with respect to safety and reliability. Development Phase September October 2005 abalt solutions limited - 2005 INTRODUCTION TO HYDROCARBON EXPLOITATION Abalt Solutions D r i l l i n g T e c h n o l o g y - W e l l C o s t i n g 2005 Abalt Solutions Limited. All rights reserved Drilling Contracts Common forms of drilling rig contracts Day Rate Day Rate Incentive Footage Turnkey Most common type is the day rate contract. Abalt Solutions D r i l l i n g T e c h n o l o g y - W e l l C o s t i n g 2005 Abalt Solutions Limited. All rights reserved Drilling Contracts Day Rate Contracts Operator in total control of drilling operation Contractor paid daily rate for use of rig Example of rates- Mobilization and Demobilization Operational rate Stand by rate Shut down rate Repair rate Force Majeure rate Extra equipment etc. Development Phase September October 2005 abalt solutions limited - 2005 INTRODUCTION TO HYDROCARBON EXPLOITATION Abalt Solutions D r i l l i n g T e c h n o l o g y - W e l l C o s t i n g 2005 Abalt Solutions Limited. All rights reserved Drilling Contracts Day Rate Incentive Bonus per foot Significant component of contractors revenue. Well drilled according to drilling programme. Contractor can advice on type of bit (not decide on it) Faster the drilling, more effective Requires high level of Supervision and adherence to Operators Policies. Operator has control of drilling Provides material and equipment to drill the well except rig. Abalt Solutions D r i l l i n g T e c h n o l o g y - W e l l C o s t i n g 2005 Abalt Solutions Limited. All rights reserved Drilling Contracts Footage Contract Rate per foot to pre determined depth, after which day rate format. Contractor supplies bits. Operator can take control anytime and revert to day rate. Contract specifies conditions for good well integrity. Suitable where downhole risks such as lost circulation are low. Development Phase September October 2005 abalt solutions limited - 2005 INTRODUCTION TO HYDROCARBON EXPLOITATION Abalt Solutions D r i l l i n g T e c h n o l o g y - W e l l C o s t i n g 2005 Abalt Solutions Limited. All rights reserved Drilling Contracts Turn Key Contracts Lump sum paid to contractor to drill to TD or pre determined depth. Contractor purchases material and equipments. Operator is liable to Government for any issues or risks taken during drilling Operator places observer on rig during operations. Useful contract in regions where Operator has no base or Contractor has good track record. Turn key contract is common when drilling market is low. Turn key contracts are tendered than negotiated. Abalt Solutions D r i l l i n g T e c h n o l o g y - W e l l C o s t i n g 2005 Abalt Solutions Limited. All rights reserved Drilling Contracts Negotiating the contract What you want from the contract ? What the contractor wants Know what you are prepared for Exploit your strengths Know what the contractor is prepared to take Get a win/win agreement Minimum Maximum Service Lowest Rated Highest Rated Rig choice Expensive Cheap Rates Contractor Operator Development Phase September October 2005 abalt solutions limited - 2005 INTRODUCTION TO HYDROCARBON EXPLOITATION Abalt Solutions D r i l l i n g T e c h n o l o g y - W e l l C o s t i n g 2005 Abalt Solutions Limited. All rights reserved Drilling Cost Categories Fixed Costs: Wellheads, bits, site preparation etc. Unit Costs: Bulk Barite , cement etc. Day Rate Costs: rig hire, rental tools etc. Some companies use Tangible and Intangible Costs Tangible costs are Unit and fixed costs. In Tangible costs are day rates. Abalt Solutions D r i l l i n g T e c h n o l o g y - W e l l C o s t i n g 2005 Abalt Solutions Limited. All rights reserved Drilling Cost Categories To Minimize Drilling costs- Specify fit for purpose materials for well Minimize NPT Optimization of drilling times with respect to safety and reliability Competitive prices on materials Minimize overheads. Development Phase September October 2005 abalt solutions limited - 2005 INTRODUCTION TO HYDROCARBON EXPLOITATION Abalt Solutions D r i l l i n g T e c h n o l o g y - W e l l C o s t i n g 2005 Abalt Solutions Limited. All rights reserved Day Rate Costs- Land Rigs 1500 Mud Logging services 5000 Electric Logging 1200 Mud engineering services 2500 Cementing services 50,000 Rig(2000 HP) 25,000 Rig(1000 HP) Cost/day($) The Costs above are a rough guide and depend upon market conditions and locations. Abalt Solutions D r i l l i n g T e c h n o l o g y - W e l l C o s t i n g 2005 Abalt Solutions Limited. All rights reserved The Authorisation for expenditure is the budget for a well and prepared and signed by a senior manager from the Operator. It contains Project Description Summary of expenditure Partners shares Well breakdown costs AFE Development Phase September October 2005 abalt solutions limited - 2005 INTRODUCTION TO HYDROCARBON EXPLOITATION Abalt Solutions D r i l l i n g T e c h n o l o g y - W e l l C o s t i n g 2005 Abalt Solutions Limited. All rights reserved AFE Abalt Solutions D r i l l i n g T e c h n o l o g y - W e l l C o s t i n g 2005 Abalt Solutions Limited. All rights reserved Factors affecting well costs Well costs for a single well depend upon- Geographical location Type of well Drill ability Hole depth Target Profile Sub surface problems Rig costs Completion type Knowledge of area: wild cat, exploration or development Development Phase September October 2005 abalt solutions limited - 2005 INTRODUCTION TO HYDROCARBON EXPLOITATION Abalt Solutions D r i l l i n g T e c h n o l o g y - W e l l C o s t i n g 2005 Abalt Solutions Limited. All rights reserved Drilling Time estimate Drilling time on hole, circulation, wiper trips , tripping , side tracking , directional work and hole opening. Flat times spent on running and cementing casing, make up BOP and wellheads. Testing and completion times Formation evaluation time Rig up and down Non Productive time (NPT) Abalt Solutions D r i l l i n g T e c h n o l o g y - W e l l C o s t i n g 2005 Abalt Solutions Limited. All rights reserved Well Costs Rig Costs Tangibles Services Development Phase September October 2005 abalt solutions limited - 2005 INTRODUCTION TO HYDROCARBON EXPLOITATION Abalt Solutions D r i l l i n g T e c h n o l o g y - W e l l C o s t i n g 2005 Abalt Solutions Limited. All rights reserved Well Costs Rig Costs Cost of hiring drilling rig and associated equipments. Depends upon rig rate per day ($/day) Rig rate depends upon : Type of rig Market conditions Length of contract Days on well Mobilization and Demobilization of rig Supervision Other charges Abalt Solutions D r i l l i n g T e c h n o l o g y - W e l l C o s t i n g 2005 Abalt Solutions Limited. All rights reserved Well Costs Tangible Costs Refer to products used on the well. Casing Tubing Completion equipment Wellhead accessories Bits Core heads Cement products Mud products Solid control consumables Fuel Other supply materials Development Phase September October 2005 abalt solutions limited - 2005 INTRODUCTION TO HYDROCARBON EXPLOITATION Abalt Solutions D r i l l i n g T e c h n o l o g y - W e l l C o s t i n g 2005 Abalt Solutions Limited. All rights reserved Well Costs Services Costs related to any service on the well. Communication: Telephone, data transfer-lump sum or cost/day. Rig positioning Logging open and cased hole Renting and running tolls such as MWD/LWD Downhole motors for directional surveys Consumables for solid control Mud and directional engineering services such as personnel, software etc. Running surveys to determine azimuth or hole angle. Cost of rental equipment and personnel. Renting cementing and mud logging unit and personnel. Ad hoc costs of Fishing tools and personnel only if required. Casing and downhole tool Each of the items are costed for individual hole section and a total cost is produced Abalt Solutions D r i l l i n g T e c h n o l o g y - W e l l C o s t i n g 2005 Abalt Solutions Limited. All rights reserved Time vs. Depth Bases for all daily drilling cost estimates. For AFE purposes, it is recommended the most likely drilling time curve be used. Development Phase September October 2005 abalt solutions limited - 2005 INTRODUCTION TO HYDROCARBON EXPLOITATION Abalt Solutions D r i l l i n g T e c h n o l o g y - W e l l C o s t i n g 2005 Abalt Solutions Limited. All rights reserved Non Productive Time Any time that has been spent for routine or abnormal operations which are carried out as a result of failure. It is important to realize that each step should follow preceding step without delay. Each step should take least possible time with good practise. Abalt Solutions D r i l l i n g T e c h n o l o g y - W e l l C o s t i n g 2005 Abalt Solutions Limited. All rights reserved Non Productive Time Classification of NPT Repair Time Rectification time Client time Development Phase September October 2005 abalt solutions limited - 2005 INTRODUCTION TO HYDROCARBON EXPLOITATION Abalt Solutions D r i l l i n g T e c h n o l o g y - W e l l C o s t i n g 2005 Abalt Solutions Limited. All rights reserved Non Productive Time Repair Time Time spent on repairs on the rig and related equipment during which drilling operations is shut down. Any operation that might be carried out to place the well in safe conditions before attempting repair and on completion returning the well to former status. Waiting on spare parts, weather or personnel before normal drilling operations are carried out. Abalt Solutions D r i l l i n g T e c h n o l o g y - W e l l C o s t i n g 2005 Abalt Solutions Limited. All rights reserved Non Productive Time Rectification time Time spent in overcoming downhole problems that delay operations. Some of the operations are : Freeing stuck pipe Fishing lost cones Squeeze cement Well kill operation Development Phase September October 2005 abalt solutions limited - 2005 INTRODUCTION TO HYDROCARBON EXPLOITATION Abalt Solutions D r i l l i n g T e c h n o l o g y - W e l l C o s t i n g 2005 Abalt Solutions Limited. All rights reserved Non Productive Time Client Time Time spent on operations requested by client that was not included in the drilling program earlier. These are not NPT, but indirectly linked and might affect the AFE. Operations are Plugging back Extra coring Extra logging