OFFICE OF CHIEF ENGINEER PANKI THERMAL POWER STATION PANKI-KANPUR
No. /PTPS/CE//MPD/O/H Estimate (III) Dt: OFFICE MEMORANDUM Sanction is hereby accorded to the Budget Estimate for over hauling of unit no. III (105 MW), PTPS, Panki, Kanpur during the year 2013-14 amounting to Rs. 3407.38 lacs (Rs Thirty four Crores Seven Lakhs Thirty Eight Thousand Only) chargeable to accounting Head 74.101 to 74.108, 74.113, 74.116 to 74.118, 74.120, 71.621, 71.631, 71.711. The Budget Estimate has been registered in this office at Sl. No ......................... for 2013-14. (ANAND KUMAR) CHIEF ENGINEER No. /PTPS/CE//MPD/O/H Estimate (III) Dt: Copy forwarded to the following for information & n.a. 1. Director (Technical), UPRVUNL, 8 th floor, Shakti Bhawan Extn, 14-Ashok Marg, Lucknow. 2. C.E. L-1(TO), UPRVUNL, 14 th floor, Shakti Bhawan Extn, 14-Ashok Marg, Lucknow. 3. CGM (Finance), UPRVUNL, 8 th floor, Shakti Bhawan Extn, 14-Ashok Marg, Lucknow. 4. S.E. (O&M)-I/II/III/HQ, PTPS, Panki, Kanpur. 5. Dy. CAO, CFA & BO, PTPS, Panki, Kanpur. 6. Ex. Engineer (MPD), PTPS, Panki, Kanpur. (ANAND KUMAR) CHIEF ENGINEER
2
BUDGET ESTIMATE FOR OVERHAULING OF UNIT No. III (105 MW) PANKI THERMAL POWER STATION, PANKI KANPUR YEAR 2013-14 (PROPOSED IN OCT - NOV. 2013) INDEX 3
SL. No. DETAILS Paae No. 1 Abstract of the Estimate 4 2 A Report, Details of the Estimate 5-6 3 BOILER PLANT AND AUXILIARIES (BMD) 7-12 4 TURBINE PLANT AND AUXILIARIES (TMD) 13-18 5 GENERATOR & ELECTRICAL EQUIPMENTS ( EMD) 19-26 6 CONTROL AND INSTRUMENTATION EQUIPMENTS (C&I MD) 27-29 7 COAL HANDLING EQUIPMENTS (CHD) 30-32 8 ECMD-I 33-34 9 EDD 35 9 OGD 36-38 10 TRANSPORT DIVISION 39 4
ESTIMATE FOR OVERHAULING OF UNIT NO. III PANKI THERMAL POWER STATION DURING THE YEAR 2013-14 AN ABSTRACT
REPORT Details of the Estimate An estimate amounting to Rs. 3407.38 lacs (Rs Thirty four Crores Seven Lakhs Thirty Eight Thousand Only) has been framed to meet out expenditure of Overhauling of Unit No. III (105 MW) of PTPS Panki during the year 2013- 14. S.N. NAME OF WORKS/ DIVISIONS SUPPLY/ SPARES (Rs. in Lac) WORKS (Rs. in Lac) CONSUMABLES (Rs. in Lac) AMOUNT (Rs. in Lac) 1 BOILER PLANT AND AUXILIARIES (BMD) 807.39 488.30 65.49 1295.69 2 TURBINE PLANT AND AUXILIARIES (TMD) 469.50 227.00 17.71 714.21 3 GENERATOR & ELECTRICAL EQUIPMENTS (EMD) 347.35 205.45 13.50 566.30 4 CONTROL AND INSTRUMENTATION EQUIPMENTS (C&I MD) 284.50 16.30 6.00 306.80 5 COAL HANDLING EQUIPMENTS (CHD) 20.00 5.00 304.50 329.50 6 ELECTRICITY DISTRIBUTION DIVISION (EDD) 5.00 4.00 --- 9.00 7 ECMD-I 43.38 26.13 --- 69.51 8 OGD 19.90 17.00 --- 36.90 9 Transport Division
12.75
12.75
TOTAL 1976.64 1023.54 407.20 3407.38 5
Estimate covers the overhauling of Boiler and its auxiliaries which includes Replacement of worn out /damaged tubes and bends in pressure parts including taking out all coils of PSH & ECONOMISER, O/H of Furnace, duct ,pent house, expansion bellow, spring support etc, Replacement of C/S Pinion assembly in all the mills, Overhauling of Ball Mill circuits including Vapour Fans, RCFs, Cyclone Separators, Classifier, mill ducting, Overhauling of ID/FD Fans, PA Fans including connected duct/ pipes, O/H of H.P Valves, O/H of Ash handling Plants, Replacement of internals of ESP fields, Replacement of ball mill main bearing, Insulation work of Boiler Plant equipment and auxiliaries, Radiography of H.P.joints etc. The Estimate covers O/H of Turbine & its auxiliaries which includes Capital O/H of T/G set, O/H of regenerative system, Butter-Fly Valves and other valves including replacement of damaged valves & pipe lines, repairing of servo motor & Oil guards etc., Thermal & Spray insulation of Turbine, steam & water Pipe lines, O/H of BFPs, CEPs, SOP, Hydraulic coupling, CT fans, ACW pumps etc., O/H of LH CW pumps, Butter-Fly Valves & Traveling water screens etc., Repairing of CW pump spares, Submersible pumps, Vertical pump etc. The Electrical system covers O/H of Generator, O/H of HT & LT motors, Protection & Testing, O/H of transformer, O/H of Switch Gear. Switch Yard, OH of Field breaker etc. Cabling works, Work of ESP and other misc. works. Major works Includes Overhauling of 6.6KV HT motors, Repairing of stator of 6.6KV HT motors, Repairing of rotors of 6.6KV HT motors, Re-shafting of rotor of 6.6KV HT motors, Replacement of rotor bars of diff.6.6KV motors, Overhauling of diff.0.4 KV LT motors, Overhauling of .4KV slip ring motors, Repairing of LT motor stators, Re-shafting of diff.LT motor rotors, Repairing of diff. LT motor rotors, Repairing of bearing housings & end covers, Testing, Servicing & Calibration of Relays, Repairing/Retrofitting of Relays, Testing of CTs & transformers, Motors & LAs etc. Centrifuging of diff. Transformer etc., The Estimate also covers Civil works of Auxiliaries foundation, Trench cover, Maintenance of roof and other miscellaneous works. The Estimate shall be executed by EE (BMD), EE (TMD), EE (EMD), EE (C&I), EE (CHD), EE (ECMD-I) Under direct supervision of S.E.-I, S.E.-II, S.E.-III, S.E.-HQ, PTPS Panki Kanpur, The Expenditure shall be met from U.P.R.V.U.N.L. Funds.
6
ESTIMATE FOR OVERHAULING OF UNIT No. III, PANKI TPS DURING THE YEAR 2013-14
BOILER MAINTENANCE DIVISION ESTIMATE FOR O/H FOR UNIT NO- 03 FOR THE YAER 2013 An estimate amounting to Total Rs 1362.41 Lacs (Rs THIRTEEN CRORES SIXTY TWO LACS FOURTY ONE THOUSANDS ONLY) has been framed to cover the cost of overhauling of boiler and auxiliaries of unit no. 3 under Boiler Maintenance Division during the year 2013-14. Provision has been made in the estimate for various spares of Boiler mostly from OEMs. The rates given in the estimate are current financial market rates. The estimate will be chargeable to the head of account of Boiler Plant equipment and auxiliaries under overhauling. Provision has also been made in the estimate for replacement of water wall tube. Platen SH tubes, Primary SH tubes/bends in the boiler after survey during O/H. Provision has been made for of all weak and damaged internals of ESP 1 NAME UPRVUNL (2X105 MW Units) Panki TPS 2 FUNDS UPRVUNL, Panki Kanpur. 3 STATION Panki Thermal Power Station, Panki, Kanpur. 4 DEPARTMENT HEAD Panki Thermal Power Station, Panki, Kanpur 5 MAJOR HEAD Plant and Machinery 6 SUB HEAD Overhauling of Plant, Equipments & Auxiliaries of Unit No. III 7 NAME OF ESTIMATE Overhauling of Plant, Equipments & Auxiliaries of Unit No. III for the Year 2013-14 DETAILS OF AMOUNT REQUIRED: Sr. No. Details of Works/ Divisions Amount (Rs. In Lac) A/C Head 1 BOILER PLANT AND AUXILIARIES (BMD) 1295.69 74.101, 74.102,74.103, 74.104,71.621,71.631,71.711 2 TURBINE PLANT AND AUXILIARIES (TMD) 714.21 74.105,74.106,74.107,74.108,74.120,71.6 3 GENERATOR & ELECTRICAL EQUIPMENTS ( EMD) 566.30 74.116 4 CONTROL AND INSTRUMENTATION EQUIPMENTS ( C&I MD) 306.80 74.117,74.113,71.621,71.711 5 COAL HANDLING EQUIPMENTS (CHD) 329.50 74.118 6 ELECTRICITY DISTRIBUTION DIVISION 9.00
7 ECMD-I 69.51
8 OGD 36.90 71.531,74.122 9 Transport Division 12.75
Fields. Major spares/equipments are to replaced in the Milling circuits and Fans where erosion is main cause of concern. Provisions in brief are as under:- 1 Replacement of worn out/damaged tubes and bends in pressure parts including taking out all coils of PSH & ECONOMISER. 2. O/H of Furnace. 3. Replacement of C/Shaft assembly in all the mills. 4. Reversal of rim gear of Ball Mill - 3A 5. Overhauling of Ball Mill circuits including Vapour Fans, RCFs, Cyclone Separators, Classifier, mill ducting. 6. Replacement of liners of Ball Mill- 3A/3B/3C. 7. Overhauling of ID/FD Fans, PA Fans including connected duct/pipes. 8. O/H of H.P. Valves. 9. O/H of Ash handling plants. 10. Replacement of internals of ESP fields. 11. Replacement of Ball Mill main NDE bearing= 01 Nos.
Total Rs. 1031.21 Lacs (RS. TEN CRORES THIRYY ONE LACS TWENTY ONE THOUSANDS ONLY)
Sr.No Schedule Ch.Head Activity Amount in lacs
Spare Works Total 1 Schedule I 74.101 Pressure Parts 261.750 273.50 634.75 2 Schedule II 74.102 Ball mill Ckt 104.50 55.94 235.39 3 Schedule III 74.103 P.A/Vap/I D/F D Fan 122.10 22.70 166.50 4 Schedule IV 74.104 Ash Handling system 38.11 37.77 75.82 5 6 7 8 Schedule V 71.621 71.631 71.711 Lubricants Grease Consumable Different types of HP & LP valves 13.10 0.24 51.50 32.50
17.50 13.10 0.24 103.12 66.77 8
ESTIMATE FOR O/H FOR UNIT NO 3 FOR YEAR 2013 Ch.Head 74.101 SCHEDULE-1 COST OF WORKS
COST OF SPARES Sr. No Items Qty. Amount(Rs in Lacs) Remarks 1 Boiler Tubes & Bends 9000 mtr. 67.50 BHEL 2 SS Coal Nozzle Tips 16 nos 26.00 BHEL 3 Coal Nozzle Casting & Seall Plates 16 nos 7.50 BHEL 4 Retainers, Binders, Clamps, Sleeves & Shields L.S 15.00 Tender/ BHEL 5 Fuel inlet Elbow(ceramic lined) 16 nos 4.00 Tender 6 Air Coal Nozzle 32 nos 06.00 BHEL 7 Oil Diffuser nozzle 16 nos 9.00 BHEL 8 Large Cone Assy. 16 nos 4.00 BHEL 9 Spare for Secondary Damper LS 02.50 BHEL 10 Deflector Plates For ESP Inlet 27 nos 3.00 BHEL 11 Cassette Baffles & Sleeves etc. LS 7.00 BHEL 12 Refractory materials 100MT 25.00 ACE 13 Vapour Burner Assy. 04 nos. 8.25 BHEL 14 Welded wire Mesh LS 2.00 Tender 15 Steel Section MS and Carbon steel 90 MT 65.00 BHEL & SAIL 16 Miscellaneous L.S 10.00 - TOTAL Rs. 261.750 LACS Sr.No WORKS QUANTITY AMOUNT(Rs in lacs) 1 Overhauling of Press Parts including corners & Triflux, L.S 200.00 2 Insulation of boiler L.S 35.00 3 Repairing of hot air ducts/spring Support /flue gas duct before ESPs etc L.S 05.00 4 Buck Stay Beams expansion bellow etc.. L.S 2.50 5 Surface hardening of SS tips Elbows & CI nozzle. L.S 15.00(By L&T) 6 Deployment of Ex. BHEL & FES Supervisors L.S 15.00 7 Radiography of boiler tube L.S 7.00 8 Overhauling of PC Feeders LS 4.00 9. Misc. Works L.S. 05.00 TOTAL RS 273.50 LAC
9
Ch.Head -74.102 Schedule-II COST OF SPARES
Sr.No Iteam Qty Amount (Rs in Lacs) Remark 1 Ball Mill Pinion 01 nos 03.00 BHEL 2 Counter shaft 01 nos 03.00 BHEL 3 Coupling 634 H/478B & Grid element 00 sets each 0.00 OEM 4. Elbow gland assembly of ball mill 0 nos. 0.0 TENDER 5. Mill Motor bearings (White metal) 06 nos. 0.90 TENDER 6 Bearing pedestal of ball mill motor 00 nos. 0.0 BHEL 7 Main Bearing of Ball mill 01 no. 14.50 TENDER 8 Double link chain for RCF 00 set 00.00 BHEL 09 Double roller chain of RCF 00 nos. 0.00 TENDER 10 Conical spiral spring 12 nos. 03.60 BHEL 11 Drive head shaft of RCF 01 nos. 0.60 BHEL 12 Tension head shaft of RCF 3 nos. 1.1 BHEL 13 Mill Piping & Vapour piping 110 mtrs. 7.5 TENDER 14 Bearing of ball mill/ RCF L.S. 4.0 TENDER 15 Various Studs and bolt of mill circuit LS 01.50 TENDER 16 RGB input pinion 1 nos. 07.00 OEM 17 C/ shaft bearing housing 0 nos. 0.00 BHEL 18 Armour insert 6 nos. 7.8 BHEL 19 Mill liners 01 set 45.00 M/s. AIA 20 Misc. Items LS 05.00 TENDER TOTAL Rs 104.50 LACS Cost of works Sr.No Items Quantity Amount (in lacs of Rs) Remarks 1 Overhauling of Ball Mills 01 jobs 12.85 TENDER 2 Replacement of main bearing 01 no 1.30 TENDER 3 Overhauling of RC chain feeder, cyclone, classifier LS 7.66 TENDER 4 Overhauling of milling ckt and pipeline LS 16.00 TENDER 5 Replacement of mill liners 01 set 06.50 TENDER 6 Reversal and alignment of rim gear 01 no. 3.30 TENDER 7 Replacement of foundation of RGB of ball mill 1 no. 2.33 TENDER 8 PC Bunker cleaning and repairing 1 job 1.0 7 Misc works LS 5.00 TENDER TOTAL Rs 55.94 LACS 10
Ch.Head -74.103 Schedule-III
Cost of works
TOTAL Rs 22.70 LACS
COST OF SPARES Sr.No Item Quantity Amount (Rs in Lacs) Remarks 1 ID fan Shaft 01 no. 04.70 BHEL 2 ID fan Impeller 01 nos 05.20 BHEL 3 R.G Vane Assy & Suction Chamber 01 no. 09.00 BHEL 4 Diffuser part (A+B) with inner drum 01 nos 10.00 BHEL 5 Inner bearing case 28,bushing ID Fan & case 24 & Bush of F D fan 02 nos 2.00 BHEL 6 Vapour Fan casing 03 nos 34.50 BHEL 7 Vapour fan Impeller(1AO&2Co type) 02 nos 14.00 BHEL 8 Suction chamber with distance piece 03 nos 19.50 BHEL 9 Vapour fan shaft 01 no. 2.50 BHEL 10 Hub of vapour fan 02 nos. 0.80 BHEL 11 Bearing 22224 CK /C3,22228C/C3,29322,22224C/C3, 22322CK/C3 etc LS 08.00 TENDER 12 White metal bearing of ID fan motor 04 nos 0.70 TENDER 13 Gear Oil pump of ID fan 02 nos 00.60 OEM 14 Cartridge of LDO pump 00nos 00.00 OEM 15 Lube oil pump for P A /Vap Fans 04 nos. 0.60 OEM 16 Impeller casing & cooling pipe 01 set 03.00 BHEL 17 Coupling sets for ID, PA fans 04 set 2.00 BHEL 18 Misc spares. LS 05.00
TOTAL Rs 122.10 LACS Sr.No Itaems Quantity Amount (in lacs of Rs) 1 Overhauling of Vapor Fans 03 nos 5.70 2 Overhauling of PA /ID/FD fans 06 nos. 08.00 3 Replacement of I D fan suction chamber & RG Vane assembly. LS 3.00 4 Removal of scrap generated by BHEL during overhauling work LS 1.0 4 Misc works LS 5.00 11
CH.HEAD 74.104 SCHEDULE IV
COST OF WORKS
Total Rs. 37.77 Lacs CH.HEAD 71.621 Schedule-V
Cost Of spares Sr.No Name of Spares Quantity Amount (Rs. In lacs) BHEL/NON BHEL 1 Spares of ESP of 2x105 MW' LS 25.30 BHEL 2 Supply of fludomat fluid coupling and other spare of clinker grinder LS 1.76
3 Supply of spares for feed gate/sluice gate of clinker grinder LS 6.03 OEM 4 Spares supply of clinker grinder, hydraulic gate/3way valve/seal. LS 5.02
Total Rs 38.11 Lacs Sl .No Works Amount (in lacs of Rs) 1 Overhauling of ESP including misc. tests(Clean air, G.D test, CAVT etc.). 25.00 2 Various works in ash handling plant during overhauling 5.00 3 Rotation of ash slurry lines in 2x105 MW 1.71 4 Overhauling of Clinker Grinder and replacement of various parts of flushing operators 1.06 5. Misc. Works 5.00 Lubricants Sl .No Works Quantity Amount (in lacs of Rs) Remarks 1 Servo system -46 1260 lt 13.10 IOC 2 Servo system -68 630 lt IOC 3 Servo system -121 420 lt IOC 4 Servo system -176/ 220 1890 lt IOC 5 ServoMesh-320 1260 lt IOC 6 Servo Coat -120/40 2000 kg IOC 7 Servo cylinder-530/460 630 lt IOC Total Rs. 13.10 Lacs 12
CH. HEAD-71.731 1- Grease 210 kg 0.24 Lac IOC CH.Head -71.111
H.P. & L.P. Valve, NRV etc. Cost of spare
Consumables Sl .No conumables Quantity Amount (in lacs of Rs) Remarks 1 M S and H T nuts and bolts LS 04.00 TENDER 2 Jointing sheet, asbestos rope, gland LS 06.00 OEM
packing rings.
3 High crome grinding media 75.00 MT 40.00 TENDER 4 Misc. like Holdite, shims, cotton waste rustoline etc LS 1.50 TENDER Total Rs. 51.50 lacs Sr.No Name of Spares Quantity Amount (Rs. In lacs) BHEL/NON BHEL 1 Self sealing ring 20 0.37
2 Gun metal bush 30 0.40
3 HP valve spindle 40 0.45
4 HP valve including globe valve of 2.5 & 4. 45 10.00
5 Safety valve 08 3.30
6 LP valve different size 20 3.50
7 Bearing of different size 30 0.50
8 Safety valve of different sizes 12 4.50
9 Bonnet of different sizes 10 0.65
10 Wedge of different sizes 15 1.35
11 HP valve of different sizes including low load line valve 30 02.50
12 Jointing sheets 00 0.00
13 Misc. Valve & its spare LS 5.00
Total Rs. 32.52 Lac. 13
Cost of work Sl .No Works Amount (in lacs of Rs) 1 Overhauling of HP, LP valve and safety valve 05.00 2 NRV 150mm and above 2.50 3 Maintenance of / , 1, 1/1/2, 2.5 HP valve & control valve 4.00 4 Reconditioning of FRS valve, Reconditioning of 65 mm to 150mm HP valve, repairing of valve bonnet and repairing of valve bush 4.50 5. On line setting of safety valve 1.50 Total Rs. 17.50 Lacs. 14
Name of Division TURBINE Name of estimate 74.105 Rs.714.21 Lac
TURBINE MAINTENANC0E DIVISION Report on estimate for the overhauling of TG Set of unit # 3 proposed in the month of aug. - oct. 2013. An estimate amounting to Rs. 714.21Lac (Rupees Seven Crore Fourteen Lac twenty one Thousand) has been framed to cover the cost of overhauling of Turbo-Generator set and its auxiliaries of Unit no III (105 MW) Panki Thermal Power Station, Panki, Kanpur during the year 2013-14. The provision has been made under the estimate for various spares, consumables, Steel sections, Lubricants, and other misc. spares and works. The estimate will be chargeable to the head of account of Turbine & its auxiliaries under overhauling. The provision has been made for capital Overhauling of Turbo-Generator as Unit will cross approximately 42,000 running hours up to July 2013, since last capital overhaul of the TG set was carried out during 2008. The provisions in brief for Capital O/H of various works are as under. 1 - Capital Overhauling of TG set. 2- O/H of Regenerative system, Debris Filter, Butter-Fly Valves and other valves including replacement of damaged valves & pipe lines. 3- Repairing of Servo motor & Oil guards etc. 4- Thermal & Spray insulation of Turbine, Steam & water Pipe lines, 5- O/H of BFPs, CEPs, SOP, Hydraulic coupling, CT fans, ACW pumps etc. 6- O/H of LH & HH CW pumps, Butter-Fly Valves, CT Fans & Traveling water screens etc. 7- Repairing of CW pump spares, Submersible pumps, Vertical pump etc. Estimate for the overhauling of TG Set of unit # 3 during the financial year 2013- 14 TURBINE MAINTENANCE DIVISION 2x105 MW PANKI THERMAL POWER STATION PANKI - KANPUR Department head OVERHAULING OF TG SET# 4 & ITS AUXILIARIES Head of account Amount of estimate 15
Summary of Estimate for Overhauling of Turbine & Auxiliaries of Unit # 4 During the Year-2013-14
TOTAL Rs. 714.21 Lac Sl. SCHEDULE Ch. Head Activity Amount in Lacs of Rs No
Spares Works Total 1 Schedule1A & 1B 74.105 & 74.106 O/H of Turbine 153.50 177.00 330.50 2 Schedule IIA& IIB 74.107 & 74.108 O/H of BFP & other auxiliaries 265.00 32.00 297.00 3 Schedule IIIA& IIIB 74.120 O/H of CW Pumps & auxiliaries 51.00 18.00 69.00 4 Schedule V 71.6 Lubricants & Grease -- -- 9.10 5 Schedule VI 71.6 Consumables -- -- 8.61 16
CH. HEAD-74.105 & 74.106 Estimate for overhauling of unit # 3 (for the year 2013-14) o Overhauling of turbine CH. HEAD-74.105 & 74.106 SCHEDULE 1B
Total Rs.177.00 Lacs SCHEDULE 1A
in Lac 1-(A) Cleaning of water box of condenser 0.40 (B) Complete cleaning of condenser along 2.60
with tubes
2- Cleaning & Overhauling of Debris Filter 0.50 3-(A) Cleaning of turbine oil coolers tubes 2.50 (B) Complete O/H & cleaning of Turbine oil
Coolers
4- Replacement of drain drip pipe lines etc. 1.50 5- Retubbing of LP Heaters 5.00 6- Retubbing of Seal oil coolers 2.00 7- Replacement of Expander 1.50 8- O/H of HP/LP Steam/Water side Valves, NRVs etc, 4.00 9- Insulation of turbine & associated pipe lines 4.00 10- Insulation of pipe lines, valves & other auxiliaries 7.00 11- Painting of turbine & associated auxiliaries 3.00 12- BHEL Works 120.00 13- repairing of HP Turbine diaphragm 19.00 14- Miscellaneous Works 4.00 COST OF WORKS Sl. No Details of work Amount (Rs.) 1- TG Spares 90.00 2- Studs, Nuts & bolts 12.00 3- Serration packing 0.50 4- Flexible hoses 0.50 5- Steam pipes & bends 10.00 6- Steam drain valves 3.50 7- Turbine oil & seal oil coolers water regulating valves 1.00 8- BFV spares 1.00 9- Spares of centrifuging machine 2.00 10- Spares of debris Filter & Flushing Pump 16.00 11- M.S. ERW pipes of different sizes 3.00 12- Hydrogen coolers (2 Nos.) 10.00 13- Misc. spares 4.00 17
COST OF SPARES Sl. No Spares Amount (Rs.) in Lac Total Rs.153.50 Lac 18
OVERHAULING OF BFP & OTHER AUXILIARIES CH. HEAD - 74.107 & 74.108 SCHEDULE IIB COST OF WORK Sl. No _______ Details of work _________________________ Amount (Rs.) in Lac
CH. HEAD-74.107 & 74.108 SCHEDULE IIA COST OF SPARES Sl. No _______ Spares ________________________________ Amount (Rs.) in Lac
1- O/H of BFP 10.00 2- O/H of CEP 3.00 3- O/H of SOP 1.50 4- Cleaning of Dearator & replacement of pipes 1.00 5- O/H of BFP, HP & LP Valves 10.00 6- O/H of ACW Pumps & CT Fans 0.50 7- Painting of piping & structure 0.50 8- Maintenance work of DG Set 1.00 9- O/H of Air Wash Pump & other misc. work 1.00 10- O/H of lub oil & working oil coolers of BFP 1.20 11- O/H & repairing of Mech. Seal coolers of BFP 0.30 12- Other misc. works 2.00
Total Rs. 32.00 Lac o OVERHAULING OF BFP & OTHER AUXILIARIES
30 Spares for BFP(new cartrage), Hydraulic coupling &
Dry Disc Coupling & spares of recirculation valve 250.00 2- Spares of CEP 1.50 3- Spares of SOP 0.50 4- ACW pump & CT Fan 2.00 5- Air wash pump 2.00 6- Spares for DG set 2.50 7- Chimney steam exhauster 0.50 8- A.C Cooling pump 1.00 9- HP/LP dozing pump spares 2.50 10- Transfer pump spares 1.50 11- MS - ERW Pipes 1.00 Total Rs. 265.00 Lacs o OVERHAULING OF CW PUMP HOUSE 19
CH. HEAD - 74.120 SCHEDULE III B COST OF WORKS Sl. No ______ Details of work _________________________ Amount (Rs.) in Lac
o OVERHAULING OF CW PUMP HOUSE CH. HEAD - 74.120 SCHEDULE III A COST OF SPARES Sl. Spares _____________________________ Amount (Rs.) in Lac
o OVERHAULING OF TURBINE & AUXILIARIES CH. HEAD-71.6 SCHEDULE V COST OF CONSUMABLES Sl.No ______ Item ______________________ Qty. Amount (Rs. In Lac) 1- Metallic Jointing sheet 275Kg. 2.00 1- O/H of LH pumps & worn out spares 2.00 2- O/H of HH pumps & worn out spares 2.00 3- Removal & disposal of silt from intake channel 2.00 4- Repairing of submersible pump( 10 HP & 5 HP) 5.00 5- O/H of TWS including repairing of worn out spares 1.50 6- Repairing of old & worn out spares of small pumps 1.50 7- O/H of BFVs (900, 1200, 1600 mm) 0.50 8- O/H of cooling tower fans, replacement of nozzles 1.50 Louvers etc
9- O/H of EOT cranes 1.00 10-Misc. Works 1.00 Total Rs. 18.00 Lacs 1- HH pumps (BHM 77) 15.00 2- LH pumps (BHM 70) 15.00 3- Spares for TWS 3.00 4- Spares for CT fan 1.00 5- Fire fighting pump 3.00 6- Screen wash pump 3.00 7- Booster pump 3.00 8- Dredger & connecting piping 2.00 9- Mulsifire system 5.00 10- Misc. spares for pump & valves 1.00 Total Rs. 51.00 Lac 20
o OVERHAULING OF TURBINE & AUXILIARIES CH. HEAD-71.6 SCHEDULE V COST OF LUBRICANTS Sl.No Lubricant ____________ Qty. (Ltr.) Amount (Rs. In Lac) 1- Servo prime-46 4000 6.00 2- Servo torque-10 1260 2.00 3- Servo system-320 420 0.80 4- Servo Gem2/3 _____________ 300Kg ____________ 0.30 Total Rs. 9.10 Lacs 2- Non Metallic Jointing sheet 100Kg. 0.80
3- Neoprene rubber sheet 200Kg. 0.70 4- Spl. Purpose welding electrodes Of various make L/S 1.00 5- Rustolene / Rustclick 200Ltr. 0.50 6- Kerosene Oil 50Ltr. 0.25 7- Holdite (1/2 Kg. Pack) 20Nos. 0.25 8- Hexa blade 100Nos. 0.04 9- M-Seal 30Kg. 0.05 10- Araldite (180gms.pack) 20Pack 0.05 11- Teflon/PVC tape (Various sizes) 50/10roll 0.03 12- Emery cloth/roll (Coarse/Medium/Fine) 300nos/20roll 0.12 13- Lapping paste (Coarse/Medium/Fine) 15nos. each 0.25 14- Hand gloves (Leather/Asbestos) 10pair each 0.20 15- Gland packing of various sizes L/S 0.60 17- Rotary Cutters 10Nos. 0.04 18- Grinding wheels of various sizes 50nos. 0.03 19- Asbestos rope/cloth of various sizes L/S 0.10 20- Hydrogen gas 400Cu.mtr. 0.40 21- CO2 Gas 400Kg 0.50 22- Old dhoti/ Hosiery cloth 600kg 0.20 23- Misc. Consumables L/S 0.50
Total Rs.8.61 Lacs 21
ELECTRICAL MANTENANCE DIVISION Report on budget estimate for overhauling of unit no.3 An estimate amounting to Rs. 566.30 lacs has been prepared to meet-out the expenditure for annual overhauling of Electrical system of Unit No.3 (110MW) of Panki Thermal Power Station, Panki - Kanpur. Cleaning, checking, repairing, replacement, re-shafting, overhauling, testing, and commissioning as per requirement shall be carried-out for various electrical equipments consisting of Generator, Generator transformer, UAT, Reserve transformer, switchyard equipments, HT/LT breakers, HT/LT motors & Cables ion system, CHP and associated MCCs, panels and desks etc. The estimate shall be operated by Executive Engineer, Electrical Maintenance Division, Panki Thermal Power Station, Panki-Kanpur-20 and expenditure shall be booked by Dy.CAO, CFA&BO, PTPS, Panki-Kanpur. ABSTRACT OF SUPPLY: 22
OUT OF ABOVE CONSUMABLES ARE FOR RS. 13.50 AND SPARES ARE FOR RS. 17.50 LACS. WORKS TO BE EXECUTED HEAD : Overhauling Of Unit # 3 FINANCIAL YEAR : 2013-14
Sr. No. DESCRIPTION OF MATERIAL QUANTITY APPROXIMATE VALUE (LACS) MAKE 1. GENERATOR
a) SERVICING /OVERHAULING OF Generator 01 Job 10.00 BHEL b) TESTING OF GENERATOR , Exciter ( Options & mandatory) Lump sum 35.00 BHEL c) REPAIRING OF EXCITER ARAMATURE & SLIP RING 01 Nos. Each 2.50 OTHERS
TOTAL 47.50
2. HT & LT MOTORS-
a) Overhauling of 6.6KV HT motors. 22 Nos. 4.0 Others. b) Repairing of stator of 6.6KV HT motors. Lump sum 8.00 Others. c) Repairing of rotors of 6.6KV HT motors. Lump sum 2.00 Others. d) Re-shafting of rotor of 6.6KV HT motors. Lump sum 16.00 Others. e) Replacement of rotor bars of diff.6.6KV motors. Lump sum 8.00 Others. f) Overhauling of diff.0.4 KV LT motors. Lump sum 4.00 Others. g) Overhauling of 0.4KV slip ring motors. Lump sum 0.50 Others. h) Repairing of LT motor stators. Lump sum 1.00 Others. i) Repairing of diff. LT motor rotors. Lump sum 0.50 Others. j) Repairing of bearing housings & end covers Lump sum 1.50 Others k) Re-tubing of water coolers of BFP motors Lump sum 5.00 Others
TOTAL 50.50
3. PROTECTION & TESTING-
a) Testing, Servicing & Calibration of Relays. Lump sum 6.00 Others c) Repairing of relays. Lump sum 2.00 Others. d) Testing of CTs , Transformers, Motors & LAs etc. Lump sum 7.00 Others. e) Installation & Commissioning of chartless
0.50 Others. 27
records 02 Nos.
f) Installation and commissioning of Battery charger 01 Set 0.50 OEM
TOTAL 16.00
4. TRANSFORMER-
a) Supervision of Overhauling work of GT- III for gasket replacement modification of conservator with air cell, replacement of explosion vent by PRD by TELKs service Engineer and bushing, checking etc. Lump sum 7.50 OEM. b) Assistance in gasket replacement of GT- III modification work & replacement of cooling fans any other associated works etc. 01 Job 2.00 Others. c) Works related to UAT servicing 01 Job 1.50 OEM. d) Centrifuging of diff. transformer. Lump sum 2.50 Others. e) Painting of diff. transformer. Lump sum 2.00 Others. f) Silver electroplating of jumpers/clamps of GTs. & Generator flexibles 01 Job 15.00 Others. g) Fabrication & supply of cooler control panel for GT Unit no.4 & fitment of electrical items to be provided by PTPS , Panki 01 Job 0.75 Others h) Servicing of 01 MVA tx. Lump sum 1.50 Others
TOTAL 32.75
5. SWITCHGEAR-
a) Overhauling & testing work of 6.6KV MOCB/SF-6 breakers. Lump sum 6.50 OEM b) Providing assistance in overhauling of breakers and Overhauling of HT /LT bus sections Lump sum 0.75 Others. c) Replacement of Gaskets & Painting of C- 4 switchgear etc. breaker panel. (6.6 KV as well as 0.4 KV) Lump sum 2.50 Others. d) Overhauling of 0.4KV breaker. Lump sum 50 Nos. 3.00 OEM/others. e) Retrofitting of 0.4KV, LT breakers. 04 Nos. 0.75 OEM f) Replacements of existing bakelite inter panel isolating sheets, through bushings, bus bar support insulators. Lump sum 1.50 OEM g) Rubberized coating on 6.6KV, bus bars. Lump sum 1.00 OEM
TOTAL 16.00
6. SWITCHYARD-
a) Servicing & modification of control/ protection of 220KV SF-6 breaker. Lump sum 1.50 OEM b) Conversion of operating mechanism of existing from pneumatic to motorized including servicing & overhauling. 08 Nos. 2.00 Others. 28
CONTROL & INSTRUMENTATION DIVISION Report An estimate amount of Rs. 306.80 Lac has been framed to meet out expenditure during 2013-14 for overhauling of C&I system and equipments of Unit No. III (105 MW). The major overhauling works proposed to be carried out during this overhauling are Servicing, Repairing and Calibration of Measurement System which includes Transmitters for Pressure, Temperature, Level, Flow, PRT/TC and related Recorders / Indicators. Overhauling of Motorized Actuators for Valves, Dampers & Vanes control, Local Pressure and Temperature gauges, Servicing of Hydrastep, Annunciation System, Checking and calibration of Turbo-Supervisory Equipments including replacement of Transducers. Installation of Interlock & Protection System, Hydrogen purity analyzers, Online Steam & Water analysis system, HEA Igniters & Flame scanners. The estimate shall be operated by Executive Engineer (C&IMD), PTPS, Panki, Kanpur and expenditure shall be booked by Dy. Chief Account Officer, CFA&BO, PTPS, Panki under head 74.117. Executive Engineer (C&IMD) c) Joints tightening of various jumpers and lines. Lump sum 0.20 Others. d) Al. painting of support structures in Lump sum 2.50 Others. e) Revival of earthing systems of Switchyard & equipments Lump sum 20.0 Others
TOTAL 26.20
7. CABLING
a) Laying & Recovery of cables. Lump sum 5.00 Others
TOTAL 5.00
8. ESP-
a) Installation & commissioning of opacity meter. 02 Nos. 2.00 OEM b) Erection of platform for new opacity 02 Nos. 0.20 Others. c) Servicing & overhauling of EP 16 Nos. 1.00 Others. d) Installation & commissioning of IOS. 01 No. 3.00 BHEL.
TOTAL 6.20
9. OTHER MISC.WORKS
a) Overhauling of electrical system of EOT crane. Lump sum 0.50 OTHERS b) Cleaning and repairing of modules of diff.0.4KV MCCs. Lump sum 1.00 OTHERS c) Painting, gasket replacement letter writing on MCCs. Lump sum 1.80 OTHERS d) Servicing different Hoists Lump sum 2.0 OEM
TOTAL 5.30
GRAND TOTAL of works Rs. 205.45 Lacs 29
Total Abstract of budget FOR C&I DIV of proposed overhauling of unit No.III during the month of Aug.-Oct. 2013
Rs 306.80 Lac (Rs. Three Crore Six Lac Eighty Thousand Only)_ COST OF SPARES AND NEW SYSTEMS Sl. No Description Amount (Rs.) in Lacs 1. Spares for Turbo supervisory System (Philips make). 15.00 2. Programmable Digital indicators and Temperature Transmitters. 3.00 3. Spares for Motorized actuator of Valve, vane & damper & Actuator. 10.00 4. Spares for S.H. attemperation control valve & Electrical actuators. 20.00 5. Spares for Hydrastep & Hydratech System. 10.00 6. Design, Engineering, Supply, Erection, Testing & Commissioning of Interlock & Protection System from legacy relays to safety Programmable logic controller or Distributed control system (DCS). 30.00 7. Compensating cable for J, K & S type thermocouples. 2.50 8. Analogue Circular Indicators. 0.5 9. S, J & K type Thermocouples & RTD. 15.00 10. Recording Head for different make Recorders. 5.00 11. Supply, Erection, Networking, Testing & Commissioning of chartless Recorders (15 Nos.). 15.00 12. Pressure & Temperature Gauge. 3.00 13. Supply of Impulse lines. 3.00 14. Supply of Turbo supervisory cable. 2.50 15. Spares for existing of LC-700 System. 10.00 16. Supply, Erection, Testing & Commissioning of Hydrogen Purity System. 10.00 Sl.No. Item/Work Ch.Head Amount in Lacs Rs Maintenance of C&I System (Spares) Maintenance of C&I System (Works) Cable Oil and lubricants Consumables 1. 2. 3. 4. 5. 74.117 74.117 74.113 71.621 71.711 284.50 16.30 3.00 2.50 0.50 30
31
COAL HANDLING DIVISION ESTIMATE FOR OVERHAULING OF UNIT No. 3 FOR THE YEAR 2013-14 NAME : FUND : STATION : DEPARTMENT HEAD : MAJOR HEAD : SUB HEAD : 17. Supply, Erection, Testing & Commissioning online steam & water analysis system for proper monitoring of water chemistry. 35.00 18. Design, Engineering, Supply, Erection, Testing & Commissioning of hardware and logic designing in software required to add the auto loops, contacts & signals provided in Auto control system (C-3 System) with the existing DCS system. 30.00 19. Design, Engineering, Supply, Erection, Testing & Commissioning HEA igniters. 30.00 20. Design, Engineering, Supply, Erection, Testing & Commissioning safe flame scanners 30.00 21. Supply of isolating instrumental transformer 5.00 Total Rs. 284.50 Lac COST OF WORK Sl. No. Description of Work Amount(Rs.) in Lacs 1. Mechanical overhauling of motorizes valve actuator, damper actuator, Cleaning of GVDC/MCC modules & GVDC Panels, purging of P.C. feeder impulse pipe lines. 2.00 2. Overhauling of motors. 0.50 3. Recovery of old & unused cables. 1.00 4. Packing of cutouts & Painting of Panels and Desks. 1.00 5. Welding /Replacement of impulse lines, valves, nipples, thermo wells etc. 0.50 6. Maintenance of Junction boxes and fabrication of new junction boxes as per requirement of site. 0.50 7. Repairing & Servicing of Protection Relays. 1.00 8. Repairing of different electronic cards/recorders. 8.00 9. Erection & commissioning of VFD for RC feeders. 0.80 10. Other C&I works required in O/H. 1.00 Total Rs.16.30 Lac. 32
NAME OF ESTIMATE : HEAD OF ACCOUNT : AMOUNT OF ESTIMATE : An estimate amounting to Rs. 329.50 (Rs. Three overhauling of Unit No.3 of Coal Handling Plant 2x Para 340 of Financial Hand Book Volume-VI COAL HANDLING DIVISION PANKI THERMAL POWER STATION UPRVUNL, PANKI, KANPUR U.P.R.V.U.N.L. PANKI TPS, PANKI, KANPUR PANKI THERMAL POWER STATION PLANT &MACHINARY OVERHAULING OF UNIT No.3 OVERHAULING OF UNIT No. 3 PLANT EQUIPMENT & AUXILIRIES 74.118 Rs.329.50 (Rs.Three Crore Twenty nine Lacs and fiffty thousand only) Crore Twenty Nine Lacs and fifty thousand) only for 05 MW, PTPS, Panki is hereby functioned in terms of 33
Summary of Estimate for Overhauling of Unit No.3 for the year 2013-14
o ESTIMATE OF WORKS Sl.No. Description Amount (Lacs) 1 Strenghening of R.C.Bunker 3A,3B & 3C 02.00 2 O/H of undercarriage of Bulldozer D- 155/D-170 01.00 3 One yearly Maintenance Schedule of Locomotive 02.00
Total 5.00 o ESTIMATE OF SPARES________________________ i _______ Annexure-1(B) Sl.No. Description OEM & Others Quantity Amount (Lacs) 1 Various spares of bulldozer Model BD- 155/170
LS 10.00 2 Spares of Locomotive
LS 10.00
Total
20.00 o ESTIMATE OF STEEL SECTION __________________ ________ Annexure-1(C) S.No. Description Quantity Amount 1 M.S.Plate (Th. 10mm) 5 MT 02.50
ECMD-I BUDGET ESTIMATE iudh rti fQ|rXg dh bdb io-3 dh iLr-fOr vkcRgrfyx" e dR-; tU ot^ flfOy dro! dT fOcjui (1) fQir xg {T= e fOfO/T flfOy dk4 iudh rTi fO|r xt e bdb io-3 dh vTcjgifyx d nRTu Ball Mills dh QimuM*H, vTboMho Qu dh QmuM"iu , ,QoMoQu dr QimMsH BFP x dh QimMsH dr vio^driuiK wer d-; ,Q 1o,PoMo {-= d vic";d di; Rop;iM {-= d vic";d d-;, Vp dol cuiU dT di; re-T ntT dh vic";d wer dT d-; dRT; tTUT iLrifOr ti bi d-; tr o;; fCcj.i r;R fd; w t t-fd Mho,iovTjo-2oi2 ,4 ;oihoihoVho1ho,yo-2oi 1 dh nRfiR vT/fr t ftid vu,iK bi d-; dT djTU e /TUjTf"T :o 18.41 yT[ o;; v^xT i (fCcj.i lyu)- 1yxud-1 bl di; e O;; t- (v) ITeXh (vf) : :o 3.5o yT[ (c) di; (lev e?; iftr) % :o 14.91 yw dy :o 18.41 yi[i o - (2) iudh rTi fQ|rxt d d-y tfx {-= e RyQ Vd dT vur-ft di; iudh rTi fO|r xt d dr^yr ipyu {-= e fLe-r RyQ Vd fOxr 3o oTf 1 vf/Td y x i r i j Iqt e jtU d dTRT tM-"TM voLFTT e t ,O bid icTbvi o difix, Ry ,O fQfVi dr rdTy cnyuT vic";d t i dN LFTTuf ij RyQ yTbu brUh vf/Td f?Ti pdh t fd btu ,Q fMcT d ift; dT i-no fQ"T iyVT rd vt jth t i bil fQ"T iyV Hh fx^r tt jth t i lo-bvi ,Q difix dh fLe-r yx-r-j i;Tx d dTRT v;r [rtc tr xb t ftl jy/L^hij d ift "Th?r cny t-U tr iee prt e fuu ff-r iTexh/ d-; dh rRdty vto";drT t i (fooj.i lyxu)- lyxud-2 Points & Crossing (v) iTexh % :o 12.9o yT[T (c) d-; : :o 2.4o y-[T dy :o 15.3o y-[T o jyT^ dT uohutdjUT dT; (v) iTexh : :o 25.63 yT[t (c) d-; : :o 1.82 ym dy :o 27.45 y-[T O - (3) fQiqr xt dh lvtq didiui d v-o-H; htouT d ;fuv uo-3 dtifyx Vhe d v-o-H; o;olftt dh tr ejEer/ r;tj dj-u dT fQ"-? vuj{T.T dt flfOy dt; i iudh fO|r xt dh lvtq d-yTuh d bd-b 1[;t-3 dh oTftd vTqr tfyx d nRu vtu oiyh QTt; ,tfUl; s i dT vuf-r vtoti vTqr tTf^x d-; tr vi;h Vhe d fy; dy 82 vtoti t-fd fRDr t, fPfUtr fd; x; t, dT fO"Tr vur{t.t dT; dT; ttuT iLrifOr ti d-; tg LOhdr vuc/T 1[;T-07/PTPS/CWCD/ECMD-II/T-126/2012 fnuTd- 14.01.2013 d }TRT v^elf^r /HRif"i :o7,oo,ooo.oo dh LOhdfr iTir t i bl d-; e O;; fu^ufyf^Tr t :- (v) ieXh lev 500 Cjr % :<> 1.35 ym (c) di4 % : 7.00 ym dy : 8.35 yi[] o ------------------- S.No. Description Quantity Amount 1 LDO 500KL 300Lacs
Total
300Lacs o ESTIMATE OF LDO Annexure- 1(E) 35
dy ;fx(dQIO1 +2+3) = : 69.51 y][ 36
ELECTRICITY DISTRIBUTION DIVISION Budget estimate overhauling of unit no. III (105 MW)
WORKS SUPPLY TOTAL (in Rs.) Rs. 4,00,000.00 Rs. 5,00,000.00 Rs. 9,00,000.00 S.No. Description Amount (in Rs.) 1- Works- For New/ Repairing Wiring work and installation of HPSV fittings , MCCB etc. in unit No.03 4,00,000.00 2- Supply- Following material are required during O/H of unit No. III HPSV fittings , chokes of HPSV/ Tube light Fitting , Bulbs for HPSV/HPMV, Tube lights, Ignitors , MCCB , PVC Armored Aluminium wire etc. 5,00,000.00 37
OPERATION GENERAL & WATER TREATMENT PLANT NAME OF DEPARTMENT NAME OF POWER STATION NAME OF DIVISION NAME OF ESTIMATE HEAD OF ACCOUNT AMOUNT OF ESTIMATE U.P.R.V.V.N.L PANKI THERMAL POWER SATION OPERATION GENERAL &WATER TREATMENT PLANT ESTIMATE OF OG DIVISION (INCLUDING WTP) FOR THE OVERHAULING OF UNIT-III O&M : Total Estimated Amount Rs.36.90 LACS 38
BUDGET ESTIMATE OF OVERHAULING OF UNIT-III FOR W.T.P. SUPPLY OF DIFFERENT CHEMICALS FOR WATER TREATMENT PLANT:-
SUPPLY OF DIFFERENT SPARES FOR WATER TREATMENT PLANT:- Ch-74.122
only) ESTIMATE FOR DIFFERENT WORKS IN WTP:- Ch-71.531 S. NO. Description of chemical Quantity Rate (Rs.) Amount(Rs) 1 Bleaching Powder 300 kg 20.00 per kg 6000.00 2 Liquid Ammonia 300 Ltr. 100.00 per lt. 30000.00 3 Hydrazine Hydrate 300 Kg 300.00 per kg 90000.00 4 Fine chemical & Glasswares - - 10000.00 5 Tungeston Lamp for Sp-20D+ 02 Nos. 2000.00 per 4000.00 6 Fire wire for Bomb Calorimeter 200 Mtrs. 20.00 per Mtr. 4000.00 7 Lab instruments i.e. Ph, conductivity, Turbidity meters etc.
300000.00
TOTAL (Rs.) 444000.00 (Rs. Four Lac Forty Four Thousand only) BUDGET ESTIMATE OF OVERHAULING OF UNIT-III FOR W.T.P. Sl. No Description of works Amount (Rs.) 1. Purchasing of spare parts, pipe lines etc. 5,00,000.00 2. Purchasing of service water pump, clarified pump, sludge disposal pump, degasser pump, submersible pump and acid unloading pump 10,00,000.00
Total (Rs.) 15,00,000.00 (Rs. Fifteen Lac only) Supply of different Lubricants in WATER TREATMENT PLANT:- Sl. No Description of works Qty Unit Rate Rs. Amount (Rs.) Chargeabl e Head 1 Servo System -320 100 Ltr 180.00 18000.00 21.102 2 Servo System-40 100 Ltr 175.00 17500.00 3 Servo Gem-3 50 Kg 200.00 10000.00
Total (Rs.)
45500.00
(Rs. Forty Five Thousand Five Hundred 39
TRANSPORT DIVISION
Ch- 74.122 Sl. No Description of works Amount (Rs.) 1. Fabrication, Erection and replacement of various pipes, line etc. and work of leakage arresting in WTP 600000.00 2. Installation of new cation exchanger of SICO plant in WTP 300000.00 3. Installation of 02 Nos. new alum tank in flocculator plant 300000.00 4. Aluminum painting of CST 1,2 & 3 500000.00
Total (Rs.) 1700000.00 (Rs. Seventeen Lac only) S. NO. Description of Work Quantity Amount (in lacs) 1 Overhauling of 6 Ton, 10T & 16T Capacity Departmental Cranes One job for each Crane 7.25 2 Overhauling of Departmental Trucks (02 Nos.) One Job. 1.50 3 Overhauling of Departmrntal Tagger & Trailer One Job for each 2.50 4 Replacement of Tyres, Tubes etc. For departmental vehicles in transport before overhaul. One Job 1.50 Total = Rs.12.75 lacs