S/N DESCRIPTION OF ITEM QTY UNIT RATE AMOUNT BILL NR-ONE MAIN BUILDING STAGE ONE FROM FOUNDATION TO GROUND FLOOR SLAB ALLOW A LUMPSUM FOR MATERIALS AND MEN FOR SETTING OUT OF BUILDING SUM 30,000.00 EXCAVATION AND EARTHWORKS Excavate trench for foundation start up starting from average ground level.(3.6m per partition WITH ACUAL DEPT OF 900mm) 30 Parts. 900 27,000.00 Ditto, for column base (30nr of column Bases) 30 Nr 200 6,000.00 Level and compact bottom of trench to make good to receive concrete for foundation footing. Sum 7,500.00 FOUNDATION CONCRETE Mix and place concrete 1:3:6-19mm aggregate as concrete for foundation footing 150mm thick,against trench. Inclusive of BLINDING FOR COLUMN BASES. CEMENT (50 kg bags) 38 Bags 1,800 68,400.00 SAND (using 10ton tipper) 1 Trip 12,000 12,000.00 GRAVEL (using 15ton tipper) 1 Trip 80,000 80,000.00 LABOUR For mixing of concrete 38 Bags 800 30,400.00 For tapping by mensons 4 Men 3,500 14,000.00 FOUNDATION BLOCKWORK 225mm thick Vibrated hollow sandcrete Block laid in stretcher bond and fix with cement and sand (1:6) - 5 courses on top of foundation footing. 9'' BLOCKS 1,250 Nr 150 187,500.00 CEMENT (50 kg bags) 15 Bags 1,800 27,000.00 SAND (7tons tipper) 1 Trip 12,000 12,000.00 LABOUR For mixing & fixing (MENSON AND HELPER) 1,250 Nr 50 62,500.00 Forward to Collection 564,300.00 BOLINKZ CONSULTS NIG. 07035451166 RESIDENTIAL STOREY BUILDING/PAGE-1 COST ESTIMATE FOR CARCASS OF PROPOSED STOREY BUILDING OF TWO BEDROOM, THREE BEDROOM DUPLEX S/N DESCRIPTION OF ITEM QTY UNIT RATE AMOUNT Filling to Make-up Level Filling with literate earth fill ( red mud) to make up level. 750mm thick-using 7 ton tipper 20 Trips 7,000 140,000.00 Blinding with sharp white sand not exceeding 50mm thick, well prepared to receive concrete using 7 ton tipper. 2 Trips 12,000 24,000.00 LABOUR Labour for spreading 22 Trips 1,500 33,000.00 Labour for tampering, leveling and compacting Sum 10,000.00 LABOUR FOR BACKFILLING EARTH AROUND FOUNDATION BLOCKWORK Sum 5,000.00 Reinforcement Work 12mm high yield bars for column base & STANDS 40 lengt. 1,200 48,000.00 16mm high yield bars 0 lengt. 2,400 - 8mm high yield bars as stirrups. 10 lengt. 800 8,000.00 Binding wire (10kg roll) 1 Roll 3,000 3,000.00 LABOUR Labour for cutting, bending and fixing of reinforcements 30 Nr 900 27,000.00 Concrete Floor Slab 1:3:6-19mm aggregate as concrete for floor slab 100mm thick poured against already prepared surface. CEMENT ( 50 kg bags) 45 Bags 1,800 81,000.00 SAND (using 10 tons tipper) 1 Trip 12,000 12,000.00 GRAVEL (using 15 tons tipper) 1 Trip 80,000 80,000.00 LABOUR MIXING AND PLACING 45 Bags 800 36,000.00 LABOUR FOR TAPPING 4 Men 3,500 14,000.00 Forward to Collection 521,000.00 BOLINKZ CONSULTS NIG. 07035451166 RESIDENTIAL STOREY BUILDING/PAGE-2 COST ESTIMATE FOR CARCASS OF PROPOSED STOREY BUILDING OF TWO BEDROOM, THREE BEDROOM DUPLEX S/N DESCRIPTION OF ITEM QTY UNIT RATE AMOUNT Formwork Sawn treated softwood well fixed to meet required stability as formwork for COLUMN BASES, COLUMNS AND OVERSITE CONCRETE BED not exceeding 250mm girth. 1" x 12'' x 12'' plank 30 Nr 900 27,000.00 3 nail 0.5 Bag 5,000 2,500.00 LABOUR Labour for fixing and stripping off formwork for both columns and edges of ground floor slab. Sum 35,000.00 Forward to Collection 64,500.00 COLLECTION PAGE ONE 564,300.00 PAGE TWO 521,000.00 PAGE THREE 64,500.00 Total Cost For Materials and Labour To Cover For Substructural Works(FROM FOUNDATION TO GROUND FLOOR SLAB) 1,149,800.00 TOTAL COST FOR WORK NEEDED FOR STAGE ONE 1,149,800.00 MATERIALS COST 812,400.00 LABOUR COST 337,400.00 SUPERVISION FEE TO BE NEGOTIATED (NOT INCLUDED) - TOTAL COST FOR WORKS IN THIS STAGE 1,149,800.00 BOLINKZ CONSULTS NIG. 07035451166 RESIDENTIAL STOREY BUILDING/PAGE-3 COST ESTIMATE FOR CARCASS OF PROPOSED STOREY BUILDING OF TWO BEDROOM, THREE BEDROOM DUPLEX S/N DESCRIPTION OF ITEM QTY UNIT RATE AMOUNT STAGE TWO SUPERSTRUCTURAL WORKS ON GROUND FLOOR BLOCKWORK Hollow vibrated sandcrete block laid in stretcher bond and fix with cement and sand (1:6) . 9'' BLOCKS (225mm thick) 1,700 Nr 150 255,000.00 CEMENT for fixing Blocks 25 Bags 1,800 45,000.00 SAND (using 10 tons tipper) 2 Trips 12,000 24,000.00 LABOUR Labour for mixing mortar and fixing of blocks on GROUND FLOOR (MENSON AND HELPERS) 1,700 Nr 50 85,000.00 FORMWORK Softwood fixed as formwork for lintel (THE LINTEL RUNS ALL ROUND BOTH INTERNAL AND EXTERNAL) and columns on ground floor. 1 x 12 x 12" PLANK 65 Nr 900 58,500.00 1 X 9 12" PLANK FOR SOFFIT 15 Nr 470 7,050.00 2 X 2 x 12" TIMBER AS PROPS AND BRACE 20 Nr 200 4,000.00 3 NAIL 1 Bag 5,000 5,000.00 LABOUR Labour for fixing and striping of formwork for lintel and column stand. Sum 45,000.00 REINFORCEMENT WORK Cut and fix the following as reinforcement ; 12mm high yield as reinforcement IN LINTEL 35 Nr 1,200 42,000.00 12mm high yield as reinforcement IN COLUMNS 30 Nr 1,200 36,000.00 Ditto; 8mm as stirrups in lintel and columns spaced @ 300mm c/c. 45 Nr 800 36,000.00 Binding wire (roll of 10 kg) 2 Roll 3,000 6,000.00 LABOUR Labour for cutting, bending and fixing. SUM 40,000.00 Forward to Collection 688,550.00 BOLINKZ CONSULTS NIG. 07035451166 RESIDENTIAL STOREY BUILDING/PAGE-4 COST ESTIMATE FOR CARCASS OF PROPOSED STOREY BUILDING OF TWO BEDROOM, THREE BEDROOM DUPLEX S/N DESCRIPTION OF ITEM QTY UNIT RATE AMOUNT CONCRETE WORK(1:2:4 ) Mix and place reinforced insitu concrete well parked around reinforcement in formwork as concrete in COLUMNS and LINTEL all in ground floor . CEMENT (using 50kg bag) 50 Bags 1,800 90,000.00 SAND ( using 10 ton tipper) 1 Trips 12,000 12,000.00 GRAVEL (using 15 ton tipper) 1 Trips 80,000 80,000.00 LABOUR Labour for mixing and placment of concrete 50 Bags 900 45,000.00 Labour for tapping concrete by mensons. 5 Men 3,500 17,500.00 Forward to Collection 244,500.00 COLLECTION PAGE FOUR 688,550.00 PAGE FIVE 244,500.00 TOTAL COST OF MATERIALS AND LABOUR TO COVER SUPERSTRUCTURAL WORKS AT GROUND FLOOR STAGE TWO 933,050.00 TOTAL COST FOR WORK NEEDED FOR STAGE TWO 933,050.00 MATERIALS COST 700,550.00 LABOUR COST 232,500.00 SUPERVISION FEE TO BE NEGOTIATED (NOT INCLUDED) - TOTAL COST FOR WORKS IN THIS STAGE 933,050.00 BOLINKZ CONSULTS NIG. 07035451166 RESIDENTIAL STOREY BUILDING/PAGE-5 COST ESTIMATE FOR CARCASS OF PROPOSED STOREY BUILDING OF TWO BEDROOM, THREE BEDROOM DUPLEX S/N DESCRIPTION OF ITEM QTY UNIT RATE AMOUNT (STAGE 3) COST FOR DECKING AND STAIRCASE WORK ON FIRST FLOOR FORMWORK 1 x 12 X 12" sawn treated softwood/plank as formwork for soffit of slab, staircase and attached beams. 120 Nr 900 108,000.00 2 x 3 timber as runners 80 Nr 300 24,000.00 Bamboo as props 300 Nr 100 30,000.00 2", 3" and 4" nails for formwork 3 Bag 5,000 15,000.00 1 x 6 board as riser around edges of slab and faces of steps in staircase AND FOR SOFFIT OF BEAMS. 45 Nr 450 20,250.00 LABOUR Labour for entire formwork for suspended slab, attached beams and staircase Sum 100,000.00 REINFORCMENT WORK 12mm high yield bars as main and runners 180 Nr 1,200 216,000.00 16mm high yield as reinforcement in attached beams 30 Nr 2,400 72,000.00 Ditto; 8mm as stirrups 15 Nr 800 12,000.00 Binding wire 2 Rolls 3,000 6,000.00 LABOUR Labour for iron bender to cover for cutting, bending and fixing rods in suspended slab, inclusive of staircase and attached beams Sum 90,000.00 CONCRETE WORK(1:2:4) Mix and place reinforced insitu concrete well parked around reinforcement in formwork as concrete in suspended floor slab, attached beams and staircase. 1:2:4-19mm agg. 150mm thick. CEMENT (using 50kg bag) 100 Bag 1,800 180,000.00 SAND ( using 10 ton tipper) 2 Trip 12,000 24,000.00 GRAVEL (using 15 ton tipper) 2 Trip 80,000 160,000.00 BOLINKZ CONSULTS NIG. 07035451166 RESIDENTIAL STOREY BUILDING/PAGE-6 COST ESTIMATE FOR CARCASS OF PROPOSED STOREY BUILDING OF TWO BEDROOM, THREE BEDROOM DUPLEX S/N DESCRIPTION OF ITEM QTY UNIT RATE AMOUNT LABOUR Labour for mixing and placement of concrete 100 Bag 900 90,000.00 Labour for tapping concrete by mensons. 8 Men 3,500 28,000.00 DAMP PROOF MEMBRANE 1000 gauge hysian polythene proof as dpm for decking. 0 Roll 4,000 - LABOUR Labour for spreading and pinning. Sum - ELECTRICAL INSTALLATION Allow a lumpsum to cover for the installation and piping of electrical circuit and conduit around slab for the purpose of electricity and the likes.( lumpsum to cover for Labour Only) Item 30,000.00 Ditto; to cover for materials Item 95,000.00 TOTAL COST FOR MATERIAL AND LABOUR TO COVER FOR THE DECKING AND STAIRCASE (STAGE THREE) 1,300,250.00 1,300,250.00 MATERIALS COST 962,250.00 LABOUR COST 338,000.00 SUPERVISION FEE TO BE NEGOTIATED (NOT INCLUDED) - TOTAL COST FOR MATERIALS AND LABOUR 1,300,250.00 BOLINKZ CONSULTS NIG. 07035451166 RESIDENTIAL STOREY BUILDING/PAGE-7 COST ESTIMATE FOR CARCASS OF PROPOSED STOREY BUILDING OF TWO BEDROOM, THREE BEDROOM DUPLEX S/N DESCRIPTION OF ITEM QTY UNIT RATE AMOUNT STAGE FOUR SUPERSTRUCTURAL WORKS ON FIRST FLOOR BLOCKWORK Hollow vibrated sandcrete block laid in stretcher bond and fix with cement and sand (1:6) . 9'' BLOCKS (225mm thick) 2,000 Nr 150 300,000.00 CEMENT for fixing Blocks 30 Bags 1,800 54,000.00 SAND (using 7 tons tipper) 2 Trips 12,000 24,000.00 LABOUR Labour for mixing mortar and fixing of blocks on FIRST FLOOR (MENSON AND HELPERS, ALSO TO TRANSFER) 2,000 Nr 60 120,000.00 FORMWORK 1 x 12 X 12" sawn treated softwood/plank as formwork ROOF BEAM. (50% OF INITIALLY USED FORMWORK ARE TO BE RECOVERED) 1 x 12 x 12" PLANK 0 Nr 900 - 1 X 9 12" PLANK FOR SOFFIT 0 Nr 450 - 2 X 2 x 12" TIMBER AS PROPS AND BRACE 0 Nr 200 - 3 NAIL 2 Bag 5,000 10,000.00 LABOUR Labour for fixing and striping of formwork for lintel and column stand. Sum 45,000.00 REINFORCEMENT WORK Cut and fix the following as reinforcement ; 12mm high yield as reinforcement IN LINTEL 35 Nr 1,200 42,000.00 12mm high yield as reinforcement IN COLUMNS 30 Nr 1,200 36,000.00 Ditto; 8mm as stirrups in lintel and columns spaced @ 300mm c/c. 45 Nr 800 36,000.00 Binding wire (roll of 10 kg) 1 Roll 3,000 3,000.00 LABOUR Labour for cutting, bending and fixing. SUM 40,000.00 Forward to Collection 710,000.00 BOLINKZ CONSULTS NIG. 07035451166 RESIDENTIAL STOREY BUILDING/PAGE-8 COST ESTIMATE FOR CARCASS OF PROPOSED STOREY BUILDING OF TWO BEDROOM, THREE BEDROOM DUPLEX S/N DESCRIPTION OF ITEM QTY UNIT RATE AMOUNT CONCRETE WORK(1:2:4 ) Mix and place reinforced insitu concrete well parked around reinforcement in formwork as concrete in COLUMNS and LINTEL all in FIRST floor . CEMENT (using 50kg bag) 50 Bags 1,800 90,000.00 SAND ( using 10 ton tipper) 1 Trips 12,000 12,000.00 GRAVEL (using 15 ton tipper) 1 Trips 80,000 80,000.00 LABOUR Labour for mixing and placment of concrete 50 Bags 900 45,000.00 Labour for tapping concrete by mensons. 5 Men 3,500 17,500.00 Forward to Collection 244,500.00 COLLECTION PAGE FOUR 710,000.00 PAGE FIVE 244,500.00 TOTAL COST OF MATERIALS AND LABOUR TO COVER SUPERSTRUCTURAL WORKS AT FIRST FLOOR STAGE FOUR 954,500.00 TOTAL COST FOR WORK NEEDED FOR STAGE FOUR 954,500.00 MATERIALS COST 687,000.00 LABOUR COST 267,500.00 SUPERVISION FEE TO BE NEGOTIATED (NOT INCLUDED) - TOTAL COST FOR WORKS IN THIS STAGE 954,500.00 BOLINKZ CONSULTS NIG. 07035451166 RESIDENTIAL STOREY BUILDING/PAGE-9 COST ESTIMATE FOR CARCASS OF PROPOSED STOREY BUILDING OF TWO BEDROOM, THREE BEDROOM DUPLEX S/N DESCRIPTION OF ITEM QTY UNIT RATE AMOUNT STAGE FIVE ROOF BEAM AND CONCRETE FASCIAL FORMWORK 1 x 12 X 12" sawn treated softwood/plank as formwork for TEMPLATE, AND OTHER DESIGNS 25 Nr 900 22,500.00 2 x 2 timber as STANDS AND BRACING 50 Nr 220 11,000.00 2", 3" and 4" nails for formwork 1 Bag 5,000 5,000.00 CUPPER NAILS 1 CRT 7,000 7,000.00 PLY BOARD 12 Nr 1,350 16,200.00 LABOUR LABOUR FOR ERECTING SCAFFOLD AND FRAMING OF PARAPET DESIGN AND BOARDING OF ROOF BEAM Sum 50,000.00 SEWING OF PLANKS SUM 10,000.00 REINFORCMENT WORK 12mm high yield bars as main Bars in ROOF beam 15 Nr 1,200 18,000.00 10mm high yield bars as Stirrup for roof beam and parapet 25 Nr 1,000 25,000.00 Ditto; 8mm as stirrup in roof beam 0 Nr 800 - Ditto; 8mm as distribution in parapet 20 Nr 800 16,000.00 Binding wire 1 Rolls 3,000 3,000.00 LABOUR Labour for iron bender to cover for cutting, bending and fixing rods in roof beam and parapet Sum 45,000.00 CONCRETE WORK(1:2:4) Reinforced insitu concrete as concrete in roof beam and concrete fascial CEMENT (using 50kg bag) 35 Bag 1,800 63,000.00 SAND ( using 10 ton tipper) 1 Trip 12,000 12,000.00 GRAVEL (using 10 ton tipper) 1 Trip 80,000 80,000.00 BOLINKZ CONSULTS NIG. 07035451166 RESIDENTIAL STOREY BUILDING/PAGE-10 COST ESTIMATE FOR CARCASS OF PROPOSED STOREY BUILDING OF TWO BEDROOM, THREE BEDROOM DUPLEX S/N DESCRIPTION OF ITEM QTY UNIT RATE AMOUNT LABOUR Labour for mixing and placment of concrete 35 Bags 900 31,500.00 Labour for tapping concrete by mensons. 4 Men 4,000 16,000.00 TOTAL COST FOR MATERIAL AND LABOUR TO COVER FOR CONCRETE FASCIAL AND ROOF BEAM (STAGE FIVE) 431,200.00 MATERIALS COST 278,700.00 LABOUR COST 152,500.00 SUPERVISION FEE TO BE NEGOTIATED (NOT INCLUDED) - TOTAL COST FOR WORKS IN THIS STAGE 431,200.00 BOLINKZ CONSULTS NIG. 07035451166 RESIDENTIAL STOREY BUILDING/PAGE-11 COST ESTIMATE FOR CARCASS OF PROPOSED STOREY BUILDING OF TWO BEDROOM, THREE BEDROOM DUPLEX S/N DESCRIPTION OF ITEM QTY UNIT RATE AMOUNT ROOF WORK ( STAGE SIX) CARCASSING CARPENTRY/TIMBER FRAMING Sawn hardwood of 3.6m(12ft length), well seasoned to required quality, treated with anti-termite treatment solignum or other equal approved timber preservative A 75 x 100mm wall plate. 25 Nr 850 21,250.00 B 50 x 100mm rafters. 55 Nr 650 35,750.00 C 50 x 100mm as hip, valley and ridge board 25 Nr 650 16,250.00 E 50 x 100mm tie beams. 45 Nr 650 29,250.00 F 50 x 75mm purlin @600mm C/C 110 Nr 450 49,500.00 G 50 x 100mm king post/struts/ties. 85 Nr 650 55,250.00 H 50 x 50mm as noggings. 125 Nr 300 37,500.00 K 8mm diameter rods as anchor for wall plate cast into ROOF BEAM at 2 meters spacing C/C on the external walls. 30 Nr 300 9,000.00 ROOF COVERING AND FINISHES ALUMINUM LONG SPAN ROOFING SHEET 0.45mm Guage aluminum STEP TILES long span roofing sheet L Covering to sloping roof not exceeding 40 degrees from horizontal. 210 m 2 1,450 304,500.00 M Extra over for aluminum ridge/hip/valley capping 450mm wide. 90 m 900 81,000.00 LABOUR FOR ROOF FRAMING 150,000.00 LABOUR FOR ROOF INSTALLATION 50,000.00 ROOF WORK TO SUMMARY 839,250.00 LABOUR COST 200,000.00 MATERIAL COST 639,250.00 TOTAL FOR ROOFING 839,250.00 BOLINKZ CONSULTS NIG. 07035451166 RESIDENTIAL STOREY BUILDING/PAGE-12 COST ESTIMATE FOR CARCASS OF PROPOSED STOREY BUILDING OF TWO BEDROOM, THREE BEDROOM DUPLEX S/N DESCRIPTION OF ITEM QTY UNIT RATE AMOUNT SUMMARY OF WORK FOR MATERIALS AND LABOUR STAGE ONE (FROM FOUNDATION TO FLOOR SLAB/DPC) 1,149,800.00 STAGE TWO (SUPERSTRUCTURAL WORKS ON GROUND FLOOR) 933,050.00 STAGE THREE (FIRST FLOOR DECKING, STAIRCASE AND BEAMS) 1,300,250.00 STAGE FOUR (SUPERSTRUCTURAL WORKS ON FIRST FLOOR) 954,500.00 STAGE FIVE (PARAPET AND ROOF BEAM) 431,200.00 STAGE SIX (ROOFING) 839,250.00 COST OF CONSTRUCTION (MATERIALS AND LABOUR) OF RESIDENTIAL BUILDING EXCLUSIVE OF CONTRACTORS OVERHEAD AND PROFIT. 5,608,050.00 ALLOW A LUMPSUM TO COVER FOR SITE FACILITIES NEEDED FOR THE WORK SUCH AS TEMPORARY SCAFFOLD, WATER FOR WORK, SMALL PLANTS AND TOOLS, SITE SHED, SITE HOARDING, SITE SECURITY, PROVISION OF SITE STORAGE FOR MATERIALS, REMOVAL OF WATER AND RUBBISH FROM SITE, MAINTENANCE OF SITE ACCESS ROAD, E.T.C. SUM 300,000.00 GRAND TOTAL FOR CONSTRUCTION OF CONVENIENCE BUILDING 5,908,050.00 BOLINKZ CONSULTS NIG. 07035451166 RESIDENTIAL STOREY BUILDING/PAGE-13 COST ESTIMATE FOR CARCASS OF PROPOSED STOREY BUILDING OF TWO BEDROOM, THREE BEDROOM DUPLEX S/N DESCRIPTION OF ITEM QTY UNIT RATE AMOUNT SUMMARY OF WORK FOR LABOUR ONLY STAGE ONE (FROM FOUNDATION TO FLOOR SLAB/DPC) 337,400.00 STAGE TWO (SUPERSTRUCTURAL WORKS ON GROUND FLOOR) 232,500.00 STAGE THREE (FIRST FLOOR DECKING, STAIRCASE AND BEAMS) 338,000.00 STAGE FOUR (SUPERSTRUCTURAL WORKS ON FIRST FLOOR) 267,500.00 STAGE FIVE (PARAPET AND ROOF BEAM) 152,500.00 STAGE SIX (ROOFING) 200,000.00 COST OF CONSTRUCTION (MATERIALS AND LABOUR) OF RESIDENTIAL BUILDING EXCLUSIVE OF CONTRACTORS OVERHEAD AND PROFIT. 1,527,900.00 ALLOW A LUMPSUM TO COVER FOR SITE FACILITIES NEEDED FOR THE WORK SUCH AS TEMPORARY SCAFFOLD, WATER FOR WORK, SMALL PLANTS AND TOOLS, SITE SHED, SITE HOARDING, SITE SECURITY, PROVISION OF SITE STORAGE FOR MATERIALS, REMOVAL OF WATER AND RUBBISH FROM SITE, MAINTENANCE OF SITE ACCESS ROAD, E.T.C. SUM 300,000.00 GRAND TOTAL FOR CONSTRUCTION OF CONVENIENCE BUILDING 1,827,900.00 BOLINKZ CONSULTS NIG. 07035451166 RESIDENTIAL STOREY BUILDING/PAGE-14