Professional Documents
Culture Documents
Start
10:00 AM
End
11:00 AM
Purpose
2014 Construction Meeting #6
Distribution/Attendance:
City of Ithaca
Downtown Ithaca Alliance
Sasaki Associates
Labella Associates
Vacri Construction
Power & Construction Group
Verizon
NYSEG Gas
DDS
NYSEG Electric
Next Time
10:00 AM
Prepared By
Jessica Buckley
Location
Commons Project Office 215 East State St. Ithaca, NY
(Present at meeting unless noted: A absent)
Michael Kuo, Jessica Buckley, Nicole Mason
Tammy Baker
Susannah Ross (A), Eamonn Hutton (A)
Dan Walker, James Matzat (A)
Ralph Avery, Andy Breznay, Matt Thomas(A), Roberto DeVincentis (A)
Lou Zupan, Bill Planert (A), Brian Planert (A)
James Edwards, Dave Comer (A)
Doug Stafford (A), Jack Barker, Dawn Stillwell (A)
Jeff Bubb (A)
Jack Czapranski, Dennis Kuhn (A)
Item / Description
1. RFIs
1.1. Any open RFIs at this time
2. SUBMITTALS
2.1. Any open submittals
Notes
PC&G to submit RFI log
City waiting on lighting submittals from
P&CG; Vacri to submit on TTC Alley HH &
WF Vault today; Vacri to submit shop
drawings granite, steel; PC&G to submit
on stage lighting
PC&G to submit submittal log
4. SCHEDULE
4.1. Status of deduct alternate reinstatement
WF & BM Pavilion to be issued
4.2. P&CG to schedule 1-2 additional crews
05/12: Start NW & SW end of E State
05/19 06/16: Complete N Tioga
4.3. NYSEG Electric to relocate secondary on E
State St in June
Page 1 of 2
Due
5.
6.
7.
8.
9.
DATES TO REMEMBER
Page 2 of 2