Professional Documents
Culture Documents
Previous Screen
Product: GENERATOR SET
Model: 3512B GENERATOR SET CMC
Configuration: 3512B Generator Set CMC00001-UP
Parallel Operation
SMCS - 4450
Initial Start-Up
Preparing a generator for parallel operation requires special attention. Before you attempt to parallel
units for the first time, check all the units for the following three conditions.
z
How to determine the proper phase rotation by using three light bulbs is described below.
Illustration 1
g00695380
If the lights blink in sequence, one of the units is connected backward. In order to
correct the problem, stop the units. Remove generator leads 1 and 3 at the circuit
breaker. Exchange these generator leads. This reverses the direction of phase rotation.
Terminal 2 should always be connected to line 2. Go to 5.
If the lights blink in unison, the phase rotation of both generators is the same. The
first condition of "Initial Start-Up" has been met.
a. Allow each electric set to run under load for about 30 minutes.
b. Adjust the governor control to give rated frequency at full load.
c. Remove the load and check the high idle speed. The high idle speed should be
approximately 2 to 5 percent above full load speed for governors that are equipped with
droop. If these speeds can not be obtained, contact your Caterpillar dealer.
d. For the most consistent results, repeat 2.b and 2.c until the second condition of "Initial StartUp" has been met.
3. Adjust the voltage.
There are two fundamentally different methods for reactive power equalization.
{
In the reactive droop compensation the voltage regulator causes an individual generator output
voltage to change in proportion to the reactive current. The reactive current is measured with a
current transformer (CT).
The reactive current can be either lagging or leading. As the lagging reactive current increases, the
voltage regulator will cause the generator output voltage to lower (droop) proportionally. As the
leading reactive current increases, the voltage regulator will cause the generator output voltage to
rise proportionally.
This method will tend to reduce the reactive current for better KVAR sharing with other units.
The reactive droop compensation is a standard method on the Caterpillar generator sets. The
following voltage adjustment procedure is for the reactive droop compensation.
In the cross current compensation the voltage regulator is biased by the difference in reactive
current outputs of the paralleled generators. Cross current compensation is very similar to the
reactive droop compensation. The difference is that the secondary circuits of the current
transformers are interconnected in a series string. When one of the generators carries more
reactive current than other generators or the current that the generator carries is either lagging or
leading, a net difference voltage signal will offset the generated voltage. This will also reduce the
reactive current. Refer to the Engine Data Sheet, LEKX8142, "Caterpillar Zero Droop Voltage for
Parallel Operation" for the adjustment procedure.
Note: The voltage level adjustment and voltage droop adjustment determine the amount of
circulating currents between the generators. The circulating currents between the generators will
be reduced when the voltage adjustments are carefully matched. Use the same voltmeter to make
adjustments on each unit which will be paralleled.
Note: Voltage droop is expressed as the percentage of voltage change from no load to full load.
Loads of 0.8 power factor (primarily motors) require a generator voltage droop of about 5 percent.
A voltage droop adjustment that causes 3 percent to 8 percent droop in voltage is usually required
for satisfactory division of ampere loading.
a. Adjust the voltage. Refer to the "Initial Start-Up" in the Operation Section, "Single Unit
Operation".
b. While the engine is running at rated speed, turn the voltage droop potentiometer clockwise
about 1/2 of full range.
If driven load has the unity power factor, set the voltage droop potentiometer on all
generators at half of full range. Proceed to 3.g.
c. Readjust the voltage level rheostat until the voltage is approximately 5 percent above
desired voltage.
d. Apply full load.
e. Readjust the voltage droop rheostat in order to obtain desired voltage with full load at 0.8
power factor. The voltage droop of each generator must be the same in order to
satisfactorily divide reactive load.
f. Repeat 3.c, 3.d and 3.e for each generator until the following two conditions are met.
g. Parallel the generators and apply the driven load. Check the output current of the generator.
If the sum of the amperes of the individual generator amperes exceeds the total amperes that
are going to the load by 10 percent at full load, adjust voltage droop rheostats. This will lead
to proportional current sharing between generators. Some circulating current is permitted at
light load. Some circulating current can be expected when generators are cold.
NOTICE
Damage to the generator is possible. Do NOT exceed the rated ampere
load on any single generator.
h. Make final adjustments after paralleled generators have been running at full load for one
hour or more. Tighten the locknuts on all controls. Install the access cover. The last
condition of "Initial Start-Up" has been met.
Units may be paralleled at no load or paralleled with units under load. After the initial start-up
conditions are satisfied, verify for the following requirements.
z
One of the governors can be an isochronous governor. Electronic load sharing governors are an
exception.
The different governors that can be used on 3500B generator sets are shown below.
Illustration 2
Load Sharing Module - typical example
g00630841
The generator set load sharing module provides either droop load sharing or isochronous load sharing
for paralleled generator applications. The load sharing module has a synchronizing parallel module
(SPM-A) input. The module provides proportional load sharing. More information is available in the
System Operation, Testing and Adjusting, SENR6565, "Generator Set Load Sensor and Generator Load
Sharing Module".
Illustration 3
(1) Droop potentiometer
g00637397
Speed brick converter changes the analog signal of the speed potentiometer (SP) into a pulse width
modulated (PWM) signal that the engine electronic control can recognize. The converter is mounted on
the subpanel which is located within the control panel.
The simplest governor combination for parallel generator sets is to have approximately 3 percent
speed droop characteristics for each governor. If a constant frequency from no load to full load is
required, one governor can be adjusted for isochronous operation. This isochronous unit will be
called a "lead unit".
In order for all paralleled units to accept their full share of the load, the following governor
adjustments are required. The governors should have the same full load speed. The governors
should have the same high idle (no load) speed in the case of governors which are adjusted for
speed droop operation. Governor controls should be set to the high idle position so that the full
governor range is available.
z
Operation of an isochronous governor in parallel with speed droop governors requires special
techniques.
Any number of electric sets can be operated in parallel. However, only one governor of the group
can be adjusted for isochronous operation. The exception will be some special cases of electronic
governors with automatic load sharing.
Stopping
In order to remove a generator from the line, perform the following procedure.
1. Check the load. The load must be less than the rated capacity of the remaining units.
2. Be sure that the neutral of one of the remaining units is grounded.
3. Remove the load from the outgoing unit. Refer to the Parallel Operation, "Load Division - Speed
Droop". The amperage may never go to zero due to circulating currents.
4. Open the circuit breaker.
5. Allow the engine to cool for five minutes.
6. Stop the engine.
Circulating Currents
Understanding the circulating currents becomes very important when you parallel the units. These
circulating currents are flowing between paralleled generators. The circulating currents are caused by
voltage differences between the generators and are not doing useful work. The amount of the circulating
current can be determined by subtracting the amperage which is going to the load from the total
generator amperage.
The circulating current may be as high as 25 percent of rated amperes with cold generator sets. Such
current may not even be considered harmful. The total generator current should not exceed the amperage
rating.
As the generators warm, the circulating currents will decrease. The ammeter readings should decrease
slightly, but the voltage meter readings should remain constant.