Professional Documents
Culture Documents
B-usiness
B-ehavior
C-riticism
C-reative Endeavor
3.
4.
5.
6.
7.
Reimbursable Expenses
Conditions:
1. Pertinent to the Project
2. Must occur within 100 K = radius
3. Mutual agreement
Schedule of Payments
CONTRACTOR
1. Downpayment - 20 50% of Project Cost
2. Progressive Billing base on percentage of completion (not more than 1 month)
3. Final Billing/Payment - 98% Complete
4. Guarantee Bond enforced for 1 year
ARCHITECT
1. Proposal Fee
5%
2. Schematic Design 15%
3. Design Devt
- 15%
4. Contract Docs
- 50%
5. Retention
- 15% = Liability 10%, Supervision 5%
SPECIALIZED ALLIED SERVICES SAS
1. Proposal Fee
5%
2. Prelim Drawings - 25%
3. Final Drawings
- 50%
4. Retention
- 20% = 3 months after the acceptance of the Architect
*Under Contract Doc. Phase (Refer to UAP Doc 301 General Conditions of a Contract)
GASSD
1. G-eneral Conditions Execution, Intent satisfaction to finish the proj.,
Correlation
2. A-greement
3. S-pecifications
4. S-pecial Provisions
5. D-rawings
*Under Construction Phase
Important Milestones of Construction
RERCF
1.
2.
3.
4.
5.
5 Ms of Construction
1. M-achines
2. M-oney
3. M-anpower
4. M-aterial
5. M-inutes
PROJECT CLASSIFICATION
UAP degree of difficulty/complexity of design
FCP risk of occurrence of Fire
NCP use and occupancy
ARCHITECTURAL PROJECTS (SCHEDULE OF MINIMUM BASIC FEE)
SMERM RHEAC
GROUP
S-imple (Hangars)
M-oderate (Art Galleries)
E-xceptional (Aquariums)
R-esidences
M-onumental Buildings
(Expositions,
Mausoleums, Memorials)
R-epetitive Buildings
DEFINITION
Without partitions
With partitions
Requires Consultants
Single Detached or
Duplex
Requires Concepts
Construction of Similar
Structures
H-ousing Projects
Construction of several
residential units
E-xtensive Detailing
Structures belonging to
Groups 1 to 5
Technical matters,
service as an expert
witness
PARTICULARS
Must be an EnP
PAYMENTS/SCHEDULE OF FEES
Type I Site Devt Planning
50 HAS P5000/HAS = A
50-100 A + P4500/HAS = B
100-200 B + P4000/HAS = C
over 200 C + P3000
Type II Subdivision Planning (Urban)
MM, Cities, Regional Centers, Provincial
Capitals
100 HAS P3000/HAS = A
100-200 A + P2300/HAS = B
over-200 B + P2000/HAS = C
I-nterior Design
L-andscape Design
A-coustic,
Communication and
Electronic
Engineering
Services
C-omprehensive
Planning
Licensed IND
Landscape Architect
Engineer ECE
Must be an EnP
1. Physical
Component
2. Economic
Planning
3. Socio-Cultural
4. Transport
5. Legal &
Administrative
Present
Identifies,
accredits,
recommends
potential
contractors &
suppliers
During
Present
Present
After
Present
Advertising,
Promotional
Services, Building
Administrator
Basic Functions
a. Operates as a member of Owner-Architect-Engineer-Contractor
b. Contractor men and equipment, project delivery as per contract, Owner funds
are available to complete project w/in budget estimates
c. Plan, Program, Monitor activities, Adviser of material cost and Construction
methods, Exercise Overall cost control.
Detailed Functions
a. Pre-Construction Phase
b. Construction Phase
Payments
Contractor
1. Progressive Billing partial % of Completion
2. Request for inspection
Illustration:
RA
EO
PD
PD
Additional Terms:
1. According to RA9266 all projects either big or small must have a contract.
LAWYER NOTARY REGISTER OF CONTRACT
2. Contractor pays for the Building Permit (cannot be reimbursed, not included
in Estimates)
3. Architect cannot be a Contractor at the same time.
4. Contractor is profit motivated; Builder is completion motivated; Contractor
holds the money; Builder doesnt hold the money. 15 days can a contractor,
atter giving due notice to the owner/architect suspend work or terminate a
contract. Responsible for the payment of insurance for personal injury and to
property; Responsible for the As-Built Plans of the Project
5. 2% per annum Interest (if money is not fully collected)
6. TOR Terms of Reference
7. Building Permit validity 120 days, valid 12 months if constructed has not
commenced; exception government structure; excepted if P15,000 proj. cost
8. Notary to legalize document with series no., document no., etc.
9. Arbitration can file a case after 30 days
10. Specifications are printed documents stipulating the procedural aspects of
the contract
11. Variance is the minimum possible deviation from standards which is
permitted to make a highly beneficial housing project.
12. Project duration is computed immediately from the receipt date of the NTP
13. Design of any religious structures is assessed professional fees
14. Competitive bidding is mandatory for public work projects
15. 7 Days affectivity of a Construction contract from receipt of Notice of Final
Payment
16. Civil Code liability of Architect for Regular Design of structures 15 years
17. PERT Prog. Evaluation Review Technique
18. CPM Critical Path Method