Professional Documents
Culture Documents
PROJECT QUALITY
MANAGEMENT
Start
Inspection
Batching
Receiving
Result
NO
Y
NO
Add
Admixture
Result
YES
Sample for
Y
Compressive
NO
Strength
Test
NO
Add
Admixture
Y
NO
YES
Result
NO
NO
Return to
Y
Batching
NO
Plant
Result
NO
YES
Concrete
YPouring
YES
NO
NO
Leveling
Retest the
Reserve sample
Result
NO
NO
Remove the
concrete
Y
poured section
NO
Finishing
Curing
End
CE PRACTICUM 2: AGATON, AMATA, BALMACEDA, CORTEZ, LATINA
B. Reinforcement Bars
Start
Material
Delivery
Material
Testing
Result
YES
Fabrication
Installation
of Material
Inspection
of Installed
Material
End
CE PRACTICUM 2: AGATON, AMATA, BALMACEDA, CORTEZ, LATINA
NO
Y
NO
Return to
Supplier
C. Formworks
Start
Survey
Layout
Rebar
Work
Form Enclosure
Request
Inspection
Concrete
Works
Form Stripping
Request
End
c. Receiving
When the concrete mixer arrives in the site, they should receive and notify
the Concrete Engineer. The condition of concrete should be first checked before
the pouring activity should happen.
Residences, DDT Konstract Inc. used concrete bucket and concrete pump for
pouring
g. Levelling
Levelling is applicable for slabs in which the levelness of the slab is
checked for each poured section.
h. Finishing
Power trowel is used for finishing of concrete slab to have a smooth finish.
i. Curing
Curing process is done by spraying a chemical in the cured member of
the structure.
2. Reinforcement Bars
a. Material Delivery
Once the rebar is ordered, it is delivered in the site. Visual inspection
shall be done by the Project Quality Assessment Engineer. The primary
inspections is the diameter of the bar or of there are impurities, rusts on the
delivered rebar. The quantity of the delivered rebar is also checked if it matches
the quantity ordered. DDT Konstract, Inc. has an official form for this kind of
Request named as Material Delivery Inspection Request. The form includes the
description of the material, quantity, location of usage and remarks.
b. Material Testing
After the material is inspected, a four sample specimen for each delivered
order is obtained. The sample is 500 mm in length and they obtain three for each
batch of deliver. The four sample represent the 7-days, 14-days, 28-days, and 56days specimen that is to be tested. The sample is tested with accordance of
PNS49:2002. The test methods are ASTM A370-09 (Standard Test Methods and
Definitions for Mechanical Testing of Steel Products) and PNS823/ ASTM E41508 (Standard Test Method for Atomic Emission Vacuum Spectrometric Analysis
of Carbon and Low-Alloy Steel). They also have form for testing entitled Testing
Request (Off-Site) in which they have the instruction to testing laboratory.
c. Fabrication
When the rebar passed the material testing and complied with the
standard, the rebar can then be used. It can be fabricated into what is used and in
accordance with the cutting list.
d. Installation of Rebar
After the fabrication procedure, installation of the fabricated rebar should
take place. The form used is Inspection & Work Request/Permit. In this form, it is
the nature of work is written and the signature for the approval for each engineer.
e. Inspection of Installed Rebar
In inspection of the installed reinforcement bars, the project Quality
Assessment and Quality Control Engineer should check the arrangement and the
number of reinforcement bar for each member. Checking of the spacing for each
ties is also done.
Figure 2.2 Inspection of Coupler and Rebar for Beams and Girders
3. Formworks Activity
a. Survey Layout
The Survey Layout has the actual location for the member and it conforms
the elevation and level of the member. It has also a a form which has the actual
survey location.
b. Rebar Work
The rebar work is the inspected rebar installation that is passed the
inspection. It is also the process in the rebar for major work.
c. Form Enclosure Request
It is the request for the formwork to be installed on the certain structural
member that is ready for concrete pouring.
d. Concrete Work
It is the time when the structural member is ready to be poured.
e. Form Stripping Request
It is the request when the poured concrete is passes on the certain hours
after poured depending on the structural member.
Figure 3.1 Steel samples that will be delivered to a testing center to determine
if its properties will match that of the standard.
Site Instruction
The site instruction is used by the Engineers whenever a work is not
properly done and a certain member. If the subcontractor does not follow or
fixed the inspected error in the work, the engineer will written this site
instruction and the worker or the foreman must comply on the commitment
date that is on the form. It is also in the form the observation of the quality
assurance Engineer and the specific location where he/ she sees this defect.
Also, it is on the form the proposed corrective action that is required on the
specific problem.