Professional Documents
Culture Documents
TRACKWORK
TENDER DOCUMENTS
VOLUME - III
EMPLOYER’S REQUIREMENTS:
TECHNICAL SPECIFICATION
July, 2007
CONTENT
1. INTRODUCTION
1.1.1 This specification defines the objectives, guidelines and requirements for
Design, Supply, Installation, Testing and Commissioning of Trackwork on
ballasted and ballastless sections for Versova –Andheri – Ghatkopar (VAG)
Corridor of the Mumbai MRTS.
1.1.2 Subject to the Employer’s decision to supply item under Part: B1 of Bill Of
Quantities (BOQ), the contract shall include manufacture & supply of all
materials including turn outs, cross-overs & scissors cross-overs complete with
their fittings, rail fastenings, restraining rails, and the running rails for all tracks –
main line & depot required for trackwork and shall include verification, delivery,
survey, setting out, installation, testing, including Integrated Testing and
Commissioning, technical support, training of Employer’s Representative‘s staff
and documentation for a complete system necessary to deliver the requirements
of this specification. Scope of work may also include maintenance of tracks for a
period of 5 years.
1.1.3 This Employer’s requirements – Technical Specification for the Trackwork shall
be read in conjunction with the following documents:
g) Tender Drawings
i) Quality Assurance
j) System Assurance
1.1.4 In the event of a conflict between this Specification and any other standards or
specification quoted herein, the requirements of this Specification shall prevail.
The order of precedence, with item a) having the highest priority, is:
a) Employer’s Requirements - Technical Specification
b) Employer’s Requirements - General Specification
c) Indian Standards to the extent applicable for Standard gauge, if any
d) International Standards referenced herein.
e) Other International Standards
1.1.5 The responsibility for the design of Trackwork lies with the Employer, however
the Contractor shall notify the Employer’s Representative of any shortcomings in
the design as soon as it comes to their notice.
1.2.1 Capitalised terms used and to the extent not defined herein, shall have the
respective meanings assigned to them under the Employers Requirements -
General Specification and/ or the Conditions of Contract.
1.3.1 General
1.3.1.1 The Trackworks shall meet the design and performance requirements within the
Environmental Considerations specified in GS and TS in such a way that the
Trackwork/Equipment should function to its full capacity within the
Environmental Considerations.
1.3.2.2 The Trackwork equipment will be exposed to extreme weather conditions such
as heat, dust, humidity, salinity, rainfall and occasional seepage. The system
design shall take into consideration all of the above conditions and ensure that
the performance of the system remains unaffected due to such conditions.
1.3.2.3 Special consideration shall be made by the Contractor for corrosive environment
of Mumbai.
(b) The Trackwork including all equipments shall be of proven design. The
Trackwork equipment, hardware and software proposed by the
Contractor shall have been in use and established their satisfactory
performance over a period of at least two years on two MRTS systems
during the last five years or such period as may be specified in this
specification for any particular component or subject of the Trackwork.
1.3.3.3 Adequate margin shall be built into the design particularly to take care of the
environmental considerations prevailing in Mumbai.
1.3.4.2 The systems shall meet or exceed the RAMS requirements specified in the
System Assurance document. The reliability of the system designed, supplied
and installed is the principal element for availability. It is essential that system
reliability is as high as reasonably practicable.
1.3.5.1 The Contractor shall comply with all Applicable Laws and regulations.
1.3.5.2 The Contractor shall furnish all information upon request by statutory bodies
(e.g. Commissioner of Safety, etc.) in particular format as directed by Employer.
1.3.6.2 The Contractor shall approach the Employer for the general interface
information such as interface requirements, contact points of the Designated
Contractors, and once information is received, would coordinate with them for
interface activities including the Employer in the information loop.
1.3.6.3 The Contractor shall submit and maintain an agreed Interface Management
Plan. At all stages of the work, all interfaces shall be discussed and agreed
upon, through the Employer between the Contractor and the Designated
Contractors. Interfaces should essentially be with Civil Infrastructure, Power
Supply & Traction, E & M, Telecommunications and other Designated
Contractors advised by the Employer. The Employer’s Requirements - General
Specification outlines the requirements of the Interface Management Plan.
1.3.6.4 The Contractor shall liaise with the Designated Contractors directly to discuss
and agree on interfaces. However, the Contractor shall keep the Employer
apprised in writing of all such discussions, agreements and conclusions.
1.3.6.6 It would be the responsibility of the Contractor to settle all disagreements with
the Designated Contractors. If such disagreement cannot be resolved by the
Contractor, despite all reasonable efforts, then the decision of the Employer
shall be final and binding on both parties.
1.3.6.7 Broad interface requirements between the Contractor and the Designated
Contractors detailing the interfacing issues and division of responsibility are
summarised in the Employers Requirements - General Specification.
1.3.6.8 The above interface obligations placed on the Contractor shall be read in
conjunction with the interface obligation mentioned in GS, Conditions of
Contract and other Contract documents.
1.3.9.2 The Contractor shall, as part of the safety analysis, prepare analysis to identify
Hazards and ensure their satisfactory resolution. The following analysis shall
be prepared and submitted by the Contractor for the Employer’s acceptance.
1.3.9.3 The Hazard Analysis shall be carried out in accordance with EN50126 as the
primary standard, or any other internationally accepted equivalent standard, in
areas not adequately addressed by the former standard.
1.3.9.4 The Contractor shall compile a list of safety critical and non safety critical items
identified as a result of hazard analysis, FMECA or by other means. The
Contractor shall carryout the Hazard Analysis and FMECA for key equipment /
sub-systems / systems.
1.3.9.5 All hazard resolution by procedural control shall be cross-referenced from the
safety critical and non safety critical Items List to the appropriate manuals.
1.3.9.6 Component failure or procedural deficiencies shall not result in injury to
personnel, occupational health or damage to the system.
1.3.9.9 The procedures for Operation, Maintenance, Training and the Contractor Quality
Assurance manuals shall incorporate resolution of hazards so identified from
this Hazard Analysis. Proper cross-referencing to the hazards and resolution
measures shall be provided in all these aforementioned documents.
1.3.9.10 Source of all failure rates employed to be indicated in the Hazard Analysis.
1.3.9.11 All Hazard Analysis submitted to the Employer are to be standardised by the
Contractor such that format and forms employed by all sub-Contractors are the
same.
1.3.10.2 The Contractor shall also comply with the guidelines of IEC 60300-1, IEC
60300-2 and IEC 60571 for electronic equipment, and IEC 60605-1 in meeting
the reliability, availability and maintainability requirements of equipment or as
specified in the System Assurance document.
1.3.10.3 The Contractor shall submit a Reliability, Availability and Maintainability Plan as
specified in the System Assurance document. The Contractor shall verify, after
system design have been completed, that the reliability, availability and
maintainability requirement will be met.
1.3.11 Quantitative Reliability
1.3.11.1 The Contractor shall demonstrate by quantitative methods achievement of the
specified levels of reliability for the system as a whole and specific individual
items of equipment.
1.3.13.2 In case the Contractor is not able to achieve specified/provided reliability target
of MTBF/MTBCF, the Contractor shall take necessary corrective measures
either by way of change of design of the relevant equipment/ component,
software modification or change in maintenance regime.
1.3.13.3 The Contractor shall analyse each and every failure/defect of components of
various equipment to determine the cause of failure and to propose corrective
measures, which would be reviewed by the Employer.
1.3.13.4 A record shall be maintained for each and every defect/failure in accordance
with the Failure Reporting Analysis and Corrective Action System (FRACAS) as
stated in Clause 1.3.13.1 to be submitted by the Contractor and approved by the
Employer.
1.3.13.5 Reliability shall be monitored during revenue service operation. The Contractor
shall collect and collate data on each and every deficiency and failure observed
both by him and the Employer, from handing over the System to the end of the
Defect Liability Period. Each and every failure, whether of component, sub-
system or system, during this period shall be subject to a failure analysis to
determine the cause of the failure. The Contractor shall submit investigation
reports for review and approval by the Employer.
1.3.13.6 Correction shall be made to components or subsystems that either fail to attain
predicted reliability levels or show Pattern Failure, at no additional cost to the
Employer.
1.3.15.2 In the event that the availability target as specified in the System Assurance
document is not achieved, the Contractor shall, at his own expense, take
whatever action is deemed necessary to meet the availability target.
1.3.16.3 Particular attention shall be paid during the design and supply of the equipment
to ensure that scheduled maintenance tasks are achieved in minimum time and
using minimum manpower.
1.3.16.5 The Contractor shall develop a comprehensive maintenance programme for the
each equipment and System as a whole.
1.3.16.6 The Tenderer shall submit the expected MTTR in accordance with EN 50126 of
the identified key systems.
1.3.16.7 During the design stage, the Contractor shall submit periodicity, downtime and
manpower requirements for the maintenance inspections and services
considered necessary for maintaining the System under maximum operational
conditions.
1.3.18.2 The subsystems and components which could possibly give rise to the level of
emissions under both normal and fault conditions (conducted, induced or
radiated) that may affect the safety-related systems must be identified. The
quantified risk assessment must be carried out as part of the Hazard Analysis to
determine the probabilities and effects of such interference. Measures must be
taken to reduce such emissions. The reliability of subsystems and as well as the
additional measures, e.g., filter, must be investigated.
1.3.18.3 The probabilities of various conditions which could lead to an unsafe operation
must be determined. A technical construction file suitable for safety audit must
be developed to demonstrate to the Employer.
ii) Enclosures for control and critical equipment shall be located to provide
protection against environmental contamination and mechanical damage.
iv) The equipment shall be designed to prevent fire propagation through the
use of fire resistant equipment housings.
v) The Contractor shall submit a plan to the Employer for approval which
shall describe the process that will be used to systematically identify and
eliminate fire hazards, to avoid the use of combustible materials whenever
practical and to reduce to the extent practical the energy content and heat
release rates of the combustible material that are used.
vi) The plan shall include the Standards to be followed and the tests to be
completed and shall be submitted for approval by the Employer.
2. QUALIFICATIONS OF MANUFACTURER
2.1 Material
2.1.1 All materials and equipment to be provided for the Trackwork shall be of proven
design by a manufacturer who has manufactured and supplied similar material
and equipment for Trackwork projects for a period of at least five (5) years in the
Railway Industry..
3. SCOPE OF WORK
3.1 SCOPE
3.1.1 Subject to the Employer’s decision to supply items under Part: B1 of BOQ, this
specification establishes the requirements for the design, manufacture, supply,
installation, Integrated Testing and Commissioning of track work for Versova –
Andheri – Ghatkopar (VAG) corridor of Mumbai MRTS and the at grade depot at
DN Nagar. The track alignments and details of curves, turnouts, x-overs,
gradients, etc. are shown in the alignment drawings for the main lines and in the
layout drawings for the depot. The coordinated alignments will be issued to the
Contractor not less than 1 month before start of construction of trackwork for the
main lines and for the depot. All such information shall be verified by the
Contractor for its geometrical correctness before setting out and survey checks
shall be made before and after laying the tracks to ensure clearance is provided
to all infrastructure works in compliance with the Structure Gauge given in the
Schedule of Dimension attached herewith in Volume IV.
3.1.2 A work base area for execution of this Contract will be provided by the
Employer at a suitable location. If required by the Contractor, other work areas
along the corridor shall be arranged and established by the Contractor as
necessary at no cost to the Employer.
3.1.3 The track work in DN Nagar Depot shall be installed according to the
mathematised depot layout after duly interfacing with the Employer’s
Representative and the Designated Contractors.
3.1.4 The Contractor shall arrange his own mobile flash butt welding plant which can
be used on elevated viaduct.
3.1.5 For the ballasted trackwork in the depot the Contractor shall arrange to use off
track tamper capable of tamping both plain line and turnouts.
3.1.6 The Contractor shall be required to interface closely with the various Detailed
Design Consultants and the Designated Contractors.
3.1.7 The scope of work shall include, but not be limited to, the following:
• Supply of all track and other materials, including running rails, turnouts,
cross-overs and scissors cross-overs (complete with their fittings), rail
fastenings, restraining rails, which may be supplied by the Employer. The
Contractor will make arrangements for the handling and transportation of all
materials to the Site.
A. Ballastless Track
I. Transporting rails and welding them into long panels, testing by Ultra
Sonic Flaw Detection, painting of rail welds, weld markings,
II. Linking of rails to the line and level with fastenings, assembly of
Points & Crossings,
VI. Removing dummy plates and complete rear work & reassembly of
rail panels,
IX. Fixing Km, Gradient, Fouling Mark, Turnout posts, Curve posts &
other posts,
B. Ballasted Track
V. Ballasting,
VI. Tamping, squaring of sleepers, boxing of ballast, adjusting line & level,
IX. Destressing of Long Welded Rail, adjusting Rail Expansion Joint gap,
CRITERIA DIMENSION
1 Gauge 1435 mm
80 m (depot track)
7 Inclination of Rail 1 in 20
Ballasted Ballastless(DFF)
Rail type main line UIC 60, 880 grade
--- and1080 grade Head
Hardened
Rail type depot UIC 60, grade 880 & UIC 60, 880 and 1080
grade 1080 grade HH grade HH
Maximum cant
50mm 125mm
Type of turnout
(i) Main line --- 190-1:9 (40km/h) and
190-1:7 (40km/h)
Long welded rail strings shall be joined to form continuous welded rails and
finally fastened so that the zero thermal stress rail temperature lies within the
range of (mean-rail-temperature + 5) to (mean-rail-temperature + 10) degree
Celsius using a mean-rail-temperature value of 37 ゚ C.
The Contractor shall ensure that no permanent structure is within the Structure
Gauge profile and the material & installation of track work shall comply with the
provisions of Schedule of Dimensions. The Schedule of Dimensions is tentative
and any change to it shall be advised to the Contractor.
4. INTERFACES
Interface Matrices are included in the General Specification. These describe the
principal interfaces between the Contractor and the Designated Contractors.
These matrices shall be developed, updated and expanded as necessary to
encompass all the relevant interface issues encountered during the execution of
Contract.
5.1 REQUIREMENTS
5.1.1.1 The Contractor shall comply with all Applicable Laws in executing the works,
including but not limited to all Statutory provisions on occupational health and
safety.
5.1.1.2 The Contractor shall co-ordinate with the Designated Contractors in the
execution of the Works.
5.1.1.3 The Contractor shall also co-operate with all Relevant Authorities in the
execution of the works.
5.1.1.4 All machinery and equipment shall be properly maintained and operated at all
times by suitably trained and competent employees of the Contractor and to the
satisfaction of the Employer’s Representative.
5.1.1.5 Only appropriate tools, plant, machinery and equipment and vehicles shall be
used.
5.1.1.6 The Contractor shall, prior to starting any installation and construction work,
identify any possible hazards, and implement measures of eliminating and/or
mitigating such potential hazards, in line with safe working practices.
5.1.1.7 Further details on Site Safety management are described in Safety Health
and Environment Conditions (Volume IV). The Contractor shall ensure that all
areas of work are sufficiently illuminated for the works to be undertaken and that
a safe system of work is employed for all activities.
5.1.1.8 The Contractor shall comply with all its obligations with respect to ensuring
Security of the Works at the Site. This comprises a suitable system for the
control of persons entering or working on the Site. The system shall include as a
minimum:
• Register of all employees
• Levels of competence;
• Date of joining
• Date of discharge;
5.1.1.9 The Contractor shall co-operate, at all times, with the Employer’s
Representative and the Designated Contractors to ensure that the Site is
protected from unauthorised admission, either wilfully or otherwise.
5.1.1.10 The Contractor shall make due provisions for safe access to and egress from
the Site for its staff and subcontractors. This access shall be maintained such
that it is free of all hazards and is in a safe condition throughout the duration of
the works.
5.1.1.11 The Contractor shall provide the survey equipment, track measuring equipment
and other accessories as per the instructions of Employer’s Representative as
and when required. He shall also provide all necessary help and manpower as
required by the Employer’s Representative for checking the works, whenever
required.
5.1.2.1 The installation and construction work pertaining to this contract shall include,
but not be limited to the following: -
• Survey on site and review the technical requirements shown in this
specification and the Employer’s Representative’s drawings.
6.1 INTRODUCTION
6.1.1 This Materials and Workmanship Specification for Track work shall be read in
conjunction with all the documents forming part of the Contract.
6.1.2 No Permanent Works shall be carried out until all methods and materials have
been approved.
6.1.3 Unless noted otherwise in the Contract, all components and materials shall be
handled, transported and stored, in accordance with the manufacturer’s
recommendations with prior approval of Employer’s Representative.
6.1.4 The test results of each test to be carried out as per Employer’s
Representative’s requirement shall be recorded and submitted in a format
approved by the Employer’s Representative and shall include graphical
presentation of results as well as numerical base data where ever required.
6.2.3.1 Cement
6.2.3.2 Concrete
BS : 14 (Revised)
6.2.3.3 Formwork
IRC: 87 Guidelines for design & erection of false work for road
bridge.
IS: 806 Code of practice for use of steel tubes in general building
construction.
IS: 1239 Specification of mild steel tubes. tubular and other wrought
steel fittings.
6.2.3.4 Steel
IS: 432 Part I mild steel and medium tensile steel bars.
IS: 814 Parts I & II electrodes for metal arc welding of structural
steel.
IS: 816 Code of practice for use of metal arc welding for general
construction in mild steel.
IS: 1786 Specification for high strength deformed steel bars and
wires for concrete reinforcement.
IS: 2502 Code of practice for bending and fixing of bars for concrete
reinforcement.
IS: 4759 Hot-dip zinc coating of structural steel and other allied
products.
IS: 2751 Code of practice for welding of mild steel plain and
deformed bars for reinforced concrete construction.
IRS T-37 GR sole plate (for 6 mm sole plate pad and any other
relevant specification)
Indian Railway Manual for Ultra Sonic Testing of Rails and Welds 1998
The technical specifications and manuals etc. of Indian Railways which are mentioned in
clause 6.2.6, shall be used only as far as they are applicable to a Standard Gauge
system. The Contractor shall be responsible for collecting the latest revision of all relevant
technical specifications to be used, including any correction slips and alterations, from the
issuing body at his own cost and shall submit them to the Employer’s Representative for
his approval before starting of work.
7.1.1. The 1080 grade HH running rails, turnouts, cross-overs & scissors cross-overs
complete with their fittings, UIC 33 restraining rails and rail fastenings for the
ballastless, tracks may be procured by the Employer for installation by the
Contractor.
7.1.2. Materials supplied by the Employer or the Contractor above shall be imported CIF
Mumbai port, and in this case, the Contractor shall be responsible for all the
remaining activities on arrival of these materials at Mumbai port such as taking
delivery of these materials including coordination with the customs authorities,
shipping lines, port authorities etc. The Contractor shall also be responsible for
their safe transportation from Mumbai port to Site without causing any damage to
them taking proper care & precaution & following appropriate methods including
loading, unloading, local transport and temporary storage at Mumbai (if required),
handling/rehandling, coordination with port and transport authorities, obtaining
necessary transport permits, transit insurance and proper stacking/storage with
proper accountal etc. as directed by Employer’s Representative.
7.1.3. For the materials imported by the Employer or the Contractor Mumbai Port, the
Contractor shall assess the damage to the materials, if any, and advise the
Employer’s Representative about the same immediately. The material, which in
the opinion of the Employer is damaged, shall not be transported to site, instead
shall be kept in Contractor custody in the Contractor temporary storage area in
Mumbai for a period not exceeding 28 days. Any damage to the materials which
have been transported by the Contractor to site shall be on Contractor account to
rectify.
7.1.4. The material, which in the opinion of the Employer is damaged, shall be jointly
inspected by the Employer’s Representative and the Contractor at the Contractor
storage area in Mumbai (The Contractor shall arrange required tools /equipment,
labour etc. for such joint inspections) and the acceptance /rejection of such
materials shall be as finally decided by the Employer’s Representative. The
rejected material shall remain in the safe custody of the Contractor at Mumbai till
its final disposal by the Employer’s Representative within 28 days.
7.1.5. Similarly the 880 grade rails may be procured by the Employer for installation by
the Contractor.
7.1.6. The 880 grade rails supplied by the Employer as described in 7.1.5 above or by
the Contractor shall be delivered to DN Nagar depot, and in this case the
Contractor shall be responsible for coordinating their unloading including
receiving, acknowledging the necessary vouchers without causing any delay and
proper accountal thereof etc. as directed by the Employer’s Representative. The
location/area for stacking of these materials shall have to be identified,
demarcated and got approved by the Contractor well in advance of actual arrival
of these materials so that no delay is caused on this account.
7.1.7. For the 880 grade rails supplied by the Employer or the Contractor, the joint
inspection for all the materials, equipments, goods etc, supplied by either the
Employer or the Contractor under the contract, the provision of handling, inland
transportation, damage checking etc shall be the same as mentioned above in clause
7.1 shall be done on arrival of these materials at Site.
7.2 RAILS
7.2.1 Rail Sections
7.2.1.3 The Contractor shall be responsible for preparing the firm and level ground for
stacking of Rails as approved by the Employer’s Representative. The Contractor
shall also arrange the required wooden battens/spacers for keeping rails in
layers as directed by the Employer’s Representative.
All ballasted plain line track laid on PSC sleepers shall be installed with a
proprietary fastening system, which shall have a satisfactory proven service
record of not less than 5 years in conditions similar to those found on the
Project.
7.3.2.1 All plain line ballastless track for the main lines and the tracks on the depot
approach ramp viaducts shall be installed on cast in-situ reinforced concrete
plinths, the design for which shall be provided by the Employer, using a
proprietary fastening system, which shall have a satisfactory service proven
record of not less than 5 years in conditions similar to those found on the Project
and which complies with all relevant requirements of EN13481.
7.3.2.2 The fastening system shall facilitate track adjustments of +/- 10mm
horizontally and up to +10mm vertically, with a minimum requirement of extra
components and time to adjust.
7.3.2.3 The fastening system shall be designed to minimise noise and vibration whilst
maintaining track gauge and stability both on tangents and on curves down to
100m radius.
7.3.2.4 The fastening system shall provide support to the rails sufficient to resist the
anticipated lateral and overturning forces on straight track and on curves down
to the minimum radius of 100m. The toe load applied to the rails by the fastening
system shall provide restraint to the rails, sufficient to limit potential pull-apart
gaps to less than 50mm and to resist the anticipated longitudinal braking and
traction forces on the steepest gradients whilst allowing the continuously welded
rails to distribute thermal forces across the viaduct expansion joints without the
need for rail expansion joints and without the build up of excessive rail stresses.
Standard fishplates and fish bolts shall be suitable for use with UIC60 rail
section and shall be of four bolt type and shall be manufactured in accordance
with the relevant technical specifications of Indian Railway as mentioned in
clause 6.2.6.
The Glued Insulated Rail Joints (GIRJ) shall be manufactured by using UIC 60
grade 1080 HH rail G-3 (L) type in accordance with the RDSO Drawing no. T -
5843 and relevant Technical Specifications/manuals of Indian Railways as
mentioned in clause 6.2.6 for the Supply of Glued Insulated Rail Joints.
7.3.5 Ballast
7.3.5.1 Basic Quality: The 50mm nominal size ballast shall be hard durable and as
far as possible angular along edges/corners, free from weathered portions of
parent rock, organic impurities and inorganic residues.
7.3.5.2 Particle Shape: Ballast shall be cubical in shape as far as possible individual
pieces shall not be flaky and shall have generally flat faces with not more than
two rounded /sub rounded faces.
7.3.5.5.1 Contractor shall ensure that Ballast is well graded between 65mm & 20mm size.
The Contractor shall further ensure the following size & gradation of ballast:
a) Retained on 65mm Sq. mesh sieve 5% Maximum
b) Retained on 40mm Sq. mesh sieve 40 - 60%
c) Retained on 20mm Sq. mesh sieve Not less than 98%
7.3.5.5.2 Before commencing the supply of ballast the Contractor shall get the source /
quarry approved by the Employer’s Representative duly submitting the samples
and impact & abrasion test result values (to be conducted in a mutually agreed
independent lab/institution of repute) along with the proposed gradation of the
ballast to demonstrate compliance with specifications.
7.3.6.1 The Contractor shall be responsible to design and supply mono block PSC
sleepers for the standard gauge ballasted plain line tracks with 1:20 rail
inclination to be compatible with the fastening system supplied.
7.3.6.2 The Contractor shall be responsible to design and supply PSC bearers for the
ballasted turnouts and crossovers compatible with the approved fastening
details and arrangements of the turnout manufacture. Turnout bearers shall be
arranged in a fan layout and to the greatest extent possible, the fastenings shall
incorporate similar components to those provided for the plain line.
7.3.6.3 PSC sleepers or PSC bearers for turnouts and crossovers shall be in
accordance with the relevant Technical Specification for manufacturing and
supply of turnout PSC sleepers as mentioned in clause 6.2.4
7.3.6.5 The Contractor shall ensure his proposed handling and transportation
methods do not cause any damage to the sleepers and /or its fittings. The
damaged sleepers as decided by Employer’s Representative may be
appropriately repaired by the Contractor, but no repaired sleepers shall be
incorporated in the works without the Employer’s Representative’s approval.
Any repaired sleepers which are rejected by the Employer’s Representative
shall be indelibly marked as rejects and shall not be incorporated in the works,
but shall be removed from the site forthwith.
The Contractor shall submit to the Employer’s Representative for each item or
component to be manufactured, the proven service record of the components
and full details of the previous relevant experience of the proposed
manufacturer in the production of that item, and also previous experience of
manufacturing similar products for the Railway industry as well as for MRTS
Projects. The major items that require particular and specific previous
manufacturing expertise and require prior approval of the Employer’s
Representative are as follows:
7.4.1 General
7.4.1.1 On the main line, the following types of turnouts and diamond crossing shall
be provided, and installed on reinforced concrete track slabs, as indicated in the
relevant drawings attached herewith in Volume IV.
a) UIC60-100-1:6 turnouts individual
7.4.1.2 On DN Nagar Depot lines, the following types of turnouts and diamonds shall
be provided, with two turnouts installed on track slabs and the rest on ballast, as
indicated in the relevant drawing.
a) UIC60-100-1:6 turnouts in individual, crossover and fan layouts
7.4.1.3 All ballasted turnout layouts, and the scissors x-over shall be provided on
PSC sleepers/bearers.
7.4.1.5 Turnouts on main lines and depot lines shall be designed to take the CWR
through turnouts.
7.4.1.6 All turnouts and diamond crossings on main lines and depot lines shall be
designed and installed with canted rails with an inward slope of 1 in 20. The
detailed design drawings shall be supplied to the Employer’s Representative for
approval.
designed as per drawing No. RDSO – T - 2653 and installed by the Contractor
on the non-ballasted mainlines at locations and to details approved by the
Employer’s Representative.
Track ends in the Workshop and inspection bay shall be fitted with wheel stops
capable of stopping a 6-car empty train travelling at 5km/h without damage to
the wheel stop. The wheel stops shall be designed such that they are
compatible with the wheel diameter of the vehicle to avoid or minimise damage
to the vehicle. All other track ends in the depot shall be protected by massive
concrete fixed buffer stops as shown on the Employer’s Representatives
drawings. All track ends on viaducts shall be provided with friction sliding buffer
stops with impact absorption material (non-hydraulic type) on the face. Sliding
buffer stops shall incorporate features to prevent the train from overriding and to
facilitate resetting after impact. The design and specification of wheelstops and
friction buffers shall be submitted by the Contractor for Employer’s
Representative’s approval. The Contractor shall interface with the Designated
Rolling Stock Contractor for the details required for the design of friction buffer
stops (confirmation of train mass and coupler data). However the following
provisional details shall be followed, until confirmed by interfacing with the
Rolling Stock supplier.
252 tonnes shall be allowed for the mass of an empty 6-car train (W0
loading)
408 tonnes shall be allowed for the mass of a fully loaded 6-car train (W4
loading).
The stopping performance required for empty trains on the viaduct
(Depot/Mainline Transfer Track) shall be;
The stopping performance required for fully loaded trains on the viaduct
(at the Versova and Ghatkopar ends of the mainline) shall be;
The Contractor shall be responsible to provide the road level crossings in the
depot as embedded tracks with associated under-track transition slabs at the
locations and to the details as given in the Employer’s Representative’s
drawings MMO/EPMC/P/D/TW/D1210, MMO/EPMC/P/D/TW/D1170 and
7.8.1 General
7.8.2 Concrete
The concrete for plinths and slabs shall be of M45 grade as per the Indian
Standard IS-456 – 2000, for PRC track sleeper M55 and for PRC turnout
sleeper M60
7.8.3 Reinforcement
7.8.3.1 Reinforcement shall be of Fe: 500 as per IS1786 in accordance with relevant
IS Codes.
The plinth / RCC slab electrical continuity shall be ensured by the Contractor.
The Contractor shall supply and weld a connecting galvanised M.S. flat to the
plinth / RCC slab reinforcement. This galvanised M.S. flat shall be 160x40x8
mm and bent to L-shape, pre-drilled with a 6-mm diameter hole, and shall be
installed at each plinth / RCC slab unit extremity. The galvanised M.S. flats shall
be connected by the Contractor using steel cable of adequate size to provide
electrical continuity between consecutive plinths / RCC slab duly interfacing with
the designated Power Supply & Traction (PST) Contractor.
ii) For running conditions the specified limits shall be met for the entire
speed range up to 80 km/h with all equipment operating simultaneously.
Noise level measurement to be done at a location 20-25m horizontally
from the track centreline on a horizontal plane passing through the axle
centrelines.
The welding portion and equipment required for the Alumino-Thermic rail welding
process shall be manufactured and tested in accordance with relevant Technical
Specifications for approval of the process and supply of portions for Fusion
The setting out of alignment for track construction shall be the responsibility of
the Contractor. The following principles shall be adopted for setting out and
execution.
8.1.1 The planning organisation and process of surveys for transferring the alignment
for track construction shall be the sole responsibility of the Contractor. He shall
at all times maintain common survey interface with the Civil Contractors.
8.1.2 Survey and setting out of works shall be carried out by surveyors of appropriate
experience and qualification as approved by the Employer’s Representative.
8.1.3 The Employer’s Representative may carry out random checks to verify the
accuracy of the setting out and Contractor compliance of the completed works
with given alignment and the specifications. Provisions and arrangement shall
be made by the Contractor to facilitate the checks. However, full responsibility
lies with the Contractor for the accuracy of line and level of the tracks.
The Contractor shall interface with designated Civil Contractors to take over the
reference co-ordinates system (x,y,z) of the project area as defined by the
MRTS project. The Secondary Survey Control Markers are additional points to
be established by the Contractor along alignment or in the depot from the
reference coordinate system including bench mark thus providing survey control
for the work areas. The Contractor may also establish additional survey control
Markers as local grids or reference system for setting out particular sub-set of
work.
8.3.1 As each section of track or depot becomes available the Contractor shall submit
a schedule of secondary Control Markers and Bench marks for that area duly
interfacing with the Designated Contractors. The Survey Control Markers and
Bench Marks shall be used for the control of the Works. The Contractor shall
verify the relative accuracy of the Survey Control Markers and Benchmarks prior
to use.
8.3.2 All the Survey control markers and Benchmarks provided within the project area
by the designated Civil Contractors shall be surveyed, with survey computations
based on the adopted co-ordinates system. Any changes in values shall be
supported by technical evidence and on consultation with all affected parties.
8.3.4 It shall be the Contractor’s responsibility to protect and preserve the integrity of
all the Control Markers during the period of construction of the trackworks. In the
event that any of the Secondary Control Markers or Benchmarks is damaged,
the Contractor shall replace and re-establish the points at his own cost to the
satisfaction of the Employer’s Representative.
8.4.1 Setting out points shall be established by transfer from the survey control
Markers. The Contractor shall establish physically on site such track siting
marks that may be grid or offset points to be used as the reference system for
the track work. In the event the original structural grid line are destroyed or
rendered unusable, the Contractor shall re-establish them at his own cost
without delay.
8.4.2 At each site, the position of the site main reference setting out points shall be
maintained throughout construction period. Such markers shall be checked
against the Survey Control markers by the Contractor at regular intervals to
ensure reliability of subsequent works.
8.4.3 The track siting marks corresponding to both the theoretical centre of the track
and to the theoretical level of the track running surface, as defined by the
relevant topographical data on the documents relating to track layout shall be
marked at the beginning and end of each circular curve, transition curve and
vertical curve both in the longitudinal and cross directions. The following track
siting marks shall be established:
The track siting marks for the centre of the tracks shall be shown by plates or
nails sealed on the viaducts and in the depot as approved by Employer’s
Representative. They shall be referenced by the Cartesian co-ordinates of each
point identified in this manner, and registered in the topographical logbook.
Should there be any discrepancy found by the Contractor with reference to the
geometry of civil structure, the same should be interfaced with the Civil
Contractor. The Contractor shall be responsible to prepare details duly making
necessary modifications in layout, if required as a solution to the discrepancy
and submit the same to the Employer’s Representative for his final decision.
The track siting marks for the vertical siting of the track running surface shall be
shown by angle plates sealed onto the viaduct sidewalls. They shall be
referenced with respect to the theoretical track level as approved by Employer’s
Representative.
Given that the precision of the spatial siting of track laid directly on concrete is of
the utmost importance, the Contractor shall position the above markings as
follows.
8.4.3.1 Levelling
The markings show the track altitude, shall be placed on the viaduct side walls,
at a constant height in relation to the theoretical level of the track running
surface. They shall be placed at every temporary support frame of track or 5 m,
whichever is less.
8.4.3.2 Layout
The markings show the centre line of each track, shall be fitted on the viaduct at
every temporary support frame of track or 5 m whichever is less in straight
sections, in circular curves and in transition curves.
8.4.4 The inner rail for curve and any rail for straight shall first be set out in its absolute
position from track siting marks using co-ordinates computed from the alignment
geometry, the elevation of the rail shall be checked using a level, the other rail
shall be set correctly relative to cross level and gauge from the first rail.
8.5.2 The Contractor shall ensure that all survey and track siting marks shall be
established on Site to required accuracy. He shall also be responsible for each
stage of the setting out work and for verifying compliance before construction
starts.
8.5.3 The Contractor shall develop a detailed Surveyed Track Analysis spread sheet
on Microsoft EXCEL. The detailed format of the Surveyed Track Analysis
spreadsheet shall be submitted to the Employer’s Representative for
Acceptance at least one month prior to the commencement of track laying.
8.5.4 The surveyed Track Analysis spread sheet shall tabulate against chainage, the
vertical difference (high or low) and horizontal difference (left or right) between
the actual surveyed track centre line position and the design alignment
computed from latest accepted alignment geometry. Derived cant, gauge and
twist values shall also be compared against design values on the same
spreadsheet.
8.6.1 Survey instruments used and the methodology adopted shall be appropriate to
the intended measurement task and accuracy specifications. Test
measurements and instrument calibration shall be carried under local field
conditions.
8.6.2 It is essential that before starting any initial surveys, and at frequent intervals of
not more than three months, all measuring equipment should be tested for their
accuracy.
8.6.3 All instrument deployed in the Contract shall be in good condition and properly
calibrated. Calibration certificates and/or statements of services by local
authorised instrument agents of not more than six months shall be the proof that
the instruments are in good service conditions.
8.6.4 Notwithstanding the above, instruments shall again be checked to ensure good
condition before the Contractor proceeds to carry out a critical survey task.
8.6.5 Horizontal control traverses shall be carried out with modern precise digital
survey instruments consisting of co-axial total station with an accuracy not
inferior to 2” arc and (2+2ppmxD)mm. Precise levelling runs shall be carried out
in both directions using digital level with an accuracy not inferior to 1.5mm per
Km double run. Digital data from the above instrument shall be recorded
electronically in the field. For track surveys non co-axial total station shall not be
permitted. Total stations used for track surveys shall have onboard software
permitting setting out and checking of points along a calculated alignment in the
field. Survey instruments used by the Contractor shall meet such standards.
9. INSTALLATION
9.1 INTRODUCTION
9.1.1 General
9.1.1.3 All temporary/service tracks, if required for track work on main lines and depot
lines, shall be arranged & laid by the Contractor only with prior approval of the
Employer’s Representative. The Contractor shall remove these
temporary/service tracks after completing the permanent track work as
approved by Employer’s Representative.
9.1.2.1 The ballastless trackform on main lines shall be direct fixation on reinforced
concrete plinth for plain track and on RCC slab for all turnouts.
9.1.2.2 The ballastless track in depot areas shall be of the following types as shown
on the Drawings
a) Embedded rail,
c) Ballastless plinth type track form for washable apron (low height plinth
without derailment guards).
d) Pit tracks with discrete rail supports on each side of the pit.
9.2.1.2 Method statements for track laying shall, as a minimum cover the
following items, where ever applicable:
(a) handling & transport (including for materials to be supplied by
Employer’s Representative)
(c) pre-assembly/assembly
(d) delivery
(e) surveying
(g) welding, USFD testing of rails & welds, weld tests upto failure,
planning for appropriate length of rail panels
(i) ballasting
(j) tamping
(k) lining & levelling
(l) concreting
(n) cleaning
(o) destressing
(p) cutting of rails, which may render generation of unusable small cut
pieces.
9.2.1.4 Method statements are also required as a minimum for the following
production or installation activities:
(a) Each trackform
(e) Surveying
(h) Falsework/Formwork
9.2.1.7 Each method statement shall be referenced to the relevant clauses of the
documents forming the Contract.
9.3.1 Throughout construction generally and immediately after installation of the track,
the rails, rail fastenings, the concrete track base, including ducts, track drains
and any exposed support structure shall be made clean. This cleaning shall
include the use of air/water pressure jetting and vacuum cleaners as necessary.
9.3.2 Once a section has been cleaned, tested and the required track parameters &
insulation values (as required by the relevant interfacing parties) have been
accepted by the Employer’s Representative, that section’s accepted level of
cleanliness and insulation shall be maintained until the taking over of the
section.
9.4.1 General
9.4.1.1 The track gauge throughout shall be 1435 mm on straights and 1435-0 mm +
gauge widening on curves measured between the running edge gauge point of
each rail and normal to the centre line of the track 14 mm below top of Rail.
9.4.1.2 All main line & depot line track including turnout, x-over and diamond xing
shall be laid with 1:20 inward rail slope.
9.4.1.3 The Contractor shall take due cognisance of his proposed rail jointing system
and the rail fastening assembly spacing in the selection of the appropriate length
of long welded rail panels.
9.4.1.4 The minimum closure rail length in plain line shall be 6 metre except for
specific locations as shown on the drawings or as Approved by the Employer’s
Representative.
9.4.1.5 No wastage allowance shall be permitted for the various materials supplied by
the Employer’s Representative except for the rails. The wastage allowance for
rails shall be permitted in accordance with the provisions of paragraph No. 9.4.2.
4 of Technical Specification.
9.4.2.1 All rail joints throughout the main lines & depot lines, including turnouts,
except at locations approved by the Employer’s Representative, shall be
welded.
9.4.2.2 The welding of nominal rail lengths into long welded rail panels for main lines
and depot lines shall be by mobile flash butt welding plant. Alumino-Thermic
welding shall only be used in exceptional circumstances with prior approval of
the Employer’s Representative. Temporary joints between HH rails shall be by
fish plates & clamps without drilling of holes in rails.
9.4.2.3 All the welded joint for welding less than 26m rail length on main line and
depot lines shall have prior approval of Employer’s Representative.
9.4.2.4 The Contractor shall obtain Employer’s Representative’s prior approval for any
rail cutting, which may render generation of unusable small cut pieces. These
cut pieces shall also be properly accounted, collected and stacked in DN Nagar
Depot at a place approved by the Employer’s Representative before its handing
over in acceptable condition.
The spacing of welds and joints shall not be less than 6.0 m between any two
welds and for any deviation to this, specific approval of Employer’s
Representative shall be required in each case. No welds shall be permitted
closer than 100 mm to a rail seat as measured between the centre of the weld
and the closest edge of any rail fastener. No welds shall be permitted in the
working length of the friction sliding buffer stops.
9.4.5.1 Standard fishplated joints shall only be used in the depot tracks for locations
where welded joints cannot be made and only as approved by the Employer’s
Representative.
9.4.5.2 Standard fishplated joints shall be installed centrally between two adjacent
fastenings and shall be manufactured and installed to permit the use of standard
rail fastening assemblies.
9.4.5.3 All fishplated joints shall be fitted with the nuts with spring washer.
9.4.6.1 All glued insulated rail joints shall be shop manufactured using minimum 6 m
long rails. Site fabricated glued insulated joints shall be provided only with prior
approval of the Employer’s Representative,
9.4.6.2 Except in the case of glued insulated joints in the turnout zone, the positioning
of the glued insulated joint with respect to the approach track (adjoining track)
shall be such as to keep a minimum distance of 4.00 m from an existing weld in
the rail.
9.4.7.1 Rail expansion joints shall be installed only at locations as instructed by the
Employer’s Representative.
9.4.7.2 Particular attention shall be given to ensure that rail expansion joints are
assembled and installed as per drawing No. RDSO – T – 2653.
9.4.9.1 Rails shall only be cut by using disc type rail cutting machines. The proposed
method and equipment for the cutting of rails shall have the prior approval of the
Employer’s Representative.
9.4.9.2 Rails required to be cut shall be cold sawn square and vertical across the rail.
A deviation from square or vertical of more than 0.50 mm, measured about the
rail head, shall not be permitted. All burrs shall be removed from the rail ends.
9.4.9.3 Quality of cutting shall be such as to ensure tolerances in flash butt and
Alumino–Thermic welding manual.
9.4.10.1 All fish bolt holes in rails, wherever required shall be drilled by using proper jigs
and drilling machines. The proposed method and equipment for the drilling of
rails shall have the prior approval of Employer’s Representative
9.4.10.2 All holes in the rails shall be chamfered using chamfering kit & procedure
approved by the Employer’s Representative.
9.5.1 General
(d) Rail
9.5.1.2 The completed track shall have the following minimum ballast cushion
under the sleeper or bearer:
(a) Ballast cushion :
(c) Sleeper centres shall be measured along the track centre line for straight track
and along the high rail in curved track.
9.5.1.4 A “Request for Inspection” complete with all necessary information to allow
assessment, shall be submitted to the Employer’s Representative for the
following activities and Approval must have been received prior to commencing
any follow-on activity:
(a) Acceptance of supporting structure,
(c) Acceptance of the track and turnouts for the movement of plant,
machinery & equipment
9.5.2.1 The Contractor shall check the formation level with reference to required level
to achieve proper ballast cushion at rail seat below bottom of sleeper. Any
discrepancy in level of formation shall be brought to the notice of the Employer’s
Representative with details for final decision.
9.5.2.2 Bottom ballast shall be laid directly onto the prepared support structure using
methods that keep the amount of road traffic over the support structure to a
minimum
9.5.2.5 On completion and acceptance of the bottom ballast for track laying, no
vehicle of any type shall be permitted to run over the bottom ballast.
9.5.3.1 General
9.5.3.1.1 In situ flash butt welding shall not be undertaken until the track has sufficient
ballast to hold it to alignment both before and after welding.
9.5.3.1.2 The track laying system shall be such that no pneumatic tyred vehicles shall
travel over the bottom ballast during the track laying operation.
9.5.3.1.3 On entry/exit lines of depot connected to main line, ballasted curves sharper
than 400 m radius shall be provided with extra width of shoulder ballast, as per
Indian Railways Manual of instruction on Long Welded Rails -1996, on outside
of curve to increase the lateral track strength.
9.5.3.1.4 The sleepers shall be laid out on the bottom ballast at the specified spacing. The
sleepers shall be correctly aligned in accordance with the track alignment.
9.5.3.1.5 Once a suitable length of track has been laid and before any further rail
mounted Construction Plant or equipment is allowed to run on that track,
sleepers shall be levelled and packed by off-track tamper or by manual means
9.5.3.2.1 Prior to the placing of top ballast the track shall be marked in preparation for
tamping and lining operations with the following information:
• All horizontal and vertical tangent points
• Cant details
• chainages
9.5.3.2.2 Once the top ballast is adequately regulated the track shall be lifted, levelled
and aligned as required.
9.5.3.2.3 The finished track with designed line and levels and with designed ballast profile
shall be destressed.
9.5.3.2.4 The Contractor shall deploy his own track tamper for the purpose of tamping of
track.
9.6.1 General
a) support structure
b) shear connector
c) reinforced concrete plinth for plain track & RCC slab for turnouts
9.6.2.1 The surface of the viaduct deck shall be surveyed to achieve the minimum depth
(300 mm) of plinth / RCC slab below the rail seats. For such of those locations
where minimum depth of 300 mm is not achievable, the Contractor shall, with
complete details, seek Employer’s Representative’s decision.
9.6.2.2 The reinforced concrete plinth/RCC slab shall be connected with structural
support concrete of the viaduct deck through shear connectors as shown in
Drawing No.MMO/EPMC/P/D/TW/M1110.
9.6.2.3 The Contractor shall prepare and clean the surface of supporting structure for
laying of plinth/RCC slab by methods as approved by Employer’s
Representative.
9.6.2.4 The Ballastless track shall be constructed by top down method of construction.
The laying tolerances for the various track parameters required in accordance
with the clause 9.11.2 shall be strictly met. For achieving these tolerances, the
Contractor may propose an alternative method/scheme of construction of
ballastless track along with tender submissions, if he so desires for Employer’s
Representative’s consideration. However the sole responsibility of achieving the
stipulated track laying tolerances lies with the Contractor. The tenderer shall
submit the detailed construction methodology including the method of handling
and transport of material with the details of temporary works, equipment, plant
and machinery, with details of the locations where such method/Scheme has
been used for similar project/conditions to demonstrate its success. If the
alternative method/ scheme as proposed by the tenderer is accepted by
Employer’s Representative, the Contractor shall ensure that same scheme is
adopted for construction of ballastless track on the project. If the alternative
method/ scheme as proposed by Tenderer is not accepted by the Employer’s
Representative, the Contractor shall adopt the top down method for the
construction of ballastless track.
9.6.2.5 The Contractor shall be responsible to workout the actual height of plinth / RCC
slab at each location to maintain the designed rail level as shown in the relevant
drawings and submit the same along with all relevant details for the approval of
the Employer’s Representative. The reinforced concrete plinth/RCC slab shall
be laid on the viaduct duly making the required provision for cant & vertical
curve for all heights worked out above. The indicative values of cant adopted
for horizontal curves are given in the table attached with drawings. However the
exact values of cant for all the horizontal curves shall be obtained by the
Contractor through interface with the designated Rolling Stock Contractors and
shall be submitted for the approval of the Employer’s Representative before
construction.
9.6.2.6 The reinforced concrete plinth shall normally be laid in lengths of 5 m with
intervening gaps of 0.1~0.2 m both in straight alignments and curves
9.6.2.7 During the concreting phase, the track fasteners and the running rails shall be
protected by movable covers against possible splattering of concrete.
9.6.2.8 Each plinth/RCC slab unit shall be completed in one single operation. In the
exceptional cases integral derailment walls may be cast at a later stage, but
under no circumstances shall the pouring of the concrete to the required level
under the rail supports be interrupted.
9.6.2.9 The form work may be removed after 24 hrs of pouring of plinth concrete.
9.6.2.10 In case of top down method, the plinth/RCC slab construction shall be carried
out by using perforated dummy plates of appropriate thickness as approved by
the Employer’s Representative, which shall later be replaced by intermediate
pad and elastomeric pad after the concrete attains sufficient strength.
9.6.2.11 The concreted surfaces of the plinth / RCC slab below the base plates shall be
smooth, devoid of any inclusion, roughness crack, and without showing any
aggregate at the surface. Further the anchor bolts embedded in RCC shall be
firm without showing any sign of looseness.
9.6.2.12 The presence of smooth cavities caused by air bubbles in excess of the value
mentioned below shall not be permitted in case of top down construction
method.
- Total surface area of the cavities: 10,000 mm2 on base plate area
- Maximum dimensions of the inscribing rectangle of a cavity: 20x30 mm,
- Maximum defect depth 5 mm
The rail in the embedded track of running lines shall be inclined to the same
degree as that of the adjoining track. The rail in the embedded tracks of the
workshop and in the wheel lathe building may be installed vertically. The rails
shall be lined, levelled temporarily secured in the slots left by the Depot
contractor and cast with a non-shrink grout by the Contractor as approved by
Employer’s Representative. The required flangeway gap shall be provided to the
running edges on the inside of the rails and on the outside of the rails the grout
shall be stopped 5mm below the top of rail.
9.6.4.1 The Pedestal Supporting structure constructed by the Depot Contractor shall be
surveyed and inspected by the Contractor and the Contractor should inform the
Employer’s Representative for acceptance before completion of the pedestal in
conjunction with the track laying. Any misalignment or deficiencies in the
supporting structure shall be referred to the Employer’s Representative for
decision. The rails shall be lined, levelled and fixed using special fastenings to
be manufactured locally as per the drawing provided by Employer’s
Representative. The M45 grade concrete shall be placed in the remaining depth
of 200mm of pedestal and rail seat to be epoxy grouted. No concrete shall be
placed to complete the pedestals until the final alignment has been approved by
the Employer’s Representative.
9.6.4.2 The components of the track form for the pedestals column shall be as shown in
the Drawing No.MMO/EPMC/P/D/TW/D1160.
9.6.5 Drainage
The Contractor shall be responsible for maintaining clear longitudinal & cross
drainage paths within ballastless plinth track to the main drainage system
provided by the designated Civil Contractors. The proposed track drainage
arrangement and design for crossover and scissors track slabs shall be proposed
by the Contractor for each location for the approval of the Employer’s
Representative. The Contractor shall suitably adapt and connect to the drains
provided by designated Civil Contractor.
9.7.1.1 Turnouts on ballastless track shall be so set out that the line and level of both
straight and turnout track are within designed tolerances as approved by
Employer’s Representative
9.7.1.2 Check rails shall be set and checked to the correct clearance by using the
running edge of the crossing as the datum.
9.7.1.3 The assembly sequence of turnouts, diamond crossings and derailing switches
shall be submitted for Employer’s Representative’s Approval as part of the
overall method statement for preassembly, handling, storage, transportation,
unloading and installation.
9.7.1.4 On completion of a turnout, the Contractor shall immediately scotch the switches
with a purpose made hardwood timber scotch and securely clamp the switches
for the through route with an appropriate clamp to be arranged by the Contractor
and as approved by the Employer’s Representative. The clamp shall be capable
of being padlocked with the switch in the closed position.
9.7.1.6 The Contractor shall interface & ensure the designed switch opening while
fixation of the first stretcher bar by designated signalling contractor.
9.7.1.7 All stretcher bars for switches except first stretcher bar shall be installed by the
Contractor duly interfacing with designated signalling contractor and approved
by the Employer’s Representative.
9.7.1.8 Switches shall be installed to provide adequate flange way clearance between
the stock rail and the switch rail with the switch rail in open position. The
minimum flange way clearance in switch portion shall not be less than 60 mm.
The Contractor shall provide arrangements for mounting of point operating
mechanism and shall co-ordinate and interface with designated signalling
contractor to ensure full compatibility with regards to installation requirements
and point operating mechanism. The opening of switch at toe of switch shall be
kept as 160 mm.
9.7.1.9 The Contractor shall provide all gauges and measuring equipment and labour
necessary to completely check the preassembled turnouts, crossovers, diamond
crossings and rail expansion joints
The turnouts, crossovers, diamond crossings and derailing switches shall be laid
on bottom ballast prepared as described in clause 9.5.2 - Bottom Ballast. They
shall be installed in accordance with the Approved method statement
The turnouts, x-overs and diamond x-ing shall be installed without dummy
plates, instead galvanised steel plates of appropriate thickness and dimensions
shall be supplied & provided below the intermediate pad on all base plates by the
Contractor at the time of assembling these for installation. Concreting shall be
done up to 25 mm below bottom of these plates and the gap shall be grouted
with an appropriate epoxy grout material as approved by the Employer’s
Representative.
9.8.1.1 The destressing of rails shall not be undertaken until it has been demonstrated
to the Employer’s Representative’s satisfaction that the track has been
completed to the specified standard & specification and the method of working
for destressing of the relevant trackform has been approved by the Employer’s
Representative.
9.8.1.2 The final welding of joints within turnouts shall be undertaken as per sequence
as approved by Employer’s Representative and within the stress free
temperature range.
9.8.1.3 The elementary long welded rail shall be laid on rollers placed on the metal base
plates or sleeper rail table, with the rollers at maximum 6.00-m intervals and
appropriate side rollers in curves. The rollers shall have suitable diameter to
avoid contact between rail and intermediate sleepers/metal base plates.
9.8.1.4 After placing the long welded rail on rollers, it shall be stress relieved by hitting
the rail on each side of the head with wooden mallets as approved by
Employer’s Representative.
9.8.1.5 For destressing of CWR, guidance may be taken from LWR manual of Indian
Railways.
9.8.1.6 The rails for continuously welded track shall be destressed in accordance with
temperature conditions as per Clause 3.2.4.
9.8.2.1 The installation details for friction buffers stops shall be submitted by Contractor
as per manufacturer’s guideline for Employer’s Representative’s approval.
9.8.2.2 Friction buffer stops shall not be installed until the track is at the design line and
level, as approved. The following requirements shall be complied with:
• There shall be no Thermit weld within the rail length of the buffer stop or the rail
sliding length of the buffer. Any weld that fall within the friction buffer stop rail
sliding length shall be ground to produce a smooth and uniform standard rail
cross section to ensure that the performance of the buffer stop is unaffected.
• Friction buffer stops shall be assembled and installed with the friction elements
properly spaced and the bolts torqued strictly in accordance with the
manufactures instructions.
9.9.1.1 All main lines and depot lines shall be USFD tested and welded into a LWR by
flash butt welding process except at location as approved by the Employer’s
Representative. Alumino-Thermic welding shall only be permitted in exceptional
circumstances when dictated by site conditions/ constraints and as approved by
the Employer’s Representative. Only RDSO approved welders and approved &
renowned welding firms shall be detailed to do welding.
9.9.1.2 The welding process shall be suitable for UIC60, 880 grade & 1080 grade HH
rails.
9.9.1.3 Weld records of all welds shall be submitted at intervals not exceeding 1 km of
rail welded into long lengths The proforma for the weld records plan shall be
submitted by Contractor for Employer’s Representative’s approval. This record
shall contain, as a minimum, the following information:
(e) Weld test record sheet reference (if different to the weld
number),
9.9.1.4 Arrangements shall be made to have test welds and their testing for proving of
the flash butt welding technique, the Alumino-Thermic weld process and
competence of welders deployed for welding work.
9.9.1.5 The welds shall be finished to final profile by controlled profile grinding as
approved by Employer’s Representative. The finished weld alignment shall be
as per specified tolerances. Rail head profile grinding to produce the finished
alignment shall not extend more than 300mm either side of the weld.
9.9.1.6 All welds shall be marked and painted as per the provisions of the relevant
welding manuals as mentioned in clause 6.2.6.
9.9.2.1 General
9.9.2.1.1 The Flash Butt Welding of rail joints shall be undertaken in accordance with the
relevant Indian Railways Manual for Flash Butt Welding of rail as mentioned in
clause 6.2.6 and as supplemented in this section.
9.9.2.1.2 For 1080 grade HH rails, the minimum breaking load and minimum deflection
as mentioned in the relevant clause of Indian Railway manual for flash butt
weld shall be such that the weld shall not show any sign of cracking up to the
specified rail deflection and the load at this deflection shall be more than
specified minimum breaking load. The values of specified deflection and
specified minimum breaking load shall be as mentioned in the Indian Railway
manual for flash butt weld 1996.
9.9.2.1.3 Three (3) samples of flash butt weld shall be made and tested for fatigue test in
laboratory approved by the Employer’s Representative. The test scheme and
arrangements should have prior approval of the Employer’s Representative.
9.9.2.1.4 Rails outside the required end straightness tolerance shall not be welded. Rail
ends that are out of tolerance for straightness after welding may be
straightened by the use of a purpose made rail end straightener as approved
by Employer’s Representative and cause no damage/indentation to the rails,
Alternatively the rail ends may be cut and rewelded, in which case the payment
of such weld shall not be made to the Contractor and the cost of associated rail
length shall be recovered from the Contractor.
All flash-butt welding machine operators shall be trained and certified either by
the manufacturer of the machine or by an independent Institution as approved
by the Employer’s Representative
these welds fails in testing, welding shall immediately stop until the cause is
identified and rectified. After rectification it shall be demonstrated by the
Contractor to the Employer’s Representative that all similarly affected welds
have been removed from the track.
9.9.2.4.1 The flash-butt welding machine shall be mobile type capable of making in situ
welds.
9.9.2.4.2 The welding clamps of rail shall provide contact area along the entire web of
rail and shall be fitted with spring loaded balls for optimum alignment of rail
ends.
9.9.2.4.3 The welding head shall be equipped with an integrated shearing device for
shearing of the weld seam automatically, immediately after the welding process
has been finished suitable for UIC 60, 880 grade & UIC 60, 1080 HH grade
rails.
9.9.2.4.4 A recorder system shall be provided for the simultaneous recording of butting
pressure, upset, and magnitude of current and duration of welding. Any
abnormal recordings shall be investigated and the relevant weld shall be
closely inspected visually and ultrasonically to ensure the weld is not defective.
The records for all the flash butt welds shall be made available to the
Employer’s Representative on a daily basis.
9.9.3.1 General
9.9.3.1.2 Where rails of dissimilar rail steel grade are welded together the weld portion
used shall be that of the higher grade rail and should be welded taking into
account the rapid cooling of higher grade (air quenching).
9.10.1.1 As the track is completed permanent markers shall be provided and installed
on both sides as follows:
(g) REJ
9.10.1.2 All permanent marker plates/boards made of aluminium and supporting angle
to be made of galvanised steel including colour scheme comprising reflective
paints and fixation arrangement proposed to be used shall have prior approval
of Employer’s Representative.
9.10.1.4 All markers required to be painted on rail for curves, turnouts and REJs etc.
shall be paint marked by the Contractor. The scheme for which shall be
submitted by the Contractor for Employer’s Representative’s approval.
9.11.1.1 The track parameters of completed track work, shall be measured by Contractor
in the presence of the Employer’s Representative and the measurement
recorded shall be in a format approved by the Employer’s Representative and
submitted both in hard and electronic copy.
9.11.1.3 All the track parameter measurements shall be taken in the floating condition of
the track. The base of measurement shall be as below:
9.11.1.4 The Contractor shall be solely responsible for complying with the track
tolerances stipulated in clause 9.11.2 with the materials supplied by the
Contractor and the Employer’s Representative as per contract.
ballastless track : ± 2 mm
ballasted track : -2 mm to + 5 mm
• Straight
Ballastless : ± 2 mm
Ballasted : ± 5 mm
• Ballastless : +/- 2 mm
• Ballasted : +/- 2 mm
(ballastless) ± 2 mm
Variation of cant/x-level ± 1 mm
• Flangeway clearance
h) Sleeper/Base plate
• (fishplated) 10 mm
a) Gauge
c) Cross Level/Cant
d) Twist
9.11.3.2 The proforma for the measurement of track parameter submitted by Contractor
for Employer’s Representative’s approved shall consist of the following as a
minimum:
h) Cross level/cant
i) Gauge
The proforma shall show the design figure, actual figure and the difference
between design and actual and shall allow columns for marking of twist.
9.11.3.3 The horizontal versine shall be measured every 10 m (half chord point) using a
20m chord and moving forward at 10 m intervals. The versine shall be
measured on the inside running edge of the outside rail in curves and either rail
of straight tracks at points 14mm below top of rails. Where a recording changes
its measuring rail there shall be a minimum overlap of readings of 60 meters.
9.11.3.4 The as-built recordings of rail level and horizontal alignment along longitudinal
direction with respect to the designed level & alignment shall be obtained by the
use of appropriate electronic survey instruments as directed by the Employer’s
Representative. Horizontal location readings shall be presented as co-ordinates.
Deviation from designed co-ordinates shall also be shown.
9.11.3.5 The vertical and horizontal rail location readings shall be taken with reference to
Kilometre location.
The recordings of rail level and horizontal location shall be taken at the intervals
as proposed by the Contractor and Approved by the Employer’s Representative.
9.11.3.6 Longitudinal locations shall additionally include, but not be limited to, switch and
crossings locations.
9.11.3.7 Rail inclination shall be measured using a purpose made digital rail inclinometer
and the recordings shall be submitted by Contractor for the Employer’s
Representative’s approval.
9.12 RECORDS
The manual records of rail level, cross-level/cant, gauge, twist, unevenness,
versine along longitudinal location and horizontal alignment with reference to the
designed locations shall be presented both electronically and in hardcopy in line
10.1 GENERAL
10.1.2.1 The Contractor shall formulate a comprehensive QA plan for the Employer’s
Representative’s approval, which shall then be followed throughout the duration
of the contract.
10.1.2.2 All materials, components or assemblies shall be tested and inspected at the
frequency stated within the latest Specification.
10.1.2.4 A sample Proforma, with typical examples, for the material inspections/tests
shall be submitted by the Contractor for Employer’s Representative’s approval.
10.1.2.6 Such of those tests and inspections, for which Employer’s Representative has
opined to witness, shall be carried out only in the presence of Employer’s
Representative. For other tests & inspections test/inspection results and
certification thereof shall be submitted as directed by Employer’s Representative
for his approval. However, Employer’s Representative may at his discretion
conduct test checks to be organised by Contractor for validation of
test/inspection results.
10.1.2.7 Suitable Proforma for the recording and witnessing of all tests and inspections
shall be submitted for Employer’s Representative’s approval. Confirmation of
date of a test or inspection shall be presented on an Approved Proforma, not
less than 21 Days prior to the date for test / inspection.
10.1.2.8 No material, component or assembly shall be shipped until the clearance for this
has been obtained from the Employer’s Representative.
10.1.2.9 Should the items to be tested or inspected fail to meet the requirements of this
Specification, necessitating additional visits to the laboratories or works for
retesting or inspection the costs of these additional visits shall be at the expense
of the Contractor.
All material and components supplied by the Contractor shall be inspected and
tested in accordance with the relevant technical specification of Indian Railways
as mentioned in clause 6.2.6.
10.2.1 Welding
10.2.1.1 General
10.2.1.1.1 All Welds (Flash butt and Alumino-Thermic) shall be tested ultrasonically as
per relevant manual for ultrasonic testing of rails and welds as mentioned in
clause 6.2.6.
10.2.1.1.2 All the defective welds whether identified as a result of USFD testing or
otherwise shall be removed from the track and rewelded by the Contractor.
The cost of all the rewelding of the defective/rejected welds and that of
associated rail length including cutting of rails, adjustments and all related
works shall be borne by the Contractor.
10.2.1.2 Welding materials
Tests for Flash-Butt Welding shall be carried out in accordance with the Indian
Railways Manual for Flash Butt Welding of Rails as mentioned in clause 6.2.6
and as detailed in clause 9.9.2.1of Technical Specification.
10.2.1.4 Alumino-Thermic weld tests
Tests for Alumino-Thermic Welding shall be carried out in accordance with the
Indian Railways Manual for Alumino-Thermic Welding of Rails as mentioned in
clause 6.2.6.
10.3.1.1 Switches with fixed heel shall be checked as full sets. Running edge offsets and
gauge shall be checked at coincidental locations, on both the main and turnout
track.
10.3.1.2 Running edge offsets shall be taken at maximum 1000 mm intervals. Running
edge offsets shall be within +2mm/ - 1 mm of their design value.
10.3.1.3 The inspection of switches and derailing switches shall include, but not be
limited to, the following:
(a) The switch rail evenly butts with the stock rail throughout the length
of the switch planing with the switch lying naturally.
(b) The underside of the switches and stock rails bear evenly on all
slide base plates.
(d) The switch rails over their free length are not twisted/bent.
10.3.1.4 The switch toes shall not be out of square/beyond specified tolerances.
10.4.1.1 The fabricated buffer stops shall be inspected by the Employer’s Representative
before installation. Necessary assistance shall be provided by Contractor to
facilitate the inspections. A minimum of 21 days notice in writing of the dates on
which the buffer stops will be available for inspection shall be given to the
Employer’s Representative.
10.4.1.2 The buffer stops shall have the identification plates fixed, prior to the inspection,
and these identification plates shall be maintained until the acceptance of the
buffer stops in the Works.
10.4.1.3 Inspection sheets shall be prepared and submitted for approval of each
assembly clearly showing the design and actual dimensional checks, item
number and identification marks.
10.5.1 General
10.5.2 Submissions
(a) Records and certification for all the tests and inspections identified in PS.
• Vertical Alignment
• Horizontal alignment
(c) The results and reports of all tests and materials, assemblies and
items/components.
(d) The results of all Tests shall be submitted in hard copy and electronic
format.
10.5.3.1 All trackwork shall be subjected to a rail insulation to earth test. The track shall
have a minimum rail-to-earth value to be determined after interfacing with the
Designated Contractors for ballasted and ballastless tracks in worst weather
conditions.
10.5.3.2 The rail to earth test shall be undertaken after the track has been completed and
cleaned but before it is finally formed into a continuously welded system and
before all the bonding is installed.
10.5.3.3 The test shall be undertaken on rail lengths up to maximum length of 1000 m.
10.5.3.4 The track shall not be finally formed into a continuous length, until the rail
insulation to earth tests have been undertaken and approved.
10.5.4.1.1 A ballast resistance test shall be undertaken on all track lengths over 50
metres as a check of the leakage of current through the trackbase and rail
fastening system from one rail to the other.
10.5.4.1.2 The ballasted trackbase resistance test shall be undertaken after the track has
been complete and cleaned but before it is finally formed into a continuous
length and all the bonds are attached.
10.5.4.1.3 The testing procedure and the minimum resistance shall comply with the
requirements proposed by interfacing with designated signalling contractor
and as approved by Employer’s Representative.
10.5.4.2.1 A ballastless trackbase test shall be undertaken on all track lengths over 50
metres as a check of the leakage of current through the trackbase and rail
fastening system from one rail to the other.
10.5.4.2.2 The ballastless trackbase resistance test shall be undertaken after the track
has been complete and cleaned but before it is finally formed into a continuous
length and all the bonds are attached.
10.5.4.2.3 The testing procedure and the minimum resistance shall comply with the
requirements proposed by interfacing with designated signalling contractor.
10.5.5.1 Both rails of all ballastless running line tracks shall be checked, at maximum 10
m intervals, for inclination using a purpose made approved digital inclinometer in
the presence of the Employer’s Representative.
10.5.5.2 Should any reading show the inclination to be outside the specified limits every
alternate fastening assembly shall be further checked either side of the non-
compliant reading until compliant readings are consistently obtained.
10.5.5.3 If the length of rail outside the specified inclination exceeds 9 m, the out of
tolerance lengths shall be rectified by the Contractor by a method approved by
the Employer’s Representative.
10.5.5.4 The procedure / values mentioned in Para 10.5.3, 10.5.4.1 & 10.5.4.2 are
indicative and these tests are to be carried out by the Designated Contractors.
The actual values / procedure of these tests shall be interfaced by the
Contractor with the Designated Contractors.
The Contractor will establish a full fledged most modern concrete laboratory
with trained engineers, Quality Control (QC) Manager and technicians at site/in
the casting yard. It will have facilities for testing physical properties of cement,
workability of concrete, cube strength, permeability of concrete, sieve analysis,
RCPT, aggregate tests, tests required for mix design, chloride tests of water and
admixture, concrete temperature, oven, accelerated tests for cement/concrete
strength, flexural strength of concrete. One room shall be air-conditioned to
control temp and humidity for cement tests. A typical layout of the laboratory is
attached as annexure-I
11.1 MATERIALS
All the sources of the materials shall be approved in advance before bringing to
the Site. All materials for making concrete shall be approved by the Employer’s
Representative. All approved samples shall be deposited in the office of the
Employer’s Representative before placing orders for the materials with
suppliers. The materials brought on to the works shall conform in every respect
to their approved samples and specifications.
The Employer’s Representative shall have the option to have any of the
materials tested to find whether they are in accordance with specifications at the
Contractor expense. All bills vouchers and test certificates which in the opinion
of the Employer’s Representative are necessary to convince him as to the
source and quality of materials or their suitability shall be produced for his
inspection when required.
Any materials which have not been found to conform to the specifications and
not approved by the Employer’s Representative shall be rejected forthwith and
shall be removed from the site by the Contractor at his own cost within the time
stipulated by the Employer’s Representative. The Employer’s Representative
shall have the powers to cause the Contractors to purchase and use materials
from any particular source, as may in his opinion be necessary for the quality
execution of work.
Contractor shall also ensure that all constituents of exposed concrete shall be
taken from same sources to achieve a uniform colour and texture.
11.1.1.2 Whenever possible all cements of each type shall be obtained from one
constant source throughout the contract, cement of different types shall not be
mixed together. Different brands of cement, or the same brand of cement from
different sources, shall not be used without prior approval of the Employer’s
Representative.
11.1.1.3 Packaged cement shall be delivered to the site in original sealed bags which
shall be labelled with the weight, name of manufacturer, brand and type.
Cement received in torn bags shall not be used. Cement bags will not be
handled with hooks which allow ingress of moisture. Contractor may obtain
cement in bulk and store it in suitable silos of adequate capacity.
11.1.1.4 Each type of cement shall be stored in a separate silo and it shall be ensured,
that cements of different quality are not mixed up.
11.1.1.5 All cement shall be fresh when delivered and at ambient atmospheric
temperature.
11.1.1.6 In fair faced elements, the cement used in the concrete for any complete
element shall be from a single consignment. All cement for exposed concrete
shall be from the same approved source and uniform in colour.
11.1.1.7 With each and every delivery of cement the Contractor shall provide
manufacturer’s certificate that the cement conforms to the relevant Indian
standard. The Contractor shall provide complete facilities at site for carrying out
the following tests:
11.1.1.8 Total chloride content in cement shall in no case exceed 0.05 percent by mass
of cement. Also, total sulphur content calculated as sulphuric anhydride (SO3),
shall in no case exceed 2.5 percent and 3.0 percent when tri-calcium
aluminate per cent by mass is upto 5 or greater than 5 respectively.
11.1.2 Aggregate
For fair faced concrete, the Contractor shall ensure that aggregates are free
from iron pyrites and impurities, which may cause discoloration. Aggregates
shall be stored on paved areas in different compartments according to their
nominal size.
The fine aggregate shall be river sand, manufactured sand of approved grading,
pit sand. It shall be free from clay, loam, earth or vegetable matter, salt or other
harmful chemical impurities. It shall be clean, sharp, strong, angular and
composed of hard siliceous material. Sand dredged from sea, creeks will not be
used. RMC manufactured with sand dredged from sea/creek will not be used.
The grading of fine aggregate when determined as described in IS: 2386 (part I),
shall be within the grading zones I, II, III.
The Contractor shall provide complete facilities at site for carrying out the
following tests:
D) Specific Gravity
All coarse aggregate shall conform to IS: 383 and tests for conformity shall be
carried out as per IS: 2386, Parts I to VIII.
The maximum size of coarse aggregate shall be such that the concrete can be
placed without difficulty so as to surround all reinforcement thoroughly and fill
the corners of formwork. Unless otherwise permitted by the Employer’s
Representative the nominal maximum size shall not exceed 40mm.
11.1.3 Water
Water used in the works shall be potable water and free from deleterious
materials. Water used for mixing and curing concrete as well as for cooling
and/or washing aggregate shall be fresh and clean free from injurious amounts
of oil, salts, acids, alkali, other chemicals and organic matter.
Water shall be from the source approved by the Employer’s Representative and
shall be in accordance with clause 5.4 of IS: 456 However, chloride content in
water shall not exceed 500 mg/litre.
Before starting any concreting work and wherever the source of water changes,
the water shall be tested for its chemical and other impurities to ascertain its
suitability for use in concrete for approval of the Employer’s Representative. No
water shall be used until tested and found satisfactory. Cost of all such Tests
shall be borne by the Contractor.
11.3 Admixtures:
11.3.1 Chemical admixtures are not to be used until permitted by the Employer’s
Representative. In case their use is permitted, the type, amount and method of
use of any admixtures proposed by the Contractor shall be submitted to the
Employer’s Representative for approval. The minimum cement content specified
11.3.2 The Contractor shall further provide the following information concerning each
admixture to the Employer’s Representative
11.3.3 In reinforced concrete, the chloride content of any admixture used shall not
exceed 0.1 percent by weight of the admixture as determined in accordance
with IS:6925 and the total chloride and sulphate contents in concrete mix shall
not exceed 0.10 and 4.0 percent respectively by weight of cement.
11.3.4 The admixtures when used shall conform to IS:9103. The suitability of all
admixtures shall be verified by trial mixes.
11.3.5 The addition of calcium chloride to concrete containing embedded metal will not
be permitted under any circumstances.
11.3.7 Each batch / consignment shall be tested for specific gravity & performance in
concrete before their use.
11.4.2 The Contractor shall provide Concrete mixers (IS:1791 – Batch type concrete
mixers, IS:2438 – Roller Pan Mixer) and Vibrators (IS:2505 – Concrete Vibrators
Immersion Type, IS:2506 – Screed board concrete vibrators, IS:4656 – Form
Vibrators for Concrete) supplied by recognised manufacturers.
Concrete M 25 / 20
Mix Design once approved must not be altered without prior approval of
Employer’s Representative. However, should the Contractor anticipate any
change in quality of future supply of materials than that used for preliminary mix
design, he should inform the Employer’s Representative quite in advance and
bring fresh samples sufficiently in advance, to carry out fresh trial mixes. Design
mix will indicate by means of graphs and curves etc., the extent of variation in
the grading of aggregates which can be allowed. Cement will mean
cement/blended cement/cementitious material. The S.D. and coefficient of
variation shall be established for each grade of concrete. SQC graphs shall be
submitted monthly.
Cementitious material in concrete shall not be less than 380 kg/ cum for RCC
work and 400 kg/ cum for PSC work under severe exposure. However, the
quantity of cement (excluding Fly ash) shall be limited to 450kg/ cum of
concrete. Ordinary Portland cement (OPC) of 43 and 53 grade conforming to IS:
8112 and IS: 12269 respectively shall be used. For pre-stressed concrete,
cement conforming to IRS – T – 40 specifications or OPC 53 grade cement with
Fly ash shall be used.
11.7.1 The Employer’s Representative shall select random batches of concrete for
examination at his discretion and sampling will generally be done at the point of
discharge from the mixer and at placing point.
11.7.2 From the batches thus selected two concrete cylinders shall be made in
accordance DIN 1048.
11.7.3 All cylinders shall be made, cured, stored, transported and tested in accordance
with DIN-1048 Specifications. The tests shall be carried out in the site
laboratory.
11.7.4 At least two cylinders shall be made on each day’s concreting until 60 cylinders
have been made for each grade of concrete. The cylinders will be tested as per
the procedure, given in Clause 5 next.
25 mm).
No extra payment shall be made for this test and cost of the same will be
included in his rate for concrete works.
In hot weather with temperature exceeding 40˚C, the stock piles of fine and
coarse aggregates for concreting shall be kept shaded from direct rays of sun
and the concrete aggregates sprinkled with water for a sufficient time before
concreting in order to ensure that the temperature of these ingredients is as low
as possible prior to batching. The mixer and batching equipment shall be also
shaded and if necessary painted white in order to keep their temperatures as
low as possible. The placing temperature of concrete shall be as low as possible
in warm weather and care shall be taken to protect freshly placed concrete from
overheating by sunlight in the first few hours of its laying. The time of day
selected for concreting shall also be chosen so as to minimise placing
temperatures. In case of concreting in exceptionally hot weather the Employer’s
Representative may in his discretion specify the use of ice either flaked and
used directly in the mix or blocks used for chilling the mixing water. In either
case, the Contractor shall not be paid extra for cost of ice, additional labour
involved in weighing and mixing etc. All salt and saw dust shall be removed from
ice before use. Quality of water used for making ice shall confirm to IS: 456. A
complete record of concrete temperature shall be maintained and submitted.
The temperature shall be recorded both at the mixing & placing point.
11.10.1 Transporting:
The mix after discharging from the mixer shall be transported by transit mixers,
buckets, pumps etc. or as approved by the Employer’s Representative without
causing segregation and loss of cement slurry and without altering its desired
properties with regard to water cement ratio, slump, air content, cohesion and
homogeneity. It should be ensured that the concrete is moved to its final
destination, placed and compacted before initial set.
11.10.2 Placing :
The method of placing shall be such as to prevent formation of cold joints and
segregation by providing windows in the formwork for pouring concrete or by
tremie pipe. The thickness of horizontal layers shall not exceed 300mm. High
velocity discharge of concrete causing segregation of mix shall be avoided. The
concrete shall be placed in the forms gently and not dropped from a height
exceeding 1.5m. Each layer of concrete shall be compacted fully before the
succeeding layer is placed and separate batches shall follow each other so
closely that the succeeding layer shall be placed and fully compacted before the
layer immediately below has taken initial set.
For all heights, the rate of placing of concrete by using tremie / pumps shall not
be more than 1.5m / hr or as approved by the Employer’s Representative.
Concreting of any portion or section of the work shall be carried out in one
continuous operation and no interruption of concreting work will be allowed
without approval of the Employer’s Representative. A concrete sequence shall
be prepared in advance for each concrete pour and approval of Employer’s
Representative taken.
11.10.3 Compaction:
Internal (needle) and surface (screed board) vibrators of approved make and
size shall be used for compaction of concrete.
• To secure even and dense surfaces free from aggregate pockets, vibration
shall be supplemented by tamping or tamping by rods in the corners of
forms and along the form surfaces while the concrete is plastic.
• Care must be taken to guard against over vibration especially where the
workability of the concrete mix is high since this will encourage
segregation of the concrete.
11.10.4 Concrete placed below the ground shall be protected from falling earth during
and after placing. Concrete placed in ground containing deleterious substances
shall be kept free from contact with such ground and with water draining there
from during placing and for a period of seven days or as otherwise instructed
thereafter. Approved means shall be taken to protect immature concrete from
damage by debris, excessive loading, abrasion, vibrations, deleterious ground
water, mixing with earth or other materials, and other influences that may impair
the strength and durability of the concrete.
11.10.5 Curing:
• Curing of concrete shall be complete and continuous using potable water
free from chlorides and sulphates, water that is free of harmful amounts of
deleterious materials that may attack, stain or discolour the concrete as
per IS 456. Minimum wet curing will be for ten days by ponding water
followed by moist curing by spraying water which shall be maintained up to
a total period for at least 21 days from the date of casting.
• Method of curing and their duration shall be such that the concrete will
have satisfactory durability and strength and members will suffer a
minimum distortion, be free from excessive efflorescence and will not
cause undue cracking in the works by shrinkage.
The laitance shall be removed by wire brush and aggregate exposed to 1/3rd of
its height after the initial setting of concrete, but without dislodging the
aggregate. The mortar around steel and corners shall be removed by air/water
pressure jetting. Before placing new concrete the earlier surface shall be
moistened. Cement water slurry will never be sprinkled.
Before fresh concrete is placed against a vertical joint, the old concrete shall be
chipped by a pneumatic chipping hammer, cleaned and moistened. Alternatively
the shutter can be painted with Plasticizer (retarder) before fixing. This will not
allow cement in contact with shutter to set, and same if washed with water will
provide a surface free of laitance. This is preferred method of providing vertical
construction joint. The shutter is required to be removed before the final setting
of concrete and concrete surface shall be washed with water jet .Trials shall be
made in the site laboratory to decide the methodogy.
Clear cover will mean extent of cover from the outermost steel bar including
binding wire. All binding wire ends shall be bent towards centre of the section.
11.12.2 Cover blocks shall be manufactured on vibrating tables. The grade of mix shall
be same as that of main member. All quality control shall be exercised as for
the main member The cost of cover blocks shall be deemed to have been
included in the rates.
11.13 Cracks:
If cracks, which in the opinion of the Employer’s Representative may be
detrimental to the strength and durability of the construction, develop in concrete
construction, the Contractor at his own expense shall test the structure as
specified in clause 1.1.16 of ‘Loading Tests’ of these Specifications. If under
such test loads the cracks develop further, the Contractor shall dismantle the
construction, carry away the debris, replace the construction and carry out all
consequential work thereto.
If any cracks develop in the concrete construction, which in the opinion of the
Employer’s Representative, are not detrimental to the stability of the
construction, the Contractor at his own expense shall grout the cracks with
epoxy grout or with other composition as directed by Employer’s Representative
and also at his own expense and risk shall make good to the satisfaction of the
Employer’s Representative all other works such as plaster, moulding, surface
finish, which in the opinion of the Employer’s Representative have suffered
damage either in appearance or stability owing to such cracks. The Employer’s
Representative's decision as to the extent of the liability of the Contractor in the
above matter shall be final and binding.
External crack width shall be restricted to 0.1mm. If cracks width is more than
0.1mm or in the opinion of Employer’s Representative may be detrimental to
concrete construction, the Contractor at his own expenses should epoxy grout
the cracks.
Holes for foundation or other bolts or for any other purposes shall be moulded
and steel angles, holdfasts or other fixtures shall be embedded, according to the
drawing or as instructed by the Employer’s Representative.
11.16 Finishes:
Unless otherwise instructed the face of exposed concrete placed against
formwork shall be rubbed down immediately on removal of the formwork to
remove irregularities. The face of concrete for which formwork is not provided
other than slabs shall be smoothed with a float to give a finish equal to that of
the rubbed down face, where formwork is provided. The top face of a slab which
is not intended to be covered with other materials shall be levelled and floated to
a smooth finish at the levels or falls shown on the drawings or as directed. The
floating shall be done so as not to bring an excess of mortar to the surface of the
concrete. The top face of a slab intended to be surfaced with other material shall
be left with a spaded finish. Faces of concrete intended to be plastered shall be
roughened by approved means to form key.
11.18.1 Mixing :
11.18.2 Batching:
11.18.4 Restraint :
Heavy back-up blocks of timber or concrete should be fixed on all sided of the
base plate to prevent escape of the grout, when poured through the openings
provided in the base plate. Adequate restraint must be ensured on all the sides
for a period of 7 days to obtain effective expansion and shrinkage
compensation.
11.18.5 Curing :
The grout should not dry out where external restraint is provided in the form of
form-work, the top opening and all stray openings should be covered with wet
sack for at least 14 days.
Below the bed plates the grout should be compacted using long pieces of
doubled-over flexible steel strapping or chains. The forward and backward
movement of the strap or chain will assist in the flow of the grout into place.
Steps must be taken to keep the grout in full contact with the underside of the
bedplate until the grout sets; maintaining a small head of fresh grout in the
forms.
11.20
The provision in this section shall be considered supplementary to general
provisions for reinforced concrete works.
11.20.3 Tolerances:
The following tolerances apply to finished pre-cast products at the time of
placement in the structure. The forms must be constructed to give a casting well
within these limits:
• Deviation from straight line in long sections should not be more than
+ 6mm up to 3m, + 10mm for 3m to 6m, + 12mm for 6m to 12m.
For tolerances on pre-cast segments for girders please refer Annexure 12.2.
The quantity of coarse aggregate shall be such that the concrete can be pumped,
compacted and finished without difficulty.
obtain pumpable concrete. Sands, which are deficient in either of these two
sizes, should be blended with selected finer sands to produce these desired
percentages. With this gradation, sands having a fineness modulus between 2.6
and 3.1 are generally satisfactory. However, for uniformity, the fineness
modulus of the sand should not vary more than 0.2 from the average value used
in proportioning. Sand from sea bed or creeks shall not be used.
Additions of water to compensate for slump loss should not be resorted to nor
should the design maximum water-cement ratio be exceeded. Additional dose of
retarder be used to compensate the loss of slump at Contractor cost, when
permitted by Employer’s Representative. Retempering water shall not be
allowed to be added to mixed batches to obtain desired slump. Slump records at
the time and place of concreting shall be maintained and shall conform to the
requirements.
11.21.4 Transportation:
The method of transportation used should efficiently deliver the concrete to the
point of placement without significantly altering its desired properties with regard
to water-cement ratio, slump, and homogeneity.
for at least 3.5 MPa pressure and greater for rising runs over 30 m. Couplings
should be designed to allow replacement of any section without moving other
pipe sections, and should provide full cross section with no construction or
crevices to disrupt the smooth flow of concrete.
All necessary accessories such as curved sections of rigid pipe, swivel joints
and rotary distributors, pin and gate valves to prevent backflow in the pipe line,
switch valves to direct the flow into another pipe line, connection devices to fill
forms from the bottom up, extra strong couplings for vertical runs, transitions for
connecting different sizes of pipe, air vents for downhill pumping, clean-out
equipment etc, shall be provided as and where required. Suitable power
controlled booms or specialized crane shall be used for supporting the pipe line.
11.21.7 Planning:
Proper planning of concrete supply, pump locations, line layout, placing
sequence, and the entire pumping operation shall be made and got approved.
The pump should be as near the placing area as practicable, and the entire
surrounding area shall have adequate bearing strength to support concrete
delivery pipes. Lines from pump to the placing area should be laid out with a
minimum of bends. For large placing areas, alternate lines should be installed
for rapid connection when required. Standby power and pumping equipment
should be provided to replace initial equipment, should breakdown occur. The
delivery pipes shall be covered with wet hessian cloth.
As a final check, the pump should be started and operated without concrete to
be certain that all moving parts are operating properly. A grout mortar should be
pumped into the lines to provide lubrication for the concrete, but this mortar shall
not be used in the placement. When the form is nearly full, and there is enough
concrete in the line to complete the placement the pump shall be stopped and a
go-devil inserted and shall be forced through the line by water under pressure to
clean it out. The go-devil should be stopped at a safe distance from the end of
the line so that the water in the line will not spill into the placement area. At the
end of placing operation, the line shall be cleaned in the reverse direction.
11.22.1 Mineral admixture in the form of micro silica or condensed silica fume if required
shall be permitted in the design mix. It shall comply with ASTM C 1240
“Specifications for Silica Fume for use in Hydraulic Cement Concrete and
Mortar”. It shall be obtained from proven and reliable manufacturer/supplier to
the satisfaction of the Employer’s Representative.
11.22.2 Adequate and complete dispersal of the micro silica during the concrete mixing
shall be ensured.
11.22.3 When micro silica is used in powder form the Contractor shall take all
precautions against potential health hazards during handling of the material.
11.22.4 Chilled water and/ or ice shall be used in the concrete mix depending on the
ambient temperature, dimensions of the concrete element, rate of pouring and
design mix constituents.
11.22.5 Special profuse curing arrangements shall be made for dissipation of the heat of
hydration. The water curing shall be continued for a period of 21 days.
11.22.6 The concrete design mix and arrangement for mixing, transportation, and curing
of concrete shall be subject to the approval of the Employer’s Representative.
11.22.7 The concrete temperature shall be recorded for 21 days from the time of
placement of concrete.
11.23 Measurement
11.23.1 Measurement shall be made for the finished volume of reinforced cement
concrete (excluding lean concrete) only. All linear dimensions shall be measured
correct to 1cm & restricted to design dimensions, and the volume calculation will
be correct to two decimal places in cubic meter.
11.23.2 No deduction shall be made for volume of steel / sheaths embedded in concrete
or for voids not exceeding 0.03 cum in volume.
A g g re
Note: The dimensions shown above for the concrete laboratory are tentative and
the Contractor may be asked to accommodate the concrete laboratory in a
smaller area as per availability at Site.
12. REINFORCEMENT
Any steel specified for reinforcement shall conform in every respect to the latest
relevant Indian Standard Specifications and shall be of tested quality under the
ISI Certification Scheme.
The reinforcement steel shall be from primary producers and not re-rolled steel
shall be supplied.
12.1.1 Every bar shall be inspected before assembling on the works and any
defective, brittle, rusted or burnt bars shall be removed. Cracked ends of bars
shall be cut out.
12.1.2 Reinforcement steel shall be fresh, free from corrosion. Corroded steel will not
be incorporated in work. If there are traces of corrosion, then the Contractor
have to give the following treatment to steel for which nothing extra shall be
paid.
12.1.5 Specimens sufficient for three Tensile Tests for each different size of bar for
each consignment delivered shall be sampled and tested by the Contractor.
Batches shall be rejected if the average results of each batch are not in
accordance with the specifications.
Prior to starting bar bending work, the Contractor shall prepare bar bending
schedule from the structural drawings supplied to him and get the same
approved by Employer’s Representative. Any discrepancies and inaccuracies
found by the Contractor in the drawings shall be immediately reported to the
Employer’s Representative whose interpretation and decision there to, shall be
accepted.
12.3.1 As far as possible bars of the maximum length available shall be used. Laps
shown on drawings or otherwise specified by the Employer’s Representative will
be based on the use by the Contractor of bars of maximum length. Payment for
reinforcement shall be made only for reinforcement shown in such drawings and
such laps. In case the Contractor wishes to use shorter bars, laps shall be
provided at the Contractor cost in the manner and at the locations approved by
the Employer’s Representative.
12.3.2 Bars having butt or lap welds shall be provided as specified in the drawings or
as instructed by the Employer’s Representative.
12.4.1 All reinforcement shall be placed and maintained in the positions shown on
the drawings.
12.4.2 The Contractor shall provide approved types of supports for maintaining the
bars in position and ensuring required spacing and correct cover of concrete to
the reinforcement as specified on the drawings. Cover blocks of required shape
and size, M.S. Chairs and spacer bars shall be used to ensure accurate
positioning of reinforcement.
12.4.3 Bars must be cleaned, before concreting commences, of all scale, rust or
partially set concrete which may have been deposited there during placing of
previous lift of concrete.
12.4.5 G.I. wire shall be used for binding reinforcement and their ends to be bent
towards the centre of element.
12.5 Welding:
12.5.1 Wherever specified all lap and butt welding of bars shall be carried in
accordance with IS: 2571. Only qualified welders shall be permitted to carry out
such welding.
12.5.4 Slag produced in welding after alternative run should be chipped and removed
by brush.
12.6 Measurement:
The measurement shall be done in MT on the basis of standard weight.
Payment for reinforcement shall be made only for reinforcement shown in
drawings and laps as per Clause 11.3.1 Payments shall not be made for
reinforcement bars used for lifting, hooks, handling, chairs, spacers etc., as cost
of which shall be deemed to be included in item rate.
13. FORMWORK
13.2 Materials:
Formwork shall be of steel or any other suitable material as approved by the
Employer’s Representative. The formwork shall be capable of resisting damage
to the contact faces under normal conditions of erecting forms, fixing steel and
placing concrete. The selection of materials suitable for formwork shall be made
by the Contractor based on the quality consistent with the specified finishes and
safety.
All formwork supports (centering, props, scaffolds etc.) shall only be in structural
steel and preferably of pipes conforming to IS:806, IS:1161, IS:1239, IS:2750.
Wooden ballies shall not be permitted as props/formwork supports. All props
shall be properly braced using x & k bracings.
Methodology for removal of form should be planned as a part of total form work
design.
13.4.1 The Contractor shall obtain the approval of the Employer’s Representative for
the design of forms and the type of material used before fabricating the forms.
(Ref. ACI 347 Formwork for Concrete or equivalent I.S. Code).
13.4.2 Provision shall be made for adjustment of supporting struts where necessary.
When reinforcement passes through the formwork care should be taken to
ensure close fitting joints against the steel bars so as to avoid loss of fines
during the compaction of concrete.
13.4.4 Surfaces of forms in contact with concrete shall be oiled with a mould oil of
approved quality or clean diesel oil. If required by the Employer’s
Representative the Contractor shall execute different parts of the work with
different mould oils to enable the Employer’s Representative to select the most
suitable. The use of oil which results in blemishes of the surface of the concrete
shall not be allowed. Oil shall be applied before reinforcement has been placed
and care shall be taken that no oil comes in contact with the reinforcement while
it is being placed in position. The formwork shall be kept thoroughly wet during
concreting and the whole time that it is left in place. Nothing extra shall be paid
to Contractor for oiling.
This section deals with the surface of concrete on which forms had been fixed
while concreting.
In the event of finishing not being definitely specified herein or in the drawings,
finishes to be adopted shall be as directed by the Employer’s Representative.
The top of plinth shall be a trowelled finish and shall be used for tops of
parapets, etc prominently exposed to view. When the floated surface has
hardened sufficiently, steel trowelling shall be started. Steel trowelling on
hardened, floated surface shall be performed with firm pressure to produce a
dense uniform surface free from blemishes and trowel marks and having slightly
glossy appearance. Surface irregularities shall not exceed 5mm.